RU2695908C1 - Well completion method - Google Patents

Well completion method Download PDF

Info

Publication number
RU2695908C1
RU2695908C1 RU2018127258A RU2018127258A RU2695908C1 RU 2695908 C1 RU2695908 C1 RU 2695908C1 RU 2018127258 A RU2018127258 A RU 2018127258A RU 2018127258 A RU2018127258 A RU 2018127258A RU 2695908 C1 RU2695908 C1 RU 2695908C1
Authority
RU
Russia
Prior art keywords
pressure
perforation
acid
mpa
perforator
Prior art date
Application number
RU2018127258A
Other languages
Russian (ru)
Inventor
Рашит Марданович Миннуллин
Руслан Рустямович Фасхутдинов
Original Assignee
Публичное акционерное общество "Татнефть" имени В.Д. Шашина
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Публичное акционерное общество "Татнефть" имени В.Д. Шашина filed Critical Публичное акционерное общество "Татнефть" имени В.Д. Шашина
Priority to RU2018127258A priority Critical patent/RU2695908C1/en
Application granted granted Critical
Publication of RU2695908C1 publication Critical patent/RU2695908C1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/11Perforators; Permeators
    • E21B43/114Perforators using direct fluid action on the wall to be perforated, e.g. abrasive jets

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Manufacture And Refinement Of Metals (AREA)

Abstract

FIELD: oil and gas industry.SUBSTANCE: invention relates to oil industry and can be used in completion of wells. At well completion, drilling is performed with drilling of productive formation, lowering of production string, cementing of annulus space, perforation, treatment with acid and swabbing. During perforation lowering into the production string the assembly from the tubing string with piercing action perforator, performing perforation on process water with piercing perforator of production string and cement in annular space in interval of productive formation, after each actuation of perforator through perforator and formed perforation holes caverns in productive formation are washed in process water in amount of 2.5–3.5 mper 1 perforation at pressure 15–16 MPa with flow rate of 3.5–4 l/s. During treatment of the bed with acid, stepped acid treatment of the perforation interval is carried out with acid pumping and organization of acid baths under pressure with process water with stepped pressure increase at each stage until well injection capacity is not less than 0.5 l/s at pressure of 3–5 MPa. Swabbing is carried out in three stages with intensive extraction in amount of 0.5 mfor 20–30 minutes at first and second stages and low-intensity extraction in volume of 0.5 m45–60 minutes at the third stage. Process water used is water with density which provides back pressure to the formation, which includes a surfactant in amount of 0.1–0.3 wt% and a neutraliser of hydrogen sulphide of 0.08–0.12 wt%.EFFECT: technical result is reduced risk of water flooding.1 cl

Description

Изобретение относится к нефтедобывающей промышленности и может быть использовано при заканчивании скважин.The invention relates to the oil industry and can be used when completing wells.

Известен способ заканчивания скважины, согласно которому снабжают скважину обсадной колонной до кровли продуктивного пласта из обсаженной скважины. При этом в скважине определяют нефтенасыщенные пропластки. Расширяют открытый ствол скважины в зонах нефтенасыщенных пропластков и одновременно промывают нефтью. После этого обрабатывают расширенный ствол скважины гидроструйной подачей раствора кислоты через насадку для гидропескоструйной перфорации (Патент РФ №2182651, опубл. 20.05.2002).A well-known method of well completion, according to which the casing is supplied with a well to the roof of the producing formation from a cased well. At the same time, oil-saturated layers are determined in the well. Extend the open hole in the zones of oil-saturated interlayers and at the same time washed with oil. After that, the extended borehole is treated with a hydro-jet supply of an acid solution through a nozzle for hydro-sand-jet perforation (RF Patent No. 2182651, publ. 05.20.2002).

Известен способ заканчивания скважины, включающий спуск и цементирование эксплуатационной колонны, разбуривание цементного стакана с последующим созданием ствола в интервале продуктивного пласта, создание каверн и перемычек в интервале продуктивного пласта и в перемычках осуществление зондовой перфорации (патент РФ №2533783, опубл. 20.11.2014).A well-known method of well completion, including the launching and cementing of the production string, drilling a cement cup with the subsequent creation of a trunk in the interval of the reservoir, creating caverns and jumpers in the interval of the reservoir and in the bridges, the implementation of probe perforation (RF patent No. 2533783, publ. 20.11.2014) .

Наиболее близким к предложенному изобретению по технической сущности является способ обработки продуктивного карбонатного пласта, который предусматривает вскрытие бурением продуктивного пласта с промывкой буровым полимерным раствором, цементирование колонны и перфорацию ее путем сверления на большую глубину с интервалом между перфорационными отверстиями 1-3 м, спуск колонны насосно-компрессорных или бурильных труб с пакером, разобщение им верхних перфорационных каналов от нижних одного из интервалов пласта, обработка пласта кислотой путем циркуляции их в заколонном пространстве. Для ускорения операции обработки и повышения ее эффективности одновременно с обработкой пласта в призабойной зоне под пакером циклически создают вакуум - разрежение, например, путем свабирования. При этом операцию обработки осуществляют, начиная с верхнего интервала у кровли пласта под давлением ниже давления гидроразрыва пласта, создаваемым над пакером через межтрубное пространство (патент РФ №2423604, опубл. 10.07.2011 -прототип).Closest to the proposed invention in technical essence is a method of processing a productive carbonate formation, which involves opening a drilling of a productive formation with washing with a drilling polymer solution, cementing the column and perforating it by drilling to a great depth with an interval between perforations of 1-3 m, lowering the column pump -compressor or drill pipes with a packer, uncoupling of the upper perforation channels from the lower one of the intervals of the formation, treatment of the formation of acids oh by circulating them in the annulus. To speed up the processing operation and increase its efficiency simultaneously with the formation treatment in the bottom-hole zone under the packer, vacuum vacuum is cyclically created, for example, by swabbing. In this case, the processing operation is carried out starting from the upper interval at the top of the formation under pressure below the hydraulic fracturing pressure created above the packer through the annulus (RF patent No. 2423604, publ. 07/10/2011 prototype).

