US654426A - Art of building subways. - Google Patents
Art of building subways. Download PDFInfo
- Publication number
- US654426A US654426A US71020299A US1899710202A US654426A US 654426 A US654426 A US 654426A US 71020299 A US71020299 A US 71020299A US 1899710202 A US1899710202 A US 1899710202A US 654426 A US654426 A US 654426A
- Authority
- US
- United States
- Prior art keywords
- excavation
- piling
- building
- sheet
- art
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009412 basement excavation Methods 0.000 description 14
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- 238000010586 diagram Methods 0.000 description 4
- OTSMHWLYYJVJDL-UHFFFAOYSA-N SSSSSSSSS Chemical compound SSSSSSSSS OTSMHWLYYJVJDL-UHFFFAOYSA-N 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
Definitions
- the invention consists in an improvement in the art of building subways or other similar excavations or subterraneous work.
- the invention as herein outlined particularly relates to building a subway under a street upon which there is traffic; and it consists in the method of performing the work and in the means employed, so that the work may go on with the least possible interruption to the traffic, as will be more fully hereinafter described.
- Figure 1 is asectional perspective view showing the manner of sinking the sheet-piling preparatory to laying the side walls.
- Fig. 2 is a section showing the piling' sunk and the trench formed ready for the wall.
- Fig. 3 is a section through the roadway, showing on the left hand the side wall sunk and on the right hand the temporary roadway in position.
- Fig. et is a section showing the permanent roof in position and excavation under way.
- Fig. 5 is a section showing the subway complete
- Fig. 6 is a diagram plan illustrating means for draining the work during trenching or tunneling.
- Fig. 7 is a diagram section illustrating the arrangement ofthe drainage-wells.
- this temporary roadway I may lay in position at the same time the cross-girders Lwhich are to form the roof-girders of the subway. I may lay those girders under the temporary roadway and complete the rough skeleton structure thereunder.
- the pavement may be replaced and the excavation go on beneath either the permanent or temporary roadway, as desired, as shown in Fig. 4, where I have shown a section of the street with walls on opposite sides, the permanent roof in position, and the permanent roadway replaced, the excavation being in progress.
- the excavation may be continued now without danger to the side walls, as they are tied together at the top by the roof, and the only necessary indication of the activity beneath Will be at that point Where the material is drawn up from the excavation below.
- Fig. 5 shows the subway complete. In building such subways it happens at times that the excavation would go into places where there is .considerable water, or it may even go into places beneath the water-level, so that the work would be much impeded by the Water if means were not provided for drawing it away. To drain the excavation,
- I may either attach suction-pipes to the pipes C, which connect to the shoes B in advance of or adjacent to the excavation, or I may and preferably do sink a series of drive-wells of any known or usual construction, as indicated at I in Fig. 6, and connect these drive-wells with the suction apparatus, 3o
- FIG. 7 I have indicated in a simple diagram section a pair of these wells and the connecting-pipes, showing them arranged slightly in advance of the excavation. I believe this is an entirely new departure in excavationthat is, to sink wells adjacent to the trench, subway, or other excavation, so as not to interfere in any waytherewith and by suitable pumps or suction devices maintain the waterlevel in the strata in which the excavation is being done below the level at which the work is being carried on.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
No. 654,426. Patented luly 24, |900.
W. DE H. WASHINGFLM. ART 0F BUlLDlNG SUBWAYS.
{Apglicaton filed Mar. 23, 18994) LNo Model.) 3 Sheets-Sheet l,
wv: Nanms paens co, Punto-nwo.wAsHmnToN, n c.
nm o N 4, 2 W. u Il d e L n e l a P N. o T G m H s A W H. E D W 6. 2 4 4 5 6. 0. N
ABT 0F BUILDING SUBWAYS.
(Application filed Max'. 23, 1899.)
3 Sheets-Sheet 2.
SSS SSSSS S .2
mum..." ummm.
SSSSSSSSS FLL IA nu: mams s1-:ns cn. mam-uma, wAsnmmoN, 'nA c.
Patented luly 24, |900.
W. DE H. WASHINGTON.
ART 0F BUILDING SUBWAYS.
(Application led Mar. 23l 1899.)
