RU2426885C1 - Method for carrying out and fixing of mine workings in severe mining and geological conditions - Google Patents
Method for carrying out and fixing of mine workings in severe mining and geological conditions Download PDFInfo
- Publication number
- RU2426885C1 RU2426885C1 RU2009148974/03A RU2009148974A RU2426885C1 RU 2426885 C1 RU2426885 C1 RU 2426885C1 RU 2009148974/03 A RU2009148974/03 A RU 2009148974/03A RU 2009148974 A RU2009148974 A RU 2009148974A RU 2426885 C1 RU2426885 C1 RU 2426885C1
- Authority
- RU
- Russia
- Prior art keywords
- shield
- compressed air
- pneumatic
- cavity
- bottles
- Prior art date
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
Изобретение относится к горной промышленности и может быть использовано для проведения и крепления подготовительных выработок в сложных горно-геологических условиях.The invention relates to the mining industry and can be used for holding and securing preparatory workings in difficult mining and geological conditions.
Известен способ крепления горных выработок, включающий установку основной крепи технологически заданного профиля, перетяжку кровли и анкерное крепление вспучиваемых пород, причем в зонах вскрытия или присечки вспучивающих пород проводимой горной выработки в почве или бортах последней производят установку полимерных анкеров с одновременным нагнетанием быстротвердеющего полимерного состава сразу во все шпуры в соответствии с принятым паспортом крепления, при этом направления шпуров в почве осуществляют с учетом направления смещения вспучиваемых частей контура выработки (см. патент 2134350, МПК E21D 020|02).A known method of securing mine workings, including installing the main support of a technologically defined profile, hauling the roof and anchoring the intumescent rocks, moreover, in the opening or notching areas of the intumescent rocks of the conducted mining in the soil or on the sides of the latter, polymer anchors are installed while the quick-hardening polymer composition is injected immediately into all holes in accordance with the accepted fastening certificate, while the direction of the holes in the soil is carried out taking into account the direction of displacement Intumescent parts generating circuit (see patent 2134350, IPC E21D 020 |. 02).
Недостатком указанного способа является невозможность его использования в сложных горно-геологических условиях, так как отсутствуют мероприятия по разгрузке угольного массива от опасных напряжений.The disadvantage of this method is the impossibility of its use in difficult mining and geological conditions, since there are no measures for unloading the coal mass from dangerous stresses.
Известен способ защиты горных выработок, включающий бурению шпуров в кровле выработок с конусным уширением в устье каждого шпура, установку в них анкеров с хвостовиками, соединенными гибкими связями, натяжение связей с помощью анкеров, причем шпуры располагаются в точках пересечения осей, параллельных бортам выработки и делящих ее по ширине на шесть равных частей, и окружностей диаметром 0,4 В, описанных из центров, расположенных в точках пересечения осей с четными порядковыми номерами и линиями, перпендикулярными бортам выработки, при этом расстояние между упомянутыми линиями выбирают равным 0,6 В, хвостовики анкеров выполняют в виде петель, которые образуют при помощи сдвоенных анкеров, а в качестве гибких связей используют трос, при этом трос пропускают в петли, а его концы закрепляю т в шпурах (см. патент 2134330, МПК E21D 020|00 E21D 011|00).A known method of protecting mine workings, including drilling holes in the roof of workings with a conical broadening at the mouth of each hole, installing anchors in them with shanks connected by flexible ties, tensioning the ties with anchors, the holes being located at the intersection points of the axes parallel to the sides of the working and dividing its width is six equal parts, and circles with a diameter of 0.4 V, described from centers located at the intersection points of the axes with even serial numbers and lines perpendicular to the sides of the mine, at the distance between the mentioned lines is chosen equal to 0.6 V, the anchor shanks are made in the form of loops that form using double anchors, and a cable is used as flexible ties, while the cable is passed into the loops, and its ends are fixed in holes (see Patent 2134330, IPC E21D 020 | 00 E21D 011 | 00).
