[go: up one dir, main page]

SU1652592A1 - Method for supporting mine workings - Google Patents

Method for supporting mine workings Download PDF

Info

Publication number
SU1652592A1
SU1652592A1 SU894708137A SU4708137A SU1652592A1 SU 1652592 A1 SU1652592 A1 SU 1652592A1 SU 894708137 A SU894708137 A SU 894708137A SU 4708137 A SU4708137 A SU 4708137A SU 1652592 A1 SU1652592 A1 SU 1652592A1
Authority
SU
USSR - Soviet Union
Prior art keywords
anchors
shanks
anchor
mine
drill
Prior art date
Application number
SU894708137A
Other languages
Russian (ru)
Inventor
Владимир Алексеевич Смирнов
Александр Петрович Белоусов
Владимир Николаевич Рева
Валерий Самуилович Левин
Борис Яковлевич Генкин
Original Assignee
Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела filed Critical Всесоюзный научно-исследовательский институт горной геомеханики и маркшейдерского дела
Priority to SU894708137A priority Critical patent/SU1652592A1/en
Application granted granted Critical
Publication of SU1652592A1 publication Critical patent/SU1652592A1/en

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

Изобретение относитс  к горнодобывающей промышленности и может быть использовано при креплени , выработок в трещиноватых породах с помощью анкеров. Цель - повышение устойчивости выработки. Выработка крепитс  в две очереди. Сначала бур т шпуры, устанавливают в них анкера и загибают их вдоль выработки. Через петли хвостовиков бур т шпуры и устанавливают в них анкера следующего р да. На хвостовики анкеров подвешивают металлическую решетку , Затем в шахматном пор дке по отношению к анкерам первой очереди бур т шпуры и устанавливают в них анкера второй очереди. Их хвостовики загибают в поперечном направлении и прижимают ими решетку к поверхности выработки. Каждый последующий анкер вставл ют в петлю хвостовика предыдущего и сцепл ют между собой . Хвостовик предпоследнего анкера в р ду креп т анкером без хвостовика с помощью опорной плитки и клина. 4 ил. СО СThe invention relates to the mining industry and can be used for fastening workings in fractured rocks using anchors. The goal is to increase the sustainability of production. The production is fastened in two stages. First, drill the holes, install an anchor in them and bend them along the working. Through the loops of the shanks of the drill hole t, the anchors of the next row are installed in them. A metal grid is hung on the shanks of the anchors. Then, in a staggered pattern with respect to the first-turn anchors, drill holes are placed and the second-turn anchors are installed in them. Their shanks are folded in the transverse direction and they press the grate to the surface of the mine. Each subsequent anchor is inserted into the loop of the shank of the previous one and interconnected. The tail of the last but one anchor in the row is secured with a non-shank anchor using a base tile and a wedge. 4 il. WITH S

Description

Изобретение относитс  к горнодобывающей промышленности и может быть использовано при креплении горных выработок в трещиноватых породах дл  укреплени  целиков, бортов карьеров и т.п. с помощью анкеров, преимущественно железобетонных и сталеполимерных.The invention relates to the mining industry and can be used in the fastening of mine workings in fractured rocks to strengthen pillars, pit walls, etc. using anchors, mainly reinforced concrete and steel-polymer.

Цель изобретени  - повышение устойчивости выработки.The purpose of the invention is to increase the sustainability of production.

На фиг.1 показана призабойна  часть выработки, закрепленна  анкерами первой очереди, продольное сечение; на фиг,2 - участок выработки, закрепленный анкерами первой и второй очередей с металлической решеткой и торкрет-бетоном, продольное сечение; на фиг.З - выработка, закрепленна  предлагаемым способом, поперечноеFigure 1 shows the bottom-hole part of the production, fixed with anchors of the first stage, a longitudinal section; Fig, 2 - section of production, secured by anchors of the first and second stages with a metal grille and gunning concrete, longitudinal section; on fig.Z - development, fixed by the proposed method, the transverse

сечение: на фиг.4 - элементы креплени  вдоль выработки.section: in Fig. 4, fastening elements along the working.

