[go: up one dir, main page]

WO2021094339A1 - Foundation structure for an offshore apparatus - Google Patents

Foundation structure for an offshore apparatus Download PDF

Info

Publication number
WO2021094339A1
WO2021094339A1 PCT/EP2020/081691 EP2020081691W WO2021094339A1 WO 2021094339 A1 WO2021094339 A1 WO 2021094339A1 EP 2020081691 W EP2020081691 W EP 2020081691W WO 2021094339 A1 WO2021094339 A1 WO 2021094339A1
Authority
WO
WIPO (PCT)
Prior art keywords
anchor
tower
area
foundation structure
cross
Prior art date
Application number
PCT/EP2020/081691
Other languages
German (de)
French (fr)
Inventor
Daniel Bartminn
Claus Linnemann
Maria Carmen CORONEL URIONA
Original Assignee
Rwe Renewables Gmbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rwe Renewables Gmbh filed Critical Rwe Renewables Gmbh
Publication of WO2021094339A1 publication Critical patent/WO2021094339A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors

Definitions

  • the application relates to a foundation structure, in particular for an offshore device, particularly preferably an offshore wind energy device, comprising a tower section extending above a (water) ground in an installation state of the foundation structure and a tower section adjoining the tower section and in the installation state in the ground extending Ankerab cut.
  • the application relates to methods for producing a foundation structure.
  • offshore wind farms with a large number of offshore wind energy devices are installed to generate electrical energy or to provide electrical energy from so-called renewable energy sources.
  • Offshore locations are usually characterized by relatively continuous wind conditions and high average wind speeds, so that so-called offshore wind farms are increasingly being built.
  • an offshore wind park has a large number of offshore wind energy devices, such as a large number of offshore wind turbines, measuring masts and / or at least one offshore substation, via which the offshore wind park electrically, for example, with an onshore substation or another Offshore substation or offshore converter station can be connected.
  • An onshore substation in turn, can be connected to a public power grid.
  • An offshore wind turbine is set up to convert the kinetic wind energy into electrical energy.
  • energy cables are laid in the form of submarine cables.
  • offshore wind farms but also in the case of other offshore devices, it is common practice to place offshore devices on or off with a foundation structure (e.g. monopile, tripod, tripile or jacket foundations). to anchor directly in the seabed, in particular a seabed.
  • a foundation structure e.g. monopile, tripod, tripile or jacket foundations.
  • a foundation structure comprises in particular a tower section and an anchor section (in particular per pile of a foundation structure).
  • the tower section extends (essentially) upwards from the bottom of the water and is in particular at least partially formed by a tower (and / or tower element of a tower).
  • an offshore device such as a platform, a gondola, etc. can be arranged.
  • Tower and offshore device can in particular form the offshore device.
  • the anchor section adjoins the other end of the tower section.
  • the anchor section extends downward from the bottom (surface) of the water.
  • the anchor section can be at least partially formed by an anchor pile, the (horizontal) cross-sectional area of which remains constant along the entire anchor section. In other words, from the bottom of the water, the pile diameter is kept constant according to the state of the art.
  • the application is therefore based on the object of providing a foundation structure, in particular for an offshore device, particularly preferably an offshore Wind energy device to provide which can be manufactured with less use of material and in particular more cost-effectively.
  • the object is achieved according to a first aspect of the application by a foundation structure, in particular for an offshore device, particularly preferably an offshore wind energy device, according to claim 1.
  • the foundation structure comprises a tower section extending above a ground when the foundation structure is installed.
  • the foundation structure comprises an anchor section adjoining the tower section and extending in the ground in the installed state.
  • the anchor section has a connection area which adjoins the tower section.
  • the anchor section has an anchoring area which adjoins the connection area.
  • a cross-sectional area of the anchoring area is smaller than a cross-sectional area of the connection area.
  • a foundation structure for an onshore device such as an onshore Wind energy device
  • offshore device in particular an offshore wind energy device
  • the wall thicknesses of the hollow piles must have certain minimum wall thicknesses for reasons of buckling stability.
  • a Foundation structure reduces the amount of steel without reducing the buckling stability of the foundation structure.
  • the foundation structure is preferably suitable for an offshore device.
  • the foundation structure according to the application can also be used in an onshore device, such as an onshore wind energy device.
  • the application is explained below essentially using an offshore device (and a body of water).
  • the explanations can be applied to an onshore device (and a floor).
  • An offshore device or an offshore structure is preferably an offshore wind energy device, such as an offshore wind turbine, an offshore measuring mast or an offshore substation.
  • an offshore device can be a drilling or production platform.
  • An offshore device can comprise an offshore device which can be fastened by a foundation structure in the water floor, in particular a sea floor.
  • An offshore device can in particular be formed by the offshore device (e.g. a platform, a gondola, etc.) and the foundation structure.
  • a foundation structure that is frequently used is a so-called monopile, but also a tripod, tripile, etc.
  • a foundation structure comprises (precisely) two sections, one section, namely the tower section (in particular, the tower section) being in an installed state of the foundation structure, i.e. when the foundation structure is installed at the installation location in the water floor (or in the ground in the case of an onshore device) in the form of a tubular body), above the bottom of the water (or bottom) and a section, namely the anchor section, is arranged in the bottom of the water (or bottom).
  • a tower can essentially form the tower section, the tower being held in the bottom of the water, in particular a seabed, by the anchor section.
  • the anchor section comprises two areas.
  • a first area is a connecting area that directly adjoins the tower section.
  • connection area can in particular be defined in that the (horizontal) cross-sectional area (in particular a diameter) remains constant over the entire length (corresponds to the extent in a vertical direction in the installation state) and the connection area is in particular directly connected to the tower section.
  • the (horizontal) cross-sectional area of the connecting area preferably corresponds to the (horizontal) cross-sectional area of the tower section at the level of the water floor.
  • a second area (directly) adjoins the connection area, namely the anchoring area.
  • the anchoring area has a (horizontal) (total) cross-sectional area which is smaller than the (horizontal) cross-sectional area of the connecting area.
  • a cross-sectional area of the anchor section at a depth at a distance from the water bed surface must be smaller in comparison to the cross-sectional area of the anchor section at the level of the water bed surface.
  • a cross-sectional area means in particular the horizontal area enclosed by the outer circumferential edge or outer wall of a circumferential wall (and in particular not the area enclosed by the inner circumferential edge or inner wall of a circumferential wall).
  • the thickness of the wall does not matter.
  • the (horizontal) cross-sectional area (in particular a diameter) of the anchoring area can remain constant over the entire length of the anchoring area (corresponds to the extension in a vertical direction in the installed state).
  • the (horizontal) cross-sectional area (in particular a diameter) over the entire length of the anchoring area (corresponds to the extension in a vertical direction in the installation state) can be in steps (two or more steps) be reduced (looking in a vertical direction away from the (water) soil surface, i.e. with increasing embedment depth).
  • the anchoring area can be formed by (precisely) an anchor post (in the case of a monopile), which in particular is located with its predominantly vertical extension in the ground.
  • the tower section and the connecting area can be formed by a tower (or one or more connected tower elements). This means in particular that the outer wall of the connection area can be formed by the tower or its circumferential wall.
  • a cross-sectional area of the anchor pile (which corresponds to the above-mentioned cross-sectional area of the anchoring area) can be smaller than a cross-sectional area of the tower (which corresponds to the above-mentioned cross-sectional area of the connection area) in the connection area.
  • the diameter of the anchor pile can be smaller than the diameter of the tower in the area of the connection area.
  • the diameter means in particular the distance between opposite outer walls of the tower or a pile (not the inner walls).
  • the tower diameter in the connection area can be constant over the entire length of the connection area and / or the anchor pile diameter can be constant over the entire length of the anchor pile, the anchor pile diameter being smaller than the tower diameter.
  • the anchoring area can be formed by a plurality of parallel anchor piles (in the case of a monopile). At least three anchor piles, for example five anchor piles, can preferably be provided.
  • the tower section and the connecting area can be formed by a tower.
  • a total cross-sectional area of the plurality of anchor piles (which corresponds to the above-mentioned cross-sectional area of the anchoring region) can be smaller than a cross-sectional area of the Tower (which corresponds to the above-mentioned cross-sectional area of the connection area) in the connection area.
  • the total cross-sectional area results from the sum of the individual cross-sectional areas.
  • a plurality of anchor piles can have a higher rotational stiffness than a single tubular pile due to a non-circular shape.
  • At least two of the plurality of anchor piles running in parallel can in particular be in direct contact with one another.
  • the overall consumption of material can be reduced and the stability can be improved at the same time.
  • the at least two anchor piles are arranged at a distance from one another.
  • the anchor piles protrude at least partially beyond the cross-sectional area of the connecting section.
  • an anchoring area which is formed from a pile group or pile bundle formed from individual piles has the advantage that a pipe or pile with standard diameters of up to, for example, approx. 1500 mm can be manufactured significantly more cheaply than large piles.
  • the tower section can be formed by a tubular body.
  • the tower section can be formed by a plurality of largely vertical structural elements (e.g. pipe cross-sections, full cross-sections, H, 1-U profiles, etc.).
  • largely vertical structural elements e.g. pipe cross-sections, full cross-sections, H, 1-U profiles, etc.
  • At least one first anchor pile can have a first length and at least one second anchor pile can have a second length, the first length being greater than the second length.
  • at least two anchor piles can be provided in one installation state, which have different embedment depths in the seabed.
  • anchor piles with at least two different embedment depths can be of considerable advantage when installing the foundation structure.
  • such a foundation structure is less sensitive to boulders or the like that may be present in the (water) soil. If a first anchor post of a group of anchor posts encounters a boulder that blocks or at least makes it significantly more difficult to drive the first anchor post deeper into the (water) soil, it may be sufficient for stability if at least one further anchor post of the group of anchor posts is adjacent can be installed to the first anchor post and can be introduced to a greater depth than the first anchor post.
  • an (upper) end of the at least one anchor pile can at least partially engage or protrude into the tower (in the area of the connecting area).
  • the (lower) tower wall of the tower encloses the upper end of the anchor pile.
  • the tower is slipped over one end of the at least one anchor post (at least in one installation state).
  • a positive connection (at least in the installed state) can be established between an inner wall of the tower and an outer wall of the at least one anchor pile (in particular the named end of the at least one anchor pile), in particular a non-positive connection, particularly preferably a materially bonded connection Connection.
  • a non-positive connection can provide a foundation structure with sufficient structural and / or mechanical stability.
  • the (in particular cohesive) connection can be established in any way (at least in the installed state).
  • the connection can be a grout connection.
  • the parts to be connected in this case the lower end of the tower and the upper end of the at least one anchor pile (or the end of the anchor pile group or the ends of the individual anchor piles of an anchor group) can be placed on top of one another or plugged into one another.
  • the space between the inner wall of the tower and the outer wall of the at least one anchor pile can preferably be filled with a high-strength concrete (e.g. by a so-called cement soil mixing) - the so-called "grayed" - (when the foundation structure is installed).
  • a very strong one Connection between the anchor pile or the group of anchor piles and the tower can be provided (at least) in the connection area of the anchor section. It goes without saying that one end of an anchor post can also (also) protrude into the tower section within the tower.
  • the (in particular at least cohesive connection) connection can be established by at least one connecting plate.
  • the at least one connecting plate can be attached to the inner wall of the tower and the outer wall of the at least one anchor post.
  • the at least one connecting plate formed from metal can run in a substantially vertical plane.
  • a plurality of connecting plates can preferably be arranged (circumferentially) between the inner wall of the tower and the outer wall of the at least one anchor pile.
  • the at least one connecting plate can be welded to the inner wall and / or to the outer wall.
  • a material connection can be provided.
  • the remaining spaces between the inner and outer walls and the connecting plates can be filled, for example, with the (water) soil material and / or with a high-strength concrete (as described above). If the connection between the inner wall of the tower and the outer wall of the at least one anchor pile is established with preferably a plurality of connecting plates, this connection can be established in advance, for example in a port (and not at an installation site).
  • connection can be formed by a (water) soil material (in an installation state). Particularly in the case of sufficiently stiff ground conditions (and if the at least one anchor pile protrudes sufficiently far into the tower (for example between 10 and 50 m), a sufficient connection between one end of the at least one anchor pile and one end of the tower. In particular, such a connection can be established with little effort.
  • the area between the upper and lower cross-sectional area in the connecting area can also be filled with soil and / or filled with cement grout and / or have an elastomer-based layer in the vertical plane, which is largely circular and has a hole in the middle that is smaller or smaller is equal to the diameter of the smaller of the two adjoining elements, and is non-positively connected to at least one (either the upper or the lower) section.
  • the tower can be connected directly to at least one anchor post in a form-fitting, non-positive or material-fitting manner.
  • the at least one anchor post can be connected directly to the tower, e.g. by welding or screwing in the connecting zone, the at least one anchor post and / or the tower can be structurally adapted to enable a connection, for example by removing material (e.g. in the form of a slot).
  • this enables the said bodies to penetrate each other before the connection and / or the attachment of additional surfaces which, for example, enable a screw connection.
  • the length of the connection area can be between 20% and 50% of the total length of the anchor section, preferably between 25% and 40%, particularly preferably between 25% and 35% (in an installed state).
  • the cross-sectional area of the anchoring area can be between 90% and 50% of the cross-sectional area of the connection area, preferably between 85% and 60%, particularly preferably between 80% and 65%. A significant saving in material can be achieved.
  • Another aspect of the application is a method for producing a foundation structure, in particular a foundation structure described above.
  • the procedure includes:
  • At least one anchor post with a horizontal cross-sectional area smaller than the cross-sectional area can first be introduced into the (water) soil (with a certain embedment depth). If a group of anchor piles is introduced, all anchor piles of the group can in particular first be introduced into the (water) soil (each with certain minimum embedment depths).
  • the at least one anchor pile can be introduced into the (water) soil by sinking.
  • the tower can be introduced into the (water) soil, in particular around the connecting area of the foundation structure.
  • the (lower) end of the tower can be slipped over the (upper) end of the at least one anchor post (in the case of a group over all upper ends of the anchor posts).
  • the tower is preferably slipped over the at least one end of the at least one anchor post in such a way that the at least one anchor post protrudes into the tower with a predetermined length (for example between 5 and 50 m).
