[go: up one dir, main page]

SU850785A1 - Method of erecting the span structure of a gallery - Google Patents

Method of erecting the span structure of a gallery Download PDF

Info

Publication number
SU850785A1
SU850785A1 SU792834974A SU2834974A SU850785A1 SU 850785 A1 SU850785 A1 SU 850785A1 SU 792834974 A SU792834974 A SU 792834974A SU 2834974 A SU2834974 A SU 2834974A SU 850785 A1 SU850785 A1 SU 850785A1
Authority
SU
USSR - Soviet Union
Prior art keywords
span
superstructure
hinge
support
blocks
Prior art date
Application number
SU792834974A
Other languages
Russian (ru)
Inventor
Анатолий Афанасьевич Иваниченко
Агнесса Михайловна Сащенко
Виталий Трофимович Мусик
Владимир Исаакович Фрейдлин
Original Assignee
Украинский Государственный Ин-Ститут По Проектированию Метал-Лургических Заводов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Украинский Государственный Ин-Ститут По Проектированию Метал-Лургических Заводов filed Critical Украинский Государственный Ин-Ститут По Проектированию Метал-Лургических Заводов
Priority to SU792834974A priority Critical patent/SU850785A1/en
Application granted granted Critical
Publication of SU850785A1 publication Critical patent/SU850785A1/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Bridges Or Land Bridges (AREA)

Description

(54) СПОСОБ МОНТАЖА ПРОЛЕТНОГО СТРОЕНИЯ(54) METHOD OF INSTALLATION OF THE FLIGHT STRUCTURE

ГАЛЕРЕИGALLERIES

1one

Изобретение относитс  к строительству, и может быть использовано при монтаже длинномерных конструкций, преимущественно пролетных строений галерей, над действующими надземными коммуникаци ми или в стесненных услови х действующих предпри тий.The invention relates to the construction, and can be used in the installation of lengthy structures, mainly spans of galleries, over existing overhead communications or in the cramped conditions of existing enterprises.

Известен способ монтажа пролетного строени  моста, включающий сборку пролетного строени  из блоков на сборочной площадке, установку на него крана-противовеса и надвижку пролетного строени  в проектное положение по накаточным пу т м 1.There is a known method of mounting a bridge span, which includes assembling a span of blocks from an assembly site, installing a counterweight crane on it and sliding the span into a design position along the nakatochnym m 1.

Недостатки способа заключаютс  в необходимости выбора соответствующей сборочной площадки, а также в применении т говых устройств и в укладке накаточных путей дл  подвижки пролетного строени , что приводит к повыщению трудоемкости монтажа и невозможности применени  этого способа в стесненнь1х услови х действующего предпри ти .The drawbacks of the method are the need to select an appropriate assembly site, as well as the use of traction devices and laying of nakatochnyh paths for the movement of the span, which leads to an increase in the complexity of installation and the impossibility of applying this method in the constrained conditions of the existing enterprise.

Наиболее близким по технической сущности к предлагаемому  вл етс  способ монтажа пролетного строени  галереи, включающий предварительную сборку пролетного строени  из блоков и установку его на опоры с помощью грузоподъемных средств, причем раскладка блоков и сборка из них пролетного строени  производ т на сборочной площадке между опорами галереи, а подъем собранного пролетного строени  осуществл ют при малой высоте галереи самоходными кранами, а при значительной высоте полиспастами в сочетании с монтажной мачтой 2.The closest in technical essence to the present invention is a method of mounting a gallery span, including pre-assembling a span of blocks and installing it on supports using lifting means, the block layout and assembly of blocks from them being made on the assembly site between gallery supports, and the raising of the assembled span is carried out at low gallery height with self-propelled cranes, and at considerable height, the chain hoists are combined with the mounting tower 2.

Недостатком данного способа  вл етс  также необходимость устройства значительной по площади сборочной площадки, что оказываетс  трудновыполнимым при строительстве галереи над действующими коммуникаци ми и в стесненных услови х действующих предпри тий.The disadvantage of this method is also the need to set up a large area of the assembly site, which turns out to be difficult when building a gallery above existing communications and in the cramped conditions of existing enterprises.

Цель изобретени  - упрощение монтажа при возведении пролетного строени  над действующими надземными коммуникаци ми и в стесненных услови х действующих предпри тий.The purpose of the invention is to simplify installation when erecting a span over existing above-ground communications and in cramped conditions of operating enterprises.

