US1829463A - Concrete retaining wall - Google Patents
Concrete retaining wall Download PDFInfo
- Publication number
- US1829463A US1829463A US474242A US47424230A US1829463A US 1829463 A US1829463 A US 1829463A US 474242 A US474242 A US 474242A US 47424230 A US47424230 A US 47424230A US 1829463 A US1829463 A US 1829463A
- Authority
- US
- United States
- Prior art keywords
- groove
- pile
- retaining wall
- piles
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/14—Sealing joints between adjacent sheet piles
Definitions
- the present invention relates to retaining walls of reinforced concrete, such as are used for the retention of earth fills, for shore-line protection, for the core-walls of levees, dams, and for similar purposes.
- the object of the invention is to provide improved means for the construction of such walls, and an improved method of assembling said means, whereby the completed wall is an impervious, practically integral structure, which is also capable of resisting considerable longitudinal tensile stresses, and which can be built without great labor or expense.
- Fig. l is an elevation of the wall of my invention.
- Fig. 2 is an end view of the same.
- Fig. 3 is a cross section on line 33 of Fig.
- Fig. 4 is an elevation of the reinforcement.
- F ig.- 5 is a cross section of a slab
- Fig. 6 is a cross section on line 66 of Fig. 1.
- the slabs of which the wall is composed are shown at 1; they are of ing the horizontal reinforcement.
- Each slab has a truncated tongue 4 on one vertical edge and a double dovetail groove 7, 8, in the other vertical edge.
- the outer portion of the groove has inwardly converging sides 7 to fit the tongue the sides of which are of less length than the sides 7, while the inner portion of the groove has inwardly diverging walls 8, thus giving it the double dovetail shape in cross section.
- the ends of the expanded metal sheets -3 are spread apart' towards the grooved edge sion to resist shearing stresses.
- the lower end of the slab on the grooved edge is beveled ofi, as shown at 13, to assist in the driving of the slab, as will be further explained.
- the expanded metal reinforcement is extended through the face of the tongue so that it will pro ect into the inner portion of the groove of the adjacent slab.
- the first slab or pile is set up and secured in correct position by means of pile-driving templets, guides and wales, in the usual way, and is then driven to the required depth. Then the next pile is elevated so that its extension 10 can enter the top of the groove in the already driven pile. The second pile is then driven down to place. Its extension 10 cleans out the groove of the driven pile from sand, etc., so that the projecting edge of the expanded metal reinforcement extends into the inner portion of the groove. The proper vertical alinement of each pile, after the first one, is assured by the tongues 4 following down in the outer portion of the". groove of the preceding pile. After a number of piles of the free groove spaces through the small pipe 14. The cement seal is then poured in. For very long piles, pressure grouting may be used. After'the wall is completed in this way, attachments, such as anchors, copings, steps, railings, etc., may be applied.
- d The normal tongue and groove structure 1s maintained for properly guiding the piles wlithout the use of special guides or temp ets.
- Walls built in this way often develop longitudinal stresses caused by the settling of lower part of the tongues being extended laterally to the full size of the grooves, and a filling of cement in the grooves above the sald extending parts and surrounding said projecting reinforcement.
- a retaining wall composed of a plurality of reinforced concrete slab piles, tongued and grooved on their vertical edges to engage each other, the grooves being of double dovetail section and deeper than the tongues so as to leave a free space and the reinforcement extending through the tongues into. said spaces, each tongue having an extension on its lower end of a size to substantially fill said grooves, and a filling of cement in said free spaces embedding the projecting reinforcement.
- a retaining wall composed of r inforced concrete'slabs, each slab having a g i'o'ove, of
- hour-glass shape'in cross section in one edge and a tongue, of the shape of the outer part of said groove, on the other edge with the reinforcement pro ecting through its face, the
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
2 Sheets-Sheet CarL VVber;
Oct. 27, 1931. c. WEBER CONCRETE RETAINING WALL Filed Aug. 9. 1930 My I w C. WEBER Oct. 27, 1931.
CONCRET E RETAINING WALL Filed Aug. 9, 1930 2 Sheets-Shee 2 i z i g m A w wwwy Fatentecl Oct. 27, 1931 UNITEDSTATES PATENT OFFICE CARL WEBER, 0F JACKSONVILLE, FLORIDA, ASSIGNOR TO SHORE-LINE BUILDERS, INCH,
OF JACKSONVILLE, FLORIDA, A CORPORATION OF FLORIDA.
