[go: up one dir, main page]

NL2023277B1 - Retrofitting an existing offshore drilling vessel - Google Patents

Retrofitting an existing offshore drilling vessel Download PDF

Info

Publication number
NL2023277B1
NL2023277B1 NL2023277A NL2023277A NL2023277B1 NL 2023277 B1 NL2023277 B1 NL 2023277B1 NL 2023277 A NL2023277 A NL 2023277A NL 2023277 A NL2023277 A NL 2023277A NL 2023277 B1 NL2023277 B1 NL 2023277B1
Authority
NL
Netherlands
Prior art keywords
vertical
derrick
deck
firing line
hydraulic
Prior art date
Application number
NL2023277A
Other languages
Dutch (nl)
Inventor
Bernardus Wijning Diederick
Original Assignee
Itrec Bv
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Itrec Bv filed Critical Itrec Bv
Priority to NL2023277A priority Critical patent/NL2023277B1/en
Priority to PCT/EP2020/065702 priority patent/WO2020245408A1/en
Application granted granted Critical
Publication of NL2023277B1 publication Critical patent/NL2023277B1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B1/00Hydrodynamic or hydrostatic features of hulls or of hydrofoils
    • B63B1/02Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement
    • B63B1/10Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with multiple hulls
    • B63B1/107Semi-submersibles; Small waterline area multiple hull vessels and the like, e.g. SWATH
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B35/4413Floating drilling platforms, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B83/00Rebuilding or retrofitting vessels, e.g. retrofitting ballast water treatment systems
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/02Supports for the drilling machine, e.g. derricks or masts specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • E21B19/08Apparatus for feeding the rods or cables; Apparatus for increasing or decreasing the pressure on the drilling tool; Apparatus for counterbalancing the weight of the rods
    • E21B19/09Apparatus for feeding the rods or cables; Apparatus for increasing or decreasing the pressure on the drilling tool; Apparatus for counterbalancing the weight of the rods specially adapted for drilling underwater formations from a floating support using heave compensators supporting the drill string
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B1/00Hydrodynamic or hydrostatic features of hulls or of hydrofoils
    • B63B1/02Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement
    • B63B1/10Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with multiple hulls
    • B63B1/12Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with multiple hulls the hulls being interconnected rigidly
    • B63B2001/128Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with multiple hulls the hulls being interconnected rigidly comprising underwater connectors between the hulls
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/14Hull parts
    • B63B2003/147Moon-pools, e.g. for offshore drilling vessels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Fluid Mechanics (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Water Supply & Treatment (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

method of retrofitting an existing offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the existing offshore drilling vessel has a floating hull provided with a moonpool, and wherein the hull has four derrick support structures that are arranged in a rectangular grid about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick. Herein the existing offshore drilling vessel has a drilling derrick placed above and over the moonpool, the drilling derrick having four foot sections, each foot section resting on and being secured to a respective derrick support structure of the hull. The method comprises removing the drilling derrick from the existing offshore drilling vessel. After removal of the drilling derrick, the method comprises mounting a drilling installation on the existing offshore drilling vessel, so that the four derrick support structures of the hull support the drilling installation.

Description

P34139NLO0
RETROFITTING AN EXISTING OFFSHORE DRILLING VESSEL The present invention relates to the field of offshore drilling vessels for performing subsea wellbore related activities along a vertical firing line. In the field, offshore drilling vessels are in use that have a floating hull provided with a moonpool. The hull has four derrick support structures that are arranged in a rectangular grid about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick. The drilling derrick is placed above and over the moonpool, the drilling derrick having four foot sections, each foot section resting on and being secured to a respective derrick support structure of the hull.
For example, existing offshore drilling vessels are embodied as a semi-submersible drilling vessel, comprising: - a deckbox structure; - one or more pontoons, e.g. two parallel pontoons or a ring pontoon, - multiple support columns extending upward from the one or more pontoons and supporting thereon the deckbox structure; wherein the deckbox structure has an upper deck and a box bottom, and has a moonpool extending through said deckbox structure. An example of such a prior art offshore drilling vessel is, schematically, depicted in figure 1. In known embodiments, the drilling derrick is provided with a heave compensated crown block assembly. A travelling block is commonly suspended from the crown block assembly in a multiple fall arrangement of a main cable of a tubular string main hoisting device. This arrangement allows to compensate the tubulars string for heave motion of the vessel, e.g. to avoid undue vertical oscillations of the tubular string, e.g. a drill pipe string, suspended from the travelling block and extending through a riser into the wellbore. This, for example, allows to avoid undue changes in weight-on-it during drilling. An example of such a heave compensated crown block assembly is described in US2015/0008382. In WO2016062812, the present applicant has disclosed an advanced offshore drilling installation providing enhanced functionality over the above described existing offshore drilling vessels equipped with a drilling derrick and heave compensated crown block assembly.
2. It is an object of the invention to propose measures that allow for or facilitate the retrofitting of existing drilling vessels with a drilling installation of enhanced functionality. It is an object of the invention to propose measures that allow for or facilitate the retrofitting of existing drilling vessels with a drilling installation of enhanced functionality, wherein the drilling installation has a limited weight allow to make optimum use of payload capacity of the drilling vessel. This, for instance, in view of operations in remote areas, thereby reducing costs for supply vessels. Itis an object of the invention to provide a versatile offshore drilling installation, for example in view of retrofitting existing offshore drilling vessels. It is an object of the invention to provide an offshore drilling vessel equipped with a versatile offshore drilling installation.
The invention provides according to a first aspect thereof a method according to claim 1. The method pertains to retrofitting an existing offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line. The existing offshore drilling vessel, e.g. of the type illustrated schematically in figure 1, has a floating hull provided with a moonpool. The hull has multiple, e.g. four, derrick support structures that are arranged in a grid, e.g. a rectangular grid, about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick. The existing offshore drilling vessel has a drilling derrick placed above and over the moonpool, the drilling derrick having foot sections, each foot section resting on a respective derrick support structure of the hull.