  • a positive (preferably non-positive, particularly preferably material) connection between a tower and an anchor post, in particular an inner wall of the tower and an outer wall of the at least one anchor post can be established, in particular by at least Partial potting of the intermediate area between the inner wall of the tower and the outer wall of the at least one anchor pile (as described above).
  • the method can further comprise:
  • the template for example a plate-shaped element or a pipe segment, can have two or more openings for a corresponding number of anchor piles to be introduced.
  • An opening can essentially (preferably slightly larger) correspond to the cross-sectional area of an anchor pile.
  • a template can, for example, be formed from a pipe segment that has the same dimensions as the upper section of the foundation structure (or slightly smaller), i.e. as the connecting section.
  • the template can be placed stably and vertically on the bottom of the water by means of auxiliary equipment.
  • the anchor piles can be inserted through the template into the bottom of the water.
  • the template can then be lifted upwards.
  • a seal which is largely designed as an annular disk, for example made of an elastomer, can be attached to the anchoring section, for example by screwing, gluing or clamping. After the anchoring section has been introduced into the ground, the upper tower can be inserted into the anchoring section or placed over it in such a way that the attached seal at least largely prevents the ground between the anchoring section and the tower section from being flushed out.
  • Yet another aspect of the application is a method for producing a foundation structure, in particular a foundation structure described above.
  • the procedure includes:
  • the method can in particular be carried out remotely from the installation location of the offshore device or the foundation structure for the offshore device for example in or near a port.
  • a (lower) end of the tower can be slipped over one end of the anchor post (in the case of a group over all upper ends of the anchor posts).
  • a non-positive connection preferably a material connection, can then be established between the tower and the at least one anchor post.
  • at least one connecting plate can preferably be fastened, in particular welded, between the inner wall of the tower and an outer wall of at least one anchor post.
  • the (total) cross-sectional area of the anchor pile or the group of anchor piles can be smaller than the cross-sectional area of the tower that is slipped over the at least one anchor pile.
  • foundation structures and methods for producing a foundation structure can be freely combined with one another.
  • features of the description and / or the dependent claims can be independently inventive, even with complete or partial circumvention of features of the independent claims, alone or freely combined with one another.
  • Fig. 1 is a schematic view of an embodiment of a
  • Fig. 2 is a schematic view of a further embodiment of a
  • Foundation structure according to the present application shows a schematic partial view of a further exemplary embodiment of a foundation structure according to the present application,
  • FIG. 3b shows a schematic partial view of a further exemplary embodiment of a foundation structure according to the present application
  • FIG. 3c shows a schematic partial view of a further exemplary embodiment of a foundation structure according to the present application
  • FIG. 6 shows a schematic plan view of a further exemplary embodiment of a foundation structure according to the present application.
  • Fig. 7 is a schematic plan view of an embodiment of a
  • FIG. 1 shows a schematic view of an exemplary embodiment of a
  • the offshore device can be an offshore wind turbine.
  • An offshore wind turbine can have a generator that generates the kinetic Converts wind energy into electrical energy.
  • the generator can in particular be arranged in a gondola (not shown) which is carried by the upper end of the tower 110.
  • the offshore device can be formed by an offshore device, in the present example the nacelle, and the foundation structure 100.
  • the foundation structure 100 (a monopile is shown only by way of example) is shown in an installation state.
  • the foundation structure 100 is fastened in a water floor 114, in particular a sea floor 114, the tower 110 protruding vertically upwards (i.e. in the positive x-direction) and being partially arranged above the water surface 116, in particular the sea surface 116.
  • the foundation structure 100 can have two sections 102, 104, namely a tower section 102 and an anchor section 104.
  • the tower section 102 is in particular the section of the foundation structure 100 that extends above the water floor 114, for example up to the gondola. In the case of other variants of the registration, the tower section can only extend as far as the surface of the water.
  • the cross-sectional area and the diameter of the tower section 102 can preferably be conically widened from the water surface 116 to the water floor surface.
  • the anchor section 104 extends from the surface of the body of water in the vertical direction (negative x-direction) downwards or in depth.
  • the anchor section 104 is used to fasten the foundation structure 100 in the water floor 114, in particular for anchoring the foundation structure 100 in the water floor 114.
  • the anchor section 104 comprises a connection area 106 and an anchoring area 108.
  • the connection area 106 directly adjoins the tower section 102.
  • the anchoring area 108 directly adjoins the connecting area 106.
  • connection area 106 has a cross-sectional area (which is indicated by an arrow with the reference numeral 118) (running horizontally, i.e. in the y direction), which remains constant over the entire connection area 106 (viewed in the vertical direction).
  • the tower diameter 128 (approx.) Is kept constant from the surface of the water floor to the lower end of the connecting area 106.
  • the anchoring area 108 has a cross-sectional area (which is indicated by an arrow with the reference numeral 120) which remains constant over the entire anchoring area 108 (viewed in the vertical direction).
  • the cross-sectional area 120 is smaller than the cross-sectional area 118.
  • the cross-sectional area 120 of the anchoring area 108 can be between 90% and 50% of the cross-sectional area 118 of the connecting area 106, preferably between 85% and 60%, particularly preferably between 80%. and 65%.
  • the anchoring area 108 is formed by an anchor post 112.
  • the anchor pile 112 can (like the tower 110) in particular be a hollow pile, the circumferential wall of which is preferably formed from metal.
  • the tower 110 and the anchor post 112 have in particular a circular cross section 118, 120.
  • the diameter 126 of the anchor post 112 is kept constant from the end of the connecting area 106 to the end of the anchor post 112.
  • the diameter 126 of the anchor pile 112 is smaller than the diameter 128 of the tower 110 in the area of the connecting region 106.
  • the connecting region 106 also has a length 124 (in the vertical direction) which is between 25% and 50% of the total length 122 of the anchor section 108, preferably between 25% and 40%, particularly preferably between 30% and 35%.
  • the length of the connecting region 106 can be approximately 1/3 of the anchor section 104 and the length of the anchoring region 108 can be approximately 2/3 of the anchor section 104
  • FIG. 2 shows a schematic view of a further exemplary embodiment of a foundation structure 200 according to the present application for an offshore device. To avoid repetition, essentially only the differences from the exemplary embodiment according to FIG. 1 are described below. For the other components of the foundation structure 200, reference is made to the statements above.
  • the anchoring area 208 of the anchor section 204 is present in the form of a plurality of anchor piles 212.1 to 212.3 or a group of anchor piles 212.1 to 212.3. As an example, three anchor piles 212.1 to 212.3 are shown here. It goes without saying that a different number of anchor piles can also be provided (e.g. five).
  • the anchor piles can preferably be arranged next to one another in the form of a triangle (not shown).
  • the anchor piles 212.1 to 212.3 are arranged adjacent to one another and run essentially parallel to one another in the vertical direction.
  • the anchor piles 212.1 to 212.3 are arranged close to one another and contact one another.
  • an anchor post can contact at least two other anchor posts.
  • Each anchor post 212.1 to 212.3 has a cross-sectional area 230 (again indicated by an arrow).
  • the (maximum) (horizontally running) total cross-sectional area of the anchor section 208 that is to say the sum of the individual cross-sectional areas 230 of all anchor piles 212.1 to 212.3, is smaller than the cross-sectional area 218 of the connecting region 206.
  • all anchor piles of a group of anchor piles can have the same length.
  • the total cross-sectional area of the anchoring area remains constant over the entire anchoring area, viewed in the vertical direction.
  • At least one first anchor post 212.1 has a first length 234 and at least one second anchor post 212.2 has a second length 236, the first length 234 being greater than the second length 236.
  • a third anchor post 212.3 has a third length 232, wherein the third length 232 is smaller than the second length 236.
  • the anchoring area 208 has a first sub-area 208.1, the total cross-sectional area of which remains constant over the entire length 232 and is formed by the individual cross-sectional areas 230 of all anchor piles 212.1 to 212.3.
  • a second sub-area 208.2 which directly adjoins the first sub-area 208.1, has a total cross-sectional area that is smaller than the total cross-sectional area of the first sub-area 208.1.
  • the described embodiment is less sensitive to boulders 211 that may be present in the water floor 214 due to the plurality of anchor piles 212.1 to 212.3 .
  • anchor piles 212.1, 212.2 are shown in a different plane than the anchor pile 212.3 (to indicate in particular that not all anchor piles are arranged in the same plane).
  • FIGS. 3a to 3c show schematic partial views of exemplary embodiments of foundation structures 300 according to the present application.
  • the X-axis again corresponds to the vertical direction and the Y-axis to a horizontal direction.
  • Figures 3a and 3b show one
  • FIG. 3c shows a cross-sectional partial view from above.
  • FIG. 1 and FIG. 2 show essentially only the differences from the exemplary embodiments according to FIG. 1 and FIG. 2 .
  • FIGS. 3a to 3c show only a single anchor post 312 in FIGS. 3a to 3c. It goes without saying that the following explanations can also be applied to a group of anchor piles.
  • the tower 310 is placed over the anchor post 312.
  • an upper end 360 of the anchor pile 312 protrudes into the interior space 350 (which is hollow in the non-installed state) of the tower 310, in particular the lower end of the tower 310.
  • a mechanical and / or structural connection between the tower 310 and the anchor post 312 is provided.
  • this connection is formed by the water floor material 348 of the water floor 314.
  • a connection between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312 is represented by the fact that the space 346 between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312 is filled with the water bed material 348 of the water floor 314. Sufficient stability and anchoring can be achieved in this way, in particular in the case of sufficiently stiff ground conditions.
  • FIG. 3b shows an alternative embodiment.
  • the space 346 between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312 is filled with a high-strength concrete 354 (e.g. by cement soil mixing).
  • a grout connection can be established between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312.
  • FIG. 3c shows a further exemplary embodiment.
  • a plurality of connecting plates 356 are fastened between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor post 312.
  • the length of a connecting plate 356 in the x direction can correspond approximately to the length that the anchor post 312 protrudes into the tower 310.
  • the width of a connecting plate 356 can in particular correspond to the distance between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor post 312.
  • a connecting plate 356 can preferably be welded on.
  • the connecting plates 356 can be arranged radially evenly spaced from one another.
  • the remaining intermediate space 346 is in the present case filled with the water bed material 348 of the water floor 314. Alternatively or additionally, it can also be grounded.
  • an intermediate space between the inner wall of the tower and the outer wall of the anchor pile can also be at least partially filled with another filler material, such as an elastomer, polymer, sand-clay, sand-clay mixture, etc.
  • FIG. 4 shows a diagram of a method for producing a foundation structure, in particular a foundation structure previously described in connection with FIGS. 1 to 3c.
  • a first step 401 in particular at an installation location of the foundation structure, at least one anchor pile is introduced into the bottom of the body of water (at a predetermined depth).
  • all anchor piles of the group can in particular be introduced sequentially into the bottom of the water.
  • the at least one further anchor post can be introduced directly adjacent to the first anchor post and in particular at a greater depth.
  • a tower can then be introduced into the bottom of the water in such a way that a connection area is formed into which one end of the at least one anchor post engages or projects.
  • the tower can be slipped over the at least one introduced anchor post.
  • the end of the tower can preferably be introduced into the bottom of the water, so that the connection area described is formed.
  • a cross-sectional area of the anchoring area is smaller than a cross-sectional area of the connection area.
  • a connection can be established between an inner wall of the tower and an outer wall of the at least one anchor pile.
  • a preferably at least non-positive connection between the at least one anchor post and the tower can be established by at least partially grouting the intermediate area between the inner wall of the tower and the outer wall of the at least one anchor post.
  • FIG. 5 shows a diagram of a method for producing a foundation structure, in particular a foundation structure previously described in connection with FIGS. 1 to 3c.
  • the method according to FIG. 5 can preferably be carried out remotely from the installation site of the foundation structure.
  • an anchor pile (or a group of anchor piles) can be provided.
  • step 502 at least one tower can be provided.
  • step 503 at least one mechanical connection is established between an inner wall of the tower and an outer wall of the anchor pile.
  • the tower can be at least partially slipped over the at least one anchor post and preferably at least one connecting plate can be firmly bonded between the inner wall of the tower and the outer wall of the anchor post.
  • the established foundation structure can then be transported to the installation site and introduced into the bottom of the water at the installation site. Subsequently, the remaining intermediate area between the inner wall of the tower and the outer wall of the anchor pile can also be covered with soil.
  • FIG. 6 shows a schematic top view of a further exemplary embodiment of a foundation structure 600 according to the present application. To avoid repetition, essentially only the differences from the previous exemplary embodiments are described below. For the other components of the foundation structure 600, reference is made to the statements above.
  • three anchor piles 612.1 to 612.3 are provided. As can be seen from the top view, the anchor piles 612.1 to 612.3 are positioned in such a way that they protrude beyond the cross-sectional area 618 of the connection region 606.
  • the total cross-sectional area of the individual cross-sectional areas 620.1 to 620.3 is here, however, smaller than the cross-sectional area 618 of the connection region 606.
  • FIG. 6 how, in particular, a cross-sectional area 618, 620.1 to 620.3 is (fundamentally) defined in the present application.
  • the at least one anchor pile 612.1 to 612.3 can be connected directly to the tower 610, for example by welding or screwing.
  • the at least one anchor pile and / or the tower can be structurally adapted to enable a connection, for example through a prior removal of material (e.g. to form a slot).
  • this enables the said bodies 612.1 to 612.3, 610 to penetrate each other before the connection and / or the attachment of additional surfaces which, for example, enable a screw connection.
  • a connection can be made without connecting plates, but preferably by slitting an anchor post 612.1 to 612.3 in such a way that the connection area can be inserted into the slot and preferably welded, glued, screwed, etc.
  • FIG. 7 shows a schematic top view of an exemplary embodiment of a template 780 which can be used in a (previously described) method according to the present application.
  • the method according to FIG. 4 can include the following additional steps:
  • the template 780 preferably a pipe segment 780, can have two or more openings 782 (in the present example three openings 782) for a corresponding number of anchor piles to be introduced.
  • An opening 782 may correspond substantially (preferably slightly larger) to the cross-sectional area of an anchor pile.
  • a template according to the application can be used, which in particular ensures dimensional accuracy and exact positioning of the anchor piles at the installation site.
  • the pipe segment 780 can in particular be formed in such a way that it has the same dimensions as the upper section of the foundation structure (in particular the connection section described, which is preferably placed over it) (or somewhat smaller than the inner cross-sectional area of the connection section).
  • the template 780 can be placed stably and vertically on the body of water 714 by auxiliary devices (not shown).
  • the anchor piles can be inserted through the template into the body of water 714.
  • the template 780 can then be lifted upwards.
  • a tower can be introduced into the bottom of the water in such a way that a connection area is formed into which one end of the at least one anchor post engages.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