Недостатком указанного способа является невозможность его использования в сложных горно-геологических условиях, так как отсутствуют мероприятия по разгрузке угольного массива от опасных напряжений.The disadvantage of this method is the impossibility of its use in difficult mining and geological conditions, since there are no measures for unloading the coal mass from dangerous stresses.
Известен способ крепления горных выработок при проведении по выбросоопасным пластам, взятый в качестве прототипа, включающий образование разгрузочной полости (щели) над пластом и установку постоянной крепи (см. Мельников Н.И. Проведение и крепление горных выработок, М., Недра, 1988 стр.325-326).There is a method of securing mine workings when conducting along outburst formations, taken as a prototype, including the formation of a discharge cavity (gap) above the formation and the installation of a permanent lining (see Melnikov N.I. Conducting and securing mine workings, M., Nedra, 1988 p. .325-326).
Недостатком указанного способа является проведение разгрузочной полости без ее крепления, что может привести к вывалообразованиям и снижению безопасности работ.The disadvantage of this method is the holding of the discharge cavity without fixing it, which can lead to dumping and reduce the safety of work.
Техническим результатом является повышение эффективности и безопасности проведения и крепления подготовительных выработок в сложных горно-геологических условиях.The technical result is to increase the efficiency and safety of holding and securing preparatory workings in difficult mining and geological conditions.
Технический результат достигается тем, что в способе проведения и крепления горных выработок в сложных горно-геологических условиях, включающем образование разгрузочной полости впереди забоя с неснижаемым опережением полости и установку постоянной крепи, согласно изобретению в разгрузочную полость заводят два ряда пневмобаллонов со щитом, подают сжатый воздух в пневмобаллоны и поднимают щит до уровня верхняка постоянной крепи, после чего укладывают щит на раму постоянной крепи и создают распор между кровлей полости и пневмобаллонами, путем подачи сжатого воздуха в пневмобаллоны, затем проводят выемку породы под щитом на шаг установки рам постоянной крепи, а первый ряд пневмобаллонов разгружают и извлекают в закрепленную часть выработки, после чего устанавливают раму постоянной крепи под щитом и снимают распор с пневмобаллонов второго ряда путем выпуска сжатого воздуха, и извлекают пневмобаллоны в закрепленную часть выработки, затем проводят разгрузочную полость до первоначальной глубины, после чего операции повторяют.The technical result is achieved by the fact that in the method of conducting and securing mine workings in difficult geological conditions, including the formation of a discharge cavity in front of the face with irreducible advancement of the cavity and the installation of a permanent support, according to the invention, two rows of pneumocylinders with a shield are introduced into the discharge cavity, compressed air is supplied into pneumocylinders and raise the shield to the level of the upper support of the constant lining, after which they lay the shield on the frame of the constant lining and create a spacer between the roof of the cavity and the pneumatic cylinders , by supplying compressed air to the pneumatic cylinders, then excavation of the rock under the shield is carried out at the step of installing the constant support frames, and the first row of pneumatic cylinders is unloaded and removed into the fixed part of the excavation, after which the constant support frame is installed under the shield and the strut is removed from the second row pneumatic cylinders by releasing compressed air, and pneumatic cylinders are removed into the fixed part of the output, then the discharge cavity is carried out to the original depth, after which the operations are repeated.