Claims (2)

Указанна  цель достигаетс  тем, что в 20 способе монтажа пролетного строени  галереи , включающем предварительную сборку пролетного строени  из блоков и установку его на опоры с помощью грузоподъемных средств, сборку пролетного строени  из блоков производ т путем вертикального его наращивани  у опоры, на оголовке опоры укрепл ют шарнир и присоедин ют к нему собранное из блоков пролетное строение , после чего производ т установку его на опоры путем поворота вокруг гиарнира. На фиг. 1 изображен монтаж непосредственно перед поворотом пролетного строени ; на фиг. 2 - то же, в процессе поворота и после установки пролетного строени  на опоры. Способ осуществл ют следующим образом . Первоначально у проектной опоры 1 галереи производ т с помощью грузоподъемного средства, например стрелового крана 2, сборку перекрывающего два смежных пролета пролетного строени  3 из блоков, наращиваемого в вертикальном положении . При этом на головке опоры 1 укрепл ют щарпир 4.и к нему присоедин ют собранное пролетное строение. После этого производ т установку пролетного строени  на опоры 1 и 5 путем поворота его вокруг щарнира 4. При этом, если первоначально центр т жести 6 пролетного строени  расположен ниже шарнира, поворот производ т с использование.м стрелового крана 2 путем строповки его к пролетному строению ниже центра т жести. Если же последний расположен выше шарнира 4, то после прохождени  центра т жести пролетного строени  через вертикаль, соедин ющую его с осью шарнира, используют удерживающий полиспаст (не показан), присоединенный к нижней части пролетного строени  и к фундаменту опоры 1. После поворота пролетного строени  3 и установки .на опоры 1 и 5 производ т присоединение его к смежным, уже смонтированным пролетным строени м 7. Предлагаемый способ монтажа пролетного строени  моста не требует значительной по площади сборочной площадки и обеспечивает сравнительно простой монтаж пролетного строени  галереи над действующими надземными коммуникаци ми и в стеснен ных услови х действующих предпри тий. Формула изобретени  Способ монтажа пролетного строени  галереи , включающий предварительную сборку пролетного строени  из блоков и установку его на опоры с помощью трузоподъемных средств, отличающийс  тем, что, с целью упрощени  монтажа при возведении пролетного строени  над действующими надземными коммуникаци ми и в стесненных услови х действующего предпри ти , сборку пролетного строени  из блоков производ т путем вертикального его наращивани  у опоры, на оголовке опоры укрепл ют шарнир и присоедин ют к нему собранное из блоков пролетное строение, после чего производ т установку его на опоры путем поворота вокруг шарнира. Источники информации, прин тые во внимание при экспертизе 1- Авторское свидетельство СССР № 636319, кл. Е 01 D 21/00, 1978. This goal is achieved by the fact that in method 20 of mounting the superstructure of the gallery, which includes pre-assembling the superstructure from blocks and installing it on supports with load-lifting means, assembling the superstructure from blocks is made by raising it vertically at the support; a hinge and a span structure assembled from blocks is attached thereto, after which it is mounted on supports by turning it around a giarni. FIG. 1 shows the assembly immediately before the turn of the span; in fig. 2 - the same in the process of turning and after installation of the span on the supports. The method is carried out as follows. Initially, at the design support 1 of the gallery, a lifting device, such as a jib crane 2, is produced by assembling the span of two adjacent spans 3 of the blocks, built up in a vertical position, overlying two spans. At the same time, on the head of the support 1, the sharpyr 4 is fastened and an assembled span structure is attached to it. After that, the span is installed on the supports 1 and 5 by turning it around the hinge 4. At the same time, if the center of gravity of the 6th span is located below the hinge, the turn is made using the boom crane 2 by slinging it to the span below the center of gravity. If the latter is located above the hinge 4, then after the passage of the center of gravity of the superstructure through the vertical connecting it with the axis of the hinge, a retaining tackle (not shown) connected to the lower part of the superstructure and to the foundation of the support 1 is used. 3 and the installation. On support 1 and 5, it is connected to adjacent, already mounted span structures 7. The proposed method of mounting the bridge span does not require an assembly area of considerable size and provides This is a relatively simple installation of the gallery span over the existing above-ground communications and in the constrained conditions of existing enterprises. Claims The method of installation of the superstructure of the gallery, including pre-assembling the superstructure of the blocks and installing it on supports using lifting means, characterized in that, in order to simplify installation, the superstructure is erected above existing ground communications and in cramped conditions of the existing enterprise Ti, the assembly of the superstructure from the blocks is made by its vertical extension at the support; on the tip of the support they reinforce the hinge and attach to it the assembled from the block in the superstructure, after which it is installed on supports by turning it around the hinge. Sources of information taken into account in the examination of 1- USSR Author's Certificate No. 636319, cl. E 01 D 21/00, 1978. 2. Справочник монтажника стальных конструкций. М., 1959, с. 667, рис. 56, 57 (прототип).2. Handbook installer steel structures. M., 1959, p. 667, fig. 56, 57 (prototype). дзиг. гjig g
SU792834974A 1979-10-31 1979-10-31 Method of erecting the span structure of a gallery SU850785A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU792834974A SU850785A1 (en) 1979-10-31 1979-10-31 Method of erecting the span structure of a gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU792834974A SU850785A1 (en) 1979-10-31 1979-10-31 Method of erecting the span structure of a gallery

