一种顶板含水层两步骤注浆改性保水采煤方法Two-step grouting modified water-preserving coal mining method for roof aquifer
技术领域Technical field
本发明涉及矿山领域的一种保水采煤方法,具体为一种顶板含水层两步骤注浆改性保水采煤方法。The invention relates to a water-preserving coal mining method in the field of mining, in particular to a two-step grouting modified water-preserving coal mining method for a roof aquifer.
背景技术Background technique
在矿井开采过程中,覆岩发生移动变形而形成导水通道,使顶板含水层与采空区贯通,造成水资源大量流失,甚至对煤层工作面及巷道等采掘空间构成安全隐患,尤其对于我国西部水资源匮乏、生态环境脆弱的矿井而言,这些问题更加严重。如何减少煤层采动对顶板含水层的扰动,防止含水层与采空区贯通,是实现安全、保水开采必须解决的关键性问题之一。During the mining process, the overlying rock moves and deforms to form a water channel, which connects the roof aquifer and the mined area, causing a large loss of water resources, and even poses a safety hazard to the mining space such as coal seam faces and roadways, especially for my country For mines in the west where water resources are scarce and the ecological environment is fragile, these problems are even more serious. How to reduce the disturbance of coal seam mining to the roof aquifer and prevent the aquifer from passing through the goaf is one of the key issues that must be solved to achieve safe and water-preserving mining.
目前,有关对含水层的处理方法已有较多研究与实践,且取得了不错的效果。例如,通过施工钻孔提前疏放顶板含水层水体,以降低含水层的富水性;向采动形成的导水裂隙中注浆封堵导水裂隙以防止水体涌入等。At present, there have been many studies and practices on the treatment of aquifers, and good results have been achieved. For example, drilling the roof aquifer water in advance through construction drilling to reduce the water richness of the aquifer; grouting into the water-conducting fissures formed by mining to block the water-conducting fissures to prevent the influx of water.
然而,这些方法存在以下几方面问题:(1)从矿山水灾防治的角度出发,疏放含水层以降低开采安全隐患,但造成水资源大量流失;(2)目前向含水层注浆主要用于防治底板承压水灾灾害,而针对顶板含水层的应用较少;(3)以往研究大多是在采后顶板出现裂隙后进行封堵来治理顶板水害,然而此时已发生水资源大量流失;(4)针对顶板含水层的保护多以牺牲资源回收率和回采效率实现,如增加留设煤柱的厚度、限制采高、采用充填开采方法等。However, these methods have the following problems: (1) From the perspective of mine flood prevention, the aquifer is released to reduce potential safety hazards, but causes a large amount of water loss; (2) At present, grouting into the aquifer is mainly used To prevent and control floor confined flood disasters, there are fewer applications for roof aquifers; (3) Previous studies mostly used plugging after cracks in the roof after mining to treat roof water damage, but a large amount of water loss has occurred at this time; ( 4) The protection of the roof aquifer is mostly achieved at the expense of resource recovery and mining efficiency, such as increasing the thickness of the remaining coal pillars, limiting the mining height, and adopting filling mining methods.
因此,针对现有研究的局限性,提出一种顶板含水层两步骤注浆改性保水采煤方法。Therefore, in view of the limitations of existing research, a two-step grouting modified water-preserving coal mining method for roof aquifer is proposed.
发明内容Summary of the invention
本发明的目的在于提供一种顶板含水层两步骤注浆改性保水采煤方法,以解决上述背景技术中提出的问题。The object of the present invention is to provide a two-step grouting modified water-preserving coal mining method for the roof aquifer to solve the problems raised in the background art.