The inventive method of claim 1 comprises: - removing the drilling derrick from the existing offshore drilling vessel, e.g. using a blow torch to cut through the connection of each foot section to the hull, - after removal of the drilling derrick, mounting a drilling installation on the existing offshore drilling vessel, so that the derrick support structures of the hull support the drilling installation. Herein the new drilling installation has enhanced functionality over the removed drilling derrick, as it comprises: - a drilling tower structure comprising: - a lower frame configured to rest on the four derrick support structures of the hull of the existing offshore drilling vessel,
-3-
- a pair of first and second vertical tower legs erected on said lower frame, said first and second tower legs being spaced apart horizontally on diametrically opposed locations relative to a vertical firing line,
- a crown block traverse structure supported on said pair of first and second vertical tower legs, wherein a crown block assembly is supported by said crown block traverse structure, wherein the drilling tower structure is configured so that a vertical load on the crown block assembly is transmitted via the pair of tower legs to the lower frame and thereby to the derrick support structures of the hull of the existing offshore drilling vessel, wherein the drilling installation further comprises: - a tubular string main hoisting device comprising:
- one or more main hoisting winches mounted on the drilling tower structure,
- one or more main cables driven by said one or more main hoisting winches and extending to said crown block assembly,
- a travelling block suspended from said crown block assembly via said one or more main cables, which travelling block is adapted to suspend a tubular string therefrom along a firing line through said moonpool,
wherein the drilling installation comprises: - a vertically mobile working deck arranged between the pair of tower legs and vertically movable with respect to the tower legs along said firing line within a motion range including a heave compensation motion range, wherein, preferably, a slip device is provided on the working deck that is configured to suspend therefrom a tubulars string in the firing line, e.g. during a tripping operation wherein the tubulars string is tripped into or out of a wellbore, wherein the drilling installation comprises: - an integrated heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck, wherein the integrated heave compensation system comprises a hydraulic main cable compensator engaging on the one or more main cables and configured to provide a heave compensated motion of the travelling block,
wherein the integrated heave compensation system further comprises a hydraulic deck compensator, which hydraulic deck compensator is connected to the drilling tower structure
-4- and to the mobile working deck and is configured to provide a heave compensated motion of the working deck relative to the drilling tower structure within a heave compensation motion range, wherein the integrated heave compensation system is configured such that, in operation, said hydraulic deck compensator and said hydraulic main cable compensator move synchronously in order to provide heave compensation of both the travelling block and the mobile working deck.
The method may allow for effectively retrofitting rather old (semi-submersible) drilling vessels, both in view of costs and time.
The drilling tower structure does not require significant changes to the hull, in particular to the derrick support structures thereof as the vertical loads are distributed rather similar to the load distribution when the existing drilling derrick was still present. In comparison, provision of a single mast type drilling tower as shown in the exemplary figures of WO2016062812, would require a total rebuilt of the hull, at least of the deck box structure in a semi- submersible designed to support a four footed drilling derrick. The inventive retrofit method avoids this need.
In an embodiment, the mounting step comprises lifting the drilling installation as a pre- assembled unit onto the vessel in one lift, e.g. using a crane barge or a shore-mounted crane.
In an embodiment, the method comprises the step of functionally testing the drilling installation ahead of lifting the drilling installation as a pre-assembled unit onto the vessel in one lift.
As will be explained herein, the provision of the two tower legs allows for structural design details that are beneficial in view of factors like, reduced total weight of the installation, low center of gravity of the installation, even distribution of weight over the support structures, enhanced integration of additional equipment like a tubulars handling device, racker device, etc.
In an embodiment, the lower frame comprises pair of horizontal girders, e.g. as part of a rectangular lower frame. Herein the horizontal girders are located along opposite sides of the moonpool, each horizontal girder of said pair resting on two derrick support structures. For
-5. example, each tower leg is erected midway between the locations where the horizontal girder rests on the two derrick support structures, so that the girder must be designed to withstand a bending due to the vertical load exerted thereon midway between the derrick support structures.
In an embodiment, the drilling tower structure has two, and just two, single column tower legs, each tower leg having a single column that is erected from the lower frame, the two single column tower legs being arranged in a vertical plane that encompasses the firing line. So the structure than resembles an inverted U structure, with the crown block traverse bridging the tops of the two tower legs as the crown block traverse structure is supported on the two single column tower legs. For example, each single column tower leg is erected from a respective horizontal girder of the lower frame. For example, each tower leg is erected midway between the locations where the horizontal girder rests on the two derrick support structures. For example, each vertical tower leg is embodied with multiple vertical chords that are connected by a latticework (diagonal) bracing between the chords, e.g. a triangular or rectangular cross-section vertical tower leg with a chord at each corner of the cross-section.
Most preferably, each single column tower leg is embodied as a hollow box-type tower leg. In an embodiment, a tower leg is in part, e.g. in a lower part thereof, construed as a hollow box-type tower leg and in another part, e.g. in a top part thereof, construed with multiple vertical chords that are connected by a latticework (diagonal) bracing between the chords. In an embodiment, the one or more main hoisting winches are mounted to the first tower leg. Preferably, the one or more haisting winches each have a rotatable winch drum driven by one or more winch motors. In another embodiment, the one or more hoisting winches are embodied as linear winch devices, e.g. each comprising one or more hydraulic cylinders or other linear device to drive the one or more main cables. In a practically preferred embodiment, the drilling installation has two main hoisting winches each have a rotatable winch drum, each winch drum being connected to a respective end of a single main cable that extends along the crown block and the travelling block. This arranged is illustrated in WO2018062812.
-B- In another embodiment, the tubular string main hoisting device is embodied as disclosed in WO2014/209131. For example, multiple parallel main cables are wound, preferably in a single layer, side by side on the rotatable drum of a winch.
The hydraulic main cable compensator may be passive and/or active, e.g. a switchable compensator, as is known in the art. For example, the hydraulic main cable compensator may be configured as disclosed in WO2018151593 or in WO2011034422.
In an embodiment, the hydraulic main cable compensator is mounted to the second tower leg, e.g. within said second tower leq, e.g. within a hollow-box type second tower leg. In particular in combination with an embodiment wherein the one or more main hoisting winches are mounted to the first tower leg, this arrangement of the hydraulic main cable compensator is beneficial, e.g. in view of distribution of loads within the structure and of weight.
In an embodiment, the hydraulic deck compensator comprises a first hydraulic cylinder that is mounted to and along the first tower leg and a second hydraulic cylinder that is mounted to and along the second tower leg. Preferably, just one hydraulic cylinder is fitted per tower leg, e.g. to a side of a box-type tower leg, e.g. the side facing the other tower leg.
In an embodiment, the hydraulic deck compensator comprises a hydraulic cylinder that is vertically mounted to a respective tower leg, with a cylinder housing thereof attached to the respective tower leg and with a piston rod thereof being extendable downward relative to the cylinder housing, wherein the mobile working deck is connected to the lower end of the piston rod. The provision of this cylinder with the piston rod downwards, essentially results in the working deck hanging directly from the cylinder. The heave compensation effort is then provided by the hydraulic pressure in the annular chamber in the cylinder below the piston, which chamber surrounds the piston rod. This arrangement is structurally simple and allows to make use of the height of the tower legs along which the cylinder extends.
Preferably, the piston rod is extendable downward to a lowered, or lowermost, position where the working deck is at the same level as the deck region of the hull adjoining the moonpool, e.g. the working deck having a deck surface that in a lowered or lowermost position is flush with the adjoin deck region. For example, the working deck is provided with a horizontal rails thereon that align with horizontal rails on the adjoining deck region in the lowered or lowermost position, e.g. allowing transportation of equipment from the adjacent deck region
-7- onto the working deck and vice versa using a rails and, for example, a cart, e.g. a skid cart, moving over said rails.
In an embodiment, the hydraulic main cable compensator comprises a hydraulic cylinder having a cylinder housing, a piston rod, and piston separating an annular chamber around the piston rod from another, second chamber in the cylinder housing.
Herein a main cable heave compensation sheave is connected to said piston rod.
