[go: up one dir, main page]

US1829463A - Concrete retaining wall - Google Patents

Concrete retaining wall Download PDF

Info

Publication number
US1829463A
US1829463A US474242A US47424230A US1829463A US 1829463 A US1829463 A US 1829463A US 474242 A US474242 A US 474242A US 47424230 A US47424230 A US 47424230A US 1829463 A US1829463 A US 1829463A
Authority
US
United States
Prior art keywords
groove
pile
retaining wall
piles
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US474242A
Inventor
Weber Carl
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHORE LINE BUILDERS Inc
SHORE-LINE BUILDERS Inc
Original Assignee
SHORE LINE BUILDERS Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHORE LINE BUILDERS Inc filed Critical SHORE LINE BUILDERS Inc
Priority to US474242A priority Critical patent/US1829463A/en
Application granted granted Critical
Publication of US1829463A publication Critical patent/US1829463A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles

Definitions

  • the present invention relates to retaining walls of reinforced concrete, such as are used for the retention of earth fills, for shore-line protection, for the core-walls of levees, dams, and for similar purposes.
  • the object of the invention is to provide improved means for the construction of such walls, and an improved method of assembling said means, whereby the completed wall is an impervious, practically integral structure, which is also capable of resisting considerable longitudinal tensile stresses, and which can be built without great labor or expense.
  • Fig. l is an elevation of the wall of my invention.
  • Fig. 2 is an end view of the same.
  • Fig. 3 is a cross section on line 33 of Fig.
  • Fig. 4 is an elevation of the reinforcement.
  • F ig.- 5 is a cross section of a slab
  • Fig. 6 is a cross section on line 66 of Fig. 1.
  • the slabs of which the wall is composed are shown at 1; they are of ing the horizontal reinforcement.
  • Each slab has a truncated tongue 4 on one vertical edge and a double dovetail groove 7, 8, in the other vertical edge.
  • the outer portion of the groove has inwardly converging sides 7 to fit the tongue the sides of which are of less length than the sides 7, while the inner portion of the groove has inwardly diverging walls 8, thus giving it the double dovetail shape in cross section.
  • the ends of the expanded metal sheets -3 are spread apart' towards the grooved edge sion to resist shearing stresses.
  • the lower end of the slab on the grooved edge is beveled ofi, as shown at 13, to assist in the driving of the slab, as will be further explained.
  • the expanded metal reinforcement is extended through the face of the tongue so that it will pro ect into the inner portion of the groove of the adjacent slab.
  • the first slab or pile is set up and secured in correct position by means of pile-driving templets, guides and wales, in the usual way, and is then driven to the required depth. Then the next pile is elevated so that its extension 10 can enter the top of the groove in the already driven pile. The second pile is then driven down to place. Its extension 10 cleans out the groove of the driven pile from sand, etc., so that the projecting edge of the expanded metal reinforcement extends into the inner portion of the groove. The proper vertical alinement of each pile, after the first one, is assured by the tongues 4 following down in the outer portion of the". groove of the preceding pile. After a number of piles of the free groove spaces through the small pipe 14. The cement seal is then poured in. For very long piles, pressure grouting may be used. After'the wall is completed in this way, attachments, such as anchors, copings, steps, railings, etc., may be applied.
  • d The normal tongue and groove structure 1s maintained for properly guiding the piles wlithout the use of special guides or temp ets.
  • Walls built in this way often develop longitudinal stresses caused by the settling of lower part of the tongues being extended laterally to the full size of the grooves, and a filling of cement in the grooves above the sald extending parts and surrounding said projecting reinforcement.
  • a retaining wall composed of a plurality of reinforced concrete slab piles, tongued and grooved on their vertical edges to engage each other, the grooves being of double dovetail section and deeper than the tongues so as to leave a free space and the reinforcement extending through the tongues into. said spaces, each tongue having an extension on its lower end of a size to substantially fill said grooves, and a filling of cement in said free spaces embedding the projecting reinforcement.
  • a retaining wall composed of r inforced concrete'slabs, each slab having a g i'o'ove, of
  • hour-glass shape'in cross section in one edge and a tongue, of the shape of the outer part of said groove, on the other edge with the reinforcement pro ecting through its face, the