The application relates to a foundation structure (100, 200, 300, 600) for an offshore apparatus, in particular an offshore wind power apparatus, comprising: a tower section (102, 202, 302) which extends above the ground (114, 214, 314, 714) when the foundation structure (100, 200, 300, 600) is in an installed state; an anchor section (104, 204) which adjoins the tower section (102, 202, 302) and extends into the ground (114, 214, 314, 714) in the installed state, wherein: the anchor section (104, 204) has a connection region (106, 206, 306, 606) which adjoins the tower section (102, 202, 302); the anchor section (104, 204) has an anchoring region (108, 208, 308) which adjoins the connection region (106, 206, 306, 606), and a cross-sectional area (120) of the anchoring region (108, 208, 308) is smaller than a cross-sectional area (118, 218, 618) of the connection region (106, 206, 306, 606).

Description

Gründungsstruktur für eine Offshore-Vorrichtung Foundation structure for an offshore facility
Die Anmeldung betrifft eine Gründungsstruktur, insbesondere für eine Offshore- Vorrichtung, insbesondere bevorzugt eine Offshore-Windenergievorrichtung, umfassend einen sich in einem Installationszustand der Gründungsstruktur oberhalb eines (Gewässer-)Bodens erstreckenden Turmabschnitt und einen sich an den Turmabschnitt anschließenden und sich in dem Installationszustand in dem Boden erstreckenden Ankerab schnitt. Darüber hinaus betrifft die Anmeldung Verfahren zum Herstellen einer Gründungstruktur. The application relates to a foundation structure, in particular for an offshore device, particularly preferably an offshore wind energy device, comprising a tower section extending above a (water) ground in an installation state of the foundation structure and a tower section adjoining the tower section and in the installation state in the ground extending Ankerab cut. In addition, the application relates to methods for producing a foundation structure.
Vermehrt werden, insbesondere im Meer, Offshore-Bauwerke bzw. Offshore- Vorrichtungen errichtet. So werden zur elektrischen Energieerzeugung bzw. zur Bereitstellung elektrischer Energie aus so genannten erneuerbaren Energiequellen beispielsweise Offshore-Windparks mit einer Vielzahl von Offshore- Windenergievorrichtungen installiert. Offshore-Standorte zeichnen sich üblicherweise durch relativ kontinuierliche Windbedingungen und hohe durchschnittliche Windgeschwindigkeiten aus, so dass vermehrt so genannte Offshore-Windparks errichtet werden. ln der Regel weist ein Offshore-Windpark eine Vielzahl an Offshore- Windenergievorrichtungen auf, wie eine Vielzahl von Offshore-Windkraftanlagen, Messmasten und/oder mindestens eine Offshore-Substation, über die der Offshore- Windpark elektrisch beispielsweise mit einer Onshore-Substation oder einer weiteren Offshore-Substation bzw. Offshore-Konverterstation verbunden sein kann. Eine Onshore-Substation wiederum kann mit einem öffentlichen Stromnetz verbunden sein. Eine Offshore-Windkraftanlage ist zum Wandeln der kinetischen Windenergie in elektrische Energie eingerichtet. Zum Übertragen der erzeugten elektrischen Energie zwischen zwei Offshore-Windenergievorrichtungen oder einer Offshore- Windenergievorrichtung und einer Onshore-Vorrichtung werden Energiekabel in Form von Seekabeln verlegt. Increasingly, especially in the sea, offshore structures or offshore devices are being built. For example, offshore wind farms with a large number of offshore wind energy devices are installed to generate electrical energy or to provide electrical energy from so-called renewable energy sources. Offshore locations are usually characterized by relatively continuous wind conditions and high average wind speeds, so that so-called offshore wind farms are increasingly being built. As a rule, an offshore wind park has a large number of offshore wind energy devices, such as a large number of offshore wind turbines, measuring masts and / or at least one offshore substation, via which the offshore wind park electrically, for example, with an onshore substation or another Offshore substation or offshore converter station can be connected. An onshore substation, in turn, can be connected to a public power grid. An offshore wind turbine is set up to convert the kinetic wind energy into electrical energy. To transfer the generated electrical energy between two offshore wind energy devices or an offshore Wind energy device and an onshore device, energy cables are laid in the form of submarine cables.
Bei Offshore-Windparks, aber auch bei anderen Offshore-Vorrichtungen, ist es üblich, Offshore-Vorrichtung durch eine Gründungsstruktur (z.B. Monopile-, Tripod-, Tripile- oder Jacket-Gründungen) aufbzw. in dem Gewässerboden, insbesondere einem Meeresboden, direkt zu verankern. In the case of offshore wind farms, but also in the case of other offshore devices, it is common practice to place offshore devices on or off with a foundation structure (e.g. monopile, tripod, tripile or jacket foundations). to anchor directly in the seabed, in particular a seabed.
Eine Gründungsstruktur umfasst insbesondere einen Turmabschnitt und einen Ankerabschnitt (insbesondere pro Pfahl einer Gründungsstruktur). Der Turmabschnitt erstreckt sich (im Wesentlichen) von dem Gewässerboden nach oben und wird insbesondere zumindest teilweise durch einen Turm (und/oder Turmelement eines Turms) gebildet. An dem aus dem Wasser ragenden Ende des Turms kann insbesondere eine Offshore-Einrichtung, wie eine Plattform, eine Gondel etc. angeordnet sein. Turm und Offshore-Einrichtung können insbesondere die Offshore-Vorrichtung bilden. A foundation structure comprises in particular a tower section and an anchor section (in particular per pile of a foundation structure). The tower section extends (essentially) upwards from the bottom of the water and is in particular at least partially formed by a tower (and / or tower element of a tower). At the end of the tower protruding out of the water, in particular an offshore device such as a platform, a gondola, etc. can be arranged. Tower and offshore device can in particular form the offshore device.
An das andere Ende des Turmabschnitts schließt sich der Ankerabschnitt an. Insbesondere erstreckt sich beim Stand der Technik der Ankerabschnitt von dem Gewässerboden(-oberfläche) nach unten. Hierbei kann der Ankerabschnitt zumindest teilweise durch einen Ankerpfahl gebildet sein, dessen (horizontale) Querschnittsfläche entlang des gesamten Ankerabschnitts konstant bleibt. Anders ausgedrückt wird ab dem Gewässerboden der Pfahldurchmesser nach dem Stand der Technik konstant gehalten. The anchor section adjoins the other end of the tower section. In particular, in the prior art, the anchor section extends downward from the bottom (surface) of the water. Here, the anchor section can be at least partially formed by an anchor pile, the (horizontal) cross-sectional area of which remains constant along the entire anchor section. In other words, from the bottom of the water, the pile diameter is kept constant according to the state of the art.
Nachteilig an derartigen Gründungstrukturen sind der hohe Materialbedarf, insbesondere an Stahl, der für die Herstellung und Konstruktion einer Gründungsstruktur erforderlich sind, und die damit einhergehenden Kosten. Disadvantages of such foundation structures are the high material requirements, in particular steel, which are required for the manufacture and construction of a foundation structure, and the associated costs.
Daher liegt der Anmeldung die Aufgabe zugrunde, eine Gründungsstruktur, insbesondere für eine Offshore-Vorrichtung, insbesondere bevorzugt eine Offshore- Windenergievorrichtung, bereitzustellen, welche mit weniger Materialeinsatz und insbesondere kostengünstiger hergestellt werden kann. The application is therefore based on the object of providing a foundation structure, in particular for an offshore device, particularly preferably an offshore Wind energy device to provide which can be manufactured with less use of material and in particular more cost-effectively.
Die Aufgabe wird gemäß einem ersten Aspekt der Anmeldung gelöst durch eine Gründungstruktur, insbesondere für eine Offshore-Vorrichtung, insbesondere bevorzugt eine Offshore-Windenergievorrichtung, nach Anspruch 1. Die Gründungsstruktur umfasst einen sich in einem Installationszustand der Gründungsstruktur oberhalb eines Bodens erstreckenden Turmabschnitt. Die Gründungsstruktur umfasst einen sich an den Turmabschnitt anschließenden und sich in dem Installationszustand in dem Boden erstreckenden Ankerabschnitt. Der Ankerabschnitt weist einen Verbindungsbereich auf, der sich an den Turmabschnitt anschließt. Der Ankerabschnitt weist einen Verankerungsbereich auf, der sich an den Verbindungsbereich anschließt. Eine Querschnittsfläche des Verankerungsbereichs ist kleiner als eine Querschnittsfläche des Verbindungsbereichs. The object is achieved according to a first aspect of the application by a foundation structure, in particular for an offshore device, particularly preferably an offshore wind energy device, according to claim 1. The foundation structure comprises a tower section extending above a ground when the foundation structure is installed. The foundation structure comprises an anchor section adjoining the tower section and extending in the ground in the installed state. The anchor section has a connection area which adjoins the tower section. The anchor section has an anchoring area which adjoins the connection area. A cross-sectional area of the anchoring area is smaller than a cross-sectional area of the connection area.
Indem im Gegensatz zum Stand der Technik eine Gründungsstruktur mit einem Ankerabschnitt bereitgestellt wird, bei dem die (horizontale) Querschnittsfläche sich in vertikaler Richtung von dem (Gewässer-)Boden aus gesehen reduziert, wird eine Gründungstruktur für eine Onshore-Vorrichtung (wie eine Onshore- Windenergievorrichtung), insbesondere jedoch für Offshore-Vorrichtung bereitgestellt, insbesondere eine Offshore-Windenergievorrichtung, welche mit weniger Materialeinsatz und insbesondere kostengünstiger herstellbar ist. Insbesondere ist anmeldungsgemäß erkannt worden, dass beim Stand der Technik mit zunehmender Einbindetiefe in dem (Gewässer-)Boden das Material (insbesondere der Stahl) eines Ankerpfahles nicht optimal ausgenutzt wird, da die einwirkenden Momente für die interne Bemessung der Pfahlstruktur mit zunehmender Einbindelänge bzw. -tiefe abnehmen. Die Wandstärken der Hohlpfähle müssen aber aus Gründen der Beulstabilität gewisse Mindestwandstärken aufweisen. Indem jedoch die (horizontale) Querschnittsfläche, insbesondere der Durchmesser eines Pfahls, (mit zunehmender Einbindetiefe) reduziert wird (zumindest einmal), wird bei einer Gründungstruktur die Stahlmenge reduziert, ohne dass die Beulstabilität der Gründungstruktur reduziert wird. By providing, in contrast to the prior art, a foundation structure with an anchor section in which the (horizontal) cross-sectional area is reduced in the vertical direction from the (water) bottom, a foundation structure for an onshore device (such as an onshore Wind energy device), but in particular provided for offshore device, in particular an offshore wind energy device, which can be produced with less use of material and in particular more cost-effectively. In particular, it has been recognized according to the application that the material (especially the steel) of an anchor pile is not optimally used in the prior art with increasing embedment depth in the (water) soil, since the moments acting for the internal dimensioning of the pile structure with increasing embedment length or -depth decrease. However, the wall thicknesses of the hollow piles must have certain minimum wall thicknesses for reasons of buckling stability. However, by reducing the (horizontal) cross-sectional area, in particular the diameter of a pile (with increasing embedment depth) (at least once), a Foundation structure reduces the amount of steel without reducing the buckling stability of the foundation structure.
Die Gründungsstruktur ist vorzugsweise für eine Offshore-Vorrichtung geeignet. Jedoch kann die anmeldungsgemäße Gründungsstruktur auch bei einer Onshore- Vorrichtung, wie eine Onshore- Windenergievorrichtung, verwendet werden. Insbesondere wird nachfolgend die Anmeldung im Wesentlichen anhand einer Offshore-Vorrichtung (und einem Gewässerboden) erläutert. Die Ausführungen lassen sich jedoch auf eine Onshore-Vorrichtung (und einen Boden) übertragen. The foundation structure is preferably suitable for an offshore device. However, the foundation structure according to the application can also be used in an onshore device, such as an onshore wind energy device. In particular, the application is explained below essentially using an offshore device (and a body of water). However, the explanations can be applied to an onshore device (and a floor).
Eine Offshore-Vorrichtung bzw. ein Offshore-Bauwerk ist vorzugsweise eine Offshore- Windenergievorrichtung, wie eine Offshore-Windkraftanlage, ein Offshore-Messmast oder eine Offshore-Substation. Ferner kann eine Offshore-Vorrichtung eine Bohr- oder Förderplattform sein. Eine Offshore-Vorrichtung kann eine Offshore-Einrichtung umfassen, die durch eine Gründungsstruktur im Gewässerboden, insbesondere ein Meeresboden, befestigt sein kann. Eine Offshore-Vorrichtung kann insbesondere durch die Offshore-Einrichtung (z.B. eine Plattform, eine Gondel etc.) und der Gründungsstruktur gebildet sein. Eine häufig eingesetzte Gründungsstruktur ist ein so genanntes Monopile, aber auch ein Tripod, Tripile etc. An offshore device or an offshore structure is preferably an offshore wind energy device, such as an offshore wind turbine, an offshore measuring mast or an offshore substation. Furthermore, an offshore device can be a drilling or production platform. An offshore device can comprise an offshore device which can be fastened by a foundation structure in the water floor, in particular a sea floor. An offshore device can in particular be formed by the offshore device (e.g. a platform, a gondola, etc.) and the foundation structure. A foundation structure that is frequently used is a so-called monopile, but also a tripod, tripile, etc.
Eine anmeldungsgemäße Gründungstruktur umfasst (genau) zwei Abschnitte, wobei sich in einem Installationszustand der Gründungsstruktur, also wenn die Gründungsstruktur an dem Installationsort in dem Gewässerboden (oder bei einer Onshore-Vorrichtung in dem Boden) montiert ist, ein Abschnitt, nämlich der Turmabschnitt (insbesondere in Form eines rohrförmigen Körpers), oberhalb des Gewässerbodens (bzw. Bodens) und ein Abschnitt, nämlich der Ankerabschnitt, in dem Gewässerboden (bzw. Boden) angeordnet ist. Ein Turm kann im Wesentlichen den Turmabschnitt bilden, wobei der Turm durch den Ankerabschnitt im Gewässerboden, insbesondere einem Meeresboden, gehalten wird. Anmeldungsgemäß umfasst der Ankerabschnitt zwei Bereiche. Ein erster Bereich ist ein Verbindungsbereich, der sich unmittelbar an den Turmabschnitt anschließt. Der Verbindungsbereich kann insbesondere dadurch definiert sein, dass die (horizontale) Querschnittsfläche (insbesondere ein Durchmesser) über die gesamte Länge (entspricht der Erstreckung in einer vertikalen Richtung in dem Installationszustand) konstant bleibt und sich der Verbindungsbereich insbesondere unmittelbar an den Turmabschnitt anschließt. Vorzugsweise entspricht die (horizontale) Querschnittsfläche des Verbindungsbereichs der (horizontalen) Querschnittsfläche des Turmabschnitts auf Höhe des Gewässerbodens. A foundation structure according to the application comprises (precisely) two sections, one section, namely the tower section (in particular, the tower section) being in an installed state of the foundation structure, i.e. when the foundation structure is installed at the installation location in the water floor (or in the ground in the case of an onshore device) in the form of a tubular body), above the bottom of the water (or bottom) and a section, namely the anchor section, is arranged in the bottom of the water (or bottom). A tower can essentially form the tower section, the tower being held in the bottom of the water, in particular a seabed, by the anchor section. According to the application, the anchor section comprises two areas. A first area is a connecting area that directly adjoins the tower section. The connection area can in particular be defined in that the (horizontal) cross-sectional area (in particular a diameter) remains constant over the entire length (corresponds to the extent in a vertical direction in the installation state) and the connection area is in particular directly connected to the tower section. The (horizontal) cross-sectional area of the connecting area preferably corresponds to the (horizontal) cross-sectional area of the tower section at the level of the water floor.
An den Verbindungsbereich schließt sich ein zweiter Bereich (unmittelbar) an, nämlich der Verankerungsbereich. Der Verankerungsbereich weist anmeldungsgemäß eine (horizontale) (Gesamt-) Querschnittsfläche auf, die kleiner ist als die (horizontale) Querschnittsfläche des Verbindungsbereichs. Anders ausgedrückt muss eine Querschnittsfläche des Ankerabschnitts in einer von dem Gewässerbodenoberfläche beabstandeten Tiefe kleiner sein im Vergleich zu der Querschnittsfläche des Ankerabschnitts in Höhe der Gewässerbodenoberfläche. A second area (directly) adjoins the connection area, namely the anchoring area. According to the application, the anchoring area has a (horizontal) (total) cross-sectional area which is smaller than the (horizontal) cross-sectional area of the connecting area. In other words, a cross-sectional area of the anchor section at a depth at a distance from the water bed surface must be smaller in comparison to the cross-sectional area of the anchor section at the level of the water bed surface.
Eine Querschnittsfläche meint in der vorliegenden Anmeldung insbesondere die horizontale durch die äußere Umfangskante bzw. Außenwand einer umlaufenden Wand umschlossene Fläche (und insbesondere nicht die durch die innere Umfangskante bzw. Innenwand einer umlaufenden Wand umschlossene Fläche). Insbesondere kommt es nicht auf die Dicke der Wand an. In the present application, a cross-sectional area means in particular the horizontal area enclosed by the outer circumferential edge or outer wall of a circumferential wall (and in particular not the area enclosed by the inner circumferential edge or inner wall of a circumferential wall). In particular, the thickness of the wall does not matter.
