US545978A - Lining tunnels - Google Patents
Lining tunnels Download PDFInfo
- Publication number
- US545978A US545978A US545978DA US545978A US 545978 A US545978 A US 545978A US 545978D A US545978D A US 545978DA US 545978 A US545978 A US 545978A
- Authority
- US
- United States
- Prior art keywords
- concrete
- mold
- tunnel
- lining
- lining tunnels
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000004567 concrete Substances 0.000 description 48
- 238000000034 method Methods 0.000 description 4
- 238000010276 construction Methods 0.000 description 2
- 230000001627 detrimental Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/22—Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
Definitions
- My invention particularly relates to lining tunnels with concrete, and has for its object the closer juxtaposition ofthe concrete to the upper surface of the tunnel.
- the usual way of lining tunnels with concrete is to set up false work or molds within the tunnel and to lill in the space between the tunnel-surface and the false work with concrete.
- In packing concrete about the bottom or sides of the tunnel no such difficulty exists, because the concrete by its own weight assists the packing and tends to force itself close to the adjacent surfaces; but at the crown of the tunnel the concrete cannot be fed from above.
- Figure l is a longitudinal section of a part of a tunnel in the process of being lined with concrete.
- Figs. 2 and 3 are sections on lines X X and Y Y, respectively, of Fig. 1.
- Fig. 4 is an end elevation of a traveling core-inold having a sloping working face.
- Figs. 5 and 6 are sections similar to Figs. 2 and 3, showing a modified construction.
- Figs. 2 and 3 the expansion is made by a sliding block E, which is suspended by bars F and pins F at the required level, as shown in Fig. 3, until the sectional core is in place and the work has sufficiently progressed, when the block is thrust upward, by a jack or other means, until it has expanded the mold and com pressed the concrete sufficiently. Then it is held in that position by inserting pins F through the lower holes of bars F, as shown in Fig. 2. By beveling this block, as shown, the perimeter of the mold can be extended at the same time that the crown is being raised'.
- Figs. 5 and 6 instead of using a sliding block the contraction and expansion are made by the movement of shutter-like pieces Gr G. These pieces partly rest upon the fra/me work of the core-mold at II and partly upon the elevating-screw I.
- This screw is supported by the bar K, which is carried by the lugs L.
- the expansion-pieces are raised to the required height by means of the screw I and are heldin place by one or more bars M, bolted to the lugs N, as shown, wedges O being inserted between the shutters and the bar for keying up tightly.
- the tunnel being excavated to the line A, a traveling core-mold B is placed in position and is surrounded with concrete P while being drawn along in the well-known manner.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Description
. O S N A LINING TUNNELS.
No. 545,978. Patented Sept. '10, 1895.
WITNESsEs:
M W w.
ERNEST LESLIE RANSOME, OF CHICAGO, ILLINOIS;
p LINING TU'NNELS.
SPECIFICATION forming part of Letters Patent No. 545,978, dated september io, i895.
Application tiled March 18j 1895- Srial No. 542,247. (No modem To afZZ whom t may concern:
Be it known that I, ERNEST LESLIE RAN- sOME, a citizen of the United States, residing at Chicago, in the county of Cook and State of Illinois, have invented a new and useful Improvement in Lining Tunnels, of which the the following is a specification.
My invention particularly relates to lining tunnels with concrete, and has for its object the closer juxtaposition ofthe concrete to the upper surface of the tunnel. The usual way of lining tunnels with concrete is to set up false work or molds within the tunnel and to lill in the space between the tunnel-surface and the false work with concrete. In practice it has been found extremely difcult, if not impossible, with ordinary false work to so build the crown of the lining that it will remain solid and tight up against the excavated or other surface of the tunnel. In packing concrete about the bottom or sides of the tunnel no such difficulty exists, because the concrete by its own weight assists the packing and tends to force itself close to the adjacent surfaces; but at the crown of the tunnel the concrete cannot be fed from above. It has to be forced into position horizontally, and by its own Weight it settles down and away from the crown of the tun nel. I overcome this difficulty by my present invention, which consists in first placing the concrete and then forcing it hard up against the surface of the tunnel by expanding the falsework so as to contract the space occupied by the concrete. This expansion is made before the concrete sets, but after the work of filling in the lining has so far progressed ahead as to insure that the concrete compressed by the expansion of the mold will not be further disturbed to any detrimental extent by the continued progress of the Work.
The accompanying drawings illustrate how this process may be carried out.
Figure l is a longitudinal section of a part of a tunnel in the process of being lined with concrete. Figs. 2 and 3 are sections on lines X X and Y Y, respectively, of Fig. 1. Fig. 4 is an end elevation of a traveling core-inold having a sloping working face. Figs. 5 and 6 are sections similar to Figs. 2 and 3, showing a modified construction.
In Figs. 2 and 3 the expansion is made by a sliding block E, which is suspended by bars F and pins F at the required level, as shown in Fig. 3, until the sectional core is in place and the work has sufficiently progressed, when the block is thrust upward, by a jack or other means, until it has expanded the mold and com pressed the concrete sufficiently. Then it is held in that position by inserting pins F through the lower holes of bars F, as shown in Fig. 2. By beveling this block, as shown, the perimeter of the mold can be extended at the same time that the crown is being raised'.