Сущность изобретения поясняется чертежами, где на фиг.1 показана схема проведения и крепления подготовительной выработки с разгрузочной полостью; на фиг.2 показана схема проведения и крепления подготовительной выработки с разгрузочной полостью, в которой расположены пневмобаллоны со щитом, с выпуском сжатого воздуха из пневмобаллонов; на фиг.3 показана схема проведения и крепления подготовительной выработки с разгрузочной полостью, в которой расположены пневмобаллоны со щитом при подаче сжатого воздуха в пневмобаллоны; на фиг.4 показана схема проведения и крепления подготовительной выработки с разгрузочной полостью, в которой расположен пневмобаллон, и установленной рамой постоянной крепи после подвигания забоя на шаг заходки; на фиг.5 показана схема проведения и крепления подготовительной выработки с разгрузочной полостью, с установленной рамой постоянной крепи после подвигания забоя на шаг заходки и затяжкой между рамами крепи.The invention is illustrated by drawings, where figure 1 shows a diagram of the conduct and fastening of the preparatory workings with a discharge cavity; figure 2 shows a diagram of the conduct and fastening of the preparatory workings with an unloading cavity in which the air cylinders with a shield are located, with the release of compressed air from the air cylinders; figure 3 shows a diagram of the conduct and fastening of the preparatory workings with an unloading cavity, in which there are pneumatic cylinders with a shield when compressed air is supplied to the pneumatic cylinders; figure 4 shows a diagram of the conduct and fastening of the preparatory workings with the discharge cavity in which the pneumatic balloon is located, and the fixed support frame installed after moving the face to the approaching pitch; figure 5 shows a diagram of the conduct and fastening of the preparatory workings with an unloading cavity, with a fixed support frame installed after moving the face to the entry step and tightening between the support frames.
На фиг.1, 2, 3, 4 показано: 1 - забой подготовительной выработки; 2 - разгрузочная полость; 3 - пневмобаллоны; 4 - щит; 5 - верхняк постоянной крепи; 6 - стойка постоянной крепи; 7 - затяжка.Figure 1, 2, 3, 4 shows: 1 - the face of the preparatory development; 2 - discharge cavity; 3 - pneumocylinders; 4 - shield; 5 - the upper bearing of the permanent lining; 6 - stand permanent support; 7 - a puff.
Способ крепления осуществляется следующим образом: впереди забоя подготовительной выработки 1 создают разгрузочную полость 2 на глубину 2 м (фиг.1), в которую досылают два ряда пневмбаллонов 3 с уложенным н них щитом 4 (фиг.2). В пневмобаллоны 3 первого и второго рядов подают сжатый воздух. Наличие двух рядов пневмобаллонов позволяет поднимать щит с наклоном для заводки щита на раму постоянной крепи. Поднимают щит до уровня верхняка постоянной крепи, укладывают щит на раму постоянной крепи, (фиг.3), создают распор между кровлей разгрузочной полости и пневмобаллонами путем подачи сжатого воздух в пневмобаллоны, проводят выемку породы под щитом до величины, равной шагу установки рам постоянной крепи (состоящих из верхняков 5 и стоек 6). Первый ряд пневмобаллонов (ближний к рамам крепи) разгружают и извлекают в закрепленную часть выработки. После чего устанавливают раму постоянной крепи под щитом (фиг.4). Снимают распор с певмобаллона второго ряда путем выпуска сжатого воздуха. Извлекают пневмобаллон в закрепленную часть выработки, а между рамами крепи устанавливают затяжку 7 (фиг.5). 3атем проводят разгрузочную полость до первоначальной глубины (фиг.1), после чего операции по досылке в нее пневмобаллонов с уложенным на них щитом, подаче в пневмобаллоны сжатого воздуха, поднятию щита до уровня верхняка постоянной крепи, укладке щита на раму постоянной крепи, созданию распора между кровлей разгрузочной полости и пневмобаллоном, путем подачи сжатого воздух в пневмобаллоны, выемке породы под щитом до величины, равной шагу установки рам постоянной крепи, разгрузке пневмобаллона, ближнего к рамам крепи, и его извлечению в закрепленную часть выработки, установке рам постоянной крепи под щитом, снятию распора с пневмобаллона второго ряда путем выпуска сжатого воздуха, извлечению пневмобаллона второго ряда в закрепленную часть выработки, проведению разгрузочной полости до первоначальной глубины, после чего операции повторяют.The mounting method is as follows: in front of the face of the