Bei einer Ausführungsform kann die die (horizontale) Querschnittsfläche (insbesondere ein Durchmesser) des Verankerungsbereichs über die gesamte Länge des Verankerungsbereichs (entspricht der Erstreckung in einer vertikalen Richtung in dem Installationszustand) konstant bleiben. Bei einer bevorzugten Ausführungsform kann die (horizontale) Querschnittsfläche (insbesondere ein Durchmesser) über die gesamte Länge des Verankerungsbereichs (entspricht der Erstreckung in einer vertikalen Richtung in dem Installationszustand) stufenweise (zwei oder mehr Stufen) reduziert werden (in eine vertikale Richtung von den (Gewässer-)Bodenoberfläche weg gesehen, also mit größer werdender Einbindetiefe). In one embodiment, the (horizontal) cross-sectional area (in particular a diameter) of the anchoring area can remain constant over the entire length of the anchoring area (corresponds to the extension in a vertical direction in the installed state). In a preferred embodiment, the (horizontal) cross-sectional area (in particular a diameter) over the entire length of the anchoring area (corresponds to the extension in a vertical direction in the installation state) can be in steps (two or more steps) be reduced (looking in a vertical direction away from the (water) soil surface, i.e. with increasing embedment depth).
Gemäß einer ersten Ausführungsform der anmeldungsgemäßen Gründungsstruktur kann der Verankerungsbereich durch (genau) einen Ankerpfahl gebildet sein (bei einem Monopile), der sich insbesondere mit seiner überwiegenden vertikalen Erstreckung im Boden befindet. Der Turmabschnitt und der Verbindungsbereich können durch einen Turm (oder einem oder mehreren verbundenen Turmelementen) gebildet sein. Dies meint insbesondere, dass die Außenwand des Verbindungsbereichs durch den Turm bzw. dessen umlaufende Wand gebildet sein kann. According to a first embodiment of the foundation structure according to the application, the anchoring area can be formed by (precisely) an anchor post (in the case of a monopile), which in particular is located with its predominantly vertical extension in the ground. The tower section and the connecting area can be formed by a tower (or one or more connected tower elements). This means in particular that the outer wall of the connection area can be formed by the tower or its circumferential wall.
Eine Querschnittsfläche des Ankerpfahls (welche der oben genannten Querschnittsfläche des Verankerungsbereichs entspricht) kann kleiner sein als eine Querschnittsfläche des Turms (welche der oben genannten Querschnittsfläche des Verbindungsbereichs entspricht) in dem Verbindungsbereich. Insbesondere kann der Durchmesser des Ankerpfahls kleiner sein als der Durchmesser des Turms im Bereich des Verbindungsbereichs. Der Durchmesser meint insbesondere den Abstand zwischen gegenüberliegenden Außenwänden des Turms bzw. eines Pfahls (nicht der Innenwände). So kann der Turmdurchmesser im Verbindungsbereich über die gesamte Länge des Verbindungsbereichs konstant sein und/oder der Ankerpfahldurchmesser kann über die gesamte Länge des Ankerpfahls konstant sein, wobei der Ankerpfahldurchmesser kleiner ist als der Turmdurchmesser. A cross-sectional area of the anchor pile (which corresponds to the above-mentioned cross-sectional area of the anchoring area) can be smaller than a cross-sectional area of the tower (which corresponds to the above-mentioned cross-sectional area of the connection area) in the connection area. In particular, the diameter of the anchor pile can be smaller than the diameter of the tower in the area of the connection area. The diameter means in particular the distance between opposite outer walls of the tower or a pile (not the inner walls). The tower diameter in the connection area can be constant over the entire length of the connection area and / or the anchor pile diameter can be constant over the entire length of the anchor pile, the anchor pile diameter being smaller than the tower diameter.
Gemäß einer weiteren bevorzugten Ausführungsform der anmeldungsgemäßen Gründungsstruktur kann der Verankerungsbereich durch eine Mehrzahl von parallel verlaufenden Ankerpfählen gebildet sein (bei einem Monopile). Vorzugsweise können zumindest drei Ankerpfähle, beispielsweise fünf Ankerpfähle, vorgesehen sein. Wie bereits beschrieben wurde, können der Turmabschnitt und der Verbindungsbereich durch einen Turm gebildet sein. Eine Gesamtquerschnittsfläche der Mehrzahl der Ankerpfähle (welche der oben genannten Querschnittsfläche des Verankerungsbereichs entspricht) kann kleiner sein als eine Querschnittsfläche des Turms (welche der oben genannten Querschnittsfläche des Verbindungsbereichs entspricht) in dem Verbindungsbereich. Die Gesamtquerschnittsfläche ergibt sich aus der Summe der Einzelquerschnittsflächen. According to a further preferred embodiment of the foundation structure according to the application, the anchoring area can be formed by a plurality of parallel anchor piles (in the case of a monopile). At least three anchor piles, for example five anchor piles, can preferably be provided. As already described, the tower section and the connecting area can be formed by a tower. A total cross-sectional area of the plurality of anchor piles (which corresponds to the above-mentioned cross-sectional area of the anchoring region) can be smaller than a cross-sectional area of the Tower (which corresponds to the above-mentioned cross-sectional area of the connection area) in the connection area. The total cross-sectional area results from the sum of the individual cross-sectional areas.
Eine Mehrzahl von Ankerpfählen kann aufgrund einer nicht-kreisförmigen Form eine höhere Rotationssteifigkeit aufweisen, als ein einzelner rohrförmiger Pfahl. A plurality of anchor piles can have a higher rotational stiffness than a single tubular pile due to a non-circular shape.
Zumindest zwei der Mehrzahl von parallel verlaufenden Ankerpfählen können insbesondere in einem direkten Kontakt zu einander stehen. Durch die Verwendung einer Mehrzahl von Ankerpfählen mit jeweils deutlich geringeren Querschnitten (verglichen mit dem Turmquerschnitt im Verbindungsbereich) kann der Materialverbrauch insgesamt verringert und die Stabilität gleichzeitig verbessert werden. At least two of the plurality of anchor piles running in parallel can in particular be in direct contact with one another. By using a plurality of anchor piles, each with significantly smaller cross-sections (compared to the tower cross-section in the connection area), the overall consumption of material can be reduced and the stability can be improved at the same time.
Bei einer weiteren Ausführungsform kann vorgesehen sein, dass die zumindest zwei Ankerpfähle beabstandet zueinander angeordnet sind. Insbesondere kann, in einer Draufsicht gesehen, vorgesehen sein, dass die Ankerpfähle zumindest teilweise über die Querschnittsfläche des Verbindungsabschnitts hinausragen. In a further embodiment it can be provided that the at least two anchor piles are arranged at a distance from one another. In particular, seen in a plan view, it can be provided that the anchor piles protrude at least partially beyond the cross-sectional area of the connecting section.
Insbesondere ist anmeldungsgemäß festgestellt worden, dass bei hinreichend steifen Bodenverhältnissen die Einzelpfähle als Pfahlgruppe mit einer größeren Gesamtsteifigkeit wirken, als die Summe der Einzelsteifigkeiten offenbaren würde. In particular, it has been determined according to the application that, given sufficiently rigid soil conditions, the individual piles act as a pile group with a greater overall rigidity than the sum of the individual rigidity would reveal.
Zudem sind die Herstellung und der Transport von Pfählen mit geringerem Querschnitt, insbesondere Durchmesser, einfacher und insbesondere kostengünstiger. Insbesondere hat ein Verankerungsbereich, der aus einer aus Einzelpfählen gebildeten Pfahlgruppe bzw. Pfahlbündel gebildet ist, den Vorteil, dass ein Rohr bzw. Pfahl mit Standarddurchmessern bis beispielsweise ca. 1500 mm deutlich günstiger herstellbar ist als Großpfähle. Der Turmabschnitt kann durch einen rohrförmigen Körper gebildet sein. In addition, the manufacture and transport of piles with a smaller cross section, in particular diameter, are simpler and, in particular, cheaper. In particular, an anchoring area which is formed from a pile group or pile bundle formed from individual piles has the advantage that a pipe or pile with standard diameters of up to, for example, approx. 1500 mm can be manufactured significantly more cheaply than large piles. The tower section can be formed by a tubular body.
Insbesondere kann der Turmabschnitt durch eine Mehrzahl von weitestgehend vertikal verlaufenden Strukturelementen (z.B. Rohrquerschnitte, Vollquerschnitte, H-, 1- U-Profile etc.) gebildet sein. In particular, the tower section can be formed by a plurality of largely vertical structural elements (e.g. pipe cross-sections, full cross-sections, H, 1-U profiles, etc.).
Darüber hinaus kann, gemäß einer besonders bevorzugten Ausführungsform der anmeldungsgemäßen Gründungsstruktur, mindestens ein erster Ankerpfahl eine erste Länge aufweisen und mindestens ein zweiter Ankerpfahl eine zweite Länge aufweisen, wobei die erste Länge größer ist als die zweite Länge. Anders ausgedrückt können zumindest zwei Ankerpfähle in einem Installationszustand bereitgestellt werden, die unterschiedliche Einbindetiefen in den Gewässerboden aufweisen. Durch die Nutzung von Ankerpfählen mit unterschiedlicher Länge (bzw. Einbindetiefe) kann in einfacher Weise eine stufenweise Reduktion der (Gesamt-) Querschnittsfläche des Verankerungsbereichs bereitgestellt werden. In addition, according to a particularly preferred embodiment of the foundation structure according to the application, at least one first anchor pile can have a first length and at least one second anchor pile can have a second length, the first length being greater than the second length. In other words, at least two anchor piles can be provided in one installation state, which have different embedment depths in the seabed. By using anchor piles of different lengths (or embedment depths), a step-by-step reduction of the (total) cross-sectional area of the anchoring area can be provided in a simple manner.
Ferner können Ankerpfähle mit zumindest zwei unterschiedlichen Einbindetiefen von erheblichem Vorteil bei der Installierung der Gründungsstruktur sein. Insbesondere ist eine derartige Gründungsstruktur weniger empfindlich gegenüber ggf. im (Gewässer-)Boden vorhandenen Findlingen oder dergleichen. Trifft ein erster Ankerpfahl einer Gruppe von Ankerpfählen auf einen Findling, der ein tieferes Einbringen des ersten Ankerpfahls in den (Gewässer-) Boden blockiert oder zumindest deutlich erschwert, kann es für die Stabilität ausreichend sein, wenn mindestens ein weiterer Ankerpfahl der Gruppe von Ankerpfählen benachbart zu dem ersten Ankerpfahl installiert werden kann und in eine größere Tiefe eingebracht werden kann als der erste Ankerpfahl. Furthermore, anchor piles with at least two different embedment depths can be of considerable advantage when installing the foundation structure. In particular, such a foundation structure is less sensitive to boulders or the like that may be present in the (water) soil. If a first anchor post of a group of anchor posts encounters a boulder that blocks or at least makes it significantly more difficult to drive the first anchor post deeper into the (water) soil, it may be sufficient for stability if at least one further anchor post of the group of anchor posts is adjacent can be installed to the first anchor post and can be introduced to a greater depth than the first anchor post.
Darüber hinaus kann es möglich sein, bei der Verwendung mehrerer (kleiner) Ankerpfähle die einzelnen Ankerpfähle am unteren Ende nicht senkrecht zur Hauptrichtung enden, sondern einige oder alle Pfähle abgeschrägt sind, so dass die Gesamtheit der Ankerpfähle in der Seitenansicht einen unten angespitzten Pfahl ergeben, der sich mit einem geringeren Widerstand in den Boden einbringen lässt. Gemäß einer weiteren Ausführungsform einer anmeldungsgemäßen Gründungsstruktur kann ein (oberes) Ende des mindestens einen Ankerpfahls in den Turm (in dem Bereich des Verbindungsbereichs) zumindest teilweise eingreifen bzw. hineinragen. Dies meint insbesondere, dass die (untere) Turmwand des Turms das obere Ende des Ankerpfahls umschließt. Insbesondere ist der Turm über ein Ende des mindestens einen Ankerpfahls (zumindest in einem Installationszustand) übergestülpt. In addition, when using several (small) anchor piles, the individual anchor piles at the lower end do not end perpendicular to the main direction, but some or all of the piles are bevelled so that the entirety of the anchor piles result in a pile pointed at the bottom when viewed from the side, which can be inserted into the ground with less resistance. According to a further embodiment of a foundation structure according to the application, an (upper) end of the at least one anchor pile can at least partially engage or protrude into the tower (in the area of the connecting area). This means in particular that the (lower) tower wall of the tower encloses the upper end of the anchor pile. In particular, the tower is slipped over one end of the at least one anchor post (at least in one installation state).
Vorzugsweise kann, gemäß einer weiteren Ausführungsform, zwischen einer Innenwand des Turms und einer Außenwand des mindestens einen Ankerpfahls (insbesondere des genannten Endes des mindestens einen Ankerpfahls) eine formschlüssige Verbindung (zumindest im Installationszustand) hergestellt sein, insbesondere eine kraftschlüssige Verbindung, insbesondere bevorzugt eine stoffschlüssige Verbindung. Insbesondere durch eine kraftschlüssige Verbindung kann eine Gründungsstruktur mit ausreichender struktureller und/oder mechanischer Stabilität bereitgestellt werden. Preferably, according to a further embodiment, a positive connection (at least in the installed state) can be established between an inner wall of the tower and an outer wall of the at least one anchor pile (in particular the named end of the at least one anchor pile), in particular a non-positive connection, particularly preferably a materially bonded connection Connection. In particular, a non-positive connection can provide a foundation structure with sufficient structural and / or mechanical stability.
Grundsätzlich kann die (insbesondere stoffschlüssige) Verbindung in beliebiger Weise (zumindest in dem Installationszustand) hergestellt sein. Gemäß einer Ausführungsform der anmeldungsgemäßen Gründungsstruktur kann die Verbindung eine Grout-Verbindung sein. In principle, the (in particular cohesive) connection can be established in any way (at least in the installed state). According to one embodiment of the foundation structure according to the application, the connection can be a grout connection.
Wie bereits beschrieben wurde, können die zu verbindenden Teile, vorliegend das untere Ende des Turms und das obere Ende des mindestens einen Ankerpfahls (oder das Ende der Ankerpfahlgruppe bzw. die Enden der einzelnen Ankerpfähle einer Ankergruppe) übereinander gestülpt oder ineinander gesteckt sein. Der Zwischenraum zwischen der Innenwand des Turms und der Außenwand des mindestens einen Ankerpfahls kann vorzugsweise mit einem hochfesten Beton (z.B. durch ein so genanntes Zement Soil Mixing) - dem sogenannten "vergrouten" - gefüllt sein (in einem Installationszustand der Gründungsstruktur). Eine hochfeste Verbindung zwischen dem Ankerpfahl oder der Gruppe von Ankerpfählen und dem Turm kann (zumindest) in dem Verbindungsbereich des Ankerabschnitts bereitgestellt werden. Es versteht sich, dass ein Ende eines Ankerpfahls auch innerhalb des Turms (auch) in den Turmabschnitt ragen kann. As already described, the parts to be connected, in this case the lower end of the tower and the upper end of the at least one anchor pile (or the end of the anchor pile group or the ends of the individual anchor piles of an anchor group) can be placed on top of one another or plugged into one another. The space between the inner wall of the tower and the outer wall of the at least one anchor pile can preferably be filled with a high-strength concrete (e.g. by a so-called cement soil mixing) - the so-called "grayed" - (when the foundation structure is installed). A very strong one Connection between the anchor pile or the group of anchor piles and the tower can be provided (at least) in the connection area of the anchor section. It goes without saying that one end of an anchor post can also (also) protrude into the tower section within the tower.
Alternativ oder (bevorzugt) zusätzlich kann die (insbesondere zumindest stoffschlüssige Verbindung) Verbindung durch mindestens ein Verbindungsblech hergestellt sein. Das mindestens eine Verbindungsblech kann an der Innenwand des Turms und der Außenwand des mindestens einen Ankerpfahls befestigt sein. Insbesondere kann das mindestens eine aus Metall gebildete Verbindungsblech in einer im Wesentlichen vertikalen Ebene verlaufen. Vorzugsweise kann eine Mehrzahl von Verbindungsblechen (umlaufend) zwischen der Innenwand des Turms und der Außenwand des mindestens einen Ankerpfahls angeordnet sein. Insbesondere kann das mindestens eine Verbindungsblech an der Innenwand und/oder an der Außenwand angeschweißt sein. Eine stoffschlüssige Verbindung kann bereitgestellt werden. Alternatively or (preferably) additionally, the (in particular at least cohesive connection) connection can be established by at least one connecting plate. The at least one connecting plate can be attached to the inner wall of the tower and the outer wall of the at least one anchor post. In particular, the at least one connecting plate formed from metal can run in a substantially vertical plane. A plurality of connecting plates can preferably be arranged (circumferentially) between the inner wall of the tower and the outer wall of the at least one anchor pile. In particular, the at least one connecting plate can be welded to the inner wall and / or to the outer wall. A material connection can be provided.
Die verbleibenden Zwischenräume zwischen Innen- und Außenwand sowie den Verbindungsblechen können beispielsweise mit dem (Gewässer-) Bodenmaterial und/oder mit einem hochfesten Beton (wie zuvor beschrieben wurde) gefüllt sein. Wenn die Verbindung zwischen der Innenwand des Turms und der Außenwand des mindestens einen Ankerpfahls mit vorzugsweise einer Mehrzahl von Verbindungsblechen hergestellt ist, kann diese Verbindung bereits vorab, beispielsweise in einem Hafen, hergestellt werden (und nicht erst an einem Installationsort). The remaining spaces between the inner and outer walls and the connecting plates can be filled, for example, with the (water) soil material and / or with a high-strength concrete (as described above). If the connection between the inner wall of the tower and the outer wall of the at least one anchor pile is established with preferably a plurality of connecting plates, this connection can be established in advance, for example in a port (and not at an installation site).
Alternativ oder zusätzlich kann die Verbindung durch ein (Gewässer-) Bodenmaterial gebildet sein (in einem Installationszustand). Insbesondere bei hinreichend steifen Bodenverhältnissen (und wenn der mindestens eine Ankerpfahl ausreichend weit in den Turm hineinragt (z.B. zwischen 10 und 50 m), kann eine ausreichende Verbindung zwischen einem Ende des mindestens einen Ankerpfahls und einem Ende des Turms hergestellt sein. Insbesondere kann eine derartige Verbindung aufwandsarm hergestellt werden. Alternatively or additionally, the connection can be formed by a (water) soil material (in an installation state). Particularly in the case of sufficiently stiff ground conditions (and if the at least one anchor pile protrudes sufficiently far into the tower (for example between 10 and 50 m), a sufficient connection between one end of the at least one anchor pile and one end of the tower. In particular, such a connection can be established with little effort.