The annular chamber of this hydraulic cylinder of the hydraulic main cable compensator is connected to a chamber of a hydraulic liquid/gas separator cylinder, said hydraulic liquid/gas separator cylinder having another chamber that is connected to a gas buffer having an adjustable gas pressure.
An example of such an arrangement is illustrated in WO2016062812. In an embodiment wherein the hydraulic deck compensator cylinder is mounted with the piston rod downwards, each hydraulic deck compensator cylinder has piston separating an annular chamber around the piston rod and below the piston from another, second chamber, wherein said annular chamber of the hydraulic deck compensator cylinder is connected to said another, second chamber of the hydraulic main cable compensator cylinder.
In embodiments, the vessel is provided with, e.g. retrofitted with, a horizontal tubulars storage configured for storage of tubulars in a horizontal orientation.
Preferably, this storage being located on a deck of the vessel at a location adjacent the moonpool.
In embodiments, the drilling installation is devoid of any or of a sizable vertical setback for tubulars, so that during a tripping operation a tubular to be added to or removed from a tubular string, e.g. a drill pipe tubulars string or a production tubing string, is to be advanced to the drilling installation from the horizontal tubulars storage or to be returned to the horizontal tubulars storage.
In embodiments, the drilling installation can be provided with a small vertical setback, e.g. within reach of a racker device as described herein.
The small vertical setback, e.g. having at most 15 storage positions for a tubular, may serve for storage of bottomhole assemblies, or other components to be integrated in the tubulars string other than the tubulars that make up the majority of the tubular string, e.g. drill pipes or production tubing tubulars.
In embodiments, the vessel is provided with a transport device adapted for transport of a tubular from said horizontal tubulars storage to a horizontal transfer position.
For example, the vessel has guides allowing a tubular to roll into the horizontal transfer position, e.g. gravity based, as is known in the field.
-8- In embodiments, the drilling installation comprises a tubulars handling device. The tubulars handling device is, preferably, mounted to the drilling tower structure. This allows to avoid any issues with misalignment of the tubulars handled by the handling device relative to the firing line and/or relative to a racker device as described herein. If the handling device where to be mounted on the hull independent from the drilling tower structure, the mounting of the handling device would be complex and still unexpected deviations in alignment relative to the firing line and/or relative to a racker device could occur as the structural behaviour of the existing hull is not always predictable. Also this measure allows, in embodiments, to fully test the entire drilling installation including the tubulars handling device and, preferably, a racker device as described herein, ahead of the installation being mounted on the existing vessel, e.g. in one lift as discussed herein.
The tubulars handling device is configured for moving a tubular, e.g. a drill pipe or a production tubing tubular, between a horizontal transfer position, where a tubular to be handled is pickup or returned, and at least one vertical transfer position, in which the tubular is parallel to the firing line, e.g. vertically aligned with the firing line or parallel to and offset from the firing line.
In an embodiment, the tubulars handling device comprises: - a base integrated with the drilling tower structure, e.g. in the lower frame thereof, e.g. comprising one or more horizontal girders integrated in the lower frame, - a boom that is pivotal with respect to the base between a lowered position and a raised position by a boom drive, - a gripper supported by the boom and adapted for gripping a tubular, for example the gripper being rotatable relative to the boom by a gripper rotation drive, for example wherein the gripper is rotatable about a gripper rotation axis that is parallel to and spaced from a horizontal boom rotation axis, wherein the boom and gripper are operable so that, with the boom in its lowered position, the gripper is positioned to pick up a tubular at the horizontal transfer position, and with the boom in its raised position, the tubular is in said at least one vertical transfer position.
In a practical embodiment, the boom comprises two parallel beams between which the gripper and a gripped tubular pass upon rotation of the boom between the lowered and raised positions thereof.
-9- In an embodiment, a tower leg is provided with a vertical rail that extends along the tower leg, wherein the working deck is guided along the vertical rail. Preferably, the working deck is only guided along a vertical rail on one of the two tower legs, thereby avoiding alignment issues that would result from guiding the working deck along a vertical rail on each tower leg.
In an embodiment, the drilling installation further comprises: - at least one first vertical rail that extends along the first tower leg, - a trolley, said trolley being guided along said at least one first vertical rail, - a top drive device attached to the trolley, said top drive device comprising one or more top drive motors adapted to impart rotary motion to a tubulars string in the firing line when connected to said top drive device, wherein the trolley and/or the top drive device is suspended from the travelling block. In an embodiment, the working deck is also guided along said first vertical rail that guides the trolley, so the deck and the trolley share the first vertical rail. In an embodiment, the tubulars handling device is configured to bring a tubular into a vertical and offset transfer position that is parallel to and offset from the firing line, outside a vertical path of the vertically mobile working deck relative to the tower legs, wherein the drilling installation further comprises a racker device that is mounted to the drilling tower structure and that is adapted to take over a tubular from the tubulars handling device when presented at said vertical and offset transfer position and to then move said tubular from said vertical and offset transfer position to a vertical position that is vertically aligned with said firing line and in between the mobile working deck and the travelling block. Preferably, the racker device is provided with a heave motion synchronization system that is adapted to bring a tubular that has been taken over from the tubulars handling device at said vertical and offset transfer position into a vertical motion that is synchronous with a heave motion of the mobile working deck relative to the hull. In an embodiment, the drilling installation comprises at least one first vertical rail that extends along the first tower leg, wherein the racker device comprises, e.g. similar to the disclosure of WO2016/062812, a first motion arm assembly comprising a base and a movable motion arm, e.g. an extensible and retractable motion arm, wherein the base is guided said at least one first vertical rail, and wherein the motion arm has an operative reach that encompasses the firing line and said
-10- vertical and offset transfer position, said first motion arm assembly supporting a tubular gripper member adapted for gripping a tubular, said motion arm allowing to move a gripped tubular between said firing line and said vertical and offset transfer position. It will be appreciated that, in embodiments, the racker device could comprise multiple, e.g. two, motion arm assemblies, one above the other, e.g. fitted on the same first vertical rail.
In an embodiment, the one or more motion arm assemblies are provided with, or linked to, a heave motion compensating drive. For example, a toothed rack extends along or is integrated with the first vertical rail, and each motion arm assembly has a motor driven pinion to move the assembly up and down, possibly in heave compensating motion, along the toothed rack. In an embodiment the toothed rack is vertically mobile by a heave compensating drive, e.g. a hydraulic cylinder. In an embodiment, the vertically mobile working deck is provided with an opening therein that is aligned with said firing line and with a tubulars string supporting slip device that is configured to suspend a tubular string, e.g. a drill pipe string or a production tubing string, in said firing line and within a riser extending to a subsea well when the tubulars string has been disconnected from the travelling block in view of the connection of a new tubular to the suspended tubulars string.