Y 3 Sheets-Sheet 3,
(No Model.)
f :vie/111m af' Nitin STATES f P.lvrnnr'r Frick..
4WILLIAM DE I-I. WASHINGTON, OF NEV YORK, N. Y.
ART oF BUILDING suswAYs.
SPECIFICATION forming part of Letters Patent No. 654,426, dated July 24, 1900.`
Application tiled March 2 3, 1 89 9.
To alt whom, it may concern:
Be it known that I, WILLIAM-DE H. WASH- INGTON, a citizen of the United States, residing at New York,in thecounty of New York and State of New York, have invented certain-new and useful Improvements in the Art of Building Subways, dre., of which the following is a specification, reference being had therein to the accompanying drawings.
The inventionconsists in an improvement in the art of building subways or other similar excavations or subterraneous work.
The invention as herein outlined particularly relates to building a subway under a street upon which there is traffic; and it consists in the method of performing the work and in the means employed, so that the work may go on with the least possible interruption to the traffic, as will be more fully hereinafter described.
In the drawings, Figure 1 is asectional perspective view showing the manner of sinking the sheet-piling preparatory to laying the side walls. Fig. 2 is a section showing the piling' sunk and the trench formed ready for the wall. Fig. 3 is a section through the roadway, showing on the left hand the side wall sunk and on the right hand the temporary roadway in position. Fig. et is a section showing the permanent roof in position and excavation under way. Fig. 5 is a section showing the subway complete, and Fig. 6 isa diagram plan illustrating means for draining the work during trenching or tunneling. Fig. 7 is a diagram section illustrating the arrangement ofthe drainage-wells.
In constructing a subway on a street in which there is traffic I propose first to complete the side walls without disturbing the street beyond that part necessary for building such walls, and to do this without the danger of caving in, which exists in the digging of deep and narrow trenches and without the necessity of digging out the entire street.
I proceed first to drive sheet-piling A A in parallel courses separated a width equal to the wid thf of the side walls of the complete structure. This sheet-pilingl prefer to drive by hydraulic means, as follows: I build up the sheet-piling in sections, as shown in Fig. l, and apply to each section at the foot a sain No. 710,202. (no model.)
hollow pointed shoe B, having discharge-j ets, such aso., therefrom, and I connect into this shoe one or more pipes O, which connect with a source `ofwater-supply, such as the pump D. I then dig a shallow trench of sufficient depth to' stand the piling upright, as shown in Fig. 1 at the right hand. y.The water is then forced through the pipe i or pipes O, through the shoe B, and being .discharged therefrom will dig out` the earth below the piling and allow the same to sink. This sinking may be aided by pressure or by weight, such as E,.applied while the water is being discharged. Y
In the drawings I have shown the sheetpiling A' driven to vthe depth desired, while the sheet-piling A is just in the act of being sunk.- I drive this sheet-piling a consider-L able distance below the point at which the foundation is to stand, so that it acts to prevent the inow of water from the side and also acts to support the base of the sheet-piling when the trench is formed between the two sections, as shown in Fig. 2. This figure shows 'the two sections of sheet-piling in position with the trench F of the desired depth for a foundation, and suitable braces, such asG, for the upper part of the piling. The manner of sinking this sheet-piling I do not herein claim, as VI make that the subjectmatter of a concurrently-pending application, Serial No. 660,990. When the sheetpilingis driven upon one or both sides of the street and theA trench F is formed, I then build in this trench the foundation of brick or stone work, as shown at the left hand in Fig. 3. It is obvious that in laying these side walls in this manner the traffic in the street need not be seriously or at all impeded. I next remove the roadway to a slight depth and replace it with a temporary roadway II, and as this may be done in sections, one side of the street or one short section of the street ata time, and as traffic can go on over the temporary roadway as soon as'it is laid, it is evident that but a short interruption willbe necessary. In laying this temporary roadway I may lay in position at the same time the cross-girders Lwhich are to form the roof-girders of the subway. I may lay those girders under the temporary roadway and complete the rough skeleton structure thereunder.
IOO
This being done, the pavement may be replaced and the excavation go on beneath either the permanent or temporary roadway, as desired, as shown in Fig. 4, where I have shown a section of the street with walls on opposite sides, the permanent roof in position, and the permanent roadway replaced, the excavation being in progress. The excavation may be continued now without danger to the side walls, as they are tied together at the top by the roof, and the only necessary indication of the activity beneath Will be at that point Where the material is drawn up from the excavation below.
