SE510115C2 - Power plant and method for regulating its effect - Google Patents
Power plant and method for regulating its effectInfo
- Publication number
- SE510115C2 SE510115C2 SE9800641A SE9800641A SE510115C2 SE 510115 C2 SE510115 C2 SE 510115C2 SE 9800641 A SE9800641 A SE 9800641A SE 9800641 A SE9800641 A SE 9800641A SE 510115 C2 SE510115 C2 SE 510115C2
- Authority
- SE
- Sweden
- Prior art keywords
- power
- gas
- supply
- temperature
- control
- Prior art date
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F02—COMBUSTION ENGINES; HOT-GAS OR COMBUSTION-PRODUCT ENGINE PLANTS
- F02C—GAS-TURBINE PLANTS; AIR INTAKES FOR JET-PROPULSION PLANTS; CONTROLLING FUEL SUPPLY IN AIR-BREATHING JET-PROPULSION PLANTS
- F02C3/00—Gas-turbine plants characterised by the use of combustion products as the working fluid
- F02C3/20—Gas-turbine plants characterised by the use of combustion products as the working fluid using a special fuel, oxidant, or dilution fluid to generate the combustion products
- F02C3/205—Gas-turbine plants characterised by the use of combustion products as the working fluid using a special fuel, oxidant, or dilution fluid to generate the combustion products in a fluidised-bed combustor
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F02—COMBUSTION ENGINES; HOT-GAS OR COMBUSTION-PRODUCT ENGINE PLANTS
- F02C—GAS-TURBINE PLANTS; AIR INTAKES FOR JET-PROPULSION PLANTS; CONTROLLING FUEL SUPPLY IN AIR-BREATHING JET-PROPULSION PLANTS
- F02C9/00—Controlling gas-turbine plants; Controlling fuel supply in air- breathing jet-propulsion plants
- F02C9/16—Control of working fluid flow
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
- F23C—METHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN A CARRIER GAS OR AIR
- F23C6/00—Combustion apparatus characterised by the combination of two or more combustion chambers or combustion zones, e.g. for staged combustion
- F23C6/04—Combustion apparatus characterised by the combination of two or more combustion chambers or combustion zones, e.g. for staged combustion in series connection
- F23C6/042—Combustion apparatus characterised by the combination of two or more combustion chambers or combustion zones, e.g. for staged combustion in series connection with fuel supply in stages
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- Engine Equipment That Uses Special Cycles (AREA)
- Fluidized-Bed Combustion And Resonant Combustion (AREA)
Abstract
Description
20 25 30 35 510115 2 anläggning under ur miljömässig och ekonomisk synpunkt gynnsamma förhållanden. 20 25 30 35 510115 2 facility under favorable conditions from an environmental and economic point of view.
Ett problem med PFBC-tekniken är svårigheten att åstad- komma en snabb reglering av uteffekten. På grund av den stora gasvolym som anläggningen innesluter, de många kom- ponenter, som ingår såsom aktiva delar i anläggningen, och bränslets egenskaper tar det lång tid att ändra tryck och temperatur vid en laständring.A problem with the PFBC technology is the difficulty of achieving rapid regulation of the output power. Due to the large gas volume that the plant encloses, the many components that are included as active parts in the plant, and the properties of the fuel, it takes a long time to change pressure and temperature during a load change.
En annan begränsande faktor hos PFBC-tekniken, vilken har förhindrat uppnående av en verkligt hög verkningsgrad är att den övre temperaturgräns, vid vilken förbränning av exempelvis kol äger rum i en fluidiserad bädd, vanligen uppgår till omkring 850 till 950°C beroende på kolkvali- tet. Vid höga temperaturer sintrar bäddmassan, vilket för- hindrar fortsatt fluidisering. Detta innebär att drivgasen för den i PFBC-kraftanläggningen ingående gasturbinen har en temperatur som är ungefär lika stor som temperaturen i den fluidiserade bädden. Eftersom turbineffekten stiger starkt med ökad temperatur hos drivgasen är det önskvärt med en högre gastemperatur, upp till 1200 till 1500°C för att effektuttaget ur anläggningens gasturbindel skall nå en optimal nivå. För att råda bot på denna svaghet har fö- reslagits att höja temperaturen hos förbränningsgaserna som lämnar PFBC-brännkammaren och tillförs gasturbinen med hjälp av en efterbrännkammare i vilken ett bränsle för- bränns.Another limiting factor of the PFBC technology, which has prevented the achievement of a really high efficiency, is that the upper temperature limit, at which combustion of, for example, carbon takes place in a fluidized bed, usually amounts to about 850 to 950 ° C depending on the carbon quality. tet. At high temperatures, the bed mass sinter, which prevents further fluidization. This means that the propellant gas for the gas turbine included in the PFBC power plant has a temperature that is approximately equal to the temperature in the fluidized bed. Since the turbine power increases sharply with increasing temperature of the propellant gas, it is desirable to have a higher gas temperature, up to 1200 to 1500 ° C in order for the power output from the plant's gas turbine section to reach an optimal level. To remedy this weakness, it has been proposed to raise the temperature of the combustion gases leaving the PFBC combustion chamber and to supply the gas turbine with the aid of an afterburning chamber in which a fuel is combusted.
Kraftanläggningar med en gasturbin för att alstra mekanisk energi regleras traditionellt genom styrning av förbrän- ningen, dvs styrning av tillförseln av bränsle till bäd- den. Gasturbiner kan snabbt ändra uteffekten men är ofta dyra i drift eftersom de kräver exklusiva bränslen, såsom gas och olja. PFBC-anläggningar, där det är känt att reg- lera förbränningen genom att justera den fluidiserade bäd- lO 15 20 25 30 35 s 510115 dens höjd, har den nackdelen att de reagerar långsamt på förändringar i effektefterfrågan. De är däremot billiga i drift.Power plants with a gas turbine to generate mechanical energy are traditionally regulated by controlling the combustion, ie controlling the supply of fuel to the beds. Gas turbines can quickly change the output power but are often expensive to operate because they require exclusive fuels, such as gas and oil. PFBC plants, where it is known to regulate combustion by adjusting the height of the fluidized bed, have the disadvantage that they react slowly to changes in power demand. However, they are cheap to operate.
