Zhang et al., 2021 - Google Patents
An improved branch-and-bound algorithm for the one-machine scheduling problem with delayed precedence constraintsZhang et al., 2021
- Document ID
- 15306416543660286497
- Author
- Zhang W
- Sauppe J
- Jacobson S
- Publication year
- Publication venue
- INFORMS Journal on Computing
External Links
Snippet
In this paper, we discuss the one-machine scheduling problem with release and delivery times with the minimum makespan objective. Both heuristics and branch-and-bound algorithms have been formulated for the problem. One such branch-and-bound algorithm …
- 230000003111 delayed 0 title abstract description 28
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F9/00—Arrangements for programme control, e.g. control unit
- G06F9/06—Arrangements for programme control, e.g. control unit using stored programme, i.e. using internal store of processing equipment to receive and retain programme
- G06F9/46—Multiprogramming arrangements
- G06F9/48—Programme initiating; Programme switching, e.g. by interrupt
- G06F9/4806—Task transfer initiation or dispatching
- G06F9/4843—Task transfer initiation or dispatching by program, e.g. task dispatcher, supervisor, operating system
- G06F9/4881—Scheduling strategies for dispatcher, e.g. round robin, multi-level priority queues
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management, e.g. organising, planning, scheduling or allocating time, human or machine resources; Enterprise planning; Organisational models
- G06Q10/063—Operations research or analysis
- G06Q10/0631—Resource planning, allocation or scheduling for a business operation
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management, e.g. organising, planning, scheduling or allocating time, human or machine resources; Enterprise planning; Organisational models
- G06Q10/063—Operations research or analysis
- G06Q10/0631—Resource planning, allocation or scheduling for a business operation
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management, e.g. organising, planning, scheduling or allocating time, human or machine resources; Enterprise planning; Organisational models
- G06Q10/063—Operations research or analysis
- G06Q10/0633—Workflow analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F9/00—Arrangements for programme control, e.g. control unit
- G06F9/06—Arrangements for programme control, e.g. control unit using stored programme, i.e. using internal store of processing equipment to receive and retain programme
- G06F9/30—Arrangements for executing machine-instructions, e.g. instruction decode
- G06F9/38—Concurrent instruction execution, e.g. pipeline, look ahead
- G06F9/3836—Instruction issuing, e.g. dynamic instruction scheduling, out of order instruction execution
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation, e.g. computer aided management of electronic mail or groupware; Time management, e.g. calendars, reminders, meetings or time accounting
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06Q—DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation, e.g. linear programming, "travelling salesman problem" or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/30—Information retrieval; Database structures therefor; File system structures therefor
- G06F17/30943—Information retrieval; Database structures therefor; File system structures therefor details of database functions independent of the retrieved data type
- G06F17/30946—Information retrieval; Database structures therefor; File system structures therefor details of database functions independent of the retrieved data type indexing structures
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Ilavarasan et al. | Performance effective task scheduling algorithm for heterogeneous computing system | |
| Artigues et al. | Maximization of solution flexibility for robust shop scheduling | |
| Zhang et al. | A modified shifting bottleneck heuristic and disjunctive graph for job shop scheduling problems with transportation constraints | |
| Paternina-Arboleda et al. | Scheduling jobs on ak-stage flexible flow-shop | |
| Kwok et al. | FAST: A low-complexity algorithm for efficient scheduling of DAGs on parallel processors | |
| Macey et al. | A performance evaluation of CP list scheduling heuristics for communication intensive task graphs | |
| Brauer et al. | Multi-machine scheduling-a multi-agent learning approach | |
| Koehler et al. | Optimal batch schedules for parallel machines | |
| Jansen et al. | Approximation algorithms for flexible job shop problems | |
| Ilavarasan et al. | High performance task scheduling algorithm for heterogeneous computing system | |
| Vancheeswaran et al. | Two-stage heuristic procedure for scheduling job shops | |
| Zhang et al. | An improved branch-and-bound algorithm for the one-machine scheduling problem with delayed precedence constraints | |
| Thoney et al. | Satisfying due-dates in large multi-factory supply chains | |
| Chang | Heuristics for dynamic job shop scheduling with real-time updated queueing time estimates | |
| Daoud et al. | Efficient compile-time task scheduling for heterogeneous distributed computing systems | |
| Mahapatra et al. | Heuristics techniques for scheduling problems with reducing waiting time variance | |
| US8086595B2 (en) | Systems and methods for solving multiple interacting state-space search problems | |
| Kim et al. | Scheduling of parallel machines to minimize total completion time subject to s-precedence constraints | |
| Lee et al. | Minimizing the total flow time and the tardiness in a two-machine flow shop | |
| Kis et al. | On bilevel machine scheduling problems | |
| Zhang et al. | A hybrid metaheuristic algorithm for flexible job-shop scheduling problems with transportation constraints | |
| Yau et al. | Nested partitions for the large-scale extended job shop scheduling problem | |
| Garcia et al. | Approximation Algorithms for Spatial Scheduling | |
| Sleutjes | Developing an improved branching structure for constraint programming applied to the job shop problem | |
| Kim | Scheduling of uniform parallel machines with s-precedence constraints |