为实现上述目的,本发明提供如下技术方案:In order to achieve the above objectives, the present invention provides the following technical solutions:
一种顶板含水层两步骤注浆改性保水采煤方法,包括煤层和位于煤层上方的含水层,还包括以下步骤:A two-step grouting modified water-preserving coal mining method for roof aquifer includes a coal seam and an aquifer located above the coal seam, and further includes the following steps:
a、获取工作地的基本地质参数和开采技术参数;通过计算,得出采前需要改性的含水层和隔水层的第一空间范围;a. Obtain the basic geological parameters and mining technical parameters of the work site; calculate the first spatial range of the aquifer and aquifer that needs to be modified before mining;
b、在步骤a中所述第一空间范围,从地表至含水层底部间隔布置若干个第一注浆钻孔,第一注浆钻孔包括竖直钻孔、钻孔造斜段和贴合含水层底部的水平钻孔;b. In the first space range in step a, a number of first grouting boreholes are arranged at intervals from the surface to the bottom of the aquifer, and the first grouting boreholes include vertical boreholes, borehole deflection sections and bonding Horizontal boreholes at the bottom of the aquifer;
c、由地面注浆泵站通过第一注浆钻孔把具有柔塑性和隔水性的第一浆液注入b步骤中的含水层底部中,使得含水层改性;c. The ground grouting pump station injects the first slurry with flexibility and water resistance into the bottom of the aquifer in step b through the first grouting borehole to modify the aquifer;
d、注浆改性完成后,对煤层的工作面进行正常回采;d. After the grouting modification is completed, carry out normal mining on the working face of the coal seam;
e、煤层工作面开采结束后,根据步骤a中的参数计算得到注入第二浆液的第二空 间范围;e. After the coal seam working face is mined, calculate the second space range into which the second slurry is injected according to the parameters in step a;
f、从地表往所述第二空间范围钻出第二注浆钻孔,再由地面注浆泵站通过第二注浆钻孔和/或第一注浆钻孔向由于步骤d采后不稳定覆岩活动可能造成的新的导水裂隙中注入具有高强度和低渗透率的第二浆液。f. Drill a second grouting borehole from the surface to the second space range, and then go through the second grouting borehole and/or the first grouting borehole from the ground grouting pump station. A second grout with high strength and low permeability may be injected into new water-conducting fissures caused by stable overburden activity.
本发明的一个实施例:步骤a中所述基本地质参数和开采技术参数包括:含水层距煤层距离H、煤层倾角α、待采工作面采高m、走向长度l、倾向长度l’、岩层移动角走向δ、上山β、下山γ、顶板下沉系数q,进一步地,计算需要改性的含水层空间尺寸是:沿工作面走向方向,自含水层底部起的厚度d=qm cosα,长度L=1+2H cotδ,沿工作面倾向方向长度B=l′+H(cotβ+cotγ),则含水层注浆改性范围为工作面正上方自含水层底部L×B×d大小的空间区域。An embodiment of the present invention: the basic geological parameters and mining technical parameters mentioned in step a include: the distance H from the aquifer to the coal seam, the inclination angle α of the coal seam, the mining height m of the working face to be mined, the strike length l, the inclined length l', and the rock formation Moving angle trend δ, uphill β, downhill γ, roof subsidence coefficient q, further, calculate the space size of the aquifer that needs to be modified is: along the direction of the working face, the thickness from the bottom of the aquifer d=qm cosα, length L=1+2H cotδ, length along the inclination direction of the working face B=l′+H(cotβ+cotγ), the grouting modification range of the aquifer is the L×B×d space directly above the working face from the bottom of the aquifer area.
本发明的一个实施例:步骤b中第一注浆钻孔还包括从水平钻孔上分出的若干个水平分支钻孔。An embodiment of the present invention: the first grouting borehole in step b further includes several horizontal branch boreholes separated from the horizontal borehole.
本发明的一个实施例:如步骤c中第一浆液是黏土类浆液。An embodiment of the present invention: as in step c, the first slurry is a clay slurry.
本发明的一个实施例:如步骤c中注入第一浆液的注浆步骤是:An embodiment of the present invention: the grouting step of injecting the first slurry in step c is:
①先用稀的浆体主要起到对含水层下部部分裂隙的封堵作用与下部水的固化作用;①The first use of dilute slurry is mainly to plug the cracks in the lower part of the aquifer and solidify the lower water;
②再注入浓浆,通过调节注浆压力,保证浆液充满待注浆区域且均匀分布,直至达到预计改造隔水层厚度。②Inject thick slurry again, and adjust the grouting pressure to ensure that the slurry fills the area to be grouted and is evenly distributed until it reaches the expected thickness of the water barrier.