Крепление горных выработок осуществл етс  следующим образом.The fastening of mine workings is carried out as follows.

Вслед за подвиганием забо  1 в трещиноватом породном массиве в кровле и боках выработки бур т шпуры, в которые устанавливают короткие анкеры 2 первой очереди с петл ми на концах хвостовиков. Выступающие из шпуров хвостовики 3 анкеров загибают и располагают вдоль выработки по направлению к проходческому забою 1. Через петли хвостовиков 3 установленных анкеров бур т шпуры и в них устанавливают следующий р д анкеров 2, стержни которых при установке пропускают через петли хвостовиков 3 предыдущего р да анкеров 2. Таким образом, крепление выработки довоОFollowing the advancement of the bottom 1 in the fissured rock mass in the roof and sides of the drill hole, into which short anchors 2 of the first stage are installed with loops at the ends of the shanks. The shanks of the anchors protruding from the drill holes are folded and positioned along the working towards the driving face 1. Through the shank loops of the 3 installed anchors, a hole is drilled in them and the next row of anchors 2 are installed in them, the rods of which pass through the last anchor loops 2. Thus, fixing the production dovooO

елate

юYu

СПSP

юYu

hoho

д т до забо  1. Хвостовики 3 последнего р да анкеров 2 креп т у забо  1 временными извлекаемыми анкерами 5, устанавливаемыми в шпуры, пробуренные через петли хвостовиков 3 последнего р да анкеров 2. При установке анкеров 2 дл  загибани  и более плотного прижати  хвостовиков 3 к неровной поверхности выработки примен ют пневмодатчики бурильных молотков.d t to the bottom 1. Shanks 3 of the last row of anchors 2 are secured at the bottom 1 temporary removable anchors 5 installed in holes drilled through the loops of the tailings 3 of the last row of anchors 2. When installing anchors 2 for bending and tighter pressing of the shanks 3 air sensors of boring hammers are applied to the uneven surface of the mine.

Загибание хвостовиков 3 анкеров 2 можно производить в механической мастерской в процессе их изготовлени .The bending of the shanks 3 of the anchors 2 can be performed in the machine shop during their manufacture.

Таким образом, образуетс  крепь выработки , обеспечивающа  устойчивость обнажений пород, в которой хвостовики 3 анкеров 2 выполн ют роль подхватов, а их сцепление между собой обеспечивает совместную работу анкеров 2. Это существенно повышает безопасность работ в проходческом забое.Thus, a support is formed, ensuring the stability of rock outcrops, in which the shanks 3 of the anchors 2 perform the role of pickups, and their cohesion between them ensures the joint operation of the anchors 2. This significantly increases the safety of work in the tunneling face.

В таком виде крепь может примен тьс  преимущественно как временна  на период проходки.In this form, the support may be used primarily as a temporary one for the period of penetration.