Vidare är det i samband med en sådan inledningsvis angiven PFBC-kraftanläggning, som har en högtrycksturbin och en lågtrycksturbin, genom SE-B-469 039 känt att reglera an- läggningen genom att påverka gasflödet till lågtryckstur- binen medelst en vridbar ledskenekrans vid inloppet till densamma. Med en, sådan reglering' kan varvtalet på låg- tryckskompressorn justeras och på så vis styrs flödet av förbränningsluft till brännkammaren. När man emellertid önskar en lastuppgàng från dellastdrift kommer en juste- ring av ledskenekransen, på så sätt att flödet genom an- läggningen ökar, att resultera inledningsvis i en effekt- nedgång eftersom en större del av den tillgängliga effek- ten då tas ut i làgtrycksturbinen.Furthermore, in connection with such an initially specified PFBC power plant, which has a high-pressure turbine and a low-pressure turbine, it is known from SE-B-469 039 to regulate the plant by influencing the gas flow to the low-pressure turbine by means of a rotatable guide ring ring at the inlet to the same. With such a control, the speed of the low-pressure compressor can be adjusted and in this way the flow of combustion air to the combustion chamber is controlled. However, when a load rise from partial load operation is desired, an adjustment of the guide rail ring, in such a way that the flow through the plant increases, will initially result in a decrease in power since a larger part of the available power is then taken out in the low pressure turbine. .
WO 97/21916 visar en kraftanläggning med en efterbrännkam- mare och en reheatbrännkammare för höjning av temperaturen hos förbränningsgaserna innan dessa tillförs en högtrycks- turbin respektive en mellantrycksturbin. Brännbar gas alstras i en förgasningsreaktor och kan mellanlagras i en lagringstank innan den tillförs någon av efterbrännanord- ningarna. Denna skrift visar vidare möjligheten av att tillfälligt tillföra brännbar gas till någon av efter- brännanordningarna i syfte att åstadkomma en snabb effekt- ökning hos anläggningen.WO 97/21916 discloses a power plant with an afterburning chamber and a reheat combustion chamber for raising the temperature of the combustion gases before these are supplied to a high-pressure turbine and an intermediate pressure turbine, respectively. Combustible gas is generated in a gasification reactor and can be temporarily stored in a storage tank before it is fed to any of the afterburning devices. This document also shows the possibility of temporarily supplying combustible gas to one of the afterburners in order to achieve a rapid increase in power at the plant.
WO 97/21914 visar en liknande kraftanläggning och avser styrning av en booster-kompressor för att ställa in luft- flödet till förgasningsreaktorn. Med den kända booster- kompressorn kan man snabbt öka trycket i förgasningsreak- torn, vilket leder till ett större flöde av brännbara ga- ser till efterbrännkammaren och reheatbrännkammaren. Där- med fås en intensivare förbränning i dessa kamrar och lO 15 20 25 30 35 510115 4 temperaturen på förbränningsgaserna kan snabbt ökas, vil- ket möjliggör uttag av högre effekt från anläggningen. Ge- nom att flödet minskas medelst varvtalsregleringen eller ledskeneanordningen kan trycket i förgasningsreaktorn snabbt minskas och således kan på motsvarande sätt anlägg- ningen snabbt anpassas till ett lägre effektbehov.WO 97/21914 discloses a similar power plant and relates to the control of a booster compressor for adjusting the air flow to the gasification reactor. With the known booster compressor, the pressure in the gasification reactor can be increased quickly, which leads to a greater flow of combustible gases to the afterburning chamber and the reheat combustion chamber. This results in a more intensive combustion in these chambers and the temperature of the combustion gases can be increased rapidly, which enables higher power to be extracted from the plant. By reducing the flow by means of the speed control or the guide rail device, the pressure in the gasification reactor can be quickly reduced and thus the plant can be quickly adapted to a lower power requirement in a corresponding manner.
SAMMANFATTNING AV UPPFINNINGEN Ändamålet med föreliggande uppfinning är att undanröja ovan nämnda problem och närmare bestämt att skapa möjlig- heter för en kontinuerlig reglering som är snabb och följ- sam.SUMMARY OF THE INVENTION The object of the present invention is to eliminate the above-mentioned problems and more particularly to create possibilities for a continuous regulation which is fast and compliant.
Detta ändamål uppnås med den inledningsvis angivna kraftanläggningen som kännetecknas av en regleranordning som är inrättad att reglera på ett väsentligen kontinuer- ligt sätt den elektriska effekt som produceras av nämnda generator genom styrning av tillförseln av brännbar gas till efterbrännanordningen. Med en sådan regleranordning är det i väsentligen varje driftssituation möjligt att uppnå en snabb anpassning av anläggningens effekt till den från ett elnät efterfrågade effekten. Genom att tillför- seln av brännbar gas till efterbrännanordningen ökas kan temperaturen hos förbränningsgaserna höjas i det närmaste momentant, vilket omedelbart medför att den av gasturbinen producerade effekten stiger. Därvid kan nämnda ledningsor- gan innefatta en ventilanordning som är inrättad att stäl- las in medelst regleranordningen för nämnda styrning av tillförseln av brännbar gas till efterbrännanordningen.This object is achieved with the initially stated power plant which is characterized by a control device which is arranged to regulate in a substantially continuous manner the electrical power produced by said generator by controlling the supply of combustible gas to the afterburning device. With such a control device, it is possible in essentially every operating situation to achieve a rapid adaptation of the plant's power to the power requested from an electricity network. By increasing the supply of combustible gas to the afterburner, the temperature of the combustion gases can be raised almost instantaneously, which immediately means that the power produced by the gas turbine rises. In this case, said conduit means may comprise a valve device which is arranged to be set by means of the control device for said control of the supply of combustible gas to the afterburning device.
Enligt en utföringsform av uppfinningen kan regleringen av nämnda tillförsel av brännbar gas realiseras genom att regleranordningen innefattar ett effektavkänningsorgan, som är inrättat att känna av den elektriska effekt som produceras av nämnda generator för framtagande av ett ef- lO l5 20 25 30 35 s 510115 inrättad att bilda en första styrsignal vilken tar hänsyn till ett ef- fektärvärde, en första regulator, som är fektbörvärde och nämnda effektärvärde och med vilken ven- tilanordningen är inställbar. Därvid kan regleranordningen vara inrättad att bilda nämnda effektbörvärde med hänsyn tagen till anläggningens belastning.According to an embodiment of the invention, the control of said supply of combustible gas can be realized in that the control device comprises a power sensing means, which is arranged to sense the electric power produced by said generator for producing a power sensing device arranged in 510115. to form a first control signal which takes into account an effector value, a first regulator, which is the effect setpoint and said effect value and with which the valve device is adjustable. In this case, the control device can be arranged to form said power setpoint, taking into account the load of the system.