Общим недостатком известных способов является большая склонность к обводнению скважин при размещении скважин в продуктивных пластах малой толщины вблизи от водонасыщенного пласта, что связано с риском прорыва вод из нижележащего водонасыщенного пласта.A common disadvantage of the known methods is the great tendency to watering wells when placing wells in productive formations of small thickness near the water-saturated formation, which is associated with the risk of water breakthrough from the underlying water-saturated formation.

В предложенном изобретении решается задача снижения риска обводнения скважины.The proposed invention solves the problem of reducing the risk of waterlogging wells.

Задача решается тем, что в способе заканчивания скважины, включающем вскрытие бурением продуктивного пласта, спуск эксплуатационной колонны, цементирование заколонного пространства, перфорацию, обработку кислотой и свабирование, согласно изобретению, при перфорации спускают в эксплуатационную колонну компоновку из колонны насосно-компрессорных труб с перфоратором прокалывающего действия, проводят перфорацию на технической воде прокалывающим перфоратором эксплуатационной колонны и цемента в заколонном пространстве в интервале продуктивного пласта, после каждого срабатывания перфоратора через перфоратор и образованные перфорационные отверстия намывают каверны в продуктивном пласте технической водой в объеме 2,5-3,5 м3 на 1 перфорационное отверстие при давлении 15-16 МПа с расходом 3,5-4 л/с, при обработке пласта кислотой проводят ступенчатую кислотную обработку интервала перфорации с продавкой кислоты и организацией кислотных ванн под давлением технической водой со ступенчатым увеличением давления на каждой ступени до появления приемистости скважины в объеме не менее 0,5 л/с при давлении 3-5 МПа, а свабирование проводят в три этапа с интенсивным отбором в объеме 0,5 м3 за 20-30 минут на первом и втором этапах и малоинтенсивным отбором в объеме 0,5 м3 за 45-60 минут на третьем этапе, при этом в качестве технической воды используют воду с плотностью, обеспечивающей противодавление на пласт, включающей поверхностно-активное вещество в количестве 0,1-0,3% по массе (масс.) и нейтрализатор сероводорода в количестве 0,08-0,12% по массе (масс.).The problem is solved in that in the method of completing a well, which includes drilling a producing formation, lowering the production string, cementing the annulus, perforating, acidizing and swabbing, according to the invention, during perforation, the assembly of the tubing string with a perforating perforator is lowered into the production string actions, carry out perforation on industrial water with a piercing perforator of the production casing and cement in the annular space in the range of reductive formation after each actuation perforator drill and through the perforations formed in the cavity namyvayut reservoir process water in the amount of 2.5-3.5 m 3 per one perforation at a pressure of 15-16 MPa at a rate of 3.5-4 L / c, during the treatment of the formation with acid, a stepwise acid treatment of the perforation interval is carried out with acid sales and the organization of acidic baths under pressure with process water with a stepwise increase in pressure at each stage until the injectivity of the well in a volume not exceeding it is 0.5 l / s at a pressure of 3-5 MPa, and swabbing is carried out in three stages with intensive selection in a volume of 0.5 m 3 for 20-30 minutes in the first and second stages and low-intensity selection in a volume of 0.5 m 3 45-60 minutes in the third stage, while water with a density that provides backpressure on the formation, including a surfactant in an amount of 0.1-0.3% by weight (mass.) and a hydrogen sulfide neutralizer in the amount of 0.08-0.12% by weight (mass.).

Сущность изобретенияSUMMARY OF THE INVENTION

Разработка ряда нефтяных залежей в карбонатных коллекторах осложнена малыми толщинами (менее 5 м) продуктивных пластов, отсутствием притока без проведения солянокислотной обработки и увеличения поверхности фильтрации жидкостей, а также близостью нижележащих водонасыщенных пластов. При заканчивании скважин в таких условиях при интенсификационных обработках, направленных на увеличение приемистости скважин, возникает опасность образования сообщения с нижележащим водонасыщенным пластом и обводнения скважины за счет прорыва вод из нижележащего водонасыщенного пласта. В предложенном изобретении решается задача снижения риска обводнения скважины при проведении интенсификационных обработок. Задача решается следующим образом.The development of a number of oil deposits in carbonate reservoirs is complicated by the small thicknesses (less than 5 m) of productive formations, the absence of influx without hydrochloric acid treatment and an increase in the surface of fluid filtration, and the proximity of the underlying water-saturated formations. When wells are completed in such conditions during stimulation treatments aimed at increasing the injectivity of the wells, there is a danger of forming a message with the underlying water-saturated formation and watering the well due to water breakthrough from the underlying water-saturated formation. The proposed invention solves the problem of reducing the risk of watering a well during stimulation treatments. The problem is solved as follows.