Дл  усилени  образованной таким образом крепи, например, дл  поддержани  выработки в зоне вли ни  очистных работ, повышени  ее несущей способности и надежности в кровле и боках выработки бур т шпуры в шахматном пор дке по отношению к анкерам 2 первой очереди. Затем на хвостовики анкеров 2 первой очереди навешивают металлическую сварную решетку 6; в пробуренные шпуры, начина  с нижнего в р ду, устанавливают более длинные анкеры 7 второй очереди, хвостовики 8 которых загибают , располага  перпендикул рно хвостовикам 3 анкеров 2 первой очереди, при этом пропускают стержень 9 каждого последующего в р ду анкера через  чейки решетки 6 в петлю хвостовиков 8 предыдущего и прижимают хвостовик 8 каждого последующего анкера 7 вместе с решеткой 6 к поверхности выработки. Хвостовик 8 предпоследнего анкера в р ду креп т к массиву горных пород анкером 10 без хвостовика 8 с помощью опорной плитки и клина, вход щего в петлю стержн  9. Далее на поверхность выработки нанос т торкрет-бетон 11.To strengthen the lining thus formed, for example, to support the development of cleaning work in the zone of influence, to increase its bearing capacity and reliability in the roof and sides of the drilling hole in a staggered pattern with respect to the first anchors 2. Then on the shanks of the anchors 2 of the first stage hang metal welded lattice 6; In the drilled holes, starting from the bottom in the row, the longer anchors 7 of the second stage are installed, the shanks 8 of which are bent, 3 anchors 2 of the first stage are perpendicular to the shanks, and the rod 9 of each subsequent anchor is passed through the rows of the anchor a loop of the shanks 8 of the previous one and the shank 8 of each subsequent anchor 7 is pressed together with the grid 6 to the working surface. The shank 8 of the last but one anchor in the row is fastened to the rock mass with an anchor 10 without a shank 8 with the help of a base tile and a wedge entering the loop of rod 9. Next, gunning concrete 11 is applied to the working surface.

Таким образом, образуетс  крепь выработки , анкеры которой закрепл ют прикон- турный массив вокруг выработки, а их хвостовики одновременно используютс In this way, a support is formed, the anchors of which fix a surrounding array around the excavation, and their shanks are simultaneously used.

дл  предотвращени  отслоений пород на контуре выработки между анкерами. Прижатие решетки к поверхности выработки не требует применени  специальных конструктивных приспособлений в крепи и специальных операций. Оно производитс  автоматически при установке длинных анкеров П очереди.to prevent delamination of rocks in the contour of the excavation between the anchors. Pressing the grate to the surface of the mine does not require the use of special structural devices in the lining and special operations. It is produced automatically when long anchors are installed in the U queue.

Предложенный способ позвол ет быс- тро и надежно крепить кровлю и бока выработки вплоть до самого забо  при применении буровзрывного способа проходки, что особенно важно при проведении выработки в сильно трещиноватом массиве. Это существенно повышает безопасность работ в забое. Простота способа позвол ет полностью механизировать процесс креплени The proposed method allows fast and reliable fastening of the roof and sides of the excavation right up to the slab when using the drilling and blasting method of penetration, which is especially important when carrying out excavation in a highly fractured massif. This significantly increases the safety of work in the face. The simplicity of the method allows to completely mechanize the process of fastening

2525

Claims (1)

Формула изобретени Invention Formula Способ креплени  горных выработок включающий бурение шпуров р дами, установку в них анкеров с петл ми на концах хвостовиков и сцепление их между собой,The method of securing mine workings involves drilling holes with rows, installing anchors in them with loops at the ends of the shanks and coupling them together, подвеску к ним металлической решетки и прижатие бе к поверхности выработки, нанесение на нее торкрет-бетона, отличающийс  тем, что, с целью повышени  устойчивости выработки, шпуры бур т черезhanging a metal grill to them and pressing it against the surface of the mine, putting shotcrete on it, characterized in that, in order to increase the stability of the mine, the boreholes drill through петли хвостовиков анкеров последнего р да , а анкеры устанавливают в две очереди и располагают анкеры второй очереди в шахматном пор дке по отношению к первой при этом хвостовики анкеров первой oi epeди изгибают вдоль выработки, а второй - поперек и прижимают ее к поверхности, причем сцепление анкеров производ т путем пропускани  каждого последующего анкера в петлю хвостовика предыдущего, приthe loops of the shanks of the anchors of the last row, and the anchors are installed in two turns and have the anchors of the second turn in a staggered order with respect to the first one; produced by passing each successive anchor into the previous shank loop, with этом металлическую решетку подвешивают к анкерам первой очереди, а прижимают к поверхности выработки анкерами пторой очереди.This metal grid is suspended to the anchors of the first stage, and pressed to the surface of the anchors production of the second stage. //// ФИГ.ЗFIG. 3 ФИГ. ЦFIG. C
SU894708137A 1989-06-20 1989-06-20 Method for supporting mine workings SU1652592A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU894708137A SU1652592A1 (en) 1989-06-20 1989-06-20 Method for supporting mine workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU894708137A SU1652592A1 (en) 1989-06-20 1989-06-20 Method for supporting mine workings

