RU2014134259A - The method of construction of a monolithic reinforced concrete foundation with the exact location of the anchor reinforcing bars of a periodic profile with any surface topography - Google Patents
The method of construction of a monolithic reinforced concrete foundation with the exact location of the anchor reinforcing bars of a periodic profile with any surface topography Download PDFInfo
- Publication number
- RU2014134259A RU2014134259A RU2014134259A RU2014134259A RU2014134259A RU 2014134259 A RU2014134259 A RU 2014134259A RU 2014134259 A RU2014134259 A RU 2014134259A RU 2014134259 A RU2014134259 A RU 2014134259A RU 2014134259 A RU2014134259 A RU 2014134259A
- Authority
- RU
- Russia
- Prior art keywords
- vibrator
- foundation
- anchor reinforcing
- template
- concrete
- Prior art date
Links
Landscapes
- Foundations (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
Способ сооружения монолитного железобетонного фундамента с точным расположением анкерных арматурных стержней периодического профиля с любым рельефом поверхности, заключающийся в том, что в соответствии с геодезической разбивкой откапывают котлованы для монолитных фундаментов, подготавливают основание, бетонируют нижнюю часть фундамента до отметки расположения низа анкерных арматурных стержней с любым рельефом поверхности, а после схватывания бетона нижней части фундамента строительным краном монтируют шаблон-вибратор для точного монтажа 4…8 анкерных арматурных стержней, присоединенных снизу к плите и образующих с ней единое целое, последняя оснащена мишенями для точной установки шаблона-вибратора в проектное положение вместе с электро- или пневмовибратором, ориентируют шаблон-вибратор по двум лазерным нивелирам так, чтобы лучи от лазерных нивелиров совпадали с остриями мишеней, фиксируют шаблон-вибратор по горизонту, бетонируют верхнюю часть фундамента до проектной отметки, включают вибратор и уплотняют бетон, после начала схватывания бетона отсоединяют шаблон-вибратор от анкерных арматурных стержней, расположенных точно в проектном положении, строительным краном демонтируют шаблон-вибратор, отсоединяют продольно-разъемные муфты, фланцы, вновь присоединяют к анкерным арматурным стержням фундамента продольно-разъемные муфты, безвыверочно монтируют колонну, опуская выпуски арматурных стержней колонны в продольно-разъемные муфты до упора в анкерные арматурные стержни, гайковертом затягивают гайки продольно-разъемных муфт, в результате жестко соединяют колонну с монолитным фундаментом.A method of constructing a monolithic reinforced concrete foundation with the exact location of the anchor reinforcing bars of a periodic profile with any surface topography, which consists in the fact that, in accordance with the geodetic breakdown, ditches for monolithic foundations are excavated, the foundation is prepared, the lower part of the foundation is concreted to the location of the bottom of the anchor reinforcing bars with any surface relief, and after setting concrete of the lower part of the foundation with a construction crane, a vibrator template is mounted for precise about the installation of 4 ... 8 anchor reinforcing bars attached to the bottom of the plate and forming a single unit with it, the latter is equipped with targets for precise installation of the vibrator template in the design position together with an electric or pneumatic vibrator, the vibrator template is oriented along two laser levels so that the rays from the laser levels coincided with the tips of the targets, fix the vibrator template horizontally, concrete the upper part of the foundation to the design mark, turn on the vibrator and compact the concrete, after the concrete has set, disconnect the scab he-vibrator from anchor reinforcing rods located exactly in the design position, dismantle the vibrator template with a construction crane, disconnect the longitudinally-detachable couplings, flanges, reconnect the longitudinally-detachable couplings to the anchor reinforcing rods of the foundation, unequally mount the column, omitting the outlets of the reinforcing rods of the column in longitudinally split couplings all the way into the anchor reinforcing bars, tighten the nuts of longitudinally split couplings with a wrench, as a result, the column is rigidly connected to the monolithic foundation.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2014134259/03A RU2583381C2 (en) | 2014-08-20 | 2014-08-20 | Method for construction of monolithic reinforced concrete foundation with exact location of anchor reinforcement bars of periodic profile with any surface relief |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2014134259/03A RU2583381C2 (en) | 2014-08-20 | 2014-08-20 | Method for construction of monolithic reinforced concrete foundation with exact location of anchor reinforcement bars of periodic profile with any surface relief |
Publications (2)
Publication Number | Publication Date |
---|---|
RU2014134259A true RU2014134259A (en) | 2016-03-20 |