Вскрывают бурением продуктивный пласт. В скважину спускают эксплуатационную колонну до забоя, цементируют заколонное пространство, проводят выдержку для схватывания и твердения цемента. В скважине проводят операции, связанные с удалением остатков цемента, промывкой, шаблонированием, опрессовкой, т.е. готовят скважину к перфорации. Заполняют скважину технической водой. В качестве технической воды используют воду с плотностью, обеспечивающей противодавление на пласт, включающей поверхностно-активное вещество в количестве 0,1-0,3% (масс.) и нейтрализатор сероводорода в количестве 0,08 - 0,12% (масс.).Drilling a productive formation. The production casing is lowered to the bottom to the bottom, the annulus is cemented, holding is carried out to set and harden the cement. In the well, operations are carried out associated with the removal of cement residues, flushing, templating, crimping, i.e. prepare the well for perforation. Fill the well with technical water. As industrial water, water is used with a density that provides back pressure to the formation, including a surfactant in an amount of 0.1-0.3% (mass.) And a hydrogen sulfide neutralizer in an amount of 0.08 - 0.12% (mass.) .

В качестве поверхностно-активного вещества используют вещества типа МЛ-81, МЛ-81Б, ТН-МС и т.п.As a surfactant, substances of the type ML-81, ML-81B, TN-MS, etc. are used.

МЛ-81 выпускается по ТУ 2481-007-48482528-99. Представляет собой вязкую жидкость от желтого до коричневого цвета, температура застывания -30°СML-81 is produced according to TU 2481-007-48482528-99. It is a viscous liquid from yellow to brown in color, pour point -30 ° C

МЛ-81 Б выпускается по ТУ 2481-007-48482528-99. Представляет собой вязкую жидкость от желтого до коричневого цвета, температура застывания -30°СML-81 B is produced according to TU 2481-007-48482528-99. It is a viscous liquid from yellow to brown in color, pour point -30 ° C

Моющий реагент ТН-МС выпускается по ТУ 20.59.42-005-13004554-2017. Представляет собой прозрачную жидкость от бесцветного до коричневого цвета.The washing reagent TN-MS is produced according to TU 20.59.42-005-13004554-2017. It is a clear liquid from colorless to brown.

В качестве нейтрализатора сероводорода используют продукты НСТ, НСВУ-1, ТНХС-НС, СНПХ-1050, двуокись марганца и т.п.The products НСТ, НСВУ-1, ТНХС-НС, СНПХ-1050, manganese dioxide, etc. are used as a hydrogen sulfide neutralizer.

Продукт нейтрализатор сероводорода НСТ выпускается по ТУ 2458-003-57242740-2006. Представляет собой жидкость от бесцветного до серого цвета, температура застывания -35°С.The HCT hydrogen sulfide neutralizer product is produced according to TU 2458-003-57242740-2006. It is a colorless to gray liquid with a pour point of -35 ° C.

НСВУ-1- нейтрализатор сероводорода универсальный выпускается по ТУ 2458-001-50801389-2006, представляет собой комплекс реагентов, которые при совместном контакте с водой обеспечивают генерацию пены и нейтрализацию газообразного и растворенного сероводорода. Компоненты нейтрализатора сероводорода НСВУ-1-поступают в виде цилиндров, порошка или гранул различных размеров, упакованных в оболочку из картона или бумаги, и поставляются в картонных коробках иди деревянных ящиках.NSVU-1-universal hydrogen sulfide neutralizer is produced according to TU 2458-001-50801389-2006, it is a complex of reagents that, when combined with water, provide foam generation and neutralize gaseous and dissolved hydrogen sulfide. The components of the NSVU-1-hydrogen sulfide neutralizer come in the form of cylinders, powder or granules of various sizes, packed in a shell made of cardboard or paper, and are delivered in cardboard boxes or wooden boxes.

Нейтрализатор сероводорода ТНХС-НС, выпускается по ТУ2458-213-83459339-2010. Представляет собой жидкость без твердых примесей, от бесцветного до коричневого цвета.The hydrogen sulfide neutralizer TNHS-NS, is produced according to TU2458-213-83459339-2010. It is a liquid without solid impurities, from colorless to brown.

СНПХ-1050 выпускается по ТУ 2458-256-05765670-2008. Представляет собой жидкость желтоватого цвета.SNPCH-1050 is produced according to TU 2458-256-05765670-2008. It is a yellowish liquid.

Двуокись марганца соответствует ГОСТ 4470-79. Представляет собой порошок черного цвета.Manganese dioxide complies with GOST 4470-79. It is a black powder.