CONCRETE RETAINING WALL Application filed August 9, 1930. Serial No. 474,242.
The present invention relates to retaining walls of reinforced concrete, such as are used for the retention of earth fills, for shore-line protection, for the core-walls of levees, dams, and for similar purposes.
The object of the invention is to provide improved means for the construction of such walls, and an improved method of assembling said means, whereby the completed wall is an impervious, practically integral structure, which is also capable of resisting considerable longitudinal tensile stresses, and which can be built without great labor or expense.
I attain this result by the use of reinforced concrete slab piles of special construction, as will now be described with reference to the accompanying drawings, in which,
Fig. l is an elevation of the wall of my invention.
Fig. 2 .is an end view of the same.
Fig. 3 is a cross section on line 33 of Fig.
Fig. 4 is an elevation of the reinforcement.
in one of the slabs.
F ig.- 5 is a cross section of a slab, and
Fig. 6 is a cross section on line 66 of Fig. 1. p
In these views, the slabs of which the wall is composed are shown at 1; they are of ing the horizontal reinforcement.
reinforced concrete, containing vertical rods 2 and sheets of expanded metal 3, constitut Each slab has a truncated tongue 4 on one vertical edge and a double dovetail groove 7, 8, in the other vertical edge. The outer portion of the groove has inwardly converging sides 7 to fit the tongue the sides of which are of less length than the sides 7, while the inner portion of the groove has inwardly diverging walls 8, thus giving it the double dovetail shape in cross section. As shown in Figs. 3 and 6, the ends of the expanded metal sheets -3 are spread apart' towards the grooved edge sion to resist shearing stresses. The lower end of the slab on the grooved edge is beveled ofi, as shown at 13, to assist in the driving of the slab, as will be further explained. 14 represents a small water pipe used to wash out the free space in the grooves before it is grouted or filled with mortar, cement or the like. The expanded metal reinforcement is extended through the face of the tongue so that it will pro ect into the inner portion of the groove of the adjacent slab. The operation of building the wall is as follows:
The first slab or pile is set up and secured in correct position by means of pile-driving templets, guides and wales, in the usual way, and is then driven to the required depth. Then the next pile is elevated so that its extension 10 can enter the top of the groove in the already driven pile. The second pile is then driven down to place. Its extension 10 cleans out the groove of the driven pile from sand, etc., so that the projecting edge of the expanded metal reinforcement extends into the inner portion of the groove. The proper vertical alinement of each pile, after the first one, is assured by the tongues 4 following down in the outer portion of the". groove of the preceding pile. After a number of piles of the free groove spaces through the small pipe 14. The cement seal is then poured in. For very long piles, pressure grouting may be used. After'the wall is completed in this way, attachments, such as anchors, copings, steps, railings, etc., may be applied.
Among the special advantages of the construction described are: d 1. The normal tongue and groove structure 1s maintained for properly guiding the piles wlithout the use of special guides or temp ets.
2. The perfect sealing and locking of the piles is obtained without extra cost by the projection of the reinforcement of one pile into the groove of the'next, whereby the piles form an inseparable unit whole.
3. The self-cleaning feature of the groove of driving the adjoining by the tongue so that soil filling the groove of the driven pile is removed by the operatlon ile, so that the groove is freed from anyo struction which might affect the projecting reinforcement and is ready for the introduction of the sealing mortar or cement.
a It is common practice to build walls of this kind with tongued and grooved sheet piles, but in such cases the tongues and grooves are merely for the purpose of providing guides to aline the piles during the driving operation. Attempts have also been made to grout the grooves in such walls to seal the joints, but this did not form an interlock. In many cases the gulde tongues have been omitted in order to provide a grouted joint of sufficient size, with the result that I claim is:
temporary pile-driven guides must be used,
thereby greatly increasing the expense. Walls built in this way often develop longitudinal stresses caused by the settling of lower part of the tongues being extended laterally to the full size of the grooves, and a filling of cement in the grooves above the sald extending parts and surrounding said projecting reinforcement. v
Signed at Jacksonville, in the county of Duval and State of Florida, this 28th day of July, A. D. 1930.
CARL WEBER.
the backfill, soft ground, loss of foreshore,
or even by normal backfill and surcharge pressures, temperature changes and the like. To avoid these defects, combination concrete and metal piles have been used, the metal parts forming the joints or interlocks, but
such piles are too costly. The common form of such interlocking joints is one between sheet steel piles or rolled structural. shapes, embedded in the concrete to prevent rusting;
By beveling off the grooved edges at their lower ends, as shown at 13, the pile being driven is crowded over towards the pile already driven, so as wto keep the tongue and groove in engagement.