Enligt en ytterligare utföringsform av uppfinningen inne- fattar som är inrättat att känna av temperaturen hos förbrän- regleranordningen ett temperaturavkänningsorgan, ningsgaserna i området av gasturbinanordningens inlopp för framtagande av ett temperaturärvärde, och en andra regula- tor, som är inrättad att bilda en andra styrsignal vilken tar hänsyn till ett temperaturbörvärde och nämnda tempera- turärvärde och med vilken ventilanordningen är inställbar.According to a further embodiment of the invention, which is arranged to sense the temperature of the combustion control device comprises a temperature sensing means, the sensing gases in the area of the gas turbine device inlet for producing a temperature value, and a second regulator which is arranged to form a second control signal. which takes into account a temperature setpoint and said temperature value and with which the valve device is adjustable.
Därvid kan med fördel regleranordningen innefatta ett väl- jarorgan som är inrättat att välja den minsta av den första och andra styrsignalen för styrning av nämnda till- försel av brännbar gas till efterbrännanordningen.In this case, the control device can advantageously comprise a selector means which is arranged to select the smallest of the first and second control signal for controlling said supply of combustible gas to the afterburning device.
Enligt en ytterligare utföringsform av uppfinningen inne- fattar regleranordningen en första beräkningsenhet som är inrättad att bilda ett börvärde för höjden hos den fluidi- serade bädden genom framkoppling' av' effektbörvärdet för styrning av bäddens höjd. Pâ så sätt kan bäddhöjden snabbt anpassas till anläggningens efterfrågade effekt.According to a further embodiment of the invention, the control device comprises a first calculation unit which is arranged to form a setpoint for the height of the fluidized bed by supplying the power setpoint for controlling the height of the bed. In this way, the bed height can be quickly adapted to the system's required power.
Enligt en ytterligare utföringsform av uppfinningen inne- fattar kraftanläggningen en av gasturbinanordningen driven kompressoranordning som är inrättad att tillföra ett flöde av en syrehaltig gas till brännkammaren, varvid regler- anordningen innefattar en andra beräkningsenhet som är in- rättad att bilda ett börvärde för nämnda flöde genom fram- koppling av effektbörvärdet för styrning av nämnda flöde.According to a further embodiment of the invention, the power plant comprises a compressor device driven by the gas turbine device which is arranged to supply a flow of an oxygen-containing gas to the combustion chamber, the control device comprising a second calculation unit which is arranged to form a setpoint for said flow by supplying the power setpoint for controlling said flow.
Pâ så sätt kan även gasflödet till brännkammaren och genom 10 15 20 25 30 35 U1 ...A 0115 kraftanläggningen snabbt anpassas till anläggningens ef- terfrågade effekt.In this way, the gas flow to the combustion chamber and through the 10 15 20 25 30 35 U1 ... A 0115 power plant can also be quickly adapted to the plant's required demand.
Enligt en ytterligare utföringsform av uppfinningen inne- fattar kraftanläggningen en förgasningsanordning som är inrättad att framställa nämnda brännbara gas och ett led- ningsorgan som är inrättat att tillföra syrehaltig gas till förgasningsanordningen, varvid regleranordningen är inrättad att styra tillförseln av syrehaltig gas med hän- syn tagen till tillförseln av' brännbar gas till efter- brännanordningen. Med fördel är regleranordningen inrättad att styra tillförseln av syrehaltig gas till förgasnings- anordningen på så sätt att ett tryckfall av ett bestämt erhålls Med ett tryckfall underlättas regleringen av tillförseln av bränn- värde över ventilanordningen. sådant bar gas eftersom det medför en god förutsägbarhet av för- hållandet mellan ventilanordningens öppningsgrad och flö- det.According to a further embodiment of the invention, the power plant comprises a gasification device which is arranged to produce said combustible gas and a line means which is arranged to supply oxygen-containing gas to the gasification device, the control device being arranged to control the supply of oxygen-containing gas with regard to to the supply of combustible gas to the afterburner. Advantageously, the control device is arranged to control the supply of oxygen-containing gas to the gasification device in such a way that a pressure drop of a certain is obtained. With a pressure drop, the control of the supply of calorific value over the valve device is facilitated. such a bare gas because it provides a good predictability of the relationship between the degree of opening of the valve device and the flow.
Det ovan nämnda ändamålet uppnås också med det inlednings- vis angivna förfarande som kännetecknas av att den elek- triska effekten som produceras av nämnda generator regle- ras på ett väsentligen kontinuerligt sätt medelst en reg- leranordning genom styrning av tillförseln av brännbar gas till efterbrännanordningen.The above-mentioned object is also achieved with the initially stated method which is characterized in that the electric power produced by said generator is regulated in a substantially continuous manner by means of a control device by controlling the supply of combustible gas to the afterburning device.
Fördelaktiga utföringsformer av förfarandet anges i de be- roende kraven 12 - 18.Advantageous embodiments of the method are set out in the dependent claims 12 - 18.
KORT BESKRIVNING AV RITNINGARNA skall av olika, såsom exempel angivna utföringsformer av vilka en Uppfinningen nu förklaras närmare med hjälp åskådliggörs på de bifogade ritningarna, pà vilka Fig 1 schematiskt visar en PFBC-kraftanläggning med en kombinerad gas- och ångcykel och 10 l5 20 25 30 35 v 510115 Fig 2 visar schematiskt uppbyggnaden av en del av en reg- leranordning hos anläggningen i Fig 1.BRIEF DESCRIPTION OF THE DRAWINGS Various embodiments, by way of example, of which the invention will now be explained, will be further illustrated by the accompanying drawings, in which Fig. 1 schematically shows a PFBC power plant with a combined gas and vapor cycle and Fig. 2 schematically shows the construction of a part of a control device of the plant in Fig. 1.