本发明的一个实施例:步骤e中的第二浆液是由水、水泥浆、水玻璃混合而成的高强低渗浆液。An embodiment of the present invention: the second slurry in step e is a high-strength and low-permeability slurry formed by mixing water, cement slurry, and water glass.
本发明的一个实施例:步骤e所述的第二空间范围是封闭的环形结构,具体尺寸如下:在工作面走向方向上,自煤壁正上方向实体煤侧宽度为H cotδ,沿工作面倾向方向上,在上下端头、自煤壁正上方向实体煤侧宽度分别为H cotγ、H cotβ的一环形区域。An embodiment of the present invention: the second space range described in step e is a closed annular structure, and the specific dimensions are as follows: in the direction of the working face, the width of the solid coal side from the top of the coal wall is Hcotδ, along the working face In the direction of inclination, an annular area with the width of H cot γ and H cot β at the upper and lower ends of the solid coal side from directly above the coal wall.
与现有技术相比,本发明的有益效果是:该方法通过在采前、采后对顶板含水层分别注入不同材料的浆体,一方面采前增加隔水层厚度,减弱煤层采动对顶板含水层的扰动,另一方面也可防止采后导水裂隙导通含水层与采空区,从而实现保水开采。Compared with the prior art, the present invention has the following beneficial effects: the method injects slurry of different materials into the roof aquifer before and after mining. On the one hand, the thickness of the water barrier is increased before mining and the impact of coal mining is reduced. The disturbance of the roof aquifer, on the other hand, can also prevent the post-harvest water conducting fissures from connecting the aquifer and the mined-out area, thereby realizing water-retaining mining.
附图说明Description of the drawings
图1为本发明正面结构示意图;Figure 1 is a schematic diagram of the front structure of the present invention;
图2为本发明含水层在改性后的俯视图;Figure 2 is a top view of the modified aquifer of the present invention;
图3为图2中A-A处的剖视图。Fig. 3 is a cross-sectional view at A-A in Fig. 2.
图中:1、地面注浆泵站,2、第一注浆钻孔,3、表土层,4、含水层,41隔水层,5、煤层,6、工作面,7、第一空间,8、采空区,9、第二空间、91、第二注浆钻孔。In the picture: 1. Ground grouting pump station, 2. The first grouting borehole, 3. The surface soil layer, 4. Aquifer, 41 water barrier, 5. Coal seam, 6. Working face, 7. The first space, 8. Goaf, 9. Second space, 91, second grouting hole.
具体实施方式detailed description
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work shall fall within the protection scope of the present invention.
在背景技术中详细记载了本申请要解决的技术问题,即:提出一种可以既可以保水,又可以提高产出率的采煤方法,具体实施方式可以如下:In the background art, the technical problem to be solved by this application is described in detail, that is, a coal mining method that can not only retain water but also increase the output rate is proposed. The specific implementation may be as follows:
如图1所示,一种顶板含水层两步骤注浆改性保水采煤方法,包括煤层5和位于煤层5上方的含水层4,一般情况下,当煤层5采空后,就会造成含水层4下方的隔水层41的岩层出现破损裂缝,当裂缝持续发育并沟通含水层与煤层,便会形成突水。在使用本申请的方法之前,需要先按照如下的步骤实施:As shown in Figure 1, a two-step grouting modified water-preserving coal mining method for roof aquifers includes coal seam 5 and aquifer 4 located above coal seam 5. Under normal circumstances, when coal seam 5 is mined, it will cause water The rock layer of the water barrier 41 below layer 4 has broken cracks. When the cracks continue to develop and communicate with the aquifer and the coal seam, water inrush will form. Before using the method of this application, you need to implement the following steps:
如图1,a、获取工作地的基本地质参数和开采技术参数,获得参数的方式很多,可以通过实地勘测或者查询资料等,主要获得的参数包括含水层4距煤层距离H、煤层倾角α、待采工作面6的采高m、走向长度l、倾向长度l’、岩层移动角走向δ、上山β、下山γ、顶板下沉系数q,通过这些数据的计算,得出采前需要改性的含水层4和隔水层41的第一空间范围。这里的空间范围具体来说是需要改性的含水层空间尺寸是:沿工作面走向方向,自含水层4底部起的厚度d=qm cosα,长度L=l+2H cotδ,沿工作面倾向方向长度B=l′+H(cotβ+cotγ),则含水层4注浆改性范围为工作面正上方自含水层底部L×B×d大小的空间区域。As shown in Figure 1, a. Obtain the basic geological parameters and mining technical parameters of the work site. There are many ways to obtain the parameters. You can use field surveys or query data. The main parameters obtained include the distance H from the aquifer 4 to the coal seam, the coal seam inclination α, The mining height m, strike length l, inclination length l', strata movement angle strike δ, uphill β, downhill γ, roof subsidence coefficient q of working face 6 to be mined are calculated, and it is concluded that modification is required before mining. The first spatial extent of the aquifer 4 and the water barrier 41. The spatial scope here specifically refers to the spatial dimensions of the aquifer that needs to be modified: along the direction of the working surface, the thickness from the bottom of the aquifer 4 is d=qm cosα, the length L=l+2Hcotδ, along the direction of the working surface’s inclination The length B=l′+H(cotβ+cotγ), the grouting modification range of the aquifer 4 is the space area L×B×d directly above the working surface from the bottom of the aquifer.
如图1、2中,b、在步骤a中所述第一空间7范围,从地表至含水层底部间隔布置若干个第一注浆钻孔2,第一注浆钻孔包括竖直钻孔、钻孔造斜段和贴合含水层底部的水平钻孔。这里为了确保整个含水层4的底部L×B×d大小的空间区域中都被第一浆液改性,需要在地表每隔一段距离就钻出一条第一注浆钻孔2,具体的间隔距离可以根据现场含水层4的透水性计算得知。As shown in Figures 1 and 2, b. In the range of the first space 7 described in step a, several first grouting boreholes 2 are arranged at intervals from the surface to the bottom of the aquifer. The first grouting boreholes include vertical boreholes. , Borehole deflection section and horizontal borehole that fits the bottom of the aquifer. In order to ensure that the entire L×B×d space at the bottom of the aquifer 4 is modified by the first slurry, a first grouting borehole 2 needs to be drilled at intervals on the ground surface. The specific spacing distance is It can be calculated according to the water permeability of the aquifer 4 on site.
而步骤b中的第一注浆钻孔2为了让第一浆液更强全面的对含水层4改性,还可以让第一注浆钻孔2包括从水平钻孔上分出的若干个水平分支钻孔。这里的水平分支钻孔属于钻探领域的现有技术,这里就不详述。In order for the first grouting borehole 2 in step b to make the first grout more comprehensively modify the aquifer 4, the first grouting borehole 2 can also include several levels separated from the horizontal borehole. Branch drilling. The horizontal branch drilling here belongs to the existing technology in the field of drilling and will not be detailed here.
c、由地面注浆泵站通过第一注浆钻孔2把具有柔塑性和隔水性的第一浆液注入b步骤中的含水层4底部中,以使得让含水层4改性。c. The ground grouting pump station injects the first slurry with flexibility and water resistance into the bottom of the aquifer 4 in step b through the first grouting bore 2 to modify the aquifer 4.
对于使用的第一浆液具体配方可以是黏土类浆液,更详细的说可以是第一浆液的配方是,黏土∶水∶水泥=5∶10∶1。The specific formulation of the first slurry used may be a clay-based slurry, and more specifically, the formulation of the first slurry may be clay: water: cement = 5:10:1.
并且,为了让第一浆液更好的注入含水层4的岩层中,可以按照如下的操作方法:Moreover, in order to better inject the first slurry into the rock formation of the aquifer 4, the following operating methods can be followed:
①先用稀的浆体主要起到对含水层4下部部分裂隙的封堵作用与下部水的固化作用;①First, the thin slurry is used to plug the cracks in the lower part of the aquifer 4 and solidify the lower water;
②再注入浓浆,通过调节注浆压力,保证浆液充满待注浆区域且均匀分布,直至达到预计改造隔水层41厚度。②Inject thick slurry again, and adjust the grouting pressure to ensure that the slurry fills the area to be grouted and is evenly distributed until the thickness of the water barrier layer 41 is expected to be transformed.
