[go: up one dir, main page]

SU1027393A1 - Method of working sloping and steep ore beds - Google Patents

Method of working sloping and steep ore beds Download PDF

Info

Publication number
SU1027393A1
SU1027393A1 SU823432717A SU3432717A SU1027393A1 SU 1027393 A1 SU1027393 A1 SU 1027393A1 SU 823432717 A SU823432717 A SU 823432717A SU 3432717 A SU3432717 A SU 3432717A SU 1027393 A1 SU1027393 A1 SU 1027393A1
Authority
SU
USSR - Soviet Union
Prior art keywords
blocks
ore
wells
reserves
block
Prior art date
Application number
SU823432717A
Other languages
Russian (ru)
Inventor
Леонтий Антонович Мамсуров
Вениамин Евгеньевич Аврамов
Михаил Иванович Казьмин
Борис Александрович Никуличев
Виктор Константинович Сифоркин
Владимир Александрович Барсуков
Original Assignee
Сибирский государственный проектный и научно-исследовательский институт цветной металлургии
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Сибирский государственный проектный и научно-исследовательский институт цветной металлургии filed Critical Сибирский государственный проектный и научно-исследовательский институт цветной металлургии
Priority to SU823432717A priority Critical patent/SU1027393A1/en
Application granted granted Critical
Publication of SU1027393A1 publication Critical patent/SU1027393A1/en

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

СПОСОБ РАЗРАБОТКИ НАКЛОННЫХ И КРУТОПАДАЮЩИХ РУДНЫХ ЖИЛ, включающий проведение этажных и подэтажных штреков в блоках, блоковых и отрезных восстающих, сплошную выем ку запасов руды сверху вниз, бурение и взрывание нисход щих скважин в верхней части подэтажа и восход щих скважин в нижней части подэтажа, формирование временных ленточных и надщтрековых целиков, в полублоках, магазинирование и выпуск руды , отличающийс  тем, что, с целью повышени  эффективности разработки за счет снижени  объема подготовитльно-нарезных выработок, повышени  безопасности работ и уменьшени  потерь и разубоживани  руды, выемку запасов осуществл ют одновременно в смежных полублоках соседних блоков, при этом на границе блоков формируют неподсеченную подэтажными штреками часть запасов , которую разбуривают веерами скважин по подэтажем из подэтажных штреков до границы блока, а по мере выемки запасов подэтажей и надштрековых целиков путем бурени  и взрывани  скважин произвоS д т обрушение налегающих пород попод (Л этажам в направлении от границ к центру блока. to со со соMETHOD FOR DEVELOPING tilt and steeply dipping ore veins, comprising carrying storey and sublevel drifts in units of block and cutting rising, continuous workpits ku ore reserves downward drilling and blasting downlink wells at the top of substage and uplink wells at the bottom of substage, the formation temporary tape and supersline pillars, in semi-blocks, ore mining and production, characterized in that, with the aim of increasing the efficiency of development by reducing the volume of preparatory-rifled workings, Because of the safety of work and the reduction of losses and ore dilution, the reserves are removed simultaneously in the adjacent semi-blocks of neighboring blocks, while at the border of the blocks they form part of the reserves that are not divided by sublevel drifts and drilled by fans of the wells along the sublevel from the sublevel drifts to the boundary of the block and Stocks of sub-floors and cross-pillars, by drilling and blasting wells, produce collapse of overburden popod (L floors in the direction from the borders to the center of the block. to with with