DETALJERAD BESKRIVNING AV OLIKA UTFÖRINGSFORMER En PFBC-kraftanläggning, dvs en anläggning för förbränning av partikulärt bränsle i en trycksatt fluidiserad bädd, Fig 1. som är inrymd i ett tryckkärl 2, kan ha en volym i storleksordningen 104m3 innefattar en vilket visas schematiskt i Anläggningen brännkammare 1, och vilket kan (abs). i det visade exemplet luft, trycksättas till exempelvis cirka 16 bar Komprime- rad syrehaltig gas, tillförs tryckkärlet 2 för trycksättning av brännkammaren 1 och för fluidisering av en bädd 3 i brännkammaren 1. Den komprime- rade luften tillföres brännkammaren 1 från tryckkärlet 2 via schematiskt antydda fluidiseringsmunstycken 4 smn är anordnade i botten av brännkammaren 1 för fluidisering av den i brännkammaren 1 inneslutna bädden 3. Bädden 3 utgörs av bäddmaterial, kornformig absorbent och ett partikulärt företrädesvis krossat kol som förbränns i den Bäddens 3 höjd kan styras genom inmatning från och utmatning till bäddma- känt sätt, Bäddmaterial kan sugas upp j. behållaren 5 bränsle, till bädden 3 förda fluidiseringsluften. terialbehållare 5 på i sig US-4,530,207. fràn bädden 3 via en utmatningsledning och matas in i bäd- exempelvis den 3 fràn behållaren 5 via en inmatningsledning som myn- nar i bädden 3 pá samma höjd som utmatningsledningen. Ut- matningen àstadkoms genom att en ventil 5' hos en förbin- delse till atmosfären öppnas. Inmatningen ástadkoms genom att en ventil 5" hos en fràn tryckkärlet 2 till inmat- ningsledningen sig sträckande ledning öppnas, varigenom bäddmaterialet kommer att matas in i bädden 3 medelst ejektorverkan. Förbränningsgaserna från bädden 3 förs se- dan via en reningsanläggning 6, vilken i exemplet utgörs av ett högtemperaturfilter, som kan vara av keramisk typ och som är avsett för höga temperaturer, och en inter- 10 15 20 25 30 35 510115 s ceptventil 7 vidare till en efterbrännanordning i form av en efterbrännkammare 8. Till efterbrännkammaren 8 föres även en brännbar gas via en ledning 9 fràn en förgas- ningsreaktor 10 via ett ytterligare högtemperaturfilter 11. Förgasningsreaktorn 10 är fristående, dvs anordnad åt- skild från brännkammaren 1 och utanför tryckkärlet 2. Flö- det av brännbar gas till efterbrännkammaren 8 regleras med hjälp av reglerventilen 12. I efterbrännkammaren 8 förbränns de brännbara gaserna i samband med tillförsel av komprimerad luft från en högtryckskompressor 13 med hjälp förbrän- visad brännare för Tillförseln av luft till efter- av en icke höjande av ningsgasernas temperatur. brännkammaren 8 kan regleras med hjälp av en reglerventil 14. De gaser som lämnar efterbrännkammaren 8 uppvisar en temperatur av cirka 1200 - 1500°C, vilket gör dem väl läm- pade som drivgas för drivande av en första gasturbin 15 i form av en högtrycksturbin. Genom efterbrännkammaren 8 har temperaturen pà nämnda förbränningsgaser således höjts frän cirka 850 - 950°C till 1200 - l500°C.DETAILED DESCRIPTION OF DIFFERENT EMBODIMENTS A PFBC power plant, i.e. a particulate fuel combustion plant in a pressurized fluidized bed, Fig. 1 housed in a pressure vessel 2, may have a volume of the order of 104m3. 1, and which can (abs). in the example shown air, is pressurized to, for example, about 16 bar Compressed oxygen-containing gas, is supplied to the pressure vessel 2 for pressurizing the combustion chamber 1 and for fluidizing a bed 3 in the combustion chamber 1. The compressed air is supplied to the combustion chamber 1 from the pressure vessel 2 via schematic The fluidization nozzles 4 smn are arranged at the bottom of the combustion chamber 1 for fluidizing the bed 3 enclosed in the combustion chamber 1. The bed 3 consists of bed material, granular absorbent and a particulate preferably crushed carbon which is combusted at the height of the bed 3 and to bed-made manner, Bed material can be sucked up j. the container 5 fuel, to the bed 3 the fluidizing air fed. material container 5 on per se US-4,530,207. from the bed 3 via a discharge line and is fed into the bed - for example the 3 from the container 5 via a feed line which opens into the bed 3 at the same height as the discharge line. The discharge is achieved by opening a valve 5 'of a connection to the atmosphere. The supply is effected by opening a valve 5 "of a line extending from the pressure vessel 2 to the supply line, whereby the bed material will be fed into the bed 3 by means of ejector action. The combustion gases from the bed 3 are then fed via a treatment plant 6, which in the example consists of a high-temperature filter, which may be of the ceramic type and which is intended for high temperatures, and an intercept valve 7 further to an afterburning device in the form of an afterburning chamber 8. To the afterburner 8 is also fed a combustible gas via a line 9 from a gasification reactor 10 via a further high-temperature filter 11. The gasification reactor 10 is independent, ie arranged separately from the combustion chamber 1 and outside the pressure vessel 2. The flow of combustible gas to the afterburning chamber 8 is regulated by means of the control valve 12. In the afterburner 8, the combustible gases are burned in connection with the supply of compressed air from a high-pressure compressor or 13 with the aid of a combustion burner for the supply of air following a non-increase in the temperature of the gases. the combustion chamber 8 can be regulated by means of a control valve 14. The gases leaving the afterburning chamber 8 have a temperature of about 1200 - 1500 ° C, which makes them well suited as propellant for driving a first gas turbine 15 in the form of a high pressure turbine. Through the afterburning chamber 8, the temperature of said combustion gases has thus been raised from about 850 - 950 ° C to 1200 - 1500 ° C.