Проводят перфорацию прокалывающим перфоратором эксплуатационной колонны и цемента в заколонном пространстве в интервале продуктивного пласта. После каждого срабатывания перфоратора через перфоратор и образованные перфорационные отверстия (как правило, два отверстия при каждом срабатывании перфоратора) намывают каверны в продуктивном пласте технической водой в объеме 2,5-3,5 м3 на 1 перфорационное отверстие при давлении 14-16 МПа с расходом 3,5-4 л/с.Perforation is carried out by a piercing perforator of the production string and cement in the annulus in the interval of the reservoir. After each operation of the punch, through the punch and formed perforations (usually two holes each time the punch is triggered), caverns in the reservoir are filled with industrial water in a volume of 2.5-3.5 m 3 per 1 perforation at a pressure of 14-16 MPa s flow rate of 3.5-4 l / s.

Далее проводят обработку околоскважинного пространства кислотой по колонне насосно-компрессорных труб с перфоратором. Проводят ступенчатую кислотную обработку интервала перфорации с продавкой кислоты и организацией кислотных ванн под давлением технической водой со ступенчатым увеличением давления на каждой ступени до появления приемистости скважины. Наиболее предпочтительным является режим, при котором продавку кислоты производят под давлением, начиная с 3 МПа. Увеличение давления закачки осуществляют ступенчато по 1 МПа с выдержкой во времени в режиме ванны 15-60 минут, не превышая при этом давления опрессовки колонны. При этом критерием успешности кислотной обработки является достижение приемистости 0,5 л/с при давлении 3-5 МПа. Критерием прекращения кислотной обработки является увеличение приемистости более 1,5 л/с при давлении 3-5 МПа.Next, the near-borehole space is treated with acid along the tubing string with a perforator. Carry out stepwise acid processing of the perforation interval with the sale of acid and the organization of acid baths under pressure with process water with a stepwise increase in pressure at each stage until the injectivity of the well. Most preferred is a regimen in which the acid is forced under pressure, starting at 3 MPa. The injection pressure is increased stepwise by 1 MPa with a time delay in the bath mode of 15-60 minutes, without exceeding the pressure of the pressure testing of the column. In this case, the criterion for the success of acid treatment is the achievement of injectivity of 0.5 l / s at a pressure of 3-5 MPa. The criterion for the termination of acid treatment is an increase in injectivity of more than 1.5 l / s at a pressure of 3-5 MPa.

После реагирования кислоты в течение 2-4 часов скважину свабируют по колонне насосно-компрессорных труб с перфоратором..After the reaction of the acid for 2-4 hours, the well is swabbed along the tubing string with a perforator ..

Выполняют свабирование в три этапа с интенсивным отбором воды и газа на первом этапе, интенсивным отбором нефтяной эмульсии, нефти и газа на втором этапе, и малоинтенсивным отбором нефти и газа на третьем этапе.Swabbing is performed in three stages with intensive extraction of water and gas in the first stage, intensive extraction of oil emulsion, oil and gas in the second stage, and low-intensity extraction of oil and gas in the third stage.

Интенсивный отбор производится при откачке технологической жидкости с объемом в 0,5 м3 за 20-30 минут, малоинтенсивный отбор - 0,5 м3 за 45-60 минут.Intensive sampling is performed during pumping out of the technological fluid with a volume of 0.5 m 3 in 20-30 minutes, low-intensity sampling is 0.5 m 3 in 45-60 minutes.

В результате удается обеспечить необходимую продуктивность скважины без риска обводнения от нижележащего водонасыщенного пласта. Примеры конкретного выполненияAs a result, it is possible to ensure the necessary productivity of the well without the risk of flooding from the underlying water-saturated formation. Case Studies

Пример 1. Бурят скважину стволом диаметром 156 мм карбонатном пласте. Продуктивный пласт расположен на глубине 1159-1168 м, толщина пласта 9 м. Ниже расположен водонасыщенный пласт. В скважину до забоя спускают эксплуатационную колонну диаметром 114 мм. Цементируют заколонное пространство. Скважина заполнена водой плотностью 1 г/см3. После схватывания и твердения цемента в скважине проводят операции, связанные с удалением остатков цемента, промывкой, шаблонированием, опрессовкой, т.е. готовят скважину к перфорации. Заполняют скважину технической водой плотностью 1,16 г/см3, включающей 0,2% (масс.) поверхностно-активного вещества МЛ-81Б и 0,1% (масс.) нейтрализатора сероводорода - продукт нейтрализатор сероводорода НСТ.Example 1. Drill a well with a barrel with a diameter of 156 mm carbonate formation. The reservoir is located at a depth of 1159-1168 m, the thickness of the reservoir is 9 m. Below is a water-saturated reservoir. A production casing with a diameter of 114 mm is lowered into the well before the bottom. Cement annular space. The well is filled with water with a density of 1 g / cm 3 . After setting and hardening of cement in the well, operations are carried out associated with the removal of cement residues, washing, templating, crimping, i.e. prepare the well for perforation. The well is filled with technical water with a density of 1.16 g / cm 3 , including 0.2% (mass.) Of the ML-81B surfactant and 0.1% (mass.) Of a hydrogen sulfide neutralizer — a product of HCT hydrogen sulfide neutralizer.

В эксплуатационную колонну спускают компоновку, состоящую из колонны насосно-компрессорных труб с перфоратором прокалывающего действия марки ГМПП (гидромеханический прокалывающий перфоратор).An assembly consisting of a tubing string with a perforating gun of the GMPP grade (hydromechanical piercing perforator) is lowered into the production casing.