Данный способ проведения и крепления подготовительных выработок позволит повысить эффективность и безопасность проведения и крепления горных выработок в сложных горно-геологических условиях.This method of conducting and securing preparatory workings will improve the efficiency and safety of carrying out and securing mine workings in difficult geological conditions.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2009148974/03A RU2426885C1 (en) | 2009-12-28 | 2009-12-28 | Method for carrying out and fixing of mine workings in severe mining and geological conditions |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2009148974/03A RU2426885C1 (en) | 2009-12-28 | 2009-12-28 | Method for carrying out and fixing of mine workings in severe mining and geological conditions |
Publications (2)
Publication Number | Publication Date |
---|---|
RU2009148974A RU2009148974A (en) | 2011-07-10 |
RU2426885C1 true RU2426885C1 (en) | 2011-08-20 |
Family
ID=44739906
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
RU2009148974/03A RU2426885C1 (en) | 2009-12-28 | 2009-12-28 | Method for carrying out and fixing of mine workings in severe mining and geological conditions |
Country Status (1)
Country | Link |
---|---|
RU (1) | RU2426885C1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2487242C1 (en) * | 2011-12-16 | 2013-07-10 | Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный университет" | Method for construction and support of mines under complicated mining and geological conditions |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110792450B (en) * | 2019-09-26 | 2020-10-27 | 中国矿业大学 | A method for determining the advance support of grouting anchor cable |
-
2009
- 2009-12-28 RU RU2009148974/03A patent/RU2426885C1/en not_active IP Right Cessation
Non-Patent Citations (1)
Title |
---|
МЕЛЬНИКОВ Н.И. Проведение и крепление горных выработок. - М.: Недра, 1988, с.325-326. * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2487242C1 (en) * | 2011-12-16 | 2013-07-10 | Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный университет" | Method for construction and support of mines under complicated mining and geological conditions |
Also Published As
Publication number | Publication date |
---|---|
RU2009148974A (en) | 2011-07-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2013358812B2 (en) | Solid-filling coal mining method with two pre-excavated tunnels for advancing | |
RU2348811C1 (en) | Method of supporting mine tunnels | |
CN108643907B (en) | A method for mining without coal pillars by caving roof with broken direct roof along the air | |
CN108457651B (en) | Coal mine roadside filling gob-side entry retaining hydraulic splitting roof cutting method | |
BR112012021093B1 (en) | method for block abatement mining | |
CN109681248A (en) | A kind of grouting cable anchor advanced support method | |
CN103147793A (en) | Non-chain-pillar roadway protection method adopting filling beside thin coal seam roadway | |
WO2010058933A3 (en) | Tunnel excavation method | |
RU2428566C1 (en) | Development method of gently sloping coal beds | |
CN103485795B (en) | Method for quickly tunneling mine roadway and consecutively timbering mine roadway | |
CN104533419A (en) | Method for partial recovery of residual coal from wide coal pillar | |
RU2426885C1 (en) | Method for carrying out and fixing of mine workings in severe mining and geological conditions | |
CN104405392B (en) | Three soft high seam tunnel jackings are kept on file anchor rete cord active support longwall top coal caving method | |
CN102155249A (en) | Method for supporting tunnel roof below mined-out area | |
CN209494569U (en) | A new type of rapid roadheader for coal roadway | |
JP3750043B2 (en) | Large section underground hollow quarry | |
CN102383795B (en) | Comprehensive mechanical rock drift excavating process | |
CN102155239A (en) | Ground stress release method for high ground stress soft rock tunnel positive step excavation | |
RU2487242C1 (en) | Method for construction and support of mines under complicated mining and geological conditions | |
RU2341657C1 (en) | Method of prevention of development entries in coal bed areas | |
CN108316925B (en) | Simple gob-side entry retaining method for drilling and roof breaking of working face with three-soft coal layer thickness direct roof | |
CN103628897B (en) | A kind of by tunnel caving place method | |
CN202560232U (en) | Rear-mounted anchoring guider in hole | |
CN110259448A (en) | Unload crush the lane Ding Yukuan flexible wall prevention and treatment tight roof stay lane bump method | |
CN103422870A (en) | Roof supporting method for full super-high seam mining |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
MM4A | The patent is invalid due to non-payment of fees |
Effective date: 20111229 |