Högtrycksturbinen 15 och högtryckskompressorn 13 är anord- cirka nade pá samma axel som en generator 16, ur vilken nyttig elektrisk energi kan uttagas. Högtryckskompressorn 13 le- vererar även komprimerad luft till PFBC-brännkammaren 1 via ledningen 17. Därvid är en interceptventil 18 anordnad mellan högtryckskompressorn 13 och brännkammaren 1. Hög- tryckskompressorn 13 levererar även luft via ledningen 19 till förgasningsreaktorn 10. Det restbränsle som bildas i förgasningsreaktorn 10 vid den brännbara gasens alstrande bädden 3 i brännkammaren 1. via en kan tillföras bränsleledning 20.The high-pressure turbine 15 and the high-pressure compressor 13 are arranged approximately on the same axis as a generator 16, from which useful electrical energy can be extracted. The high pressure compressor 13 also delivers compressed air to the PFBC combustion chamber 1 via line 17. An intercept valve 18 is arranged between the high pressure compressor 13 and the combustion chamber 1. The high pressure compressor 13 also delivers air via line 19 to the gasification reactor 10. The residual fuel formed in the gasification reactor 10 at the combustible gas generating bed 3 in the combustion chamber 1. via a fuel line 20 can be supplied.
Den i figuren visade PFBC-kraftanläggningen är av ett avancerat slag och uppvisar en ytterligare gasturbin 21, i form av en mellantrycksturbin, vilken är anordnad på samma axel 22 som högtrycksturbinen 15 och högtryckskompressorn 13. Den i högtrycksturbinen 15 expanderade och temperatur- 10 15 20 25 30 35 sänkta gasen leds till en ytterligare efterbrännanordning 23 som innefattar en så kallad reheatbrännkammare eller återuppvärmningsbrännkammare_ Reheatbrännkammaren 23 er- håller ett flöde av nämnda brännbara gaser, vilket regle- ras med hjälp av reglerventilen 24 och härrör från för- gasningsreaktorn 10, samt ett flöde av komprimerad luft från högtryckskompressorn 13, vilket regleras med hjälp av en reglerventil 25. De brännbara gaserna förbränns i re- heatbrännkammaren 23 medelst en icke närmare visad brän- nare och de så bildade heta gaserna blandas med förbrän- ningsgaserna från högtrycksturbinen 15 för att åter höja dessas temperatur innan de förs vidare via en ledning till På detta sätt mellantrycksturbinen 21 uttagna effekten höjas avsevärt. mellantrycksturbinen 21. kan den från De i nællantrycksturbinen 21 expanderade förbränningsga- serna föres till en lågtrycksturbin 26. De förbränningsga- ser som lämnar lågtrycksturbinen 26 innehåller fortfarande energi som kan tas tillvara i en economizer 27. Lågtrycks- turbinen 26 är anordnad på en andra axel 28 på vilken även en lågtryckskompressor 29 är anordnad. Làgtryckskompres- Låg- tryckskompressorn 29 drivs sålunda av lågtrycksturbinen 26 sorn 29 tillföres atmosfärsluft via ett filter 30. och förser från sitt utlopp högtryckskompressorn 13 med luft som har komprimerats i ett första steg. Lågtryckstur- binens 26 inlopp är försett med en flödesreglerande 31 med ledskovlar med vilken varvtalet på den andra axeln 28 kan anordning i form av en ledskenekrans styrbara varieras. Mellan lågtryckskompressorn 29 och högtrycks- kompressorn 13 är en mellankylare 32 anordnad för att sänka temperaturen på den luft som tillföres högtrycks- kompressorns 13 inlopp.The PFBC power plant shown in the figure is of an advanced type and has an additional gas turbine 21, in the form of an intermediate pressure turbine, which is arranged on the same shaft 22 as the high-pressure turbine 15 and the high-pressure compressor 13. The expansion and temperature in the high-pressure turbine 15 The reduced gas is led to a further afterburning device 23 which comprises a so-called reheat combustion chamber or reheating combustion chamber. The reheat combustion chamber 23 receives a flow of said combustible gases, which is regulated by means of the control valve 24 and originates from the gasification reactor 10, flow of compressed air from the high-pressure compressor 13, which is regulated by means of a control valve 25. The combustible gases are combusted in the heat burner chamber 23 by means of a burner (not shown) and the hot gases thus formed are mixed with the combustion gases from the high-pressure turbine 15 to raise their temperature again before passing them on via a line to On it take the medium pressure turbine 21 drawn power is significantly increased. the medium-pressure turbine 21. the combustion gases expanded from the low-pressure turbine 21 can be fed to a low-pressure turbine 26. The combustion gases leaving the low-pressure turbine 26 still contain energy which can be utilized in an economizer 27. The low-pressure turbine 26 is arranged on a second shaft 28 on which also a low-pressure compressor 29 is arranged. The low-pressure compressor The low-pressure compressor 29 is thus driven by the low-pressure turbine 26. The air 29 is supplied with atmospheric air via a filter 30. and supplies from its outlet the high-pressure compressor 13 with air which has been compressed in a first stage. The inlet of the low-pressure turbine 26 is provided with a flow regulating 31 with guide vanes with which the speed of the second shaft 28 can be varied in a controllable manner in the form of a guide rail ring. Between the low-pressure compressor 29 and the high-pressure compressor 13, an intercooler 32 is arranged to lower the temperature of the air supplied to the inlet of the high-pressure compressor 13.
Vidare uppvisar kraftanläggningen en ångkrets 33 som visas schematiskt och som innefattar en ångturbin för drivning av en generator för generering av elektrisk effekt och ett lO 15 20 25 30 35 518115 io tubarrangemang 34 vilket är anordnat i den fluidiserade bädden 3 och överhettas genom värmeväxling mellan tuberna och bäddmate- i vilket vatten cirkuleras, förángas och rialet för upptagande av vid den i. bädden 13 genomförda förbränningen alstrad värme.Furthermore, the power plant has a steam circuit 33 which is shown schematically and which comprises a steam turbine for driving a generator for generating electric power and a tube arrangement 34 which is arranged in the fluidized bed 3 and is overheated by heat exchange between the tubes. and bed material in which water is circulated, evaporated and the material for absorbing heat generated during the combustion carried out in the bed 13.