Description

Изобретение относитс  к горной промышленности и может быть использовано при подземной разработке тонких и средней мощности наклонных и крутопадающих жил, в том числе при сложных элементах залега:н1  жил в породах средней и выше средней :тойчивости. Известен способ разработки тонких и средней мощности наклонных и крутопадающих жил, включающий выемку запасов этажами , проходку штреков и восстающих и -плошную выемку руды в блоках 1. Недостатком известного способа  вл етс  относительно низка  производительность труда и сравнительно высокие потери руды. Наиболее близким к предлагаемому по техниче(:кои сущности и достигаемому результату  вл етс  способ разработки наклонных и крутопадающих рудных жил, включающий проведение этажных и подэтажных штреков в блоках, блоковых и отрезных восстающих, сплощную выемку запасов руды сверху вниз, бурение и взрывание нисход щих скважин в верхней части подэтажа и восход щих скважин в нижней части подэтажа, формирование временных ленточных и надщтрековых целиков в полублоках , магазинирование и выпуск руДы 1. Недостатком этого способа  вл етс  относительно невысока  эффективность выемки в св зи с значительным объемом подготовительных работ и повыщенной опасностью работ в св зи с наличием открытого выработанного пространства. Цель изобретени  - повышение эффективности разработки за счет снижени  объема подготовительно-нарезных выработок, повышени  безопасности работ и уменьшени  потерь и разубоживани  руды. Поставленна  цель достигаетс  тем, что согласно способу разработки наклонных и крутопадающих рудных жил, включающему проведение этажных и подэтажных щтреков в блоках, блоковых и отрезных восстающих , сплощную выемку запасов руды сверху вниз, бурение и взрывание нисход щих скважин в верхней части подэтажа и восход щих скважин в верхней части подэтажа и восход щих скважин в нижней части подэтажа, формирование временных ленточных и надштрековых целиков в полублоках , магазинирование и выпуск руды, выемку запасов осуществл ют одновременно в смежных полублоках соседних блоков, при этом на границе блоков формируют неподсеченную подэтажными щтреками часть запасов, которую разбуривают веерами скважин по подэтажам из подэтажных щтреков до границы блока, а по мере выемки запасов подэтажей и надщтрековых целиков путем бурени  и взрывани  скважин производ т обрущение налегающих пород по подэтажам в направлении от границ к центру блока. На фиг. 1 представлен план горных работ в период развити  очистной выемки в первом подэтаже; на фиг. 2 - очистна  выемка третьего подэтажа, выемка надштрековых целиков второго подэтажа и обрушение пород кровли отработанного пространства второго подэтажа. Способ осуществл ют следующим образом . Блок подготавливают штреками 1 и 2 и центральным восстающим 3. Нарезные работы включают проходку из центрального восстающего подэтажных штреков 4, не достига  границ блока, и отрезных вентил ционных восстающих 5 по флангам подэтажных щтреков 4, а также по границам дайковых включений 6, формиру  тем самым неподсеченный штреками участок запасов. Выемку подэтажей ведут сверху вниз. Очистные работы в подэтаже начинают с обуривани  неподсеченного подэтажным штреком массива веером скважин 7. При условии , если нет необходимости сохран ть вентил ционный штрек 2, производ т одновременное обуриваНие нисход щими скважинами 8 и магазинирование руды верхней части . подэтажа. После завершени  очистных работ на флангах блока (на границе блока 9) отбитую руду 10 магазинируют и приступают к обуриванию верхней и нижней частей подэтажей восход пдими 11 и нисход щими 8 скважинами с, подэтажных штреков с учетом морфологии залегани  жилы . Отбитую руду транспортируют по подэтажному штреку до центрального восстающего 3 и скреперуют на откаточный штрек. Остатки руды в выработанном пространстве убирают гидросмывом. Отбитую руду в верхней подсечке подэтажа магазинируют. Временно оставл емые надштрековые целики 12, ленточные целики у центрального восстающего 13 и дайковые включени  6 выполн ют функции поддержани  кровли до полной отработки запасов подэтажа. Пролеты кровли между надштрековыми целиками 12 поддерживают дерев нной распорной крепью 14, состо щей из стоек или кустов. Пространство между ними перекрывают досками или плахами. Пос,те отработки запасов вышележащего подэтажа блока приступают в аналогичной последовательности к отработке нижележащего подэтажа. При этом ведетс  последовательное погашение надштрековых целиков 12 с одновременной подрывкой глубокими скважи.на.