Проводят перфорацию прокалывающим перфоратором эксплуатационной колонны и цемента в заколонном пространстве в интервале 1168-1159 м продуктивного пласта. Выполняют 46 проколов - отверстий. После каждого срабатывания перфоратора через перфоратор и образованные перфорационные отверстия намывают каверны в продуктивном пласте технической водой плотностью 1,16 г/см3, включающей 0,2% (масс.) поверхностно-активного вещества МЛ- 81Б и 0,1% (масс.) нейтрализатора сероводорода - продукт нейтрализатор сероводорода НСТ, в объеме 3 м3 на 1 перфорационное отверстие при давлении 15 МПа с расходом 3,8 л/с.Perforation is carried out by piercing a production casing and cement perforator in the annulus in the interval 1168-1159 m of the productive formation. Perform 46 punctures - holes. After each actuation of the perforator through the perforator and formed perforations, cavities in the reservoir are washed with industrial water with a density of 1.16 g / cm 3 , including 0.2% (mass.) Of the ML-81B surfactant and 0.1% (mass. ) a hydrogen sulfide neutralizer - a product of an HCT hydrogen sulfide neutralizer, in a volume of 3 m 3 per 1 perforation hole at a pressure of 15 MPa with a flow rate of 3.8 l / s.

По колонне насосно-компрессорных труб с перфоратором закачивают 24%-ную соляную кислоту в объеме 3,57 м3 при открытой затрубной задвижке. Закрывают затрубную задвижку. Закачивают по колонне насосно-компрессорных труб ту же соляную кислоту при начальном давлении 3 МПа. Скважина при постоянной закачке не принимает. Проводят технологическую выдержку в режиме ванны 1 час, при этом давление с 3 МПа снижается до 1,5 МПа. Продавливают ту же соляную кислоту с дренированием при давлении 3 МПа. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту при давлении 4 МПа. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту в объеме 0,1 м3 за 1 час при давлении 5 МПа с ожиданием падения давления. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту в объеме 6,33 м3 с подъемом давления до 6 и постепенном снижении на конечном этапе до 4,5 МПа с оставлением кислотной ванны на 10 минут через каждые 500 л прокаченной кислоты. Продавливают соляную кислоту технической водой в объеме 4,6 м3 с оставлением кислотной ванны на 10 минут через каждые 500 л. Проводят ожидание на реагирование кислоты в течение 2 часов. Скважина принимает при давлении 4 МПа при постоянном расходе 0,8 л/с.24% hydrochloric acid in a volume of 3.57 m 3 with an annular valve open is pumped through a tubing string with a perforator. Close the annular valve. The same hydrochloric acid is pumped through the tubing string at an initial pressure of 3 MPa. A well with continuous injection does not accept. Spend technological exposure in the bath mode for 1 hour, while the pressure from 3 MPa decreases to 1.5 MPa. The hydrochloric acid is drained with drainage at a pressure of 3 MPa. A well with continuous injection does not accept. The same hydrochloric acid is injected at a pressure of 4 MPa. A well with continuous injection does not accept. The same hydrochloric acid is injected in a volume of 0.1 m 3 for 1 hour at a pressure of 5 MPa with the expectation of a pressure drop. A well with continuous injection does not accept. The same hydrochloric acid is pumped in a volume of 6.33 m 3 with a rise in pressure to 6 and a gradual decrease at the final stage to 4.5 MPa, leaving an acid bath for 10 minutes every 500 l of pumped acid. Hydrochloric acid is pushed with technical water in a volume of 4.6 m 3 , leaving an acid bath for 10 minutes every 500 l. Wait for the reaction of the acid for 2 hours. The well receives at a pressure of 4 MPa at a constant flow rate of 0.8 l / s.

Проводят первый этап свабирования с интенсивным отбором по колонне насосно-компрессорных труб с отбором 3 м3 воды плотностью 1,13 г/см3 и газа. Всего отсвабировано 25 м3. Наблюдают сильный газовый фактор.The first stage of swabbing is carried out with intensive sampling of the tubing string with the extraction of 3 m 3 of water with a density of 1.13 g / cm 3 and gas. A total of 25 m 3 was swabbed. Observe a strong gas factor.

Проводят второй этап свабирования с интенсивным отбором по колонне насосно-компрессорных труб с отбором 18 м3 густой эмульсии, нефти и газа.The second stage of swabbing is carried out with intensive sampling of the tubing string with sampling of 18 m 3 of thick emulsion, oil and gas.

Проводят третий этап свабирования с малоинтенсивным отбором по колонне насосно-компрессорных труб с отбором 4 м3 нефти с газом.The third stage of swabbing is carried out with low-intensity selection along the tubing string with the selection of 4 m 3 of oil and gas.

Поднимают компоновку из скважины, спускают насосное оборудование и осваивают скважину. В результате дебит скважины составил 12 т/сут. безводной нефти.They raise the layout from the well, lower the pumping equipment and develop the well. As a result, the flow rate of the well was 12 tons / day. anhydrous oil.

Пример 2. Выполняют как пример 1.Example 2. Perform as example 1.

Заполняют скважину технической водой плотностью 1,15 г/см3, включающей 0,1% (масс.) поверхностно-активного вещества МЛ- 81 и 0,08% (масс.) нейтрализатора сероводорода - НСВУ-1.The well is filled with technical water with a density of 1.15 g / cm 3 , including 0.1% (mass.) Of the surfactant ML-81 and 0.08% (mass.) Of a hydrogen sulfide neutralizer - NSVU-1.