Den fràn högtryckskompressorn 13 kommande ledningen 19 för tillförsel av komprimerad luft till förgasningsreaktorn 10 innefattar en kompressoranordning 35, som i det visade ex- emplet utgörs av en så kallad booster-kompressor och som drivs med en elektrisk drivmotor 36. Medelst booster- kompressorn 35 kan gastrycket hos den luft som tillförs förgasningsreaktorn 10 ökas ytterligare, då det är önsk- värt att det gasflöde som förgasningsreaktorn 10 levererar till och/eller reheatbrännkammaren 23 anländande flödet av för- har ett högre tryck än det efterbrännkammaren 8 bränningsgas. Därigenom kan de brännbara gaserna i varje given trycksituation enkelt tillföras efterbrännkammaren 8 och/eller reheatbrännkammaren 23. I förgasningsreaktorn 10 förgasas ett flytande eller fast bränsle, i detta exempel som vid en understökiometrisk process på Om kol Genom att på detta partikulärt kol, känt sätt alstrar brännbara gaser. används kan förgasningen ske helt eller delvis. en fristående som sätt anordna förgasningsreaktor 10, arbetar vid högre tryck än PFBC-bädden 3, fås ett tryck- fall över reglerventilerna 12 och 24, vilket möjliggör ef- fektiv reglering av bränsleflödet och en jämn fördelning av bränsleflödet i dessa brännkammare 8, 23. Således kan vid eventuellt 16 bars tryck i PFBC-brännkammaren 1 ett tryck av cirka 18-30 bar àstadkommas i förgasningsreaktorn l0.The line 19 coming from the high-pressure compressor 13 for supplying compressed air to the gasification reactor 10 comprises a compressor device 35, which in the example shown consists of a so-called booster compressor and which is driven by an electric drive motor 36. By means of the booster compressor 35, the gas pressure of the air supplied to the gasification reactor 10 is further increased, as it is desirable that the gas flow which the gasification reactor 10 supplies to and / or the reheat combustion chamber 23 arriving the flow of pre has a higher pressure than the afterburning chamber 8 combustion gas. Thereby, the combustible gases in any given pressure situation can easily be supplied to the afterburning chamber 8 and / or the reheat combustion chamber 23. In the gasification reactor 10 a liquid or solid fuel is gasified, in this example as in a subchiometric process of Om coal By generating known particles in this particular coal combustible gases. used, the gasification can take place in whole or in part. a stand-alone gasification reactor 10, operating at a higher pressure than the PFBC bed 3, a pressure drop is obtained across the control valves 12 and 24, which enables efficient control of the fuel flow and an even distribution of the fuel flow in these combustion chambers 8, 23. Thus, at a possible pressure of 16 bar in the PFBC combustion chamber 1, a pressure of about 18-30 bar can be achieved in the gasification reactor 10.
Anläggningen innefattar vidare en regleranordning 37 för kontinuerlig reglering av den elektriska effekt som produ- ceras av anläggningens generator 16. Regleranordningen 37 är därvid ansluten till de tvà reglerventilerna 12 och 24 10 15 20 25 30 35 11 510115 för styrning av tillförseln av brännbar gas till efter- brännkammaren 8 respektive reheatbrännkammaren 23, till booster-kompressorns 35 drivmotor 36, till ledskenekransen 31 för styrning av flödet till lágtrycksturbinen 26 och och 5" rade bäddens 3 höjd. Regleranordningen 37 är också anslu- till ventilerna 5' för styrning av den fluidise- ten till en mängd olika avkänningsorgan för att känna av olika parametrar som underlättar anläggningens reglering.The system further comprises a control device 37 for continuous control of the electrical power produced by the plant generator 16. The control device 37 is then connected to the two control valves 12 and 24 10 15 20 25 30 35 11 510115 for controlling the supply of combustible gas to the afterburner chamber 8 and the reheat combustion chamber 23, respectively, to the drive motor 36 of the booster compressor 35, to the guide rail ring 31 for controlling the flow to the low pressure turbine 26 and and the height of the 5 "bed 3. The control device 37 is also connected to the valves 5 'for controlling the fluidized to a variety of sensing means for sensing various parameters that facilitate the regulation of the installation.
Dessa avkänningsorgan innefattar ett effektavkänningsorgan 38 som är inrättat att känna av den elektriska effekt som produceras av generatorn 16, ett första temperaturavkän- ningsorgan 39 som är inrättat att känna av temperaturen hos förbränningsgaserna i området av högtrycksturbinens 15 inlopp, ett andra temperaturavkänningsorgan 40 som är in- rättat att känna av temperaturen hos förbränningsgaserna i området av mellantrycksturbinens 21 inlopp, ett avkän- ningsorgan 41 som är inrättat att känna av aktuell höjd hos den fluidiserade bädden 3, ett avkänningsorgan 42 som är inrättat att känna av en parameter hos flödet av bränn- bar gas till efterbrännkammaren 8 och ett avkänningsorgan 43 som är inrättat att känna av en parameter hos flödet av brännbar gas till reheatkammaren 23. Det skall noteras att här bara har angivits ett urval av de avkänningsorgan och till regleranordning 37 är ansluten. styrinrättningar vilka anläggningens övergripande Det finns också många be- gränsningsparametrar som man måste ta hänsyn till vid an- läggningens reglering, kärlet 2, tryckförhållandet mellan in- och utlopp hos kompressorerna såsom exempelvis trycket i tryck- temperaturen i mellankylarens 32 luftutlopp, 13 och 29, den fluidiserade bäddens 3 temperatur etc.These sensing means comprise a power sensing means 38 which is arranged to sense the electric power produced by the generator 16, a first temperature sensing means 39 which is arranged to sense the temperature of the combustion gases in the area of the inlet of the high pressure turbine 15, a second temperature sensing means 40 which is in corrected to sense the temperature of the combustion gases in the area of the inlet of the intermediate pressure turbine 21, a sensing means 41 which is arranged to sense the current height of the fluidized bed 3, a sensing means 42 which is arranged to sense a parameter of the flow of the combustion gas. bare gas to the afterburning chamber 8 and a sensing means 43 which is arranged to sense a parameter of the flow of combustible gas to the reheat chamber 23. It should be noted that only a selection of the sensing means has been specified here and to control device 37 is connected. There are also many limiting parameters that must be taken into account when regulating the system, the vessel 2, the pressure ratio between inlet and outlet of the compressors such as the pressure in the pressure temperature in the intercooler 32 air outlets, 13 and 29, the temperature of the fluidized bed 3, etc.