In Figs. 5 and 6, instead of using a sliding block the contraction and expansion are made by the movement of shutter-like pieces Gr G. These pieces partly rest upon the fra/me work of the core-mold at II and partly upon the elevating-screw I. This screw is supported by the bar K, which is carried by the lugs L. The expansion-pieces are raised to the required height by means of the screw I and are heldin place by one or more bars M, bolted to the lugs N, as shown, wedges O being inserted between the shutters and the bar for keying up tightly. The tunnel being excavated to the line A, a traveling core-mold B is placed in position and is surrounded with concrete P while being drawn along in the well-known manner. In the rear of this traveling mold sectional cores B are placed7 one ahead of another, as fast as room is made for them by the forward movement of the traveling mold. As this traveling molddraws away from the sectional cores, the concrete settles down upon them. This settlement increases the unfilled space at C. After the traveling mold has so far progressed ahead that the jarring occasioned by the placing of the concrete is no longer felt, then the sectional molds are expanded at X X until they are brought to their proper height and the concrete above them has been compressed until it entirely and tightly fills the space C and the excess thereof flows ahead. These sec tional core-molds then remain in place until the concrete has sufficiently set, when they are removed.
I do not limit this invention to sectional cores, neither in conjunction with nor independent of a traveling mold. It can be applied equally well to any ordinary false work.
IOO
Nor do I limit this invention to concrete alone. It is equally applicable to any like plastic material.
Having thus described my invention, what l. The method of lining tunnels with concrete which consists in introducing the concrete between the mold and the Wall of the tunnel and in compacting the same against 1o the Wall by pressure from Within the mold.
2. The method of lining tunnels With con crete which consists in introducing the concrete between the mold and the Wall of the tunnel and in forcing the concrete into contact with the upper portion of said Wall by an upward pressure from within the mold.
ERNEST LESLIE RANSOME.
Witnesses:
CASPER L. REDEIELD, STEPHEN T. MATHER.
Publications (1)
Publication Number | Publication Date |
---|---|
US545978A true US545978A (en) | 1895-09-10 |
Family
ID=2614722
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US545978D Expired - Lifetime US545978A (en) | Lining tunnels |
Country Status (1)
Country | Link |
---|---|
US (1) | US545978A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3205550A (en) * | 1963-06-18 | 1965-09-14 | Floyd E Martin | Pipe forming machine |
EP0024157A1 (en) * | 1979-08-09 | 1981-02-25 | Johnston Construction Limited | Method of lining or relining tunnels and tunnels lined or relined by such a method |
US4917538A (en) * | 1988-04-26 | 1990-04-17 | Shigetoshi Koga | Tunnel lining process and apparatus therefor |
US5190705A (en) * | 1990-09-14 | 1993-03-02 | Leo Corazza | Method for lining large-diameter pipes |
US5263843A (en) * | 1990-07-02 | 1993-11-23 | British Gas Plc | Splittable die used in pipe lining |
-
0
- US US545978D patent/US545978A/en not_active Expired - Lifetime
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3205550A (en) * | 1963-06-18 | 1965-09-14 | Floyd E Martin | Pipe forming machine |
EP0024157A1 (en) * | 1979-08-09 | 1981-02-25 | Johnston Construction Limited | Method of lining or relining tunnels and tunnels lined or relined by such a method |
US4917538A (en) * | 1988-04-26 | 1990-04-17 | Shigetoshi Koga | Tunnel lining process and apparatus therefor |
US5263843A (en) * | 1990-07-02 | 1993-11-23 | British Gas Plc | Splittable die used in pipe lining |
US5190705A (en) * | 1990-09-14 | 1993-03-02 | Leo Corazza | Method for lining large-diameter pipes |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3555830A (en) | Concrete wall structure and method | |
US545978A (en) | Lining tunnels | |
CN108867690B (en) | Reverse construction method for pile plate retaining wall of large foundation pit | |
CN106120870A (en) | The advanced enclosed construction of poured band of outer wall of basement and construction method | |
JP6543176B2 (en) | Building method | |
US961492A (en) | Method of constructing piles. | |
CN105370032B (en) | Construction method for air bag type concrete project deformation joint water stop cavity mold | |
KR101468613B1 (en) | Underground structure construction method using the moveable temporary supporting frame | |
CN104120739A (en) | Multi-pilot tunnel excavation one-off arching construction method | |
US887175A (en) | Method of forming foundations. | |
NO121862B (en) | ||
US1053646A (en) | Building construction. | |
US1181212A (en) | Method of constructing pile foundations. | |
JP6307135B2 (en) | Open shield method | |
US885337A (en) | Concrete pile. | |
US822588A (en) | Method of sinking and building concrete piles. | |
JP7444763B2 (en) | Tunnel lining structure and tunnel construction method | |
US411981A (en) | Method of cementing cisterns or wells | |
JP6514739B2 (en) | Construction method for forming underground structure and underground structure completed thereby | |
US918231A (en) | Reinforced-concrete construction. | |
US1480674A (en) | Drilling wells | |
US984491A (en) | Method of constructing concrete buildings. | |
US1372856A (en) | Method of building sewers and tunnels | |
US723307A (en) | Tunnel construction. | |
CN221192982U (en) | Change-over beam bottom support sand box |