[go: up one dir, main page]

SU1177776A1 - Method of determining distance of location of cable insulation fault - Google Patents

Method of determining distance of location of cable insulation fault Download PDF

Info

Publication number
SU1177776A1
SU1177776A1 SU833534616A SU3534616A SU1177776A1 SU 1177776 A1 SU1177776 A1 SU 1177776A1 SU 833534616 A SU833534616 A SU 833534616A SU 3534616 A SU3534616 A SU 3534616A SU 1177776 A1 SU1177776 A1 SU 1177776A1
Authority
SU
USSR - Soviet Union
Prior art keywords
resistance
damaged
circuit
bridge circuit
damage
Prior art date
Application number
SU833534616A
Other languages
Russian (ru)
Inventor
Анатолий Петрович Рой
Николай Петрович Гапон
Original Assignee
Предприятие П/Я А-1221
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Предприятие П/Я А-1221 filed Critical Предприятие П/Я А-1221
Priority to SU833534616A priority Critical patent/SU1177776A1/en
Application granted granted Critical
Publication of SU1177776A1 publication Critical patent/SU1177776A1/en

Links

Landscapes

  • Locating Faults (AREA)

Abstract

СПОСОБ ОПРЕДЕЛЕНИЯ РАССТОЯНИЯ ДО МЕСТА ПОВРЕЖДЕНИЯ ИЗОЛЯЦИИ КАБЕ.ПЯ, основанный на двусторонних измерени х, отличающийс   тем, что, с целью повышени  точности определени  места повреждени  , в первом цикле измерени  в мостовую схему в качестве плеч сравнени  включают переходные сопротивлени , дл  чего к первому эходу поврежденной цепи подключают источник питани , а к второму входу поврежденной цепи - магазин сопротивлений , и М1бжду точкой его соединени  с проводом,- имеющим меньшее переходное сопротивление, и землей включа- . ют индикатор и указанным магазином сопротивлений уравновешивают мостовую схему, во втором цикле измерений между первыми входами поврежденного и неповрежденного кабелей включают магазин сопротивлений с индикатором, включенным между точкой соединени  магазина сопротивлений с проводом кабел  с наименьшим переходным сопротивлением и землей, а к второму i входу поврежденной цепи подключают источник питани , указанным магазином (Л сопротивлений уравновешивают мостовую схему и по показани м магазина сопротивлений, полученным при уравновешивании мостовой схемы при первом и втором измерени х, расчитывают рассто ние до места повреждени . vi ч ч 9дA METHOD FOR DETERMINING DISTANCE TO THE DAMAGE OF INSULATION OF THE CABE.LR, based on bilateral measurements, characterized in that, in order to improve the accuracy of determining the location of damage, in the first measurement cycle, the bridge circuit includes contact resistances for the first run the damaged circuit is connected to a power source, and to the second input of the damaged circuit there is a resistance box, and M1 is its connection point to the wire, which has a lower transient resistance, and the ground is turned on. The indicator and the indicated resistance box balance the bridge circuit, in the second measurement cycle between the first inputs of the damaged and intact cables include a resistance box with an indicator connected between the connection point of the resistance box and the cable with the lowest transition resistance and ground, and to the second i input of the damaged circuit connect the power source indicated by the store (L resistances balance the bridge circuit and, according to the readings of the resistance box obtained by ravnoveshivanii bridge circuit with first and second dimensions, is calculated the distance to the fault. vi h h 9e