Pig 2 visar schematiskt uppbyggnaden av en del av en reg- leranordning hos anläggningen i Pig 1. Med hjälp av ef- fektavkänningsorganet 38 erhålls ett effektärvärde ea ge- nom avkänning av den elektriska effekt som produceras av generatorn 16. Ett effektbörvärde eb bildas med hänsyn ta- 10 15 20 25 30 35 51Û 115 12 gen till anläggningens momentana belastning, dvs den ef- fekt som efterfrågas från det elnät till vilket anlägg- ningen är ansluten. Skillnaden mellan effektbörvärdet eb och effektärvärdet ea tillförs en första regulator 44, som inrättad att kan innefatta en PI-regulator och som är bilda en första styrsignal.Fig. 2 schematically shows the construction of a part of a control device of the plant in Fig. 1. By means of the power sensing means 38 a power value is obtained ea by sensing the electric power produced by the generator 16. A power setpoint eb is formed with regard to 10 15 20 25 30 35 51Û 115 12 12 to the instantaneous load of the system, ie the power required from the mains to which the system is connected. The difference between the power setpoint eb and the power value ea is applied to a first controller 44, which is arranged to comprise a PI controller and which is to form a first control signal.
På motsvarande sätt erhålls ett temperaturärvärde tia för temperaturen hos förbränningsgaserna genom avkänning av temperaturen vid högtrycksturbinens 15 respektive mellan- trycksturbinens 21 inlopp. Ett motsvarande temperaturbör- värde tm bildas och skillnaden mellan temperaturbörvärdet tm och temperaturärvärdet tm tillförs en andra regulator 45, som också kan innefatta en PI-regulator och som är in- rättad att bilda en andra styrsignal.Correspondingly, a temperature value ten is obtained for the temperature of the combustion gases by sensing the temperature at the inlet of the high-pressure turbine 15 and the medium-pressure turbine 21, respectively. A corresponding temperature setpoint tm is formed and the difference between the temperature setpoint tm and the temperature setpoint tm is applied to a second controller 45, which may also include a PI controller and which is arranged to form a second control signal.
De så bildade styrsignalerna tillförs ett väljarorgan 46 som innefattar en så kallad min-väljare och som är inrät- tat att välja den minsta av den första och andra styrsig- nalen såsom reglerande styrsignal. Med den valda styrsig- nalen justeras öppningsgraden hos reglerventilerna 12 och 24, dvs tillförseln av brännbar gas till efterbrännkamma- ren 8 respektive till reheatbrännkammaren 23. För att yt- terligare förbättra samordningen mellan de erhållna styr- signalerna är det dessutom möjligt att utnyttja så kallad följning, dvs den icke reglerande styrsignalen justeras med hjälp av en ej visad separat krets på så sätt att den alltid är något högre, exempelvis 2 - %, än den regle- rande styrsignalen. På så vis fås ett snabbare övertagande när min-väljaren 46 övergår från en styrsignal till den andra.The control signals thus formed are supplied to a selector means 46 which comprises a so-called min-selector and which is arranged to select the smallest of the first and second control signal as a control control signal. With the selected control signal, the degree of opening of the control valves 12 and 24 is adjusted, ie the supply of combustible gas to the afterburning chamber 8 and to the reheat combustion chamber 23, respectively. To further improve the coordination between the obtained control signals, it is also possible to use so-called tracking, ie the non-regulating control signal is adjusted by means of a separate circuit (not shown) in such a way that it is always slightly higher, for example 2%, than the regulating control signal. In this way, a faster takeover is obtained when the min selector 46 transitions from one control signal to the other.
I syfte att bädden 3 till den efterfrågade effekten framkopplas ef- snabbt anpassa höjden hos den fluidiserade fektbörvärdet eb till en tredje regulator 47 för styrning av ventilerna 5' och 5" som reglerar bäddmaterialbehålla- 10 15 20 25 30 35 13 510115 rens 5 inmatning respektive utmatning av bäddmaterial till och från bädden 3. Denna framkoppling erhålls med hjälp av en beräkningsenhet 48 som innefattar en lead-lag-funktion, hos vilken förstärkningen kallad dvs en förstärkande enhet 49, kan variera och vilken kan utgöras av en så funktionsgenerator, och en deriverande enhet SO.In order for the bed 3 to be fed to the requested power, the height of the fluidized power setpoint eb is quickly coupled to a third regulator 47 for controlling the valves 5 'and 5 "which regulate the input of the bed material container 5 and discharge of bed material to and from the bed 3. This feed is obtained by means of a calculation unit 48 which comprises a lead-layer function, in which the gain called i.e. a reinforcing unit 49, can vary and which can be constituted by such a function generator, and a derivative unit SO.
I syfte att dessutom snabbt anpassa tillförseln av luft till brännkammaren 1 till den efterfrågade effekten fram- kopplas effektbörvärdet eb även till en fjärde regulator 51 för styrning av ledskenekransen 31 med vilken gasflödet genom anläggningen. kan regleras. Denna framkoppling er- hålls med hjälp av en ytterligare beräkningsenhet 52 som också innefattar en lead-lag-funktion, dvs en förstärkande enhet 53, kan utgöras av en så kallad funktionsgenerator, och en de- hos vilken förstärkningen kan variera och vilken riverande enhet 54.In addition, in order to quickly adapt the supply of air to the combustion chamber 1 to the requested power, the power setpoint eb is also fed to a fourth regulator 51 for controlling the guide rail ring 31 with which the gas flow through the plant. can be regulated. This feedback is obtained by means of a further calculation unit 52 which also comprises a lead-lag function, i.e. a amplifying unit 53, can be constituted by a so-called function generator, and a de- in which the amplification can vary and which tearing unit 54 .
