SU89894A1 - The method of operation of the individual dust preparation system for furnaces of steam boilers and industrial furnaces - Google Patents
The method of operation of the individual dust preparation system for furnaces of steam boilers and industrial furnacesInfo
- Publication number
- SU89894A1 SU89894A1 SU414669A SU414669A SU89894A1 SU 89894 A1 SU89894 A1 SU 89894A1 SU 414669 A SU414669 A SU 414669A SU 414669 A SU414669 A SU 414669A SU 89894 A1 SU89894 A1 SU 89894A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- furnaces
- dust
- preparation system
- fuel
- steam boilers
- Prior art date
Links
Landscapes
- Combustion Of Fluid Fuel (AREA)
Description
npeflMeioN изобретени вл етс способ работы системы индивидуального пылеприготовленн дл топок паровых котлов и промышленных печей.The inventive MeioN of the invention is a method for operating an individual dust-prepared system for boilers and industrial furnaces.
Описываемый способ отличаетс от существующих тем, .что он позвол ет создать запас сухого топлива в промежуточном бункере и тем ускорить растопку котла без .генени мазута, а также дает возможность производить подсыпку сухого топлива по тракту топливоподачи , с целью придани сыпучести сырому топливу. Дл придапи сыпучести сырому топливу поток аэропыли после мельничной установки раздел етс на два потока, из которых один, основной, направл етс непосредственно в основные топливные горелки, а другой, меньший, через циклон в нылевой бункер, с последуюп1,им иснользованием этой пыли по указаппому назначению.The described method differs from the existing topics in that it allows to create a supply of dry fuel in the intermediate bunker and in that way accelerates the kindling of the boiler without fuel oil generation, and also makes it possible to add dry fuel along the fuel supply path in order to give flowability to the raw fuel. To adapt the flowability of the raw fuel, the air flow after the mill installation is divided into two streams, one of which, the main one, is sent directly to the main fuel burners, and the other, smaller, through a cyclone into a hole hopper, followed by this dust purpose.
На чертеже изображена схема системы пылеприготовлени .The drawing shows a diagram of the dust preparation system.
Система индивидуального пылеприготовлени состоит из мельничной устаповки /, основных топливных горелок 2 топки 3, дополнительных горелок 4, циклопа 5, промежуточного бункера 6, пылепитателе 1 7, шнека 8 и вентил тора 9 с соединительными пылепроводами и воздухопроводами.The individual dust preparation system consists of mill installation /, main fuel burners 2 firebox 3, additional burners 4, cyclops 5, intermediate hopper 6, dust picker 1 7, screw 8 and fan 9 with connecting dust pipes and air ducts.
В мельничную установку / входит бункер сырого топлива с питателем, собственно мельница (сепаратор и мельничный вентил тор на чертеже не показаны).The mill installation / includes a raw fuel bunker with a feeder, the mill itself (the separator and the mill fan are not shown in the drawing).
Часть аэросмеси от мельпичной установки / поступает непосредственно в основные горелки 2 топки X а друга часть отсасываетс в циклоп 5 вентил тором 9.Part of the mixture from the mill installation / enters directly into the main burner 2 of the furnace X and the other part is sucked into the cyclop 5 by the fan 9.
Пыль, уловленна циклонолт 5, накапливаетс в промежуточном бункере 6, под которым расположены пыленитатели 7 по числу дополнительных горелок 4. Последние служат дл ускорени растонки котла без применени мазута, дл «подсвеч1нзани ; топки при малых пагрузках.The dust trapped by cyclonets 5 accumulates in the intermediate bunker 6, under which the dust collectors 7 are located according to the number of additional burners 4. The latter serve to accelerate the boiler spout without the use of fuel oil, for backlighting; firebox at small load.
Кроме того, подготовленное топливо в промежуточном бункере 6 служит дл подсыпки сухого тонлива по тракту топливоподачи дл гфедотврап;епн слппанн влажного топлива.In addition, the prepared fuel in the intermediate bunker 6 serves to add dry toning along the fuel supply line for the hydrofluoroprop;
Рециркул ци в пылепроводе 10 осуществл етс в тех случа х, когда количество агента, необходимого дл минимальной вентил ции мельницы , оказываетс больше пропускной способности циклона 5.The recirculation in the dust duct 10 is carried out in cases where the amount of agent required for minimum ventilation of the mill is greater than the throughput of the cyclone 5.
При нормальном эксплуатационном режиме в работе находитс мельнична установка / только с основными горелками 2. . По мере надобности включаютс дополнительные горе.пки 4, питаемые пылЬю из бункера 6 включением в работу питателен 7 и вентил тора 9.Under normal operating conditions, there is a mill installation in operation / only with main burners 2.. As needed, additional mounts 4, powered by dust from the bunker 6, are switched on by switching on the power supply 7 and the fan 9.
При ма,1ых или колеблющихс нагрузках топки, а также при форсировке ее, донолпительные горелки 4 работают непре|)ывно, параллельь о с основными горелками 2.When ma, 1st or oscillating loads of the firebox, as well as when forcing it, donal-burners 4 work continuously, parallel to the main burners 2.