In an embodiment, the drilling installation comprises a well center tool handling device, which well center tool handling device comprises: - at least one second vertical rail that extends along the second tower leg, - a second motion arm assembly comprising a base and a movable motion arm, e.g. an extensible and retractable motion arm, wherein the base is guided said at least one second vertical rail, and wherein the motion arm has an operative reach that encompasses the firing line, said motion arm assembly being adapted to support at least a well center tool, e.g. an iron roughneck tool, and allowing to bring said well center tool in the firing line. In particular with the provision of the racker device at the first tower leg, this arrangement of the well center tool handling device on the second tower leg is beneficial, e.g. in view of weight distribution, interference between the pipe racker and the well center tool handling device, etc. In an embodiment, the well center tool handling device is provided with a heave motion synchronization system that is adapted to bring the motion arm thereof and the well center tool supported thereby into a vertical motion that is synchronous with a heave motion of the mobile working deck and of a tubulars string supporting slip device provided thereon. For
-11- example, the well center tool is an iron roughneck device that is then operated during a tripping operation performed with the working deck and the slip device in heave compensating motion to make up or break a connection between tubulars of the tubulars string.
In an embodiment, the drilling installation comprises a workmen accessible platform that is mountable underneath the vertically mobile working deck allowing one or more workers to perform activities related to the tubulars string at a location underneath the working deck. For example, the workers are involved in securing one or more control lines to the outside of the tubulars string that is to be deployed into the wellbore, e.g. production tubing string, whilst the working deck and the slip device thereon holding the tubulars string are in heave compensating motion relative to the hull. This functionality allows to avoid undue chaffing and possible fatally damaging of such externally mounted control lines during the deployment of the tubulars string.
In an embodiment, the motion range of the vertically mobile working deck comprises a lower stationary position, wherein the working deck is usable as a drill floor deck that is stationary with respect to the hull and preferably aligned with a deck structure of the hull, and wherein the heave compensation motion range lies higher than said lower stationary position. This arrangement allows to use the working deck in the lower stationary position as a regular drill floor. The invention also relates to a drilling installation configured for use on-board an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, e.g. configured for retrofitting an existing offshore drilling vessel, wherein the offshore drilling vessel has a floating hull provided with a moonpool, wherein the drilling installation comprises: - adrilling tower structure comprising: - a lower frame configured to rest on the hull of the offshore drilling vessel, - a pair of first and second vertical tower legs erected on said lower frame, said first and second tower legs being spaced apart horizontally on diametrically opposed locations relative to a vertical firing line, - a crown block traverse structure supported on said pair of first and second vertical tower legs, wherein a crown block assembly is supported by said crown block traverse structure,
-12- wherein the drilling installation further comprises: - a tubular string main hoisting device comprising: - one or more main hoisting winches mounted on the drilling tower structure, - one or more main cables driven by said one or more main hoisting winches and extending to said crown block assembly, - a travelling block suspended from said crown block assembly via said one or more main cables, which travelling block is adapted to suspend a tubular string therefrom along a firing line through said moonpool,
wherein the drilling installation comprises: - a vertically mobile working deck arranged between the pair of vertical tower legs and vertically movable with respect to the tower legs along said firing line within a motion range including a heave compensation motion range, wherein, preferably, a slip device is provided on the working deck that is configured to suspend therefrom a tubulars string in the firing line, e.g. during a tripping operation wherein the tubulars string is tripped into or out of a wellbore, wherein the drilling installation comprises: - an integrated heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck, wherein the integrated heave compensation system comprises a hydraulic main cable compensator engaging on the one or more main cables and configured to provide a heave compensated motion of the travelling block,
wherein the integrated heave compensation system further comprises a hydraulic deck compensator, which hydraulic deck compensator is connected to the drilling tower structure and to the mobile working deck and is configured to provide a heave compensated motion of the working deck relative to the drilling tower structure within a heave compensation motion range, wherein the integrated heave compensation system is configured such that, in operation, said hydraulic deck compensator and said hydraulic main cable compensator move synchronously in order to provide heave compensation of both the travelling block and the mobile working deck.
-13- The invention also relates to an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the offshore drilling vessel has a floating hull provided with a moonpool,
wherein the offshore drilling vessel has a drilling installation comprises: - a drilling tower structure comprising: - a pair of first and second vertical tower legs, for example erected on a lower frame resting on the hull of the offshore drilling vessel, said first and second tower legs being spaced apart horizontally on diametrically opposed locations relative to a vertical firing line, - a crown block traverse structure supported on said pair of first and second vertical tower legs, wherein a crown block assembly is supported by said crown block traverse structure,
wherein the drilling installation further comprises: - a tubular string main hoisting device comprising: - one or more main hoisting winches mounted on the drilling tower structure, - one or more main cables driven by said one or more main hoisting winches and extending to said crown block assembly, - a travelling block suspended from said crown block assembly via said one or more main cables, which travelling block is adapted to suspend a tubular string therefrom along a firing line through said moonpool, wherein the drilling installation comprises: - a vertically mobile working deck arranged between the pair of vertical tower legs and vertically movable with respect to the tower legs along said firing line within a motion range including a heave compensation motion range, wherein, preferably, a slip device is provided on the working deck that is configured to suspend therefrom a tubulars string in the firing line, e.g. during a tripping operation wherein the tubulars string is tripped into or out of a wellbore, wherein the drilling installation comprises: - an integrated heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck,
-14- wherein the integrated heave compensation system comprises a hydraulic main cable compensator engaging on the one or more main cables and configured to provide a heave compensated motion of the travelling block, wherein the integrated heave compensation system further comprises a hydraulic deck compensator, which hydraulic deck compensator is connected to the drilling tower structure and to the mobile working deck and is configured to provide a heave compensated motion of the working deck relative to the drilling tower structure within a heave compensation motion range, wherein the integrated heave compensation system is configured such that, in operation, said hydraulic deck compensator and said hydraulic main cable compensator move synchronously in order to provide heave compensation of both the travelling block and the mobile working deck.
It will be appreciated that any of the drilling installations according to the first aspect of the invention may include one or more features discussed herein with reference to the drilling installation of any of the claims 1 — 20 or in general discussed herein.
A second aspect of the invention relates to a drilling installation configured for use on-board an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, e.g. for retrofitting an existing drilling vessel equipped with a drilling derrick, wherein the offshore drilling vessel has a floating hull provided with a moonpool, wherein the drilling installation comprises: - a drilling tower structure comprising: - a lower frame configured to rest on the hull of the offshore drilling vessel, - a pair of first and second vertical tower legs erected on said lower frame, said first and second tower legs being spaced apart horizontally on diametrically opposed locations relative to a vertical firing line, - a crown block traverse structure supported on said pair of first and second vertical tower legs, wherein a crown block assembly is supported by said crown block traverse structure,
-15- and wherein the drilling tower structure is configured so that a vertical load on the crown block assembly is transmitted via the pair of tower legs to the lower frame and thereby to the hull of the offshore drilling vessel, wherein the drilling installation further comprises: - a tubular string main hoisting device comprising: - one or more main hoisting winches mounted on the drilling tower structure, - one or more main cables driven by said one or more main hoisting winches and extending to said crown block assembly, - a travelling block suspended from said crown block assembly via said one or more main cables, which travelling block is adapted to suspend a tubular string therefrom along a firing line through said moonpool, wherein the drilling installation comprises: - a vertically mobile working deck arranged between the pair of vertical tower legs and vertically movable with respect to the tower legs along said firing line within a motion range including a heave compensation motion range, wherein the drilling installation comprises: - a heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck, wherein the integrated heave compensation system comprises a hydraulic main cable compensator engaging on the one or more main cables and configured to provide a heave compensated motion of the travelling block, wherein the heave compensation system comprises a mechanical connection between the travelling block and the mobile working deck to provide a heave compensated motion of the working deck relative to the drilling tower structure, such that, in operation, said hydraulic main cable compensator provides heave compensation of both the travelling block and the mobile working deck.