Publications (1)

Publication Number Publication Date
SU850785A1 true SU850785A1 (en) 1981-07-30

Family

ID=20857196

Family Applications (1)

Application Number Title Priority Date Filing Date
SU792834974A SU850785A1 (en) 1979-10-31 1979-10-31 Method of erecting the span structure of a gallery

Country Status (1)

Country Link
SU (1) SU850785A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2666164C2 (en) * 2016-05-26 2018-09-06 Александр Николаевич Головин Assembling of bridge spans with the use of hinge
RU2673345C1 (en) * 2017-08-07 2018-11-26 Федеральное государственное казенное военное образовательное учреждение высшего образования "ВОЕННАЯ АКАДЕМИЯ МАТЕРИАЛЬНО-ТЕХНИЧЕСКОГО ОБЕСПЕЧЕНИЯ имени генерала армии А.В. Хрулева" Method of installing bridge span structures of rem-500 metal overhead
CN115095013A (en) * 2022-06-10 2022-09-23 中国建筑第五工程局有限公司 Structure is assembled to high altitude steel construction vestibule

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2666164C2 (en) * 2016-05-26 2018-09-06 Александр Николаевич Головин Assembling of bridge spans with the use of hinge
RU2673345C1 (en) * 2017-08-07 2018-11-26 Федеральное государственное казенное военное образовательное учреждение высшего образования "ВОЕННАЯ АКАДЕМИЯ МАТЕРИАЛЬНО-ТЕХНИЧЕСКОГО ОБЕСПЕЧЕНИЯ имени генерала армии А.В. Хрулева" Method of installing bridge span structures of rem-500 metal overhead
CN115095013A (en) * 2022-06-10 2022-09-23 中国建筑第五工程局有限公司 Structure is assembled to high altitude steel construction vestibule
CN115095013B (en) * 2022-06-10 2024-01-26 中国建筑第五工程局有限公司 Structure is assembled to high altitude steel construction vestibule

Similar Documents

Publication Publication Date Title
CN101476294B (en) Method for mounting lower beam section of large-span steel box girder cable-stayed bridge tower
CN210177371U (en) Cable-stayed cantilever type integrated bridge girder erection machine capable of piling
RU195276U1 (en) CONSOLE CRANE FOR INSTALLING SUPPORT ADJUSTERS ON THE DEPARTURE MORE THAN 18m
SU850785A1 (en) Method of erecting the span structure of a gallery
JPH10195826A (en) Bridge construction method and device thereof
KR200363059Y1 (en) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
JP2014098258A (en) Steel tower assembling/demolition method by stand bar, and device
SU823550A1 (en) Structure erecting method
SU1498698A1 (en) Self-erecting tower crane
RU2130524C1 (en) Guy suspension bridge and method for its erection
SU998683A1 (en) Method of reconstructing a tower crane
RU2768534C1 (en) Method of mounting a permanent quick-erect lightweight support for emergency recovery works on power transmission lines
SU943180A1 (en) Gantry crane erecting method
CN219034610U (en) Combined type foundation pit cat ladder channel
SU964092A1 (en) Method of erecting upper parts of vertical structures
CN109205475A (en) Truss connection beam type door machine assembling and disassembling device and method in tunnel
RU2112121C1 (en) Fixture for mounting of cranes-reloaders of tubular-beam construction
JPH0667511U (en) Electric automatic special support lifting device
SU1330291A1 (en) Arrangement for mounting top sections of vertical structures
SU1218032A1 (en) Arrangement for maintenance working on vertical high-rise buildings
SU591402A1 (en) Mast for erecting tower-type cranes
SU1331823A1 (en) Arrangement for placing power transmission line mast onto foundation
SU912626A1 (en) Tower crane for construction, installation and concreting operations
JPS5851084B2 (en) Construction methods and equipment for main towers such as suspension bridges and cable-stayed bridges
SU1143683A1 (en) Method of mounting single-i-beam travelling crane