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

2 Sheets-Sheet CarL VVber;
Oct. 27, 1931. c. WEBER CONCRETE RETAINING WALL Filed Aug. 9. 1930 My I w C. WEBER Oct. 27, 1931.
CONCRET E RETAINING WALL Filed Aug. 9, 1930 2 Sheets-Shee 2 i z i g m A w wwwy Fatentecl Oct. 27, 1931 UNITEDSTATES PATENT OFFICE CARL WEBER, 0F JACKSONVILLE, FLORIDA, ASSIGNOR TO SHORE-LINE BUILDERS, INCH,
OF JACKSONVILLE, FLORIDA, A CORPORATION OF FLORIDA.
CONCRETE RETAINING WALL Application filed August 9, 1930. Serial No. 474,242.
The present invention relates to retaining walls of reinforced concrete, such as are used for the retention of earth fills, for shore-line protection, for the core-walls of levees, dams, and for similar purposes.
The object of the invention is to provide improved means for the construction of such walls, and an improved method of assembling said means, whereby the completed wall is an impervious, practically integral structure, which is also capable of resisting considerable longitudinal tensile stresses, and which can be built without great labor or expense.
I attain this result by the use of reinforced concrete slab piles of special construction, as will now be described with reference to the accompanying drawings, in which,
Fig. l is an elevation of the wall of my invention.
Fig. 2 .is an end view of the same.
Fig. 3 is a cross section on line 33 of Fig.
Fig. 4 is an elevation of the reinforcement.
in one of the slabs.
F ig.- 5 is a cross section of a slab, and
Fig. 6 is a cross section on line 66 of Fig. 1. p
In these views, the slabs of which the wall is composed are shown at 1; they are of ing the horizontal reinforcement.
reinforced concrete, containing vertical rods 2 and sheets of expanded metal 3, constitut Each slab has a truncated tongue 4 on one vertical edge and a double dovetail groove 7, 8, in the other vertical edge. The outer portion of the groove has inwardly converging sides 7 to fit the tongue the sides of which are of less length than the sides 7, while the inner portion of the groove has inwardly diverging walls 8, thus giving it the double dovetail shape in cross section. As shown in Figs. 3 and 6, the ends of the expanded metal sheets -3 are spread apart' towards the grooved edge sion to resist shearing stresses. The lower end of the slab on the grooved edge is beveled ofi, as shown at 13, to assist in the driving of the slab, as will be further explained. 14 represents a small water pipe used to wash out the free space in the grooves before it is grouted or filled with mortar, cement or the like. The expanded metal reinforcement is extended through the face of the tongue so that it will pro ect into the inner portion of the groove of the adjacent slab. The operation of building the wall is as follows:
The first slab or pile is set up and secured in correct position by means of pile-driving templets, guides and wales, in the usual way, and is then driven to the required depth. Then the next pile is elevated so that its extension 10 can enter the top of the groove in the already driven pile. The second pile is then driven down to place. Its extension 10 cleans out the groove of the driven pile from sand, etc., so that the projecting edge of the expanded metal reinforcement extends into the inner portion of the groove. The proper vertical alinement of each pile, after the first one, is assured by the tongues 4 following down in the outer portion of the". groove of the preceding pile. After a number of piles of the free groove spaces through the small pipe 14. The cement seal is then poured in. For very long piles, pressure grouting may be used. After'the wall is completed in this way, attachments, such as anchors, copings, steps, railings, etc., may be applied.
Among the special advantages of the construction described are: d 1. The normal tongue and groove structure 1s maintained for properly guiding the piles wlithout the use of special guides or temp ets.
2. The perfect sealing and locking of the piles is obtained without extra cost by the projection of the reinforcement of one pile into the groove of the'next, whereby the piles form an inseparable unit whole.
3. The self-cleaning feature of the groove of driving the adjoining by the tongue so that soil filling the groove of the driven pile is removed by the operatlon ile, so that the groove is freed from anyo struction which might affect the projecting reinforcement and is ready for the introduction of the sealing mortar or cement.
a It is common practice to build walls of this kind with tongued and grooved sheet piles, but in such cases the tongues and grooves are merely for the purpose of providing guides to aline the piles during the driving operation. Attempts have also been made to grout the grooves in such walls to seal the joints, but this did not form an interlock. In many cases the gulde tongues have been omitted in order to provide a grouted joint of sufficient size, with the result that I claim is:
temporary pile-driven guides must be used,
thereby greatly increasing the expense. Walls built in this way often develop longitudinal stresses caused by the settling of lower part of the tongues being extended laterally to the full size of the grooves, and a filling of cement in the grooves above the sald extending parts and surrounding said projecting reinforcement. v
Signed at Jacksonville, in the county of Duval and State of Florida, this 28th day of July, A. D. 1930.
CARL WEBER.
the backfill, soft ground, loss of foreshore,
or even by normal backfill and surcharge pressures, temperature changes and the like. To avoid these defects, combination concrete and metal piles have been used, the metal parts forming the joints or interlocks, but
such piles are too costly. The common form of such interlocking joints is one between sheet steel piles or rolled structural. shapes, embedded in the concrete to prevent rusting;
By beveling off the grooved edges at their lower ends, as shown at 13, the pile being driven is crowded over towards the pile already driven, so as wto keep the tongue and groove in engagement.
Having thus described my invention, what 2. A retaining wall composed of a plurality of reinforced concrete slab piles, tongued and grooved on their vertical edges to engage each other, the grooves being of double dovetail section and deeper than the tongues so as to leave a free space and the reinforcement extending through the tongues into. said spaces, each tongue having an extension on its lower end of a size to substantially fill said grooves, and a filling of cement in said free spaces embedding the projecting reinforcement.
3. A retaining wall composed of r inforced concrete'slabs, each slab having a g i'o'ove, of
. hour-glass shape'in cross section, in one edge and a tongue, of the shape of the outer part of said groove, on the other edge with the reinforcement pro ecting through its face, the
US474242A 1930-08-09 1930-08-09 Concrete retaining wall Expired - Lifetime US1829463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US474242A US1829463A (en) 1930-08-09 1930-08-09 Concrete retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US474242A US1829463A (en) 1930-08-09 1930-08-09 Concrete retaining wall