После каждого срабатывания перфоратора через перфоратор и образованные перфорационные отверстия намывают каверны в продуктивном пласте технической водой плотностью 1,15 г/см3, включающей 0,1% (масс.) поверхностно-активного вещества МЛ-81 и 0,08% (масс.) нейтрализатора - НСВУ-1, в объеме 2,5 м3 на 1 перфорационное отверстие при давлении 15 МПа с расходом 3,5 л/с.After each actuation of the perforator through the perforator and the perforations formed, cavities in the reservoir are washed with industrial water with a density of 1.15 g / cm 3 , including 0.1% (mass.) Of the ML-81 surfactant and 0.08% (mass. ) neutralizer - NSVU-1, in a volume of 2.5 m 3 per 1 perforation hole at a pressure of 15 MPa with a flow rate of 3.5 l / s.

По колонне насосно-компрессорных труб с перфоратором закачивают 24%-ную соляную кислоту в объеме 4 м3 при открытой затрубной задвижке. Закрывают затрубную задвижку. Закачивают по колонне насосно-компрессорных труб ту же соляную кислоту при начальном давлении 3 МПа. Скважина не принимает. Проводят технологическую выдержку в режиме ванны 1 час, при этом давление с 3 МПа снижается до 1,5 МПа. Продавливают ту же соляную кислоту с дренированием при давлении 3 МПа. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту при давлении 4 МПа. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту в объеме 0,1 м3 за 1 час при давлении 5 МПа с ожиданием падения давления до 1,5 МПа. Поднимают давление до 5 МПа скважина начинает принимать с расходом 0,6 л/с, продавливают при давлении 5 МПа 8 м3 соляной кислоты 24%-ной концентрации. Оставляют на реагирование на 3 часа.24% hydrochloric acid is pumped through a tubing string with a perforator in a volume of 4 m 3 with an annular gate valve open. Close the annular valve. The same hydrochloric acid is pumped through the tubing string at an initial pressure of 3 MPa. The well does not accept. Spend technological exposure in the bath mode for 1 hour, while the pressure from 3 MPa decreases to 1.5 MPa. The hydrochloric acid is drained with drainage at a pressure of 3 MPa. A well with continuous injection does not accept. The same hydrochloric acid is injected at a pressure of 4 MPa. A well with continuous injection does not accept. The same hydrochloric acid is pumped in a volume of 0.1 m 3 for 1 hour at a pressure of 5 MPa with the expectation of a pressure drop of up to 1.5 MPa. The pressure is raised to 5 MPa; the well begins to be taken at a flow rate of 0.6 l / s; it is forced through at a pressure of 5 MPa, 8 m 3 of hydrochloric acid of 24% concentration. Leave to respond for 3 hours.

Скважина принимает при давлении 5 МПа при постоянном расходе 0,6 л/с.The well receives at a pressure of 5 MPa at a constant flow rate of 0.6 l / s.

Свабирование проводят в три этапа с интенсивным отбором воды и газа на первом этапе, интенсивным отбором нефтяной эмульсии, нефти и газа на втором этапе, и малоинтенсивным отбором и нефти и газа на третьем этапе.Swabbing is carried out in three stages with intensive extraction of water and gas in the first stage, intensive extraction of oil emulsion, oil and gas in the second stage, and low-intensity extraction of oil and gas in the third stage.

Поднимают компоновку из скважины, спускают насосное оборудование и осваивают скважину. В результате дебит скважины составил 14 т/сут. безводной нефти.They raise the layout from the well, lower the pumping equipment and develop the well. As a result, the flow rate of the well was 14 tons / day. anhydrous oil.

Пример 3. Выполняют как пример 1.Example 3. Perform as example 1.

Заполняют скважину технической водой плотностью 1,14 г/см3, включающей 0,3% (масс.) поверхностно-активного вещества ТН-МС и 0,12% (масс.) нейтрализатора сероводорода СНПХ-1050.The well is filled with technical water with a density of 1.14 g / cm 3 , including 0.3% (mass.) Of the TH-MS surfactant and 0.12% (mass.) Of a hydrogen sulfide neutralizer SNPCH-1050.

После каждого срабатывания перфоратора через перфоратор и образованные перфорационные отверстия намывают каверны в продуктивном пласте в объеме 3,5 м3 на 1 перфорационное отверстие при давлении 16 МПа с расходом 4 л/с технической водой плотностью 1,14 г/см3, включающей 0,3% (масс.) поверхностно-активного вещества ТН-МС и 0,12% (масс.) нейтрализатора сероводорода СНПХ-1050.After each operation of the punch, through the punch and formed perforations, caverns in the reservoir are washed in the volume of 3.5 m 3 per 1 punch hole at a pressure of 16 MPa with a flow rate of 4 l / s with industrial water with a density of 1.14 g / cm 3 , including 0, 3% (mass.) Of the TH-MS surfactant and 0.12% (mass.) Of a hydrogen sulfide neutralizer SNPCH-1050.