ми 1 5 и посадкой полос кровли 16 вышележащего подэтажа . Использованче изобретени  позволит повысить эффективность систем разработки рудных месторождений с магазинированием руды.The invention relates to the mining industry and can be used in the underground mining of thin and average thickness of inclined and steeply dipping veins, including when complex elements of the bed are laid: n1 lived in rocks of medium and above average: resistance. There is a known method of developing inclined and steeply dipping veins, which include excavation of floors, penetration of drifts and rebels, and continuous ore extraction in blocks 1. The disadvantage of this method is relatively low productivity and relatively high ore losses. The closest to the proposed technical (: the essence and the achieved result is a method of developing inclined and steeply dipping ore veins, including conducting floor and sublevel drifts in blocks, block and detachable rebels, flat dredging of ore reserves from top to bottom, drilling and blasting downhole wells in the upper part of the substage and ascending wells in the lower part of the substage, the formation of temporary tape and superstrack pillars in the semi-blocks, the storage and release of ore 1. The disadvantage of this method is The excavation efficiency is relatively low due to the large amount of preparatory work and the increased risk of work due to the open mined space. The aim of the invention is to increase the efficiency of development by reducing the amount of preparatory-rifled openings, improving work safety and reducing losses and ore dilution. The goal is achieved by the fact that according to the method of developing inclined and steeply dipping ore veins, including the conduct of floor and subsurface shchrek in blocks , block and detachable ascending, flat mining of ore reserves from top to bottom, drilling and blasting downhole wells in the upper part of the sub-floor and ascending wells in the upper part of the sub-floor and ascending wells in the lower part of the sub-floor, the formation of temporary tape and nadstrekovyh pillars in semi-blocks, storage and the release of ore, the extraction of reserves is carried out simultaneously in adjacent semi-blocks of neighboring blocks, while on the border of the blocks form part of the reserves that are not truncated by sublevel shchrekami, which are drilled by fans of wells along the sub-floors from the subsurface wells to the block border, and as the reserves of the sub-floors and sublevel pillars are dredged, by drilling and blasting wells, overburden is crushed along the sub-floors in the direction from the boundaries to the center of the block. FIG. 1 shows the plan of mining operations in the period of development of the clearing recess in the first sub-floor; in fig. 2 - the clearing excavation of the third substage, the excavation of the sub-axle pillars of the second substage and the collapse of the roof rocks of the spent space of the second substage. The method is carried out as follows. The block is prepared with drifts 1 and 2 and central rebels 3. Cutting works include penetration from the central rising subsurface drifts 4, not reaching the boundaries of the block, and cutting off ventilation rebels 5 along the flanks of the subsurface plugs 4, as well as along the boundaries of the dike inclusions 6, thereby forming drift-free area of stock. The recess of the sub-floors is from the top down. The cleaning works in the sub-floor begin with the drilling of an array not drilled with a sublevel drift by fan 7. Provided that it is not necessary to maintain the ventilation drift 2, the downward wells 8 are drilled simultaneously and the upper part of the ore is stored. substage. After the completion of cleaning works on the flanks of the block (on the border of block 9), the broken ore 10 is stored and the upper and lower parts of the sub-floors begin to sediment with the rising of 11 and 10 down-holes with sublevel drifts, taking into account the morphology of the vein. Repulsed ore is transported by subsurface drift to central rising 3 and scraped onto a haulage drift. The remains of ore in the developed space is cleaned up with a hydraulic wash. Broken ore in the upper cutting substage store. Temporarily left pillar posts 12, tape pillars at central ascending 13 and dike inclusions 6 perform the functions of supporting the roof until the reserves of the sub-floor have been fully developed. Roof spans between the pivotal pillars 12 are supported by wooden spacer support 14 consisting of racks or bushes. The space between them is covered with boards or planes. POS, those working out the reserves of the overlying substage of the block proceed in a similar sequence to the development of the underlying substage. This leads to a consistent repayment of the pivotal pillars 12 with simultaneous undermining by deep wells. We are 1 5 and planting strips of the roof 16 of the overlying substage. The use of the invention will improve the efficiency of ore mining systems with ore mining.