Auch kann der Bereich zwischen oberer und unterer Querschnittsfläche in dem Verbindungsbereich mit Boden ausgefüllt sein und/oder mit Zementgrout ausgefüllt sein und/oder in der vertikalen Ebene eine elastomerbasierte Schicht aufweisen, welche weitestgehend kreisförmig ist und in der Mitte ein Loch aufweist, welches kleiner oder gleich dem Durchmesser des kleineren der beiden anschließenden Elemente ist, und mit mindestens einem (entweder dem oberen oder dem unteren) Abschnitt kraftschlüssig verbunden ist. The area between the upper and lower cross-sectional area in the connecting area can also be filled with soil and / or filled with cement grout and / or have an elastomer-based layer in the vertical plane, which is largely circular and has a hole in the middle that is smaller or smaller is equal to the diameter of the smaller of the two adjoining elements, and is non-positively connected to at least one (either the upper or the lower) section.
Gemäß einer weiteren Ausführungsform kann der Turm) direkt mit mindestens einem Ankerpfahl form-, kraft- oder stoffschlüssig verbunden sein. Insbesondere wenn mindestens ein Ankerpfahl zumindest teilweise außerhalb des Umfangs des Verbindungsbereichs des Turmes liegt, kann der mindestens eine Ankerpfahl direkt mit dem Turm verbunden sein, z.B. durch Verschweißen oder Verschrauben ln der Verbindungszone kann/können der mindestens eine Ankerpfahl und/oder der Turm konstruktiv angepasst sein, um eine Verbindung zu ermöglichen, zum Beispiel durch das Entfernen von Material (z.B. in Form eines Schlitzes). Insbesondere kann hierdurch eine gegenseitige Durchdringung der genannten Körper vor der Verbindung ermöglicht werden und/oder das Anbringen von zusätzlichen Flächen erreicht werden, die z.B. eine Verschraubung ermöglichen. According to a further embodiment, the tower) can be connected directly to at least one anchor post in a form-fitting, non-positive or material-fitting manner. In particular, if at least one anchor post is at least partially outside the circumference of the connecting area of the tower, the at least one anchor post can be connected directly to the tower, e.g. by welding or screwing in the connecting zone, the at least one anchor post and / or the tower can be structurally adapted to enable a connection, for example by removing material (e.g. in the form of a slot). In particular, this enables the said bodies to penetrate each other before the connection and / or the attachment of additional surfaces which, for example, enable a screw connection.
Gemäß einer weiteren Ausführungsform der anmeldungsgemäßen Gründungsstruktur kann die Länge des Verbindungsbereichs zwischen 20 % und 50 % der Gesamtlänge des Ankerabschnitts liegen, bevorzugt zwischen 25 % und 40 %, insbesondere bevorzugt zwischen 25 % und 35 % (in einem Installationszustand). Insbesondere für den Fall, dass bei einem Ankerabschnitt zwischen 25 % und 35 % der Länge durch den Verbindungsbereich und zwischen 65 % und 75 % der Länge durch einen Verankerungsbereich (mit einer gegenüber dem Verbindungsbereich reduzierten Querschnittsfläche) gebildet ist, kann eine ausreichende strukturelle und mechanische Stabilität und gleichzeitig eine signifikante Materialreduktion (insbesondere Stahlreduktion) bei einer Gründungsstruktur erreicht werden. According to a further embodiment of the foundation structure according to the application, the length of the connection area can be between 20% and 50% of the total length of the anchor section, preferably between 25% and 40%, particularly preferably between 25% and 35% (in an installed state). In particular in the event that in an anchor section between 25% and 35% of the length is formed by the connection area and between 65% and 75% of the length is formed by an anchoring area (with a reduced cross-sectional area compared to the connection area), a sufficient structural and mechanical stability and at the same time a significant material reduction (especially steel reduction) can be achieved in a foundation structure.
Ferner kann, gemäß einer weiteren Ausführungsform der anmeldungsgemäßen Gründungsstruktur, die Querschnittsfläche des Verankerungsbereichs zwischen 90 % und 50 % der Querschnittsfläche des Verbindungsbereichs liegen, bevorzugt zwischen 85 % und 60 %, insbesondere bevorzugt zwischen 80 % und 65 %. Eine deutliche Materialersparnis kann erzielt werden. Furthermore, according to a further embodiment of the foundation structure according to the application, the cross-sectional area of the anchoring area can be between 90% and 50% of the cross-sectional area of the connection area, preferably between 85% and 60%, particularly preferably between 80% and 65%. A significant saving in material can be achieved.
Ein weiterer Aspekt der Anmeldung ist ein Verfahren zum Herstellen einer Gründungsstruktur, insbesondere einer zuvor beschriebenen Gründungsstruktur. Das Verfahren umfasst: Another aspect of the application is a method for producing a foundation structure, in particular a foundation structure described above. The procedure includes:
Einbringen mindestens eines Ankerpfahls in den Boden (insbesondere Gewässerboden), und anschließendes Einbringen eines Turms in den Boden (insbesondere Gewässerboden), derart, dass ein Verbindungsbereich gebildet wird, in den ein Ende des mindestens einen Ankerpfahls eingreift. Insertion of at least one anchor pile into the ground (in particular body of water), and subsequent insertion of a tower into the ground (in particular body of water) in such a way that a connection area is formed into which one end of the at least one anchor pile engages.
Das anmeldungsgemäße Verfahren wird insbesondere an dem Installationsort der Onshore- oder Offshore-Vorrichtung durchgeführt. Mindestens ein Ankerpfahl mit einer horizontalen Querschnittsfläche kleiner als die Querschnittsfläche kann zunächst in den (Gewässer-) Boden (mit einer bestimmten Einbindetiefe) eingebracht werden. Wenn eine Gruppe von Ankerpfählen eingebracht wird, können insbesondere zunächst sämtliche Ankerpfähle der Gruppe in den (Gewässer-)Boden (jeweils mit bestimmten Mindesteinbindetiefen) eingebracht werden. The method according to the application is carried out in particular at the installation site of the onshore or offshore device. At least one anchor post with a horizontal cross-sectional area smaller than the cross-sectional area can first be introduced into the (water) soil (with a certain embedment depth). If a group of anchor piles is introduced, all anchor piles of the group can in particular first be introduced into the (water) soil (each with certain minimum embedment depths).
Die Einbringung des mindestens einen Ankerpfahls in den (Gewässer-) Boden kann durch Abteufen erfolgen. The at least one anchor pile can be introduced into the (water) soil by sinking.
Nach der Installation des mindestens einen Ankerpfahls kann der Turm in den (Gewässer-)Boden eingebracht werden, um insbesondere den Verbindungsbereich der Gründungstruktur zu bilden. Insbesondere kann das (untere) Ende des Turms über das (obere) Ende des mindestens einen Ankerpfahls (bei einer Gruppe über sämtliche oberen Enden der Ankerpfähle) gestülpt werden. Vorzugsweise wird der Turm derart über das mindestens eine Ende des mindestens einen Ankerpfahls gestülpt, dass der mindestens eine Ankerpfahl mit einer vorgegebenen Länge (z.B. zwischen 5 und 50 m) in den Turm hineinragt. After the installation of the at least one anchor pile, the tower can be introduced into the (water) soil, in particular around the connecting area of the foundation structure. In particular, the (lower) end of the tower can be slipped over the (upper) end of the at least one anchor post (in the case of a group over all upper ends of the anchor posts). The tower is preferably slipped over the at least one end of the at least one anchor post in such a way that the at least one anchor post protrudes into the tower with a predetermined length (for example between 5 and 50 m).
Gemäß einer bevorzugten Ausführungsform des anmeldungsgemäßen Verfahrens kann nach dem Einbringen des Turms eine formschlüssige (vorzugsweise kraftschlüssige, insbesondere bevorzugt stoffschlüssige) Verbindung zwischen einem Turm und einem Ankerpfahl, insbesondere einer Innenwand des Turms und einer Außenwand des mindestens einen Ankerpfahls, hergestellt werden, insbesondere durch zumindest teilweises Vergrouten des Zwischenbereichs zwischen der Innenwand des Turms und der Außenwand des mindestens einen Ankerpfahls (wie zuvor beschrieben wurde). According to a preferred embodiment of the method according to the application, after the tower has been introduced, a positive (preferably non-positive, particularly preferably material) connection between a tower and an anchor post, in particular an inner wall of the tower and an outer wall of the at least one anchor post, can be established, in particular by at least Partial potting of the intermediate area between the inner wall of the tower and the outer wall of the at least one anchor pile (as described above).
Gemäß einer weiteren besonders bevorzugten Ausführungsform kann das Verfahren ferner umfassen: According to a further particularly preferred embodiment, the method can further comprise:
Bereitstellen einer Schablone mit mindestens einer Öffnung für mindestens einen einzubringenden Ankerpfahl, Providing a template with at least one opening for at least one anchor pile to be introduced,
Positionieren der Schablone auf einer Bodenoberfläche, insbesondere einer Gewässerbodenoberfläche, und Positioning the template on a soil surface, in particular a body of water, and
Einbringen des mindestens einen Ankerpfahls in den Boden durch die mindestens eine Öffnung. Introducing the at least one anchor post into the ground through the at least one opening.
Insbesondere kann die Schablone, beispielsweise ein plattenförmiges Element oder ein Rohrsegment, zwei oder mehr Öffnungen für eine entsprechende Anzahl von einzubringenden Ankerpfählen aufweisen. Eine Öffnung kann im Wesentlichen (vorzugsweise geringfügig größer) zu der Querschnittsfläche eines Ankerpfahls korrespondieren. Insbesondere bei der Verwendung von mehreren Ankerpfählen, die während der Installation noch nicht fest mit dem oberen Abschnitt der Gründungsstruktur verbunden sind, kann eine anmeldungsgemäße Schablone verwendet werden, die insbesondere die Maßhaltigkeit und eine exakte Positionierung der Ankerpfähle an dem Installationsort gewährleistet. In particular, the template, for example a plate-shaped element or a pipe segment, can have two or more openings for a corresponding number of anchor piles to be introduced. An opening can essentially (preferably slightly larger) correspond to the cross-sectional area of an anchor pile. Especially when using several anchor piles that are not yet firmly attached to the upper section of the Foundation structure are connected, a template according to the application can be used, which in particular ensures the dimensional accuracy and exact positioning of the anchor piles at the installation site.
Eine Schablone kann zum Beispiel aus einem Rohrsegment gebildet sein, dass die selben Maße hat wie der obere Abschnitt der Gründungsstruktur (oder etwas kleiner), also wie der Verbindungsabschnitt. Durch Hilfseinrichtungen kann die Schablone stabil und lotrecht auf dem Gewässerboden platziert werden. Die Ankerpfähle können durch die Schablone hindurch in den Gewässerboden eingebracht werden. Anschließend kann die Schablone nach oben weggehoben werden. ln einer weiteren Ausführungsform kann zunächst eine weitestgehend als Ringscheibe ausgebildete, z.B. aus einem Elastomer hergestellte, Abdichtung an dem Verankerungsabschnitt, z.B. durch Schrauben, Kleben oder Klemmen, angebracht werden. Nach dem der Verankerungsabschnitt in den Boden eingebracht wurde, kann der obere Turm so in den Verankerungsabschnitt eingesetzt, bzw. über diesen drüber gesetzt werden, dass die angebrachte Abdichtung ein Ausspülen des zwischen Verankerungsabschnitt und Turmabschnitt befindlichen Boden zumindest weitestgehend verhindert. A template can, for example, be formed from a pipe segment that has the same dimensions as the upper section of the foundation structure (or slightly smaller), i.e. as the connecting section. The template can be placed stably and vertically on the bottom of the water by means of auxiliary equipment. The anchor piles can be inserted through the template into the bottom of the water. The template can then be lifted upwards. In a further embodiment, a seal which is largely designed as an annular disk, for example made of an elastomer, can be attached to the anchoring section, for example by screwing, gluing or clamping. After the anchoring section has been introduced into the ground, the upper tower can be inserted into the anchoring section or placed over it in such a way that the attached seal at least largely prevents the ground between the anchoring section and the tower section from being flushed out.
Ein noch weiterer Aspekt der Anmeldung ist ein Verfahren zum Herstellen einer Gründungsstruktur, insbesondere einer zuvor beschriebenen Gründungsstruktur. Das Verfahren umfasst: Yet another aspect of the application is a method for producing a foundation structure, in particular a foundation structure described above. The procedure includes:
Bereitstellen mindestens eines Ankerpfahls, Provision of at least one anchor pile,
Bereitstellen mindestens eines Turms, und Deploy at least one tower, and
Herstellen mindestens einer mechanischen Verbindung zwischen dem Turm und dem Ankerpfahls, insbesondere zwischen einer Innenwand des Turms und einer Außenwand des Ankerpfahls.. Establishing at least one mechanical connection between the tower and the anchor pile, in particular between an inner wall of the tower and an outer wall of the anchor pile ..
Das Verfahren kann insbesondere entfernt von dem Installationsort der Offshore- Vorrichtung bzw. der Gründungstruktur für die Offshore-Vorrichtung durchgeführt werden, beispielsweise in oder bei einem Hafen. Insbesondere kann ein (unteres) Ende des Turms über ein Ende des Ankerpfahls (bei einer Gruppe über sämtliche oberen Enden der Ankerpfähle) gestülpt werden. Dann kann eine kraftschlüssige Verbindung, vorzugsweise eine stoffschlüssige Verbindung, zwischen dem Turm und dem mindestens einen Ankerpfahl hergestellt werden. Vorzugsweise kann entsprechend den vorherigen Ausführungen mindestens ein Verbindungsblech zwischen der Innenwand des Turms und einer Außenwand mindestens eines Ankerpfahls befestigt, insbesondere angeschweißt werden. Die (Gesamt- ) Querschnittsfläche des Ankerpfahls bzw. der Gruppe von Ankerpfählen kann kleiner sein als die Querschnittsfläche des Turms, der über den mindestens einen Ankerpfahl gestülpt wird. The method can in particular be carried out remotely from the installation location of the offshore device or the foundation structure for the offshore device for example in or near a port. In particular, a (lower) end of the tower can be slipped over one end of the anchor post (in the case of a group over all upper ends of the anchor posts). A non-positive connection, preferably a material connection, can then be established between the tower and the at least one anchor post. According to the previous statements, at least one connecting plate can preferably be fastened, in particular welded, between the inner wall of the tower and an outer wall of at least one anchor post. The (total) cross-sectional area of the anchor pile or the group of anchor piles can be smaller than the cross-sectional area of the tower that is slipped over the at least one anchor pile.
Die Merkmale der Gründungsstrukturen und Verfahren zum Herstellen einer Gründungsstruktur sind frei miteinander kombinierbar. Insbesondere können Merkmale der Beschreibung und/oder der abhängigen Ansprüche, auch unter vollständiger oder teilweiser Umgehung von Merkmalen der unabhängigen Ansprüche, in Alleinstellung oder frei miteinander kombiniert, eigenständig erfinderisch sein. The features of the foundation structures and methods for producing a foundation structure can be freely combined with one another. In particular, features of the description and / or the dependent claims can be independently inventive, even with complete or partial circumvention of features of the independent claims, alone or freely combined with one another.
Es gibt nun eine Vielzahl von Möglichkeiten, die anmeldungsgemäße Gründungstruktur und die anmeldungsgemäßen Verfahren auszugestalten und weiterzuentwickeln. Hierzu sei einerseits verwiesen auf die den unabhängigen Ansprüchen nachgeordneten Ansprüche, andererseits auf die Beschreibung von Ausführungsbeispielen in Verbindung mit der Zeichnung ln der Zeichnung zeigt: There are now a multitude of possibilities for designing and further developing the foundation structure and the processes according to the application. For this purpose, reference is made, on the one hand, to the claims subordinate to the independent claims, and, on the other hand, to the description of exemplary embodiments in conjunction with the drawing.
Fig. 1 eine schematische Ansicht eines Ausführungsbeispiels einerFig. 1 is a schematic view of an embodiment of a
Gründungstruktur gemäß der vorliegenden Anmeldung, Foundation structure according to the present application,
Fig. 2 eine schematische Ansicht eines weiteren Ausführungsbeispiels einerFig. 2 is a schematic view of a further embodiment of a
Gründungstruktur gemäß der vorliegenden Anmeldung, Fig. 3a eine schematische Teilansicht eines weiteren Ausführungsbeispiels einer Gründungstruktur gemäß der vorliegenden Anmeldung, Foundation structure according to the present application, 3a shows a schematic partial view of a further exemplary embodiment of a foundation structure according to the present application,
Fig. 3b eine schematische Teilansicht eines weiteren Ausführungsbeispiels einer Gründungstruktur gemäß der vorliegenden Anmeldung, 3b shows a schematic partial view of a further exemplary embodiment of a foundation structure according to the present application,
Fig. 3c eine schematische Teilansicht eines weiteren Ausführungsbeispiels einer Gründungstruktur gemäß der vorliegenden Anmeldung, 3c shows a schematic partial view of a further exemplary embodiment of a foundation structure according to the present application,
Fig. 4 ein Diagramm eines Ausführungsbeispiels eines Verfahrens gemäß der vorliegenden Anmeldung, 4 shows a diagram of an exemplary embodiment of a method according to the present application,
Fig. 5 ein Diagramm eines weiteren Ausführungsbeispiels eines Verfahrens gemäß der vorliegenden Anmeldung, 5 shows a diagram of a further exemplary embodiment of a method according to the present application,
Fig. 6 eine schematische Draufsicht eines weiteren Ausführungsbeispiels einer Gründungstruktur gemäß der vorliegenden Anmeldung, und 6 shows a schematic plan view of a further exemplary embodiment of a foundation structure according to the present application, and
