[go: up one dir, main page]

SU51519A1 - Method for developing trenches under water - Google Patents

Method for developing trenches under water

Info

Publication number
SU51519A1
SU51519A1 SU90A SU90A SU51519A1 SU 51519 A1 SU51519 A1 SU 51519A1 SU 90 A SU90 A SU 90A SU 90 A SU90 A SU 90A SU 51519 A1 SU51519 A1 SU 51519A1
Authority
SU
USSR - Soviet Union
Prior art keywords
shields
trench
under water
soil
slopes
Prior art date
Application number
SU90A
Other languages
Russian (ru)
Inventor
А.А. Боровик
Original Assignee
А.А. Боровик
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by А.А. Боровик filed Critical А.А. Боровик
Priority to SU90A priority Critical patent/SU51519A1/en
Application granted granted Critical
Publication of SU51519A1 publication Critical patent/SU51519A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Description

Откосы песчаного грунта держатс  в воде под небольшим углом (26-28) и при текучей воде скоро размываютс ; поэтому в случае выемки траншеи в дне из песчаного грунта приходитс  давать траншее весьма пологие откосы.The slopes of the sandy soil are kept in water at a slight angle (26-28) and are rapidly washed out with flowing water; therefore, in the case of excavating a trench in the bottom of sandy soil, a trench has to be provided with very gentle slopes.

Чтобы удержать откосы песчаного грунта под водой под большим углом и защитить их временно от размыва, согласно предлагаемому способу, на дчо водоема по сторонам намеченной к разработке траншеи укладывают т желые ш,иты из железных балок. Нагрузка на откосе от ш,итов увеличивает устойчивость откоса, причем дл  устранени  возможности оползани  самих ш,итов верхние кра  их прив зывают к сва м или другим анкерным средствам , забитым вне призмы обрушени . Выемку грунта производ т между щитами, постепенно опускаюш,имис  на откосы. Дополнительна  призма грунта, удерживаемого щитами выше угла естественного откоса, определ етс  из услови  равновеси  щитов относительно оси поворота, проход щей через точку О (фиг. 1), т. е. верхнего кра .In order to keep the slopes of the sandy soil under water at a large angle and protect them temporarily from erosion, according to the proposed method, heavy w, ity from iron beams are laid on the pond dcho on the sides of the trench to be developed. The load on the slope from w, itov increases the stability of the slope, and, to eliminate the possibility of creeping themselves w, itov their upper edges bind to the pile or other anchoring means, clogged outside the prism of the collapse. Excavation is made between the shields, gradually lowering, imis on the slopes. The additional prism of the soil held by the shields above the angle of repose is determined from the condition of the balance of the shields relative to the axis of rotation passing through point O (Fig. 1), i.e. the upper edge.

На чертеже фиг. 1 изображает схему , по сн ющую теоретические обосновани  предлагаемого способа; фиг. 2 и 3-устройство щитов (в двух взаимно перпендикул рных разрезах); фиг. 4 и 5-схему разработки траншеи (поперечный разрез и вид сверху).In FIG. 1 shows a diagram explaining the theoretical justification of the proposed method; FIG. 2 and 3 device shields (in two mutually perpendicular cuts); FIG. 4 and 5 is a trench development scheme (cross section and top view).

Укладываемые по сторонам предполагаемой траншеи на дно водоема щиты состо т из соединенных между собою балок / (фиг. 2 и 3) в группы по 5-б штук. На концах балок / имеютс  отверсти  дл  болтов и кажда  группа балок св зана по концамShields stacked on the sides of the intended trench to the bottom of the reservoir consist of beams connected together (Fig. 2 and 3) in groups of 5-b pieces. At the ends of the beams / there are holes for the bolts and each group of beams is connected at the ends

короткими поперечными балками с прокладками 2 из досок. Щиты 3short transverse beams with gaskets 2 of the boards. Shields 3

укладывают на дно водоема до приступа к выемке грунта дл  траншеи, причем грунт вынимаетс  из пространства , оставл емого между двум  щитами по оси траншеи. При выемке грунта щиты 3 (фиг. 4) опускаютс  на образуемые откосы от оползани  грунта и прикрывают их.placed on the bottom of the reservoir before the attack to excavate the soil for the trench, and the soil is removed from the space left between the two shields along the axis of the trench. When excavating, the shields 3 (Fig. 4) are lowered onto the formed slopes from the soil slide and cover them.

Можно также укладывать щиты на готовые откосы, когда они еще недостаточно крутые, т. е. сначала производить выемку грунта до неполной глубины и продолжать дальнейшую выемку грунта между щитами по оси траншеи до требуемой глубины. Щиты 3 при этом будут опускатьс  иYou can also lay the shields on the finished slopes when they are still not steep enough, i.e., first excavate to incomplete depth and continue further excavation between the shields along the trench axis to the required depth. The shields 3 will be lowered and

образуют углы, большие угла естественного откоса f, причем верхний их край прив зываетс  к сва м 4. После укладки в готовую траншею секций труб или тоннел  ш,иты 3 поднимаютс  и используютс  на соседнем участке траншеи.they form angles greater than the angle of repose f, and their upper edge is attached to the pile 4. After the pipe sections or tunnel w are installed in the finished trench, they 3 are lifted and used in the next section of the trench.