Publications (1)

Publication Number Publication Date
US1829463A true US1829463A (en) 1931-10-27

Family

ID=23882743

Family Applications (1)

Application Number Title Priority Date Filing Date
US474242A Expired - Lifetime US1829463A (en) 1930-08-09 1930-08-09 Concrete retaining wall

Country Status (1)

Country Link
US (1) US1829463A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2539670A (en) * 1945-09-25 1951-01-30 Ognibene Tito Method for the construction of a cutoff wall
US3197964A (en) * 1959-12-24 1965-08-03 Fehlmann Method for making a reinforced concrete structure
US10138616B2 (en) * 2016-08-12 2018-11-27 Wuhan Zhihe Geotechnical Engineering Co., Ltd. Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2539670A (en) * 1945-09-25 1951-01-30 Ognibene Tito Method for the construction of a cutoff wall
US3197964A (en) * 1959-12-24 1965-08-03 Fehlmann Method for making a reinforced concrete structure
US10138616B2 (en) * 2016-08-12 2018-11-27 Wuhan Zhihe Geotechnical Engineering Co., Ltd. Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure

Similar Documents

Publication Publication Date Title
CN109555540B (en) Tunnel form prestressed pipe curtain structure and construction method
US3226933A (en) Sheeting wall system and method of constructing same
US3226935A (en) Retaining wall and method of constructing same
CN112324458B (en) A repair construction method for a pierced segment of a shield tunnel adjacent to a power transmission tower
KR102431393B1 (en) Construction Method of Underground Structures
CN113550321A (en) Prestressed PC construction method combined steel pipe pile foundation pit supporting structure and construction method thereof
CN111676982A (en) A kind of cement-soil retaining wall-prefabricated pile cantilever combined support
CN109555535A (en) The purlin Xia Lu form prestressed pipe curtain structure and construction method
US1747038A (en) Retaining wall
CN106193120B (en) Basement is encorbelmented, and bottom plate is inverse to make structure and construction method
KR20210090101A (en) Integrated slurry wall construction structure and method using pouring blocking device and extension rebar, and construction device thereof
KR20220030686A (en) Construction method and construction structure of water expansion index to prevent leakage of underground continuous wall
US1829463A (en) Concrete retaining wall
CN106978814A (en) A kind of Fabricated Structure for Support of Excavation
CN110158542A (en) The Lossless connection structure and construction method of cut-pff wall and nut cap concrete
CN105113513A (en) Anti-seepage foundation pit supporting structure and construction method
CN102296620B (en) Curtain water-stop slope wall and construction method thereof
CN112709243A (en) Construction method of lock catch steel pipe pile cofferdam bearing platform
EP0258324B1 (en) Process for restoring channels threatening to collapse, in particular profiled channels
CN116607562A (en) Grouting sheet stone retaining wall body grouting reinforcement structure and construction method thereof
CN107090834A (en) A kind of construction method of Fabricated Structure for Support of Excavation
CN108457303A (en) A method of increasing underground parking newly under existing building
CN115012947A (en) Reverse method prefabricated shaft and its construction method
CN210857186U (en) Prestressed U-shaped sheet pile
US1474195A (en) Sheet-piling wall and method of installing same