Having thus described my invention, what 2. A retaining wall composed of a plurality of reinforced concrete slab piles, tongued and grooved on their vertical edges to engage each other, the grooves being of double dovetail section and deeper than the tongues so as to leave a free space and the reinforcement extending through the tongues into. said spaces, each tongue having an extension on its lower end of a size to substantially fill said grooves, and a filling of cement in said free spaces embedding the projecting reinforcement.
3. A retaining wall composed of r inforced concrete'slabs, each slab having a g i'o'ove, of
. hour-glass shape'in cross section, in one edge and a tongue, of the shape of the outer part of said groove, on the other edge with the reinforcement pro ecting through its face, the
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US474242A US1829463A (en) | 1930-08-09 | 1930-08-09 | Concrete retaining wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US474242A US1829463A (en) | 1930-08-09 | 1930-08-09 | Concrete retaining wall |
Publications (1)
Publication Number | Publication Date |
---|---|
US1829463A true US1829463A (en) | 1931-10-27 |
Family
ID=23882743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US474242A Expired - Lifetime US1829463A (en) | 1930-08-09 | 1930-08-09 | Concrete retaining wall |
Country Status (1)
Country | Link |
---|---|
US (1) | US1829463A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2539670A (en) * | 1945-09-25 | 1951-01-30 | Ognibene Tito | Method for the construction of a cutoff wall |
US3197964A (en) * | 1959-12-24 | 1965-08-03 | Fehlmann | Method for making a reinforced concrete structure |
US10138616B2 (en) * | 2016-08-12 | 2018-11-27 | Wuhan Zhihe Geotechnical Engineering Co., Ltd. | Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure |
-
1930
- 1930-08-09 US US474242A patent/US1829463A/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2539670A (en) * | 1945-09-25 | 1951-01-30 | Ognibene Tito | Method for the construction of a cutoff wall |
US3197964A (en) * | 1959-12-24 | 1965-08-03 | Fehlmann | Method for making a reinforced concrete structure |
US10138616B2 (en) * | 2016-08-12 | 2018-11-27 | Wuhan Zhihe Geotechnical Engineering Co., Ltd. | Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109555540B (en) | Tunnel form prestressed pipe curtain structure and construction method | |
US3226933A (en) | Sheeting wall system and method of constructing same | |
US3226935A (en) | Retaining wall and method of constructing same | |
CN112324458B (en) | A repair construction method for a pierced segment of a shield tunnel adjacent to a power transmission tower | |
KR102431393B1 (en) | Construction Method of Underground Structures | |
CN113550321A (en) | Prestressed PC construction method combined steel pipe pile foundation pit supporting structure and construction method thereof | |
CN111676982A (en) | A kind of cement-soil retaining wall-prefabricated pile cantilever combined support | |
CN109555535A (en) | The purlin Xia Lu form prestressed pipe curtain structure and construction method | |
US1747038A (en) | Retaining wall | |
CN106193120B (en) | Basement is encorbelmented, and bottom plate is inverse to make structure and construction method | |
KR20210090101A (en) | Integrated slurry wall construction structure and method using pouring blocking device and extension rebar, and construction device thereof | |
KR20220030686A (en) | Construction method and construction structure of water expansion index to prevent leakage of underground continuous wall | |
US1829463A (en) | Concrete retaining wall | |
CN106978814A (en) | A kind of Fabricated Structure for Support of Excavation | |
CN110158542A (en) | The Lossless connection structure and construction method of cut-pff wall and nut cap concrete | |
CN105113513A (en) | Anti-seepage foundation pit supporting structure and construction method | |
CN102296620B (en) | Curtain water-stop slope wall and construction method thereof | |
CN112709243A (en) | Construction method of lock catch steel pipe pile cofferdam bearing platform | |
EP0258324B1 (en) | Process for restoring channels threatening to collapse, in particular profiled channels | |
CN116607562A (en) | Grouting sheet stone retaining wall body grouting reinforcement structure and construction method thereof | |
CN107090834A (en) | A kind of construction method of Fabricated Structure for Support of Excavation | |
CN108457303A (en) | A method of increasing underground parking newly under existing building | |
CN115012947A (en) | Reverse method prefabricated shaft and its construction method | |
CN210857186U (en) | Prestressed U-shaped sheet pile | |
US1474195A (en) | Sheet-piling wall and method of installing same |