SU1705472A1 - Forms for erecting asphalt-concrete core wall in earth dam - Google Patents

Forms for erecting asphalt-concrete core wall in earth dam Download PDF

Info

Publication number
SU1705472A1
SU1705472A1 SU904779322A SU4779322A SU1705472A1 SU 1705472 A1 SU1705472 A1 SU 1705472A1 SU 904779322 A SU904779322 A SU 904779322A SU 4779322 A SU4779322 A SU 4779322A SU 1705472 A1 SU1705472 A1 SU 1705472A1
Authority
SU
USSR - Soviet Union
Prior art keywords
asphalt
formwork
erecting
diaphragm
boards
Prior art date
Application number
SU904779322A
Other languages
Russian (ru)
Inventor
Сергей Васильевич Гаврилов
Анатолий Абрамович Равкин
Вячеслав Михайлович Давиденко
Original Assignee
Всесоюзный научно-исследовательский институт гидротехники им.Б.Е.Веденеева
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный научно-исследовательский институт гидротехники им.Б.Е.Веденеева filed Critical Всесоюзный научно-исследовательский институт гидротехники им.Б.Е.Веденеева
Priority to SU904779322A priority Critical patent/SU1705472A1/en
Application granted granted Critical
Publication of SU1705472A1 publication Critical patent/SU1705472A1/en

Links

Landscapes

  • Revetment (AREA)

Abstract

Изобретение относитс  к строительству и может быть использовано дл  возведени  асфальтобетонных диафрагм о грунтовых плотинах. Цел ь изобретени  - повышение про- тивофильтрационной надежности диафрагмы и примыкающих к ней слоев каменной наброски. Опалубка включает опалубочные щиты 1 и 2,соединенные между собой перемычками 3 с открылками 4. К боковым поверхност м щитов креп тс  направл ющие элементы со свободно перемещающимис  вверх или вниз фиксаторными штыр ми. Щиты выполн ют с вертикальными щел ми по всей их длине. При этом образуетс  гребенчатый профиль, позвол ющий достичь наилучшие услови  пропитки асфальтобетоном каменной наброски, расположенной по боковым сторонам диафрагмы. 5 ил. (Л СThe invention relates to the construction and can be used for the construction of asphalt diaphragms on earthen dams. The purpose of the invention is to increase the anti-filtration reliability of the diaphragm and the adjacent layers of ripling. The formwork includes formwork boards 1 and 2 interconnected by jumpers 3 with wing 4. Guiding elements are attached to the side surfaces of the boards with free-moving pins that move up or down. The shields are provided with vertical slots along their entire length. In this case, a comb profile is formed, which allows to achieve the best conditions for the impregnation of asphalt concrete with a rough layer located on the sides of the diaphragm. 5 il. (Ls

Description

Изобретение относитс  к строительству и предназначено дл  создани  элементов типа диафрагм в каменной наброске грунтовых плотин.The invention relates to the construction and is intended to create elements such as diaphragms in the sketching of earth dams.

Цель изобретени  - повышение проти- вофильтрационной надежности диафрагмы и примыкающих к ней слоев каменной наброски .The purpose of the invention is to increase the anti-filtration reliability of the diaphragm and the adjacent layers of ripling.

На фиг.1 показан общий вид опалубки; на фиг.2 - то же, вид сверху; на фиг.З - фрагмент общего вида в увеличенном масштабе; на фиг.4 - разрез по А-А на фиг.2; на фиг.5 - вариант опалубки при односторонней пропитке по разрезу А-А фиг.2 (а - - установка опалубки; б L заливка раствора; в - окончание работы).Figure 1 shows a general view of the formwork; figure 2 is the same, top view; fig.Z - fragment of a general form on an enlarged scale; figure 4 is a section along aa in figure 2; figure 5 is a variant of the formwork with one-sided impregnation along the section A-A of figure 2 (a - setting formwork; b L pouring mortar; c - ending work).

Опалубка включает опалубочные щиты 1 и 2, объединенные перемычками 3 с открылками 4. К боковым наружным поверхност м щитов прикреплены направл ющиеThe formwork includes formwork boards 1 and 2, connected by bridges 3 with wing-pieces 4. Guides are attached to the side outer surfaces of the boards.

элементы 5, внутри которых перемещаютс  фиксаторные штыри 6. Щиты имеют гребенчатый профиль, рассто ние между зубь ми 7 которых выполнено из услови , что оно не превышает средний размер фракции 8 каменной наброски.elements 5, inside of which the locking pins 6 move. The shields have a comb-shaped profile, the distance between the teeth 7 of which is made on the condition that it does not exceed the average size of fraction 8 of the rough draft.

Конструкци  опалубки дл  возведени  асфальтобетонной диафрагмы в грунтовой плотине работает следующим оСфэзом.The construction of the formwork for erecting an asphalt diaphragm in a dirt dam works as follows.

Опалубка устанавливаетс  в заданное место по проектной оси (или на предыдущий  рус диафрагмы) и фиксируетс  в требуемом положении штыр ми б путем заглублени  их в каменной наброске 8. Далее опалубка обсыпаетс  снаружи камнем, поры которого должны быть пропитаны асфальтобетоном .The formwork is installed at a predetermined location along the design axis (or on the previous diaphragm shaft) and fixed in position by the pins b by digging them into the stone drawing 8. Next, the formwork is covered with stone outside, the pores of which should be impregnated with asphalt concrete.