For example, similar to the disclosure in W02013169099, the mobile working deck can be suspended via chains, cables, a rigid links, from the heave compensated travelling block.
-18- The drilling installation of the second aspect of the invention may be provided with one or more of the features, including optional features, discussed herein with reference to the first aspect of the invention, e.g. as discussed in any of claims 1 — 20.
The second aspect of the invention also relates to an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line provided with the drilling installation of the second aspect of the invention.
The second aspect of the invention also relates to a method of retrofitting an existing offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the existing offshore drilling vessel has a floating hull provided with a moonpool, and wherein the hull has four derrick support structures that are arranged in a rectangular grid about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick, and wherein the existing offshore drilling vessel has a drilling derrick placed above and over the moonpool, the drilling derrick having four foot sections, each foot section resting on and being secured to a respective derrick support structure of the hull, wherein the method comprises: - removing the drilling derrick from the existing offshore drilling vessel, - after removal of the drilling derrick, mounting the drilling installation on the existing offshore drilling vessel, so that the four derrick support structures of the hull support the drilling installation.
A third aspect of the present invention relates to a drilling installation configured for use on- board an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the offshore drilling vessel has a floating hull provided with a moonpool, wherein the drilling installation comprises: - a drilling tower structure comprising, for example: - a lower frame configured to rest on the hull of the offshore drilling vessel, - a pair of first and second vertical tower legs erected on said lower frame, said first and second tower legs being spaced apart horizontally on diametrically opposed locations relative to a vertical firing line, wherein the drilling installation further comprises: - atubular string main hoisting device comprising: - one or more main hoisting winches mounted on the drilling tower structure,
-17-
- a vertically mobile crown block assembly mounted on the drilling tower structure, one or more hydraulic crown block cylinders supporting the crown block assembly and configured to move said crown block assembly vertically relative to the drilling tower structure,
- one or more main cables driven by said one or more main hoisting winches and extending to said crown block assembly,
- a travelling block suspended from said crown block assembly via said one or more main cables, which travelling block is adapted to suspend a tubular string, e.g. a drill pipe string, therefrom along a firing line through said moonpool,
wherein the drilling installation comprises: - a vertically mobile working deck that is vertically movable with respect to the drilling tower structure, e.g. relative to the tower legs, along said firing line within a motion range including a heave compensation motion range, e.g. said working deck being arranged between the pair of vertical tower legs, wherein the drilling installation comprises: - a heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck,
wherein the integrated heave compensation system comprises said one or more one or more hydraulic crown block cylinders being configured as one or more hydraulic main cable compensators and to provide a heave compensated motion of the travelling block, and wherein: a) the integrated heave compensation system comprises a mechanical connection between the crown block assembly and the mobile working deck to provide a heave compensated motion of the working deck relative to the drilling tower structure, such that, in operation, said one or more hydraulic crown block compensators provide heave compensation of both the travelling block and of the mobile working deck, for example, similar to the disclosure in WO2013189099, the mobile working deck can be suspended via chains, cables, a rigid links, from the crown block assembly, or wherein:
-18- b) the integrated heave compensation system further comprises a hydraulic deck compensator, which hydraulic deck compensator is connected to the drilling tower structure and to the mobile working deck and is configured to provide a heave compensated motion of the working deck relative to the drilling tower structure within a heave compensation motion range, such that, in operation, said hydraulic deck compensator and said one or more hydraulic crown block cylinders move synchronously in order to provide heave compensation of both the travelling block and the mobile working deck. The third aspect of the invention pertains to a drilling installation having a main hoisting device of the type that operates in a manner that has become known as the RamRig ® in the field. The drilling installation of the third aspect of the invention may be provided with one or more of the features, including optional features, discussed herein with reference to the first aspect of the invention, e.g. as discussed in any of claims 1 — 20. The third aspect of the invention also relates to an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line provided with the drilling installation of the third aspect of the invention.
The third aspect of the invention also relates to a method of retrofitting an existing offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the existing offshore drilling vessel has a floating hull provided with a moonpool, and wherein the hull has four derrick support structures that are arranged in a rectangular grid about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick, and wherein the existing offshore drilling vessel has a drilling derrick placed above and over the moonpool, the drilling derrick having four foot sections, each foot section resting on and being secured to a respective derrick support structure of the hull, wherein the method comprises: - removing the drilling derrick from the existing offshore drilling vessel, - after removal of the drilling derrick, mounting the drilling installation on the existing offshore drilling vessel, so that the four derrick support structures of the hull support the drilling installation.
A fourth aspect of the invention relates to a drilling installation configured for use on-board an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the offshore drilling vessel has a floating hull provided with a moonpool,
-19- wherein the drilling installation comprises: - a drilling tower structure comprising: - a pair of first and second vertical tower legs, said first and second tower legs being spaced apart horizontally on diametrically opposed locations relative to a vertical firing line, - a tubular string main hoisting device comprising: - one or more main hoisting winches mounted on the drilling tower structure, - one or more main cables driven by said one or more main hoisting winches, - a travelling block suspended from said one or mare main cables, which travelling block is adapted to suspend a tubular string therefrom along a firing line through said moonpool, - a vertically mobile working deck arranged between the pair of vertical tower legs and vertically movable with respect to the tower legs along said firing line within a motion range including a heave compensation motion range, - an integrated heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck, such that, in operation, said travelling block and working deck move synchronously in heave compensation.
The drilling installation of the fourth aspect of the invention may be provided with one or more of the features, including optional features, discussed herein with reference to the first aspect of the invention, e.g. as discussed in any of claims 1 — 20.
The fourth aspect of the invention also relates to an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line provided with the drilling installation of the fourth aspect of the invention.
The fourth aspect of the invention also relates to a method of retrofitting an existing offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the existing offshore drilling vessel has a floating hull provided with a moonpool, and wherein the hull has four derrick support structures that are arranged in a rectangular grid about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick, and wherein the existing offshore drilling vessel has a drilling derrick placed above and over the moonpool, the drilling derrick having four foot sections,
-20- each foot section resting on and being secured to a respective derrick support structure of the hull, wherein the method comprises: - removing the drilling derrick from the existing offshore drilling vessel, - after removal of the drilling derrick, mounting the drilling installation on the existing offshore drilling vessel, so that the four derrick support structures of the hull support the drilling installation.