Description

Изобретение относитс  к измерительной технике и может быть использовано при определении места повреждени  кабелей при переходных сопротивлени х соизмеримых со значением 5 сопротивлени  шлейфа. Целью изобретени   вл етс  повышение точности определени  места повреждени  за счет исключени  погрешностей , возникаюш;их в приборных 0 плечах моста. На фиг. 1 и 2 приведены электрические схемы дл  осуществлени  предлагаемого способа. Схемы содержат магазин 1 сопротив-15 лений, переходное сопротивление - 2 условно исправной жилы в местеповреждени , источник 3 питани , индикатор 4, сопротивление 5 условно исправной жилы до места повреж,цени  20 от первого входа поврежденной цепи сопротивление 6 поврежденной жилы до места повреждени  от первого входа поврежденной (или измер емой) цепи,сопротивление 7 условно исправ- 25 ной жилы до места повреждени  от второго входаповрежденной (измер е:мой ) цепи сопротивление 8 поврежденной жилы до места повреждени  от второго входа поврежденной (измер емой) ЗО цепи, переходное сопротивление 9 поврежденной жилы. Процесс измерени  осуществл етс  следующим образом. В мостовую схему в качестве плеч 35 сравнени  включают переходное сопротивление 2 и переходное сопротивление 9 поврежденной жилы, дл  чего в первом цикле измерени  с одной стороны между жилами подключают источ- 40 ник 3 питани , а к противоположным выводам - магазин 1 сопротивлений, а между точкой его соединени  с 5кш1ой. имеющей меньшее переходное сопротивление , и земпей включают индикатор 45 R/i 4. Мостова  схема, двум  плечами ко- где торой  вл ютс  магазин 1 сопротивлений с сопротивлением 5 и сопротивление 6, а двум  другими плечами срав-: нени  - переходное сопротивление 2 и 50 переходное сопротивление 9, одной диаганалью мостовой схемы  вл ютс  индикатор 4, другой - сопротивление 7 полу и сопротивление 8 с включенным между ними источником 3 питани , уран- 55 новешив етс  магазином 1 сопротивлений . При равновесии мостовой схемы имеет место равенство где мес вхо на вом в м ной в м жил зин межд режд ром пов ни  мага шива мага втор где из у учит В водо Ъыть Ид + Rf-i R Rfli Кд - сопротивление жилы до а повреждени  от измер емого а,, при первом цикле измерени ; сопротивление, полученное агазине сопротивлений при перцикле измерений R - переходное сопротивление сте повреждени  условно исправжилы; ) П2. переходное сопротивление сте повреждени  поврежденной . ри втором цикле измерений мага1 сопротивлений с включенным у точкой его соединени  с повенной жилой и землей индикато4 подключают к другой стороне ежденной цепи,а источник 3 питаподключают на сторону, где был зин 1 сопротивлений. Уравновеют полученную мостовую схему зином сопротивлений и получают ое уравнение R 1 - RXA - RM6 Rn K-j хА R - сопротивление одного провода поврежденной цепи; Rд.g- значение, набранное на магазине сопротивлений при измерении во втором цикле. RXA R/MA Кл - КХЛ Кнь-оч „--5 оjV-J/ 1 ХЛ равнени  (з) имеем ыва , что Ry. R км L, L - длина поврежденной цепи; ул рассто ние до места повреждени  в первом цикле измерений; R - пилометрическое сопротивкм ление одного провода поврежденной цепи, чаем ХА случа х, когда сопротивлени  пров различны, уравнение (3) может записано в виде К (RA - RXA) - RM К RXA ,RMA RITA RA - RXA к - коэффициент пропорционал где ности, равен отношению RAW RXA где Кд., - сопротивление условно ис правной жилы; сопротивление поврежденн жилы: сопротивление до повреждени  по условно исправной жиле; R)(f- сопротивление до места повреждени  по поврежденной жиле. Определив из уравнени  (6) Ry , получаем выражение (4), т.е.