Claims (1)

СПОСОБ РАЗРАБОТКИ НАКЛОННЫХ И КРУТОПАДАЮЩИХ РУДНЫХ ЖИЛ, включающий проведение этажных и подэтажных штреков в блоках, блоковых и отрезных восстающих, сплошную выем ку запасов руды сверху вниз, бурение и взры- вание нисходящих скважин в верхней части подэтажа и восходящих скважин в нижней части подэтажа, формирование временных ленточных и надштрековых целиков, в полублоках, магазинирование и выпуск руды, отличающийся тем, что, с целью повышения эффективности разработки за Счет снижения объема подготовитльно-нарезных выработок, повышения безопасности работ и уменьшения потерь и разубоживания руды, выемку запасов осуществляют одновременно в смежных полублоках соседних блоков, при этом на границе блоков формируют неподсеченную подэтажными штреками часть запасов, которую разбуривают веерами скважин по подэтажем из подэтажных штреков до границы блока, а по мере выемки запасов подэтажей и надштрековых целиков путем бурения и взрывания скважин произво- S дят обрушение налегающих пород по'подэтажам в направлении от границ к центру блока.METHOD FOR DEVELOPING AN INCLINED AND STEEL FALLING ORE VEINS, including carrying out floor and sub-floor drifts in blocks, block and cutting risers, continuous excavation of ore reserves from top to bottom, drilling and blasting of descending wells in the upper part of the sub-floor and ascending wells in the lower part temporary tape and nadshtrekovym pillars, in semi-blocks, ore stacking and production, characterized in that, in order to increase development efficiency by reducing the volume of preparatory-cut workings, increase The safety of work and the reduction of losses and dilution of ore, the extraction of reserves is carried out simultaneously in adjacent semi-blocks of neighboring blocks, while at the border of the blocks an un-cut part of the stocks is drilled, which is drilled by fans of wells along the floors from the floor drifts to the block boundary, and as the reserves of the floors are removed and over-pillar pillars by drilling and blasting wells produce collapse of overlying rocks along 'floors in the direction from the borders to the center of the block. >>
SU823432717A 1982-04-28 1982-04-28 Method of working sloping and steep ore beds SU1027393A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823432717A SU1027393A1 (en) 1982-04-28 1982-04-28 Method of working sloping and steep ore beds

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823432717A SU1027393A1 (en) 1982-04-28 1982-04-28 Method of working sloping and steep ore beds

Publications (1)

Publication Number Publication Date
SU1027393A1 true SU1027393A1 (en) 1983-07-07

Family

ID=21009982

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823432717A SU1027393A1 (en) 1982-04-28 1982-04-28 Method of working sloping and steep ore beds

Country Status (1)

Country Link
SU (1) SU1027393A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР № 72421, кл. Е 21 С 41/06 1944. 2. Авторское свидетельство СССР № 761706, кл. Е 21 С 41/06, 1978 (прототип) . *

Similar Documents

Publication Publication Date Title
US4213653A (en) Method of mining of thick seam materials
CN108952725B (en) A low-dilution mining method suitable for gently inclined thin ore bodies
US4878712A (en) Hydraulic method of mining coal
RU2632606C1 (en) Method for depreservation steeply inclined nonactive sidewalls
SU1027393A1 (en) Method of working sloping and steep ore beds
CN108266188A (en) The checkerboard type recovery method of engineering puppet inclination arrangement need not be cut based on in-vein preparatory work
RU2642903C1 (en) Method for open-cut mining of mineral deposits
RU2632604C1 (en) Method for forming and depreserving steep temporary nonactive walls when developing deep laying deposits
RU2114307C1 (en) Method for opencast mining of flooded mineral deposits
RU2099524C1 (en) Combined method of mining of formation of steeply dipping coal seams
RU2757883C1 (en) Method for underground mining of steeply dipping thick ore bodies
SU1257221A1 (en) Method of mining ore bodies
RU2038476C1 (en) Coal deposit exploitation method
RU2790648C1 (en) Method for underground development of steeping ore bodies in descenting order with chamber system
SU1083662A1 (en) Method of mining steep-slope ore-bodies
SU949182A1 (en) Method for working gently sloping mineral seams
SU1078070A1 (en) Method of recultivation in strip mining of mineral deposits
SU1765408A1 (en) Method at mining steep medium-thickness mineral deposit seams
SU1456572A1 (en) Method of mining mineral deposits
RU2425219C1 (en) Open development method of mineral deposits
RU2096618C1 (en) Drill-and-drift method for underground mining of coal seams
SU1458574A1 (en) Method of mining ore bodies
SU636394A1 (en) Method of mining mineral deposits
RU2319011C2 (en) Method for steeply dipping ore body development
SU1740667A1 (en) Method of coal seam working