根据毛细理论,较稀第一浆液可以快速向含水层4内部的毛细管扩散,利用这种扩散可以把含水层4中的毛细管全部堵塞,这样就变相的把含水层4改性成为隔水层41。再注入浓浆,这样又可以堵塞住更粗的毛细管,通过上述的方法,达到对含水层4改性的目的。According to the capillary theory, the thinner first slurry can quickly diffuse into the capillaries inside the aquifer 4, and this diffusion can block all the capillaries in the aquifer 4, thus transforming the aquifer 4 into a water barrier 41 in a disguised form. . Then inject the thick slurry, which can block the thicker capillary tube. Through the above method, the purpose of modifying the aquifer 4 is achieved.
如图3中,d、注浆改性完成后,对煤层5的工作面6进行正常回采,但是由于含水层4已经是改性过的具有一定的抗干扰能力,因此,可以确保整个含水层4不会出现突水的情况。As shown in Figure 3, d. After the grouting modification is completed, the working face 6 of the coal seam 5 is normally recovered, but because the aquifer 4 has been modified and has a certain anti-interference ability, it can ensure the entire aquifer 4 There will be no water inrush.
如图3中,本发明在考虑到工作面顶板下沉量,改性后含水层4还要一个更重要的作用:改性后含水层4的高度刚好可以补充下陷造成的凹陷区。As shown in Fig. 3, the present invention takes into account the roof subsidence of the working face, and the modified aquifer 4 has a more important function: the height of the modified aquifer 4 can just supplement the depression caused by the subsidence.
如图2和3中,在步骤d中虽然含水层4没有出现突水的情况,但是由于工作面顶板 的下沉,会导致改性含水层4的边缘出现新的拉伸裂痕。因此,为了消除隐患,在步骤e中,煤层工作面开采结束后,根据步骤a中的参数计算得到注入第二浆液的第二空间9范围,具体的范围如下:As shown in Figs. 2 and 3, although the aquifer 4 does not incur water inrush in step d, due to the sinking of the roof of the working face, new tensile cracks will appear on the edge of the modified aquifer 4. Therefore, in order to eliminate hidden dangers, in step e, after the coal seam face is mined, the second space 9 range into which the second slurry is injected is calculated according to the parameters in step a, and the specific range is as follows:
第二空间9范围是封闭的环形结构,具体尺寸如下:在工作面走向方向上,自煤壁正上方向实体煤侧宽度为H cotδ,沿工作面倾向方向上,在上下端头、自煤壁正上方向实体煤侧宽度分别为H cotγ、H cotβ的一环形区域。具体的工作过程如步骤f:从地表往所述第二空间范围钻出第二注浆钻孔91,再由地面注浆泵站1通过第二注浆钻孔91和/或第一注浆钻孔2向由于步骤d采后不稳定覆岩活动可能产生的新的导水裂隙中注入具有高强度和低渗透率的第二浆液。The scope of the second space 9 is a closed ring structure. The specific dimensions are as follows: in the direction of the working face, the width of the solid coal side is H cot δ from the top of the coal wall, and in the direction of the working face, at the upper and lower ends of the coal The width of the solid coal side on the upper side of the wall is an annular area with Hcotγ and Hcotβ respectively. The specific working process is as step f: drill a second grouting borehole 91 from the surface to the second space range, and then pass the second grouting borehole 91 and/or the first grouting hole from the ground grouting pump station 1 Drill hole 2 injects a second slurry with high strength and low permeability into new water-conducting fractures that may be generated due to unstable overburden activity after step d.
第二浆液可以是由水、水泥浆、水玻璃混合而成的,具体来说它们的比例,水∶水泥∶水玻璃的配比为2∶2∶3。The second slurry may be a mixture of water, cement slurry, and water glass. Specifically, the ratio of water: cement: water glass is 2:2:3.