По колонне насосно-компрессорных труб с перфоратором закачивают 24%-ную соляную кислоту в объеме 3,5 м3 при открытой затрубной задвижке. Закрывают затрубную задвижку. Закачивают по колонне насосно-компрессорных труб ту же соляную кислоту при начальном давлении 3 МПа. Скважина не принимает. Проводят технологическую выдержку в режиме ванны 1 час, при этом давление с 3 МПа снижается до 1,5 МПа. Продавливают ту же соляную кислоту с дренированием при давлении 3 МПа. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту при давлении 4 МПа. Скважина при постоянной закачке не принимает. Закачивают ту же соляную кислоту в объеме 0,1 м3 за 1 час при давлении 5,6 МПа с ожиданием падения давления. Поднимают давление до 6 МПа, скважина начинает принимать с расходом 0,5 л/с, продавливают при давлении 6 МПа. После продавливания 3 м3 кислоты давление постепенно снижается до 3 МПа. Оставляют на реагирование на 3 часа.24% hydrochloric acid is pumped into the tubing string with a perforator in a volume of 3.5 m 3 with an annular gate valve open. Close the annular valve. The same hydrochloric acid is pumped through the tubing string at an initial pressure of 3 MPa. The well does not accept. Spend technological exposure in the bath mode for 1 hour, while the pressure from 3 MPa decreases to 1.5 MPa. The hydrochloric acid is drained with drainage at a pressure of 3 MPa. A well with continuous injection does not accept. The same hydrochloric acid is injected at a pressure of 4 MPa. A well with continuous injection does not accept. The same hydrochloric acid is pumped in a volume of 0.1 m 3 for 1 hour at a pressure of 5.6 MPa with the expectation of a pressure drop. They raise the pressure to 6 MPa, the well begins to take with a flow rate of 0.5 l / s, push through at a pressure of 6 MPa. After forcing 3 m 3 of acid, the pressure gradually decreases to 3 MPa. Leave to respond for 3 hours.

Скважина принимает при давлении 3 МПа при постоянном расходе 0,9 л/с.The well receives at a pressure of 3 MPa at a constant flow rate of 0.9 l / s.

Свабирование проводят в три этапа с интенсивным отбором воды и газа на первом этапе, интенсивным отбором нефтяной эмульсии, нефти и газа на втором этапе, и малоинтенсивным отбором нефти и газа на третьем этапе.Swabbing is carried out in three stages with intensive extraction of water and gas in the first stage, intensive extraction of oil emulsion, oil and gas in the second stage, and low-intensity extraction of oil and gas in the third stage.

Поднимают компоновку из скважины, спускают насосное оборудование и осваивают скважину. В результате дебит скважины составил 13 т/сут. безводной нефти.They raise the layout from the well, lower the pumping equipment and develop the well. As a result, the flow rate of the well was 13 tons / day. anhydrous oil.

В результате удается добывать нефть без обводнения от нижележащего водонасыщенного пласта.As a result, it is possible to extract oil without watering from the underlying water-saturated formation.

Применение предложенного способа позволит решить задачу снижения риска обводнения скважины.The application of the proposed method will solve the problem of reducing the risk of watering the well.

Claims (1)

Способ заканчивания скважины, включающий вскрытие бурением продуктивного пласта, спуск эксплуатационной колонны, цементирование заколонного пространства, перфорацию, обработку кислотой и свабирование, отличающийся тем, что при перфорации спускают в эксплуатационную колонну компоновку из колонны насосно-компрессорных труб с перфоратором прокалывающего действия, проводят перфорацию на технической воде прокалывающим перфоратором эксплуатационной колонны и цемента в заколонном пространстве в интервале продуктивного пласта, после каждого срабатывания перфоратора через перфоратор и образованные перфорационные отверстия намывают каверны в продуктивном пласте технической водой в объеме 2,5-3,5 м3 на 1 перфорационное отверстие при давлении 15-16 МПа с расходом 3,5-4 л/с, при обработке пласта кислотой проводят ступенчатую кислотную обработку интервала перфорации с продавкой кислоты и организацией кислотных ванн под давлением технической водой со ступенчатым увеличением давления на каждой ступени до достижения приемистости скважины в объеме не менее 0,5 л/с при давлении 3-5 МПа, а свабирование проводят в три этапа с интенсивным отбором в объеме 0,5 м3 за 20-30 минут на первом и втором этапах и малоинтенсивным отбором в объеме 0,5 м3 за 45-60 минут на третьем этапе, при этом в качестве технической воды используют воду с плотностью, обеспечивающей противодавление на пласт, включающую поверхностно-активное вещество в количестве 0,1-0,3 мас.% и нейтрализатор сероводорода в количестве 0,08-0,12 мас.%.A method of completing a well, including drilling a producing formation, lowering a production string, cementing an annulus, perforating, acidizing and swabbing, characterized in that during perforation, the assembly of a tubing string with a perforating puncture action is lowered into the production string, perforation is performed industrial water by piercing the production casing and cement punch in the annulus in the interval of the reservoir, after After the perforator is triggered through the perforator and the perforations formed, the cavities in the reservoir are washed with technical water in the amount of 2.5-3.5 m 3 per 1 perforation at a pressure of 15-16 MPa with a flow rate of 3.5-4 l / s, during processing formation with acid conduct stepwise acid processing of the perforation interval with the sale of acid and organization of acid baths under pressure with process water with a stepwise increase in pressure at each stage until the well injectivity is achieved in a volume of at least 0.5 l / s at a pressure of 3-5 MPa and swabbing is carried out in three stages with intensive selection in a volume of 0.5 m 3 for 20-30 minutes in the first and second stages and low-intensity selection in a volume of 0.5 m 3 for 45-60 minutes in the third stage, while as industrial water use water with a density that provides backpressure on the reservoir, including a surfactant in an amount of 0.1-0.3 wt.% and a hydrogen sulfide neutralizer in an amount of 0.08-0.12 wt.%.
RU2018127258A 2018-07-24 2018-07-24 Well completion method RU2695908C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2018127258A RU2695908C1 (en) 2018-07-24 2018-07-24 Well completion method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2018127258A RU2695908C1 (en) 2018-07-24 2018-07-24 Well completion method