Fig. 7 eine schematische Draufsicht eines Ausführungsbeispiel einerFig. 7 is a schematic plan view of an embodiment of a
Schablone, die bei einem Verfahren gemäß der vorliegenden Anmeldung verwendet werden kann. Template that can be used in a method according to the present application.
Nachfolgend werden für gleiche Elemente gleiche Bezugszeichen verwendet. The same reference symbols are used below for the same elements.
Die Figur 1 zeigt eine schematische Ansicht eines Ausführungsbeispiels einerFIG. 1 shows a schematic view of an exemplary embodiment of a
Gründungstruktur 100 gemäß der vorliegenden Anmeldung für eine Offshore-Foundation structure 100 according to the present application for an offshore
Vorrichtung. Die nachfolgenden Ausführungen können auf Onshore-Vorrichtungen übertragen werden. Contraption. The following explanations can be transferred to onshore devices.
Beispielsweise kann die Offshore-Vorrichtung eine Offshore-Windkraftanlage sein.For example, the offshore device can be an offshore wind turbine.
Eine Offshore-Windkraftanlage kann einen Generator aufweisen, der die kinetische Energie des Winds in elektrische Energie wandelt. Der Generator kann insbesondere in einer (nicht dargestellten) Gondel angeordnet sein, die von dem oberen Ende des Turms 110 getragen wird. Insbesondere kann die Offshore-Vorrichtung durch eine Offshore-Einrichtung, vorliegend beispielhaft die Gondel, und die Gründungstruktur 100 gebildet sein. An offshore wind turbine can have a generator that generates the kinetic Converts wind energy into electrical energy. The generator can in particular be arranged in a gondola (not shown) which is carried by the upper end of the tower 110. In particular, the offshore device can be formed by an offshore device, in the present example the nacelle, and the foundation structure 100.
Vorliegend ist die Gründungstruktur 100 (lediglich beispielhaft ist ein Monopile dargestellt) in einem Installationszustand dargestellt. Insbesondere ist die Gründungstruktur 100 in einem Gewässerboden 114, insbesondere einem Meeresboden 114, befestigt, wobei der Turm 110 vertikal nach oben (also in positive x-Richtung) ragt und teilweise oberhalb der Gewässeroberfläche 116, insbesondere der Meeresoberfläche 116, angeordnet ist. In the present case, the foundation structure 100 (a monopile is shown only by way of example) is shown in an installation state. In particular, the foundation structure 100 is fastened in a water floor 114, in particular a sea floor 114, the tower 110 protruding vertically upwards (i.e. in the positive x-direction) and being partially arranged above the water surface 116, in particular the sea surface 116.
Die Gründungsstruktur 100 kann zwei Abschnitte 102, 104 aufweisen, nämlich einen Turmabschnitt 102 und einen Ankerab schnitt 104. Der Turmanschnitt 102 ist insbesondere der Abschnitt der Gründungsstruktur 100, der sich oberhalb des Gewässerbodens 114 erstreckt, beispielsweise bis zur Gondel. Bei anderen Varianten der Anmeldung kann sich der Turmabschnitt auch nur bis zur Gewässeroberfläche erstrecken. The foundation structure 100 can have two sections 102, 104, namely a tower section 102 and an anchor section 104. The tower section 102 is in particular the section of the foundation structure 100 that extends above the water floor 114, for example up to the gondola. In the case of other variants of the registration, the tower section can only extend as far as the surface of the water.
Die Querschnittsfläche und der Durchmesser des Turmabschnitts 102 können vorzugweise von der Wasseroberfläche 116 bis zur Gewässerbodenoberfläche konisch aufgeweitet sein. The cross-sectional area and the diameter of the tower section 102 can preferably be conically widened from the water surface 116 to the water floor surface.
Der Ankerabschnitt 104 erstreckt sich von der Gewässerbodenoberfläche in vertikaler Richtung (negative x-Richtung) nach unten bzw. in die Tiefe. Der Ankerabschnitt 104 dient der Befestigung der Gründungstruktur 100 in dem Gewässerboden 114, insbesondere zur Verankerung der Gründungstruktur 100 in dem Gewässerboden 114. Der Ankerabschnitt 104 umfasst vorliegend einen Verbindungsbereich 106 und einen Verankerungsbereich 108. Der Verbindungsbereich 106 schließt sich unmittelbar an den Turmabschnitt 102 an. Der Verankerungsbereich 108 schließt sich unmittelbar an den Verbindungsbereich 106 an. The anchor section 104 extends from the surface of the body of water in the vertical direction (negative x-direction) downwards or in depth. The anchor section 104 is used to fasten the foundation structure 100 in the water floor 114, in particular for anchoring the foundation structure 100 in the water floor 114. In the present case, the anchor section 104 comprises a connection area 106 and an anchoring area 108. The connection area 106 directly adjoins the tower section 102. The anchoring area 108 directly adjoins the connecting area 106.
Wie zu erkennen ist, weist der Verbindungsbereich 106 eine (horizontal, also in y Richtung, verlaufende) Querschnittsfläche (die durch einen Pfeil mit dem Bezugszeichen 118 angedeutet ist) auf, die über dem gesamten Verbindungsbereich 106 (in vertikaler Richtung gesehen) konstant bleibt. Insbesondere wird der Turmdurchmesser 128 (ca.) ab der Gewässerbodenoberfläche bis zum unteren Ende des Verbindungsbereichs 106 konstant gehalten. As can be seen, the connection area 106 has a cross-sectional area (which is indicated by an arrow with the reference numeral 118) (running horizontally, i.e. in the y direction), which remains constant over the entire connection area 106 (viewed in the vertical direction). In particular, the tower diameter 128 (approx.) Is kept constant from the surface of the water floor to the lower end of the connecting area 106.
Im vorliegenden Ausführungsbeispiel weist der Verankerungsbereich 108 eine Querschnittsfläche (die durch einen Pfeil mit dem Bezugszeichen 120 angedeutet ist) auf, die über dem gesamten Verankerungsbereich 108 (in vertikaler Richtung gesehen) konstant bleibt. In the present exemplary embodiment, the anchoring area 108 has a cross-sectional area (which is indicated by an arrow with the reference numeral 120) which remains constant over the entire anchoring area 108 (viewed in the vertical direction).
Wie zu erkennen ist, ist die Querschnittsfläche 120 kleiner als die Querschnittsfläche 118. Insbesondere kann die Querschnittsfläche 120 des Verankerungsbereichs 108 zwischen 90 % und 50 % der Querschnittsfläche 118 des Verbindungsbereichs 106 liegen, bevorzugt zwischen 85 % und 60 %, insbesondere bevorzugt zwischen 80 % und 65 %. As can be seen, the cross-sectional area 120 is smaller than the cross-sectional area 118. In particular, the cross-sectional area 120 of the anchoring area 108 can be between 90% and 50% of the cross-sectional area 118 of the connecting area 106, preferably between 85% and 60%, particularly preferably between 80%. and 65%.
Der Verankerungsbereich 108 ist vorliegend durch einen Ankerpfahl 112 gebildet. Der Ankerpfahl 112 kann (wie der Turm 110) insbesondere ein Hohlpfahl sein, dessen umlaufende Wand vorzugsweise aus Metall gebildet ist. Der Turm 110 und der Ankerpfahl 112 weisen insbesondere einen kreisförmigen Querschnitt 118, 120 auf. In the present case, the anchoring area 108 is formed by an anchor post 112. The anchor pile 112 can (like the tower 110) in particular be a hollow pile, the circumferential wall of which is preferably formed from metal. The tower 110 and the anchor post 112 have in particular a circular cross section 118, 120.
Der Durchmesser 126 des Ankerpfahls 112 wird ab dem Ende des Verbindungsbereichs 106 bis zum Ende des Ankerpfahls 112 konstant gehalten. Der Durchmesser 126 des Ankerpfahls 112 ist vorliegend kleiner als der Durchmesser 128 des Turms 110 im Bereich des Verbindungsbereichs 106. The diameter 126 of the anchor post 112 is kept constant from the end of the connecting area 106 to the end of the anchor post 112. The In the present case, the diameter 126 of the anchor pile 112 is smaller than the diameter 128 of the tower 110 in the area of the connecting region 106.
Der Verbindungsbereich 106 weist ferner eine Länge 124 (in vertikaler Richtung) auf, die zwischen 25 % und 50 % der Gesamtlänge 122 des Ankerabschnitts 108 liegt, bevorzugt zwischen 25 % und 40 %, insbesondere bevorzugt zwischen 30 % und 35 %. Insbesondere kann die Länge des Verbindungsbereichs 106 ca. 1/3 des Ankerabschnitts 104 und die Länge des Verankerungsbereichs 108 ca. 2/3 des Ankerabschnitts 104 betragen The connecting region 106 also has a length 124 (in the vertical direction) which is between 25% and 50% of the total length 122 of the anchor section 108, preferably between 25% and 40%, particularly preferably between 30% and 35%. In particular, the length of the connecting region 106 can be approximately 1/3 of the anchor section 104 and the length of the anchoring region 108 can be approximately 2/3 of the anchor section 104
Die Figur 2 zeigt eine schematische Ansicht eines weiteren Ausführungsbeispiels einer Gründungstruktur 200 gemäß der vorliegenden Anmeldung für eine Offshore- Vorrichtung. Zur Vermeidung von Wiederholungen werden nachfolgend im Wesentlichen nur die Unterschiede zu dem Ausführungsbeispiel nach Figur 1 beschrieben. Für die anderen Komponenten der Gründungstruktur 200 wird auf die obigen Ausführungen verwiesen. FIG. 2 shows a schematic view of a further exemplary embodiment of a foundation structure 200 according to the present application for an offshore device. To avoid repetition, essentially only the differences from the exemplary embodiment according to FIG. 1 are described below. For the other components of the foundation structure 200, reference is made to the statements above.
Der Verankerungsbereich 208 des Ankerabschnitts 204 ist vorliegend durch eine Mehrzahl von Ankerpfählen 212.1 bis 212.3 bzw. durch eine Gruppe von Ankerpfählen 212.1 bis 212.3. Beispielhaft sind vorliegend drei Ankerpfähle 212.1 bis 212.3 dargestellt. Es versteht sich, dass auch eine andere Anzahl von Ankerpfählen vorgesehen sein kann (z.B. fünf). Vorzugsweise können die Ankerpfähle in Form eines Dreiecks nebeneinander angeordnet sein (nicht dargestellt). The anchoring area 208 of the anchor section 204 is present in the form of a plurality of anchor piles 212.1 to 212.3 or a group of anchor piles 212.1 to 212.3. As an example, three anchor piles 212.1 to 212.3 are shown here. It goes without saying that a different number of anchor piles can also be provided (e.g. five). The anchor piles can preferably be arranged next to one another in the form of a triangle (not shown).
Die Ankerpfähle 212.1 bis 212.3 sind benachbart zueinander angeordnet und verlaufen im Wesentlichen parallel zueinander in vertikaler Richtung. Insbesondere sind die Ankerpfähle 212.1 bis 212.3 eng aneinander angeordnet und kontaktieren sich. Beispielsweise kann ein Ankerpfahl zumindest zwei andere Ankerpfähle kontaktieren. Jeder Ankerpfahl 212.1 bis 212.3 weist eine Querschnittsfläche 230 (wiederum angedeutet durch einen Pfeil) auf. Die (maximale) (horizontal verlaufende) Gesamtquerschnittsfläche des Ankerabschnitts 208, also die Summe der einzelnen Querschnittsflächen 230 sämtlicher Ankerpfähle 212.1 bis 212.3, ist kleiner als die Querschnittsfläche218 des Verbindungsbereichs 206. The anchor piles 212.1 to 212.3 are arranged adjacent to one another and run essentially parallel to one another in the vertical direction. In particular, the anchor piles 212.1 to 212.3 are arranged close to one another and contact one another. For example, an anchor post can contact at least two other anchor posts. Each anchor post 212.1 to 212.3 has a cross-sectional area 230 (again indicated by an arrow). The (maximum) (horizontally running) total cross-sectional area of the anchor section 208, that is to say the sum of the individual cross-sectional areas 230 of all anchor piles 212.1 to 212.3, is smaller than the cross-sectional area 218 of the connecting region 206.
In einer (nicht dargestellten) Ausführungsform können sämtliche Ankerpfähle einer Gruppe von Ankerpfählen die gleiche Länge aufweisen. In diesem Fall bleibt die Gesamtquerschnittsfläche des Verankerungsbereichs über dem gesamten Verankerungsbereichs in vertikaler Richtung gesehen konstant. In one embodiment (not shown), all anchor piles of a group of anchor piles can have the same length. In this case, the total cross-sectional area of the anchoring area remains constant over the entire anchoring area, viewed in the vertical direction.
Vorliegend weist mindestens ein erster Ankerpfahl 212.1 eine erste Länge 234 auf und mindestens ein zweiter Ankerpfahl 212.2 eine zweite Länge 236 auf, wobei die erste Länge 234 größer ist als die zweite Länge 236. Insbesondere weist vorliegend ein dritter Ankerpfahl 212.3 eine dritte Länge 232 auf, wobei die dritte Länge 232 kleiner ist als die zweite Länge 236. In the present case, at least one first anchor post 212.1 has a first length 234 and at least one second anchor post 212.2 has a second length 236, the first length 234 being greater than the second length 236. In particular, a third anchor post 212.3 has a third length 232, wherein the third length 232 is smaller than the second length 236.
Durch das Vorsehen von mindestens zwei Ankerpfählen 212.1 bis 212.3 mit einer unterschiedlichen Länge, ausgehend von dem (unteren Ende des) Verbindungsbereichs 206, kann eine stufenweise Reduktion der Gesamtquerschnittsfläche des Verankerungsbereichs 208 in vertikaler Richtung (in negative X-Richtung gesehen) bereitgestellt werden. By providing at least two anchor piles 212.1 to 212.3 with a different length, starting from the (lower end of) connecting area 206, a gradual reduction of the total cross-sectional area of anchoring area 208 in the vertical direction (viewed in the negative X-direction) can be provided.
Vorliegend weist der Verankerungsbereich 208 einen ersten Subbereich 208.1 auf, dessen Gesamtquerschnittsfläche über die gesamte Länge 232 konstant bleibt und durch die einzelnen Querschnittsfläche 230 sämtlicher Ankerpfähle 212.1 bis 212.3 gebildet wird. In the present case, the anchoring area 208 has a first sub-area 208.1, the total cross-sectional area of which remains constant over the entire length 232 and is formed by the individual cross-sectional areas 230 of all anchor piles 212.1 to 212.3.
Ein zweiter Subbereich 208.2, der sich unmittelbar an den ersten Subbereich 208.1 anschließt, weist eine Gesamtquerschnittsfläche auf, die kleiner ist als die Gesamtquerschnittsfläche des ersten Subbereichs 208.1. Die Gesamtquerschnittsfläche des zweiten Subbereichs 208 bleibt über die gesamte Länge des zweiten Subbereichs 208.2 (Länge des zweiten Subbereichs = Länge 236 - Länge 232) konstant und wird durch die einzelnen Querschnittsfläche 230 des ersten und zweiten Ankerpfahls 212.1, 212.2 gebildet. A second sub-area 208.2, which directly adjoins the first sub-area 208.1, has a total cross-sectional area that is smaller than the total cross-sectional area of the first sub-area 208.1. The The total cross-sectional area of the second sub-area 208 remains constant over the entire length of the second sub-area 208.2 (length of the second sub-area = length 236 - length 232) and is formed by the individual cross-sectional areas 230 of the first and second anchor piles 212.1, 212.2.
Ein dritter Subbereich 208.3, der sich unmittelbar an den zweiten Subbereich 208.2 anschließt, weist eine Gesamtquerschnittsfläche auf, die kleiner ist als die Gesamtquerschnittsfläche des zweiten Subbereichs 208.2. DieA third sub-area 208.3, which directly adjoins the second sub-area 208.2, has a total cross-sectional area that is smaller than the total cross-sectional area of the second sub-area 208.2. The
Gesamtquerschnittsfläche des dritten Subbereichs 208 bleibt über die gesamte Länge des dritten Subbereichs 208.3 (Länge des dritten Subbereichs = Länge 234 - Länge 236) konstant und wird durch die einzelne Querschnittsfläche 230 des ersten Ankerpfahls 212.1 gebildet. The total cross-sectional area of the third sub-area 208 remains constant over the entire length of the third sub-area 208.3 (length of the third sub-area = length 234 - length 236) and is formed by the individual cross-sectional area 230 of the first anchor post 212.1.
Neben einer noch weiteren Materialersparnis ist das beschriebene Ausführungsbeispiel aufgrund der Mehrzahl von Ankerpfählen 212.1 bis 212.3 weniger empfindlich gegenüber ggf. im Gewässerboden 214 vorhandenen Findlingen 211. Zudem wirken bei hinreichend steifen Bodenverhältnissen die Einzelpfähle als Pfahlgruppe mit einer größeren Gesamtsteifigkeit als die Summe der Einzelsteifigkeiten offenbaren würde. In addition to a further saving in material, the described embodiment is less sensitive to boulders 211 that may be present in the water floor 214 due to the plurality of anchor piles 212.1 to 212.3 .
Es sei angemerkt, dass in der Figur 2 die Ankerpfähle 212.1, 212.2 in einer anderen Ebene dargestellt sind, als der Ankerpfahl 212.3 (um insbesondere anzudeuten, dass nicht sämtliche Ankerpfähle in der gleichen Ebene angeordnet sind). It should be noted that in FIG. 2 the anchor piles 212.1, 212.2 are shown in a different plane than the anchor pile 212.3 (to indicate in particular that not all anchor piles are arranged in the same plane).
Die Figuren 3a bis 3c zeigen schematische Teilansichten von Ausführungsbeispielen von Gründungstrukturen 300 gemäß der vorliegenden Anmeldung ln den Figuren 3a bis 3c entspricht die X-Achse erneut der vertikalen Richtung und die Y-Achse einer horizontalen Richtung. Die Figuren 3a und 3b zeigen eineFIGS. 3a to 3c show schematic partial views of exemplary embodiments of foundation structures 300 according to the present application. In FIGS. 3a to 3c, the X-axis again corresponds to the vertical direction and the Y-axis to a horizontal direction. Figures 3a and 3b show one
Querschnittsseitenteilansicht und die Figur 3c eine Querschnittsdrauf-Teilansicht. Zur Vermeidung von Wiederholungen werden nachfolgend im Wesentlichen nur die Unterschiede zu den Ausführungsbeispielen nach Figur 1 und Figur 2 beschrieben. Für die anderen Komponenten der Gründungstruktur 300 wird auf die obigen Ausführungen verwiesen. Nachfolgend ist zu Gunsten einer besseren Übersicht in den Figuren 3a bis 3c nur ein einzelner Ankerpfahl 312 dargestellt. Es versteht sich, dass die nachfolgenden Ausführungen auch auf eine Gruppe von Ankerpfählen übertragen werden können. Cross-sectional side partial view and FIG. 3c shows a cross-sectional partial view from above. To avoid repetition, essentially only the differences from the exemplary embodiments according to FIG. 1 and FIG. 2 are described below. For the other components of the foundation structure 300, reference is made to the statements above. In the following, for the sake of a better overview, only a single anchor post 312 is shown in FIGS. 3a to 3c. It goes without saying that the following explanations can also be applied to a group of anchor piles.