本发明的原理大致分成2个步骤:第一步骤是把含水层4的底部改性成隔水层。由于含水层4底部本身就在原隔水层41的上方,且因使用黏土类浆液,抗扰动能力较强,因此改性后一方面当原隔水层41出现断裂后,使用的第一浆液会起到隔水作用;另一方面,改性后的含水层4叠加在隔水层41后,增加了隔水层的厚度,这个多出来的厚度会用作补充采空区下沉的高度差。The principle of the present invention is roughly divided into two steps: The first step is to modify the bottom of the aquifer 4 into a water barrier. Since the bottom of the aquifer 4 itself is above the original water-resistant layer 41, and because of the use of clay slurry, the anti-disturbance ability is relatively strong. Therefore, after the modification, when the original water-resistant layer 41 is broken, the first slurry used will be Play a water barrier function; on the other hand, after the modified aquifer 4 is superimposed on the barrier layer 41, the thickness of the barrier layer is increased. This extra thickness will be used to supplement the height difference of the subsidence of the goaf .
而本发明第二步骤的作用是再次注浆堵住改性后含水层4边缘新出现的裂隙,第二步骤的作用除了封堵裂隙,还有另外的一个作用是:给改性后含水层4边缘的一个拉力,让改性后的含水层4和第二浆液二者构成一个整体,可以确保整个水层的水源不会枯竭,并且使用本方法还可以把整个工作面6的煤全部开采掉,提高产出效率。The second step of the present invention is to re-grouting to block the newly emerging cracks at the edge of the modified aquifer 4. In addition to plugging the cracks, the second step has another role: A pulling force on the edge of 4 allows the modified aquifer 4 and the second slurry to form a whole, which can ensure that the water source of the entire water layer will not be exhausted, and the use of this method can also mine all the coal in the entire working face 6 To improve output efficiency.
下面结合一个具体的实施案例来说明本发明的实际运用。The practical application of the present invention will be described below in conjunction with a specific implementation case.
我国西北部某矿地表生态环境恶劣,水资源短缺。根据矿方资料可得,研究煤层为近水平煤层,煤层倾角7°,煤层埋深260m,可采煤层厚度8m,工作面推进长度1800m,工作面长度200m,采用走向长壁综采放顶煤采煤法开采,全部垮落法管理顶板。经地质勘探,煤层上方165m处存在一厚度15m左右的含水层,资料表明,本区域条件下,采动下沉系数0.6,岩层移动角分别为:走向移动角65°,下山移动角55°,上山移动角60°。在原有开采方法下,水资源流失严重。The surface ecological environment of a mine in northwest my country is harsh and water resources are scarce. According to the mine data, the study coal seam is a nearly horizontal coal seam, with a 7° coal seam inclination, a coal seam depth of 260m, a mineable coal seam thickness of 8m, a working face advance length of 1800m, and a working face length of 200m. Coal mining method is used for mining, and the roof is managed by all caving methods. After geological exploration, there is an aquifer with a thickness of about 15m at 165m above the coal seam. The data shows that under the conditions of this area, the mining subsidence coefficient is 0.6, and the rock movement angles are: strike movement angle 65°, downhill movement angle 55°, Uphill movement angle is 60°. Under the original mining method, water resources were lost seriously.
1)获取工作面基本地质参数与开采技术参数。通过查阅矿井基本资料,含水层距煤层距离H=165m,含水层厚度15m,煤层倾角α=7°,煤层埋深260m,可采煤层厚度m=8m,工作面推进长度l=1800m,工作面长度l’=200m。采动下沉系数q=0.6,岩层移动角分别为:走向移动角δ=65°,下山移动角β=55°,上山移动角γ=60°。1) Obtain the basic geological parameters and mining technical parameters of the working face. By consulting the basic information of the mine, the distance between the aquifer and the coal seam is H=165m, the thickness of the aquifer is 15m, the inclination angle of the coal seam is α=7°, the buried depth of the coal seam is 260m, the thickness of the mineable coal seam is m=8m, and the working face advance length l=1800m. The surface length l'=200m. The mining subsidence coefficient q=0.6, and the rock formation movement angles are: strike movement angle δ=65°, downhill movement angle β=55°, and uphill movement angle γ=60°.