При весе грунта (песка) в воде Я ПООл:г и угле его естественного откоса J 26°, задава сь нагрузкой/ от щитов (фиг. 1), можно определитьWith the weight of the soil (sand) in the water I POOL: g and the angle of its repose J 26 °, given by the load / from the shields (Fig. 1), one can determine

углы X дл  различных глубин Н из рассмотрени  условий равновеси  щитов относительно оси поворота кх (фиг. 1). Величина X пропорциоangles X for different depths H from consideration of the equilibrium conditions of the shields relative to the axis of rotation kx (Fig. 1). X is proportional to

I нальна нагрузке р и обратно порцкональна //.I nn load p and vice versa // /.

Гезультаты подсчета, произведенного автором дл  случаев, чаще встре; чающихс  в практике, т. е. дл  глуI бины от 8 до 14 м, приведены в нижеI следующей таблице:The results of the calculation made by the author for cases, more often by meeting; in practice, i.e. for depth from 8 to 14 m, are given in the following table below:

Предмет изобретени .The subject matter of the invention.

Claims (2)

1. Способ разработки траншей под водой, отличающийс  тем, что по сторонам предполагаемой траншеи на дно водоема укладывают т желые щиты, прив зыва  их к сва м или другим анкерным средствам, и производ т выемку грунта между этими щитами с целью увеличени  угла откосов траншеи благодар  пригрузке1. A method of developing trenches under water, characterized in that heavy shields are laid on the sides of the supposed trench, leading them to their own or other anchoring means, and excavating between these shields to increase the angle of slope of the trench thanks to loading щитов, опускающихс  на откосы по мере выемки грунта.shields, descending on the slopes as the excavation. 2. Прием осуществлени  способа по п. 1, отличающийс  тем, что сначала производ т выемку грунта до неполной глубины, а затем укладывают щиты на откось выемки и продолжают далы-1ейшую выемку грунта между щитами до необходимой глубины траншеи.2. Acceptance of the method according to claim 1, characterized in that the soil is first excavated to an incomplete depth, and then the shields are laid on the slope of the excavation and the dredging continues between the shields to the desired trench depth. к авторскому свидетельству А. А. Боровикto the author's testimony A. A. Borovik № 51519 No. 51519 фиг. 2FIG. 2 -- - -о,-- - -about,
SU90A 1936-11-25 1936-11-25 Method for developing trenches under water SU51519A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU90A SU51519A1 (en) 1936-11-25 1936-11-25 Method for developing trenches under water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU90A SU51519A1 (en) 1936-11-25 1936-11-25 Method for developing trenches under water

Publications (1)

Publication Number Publication Date
SU51519A1 true SU51519A1 (en) 1936-11-30

Family

ID=51965420

Family Applications (1)

Application Number Title Priority Date Filing Date
SU90A SU51519A1 (en) 1936-11-25 1936-11-25 Method for developing trenches under water

Country Status (1)

Country Link
SU (1) SU51519A1 (en)

Similar Documents

Publication Publication Date Title
SU51519A1 (en) Method for developing trenches under water
CN204875807U (en) Bridge main pier cushion cap foundation pit supporting structure on river channel abrupt slope basement rock
VINER BRADY FOLKESTONE WARREN LANDSLIPS: REMEDIAL MEASURES, 1948-1954.
Kennard et al. SELSET RESERVOIR: DESIGN AND CONSTRUCTION.
US2338110A (en) Graving dry dock and method of construction
RU2791119C1 (en) Method for construction of geotechnical structures in the water area of urban rivers and canals
US4662780A (en) Method for docking of a floating structure
US1884347A (en) Subterraneous masonry structure and method of making the same
Muirhead THE STABILIZING OF A QUAY-WALL.
SU123471A1 (en) Vyborna Embankment
SU1142580A1 (en) Method of constructing a cellular dam
BOSTOCK et al. CORRESPONDENCE ON 5222. REMODELLING OF THE ASSIUT BARRAGE, EGYPT.
DU PLAT TAYLOR EXTENSIONS AT TILBURY DOCKS 1912-1917.(INCLUDES APPENDIX AND PLATE AT BACK OF VOLUME).
Wallace et al. Trombay power station: cooling water system
BAGSHAWE et al. CORRESPONDENCE. THE KIDDERPUR DOCKS.
PEARSON THE CONSTRUCTION AND SINKING OF MONOLITHS AT KING GEORGE'S DOCK, CALCUTTA.(INCLUDES PLATE AT BACK OF VOLUME).
Basha et al. Construction of Ameria caisson in Egypt
HOLDEN et al. CORRESPONDENCE. THE NAG HAMMADI BARRAGE, UPPER EGYPT.
SU727766A1 (en) Retaining wall and method of erecting same
Brown et al. Design and sinking of a large concrete caisson at the Huntly Power Project
McIldowie THE CONSTRUCTION OF THE SILENT VALLEY RESERVOIR, BELFAST WATER-SUPPLY (INCLUDES APPENDICES AND PLATE AT BACK OF VOLUME).
MCLAREN Interlocking steel sheet piling for temporary dams at Grimsby
HAIGH THE EMERSON BARRAGE.
Ridehalgh THE RECONSTRUCTION OF GREENWELL'S NO. 1 DRY DOCK AND ANCILLARY WORKS AT SUNDERLAND.
Geuss Box Canyon Hydroelectric Project