Wie in Figur 3a dargestellt, ist in dem dargestellten Installationszustand der Gründungstruktur 300 der Turm 310 über den Ankerpfahl 312 gestülpt. Anders ausgedrückt ragt ein oberes Ende 360 des Ankerpfahls 312 in den Innerraum 350 (der im nicht installierten Zustand hohl ist) des Turms 310, insbesondere des unteren Endes des Turms 310. As shown in FIG. 3 a, in the installation state of the foundation structure 300 shown, the tower 310 is placed over the anchor post 312. In other words, an upper end 360 of the anchor pile 312 protrudes into the interior space 350 (which is hollow in the non-installed state) of the tower 310, in particular the lower end of the tower 310.
Ferner ist eine mechanische und/oder strukturelle Verbindung zwischen dem Turm 310 und dem Ankerpfahl 312 vorgesehen. Diese Verbindung ist in dem Ausführungsbeispiel nach Figur 3a durch das Gewässerbodenmaterial 348 des Gewässerbodens 314 gebildet. Insbesondere wird eine Verbindung zwischen der Innenwand 344 des Turms 310 und der Außenwand 342 des Ankerpfahls 312 dadurch dargestellt, dass der Zwischenraum 346 zwischen der Innenwand 344 des Turms 310 und der Außenwand 342 des Ankerpfahls 312 mit dem Gewässerbodenmaterial 348 des Gewässerbodens 314 gefüllt ist. Insbesondere bei hinreichend steifen Bodenverhältnissen kann eine ausreichende Stabilität und Verankerung hierdurch erreicht werden. Furthermore, a mechanical and / or structural connection between the tower 310 and the anchor post 312 is provided. In the exemplary embodiment according to FIG. 3 a, this connection is formed by the water floor material 348 of the water floor 314. In particular, a connection between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312 is represented by the fact that the space 346 between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312 is filled with the water bed material 348 of the water floor 314. Sufficient stability and anchoring can be achieved in this way, in particular in the case of sufficiently stiff ground conditions.
Die Figur 3b zeigt ein alternatives Ausführungsbeispiel ln dem Beispiel nach Figur 3b ist der Zwischenraum 346 zwischen der Innenwand 344 des Turms 310 und der Außenwand 342 des Ankerpfahls 312 mit einem hochfesten Beton 354 (z.B. durch Zement Soil Mixing) gefüllt. Anders ausgedrückt kann zwischen der Innenwand 344 des Turms 310 und der Außenwand 342 des Ankerpfahls 312 eine Grout-Verbindung hergestellt sein. Eine ausreichend sichere Verankerung kann bereitgestellt werden. Die Figur 3c zeigt ein weiteres Ausführungsbeispiel. Bei dem gezeigten Beispiel ist insbesondere eine Mehrzahl von Verbindungsblechen 356 zwischen der Innenwand 344 des Turms 310 und der Außenwand 342 des Ankerpfahls 312 befestigt. Die Länge eines Verbindungsblechs 356 in x-Richtung kann in etwa der Länge entsprechen, die der Ankerpfahl 312 in den Turm 310 hineinragt. FIG. 3b shows an alternative embodiment. In the example according to FIG. 3b, the space 346 between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312 is filled with a high-strength concrete 354 (e.g. by cement soil mixing). In other words, a grout connection can be established between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor pile 312. Sufficiently secure anchoring can be provided. FIG. 3c shows a further exemplary embodiment. In the example shown, in particular a plurality of connecting plates 356 are fastened between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor post 312. The length of a connecting plate 356 in the x direction can correspond approximately to the length that the anchor post 312 protrudes into the tower 310.
Die Breite eines Verbindungsblechs 356 kann insbesondere dem Abstand zwischen der Innenwand 344 des Turms 310 und der Außenwand 342 des Ankerpfahls 312 entsprechen. Vorzugsweise kann ein Verbindungsblech 356 angeschweißt sein. Besonders bevorzugt können die Verbindungsbleche 356 radial gleichmäßig beabstandet zueinander angeordnet sein. The width of a connecting plate 356 can in particular correspond to the distance between the inner wall 344 of the tower 310 and the outer wall 342 of the anchor post 312. A connecting plate 356 can preferably be welded on. Particularly preferably, the connecting plates 356 can be arranged radially evenly spaced from one another.
Der verbleibende Zwischenraum 346 ist vorliegend mit dem Gewässerbodenmaterial 348 des Gewässerbodens 314 gefüllt. Alternativ oder zusätzlich kann auch ein Vergrouten erfolgen. The remaining intermediate space 346 is in the present case filled with the water bed material 348 of the water floor 314. Alternatively or additionally, it can also be grounded.
Es versteht sich, dass bei anderen Varianten der Anmeldung ein Zwischenraum zwischen Innenwand des Turms und Außenwand des Ankerpfahls auch mit einem anderen Füllmaterial, wie etwa einem Elastomer, Polymer, Sand-Ton, Sand-Ton- Gemisch etc. zumindest teilweise gefüllt sein kann. It goes without saying that in other variants of the application, an intermediate space between the inner wall of the tower and the outer wall of the anchor pile can also be at least partially filled with another filler material, such as an elastomer, polymer, sand-clay, sand-clay mixture, etc.
Die Figur 4 zeigt ein Diagramm eines Verfahrens zum Herstellen einer Gründungsstruktur, insbesondere einer zuvor in Zusammenhang mit den Figuren 1 bis 3c beschriebenen Gründungsstruktur. ln einem ersten Schritt 401 erfolgt, insbesondere an einem Installationsort der Gründungsstruktur, ein Einbringen mindestens eines Ankerpfahls in den Gewässerboden (in eine vorgegebene Tiefe). Bei einer Gruppe von Ankerpfählen können in Schritt 401 sämtliche Ankerpfähle der Gruppe insbesondere sequentiell in den Gewässerboden eingebracht werden. Insbesondere für den Fall, dass bei einer Gruppe von Ankerpfählen ein Ankerpfahl bei der Einbringung auf einen Findling stößt, kann dieser (sofern eine bestimmte Mindesttiefe erreicht wurde und zumindest ein weiterer Ankerpfahl tiefer eingebracht werden kann) nicht tiefer eingebracht werden. Der mindestens eine weitere Ankerpfahl kann unmittelbar benachbart zu dem ersten Ankerpfahl und insbesondere in eine größere Tiefe eingebracht werden. FIG. 4 shows a diagram of a method for producing a foundation structure, in particular a foundation structure previously described in connection with FIGS. 1 to 3c. In a first step 401, in particular at an installation location of the foundation structure, at least one anchor pile is introduced into the bottom of the body of water (at a predetermined depth). In the case of a group of anchor piles, in step 401 all anchor piles of the group can in particular be introduced sequentially into the bottom of the water. In particular in the event that an anchor pile encounters a boulder in a group of anchor piles when it is being inserted, it cannot be driven deeper (provided a certain minimum depth has been reached and at least one further anchor pile can be inserted deeper). The at least one further anchor post can be introduced directly adjacent to the first anchor post and in particular at a greater depth.
In einem Schritt 402 kann ein anschließendes Einbringen eines Turms in den Gewässerboden erfolgen, derart, dass ein Verbindungsbereich gebildet wird, in den ein Ende des mindestens einen Ankerpfahls eingreift bzw. hineinragt. Insbesondere kann in Schritt 402 der Turm über den mindestens einen eingebrachten Ankerpfahl übergestülpt werden. Das Ende des Turms kann vorzugsweise in den Gewässerboden eingebracht werden, so dass sich der beschriebene Verbindungsbereich bildet. Hierbei ist eine Querschnittsfläche des Verankerungsbereichs kleiner als eine Querschnittsfläche des Verbindungsbereichs. In a step 402, a tower can then be introduced into the bottom of the water in such a way that a connection area is formed into which one end of the at least one anchor post engages or projects. In particular, in step 402 the tower can be slipped over the at least one introduced anchor post. The end of the tower can preferably be introduced into the bottom of the water, so that the connection area described is formed. Here, a cross-sectional area of the anchoring area is smaller than a cross-sectional area of the connection area.
Optional kann in Schritt 403 nach dem Einbringen des Turms eine Verbindung zwischen einer Innenwand des Turms und einer Außenwand des mindestens einen Ankerpfahls hergestellt werden. Insbesondere kann durch zumindest teilweises Vergrouten des Zwischenbereichs zwischen der Innenwand des Turms und der Außenwand des mindestens einen Ankerpfahls eine vorzugsweise zumindest kraftschlüssige Verbindung zwischen dem mindestens einen Ankerpfahl und dem Turm hergestellt werden. Optionally, in step 403, after the tower has been introduced, a connection can be established between an inner wall of the tower and an outer wall of the at least one anchor pile. In particular, a preferably at least non-positive connection between the at least one anchor post and the tower can be established by at least partially grouting the intermediate area between the inner wall of the tower and the outer wall of the at least one anchor post.
Die Figur 5 zeigt ein Diagramm eines Verfahrens zum Herstellen einer Gründungsstruktur, insbesondere einer zuvor in Zusammenhang mit den Figuren 1 bis 3c beschriebenen Gründungsstruktur. Das Verfahren gemäß der Figur 5 kann vorzugsweise entfernt von dem Installationsort der Gründungstruktur durchgeführt werden. In einem Schritt 501 kann ein Bereitstellen eines Ankerpfahls (oder einer Gruppe von Ankerpfählen) erfolgen. FIG. 5 shows a diagram of a method for producing a foundation structure, in particular a foundation structure previously described in connection with FIGS. 1 to 3c. The method according to FIG. 5 can preferably be carried out remotely from the installation site of the foundation structure. In a step 501, an anchor pile (or a group of anchor piles) can be provided.
In Schritt 502 kann ein Bereitstellen mindestens eines Turms erfolgen. In step 502, at least one tower can be provided.
In Schritt 503 erfolgt ein Herstellen mindestens einer mechanischen Verbindung zwischen einer Innenwand des Turms und einer Außenwand des Ankerpfahls. Insbesondere kann der Turm zumindest teilweise über den mindestens einen Ankerpfahl gestülpt werden und vorzugsweise mindestens ein Verbindungsblech stoffschlüssig zwischen der Innenwand des Turms und der Außenwand des Ankerpfahls befestigt werden. In step 503, at least one mechanical connection is established between an inner wall of the tower and an outer wall of the anchor pile. In particular, the tower can be at least partially slipped over the at least one anchor post and preferably at least one connecting plate can be firmly bonded between the inner wall of the tower and the outer wall of the anchor post.
Optional kann anschließend die hergestellte Gründungsstruktur zu dem Installationsort transportiert und an dem Installationsort in den Gewässerboden eingebracht werden. Anschließend kann zusätzlich ein Vergrouten in dem verbleibenden Zwischenbereich zwischen der Innenwand des Turms und der Außenwand des Ankerpfahls erfolgen. Optionally, the established foundation structure can then be transported to the installation site and introduced into the bottom of the water at the installation site. Subsequently, the remaining intermediate area between the inner wall of the tower and the outer wall of the anchor pile can also be covered with soil.
Die Figur 6 zeigt eine schematische Draufsicht eines weiteren Ausführungsbeispiels einer Gründungstruktur 600 gemäß der vorliegenden Anmeldung. Zur Vermeidung von Wiederholungen werden nachfolgend im Wesentlichen nur die Unterschiede zu den vorherigen Ausführungsbeispielen beschrieben. Für die anderen Komponenten der Gründungstruktur 600 wird auf die obigen Ausführungen verwiesen. FIG. 6 shows a schematic top view of a further exemplary embodiment of a foundation structure 600 according to the present application. To avoid repetition, essentially only the differences from the previous exemplary embodiments are described below. For the other components of the foundation structure 600, reference is made to the statements above.
In dem dargestellten Beispiel sind drei Ankerpfähle 612.1 bis 612.3 vorgesehen. Wie aus der Draufsicht ersichtlich ist, sind die Ankerpfähle 612.1 bis 612.3 derart positioniert, dass sie über die Querschnittsfläche 618 des Verbindungsbereichs 606 hinausragen. Die Gesamtquerschnittsfläche der einzelnen Querschnittsflächen 620.1 bis 620.3 ist hierbei jedoch geringer als die Querschnittsfläche 618 des Verbindungsbereichs 606. Ferner wird durch die Figur 6 deutlich, wie insbesondere eine Querschnittsfläche 618, 620.1 bis 620.3 in der vorliegenden Anmeldung (grundsätzlich) definiert ist. Die Querschnittsfläche berechnet sich nach der Formel: A = Ti*d2/4, wobei d der Durchmesser 670 bzw. 672, wie dargestellt, zwischen den Außenkanten bzw. Außenwänden des jeweiligen Pfahls ist (und nicht zwischen den Innenkanten bzw. Innenwänden). In the example shown, three anchor piles 612.1 to 612.3 are provided. As can be seen from the top view, the anchor piles 612.1 to 612.3 are positioned in such a way that they protrude beyond the cross-sectional area 618 of the connection region 606. The total cross-sectional area of the individual cross-sectional areas 620.1 to 620.3 is here, however, smaller than the cross-sectional area 618 of the connection region 606. Furthermore, it is clear from FIG. 6 how, in particular, a cross-sectional area 618, 620.1 to 620.3 is (fundamentally) defined in the present application. The cross-sectional area is calculated according to the formula: A = Ti * d 2/4 , where d is the diameter 670 or 672, as shown, between the outer edges or outer walls of the respective pile (and not between the inner edges or inner walls).
Vorliegend kann der mindestens eine Ankerpfahl 612.1 bis 612.3 direkt mit dem Turm 610 verbunden sein, z.B. durch Verschweißen oder Verschrauben ln der Verbindungszone kann/können der mindestens eine Ankerpfahl und/oder der Turm konstruktiv angepasst sein, um eine Verbindung zu ermöglichen, zum Beispiel durch ein vorheriges Entfernen von Material (z.B. zum Bilden eines Schlitzes). Insbesondere kann hierdurch eine gegenseitige Durchdringung der genannten Körper 612.1 bis 612.3, 610 vor der Verbindung ermöglicht werden und/oder das Anbringen von zusätzlichen Flächen erreicht werden, die z.B. eine Verschraubung ermöglichen. Insbesondere kann eine Verbindung ohne Verbindungsbleche erfolgen, sondern vorzugsweise dadurch, dass ein Ankerpfahl 612.1 bis 612.3 so geschlitzt wird, dass der Verbindungsbereich in den Schlitz gesteckt und vorzugsweise verschweißt, verklebt, verschraubt etc. werden kann. In the present case, the at least one anchor pile 612.1 to 612.3 can be connected directly to the tower 610, for example by welding or screwing. In the connection zone, the at least one anchor pile and / or the tower can be structurally adapted to enable a connection, for example through a prior removal of material (e.g. to form a slot). In particular, this enables the said bodies 612.1 to 612.3, 610 to penetrate each other before the connection and / or the attachment of additional surfaces which, for example, enable a screw connection. In particular, a connection can be made without connecting plates, but preferably by slitting an anchor post 612.1 to 612.3 in such a way that the connection area can be inserted into the slot and preferably welded, glued, screwed, etc.
Die Figur 7 zeigt eine schematische Draufsicht eines Ausführungsbeispiels einer Schablone 780, die bei einem (zuvor beschriebenen) Verfahren gemäß der vorliegenden Anmeldung verwendet werden kann. Insbesondere kann das Verfahren nach Figur 4 zusätzliche folgende Schritte umfassen: FIG. 7 shows a schematic top view of an exemplary embodiment of a template 780 which can be used in a (previously described) method according to the present application. In particular, the method according to FIG. 4 can include the following additional steps:
Bereitstellen einer Schablone mit mindestens einer Öffnung für mindestens einen einzubringenden Ankerpfahl, Providing a template with at least one opening for at least one anchor pile to be introduced,
Positionieren der Schablone auf einer Bodenoberfläche, insbesondere einer Gewässerbodenoberfläche, und Positioning the template on a soil surface, in particular a body of water, and
Einbringen des mindestens einen Ankerpfahls in den Boden durch die mindestens eine Öffnung. Insbesondere kann die Schablone 780, vorzugsweise ein Rohrsegment 780, zwei oder mehr Öffnungen 782 (vorliegend beispielhaft drei Öffnungen 782) für eine entsprechende Anzahl von einzubringenden Ankerpfählen aufweisen. Eine Öffnung 782 kann im Wesentlichen (vorzugsweise geringfügig größer) zu der Querschnittsfläche eines Ankerpfahls korrespondieren. Insbesondere bei derIntroducing the at least one anchor post into the ground through the at least one opening. In particular, the template 780, preferably a pipe segment 780, can have two or more openings 782 (in the present example three openings 782) for a corresponding number of anchor piles to be introduced. An opening 782 may correspond substantially (preferably slightly larger) to the cross-sectional area of an anchor pile. Especially with the
Verwendung von mehreren Ankerpfählen, die während der Installation noch nicht fest mit dem oberen Abschnitt der Gründungsstruktur verbunden sind, kann eine anmeldungsgemäße Schablone verwendet werden, die insbesondere die Maßhaltigkeit und eine exakte Positionierung der Ankerpfähle an dem Installationsort gewährleistet. Using several anchor piles that are not yet firmly connected to the upper section of the foundation structure during installation, a template according to the application can be used, which in particular ensures dimensional accuracy and exact positioning of the anchor piles at the installation site.
Das Rohrsegment 780 kann insbesondere derart gebildet sein, dass es dieselben Maße aufweisen, wie der obere Abschnitt der Gründungsstruktur (insbesondere der beschriebene Verbindungsabschnitt, der vorzugsweise drüber gestülpt wird) (oder etwas kleiner als die Innenquerschnittsfläche des Verbindungsabschnitts). Durch (nicht gezeigte) Hilfseinrichtungen kann die Schablone 780 stabil und lotrecht auf dem Gewässerboden 714 platziert werden. Die Ankerpfähle können durch die Schablone hindurch in den Gewässerboden 714 eingebracht werden. Anschließend kann die Schablone 780 nach oben weggehoben werden. Optional kann vor einem Entfernen der Schablone ein Einbringen eines Turms in den Gewässerboden derart erfolgen, dass ein Verbindungsbereich gebildet wird, in den ein Ende des mindestens einen Ankerpfahls eingreift. The pipe segment 780 can in particular be formed in such a way that it has the same dimensions as the upper section of the foundation structure (in particular the connection section described, which is preferably placed over it) (or somewhat smaller than the inner cross-sectional area of the connection section). The template 780 can be placed stably and vertically on the body of water 714 by auxiliary devices (not shown). The anchor piles can be inserted through the template into the body of water 714. The template 780 can then be lifted upwards. Optionally, before removing the template, a tower can be introduced into the bottom of the water in such a way that a connection area is formed into which one end of the at least one anchor post engages.