2)工作面开采前,对自含水层底部一定范围进行注浆改性。具体步骤为:2) Before mining at the working face, grouting is modified to a certain range from the bottom of the aquifer. The specific steps are:
(1)工作面开采前,首先根据所述基本参数,通过计算确定采前注浆改性范围:自含水层底部厚度d=qmcosα,沿工作面走向方向长度L=l+2Hcotδ,沿工作面倾向方向长度B=l’+H(cotβ+cotγ)。将相关参数代入公式计算可得,自含水层底部厚度d=0.6×8×cos7°=4.8m,沿工作面走向方向长度L=1800+2×165×cot65°=1954m,沿工作面倾向方向长度B=200+165×(cot55°+cot65°)=411m,则需注浆的范围为工作面正上方自含水层底部1954m×411m×4.8m大小的区域,形成了如图1中第一空间7。(1) Before mining the working face, firstly determine the pre-mining grouting modification range by calculation according to the basic parameters: thickness from the bottom of the aquifer d=qmcosα, length along the strike direction of the working face L=l+2Hcotδ, along the working face Inclination direction length B=1'+H(cotβ+cotγ). Substituting the relevant parameters into the formula to calculate, the bottom thickness of the aquifer is d=0.6×8×cos7°=4.8m, the length along the strike direction of the working face is L=1800+2×165×cot65°=1954m, along the direction of the working face’s inclination Length B=200+165×(cot55°+cot65°)=411m, then the range of grouting is 1954m×411m×4.8m from the bottom of the aquifer directly above the working surface, forming the first in Figure 1. Space 7.
(2)根据1)中探测得到的含水层位置及计算得到的注浆改性范围,由地面注浆泵 站向含水层中布置注浆钻孔,注浆钻孔由竖直钻孔、钻孔造斜段、水平钻孔以及水平分支钻孔四部分构成。如图1中(2)所示,竖直钻孔钻至埋深55m处,距含水层垂直距离20m~30m,为之后钻孔造斜提供足够的弯曲空间;之后进行钻孔造斜,使主钻孔能够水平的打入含水层下部;水平钻孔布置在计算得到的改造隔水层位置,走向长度为1980m,略大于隔水层走向长度L,贯穿整个工作面上方;最后通过无磁钻杆调节位置,在含水层注浆改性区域内布置若干分支钻孔,分支钻孔长度为420m,采用均匀分布的布置方式,保证注入浆液能够在确定的区域内均匀分布,形成预计厚度的隔水层。(2) According to the position of the aquifer detected in 1) and the range of grouting modification obtained by calculation, grouting boreholes are arranged into the aquifer from the ground grouting pump station. The hole-making section, horizontal drilling and horizontal branch drilling are composed of four parts. As shown in Figure 1 (2), the vertical borehole is drilled to a buried depth of 55m, and the vertical distance from the aquifer is 20m-30m, which provides sufficient bending space for the subsequent drilling and deflection; The main borehole can be drilled into the lower part of the aquifer horizontally; the horizontal borehole is arranged at the position of the reconstructed aquifer calculated by calculation, the strike length is 1980m, which is slightly longer than the strike length L of the aquifer, and runs through the entire working surface; Adjust the position of the drill pipe, arrange several branch boreholes in the grouting modification area of the aquifer. The length of the branch boreholes is 420m. The arrangement method is evenly distributed to ensure that the injected slurry can be evenly distributed in the determined area to form the expected thickness Water barrier.
