Singh, 2020 - Google Patents
Construction of Bogada Tunnel of South Central Railway (India)Singh, 2020
- Document ID
- 10430085882782529383
- Author
- Singh K
- Publication year
- Publication venue
- Tunnelling Asia 2000: Proceedings New Delhi 2000
External Links
Snippet
The Ministry of Railways undertook the gigantic task for converting metre gauge network of track to broad gauge under Project Unit-Gauge. The South Central Railway has taken up the gauge conversion of the section between Giddalur and Nandyal which was originally …
- 238000010276 construction 0 title abstract description 13
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/006—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/02—Portable drilling rigs, truck-or skid-mounted, with their own drive
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/003—Machines for drilling anchor holes and setting anchor bolts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C47/00—Machines for obtaining or the removal of materials in open-pit mines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4009579A (en) | Method for constructing a tunnel or underpass | |
CN109723443B (en) | Tunnel construction method | |
EA037864B1 (en) | Construction method of strong karst water-rich urban shallow-buried tunnel using cantilever boring machine | |
Sandbak et al. | Ground support strategies at the turquoise ridge joint venture, Nevada | |
Singh | Construction of Bogada Tunnel of South Central Railway (India) | |
CN114483054A (en) | Non-explosive excavation construction method for pilot tunnel in upper soft and lower hard stratum | |
Ferraro et al. | Tunneling under highway 401: Construction of a large diameter pre-support pipe canopy | |
SU1761953A1 (en) | Method of working steep coal bed | |
Williams et al. | Recent large-diameter tunnel construction in Singapore using sprayed concrete linnings | |
JP7434046B2 (en) | Shoring unit and steel shoring erection method | |
Zou | Introduction to underground excavation by drilling and blasting | |
JP2001323773A (en) | Tunnel excavation method utilizing advancing drift | |
Poh et al. | Circle Line Phase 6: Completing the Circle Line | |
Varangaonkar | Shafts and Inclined Tunnels | |
BERTA | Tunnel Interior Design and Construction | |
Grieves | Deep Shafts | |
Khali | Construction of railway tunnels for the East Coast Railway, from Adanigarh to PuranaKatak: Issues and challenges for fastest construction | |
Bilgin et al. | A Review of the Conventional Tunneling Methods | |
Ittner et al. | Expansion of the Stockholm metro blue line between Sickla and Nacka: Rock engineering challenges | |
Namli et al. | Effect of changing methodology of tunnel final lining on the construction duration of a metro project | |
Walter | Tunneling in Tight Quarters | |
Dubočanin | The implementation of modified pillar method in the excavation field 2 (OP-2) in the'Osojno-jug'RL'Lubnica'Mine | |
Kadkade | Techniques of Excavation and New Equipment for Tunnelling | |
Talbot et al. | Mining in consolidated and presupported karstified ground conditions | |
Bennet et al. | Tunnels |