Fig. 5 shows the subway complete. In building such subways it happens at times that the excavation would go into places where there is .considerable water, or it may even go into places beneath the water-level, so that the work would be much impeded by the Water if means were not provided for drawing it away. To drain the excavation,
(in advance of the excavation in this or similar work,) I may either attach suction-pipes to the pipes C, which connect to the shoes B in advance of or adjacent to the excavation, or I may and preferably do sink a series of drive-wells of any known or usual construction, as indicated at I in Fig. 6, and connect these drive-wells with the suction apparatus, 3o
such as the pump indicated in diagram at K, drawing the Water from a point below the excavation and maintaining it below that point at all times and in advance of the work. In Fig. 7 I have indicated in a simple diagram section a pair of these wells and the connecting-pipes, showing them arranged slightly in advance of the excavation. I believe this is an entirely new departure in excavationthat is, to sink wells adjacent to the trench, subway, or other excavation, so as not to interfere in any waytherewith and by suitable pumps or suction devices maintain the waterlevel in the strata in which the excavation is being done below the level at which the work is being carried on.
What I claim as my invention is In a subway, the side walls, sheathing on both sides thereof and extending a-considerable distance below the bottom thereof, to form in effect a dam below the walls. l In testimony whereof I affix my signature in presence of two witnesses.
VILLIAM DE H. WASHINGTON.
Witnesses:
SAML. WORTHINGTON, JULIAN E. INGLE, Jr.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US71020299A US654426A (en) | 1899-03-23 | 1899-03-23 | Art of building subways. |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US71020299A US654426A (en) | 1899-03-23 | 1899-03-23 | Art of building subways. |
Publications (1)
Publication Number | Publication Date |
---|---|
US654426A true US654426A (en) | 1900-07-24 |
Family
ID=2722995
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US71020299A Expired - Lifetime US654426A (en) | 1899-03-23 | 1899-03-23 | Art of building subways. |
Country Status (1)
Country | Link |
---|---|
US (1) | US654426A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3377806A (en) * | 1965-01-29 | 1968-04-16 | Morrice Anthony Ronald Seaton | Construction in trench of pipelines and similar operations |
US3999394A (en) * | 1976-03-29 | 1976-12-28 | Eberhardt William H | Precast ribbed arch subway structure and method |
-
1899
- 1899-03-23 US US71020299A patent/US654426A/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3377806A (en) * | 1965-01-29 | 1968-04-16 | Morrice Anthony Ronald Seaton | Construction in trench of pipelines and similar operations |
US3999394A (en) * | 1976-03-29 | 1976-12-28 | Eberhardt William H | Precast ribbed arch subway structure and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103775110A (en) | Underground excavation construction method for multilayer underground space of soft soil area | |
RU2686206C1 (en) | Method of erection of underground structures along river bed or canal | |
US3326003A (en) | Method of forming ground cut-off wall | |
US654426A (en) | Art of building subways. | |
US786382A (en) | Method of subway construction. | |
RU2501912C2 (en) | Method to erect underwater tunnels | |
Prentis et al. | Underpinning: its practice and applications | |
US960940A (en) | Art of constructing tunnels in the earth. | |
US2007498A (en) | Method of erecting an iron frame building having deep underground floors | |
US1032952A (en) | Method of constructing subways. | |
US620101A (en) | Art of constructing tunnels | |
US78793A (en) | Improved subaqueous foundation | |
US1698529A (en) | Method of and apparatus for forming trenches | |
US1323884A (en) | Method and apparatus for controlling hill and embankment slides | |
US1320720A (en) | Foundations | |
US440576A (en) | Robert d | |
CN106436760B (en) | A kind of adverse construction method method | |
US1609812A (en) | Underpinning | |
US1088152A (en) | Tunnel and method of constructing same. | |
US262403A (en) | John c | |
US699729A (en) | System of submarine construction. | |
US1151958A (en) | Tunnel construction. | |
US1163096A (en) | Tunnel construction. | |
US1007287A (en) | Art of constructing concrete walls, subways, &c., in the earth. | |