RU2583381C2 RU2583381C2 (en) | 2016-05-10 |
Family
ID=55530657
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
RU2014134259/03A RU2583381C2 (en) | 2014-08-20 | 2014-08-20 | Method for construction of monolithic reinforced concrete foundation with exact location of anchor reinforcement bars of periodic profile with any surface relief |
Country Status (1)
Country | Link |
---|---|
RU (1) | RU2583381C2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116934179A (en) * | 2023-09-15 | 2023-10-24 | 菏泽建工建筑设计研究院 | Building engineering quality detection data analysis management system based on big data |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2687830C1 (en) * | 2018-01-29 | 2019-05-16 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Пензенский государственный университет архитектуры и строительства" | Rigid toothed joint of two-branch columns with foundations |
RU2675272C1 (en) * | 2018-03-05 | 2018-12-18 | Борис Никифорович Сушенцев | Interface node of assembly reinforced concrete column with monolithic base (options) |
RU2679214C1 (en) * | 2018-03-16 | 2019-02-06 | Общество с ограниченной ответственностью Производственно строительная фирма "СТАЛЬКОН" (ООО ПСФ "СТАЛЬКОН") | Device for adjustment and temporary attachment of structures on a horizontal base |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1010396A1 (en) * | 1981-11-27 | 1983-04-07 | Всесоюзный Научно-Исследовательский Институт По Монтажным И Специальным Строительным Работам | Device for mounting support elements onto foundation |
SU1157313A1 (en) * | 1982-08-17 | 1985-05-23 | Моторвагонное Депо Минск-Северный Белорусской Железной Дороги | Method of erecting equipment |
FR2777923A1 (en) * | 1998-04-22 | 1999-10-29 | Philippe Blanc | Foundation module that is prefabricated |
RU2459908C1 (en) * | 2011-04-01 | 2012-08-27 | Общество с ограниченной ответственностью "Инженерно-консультационный центр "Мысль" Новочеркасского государственного технического университета | Method to erect support of aerial cableway |
-
2014
- 2014-08-20 RU RU2014134259/03A patent/RU2583381C2/en not_active IP Right Cessation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116934179A (en) * | 2023-09-15 | 2023-10-24 | 菏泽建工建筑设计研究院 | Building engineering quality detection data analysis management system based on big data |
CN116934179B (en) * | 2023-09-15 | 2023-12-01 | 菏泽建工建筑设计研究院 | Building engineering quality detection data analysis management system based on big data |
Also Published As
Publication number | Publication date |
---|---|
RU2583381C2 (en) | 2016-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2014134259A (en) | The method of construction of a monolithic reinforced concrete foundation with the exact location of the anchor reinforcing bars of a periodic profile with any surface topography | |
GB2557702A (en) | Tunnel | |
RU2016101603A (en) | BASE OF THE WIND POWER INSTALLATION | |
CN103835527B (en) | A kind of dismountable supporting device | |
CN204151820U (en) | Stone bolt location and installation support | |
MX2016010698A (en) | Prefabricated footing for wind turbines. | |
JP6357324B2 (en) | Construction adjustment method and building | |
CN104897143A (en) | Cylinder forced centering observation pillar and embedment method thereof | |
PH12017501962B1 (en) | Scour protection for an underwater bottom alongside a quay wall, and method for providing the same | |
CN104149177A (en) | Novel assembly type reinforced concrete cable groove production mould | |
JP6897055B2 (en) | Structure installation method and installation foundation | |
JP6301742B2 (en) | Steel pipe pole and its installation method | |
RU2013108518A (en) | TUNNEL TUBING RING FOR UNDERGROUND METRO STRUCTURES | |
JP2014169596A (en) | Repair method for existing irrigation channel | |
JP5905802B2 (en) | Construction method of breakwater using multi-purpose post | |
GB2542289A8 (en) | Load Transmission device | |
RU96381U1 (en) | REGULATED FOUNDATION FOR OPERATING FRAME FRAME REINFORCED CONCRETE BUILDINGS | |
FI125848B (en) | Method of forming a foundation of a tower-like building | |
ES2565518A1 (en) | Method for the manufacture of tubular segments of concrete and for the erection of towers by means of said tubular segments (Machine-translation by Google Translate, not legally binding) | |
CN204343253U (en) | Waters, non-navigation channel replaceable shaft tower pile anti-collision structure | |
CN204252154U (en) | Foundation for tower crane | |
PL416971A1 (en) | Large size precast assembled foundation with increased stability and strength | |
RU2601787C1 (en) | Method for construction of foundation support | |
RU2014101578A (en) | METHOD FOR ESTABLISHING A COLUMNED BASE WITH CAMOUFLET EXPANSION | |
RU2014125848A (en) | Prefabricated concrete structure for civil buildings assembled without the use of mortar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
HZ9A | Changing address for correspondence with an applicant | ||
MM4A | The patent is invalid due to non-payment of fees |