(3)注浆浆液使用黏土固化浆液,配比为黏土∶水∶水泥=5∶10∶1,可根据情况加入适量水玻璃适当提高凝结速度。注浆顺序采用先稀后浓的注浆方式,稀稠的浆体主要起到对含水层下部部分裂隙的封堵作用与下部水的固化作用,然后注入浓浆,通过调节注浆压力,保证浆液充满待注浆区域且均匀分布,直至达到预计改造隔水层厚度。(3) Clay solidification slurry is used for grouting slurry, and the ratio is clay: water: cement = 5: 10:1, and appropriate amount of water glass can be added to increase the setting speed appropriately according to the situation. The grouting sequence adopts the first thin and then thick grouting method. The thin and thick slurry mainly plays the role of plugging the cracks in the lower part of the aquifer and solidifying the lower water. Then the thick slurry is injected, and the grouting pressure is adjusted to ensure The grout fills the area to be grouted and is evenly distributed until it reaches the expected thickness of the reconstructed water barrier.
3)采前注浆改性完成后,工作面进行正常回采。3) After the pre-mining grouting modification is completed, the working face shall undergo normal mining.
4)工作面开采后,改造隔水层受到的采动影响,尤其是上覆岩层变形导致开采边界顶板上方部分区域产生张拉裂隙,需要通过注浆强性,封堵这些可能产生的导水裂隙。具体步骤为:4) After mining on the working face, the modified water-resistant layer is affected by mining, especially the deformation of the overlying rock layer causes tension cracks in some areas above the mining boundary roof. It is necessary to plug these possible water conduction through grouting strength Rift. The specific steps are:
(1)工作面开采后,首先,根据所述基本参数,计算得到采后注浆的第二空间9范围:工作面走向方向上,自煤壁正上方向实体煤侧宽度为Hcotδ,沿工作面倾向方向上,在上下端头,自煤壁正上方向实体煤侧宽度分别为Hcotγ、Hcotβ。将相关参数代入公式计算可得,沿工作面走向方向上,实体煤两侧需注浆区域的宽度为Hcotδ=165×cot65°=77m,沿工作面倾向方向上,上端头实体煤侧宽度为Hcotγ=165×cot60°=95m,下端头实体煤侧宽度为Hcotβ=165×cot55°=116m。注浆范围为一环形区域。(1) After mining of the working face, firstly, according to the basic parameters, the second space 9 range of post-mining grouting is calculated: in the strike direction of the working face, the width of the solid coal side from the top of the coal wall is Hcotδ, In the direction of face inclination, at the upper and lower ends, the width of the solid coal side from directly above the coal wall is Hcotγ and Hcotβ respectively. Substituting the relevant parameters into the formula to calculate, the width of the area to be grouted on both sides of the solid coal along the strike direction of the working face is Hcotδ=165×cot65°=77m, and the width of the solid coal side at the upper end of the working face is Hcotγ=165×cot60°=95m, and the width of the solid coal side at the lower end is Hcotβ=165×cot55°=116m. The grouting range is an annular area.
(2)如图3所示,从地面直接将钻孔布置到需要注浆的区域,钻孔终孔钻入改造隔水层底部,钻孔深度95m,位于注浆范围中心位置,注浆钻孔在走向、倾向方向上每50m布置一个。该工作面倾向注浆长度为411m,走向注浆长度为1954m,因此倾向方向每侧布置注浆钻孔8个,走向方向每侧布置注浆钻孔40个。(2) As shown in Figure 3, the drilling holes are directly arranged from the ground to the area where grouting is required. The final hole is drilled into the bottom of the reconstructed water barrier. The drilling depth is 95m and is located at the center of the grouting range. The holes are arranged every 50m in the direction of direction and inclination. The inclined grouting length of this working face is 411m, and the strike grouting length is 1954m. Therefore, 8 grouting holes are arranged on each side of the inclined direction, and 40 grouting holes are arranged on each side of the strike direction.
(3)注浆材料建议使用高强度、低渗透率的浆液。在该实例中,注浆浆液选择水玻璃、水泥浆混合浆液,配比为水∶水泥∶水玻璃=2∶2∶3。(3) It is recommended to use high-strength, low-permeability grout for the grouting material. In this example, the grouting slurry chooses water glass and cement slurry mixed slurry, and the ratio is water: cement: water glass = 2:2:3.
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those of ordinary skill in the art can understand that various changes, modifications, and substitutions can be made to these embodiments without departing from the principle and spirit of the present invention. And variations, the scope of the present invention is defined by the appended claims and their equivalents.