Предмет изобретени Subject invention
Способ работы системы индивидуального пылеприготовлени дл топок паровых котлов и промышленных печей, о т л и ч а ю щ и и с тем, что, с целью обеспечени установки сухим топливом, необходимым при растопке и подсвечивании котла , а также подсыпки его по тракту топливоподачи, дл предотвращени слипани там топлива.The method of operation of the individual dust preparation system for the furnaces of steam boilers and industrial furnaces is necessary in order to provide the plant with dry fuel necessary for heating and lighting the boiler, as well as adding it along the fuel feed path, to prevent fuel sticking there.
Циклон 5, пылепитатели 7 и вентил тор 9 работают непрерывно.Cyclone 5, dust suppressors 7 and fan 9 operate continuously.
При растапливании топки и при 1{аличии соседнего агрегата, паход п 1 ,егос в работе, готова пы.чь от последнего подаетс шнеком 8 в бункер 6 и далее транспортируетс гор чим воздухом в дополнительнь е горелки 4 включением в работу вентил тора 9.When the furnace is melted and at 1 {the presence of a neighboring unit, the pass n. 1, which is in operation, is ready from the latter, is fed by the screw 8 to the bunker 6 and further transported by hot air to the additional burner 4 by switching on the fan 9.
Гор чий воздух в этом режиме также подаетс от соседнего агрегата по коллектору 11.Hot air in this mode is also supplied from a neighboring unit through the manifold 11.
При использовании пыли дл увеличени сыпучести сырого топлива вк.чючаетс в работу циклоп 5, пыль из которого выдаетс на шнек 8 и далее поступает в бункер сырого угл данной установки или соседних с ней.When using dust to increase the flowability of raw fuel, it is poured into the work of the Cyclops 5, the dust from which is delivered to the screw 8 and then enters the raw coal bunker of this installation or its neighbors.
поток аэропыли после мельничной установки раздел етс на два потока , из которых первый, основной, направл етс непосредственно в основные горелки топки, а второй, меньший, через циклон в пылевой бункер, с последующим использованием этой пыли дл растопки, подсвечивани котла, а также подсыпки по тракту топливоподачи.the air stream after the mill installation is divided into two streams, of which the first main stream is directed directly to the main burners of the furnace, and the second, smaller one, through a cyclone into the dust bunker, followed by using this dust for kindling, lighting the boiler, and bedding on the path of the fuel supply.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU414669A SU89894A1 (en) | 1950-03-23 | 1950-03-23 | The method of operation of the individual dust preparation system for furnaces of steam boilers and industrial furnaces |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU414669A SU89894A1 (en) | 1950-03-23 | 1950-03-23 | The method of operation of the individual dust preparation system for furnaces of steam boilers and industrial furnaces |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU762423857A Addition SU650143A2 (en) | 1976-11-23 | 1976-11-23 | Unized distributing device cabinet |
Publications (1)
Publication Number | Publication Date |
---|---|
SU89894A1 true SU89894A1 (en) | 1950-11-30 |
Family
ID=48261041
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU414669A SU89894A1 (en) | 1950-03-23 | 1950-03-23 | The method of operation of the individual dust preparation system for furnaces of steam boilers and industrial furnaces |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU89894A1 (en) |
-
1950
- 1950-03-23 SU SU414669A patent/SU89894A1/en active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209495349U (en) | A kind of biomass molding fuel and coal direct-coupling pulverized coal preparation system | |
CN105864748A (en) | Combined combustion system of chain boiler | |
CN106940026A (en) | Boiler milling system | |
CN102418920B (en) | Circulating fluidized bed power generating boiler capable of blended combustion of industrial waste residues | |
GB384877A (en) | Method of and apparatus for disposing of fly ash of furnaces | |
CN110486717A (en) | It is a kind of to mix the CFB boiler system for burning waste gas and waste liquid | |
SU89894A1 (en) | The method of operation of the individual dust preparation system for furnaces of steam boilers and industrial furnaces | |
CN103206716A (en) | Multi-coal adaptive low NOxCombustion system | |
CN210638067U (en) | Stable combustion energy-saving efficiency-improving system for boiler of thermal power plant | |
US2343895A (en) | Vapor generator | |
CN203586193U (en) | Middle storing bin type hot wind powder feeding and manufacturing system | |
SU1755005A1 (en) | Method of crushed-coal grate firing | |
CN116164294A (en) | Large-scale disposal system and disposal method for coal chemical industry by contact drying gasification slag combustion method | |
CN212869743U (en) | Double-fuel boiler capable of burning pure gas | |
US2856872A (en) | Pulverized coal firing system | |
CN112283734A (en) | A concentrate powder process system for low volatile matter coal kind | |
CN207880824U (en) | A kind of novel fluidization system | |
JP2017058077A (en) | Boiler plant | |
SU86806A2 (en) | Drying and mill system with the discharge of the drying agent into the furnace | |
CN204943457U (en) | Bagasse boiler circulating combustion and smoke evacuation dry dust removal apparatus | |
CN208349287U (en) | A kind of coal chemical industry solid waste utilization of resources system | |
CN105091012B (en) | A kind of vent pulverized coal handling system for lignite germanium-extracting technology | |
US2029296A (en) | Multiple underfeed stoker | |
GB1094441A (en) | Apparatus for the combustion of solid fuel | |
CN205137466U (en) | Rubbish and coal mixing burning boiler |