A fifth aspect of the invention relates to a drilling installation configured for use on-board an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the offshore drilling vessel has a floating hull provided with a moonpool, wherein the drilling installation comprises: - a drilling tower structure,
- a tubular string main hoisting device comprising: - one or more main hoisting winches mounted on the drilling tower structure, - one or more main cables driven by said one or more main hoisting winches, - a travelling black suspended from said one or more main cables, which travelling block is adapted to suspend a tubular string therefrom along a firing line through said moonpool, - a vertically mobile working deck that is vertically movable with respect to the drilling tower structure along said firing line within a motion range including a heave compensation motion range, - an integrated heave compensation system configured to provide a heave compensation of the travelling block as well as of the mobile working deck, such that, in operation, said travelling block and said working deck move synchronously in heave compensation motion,
- a tubulars handling device that is, preferably, mounted to the drilling tower structure, wherein the tubulars handling device is configured for moving tubulars between a horizontal first transfer position, where a tubular to be handled is pickup or returned, and at least one vertical and offset transfer position, in which the tubular is parallel and offset from the firing line,
-21- - a racker device that is adapted to take over a tubular from the tubulars handling device and to move said tubular from said vertical transfer position to a firing line position that is aligned with said firing line and in between the mobile working deck and the travelling block, wherein the racker device is provided with a heave motion synchronization system that is adapted to bring a tubular that has been taken over by the racker device from the tubulars handling device at said vertical transfer position into a vertical motion that is synchronous with a heave motion of the mobile working deck, said working deck, for example, being provided with a drill string slip device that is configured to suspend a drill string therefrom, e.g. during a tripping operation.
The drilling installation of the fifth aspect of the invention may be provided with one or more of the features, including optional features, discussed herein with reference to the first aspect of the invention, e.g. as discussed in any of claims 1 — 20.
The fifth aspect of the invention also relates to an offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line provided with the drilling installation of the fourth aspect of the invention.
The fifth aspect of the invention also relates to a method of retrofitting an existing offshore drilling vessel for performing subsea wellbore related activities along a vertical firing line, wherein the existing offshore drilling vessel has a floating hull provided with a moonpool, and wherein the hull has four derrick support structures that are arranged in a rectangular grid about the moonpool, each derrick support structure being configured to support thereon a foot section of a drilling derrick, and wherein the existing offshore drilling vessel has a drilling derrick placed above and over the moonpool, the drilling derrick having four foot sections, each foot section resting on and being secured to a respective derrick support structure of the hull, wherein the method comprises: - removing the drilling derrick from the existing offshore drilling vessel, - after removal of the drilling derrick, mounting the drilling installation on the existing offshore drilling vessel, so that the four derrick support structures of the hull support the drilling installation.
It will be appreciated that any of the drilling installations according to the first or any other aspect of the invention may be configured for retrofitting an existing offshore drilling vessel. The described installations may, however, also be installed on new drilling vessels when desired. In a retrofit embodiment, preferably, the drilling tower structure of such an
29. installation comprises a lower frame that is configured to be placed on the derrick support structures of an existing vessel, which structures previously supported the drilling derrick that was removed in the course of the retrofit process. For example, the lower frame is embodied as discussed with reference to the installation of claim 1.
The invention also relates to a method for performing subsea wellbore related activities along a vertical firing line, wherein use is made of a drilling vessel, a drilling installation, and/or an offshore drilling vessel as described herein, e.g. according to any one or more of the first, second, third, fourth, and/or fifth aspect of the invention.
The invention will now be explained with reference to the drawings. In the drawings: Fig. 1 illustrates schematically an existing semi-submersible offshore drilling vessel, Fig. 2 illustrates an drilling installation according to the invention, Fig. 3 illustrates another view onto the drilling installation of figure 2, Fig. 4 shows the drilling installation of figure 2 with the tower structure removed for clarity, Fig. 5. shows the drilling installation of figure 2 with the tower structure removed for clarity, Fig. 8 illustrates the mounting of the drilling installation of figure 2 on the hull of an existing offshore drilling vessel having a moonpool, Fig. 7 shows the mounting of figure 6 at a perpendicular direction, Figs. 8a,b illustrates the operation of the tubulars handling device of the drilling installation of figure 2, Fig. 9 illustrates the tubulars string main hoisting device of the drilling installation of figure 2 as well as the integrated heave compensation system thereof, Fig. 10 illustrates the operation of the well center tool device of the drilling installation of figure 2, Fig. 11 illustrates the operation of the racker device of the drilling installation of figure 2. Figure 1 shows an existing offshore drilling vessel 1 for performing subsea wellbore related activities along a vertical firing line 2.
The existing offshore drilling vessel 1 has a floating hull 3 provided with a moonpool 4. The hull has four derrick support structures 5 that are arranged in a rectangular grid about the moonpool 4. Each derrick support structure 5 is configured to support thereon a foot section 7a of a drilling derrick 7.
23. The existing offshore drilling vessel 1 has a drilling derrick 7 placed above and over the moonpool 4. The drilling derrick has four foot sections 7a, each foot section 7a resting on and being secured to a respective derrick support structure 5 of the hull. The depicted existing offshore drilling vessel 1 is embodied as a semi-submersible drilling vessel, comprising: - a deckbox structure 8; - one or more pontoons, here two parallel pontoons 9, - multiple support columns 10 extending upward from the one or more pontoons 9 and supporting thereon the deckbox structure 8. The deckbox structure 8 has an upper deck 8a and a box bottom above the waterline of the vessel 1. The moonpool 4 extends through the deckbox structure 8. In the context of this description it is envisaged that the existing vessel 1 is retrofitted with a drilling installation 20 as illustrated in the figures 2 — 11. The retrofitting of the vessel 1 is done by a method which comprises: - removing the drilling derrick 7 from the existing offshore drilling vessel 1, - after removal of the drilling derrick 7, mounting a drilling installation 20 on the existing offshore drilling vessel, so that the four derrick support structures 5 of the hull support the drilling installation 20. In an embodiment, the mounting step comprises lifting the drilling installation 20 as a pre- assembled unit onto the vessel 1 in one lift, e.g. using a crane barge or a shore-mounted crane.
In an embodiment, the method comprises the step of functionally testing the drilling installation 20 ahead of lifting the drilling installation as a pre-assembled unit onto the vessel 1 in one lift. The drilling installation 20 comprises a drilling tower structure comprising: - a lower frame 31 configured to rest on the four derrick support structures 5 of the hull of the existing offshore drilling vessel 1,
-24- - a pair of first and second vertical tower legs 35, 36 erected on the lower frame 31, said first and second tower legs 35, 36 being spaced apart horizontally on diametrically opposed locations relative to vertical firing line 2, - a crown block traverse structure 37 supported on the pair of first and second vertical tower legs 35, 36, wherein a crown block assembly 40 is supported by the crown block traverse structure 37. The lower frame comprises pair of horizontal girders 32, 33 as part of a rectangular lower frame 31.
In the mounting step, the horizontal girders 32, 33 are located along opposite sides of the moonpool, so that each horizontal girder 32, 33 of said pair rests on, and is secured to, two derrick support structures 5.