Claims

P a t e n t a n s p r ü c h e P a t e n t a n s p r ü c h e
1. Gründungsstruktur (100, 200, 300, 600), umfassend: einen sich in einem Installationszustand der Gründungsstruktur (100, 200, 300, 600) oberhalb eines Bodens (114, 214, 314, 714) erstreckenden Turmabschnitt (102, 202, 302), einen sich an den Turmabschnitt (102, 202, 302) anschließenden und sich in dem Installationszustand in dem Boden (114, 214, 314, 714) erstreckenden Ankerabschnitt (104, 204), dadurch gekennzeichnet, dass der Ankerab schnitt (104, 204) einen Verbindungsbereich (106, 206, 306, 606) aufweist, der sich an den Turmabschnitt (102, 202, 302) anschließt, der Ankerab schnitt (104, 204) einen Verankerungsbereich (108, 208, 308) aufweist, der sich an den Verbindungsbereich (106, 206, 306, 606) anschließt, wobei eine Querschnittsfläche (120) des Verankerungsbereichs (108, 208, 308) kleiner ist als eine Querschnittsfläche (118, 218, 618) des Verbindungsbereichs (106, 206, 306, 606). 1. Foundation structure (100, 200, 300, 600) comprising: a tower section (102, 202) extending above a ground (114, 214, 314, 714) in an installed state of the foundation structure (100, 200, 300, 600), 302), an anchor section (104, 204) adjoining the tower section (102, 202, 302) and extending in the installed state in the ground (114, 214, 314, 714), characterized in that the anchor section (104 , 204) has a connecting area (106, 206, 306, 606) which adjoins the tower section (102, 202, 302), the anchor section (104, 204) has an anchoring area (108, 208, 308) which adjoins the connecting area (106, 206, 306, 606), a cross-sectional area (120) of the anchoring area (108, 208, 308) being smaller than a cross-sectional area (118, 218, 618) of the connecting area (106, 206, 306) , 606).
2. Gründungsstruktur (100, 200, 300, 600) nach Anspruch 1, dadurch gekennzeichnet, dass der Verankerungsbereich (108, 208, 308) durch einen Ankerpfahl (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) zumindest teilweise gebildet ist, der Turmabschnitt (102, 202, 302) und der Verbindungsbereich (106, 206, 306, 606) durch einen Turm (110, 210, 310, 610) zumindest teilweise gebildet ist, und eine Querschnittsfläche (120) des Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) kleiner ist als eine Querschnittsfläche (118, 218, 618) des Turms (110, 210, 310, 610) in dem Verbindungsbereich (106, 206, 306, 606). 2. Foundation structure (100, 200, 300, 600) according to claim 1, characterized in that the anchoring area (108, 208, 308) by an anchor post (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) at least is partially formed, the tower section (102, 202, 302) and the connecting area (106, 206, 306, 606) is at least partially formed by a tower (110, 210, 310, 610), and a cross-sectional area (120) of the anchor pile (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) is smaller than a cross-sectional area (118, 218, 618) of the tower (110, 210, 310, 610) in the connecting area (106, 206, 306, 606).
3. Gründungsstruktur (100, 200, 300, 600) nach Anspruch 1, dadurch gekennzeichnet, dass der Verankerungsbereich (108, 208, 308) durch eine Mehrzahl von parallel verlaufenden Ankerpfählen (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) gebildet ist, der Turmabschnitt (102, 202, 302) und der Verbindungsbereich (106, 206, 306, 606) durch einen Turm (110, 210, 310, 610) gebildet ist, und eine Gesamtquerschnittsfläche der Mehrzahl der Ankerpfähle (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) kleiner ist als eine Querschnittsfläche (118, 218, 618) des Turms (110, 210, 310, 610) in dem Verbindungsbereich (106, 206, 306, 606). 3. Foundation structure (100, 200, 300, 600) according to claim 1, characterized in that the anchoring area (108, 208, 308) is formed by a plurality of parallel anchor piles (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3 , 612.3), the tower section (102, 202, 302) and the connecting area (106, 206, 306, 606) is formed by a tower (110, 210, 310, 610), and a total cross-sectional area of the plurality of anchor piles ( 112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) is smaller than a cross-sectional area (118, 218, 618) of the tower (110, 210, 310, 610) in the connection area (106, 206, 306, 606 ).
4. Gründungsstruktur (100, 200, 300, 600) nach Anspruch 3, dadurch gekennzeichnet, dass mindestens ein erster Ankerpfahl (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) eine erste Länge (234) aufweist und mindestens ein zweiter Ankerpfahl (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) eine zweite Länge (236) aufweist, wobei die erste Länge (234) größer ist als die zweite Länge (236). 4. foundation structure (100, 200, 300, 600) according to claim 3, characterized in that at least one first anchor post (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) has a first length (234) and at least a second anchor post (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) has a second length (236), the first length (234) being greater than the second length (236).
5. Gründungsstruktur (100, 200, 300, 600) nach einem der Ansprüche 2 bis 4, dadurch gekennzeichnet, dass ein Ende (360) des mindestens einen Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) in den Turm (110, 210, 310, 610) zumindest teilweise eingreift. 5. Foundation structure (100, 200, 300, 600) according to one of claims 2 to 4, characterized in that one end (360) of the at least one anchor post (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) at least partially engages in the tower (110, 210, 310, 610).
6. Gründungsstruktur (100, 200, 300, 600) nach Anspruch 5, dadurch gekennzeichnet, dass zwischen einer Innenwand (344) des Turms (110, 210, 310, 610) und einer Außenwand (342) des mindestens einen Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) eine formschlüssige Verbindung hergestellt ist, insbesondere ein kraftschlüssige Verbindung, insbesondere bevorzugt eine stoffschlüssige Verbindung. 6. foundation structure (100, 200, 300, 600) according to claim 5, characterized in that between an inner wall (344) of the tower (110, 210, 310, 610) and an outer wall (342) of the at least one anchor pile (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) a positive connection is established, in particular a force-fit connection, particularly preferably a material connection.
7. Gründungsstruktur (100, 200, 300, 600) nach Anspruch 6, dadurch gekennzeichnet, dass die Verbindung eine Grout-Verbindung ist, und/oder die Verbindung durch mindestens ein Verbindungsblech (356) hergestellt ist, wobei das mindestens eine Verbindungsblech (356) an der Innenwand (344) des Turms (110, 210, 310, 610) und der Außenwand (342) des mindestens einen Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3) befestigt ist, und/oder die Verbindung durch ein Bodenmaterial (348) gebildet ist. 7. foundation structure (100, 200, 300, 600) according to claim 6, characterized in that the connection is a grout connection, and / or the connection is made by at least one connecting plate (356), wherein the at least one connecting plate (356 ) is attached to the inner wall (344) of the tower (110, 210, 310, 610) and the outer wall (342) of the at least one anchor post (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3), and / or the connection is formed by a floor material (348).
8. Gründungsstruktur (100, 200, 300, 600) nach einem der vorherigen Ansprüche, dadurch gekennzeichnet, dass die Länge (224) des Verbindungsbereichs (106, 206, 306, 606) zwischen 20 % und 50 % der Gesamtlänge (222) des Ankerabschnitts (104, 204) liegt, bevorzugt zwischen 25 % und 40 %, insbesondere bevorzugt zwischen 25 % und 35 %. 8. foundation structure (100, 200, 300, 600) according to any one of the preceding claims, characterized in that the length (224) of the connecting area (106, 206, 306, 606) between 20% and 50% of the total length (222) of the Anchor section (104, 204) is preferably between 25% and 40%, particularly preferably between 25% and 35%.
9. Gründungsstruktur (100, 200, 300, 600) nach einem der vorherigen Ansprüche, dadurch gekennzeichnet, dass die Querschnittsfläche (120) des Verankerungsbereichs (108, 208, 308) zwischen 90 % und 50 % der Querschnittsfläche (118, 218, 618) des Verbindungsbereichs (106, 206, 306, 606) liegt, bevorzugt zwischen 85 % und 60 %, insbesondere bevorzugt zwischen 80 % und 65 %. 9. Foundation structure (100, 200, 300, 600) according to one of the preceding claims, characterized in that the cross-sectional area (120) of the anchoring area (108, 208, 308) between 90% and 50% of the cross-sectional area (118, 218, 618 ) of the connection area (106, 206, 306, 606) is preferably between 85% and 60%, particularly preferably between 80% and 65%.
10. Verfahren zum Herstellen einer Gründungsstruktur (100, 200, 300, 600), insbesondere einer Gründungsstruktur (100, 200, 300, 600) nach einem der vorherigen Ansprüche, umfassend: Einbringen mindestens eines Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1,10. A method for producing a foundation structure (100, 200, 300, 600), in particular a foundation structure (100, 200, 300, 600) according to one of the preceding claims, comprising: Insertion of at least one anchor post (112, 212.1, 212.2, 212.3, 312, 612.1,
612.3, 612.3) in einen Boden (114, 214, 314, 714), und anschließendes Einbringen eines Turms (110, 210, 310, 610) in den Boden (114, 214, 314, 714), derart, dass ein Verbindungsbereich (106, 206, 306, 606) gebildet wird, in den ein Ende (360) des mindestens einen Ankerpfahls (112, 212.1, 212.2,612.3, 612.3) in a floor (114, 214, 314, 714), and then introducing a tower (110, 210, 310, 610) into the floor (114, 214, 314, 714), such that a connecting area ( 106, 206, 306, 606) is formed, in which one end (360) of the at least one anchor post (112, 212.1, 212.2,
212.3, 312, 612.1, 612.3, 612.3) eingreift. 212.3, 312, 612.1, 612.3, 612.3) intervenes.
11. Verfahren nach Anspruch 10, dadurch gekennzeichnet, dass nach dem Einbringen des Turms (110, 210, 310, 610) eine Verbindung zwischen einer Innenwand (344) des Turms (110, 210, 310, 610) und einer Außenwand (342) des mindestens einen Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1,11. The method according to claim 10, characterized in that after the introduction of the tower (110, 210, 310, 610) a connection between an inner wall (344) of the tower (110, 210, 310, 610) and an outer wall (342) of at least one anchor post (112, 212.1, 212.2, 212.3, 312, 612.1,
612.3, 612.3) hergestellt wird, insbesondere durch zumindest teilweises Vergrauten des Zwischenbereichs (346) zwischen der Innenwand (344) des Turms (110, 210, 310, 610) und der Außenwand (342) des mindestens einen Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1, 612.3, 612.3). 612.3, 612.3), in particular by at least partially graying the intermediate area (346) between the inner wall (344) of the tower (110, 210, 310, 610) and the outer wall (342) of the at least one anchor post (112, 212.1, 212.2) , 212.3, 312, 612.1, 612.3, 612.3).
12. Verfahren zum Herstellen einer Gründungsstruktur (100, 200, 300, 600), insbesondere einer Gründungsstruktur (100, 200, 300, 600) nach einem der vorherigen Ansprüche, umfassend: 12. A method for producing a foundation structure (100, 200, 300, 600), in particular a foundation structure (100, 200, 300, 600) according to one of the preceding claims, comprising:
Bereitstellen mindestens eines Ankerpfahls (112, 212.1, 212.2, 212.3, 312, 612.1,Provision of at least one anchor post (112, 212.1, 212.2, 212.3, 312, 612.1,
612.3.612.3), 612.3.612.3),
Bereitstellen mindestens eines Turms (110, 210, 310, 610), und Herstellen mindestens einer mechanischen Verbindung (356) zwischen dem Turm (110, 210, 310, 610) und dem Ankerpfahl (112, 212.1, 212.2, 212.3, 312,Providing at least one tower (110, 210, 310, 610), and establishing at least one mechanical connection (356) between the tower (110, 210, 310, 610) and the anchor post (112, 212.1, 212.2, 212.3, 312,
612.1.612.3.612.3). 612.1.612.3.612.3).
PCT/EP2020/081691 2019-11-14 2020-11-11 Foundation structure for an offshore apparatus WO2021094339A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102019130703.1A DE102019130703A1 (en) 2019-11-14 2019-11-14 Foundation structure for an offshore facility
DE102019130703.1 2019-11-14

Publications (1)

Publication Number Publication Date
WO2021094339A1 true WO2021094339A1 (en) 2021-05-20

Family

ID=73401489

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2020/081691 WO2021094339A1 (en) 2019-11-14 2020-11-11 Foundation structure for an offshore apparatus

Country Status (2)

Country Link
DE (1) DE102019130703A1 (en)
WO (1) WO2021094339A1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1074663A1 (en) * 1999-08-06 2001-02-07 Carl Bro as A foundation for supporting a building structure, in particular for the foundation of a tower structure, a wind turbine or the like
JP2003020657A (en) * 2001-07-06 2003-01-24 Taisei Corp Structure of connection between pile and pile head structure
US20130255169A1 (en) * 2012-03-30 2013-10-03 Allan P. Henderson Cementitious foundation cap with post-tensioned helical anchors
DE102015209661A1 (en) * 2015-05-27 2016-12-01 Rwe Innogy Gmbh Method for founding a tower construction as well as onshore tower construction
EP3103924A1 (en) * 2015-06-09 2016-12-14 RWE Innogy GmbH Monopile foundation for an offshore tower structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0324317D0 (en) * 2003-10-17 2003-11-19 Dixon Richard K A composite marine foundation
KR20120001384A (en) * 2010-06-29 2012-01-04 주식회사 디엠에스 Marine monopile construction method for wind power generator
CN102425184A (en) * 2011-12-13 2012-04-25 中交第二公路工程局有限公司 Deep water soft soil foundation reverse construction method low pile cap composite foundation cap reserved hole construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1074663A1 (en) * 1999-08-06 2001-02-07 Carl Bro as A foundation for supporting a building structure, in particular for the foundation of a tower structure, a wind turbine or the like
JP2003020657A (en) * 2001-07-06 2003-01-24 Taisei Corp Structure of connection between pile and pile head structure
US20130255169A1 (en) * 2012-03-30 2013-10-03 Allan P. Henderson Cementitious foundation cap with post-tensioned helical anchors
DE102015209661A1 (en) * 2015-05-27 2016-12-01 Rwe Innogy Gmbh Method for founding a tower construction as well as onshore tower construction
EP3103924A1 (en) * 2015-06-09 2016-12-14 RWE Innogy GmbH Monopile foundation for an offshore tower structure

Also Published As

Publication number Publication date
DE102019130703A1 (en) 2021-05-20

Similar Documents

Publication Publication Date Title
EP1735533B2 (en) Method for erecting a tower as well as wind turbine
EP3092357B1 (en) Arrangement with a concrete foundation and a tower and method for erecting a tower
EP1735506B1 (en) Method for erecting a tower
WO2015024772A1 (en) Wind turbine foundation and wind turbine
WO2016135148A1 (en) Wind power plant foundation and wind power plant
WO2013152757A1 (en) Method for producing a foundation for offshore wind energy plants
WO2009121824A2 (en) Hydropower plant
DE102016219413A1 (en) Electrical unit for a wind turbine
DE102010012094B3 (en) Grating structure for e.g. tripod of modular off-shore wind energy plant in steel ship building applications, has tower carrier or tower connector arranged on floor slab and connected with floor slab, where floor slab is located on segments
DE102005014868A1 (en) Offshore wind turbine with non-slip feet
EP4237625B1 (en) Offshore wind energy system
EP2708659B1 (en) Adjustable flange for a tower of a wind power system
DE102015209661A1 (en) Method for founding a tower construction as well as onshore tower construction
WO2021180416A1 (en) Undersea cable for laying on the bottom of bodies of water
WO2021094339A1 (en) Foundation structure for an offshore apparatus
DE102016116166A1 (en) pile foundation
EP3696326A1 (en) Foundation of an offshore structure with submarine cable duct
DE102020112997A1 (en) Foundation for an offshore structure
DE102009008870A1 (en) Apparatus and method for the production of offshore wind turbines
EP2677086B1 (en) Method for anchoring a structure to a bed of a body of water and underwater foundation
EP3051029B1 (en) Foundation pile which is vibrated into a substratum
EP4222318B1 (en) Foundation for an offshore structure
EP3530814A1 (en) Method for the construction of a transformer platform and transformer platform with at least four piles
WO2021259576A1 (en) Foundation profile for an offshore structure
DE102018132452A1 (en) Method for fastening a foundation pile with a section to a building ground

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20806958

Country of ref document: EP

Kind code of ref document: A1

DPE1 Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101)
NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20806958

Country of ref document: EP

Kind code of ref document: A1