расчетна  формула дл  обоих случаев сопротивлений проводов поврежденной цепи одинакова. Таким образом, отпадает необходимость определени  (или измерени ) их значений или значени  ихсопротивлени .The invention relates to a measurement technique and can be used in determining the location of damage to cables at transient resistances comparable with a value of 5 loop resistance. The aim of the invention is to improve the accuracy of determining the location of damage by eliminating errors that occur in the instrument 0 arms of the bridge. FIG. 1 and 2 are the electrical circuits for carrying out the proposed method. The diagrams contain the magazine 1 resistance-15, the contact resistance - 2 conditionally serviceable conductors at the site of damage, power supply 3, indicator 4, resistance 5 conditionally serviceable conductors to the damage location, value 20 from the first input of the damaged circuit, resistance 6 of the damaged conductors to the damage location the first input of the damaged (or measurable) circuit, the resistance 7 of the conditionally working 25 wires to the damage site from the second input; the damaged (measured: mine) chain resistance 8 of the damaged wires to the damage location from the second input; This (measured) ZOR circuit, contact resistance 9 damaged cores. The measurement process is carried out as follows. In the bridge circuit, as a comparison shoulder 35, transient resistance 2 and transient resistance 9 of the damaged core are included, for which in the first measurement cycle, on one side, a power supply 3 is connected between the cores, and opposite terminals have a resistance store 1, and between the point its compounds with 5xl1. having a smaller transitional resistance, and Zempey include an indicator 45 R / i 4. The bridge circuit, the two shoulders of which are the resistance store 1 with resistance 5 and resistance 6, and the other two shoulders comparison: transition resistance 2 and 50 transient resistance 9, one diagonal of the bridge circuit are indicator 4, the other is resistance to 7 floor and resistance 8 with power supply 3 connected between them, uranium 55 is weighed by resistance magazine 1. At the equilibrium of the bridge circuit, there is equality, where the wind passed in the middle of the world zin between the maine and the magician, where it teaches us to drain the Id + Rf – i R Rfli Cd - the resistance of the core to a damage from measured a ,, at the first measurement cycle; the resistance obtained at the resistance store during the measurement cycle R - the contact resistance of the damage conditionally fixable; P2. transient resistance to damage damaged. In the second cycle of measurements, the resistivity magnetizer with its connection point connected to the home vein and the earth indicator is connected to the other side of the external circuit, and the power source 3 is connected to the side where it was located 1 of the resistances. Equip the resulting bridge circuit with the resistivity and obtain the following equation: R 1 - RXA - RM6 Rn K-j xA R - resistance of one wire of the damaged circuit; Rd.g - the value typed on the resistance box when measured in the second cycle. RXA R / MA Cl - KHL Kn-och - 5 оjV-J / 1 HL Equal (h) we have ryv that Ry. R km L, L is the length of the damaged chain; The distance to the damage site in the first measurement cycle; R - pilometric resistance of one wire of a damaged circuit, tea XA cases, when the resistances of wires are different, equation (3) can be written in the form K (RA - RXA) - RM K RXA, RMA RITA RA - RXA k - coefficient proportional to where , is equal to the ratio of RAW RXA where Kd., is the resistance of the conditionally valid core; resistance of damaged cores: resistance to damage on conditionally serviceable core; R) (f- resistance to damage on the damaged core. Determining Ry from equation (6), we get the expression (4), i.e. the calculated formula for both cases of the resistance of the wires of the damaged circuit is the same. Thus, there is no need to determine (or measurements) of their values or their resistance values.