Each tower leg 35, 36 is erected midway between the locations where the respective horizontal girder 32, 33 rests on the two derrick support structures 5. The drilling tower structure 20 has two single column tower legs 35, 36, each having a single column that is erected from the lower frame 31. The two single column tower legs are arranged in a vertical plane that encompasses the firing line 2. The crown block traverse structure 37 is supported on the two single column tower legs 35, 36. Each single column tower leg 35, 36 is embodied as a hollow box-type tower leg. For example, the tower legs 35, 36 have a rectangular cross-section, e.g. of a cross-section of at least 2 x 2 meters, e.g. at most 4 x 4 meters. The legs 35, 36 may be, as shown here, composed of leg parts that are stacked onto one another, e.g. via a bolted connection.
A cross-beam 39 interconnects the legs 35, 36 at an intermediate height position. That position is, as preferred, higher than the vertical path of working deck 70. The drilling tower structure may have a height between 30 and 50 meters in practical embodiments, e.g. 42 meters as shown in the drawings.
The drilling tower structure is configured so that a vertical load on the crown block assembly 40 is transmitted via the pair of tower legs 35, 36 to the lower frame 31, here the girders 32,
D5. 33, and thereby to the four derrick support structures 5 of the hull of the existing offshore drilling vessel 1. The drilling installation 20 further comprises a tubular string main hoisting device comprising: - one or more, here two, main hoisting winches 51, 52 mounted on the drilling tower structure, - one or more main cables, here one main cable 53, driven by said one or more main hoisting winches 51, 52 and extending to said crown block assembly 40, - a travelling block 60 suspended from said crown block assembly 40 via said one or more main cables 53, which travelling block is adapted to suspend a tubular string therefrom along the firing line 2 through said moonpool 4.
The one or more main hoisting winches 51, 52 are mounted to the first tower leg 35.
In this example, the two main hoisting winches 51, 52 each have a rotatable winch drum, each winch drum being connected to a respective end of the single main cable 53 that extends along the crown block 40 and the travelling block 60.
The drilling installation further comprises a vertically mobile working deck 70 that is arranged between the pair of tower legs 35, 36 and that is vertically movable with respect to the tower legs 35, 36 along said firing line 2 within a motion range including a heave compensation motion range.
As shown in figure 6, the motion range of the vertically mobile working deck 70 comprises a lower stationary position, wherein the working deck is usable as a drill floor deck that is stationary with respect to the hull. The heave compensation motion range lies higher than said lower stationary position. In figure 6 indication A indicates the center of the heave compensation motion range, e.g. at least 5 meters above the lower stationary position of the deck 7. The indications B and C indicated the lower and upper limit of the heave compensation motion range, e.g. said range extending over a height of at least 5 meters, e.g. at least 7 meters.
A slip device 75 is provided on the working deck 70, which device 75 is configured to suspend therefrom a tubulars string in the firing line 2, e.g. during a tripping operation wherein the tubulars string is tripped into or out of a wellbore.
-28- The drilling installation further comprises an integrated heave compensation system configured to provide a heave compensation of the travelling block 60 as well as of the mobile working deck 70.
As shown here, in an embodiment, the integrated heave compensation system comprises a hydraulic main cable compensator 80 engaging on the one or more main cables 53 and configured to provide a heave compensated motion of the travelling block 80. Here the compensator 80 comprises a hydraulic cylinder 81 having a piston rod 81b supporting a sheave assembly 88 acting on the main cable 53.
The integrated heave compensation system further comprises a hydraulic deck compensator 90, which hydraulic deck compensator is connected to the drilling tower structure and to the mobile working deck 70 and is configured to provide a heave compensated motion of the working deck 70 relative to the drilling tower structure within a heave compensation motion range.
The integrated heave compensation system is configured such that, in operation, the hydraulic deck compensator 90 and the hydraulic main cable compensator 80 move synchronously in order to provide synchronized heave compensation of both the travelling block 60 and the mobile working deck 70.
The hydraulic main cable compensator 80 is mounted to the second tower leg 36, here within said second tower leg, that is within the hollow-box type second tower leg 36.
As shown, the hydraulic deck compensator comprises a first hydraulic cylinder 91 that is mounted to and along the first tower leg 35 and a second hydraulic cylinder 82 that is mounted to and along the second tower leg 36. In practical embodiments each hydraulic deck compensator cylinder 91, 92 may have a heave compensating stroke length of at least 5 meters, and in addition thereto another at least 5 meters of stroke length as the heave compensation motion range is envisaged to stay clear above the lowermost stationary position of the deck 70, e.g. by at least 3 meters.
Both the hydraulic cylinder 91 and 92 are vertically mounted to the respective tower leg 35,
36. Herein a cylinder housing 914, 92a thereof is rigidly attached to the respective tower leg 35, 36 and a piston rod thereof 91b, 92b thereof is extendable downward relative to the cylinder housing. The mobile working deck 70 is connected to the lower end of the piston rods 91b,92b.
27- The hydraulic main cable compensator 80 comprises a hydraulic cylinder 81 having a cylinder housing 81a, a piston rod 81b, and piston 81c separating an annular chamber 82 around the piston rod from another, second chamber 83 in the cylinder housing 81. A main cable heave compensation sheave assembly 88 is connected to the piston rod 81b. The annular chamber 82 is connected to a chamber 85a of a hydraulic liquid/gas separator cylinder 85, said hydraulic liquid/gas separator cylinder having another chamber 85b that is connected to a gas buffer 86 having an adjustable gas pressure.
Each hydraulic deck compensator cylinder has piston 91c, 92c separating an annular chamber 91d, 92d around the piston rod and below the piston from another, second chamber 91e, 92e. The annular chambers 91d, 92d are interconnected ad connected to the second chamber 83 of the hydraulic main cable compensator cylinder 81.
Figure 9 schematically indicates, as an optional feature, the provision of an adjusting winch 96 and associated adjusting wire 97 acting on the compensator sheave assembly and/or piston rod 81b, for example as explained in WO2018151593.
The vessel 1 is, e.g. as part of the retrofit, provided with a horizontal tubulars storage configured for storage of tubulars in a horizontal orientation. Preferably said storage is located on a deck of the vessel at a location adjacent the moonpool 4. As known in the field, the vessel is provided with a transport device adapted for transport of a tubular from said horizontal tubulars storage to a horizontal transfer position, indicated as 7 horizontal in the drawings.
The drilling installation 20 comprises a tubulars handling device 120, which tubulars handling device is mounted to the drilling tower structure.
The tubulars handling device 120 is configured for moving a tubular 100 between said horizontal transfer position T horizontal, where a tubular 100 to be handled is pickup or returned, and at least one vertical transfer position, in which the tubular is parallel to the firing line, e.g. vertically aligned with the firing line or parallel to and offset from the firing line.