Publications (1)

Publication Number Publication Date
SU1652592A1 true SU1652592A1 (en) 1991-05-30

Family

ID=21455583

Family Applications (1)

Application Number Title Priority Date Filing Date
SU894708137A SU1652592A1 (en) 1989-06-20 1989-06-20 Method for supporting mine workings

Country Status (1)

Country Link
SU (1) SU1652592A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU184279U1 (en) * 2018-06-29 2018-10-22 Акционерная компания "АЛРОСА" (публичное акционерное общество) Anchor support section
RU186421U1 (en) * 2018-02-28 2019-01-21 Виктор Романович Ногих UNIVERSAL ANCHOR FASTENERS
RU2743161C1 (en) * 2020-04-20 2021-02-15 федеральное государственное бюджетное образовательное учреждение высшего образования "Санкт-Петербургский горный университет" Method of fixing mine workings with anchors with reinforced belts

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 1108214, кл. Е21 D 20/00, 1983. Авторское свидетельство СССР № 1305356.кл. Е 21 D 11/00. 1985. *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU186421U1 (en) * 2018-02-28 2019-01-21 Виктор Романович Ногих UNIVERSAL ANCHOR FASTENERS
RU184279U1 (en) * 2018-06-29 2018-10-22 Акционерная компания "АЛРОСА" (публичное акционерное общество) Anchor support section
RU2743161C1 (en) * 2020-04-20 2021-02-15 федеральное государственное бюджетное образовательное учреждение высшего образования "Санкт-Петербургский горный университет" Method of fixing mine workings with anchors with reinforced belts

Similar Documents

Publication Publication Date Title
RU2348811C1 (en) Method of supporting mine tunnels
SU1652592A1 (en) Method for supporting mine workings
RU2177550C1 (en) Method of mine workings support
RU2128773C1 (en) Method for supporting mining workings with loose roof rock by anchor support
RU2215150C1 (en) Method of supporting of underground mine workings with combined support
RU2007577C1 (en) Method of guarding of workings in heaving soils
RU2175062C2 (en) Method of advanced anchoring of roof of edge part of seam of stope
RU97106446A (en) METHOD FOR MOUNTING MINING PRODUCTS WITH WEAK ROCKS OF ROOF ANCHORED FASTENERS
SU1544985A1 (en) Method of supporting mine workings
RU2805691C1 (en) Method for conducting mining works in development of flat coal beds
RU2400631C1 (en) Method for reinforcement of mines
CN214836382U (en) Roadway ecological supporting structure
SU909189A1 (en) Methrd of supporting the roof of mine workings
CN219932191U (en) Tunnel bamboo mixes supporting construction
SU1559185A1 (en) Method of supporting mine workings
SU1446344A1 (en) Method of reinforcing filling-up mass
SU1458573A1 (en) Method of mining steep ore bodies
SU1523675A1 (en) Method of supportting mine workings
SU1244324A1 (en) Method of mounting buntons
RU2078931C1 (en) Method of support of mine workings and frame support for its embodiment
CN205422746U (en) Broken country rock tunnelling advance support device of coal seam second mining in collecting space area
SU1665038A1 (en) Method of driving narrow-face workings with separate coal and rock extraction
SU1765441A1 (en) Method at advanced anchoring during driving of working
SU1305356A1 (en) Method of supporting mine workings
SU1138508A1 (en) Method of erecting a framework roof support in front of working-face