Regleranordningen 37 innefattar vidare en femte regulator 55 som är inrättad att bilda en styrsignal för att styra varvtalet hos booster-kompressorns 35 drivmotor 36 för att på så vis åstadkomma en styrning av tillförseln av luft till förgasningsanordningen 10. Med avkänningsorganen 42, 43 erhålls ett ärvärde för en parameter hos flödet av brännbar gas, exempelvis trycket uppströms och nedströms om reglerventilerna 12 och 24, dvs tryckfallet över dessa ventiler. Genom att booster-kompressorn styrs på så sätt att dessa tryckfall, åtminstone under stationär drift, alltid uppgår till ett bestämt värde underlättas regle- ringen av tillförseln av brännbar gas till efterbrännkam- maren 8 respektive reheatbrännkammaren 23.The control device 37 further comprises a fifth regulator 55 which is arranged to form a control signal for controlling the speed of the drive motor 36 of the booster compressor 35 in order thus to provide a control of the supply of air to the gasification device 10. With the sensing means 42, 43 an actual value is obtained. for a parameter of the flow of combustible gas, for example the pressure upstream and downstream of the control valves 12 and 24, ie the pressure drop across these valves. Because the booster compressor is controlled in such a way that these pressure drops, at least during stationary operation, always amount to a certain value, the control of the supply of combustible gas to the afterburning chamber 8 and the reheat combustion chamber 23, respectively, is facilitated.
Det är också möjligt att som alternativ eller komplement till varvtalsregleringen anordna en ledskeneanordning, ex- empelvis i form av medelst ett manöverdon styrbara led- skovlar på en ledskenekrans, i eller framför booster- lO l5 20 10115 14 kompressorn 35 för att reglera luftflödets storlek genom densamma och således mängden luft som tillförs förgas- ningsreaktorn 10. Manöverdonet är därvid anslutet till regleranordningen 37. (ej vi- Kraftanläggningen innefattar vidare anordningar sade) för tillförsel av bränsle till brännkammaren 1 och förgasningsanordningen 10. Därvid är med fördel regler- anordningen 37 även inrättad att styra bränsletillförseln till förgasningsreaktorn 10 med hänsyn tagen till tillför- seln av brännbar gas till efterbrännkammaren 8 respektive reheatbrännkammaren 23.It is also possible, as an alternative or complement to the speed control, to arrange a guide rail device, for example in the form of controllable guide vanes on a guide rail ring by means of an actuator, in or in front of the booster compressor 35 to regulate the size of the air flow through the same and thus the amount of air supplied to the gasification reactor 10. The actuator is then connected to the control device 37. (not vi- The power plant further comprises devices said) for supplying fuel to the combustion chamber 1 and the gasification device 10. In this case, the control device 37 is advantageously also arranged to control the fuel supply to the gasification reactor 10 taking into account the supply of combustible gas to the afterburning chamber 8 and the reheat combustion chamber 23, respectively.
Uppfinningen är inte pá något sätt begränsad till den ovan beskrivna utföringsformen utan en mängd möjligheter till modifikationer därav är möjliga inom ramen för de efter- följande patentkraven och torde vara uppenbara för en fackman pá området, utan att denne för den skull avviker från uppfinningens grundtanke. Exempelvis är uppfinningen även tillämplig pà en anläggning som endast uppvisar två gasturbiner, dvs att mellantrycksturbinen 26 är utlämnad.The invention is in no way limited to the embodiment described above, but a number of possibilities for modifications thereof are possible within the scope of the following claims and should be obvious to a person skilled in the art, without this departing from the basic idea of the invention. For example, the invention is also applicable to a plant which has only two gas turbines, ie that the intermediate pressure turbine 26 is dispensed.
Claims (18)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SE9800641A SE510115C2 (en) | 1998-03-02 | 1998-03-02 | Power plant and method for regulating its effect |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SE9800641A SE510115C2 (en) | 1998-03-02 | 1998-03-02 | Power plant and method for regulating its effect |
Publications (3)
Publication Number | Publication Date |
---|---|
SE9800641D0 SE9800641D0 (en) | 1998-03-02 |
SE9800641L SE9800641L (en) | 1999-04-19 |
SE510115C2 true SE510115C2 (en) | 1999-04-19 |
Family
ID=20410363
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SE9800641A SE510115C2 (en) | 1998-03-02 | 1998-03-02 | Power plant and method for regulating its effect |
Country Status (1)
Country | Link |
---|---|
SE (1) | SE510115C2 (en) |
-
1998
- 1998-03-02 SE SE9800641A patent/SE510115C2/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
SE9800641D0 (en) | 1998-03-02 |
SE9800641L (en) | 1999-04-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101449040B (en) | Goal gasification composite power generating system, and running control method thereof | |
EP2173976B1 (en) | Igcc design and operation for maximum plant output and minimum heat rate | |
US6199366B1 (en) | Gas turbine | |
WO2006129398A1 (en) | Gasification hybrid power generation equipment and method for controlling the same | |
US11300288B2 (en) | Method and a system for maintaining steam temperature with decreased loads of a steam turbine power plant comprising a fluidized bed boiler | |
US20070193249A1 (en) | Air pressure control device in integrated gasification combined cycle system | |
CN104011183B (en) | Fuel gasification system, its control method and sequence of control and possess the fuel gasification compound electricity generation system of fuel gasification system | |
JP4885199B2 (en) | Gas turbine operation control apparatus and method | |
US6247301B1 (en) | Gasifier and a power plant | |
CN105143638B (en) | The control method of the control device of gasification power generation plant, gasification power generation plant and gasification power generation plant | |
SE510115C2 (en) | Power plant and method for regulating its effect | |
KR101735989B1 (en) | Gasification power plant control device, gasification power plant, and gasification power plant control method | |
JP2716668B2 (en) | Gas turbine control device | |
JP5151921B2 (en) | Combined power generation method and apparatus using two-column gasifier | |
KR100462252B1 (en) | A power plant | |
JP3755242B2 (en) | Steam temperature controller for pressurized fluidized bed boiler | |
EP3415816B1 (en) | A method and a system for extending the load range of a power plant comprising a boiler supplying steam to a steam turbine | |
SE505570C2 (en) | power plant | |
JP3794074B2 (en) | Steam temperature control method and apparatus in pressurized fluidized bed boiler | |
EP0866914A1 (en) | A pfbc-power plant | |
SE509958C2 (en) | power plant | |
JPH08177413A (en) | Main steam temperature controller for exhaust gas re-combustion combined cycle plant | |
JPH1038201A (en) | Method and apparatus for controlling outlet water temperature of gas high-pressure feed water heater in exhaust reburning combined cycle plant | |
SE509988C2 (en) | power plant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
NUG | Patent has lapsed |
Ref document number: 9800641-4 Format of ref document f/p: F |