Publications (1)

Publication Number Publication Date
RU2695908C1 true RU2695908C1 (en) 2019-07-29

Family

ID=67586891

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2018127258A RU2695908C1 (en) 2018-07-24 2018-07-24 Well completion method

Country Status (1)

Country Link
RU (1) RU2695908C1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2750004C1 (en) * 2020-11-20 2021-06-21 Публичное акционерное общество «Татнефть» имени В.Д. Шашина Method for completing and intensifying inflow of well with carbonate reservoirs
RU2790071C1 (en) * 2022-08-01 2023-02-14 Акционерное общество "МАКойл" Well treatment method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2189435C1 (en) * 2001-12-19 2002-09-20 Суворов Геннадий Иванович Method of well completion
US7073587B2 (en) * 2001-10-13 2006-07-11 1407580 Ontario Inc System for increasing productivity of oil, gas and hydrogeological wells
RU2423604C1 (en) * 2010-03-04 2011-07-10 Ринат Раисович Хузин Procedure for development of payable carbonate bed
RU2531771C1 (en) * 2013-11-07 2014-10-27 Открытое акционерное общество "Татнефть" им. В.Д. Шашина Method of well bottom zone processing
RU2656255C1 (en) * 2017-08-01 2018-06-04 Публичное акционерное общество "Татнефть" имени В.Д. Шашина Method for perforating a well and processing a bottom-hole carbonate formation zone

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7073587B2 (en) * 2001-10-13 2006-07-11 1407580 Ontario Inc System for increasing productivity of oil, gas and hydrogeological wells
RU2189435C1 (en) * 2001-12-19 2002-09-20 Суворов Геннадий Иванович Method of well completion
RU2423604C1 (en) * 2010-03-04 2011-07-10 Ринат Раисович Хузин Procedure for development of payable carbonate bed
RU2531771C1 (en) * 2013-11-07 2014-10-27 Открытое акционерное общество "Татнефть" им. В.Д. Шашина Method of well bottom zone processing
RU2656255C1 (en) * 2017-08-01 2018-06-04 Публичное акционерное общество "Татнефть" имени В.Д. Шашина Method for perforating a well and processing a bottom-hole carbonate formation zone

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2750004C1 (en) * 2020-11-20 2021-06-21 Публичное акционерное общество «Татнефть» имени В.Д. Шашина Method for completing and intensifying inflow of well with carbonate reservoirs
RU2790071C1 (en) * 2022-08-01 2023-02-14 Акционерное общество "МАКойл" Well treatment method

Similar Documents

Publication Publication Date Title
RU2612061C1 (en) Recovery method of shale carbonate oil field
RU2558058C1 (en) Interval hydraulic fracturing of carbonate formation in horizontal wellbore with bottom water
CA3000260C (en) Methods for performing fracturing and enhanced oil recovery in tight oil reservoirs
RU2312211C1 (en) Method for well bottom zone treatment
RU2490442C1 (en) Method for well completion
RU2656255C1 (en) Method for perforating a well and processing a bottom-hole carbonate formation zone
RU2612060C1 (en) Method of development of carbonate shaly oil deposits
RU2652412C1 (en) Method of acidizing bottomhole formation zone with carbonate reservoir
RU2695908C1 (en) Well completion method
RU2540713C1 (en) Method of oil pool development
RU2550642C1 (en) Method of oil field development with horizontal wells
RU2334098C1 (en) Method of high-viscosity oil pool development
RU2616052C1 (en) Method development of shaly carbonate oil pays
RU2627338C1 (en) Solid carbonate oil deposits development method
RU2514046C1 (en) Method of oil pool development
RU2499134C2 (en) Method of development of oil pool located above gas pool and separated therefrom by impermeable parting
RU2750004C1 (en) Method for completing and intensifying inflow of well with carbonate reservoirs
RU2618542C1 (en) Method for development of oil deposits by hydraulic fracturing fractures
RU2288356C1 (en) Method for processing bottomhole zone of horizontal well
RU2543004C1 (en) Method of acid longitudinal hydraulic fracturing of low-permeable terrigenous collector
RU2645688C1 (en) Carbonate formation hydraulic fracturing method
RU2334097C1 (en) Method of high-viscosity oil pool development
RU2652399C1 (en) Method of hydraulic graduation of a formation with clayey spaces
RU2616016C9 (en) Recovery method for solid carbonate reservoirs
RU2638668C1 (en) Method of thermofoam-acid treatment of near-well zone of carbonate reservoir