Заливка смеси производитс  сверху в опалубку и в слой камн . При этом смесь одновременно проникает в пустоты камеи3The mixture is poured from above into the formwork and into the stone layer. At the same time, the mixture simultaneously penetrates into the emptiness of cameos3

елate

{ь VJ{VJ

ii

ЬB

ной наброски сверху, сбоку по всей высоте сло  со стороны опалубки. При этом, во- первых, смесь затекает в наброску с двух сторон одновременно; во-вторых, происходит лучший прогрев поверхностей кам- н , вследствие чего замедл етс  процесс остывани  смеси, проход щей между камн ми .Novel sketches from top, side along the entire height of the layer from the side of the formwork. In this case, firstly, the mixture flows into the draft from both sides simultaneously; secondly, the best heating of the stone surfaces occurs, as a result of which the process of cooling the mixture passing between the stones slows down.

Заливка производитс  до прекращени  просачивани  асфальтобетона в камень, на всю высоту сло  каменной наброски. Затем опалубка извлекаетс  вверх.Fillings are made before the asphalt concrete seeps into the stone, to the entire height of the layer of riprap. The formwork is then removed upwards.

После удалени  опалубки образуетс  диафрагма в виде прослойки из асфальтобетонной смеси с противофильтрационным слоем в каменной наброске.After removal of the formwork, a diaphragm is formed in the form of a layer of asphalt-concrete mix with an antifiltration layer in a rock layer.

Таким образом, повышаетс  степень заполнени  пустот в наброске камн  устраиваемой диафрагмы. Полнотела  сплошна  прослойка асфальтобетона гарантирует полную водонепроницаемость диафрагмы вThus, the degree of filling of voids in the sketching of the stone of the arranged diaphragm increases. Full body solid layer of asphalt concrete ensures complete water resistance of the diaphragm in

процессе эксплуатации, а также в случае просадок тела плотины и образовани  трещин , гарантируетс  их постепенным отжа- тием асфальта из прослойки,operation, as well as in the case of subsidence of the dam body and the formation of cracks, is guaranteed by their gradual release of asphalt from the layer,

Такой процесс заполнени  пустот, обеспечиваемый предлагаемой опалубкой, позвол ет увеличить высоту пропитки.Such a process of filling the voids provided by the proposed formwork allows increasing the height of the impregnation.

Claims (1)

Формула изобретени  Опалубка дл  возведени  асфальтобетонной диафрагмы в грунтовой плотине, включающа  опалубочные щиты, соединенные перемычками и имеющие вертикальные щели, отличающа с  тем, что, с целью повышени  противофильтрационной надежности диафрагмы и примыкающих к ней слоев каменной наброски, щели в щитах выполнены по всей их длине с образованием гребенчатого профил  из зубьев с шириной и шагом расположени  зубьев не более среднего размера камн  наброски.The claims formwork for erecting asphalt aperture earth dam comprising shuttering panels connected by webs and having a vertical slit, characterized in that, in order to increase impervious diaphragm reliability and adjoining layers riprap slots in the boards are made over their entire length with the formation of a comb profile of the teeth with a width and spacing of the teeth no more than an average size of the stone outline. Ј-cbЈ-cb Фиг,FIG иand Фиг.ЗFig.Z 17054721705472 А-АAa аbut вat //
SU904779322A 1990-01-09 1990-01-09 Forms for erecting asphalt-concrete core wall in earth dam SU1705472A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU904779322A SU1705472A1 (en) 1990-01-09 1990-01-09 Forms for erecting asphalt-concrete core wall in earth dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU904779322A SU1705472A1 (en) 1990-01-09 1990-01-09 Forms for erecting asphalt-concrete core wall in earth dam

Publications (1)

Publication Number Publication Date
SU1705472A1 true SU1705472A1 (en) 1992-01-15

Family

ID=21490017

Family Applications (1)

Application Number Title Priority Date Filing Date
SU904779322A SU1705472A1 (en) 1990-01-09 1990-01-09 Forms for erecting asphalt-concrete core wall in earth dam

Country Status (1)

Country Link
SU (1) SU1705472A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Борисов Г.В., Успенский В.В., Фесик В.А. Опыт подготовки и строительства асфальтобетонной грунтовой плотины, Гидротехническое строительство, 1981, № 11, с.31-32. Авторское свидетельство СССР N: 1460114, кл. Е 02 В 3/16, 1988. *

Similar Documents

Publication Publication Date Title
US4697955A (en) Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works
CN109487803B (en) A kind of prefabricated skeleton slope protection and construction method thereof
CH615236A5 (en)
KR20210119861A (en) Slurry wall, construction method for the same and wire mesh assembly
SU1705472A1 (en) Forms for erecting asphalt-concrete core wall in earth dam
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
DE1811682C3 (en) Lost formwork for a retaining wall
US2352338A (en) Building structure for insulation against insects
DE621902C (en) Process for the production of concrete bodies under water
KR102426192B1 (en) File fof retaining wall and construction method using file
EP1103663B1 (en) Pile wall capping
KR102371284B1 (en) Slurry wall, construction method for the same and wire mesh assembly
CN208105090U (en) A kind of friction pile bottom ponding culvert
DE2259462C3 (en) Process for the production of a structure in the groundwater and crossbeams for the implementation of the process
SU1004537A1 (en) Method of constructing a structure in soil
SU1502690A1 (en) Prefabricated dam
US2083593A (en) Method of making protected piling
US2337378A (en) Method of making piers
RU18718U1 (en) VERTICAL TAPE BASE
SU1527369A1 (en) Prefabricated dam
JP2524579B2 (en) Reinforcement method of existing retaining wall under water surface
SU1483007A1 (en) Method of constructing concrete dam
AT319544B (en) Prefabricated strips, preferably for ceilings and methods for producing a prefabricated strip
SU1337456A1 (en) Embankment
SU484278A1 (en) Facing ground slopes of hydraulic structures