Сриг.2Srig.2

Claims (1)

СПОСОБ ОПРЕДЕЛЕНИЯ РАССТОЯНИЯ ДО МЕСТА ПОВРЕЖДЕНИЯ ИЗОЛЯЦИИ ^КАБЕЛЯ, основанный на двусторонних измерениях, отличающий- с я тем, что, с целью повышения точности определения места повреждения , в первом цикле измерения в мостовую схему в качестве плеч сравнения включают переходные сопротивления, для чего к первому входу поврежденной цепи подключают источник питания, а к второму входу поврежденной цепи - магазин сопротивлений, и между точкой его соединения с проводом,- имеющим меньшее переходное сопротивление, и землей включа- . ют индикатор й указанным магазином сопротивлений уравновешивают мостовую схему, во втором цикле измерений между первыми входами поврежденного и неповрежденного кабелей включают магазин сопротивлений с индикатором, включенным между точкой соединения магазина сопротивлений с проводом кабеля с наименьшим переходным сопротивлением и землей, а к второму входу поврежденной цепи подключают источник питания, указанным магазином сопротивлений уравновешивают мостовую схему и по показаниям магазина сопротивлений, полученным при уравновешивании мостовой схемы при первом и втором измерениях, расчитывают расстояние до места повреждения.METHOD FOR DETERMINING THE DISTANCE TO THE DAMAGE OF INSULATION ^ CABLE, based on two-sided measurements, characterized in that, in order to improve the accuracy of determining the location of damage, in the first measurement cycle, the transition resistance is included in the bridge circuit as shoulders, for which the first a power supply is connected to the input of the damaged circuit, and a resistance store is connected to the second input of the damaged circuit, and between the point of its connection with the wire, which has a lower transition resistance, and the ground turns on. The indicator with the indicated resistance store balances the bridge circuit, in the second cycle of measurements between the first inputs of the damaged and undamaged cables, the resistance store is turned on with an indicator connected between the point of connection of the resistance store with the cable wire with the lowest transition resistance and ground, and connected to the second input of the damaged circuit the power source indicated by the resistance store balance the bridge circuit and according to the testimony of the resistance store obtained by balancing AANII bridge circuit with first and second dimensions, is calculated the distance to the fault. SU „.,1177776SU „., 1177776
SU833534616A 1983-01-06 1983-01-06 Method of determining distance of location of cable insulation fault SU1177776A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU833534616A SU1177776A1 (en) 1983-01-06 1983-01-06 Method of determining distance of location of cable insulation fault

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU833534616A SU1177776A1 (en) 1983-01-06 1983-01-06 Method of determining distance of location of cable insulation fault

Publications (1)

Publication Number Publication Date
SU1177776A1 true SU1177776A1 (en) 1985-09-07

Family

ID=21043596

Family Applications (1)

Application Number Title Priority Date Filing Date
SU833534616A SU1177776A1 (en) 1983-01-06 1983-01-06 Method of determining distance of location of cable insulation fault

Country Status (1)

Country Link
SU (1) SU1177776A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Париножко И,А., Шварцман В,О. Определение места повреждени изол ции кабелей св зи. М.: Св зь, 1967, с, 22. Там же, с,91. *

Similar Documents

Publication Publication Date Title
CN112285425B (en) Grounding resistance calculation method and device of tower grounding device and terminal equipment
CN112285426B (en) Grounding resistance testing method and system of tower grounding device and terminal equipment
SU1177776A1 (en) Method of determining distance of location of cable insulation fault
SU449307A1 (en) Method of compensation of induced noise when testing cables
CN217181179U (en) Measuring device for positioning single-phase grounding point of generator stator winding
SU1661689A1 (en) Device for determining breakage place of cable-core insulation
SU1007050A2 (en) Method of determining damaged phase at single-phase earthing in network with insulated neutral wire
SU1262429A1 (en) Method of locating cable core fault
RU2828439C1 (en) Method of determining point of damage on overhead power transmission line by measuring currents from its two ends
JPS5772078A (en) Method for chicking erroneous connection conductors of communication cable having connector
SU531106A1 (en) Method for determining the location of damage to insulation of stranded cables
RU2823691C1 (en) Method of determining the point of damage on overhead power transmission line by measuring currents from its two ends
SU756322A1 (en) Method of determining damaged phase at single-phase earthing in mains with insulated neutral wire
SU1167548A1 (en) Method of determining location of faulted cable insulation
SU622025A1 (en) Three-component alternating electric field sensor
SU58861A1 (en) Method for approximate determination of cable damage location
SU1109682A1 (en) Method of checking relative position of wires in cables
SU728097A1 (en) Method of locating cable line wires insulation flaws
SU834617A1 (en) Method of detecting post with damaged insulation in overhead electric power transmission lines
SU539277A1 (en) Method for measuring cable conductor difference
RU2018635C1 (en) Transducer of mining machine inclination angle
JPS5611514A (en) Detecting method of stop position of unattended car
US1775686A (en) Measuring resistance of ground connections
JPH034940Y2 (en)
SU1242861A1 (en) Device for determining distance to fault location in isolated-neutral electrical systems