No. 7 Line, Site L: Overcoming the Challenges of Underground Construction in the Built Environment

Sokol et al.

View PDF
Document ID
1112257996006550841
Author
Sokol N
Ghasemi A
Hurt J
Shafei B

External Links

Snippet

Site L will be a ventilation facility for the No. 7 Line Extension in midtown Manhattan. Unique challenges associated with the project include a surface excavation and two rock shafts adjacent to a tall building and two 9.2-m (30-ft) span adits excavated through existing …
Continue reading at www.researchgate.net (PDF) (other versions)

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Lay-outs therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Lay-outs therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

Similar Documents

Publication Publication Date Title
CN1837506B (en) Construction method for excavating box-shape structure over an operating tunnel
US9151047B2 (en) Undercut excavation method with continuous concrete floors
Haruyama et al. Construction of urban expressway tunnel with special large cross section by NATM–Metropolitan Inter-City Highway (Ken-O-Do) Ome Tunnel–
Sokol et al. No. 7 Line, Site L: Overcoming the Challenges of Underground Construction in the Built Environment
Goel et al. Tunnels in the Himalaya
Kramer et al. The Sequential Demolition Method–Underground Replacement of a 100 Year Old Tunnel
Boon et al. Protection of buildings and structures within the influence of tunnelling works
Konstantis et al. Box jacking/pushing method for tunnel construction in rock: Doha Metro, Gold Line Project
Çimentepe Evaluation of structural analysis methods used for the design of TBM segmental linings
Herranz et al. SEM crossover cavern in Downtown LA
Peila et al. Construction methods
Sandbak et al. Ground support strategies for weak ground masses at the Turquoise Ridge Joint Venture, Nevada
Lim et al. Construction of the linkway underneath the existing Outram Park Station
Ghani et al. Design and Construction of Ho Chi Minh City Metro Line 1 Underground Section (Contract Package 1b)
Underwood Machine tunneling on Missouri River dams
Kramer et al. Underground replacement of a 100 year old tunnel using the sequential demolition method
Miura Design and Construction of Mountain Tunnels
Mutton et al. DESIGN AND CONSTRUCTION OF WATER HOLDING BULKHEADS AT XSTRATACOAL‟ S OAKY NO 1 MINE
Raju et al. Cross Passage construction in soft soil by RCC box pushing in MRTS
Khali Construction of Railway Tunnels in Highly Adverse Geological Conditions in Himalayas by Using NATM–A Case Study
Fang by Crossing Broken Fault and Water-Rich Geological Mine Method by Using
Goller et al. LINDE FUSRAP SITE REMEDIATION, UTILITY TUNNEL REPLACEMENT, AND INDUSTRY OPERATIONS: A CASE STUDY OF CHALLENGES MET IN WESTERN NEW YORK
Keating et al. Underground Cavern Blasting–Post TBM Traverse
Kellaway et al. The use of geotechnical instrumentation to monitor ground displacements during excavation of the ingula power caverns, for model calibration and design verification purposes
Tirolo Jr et al. Construction of a TBM “Launch Box” in a Complex Urban Environment