The depicted tubulars handling device 120 comprises: -a base 121 integrated with the drilling tower structure, here with the lower frame 31 as preferred,
-28- - a boom 122 that is pivotal with respect to the base 121 between a lowered position and a raised position by a boom drive, - a gripper 123 supported by the boom 122 and adapted for gripping a tubular 100. For example, the gripper 123 is rotatable relative to the boom 122 by a gripper rotation drive. It is shown here that the gripper 123 is rotatable about a gripper rotation axis that is parallel to and spaced from a horizontal boom rotation axis. The figures 8a, b illustrate that the boom 122 and gripper 123 for a tubular 100 are operable so that, with the boom 122 in its lowered position, the gripper 123 is positioned to pick up a tubular at the horizontal transfer position T horizontal, and with the boom 122 in its raised position, the tubular 100 is in said at least one vertical transfer position. It is illustrated that the boom 122 comprises two parallel beams between which the gripper 123 and a gripped tubular 100 pass upon rotation of the boom between the lowered and raised positions thereof.
The drilling installation 20 further comprises: - at least one first vertical rail 65 that extends along the first tower leg 35, - a trolley 110, said trolley being guided along said at least one first vertical rail 65, - a top drive device 115 attached to the trolley 110, said top drive device comprising one or more top drive motors adapted to impart rotary motion to a tubulars string in the firing line when connected to said top drive device, wherein the trolley and/or the top drive device is suspended from the travelling block. The tubulars handling device 120 is configured to bring a tubular 100 into a vertical and offset transfer position, indicated in figures 10, 11 as 7 offset, that is parallel to and offset from the firing line 2, outside the vertical path of the vertically mobile working deck 70 relative to the tower legs 35,36. The drilling installation further comprises a racker device 130 that is mounted to the drilling tower structure and that is adapted to take over a tubular 100 from the tubulars handling device 120 when presented at said vertical and offset transfer position 7 offset and to then move said tubular 100 from said vertical and offset transfer position to a vertical position that is vertically aligned with said firing line 2 and in between the mobile working deck 70 and the travelling block or the top drive device 115 when present.
The racker device 130 is provided with a heave motion synchronization system that is adapted to bring a tubular 100 that has been taken over from the tubulars handling device
-29- 120 at said vertical and offset transfer position into a vertical motion that is synchronous with a heave motion of the mobile working deck 70 relative to the hull. The drilling installation comprises said at least one first vertical rail 65 that extends along the first tower leg 35. The racker device 130 comprises: - a first motion arm assembly 135 comprising a base 136 and a movable motion arm 137, e.g. an extensible and retractable motion arm 137, e.g. telescoping. The base is guided by said at least one first vertical rail 65. The motion arm 137 has an operative reach that encompasses the firing line 2 and the vertical and offset transfer position T offset. The first motion arm assembly 135 supports a tubular gripper member 138 adapted for gripping a tubular 100. The motion arm 137 allows to move a gripped tubular between said firing line and said vertical and offset transfer position.
The vertically mobile working deck 70 is provided with an opening 71 therein that is aligned with the firing line 2. The deck 70 is provided with a tubulars string supporting slip device 75 that is configured to suspend a tubular string, e.g. a drill pipe string or a production tubing string, in said firing line 2 and within a riser extending to a subsea well when the tubulars string has been disconnected from the travelling block 60, or the top drive 115, in view of the connection of a new tubular to the suspended tubulars string that extends through riser 101. The drilling installation further comprises a well center tool handling device 140, which well center tool handling device comprises: - atleast one second vertical rail 141 that extends along the second tower leg 36, - a second motion arm assembly 145 comprising a base 146 and a movable motion arm 147, e.g. an extensible and retractable motion arm, e.g. telescoping, wherein the base 146 is guided said at least one second vertical rail 141. The motion arm 147 has an operative reach that encompasses the firing line 2. The motion arm assembly 145 is adapted to support at least a well center tool, e.g. an iron roughneck tool 148, and allowing to bring said well center tool in the firing line 2. The well center tool handling device 140 may be provided with a heave motion synchronization system that is adapted to bring the motion arm 147 thereof and the well center tool 148 supported thereby into a vertical motion that is synchronous with a heave motion of the mobile working deck 70 and of a tubulars string supporting slip device 75 provided thereon, e.g. the well center tool being an iron roughneck device operated during a
-30- tripping operation to make up or break a connection between tubulars of the tubulars string that extends into the riser 101 and into the subsea wellbore. Figures 7, 10, 11 illustrate the provision of a weather wall 150 protecting the work area. The wall 150 has an opening at the location of the handling device 120. The drilling installation is provided with a small vertical setback 170 within reach of a racker device 130 as described herein. The small vertical setback 170, e.g. having at most 15 storage positions for a tubular.
Figures 2 — 5 illustrate that riser 101 is installed between the offshore drilling vessel and the subsea wellbore. The riser 101 is tensioned in well-known manner by a riser tensioning system engage an upper portion of the riser 101. Here a riser tension ring 103 is shown, to which riser tension wires 104 are connected that extend, via an arrangement of sheaves, to riser tensioner devices 105. A telescopic joint may be provided, as common, in riser 101, for example with a flex joint above the telescopic joint allowing for angular motion of the riser 101 relative to the vessel.

Claims (1)

-31--31- CONCLUSIESCONCLUSIONS 1. Werkwijze voor het aanpassen van een bestaand offshore boorvaartuig (1) voor het uitvoeren van onderzeese boorput gerelateerde activiteiten langs een verticale vuurlijn, waarbij het bestaande offshore boorvaartuig een drijvende romp (3) heeft die van een moonpool (4) is voorzien, en waarbij de romp meerdere, bijvoorbeeld vier, boortorenondersteuningsstructuren (5) heeft die in een grid, bijvoorbeeld in een rechthoekig grid, rond de moonpool zijn aangebracht, waarbij elke boortorenondersteuningsstructuur is ingericht om daarop een voetgedeelte (7a) van een boortoren (7) te ondersteunen, en waarbij het bestaande offshore boorvaartuig een boortoren (7) heeft die boven en over de moonpool geplaatst is, waarbij de boortoren vier voetgedeelten heeft, waarbij elk voetgedeelte (7a) op een respectieve boortorenondersteuningsstructuur (5) van de romp rust, waarbij de werkwijze omvat: - het verwijderen van de boortoren (7) van het bestaande offshore boorvaartuig, - na het verwijderen van de boortoren, het aanbrengen van een boorinstallatie (20) op het bestaande offshore boorvaartuig, zodanig dat de vier boortorenondersteuningsstructuren (5) van de romp de boorinstallatie ondersteunen, waarbij de boorinstallatie omvat: - een boortorenstructuur omvattende: o een onderframe (31) dat is ingericht om op de boortorenondersteuningsstructuren (5) van de romp van het bestaande offshore boorvaartuig te rusten, o een paar van eerste en tweede verticale torenbenen (35, 36) die op genoemd onderframe (31) zijn opgericht, waarbij genoemde eerste en tweede torenbenen horizontaal gescheiden zijn op diametraal tegenoverliggende locaties ten opzichte van een verticale vuurlijn (2), o een kroonblokdwarsstructuur (37) dat ondersteund wordt door genoemd paar van eerste een tweede verticale torenbenen (35, 36), waarbij een kroonbloksamenstel (40) gedragen wordt door genoemd kroonblokdwarsstructuur, en waarbij de boortorenstructuur zo is ingericht dat een verticale last op het kroonbloksamenstel (4) via het paar van torenbenen (35, 36) naar het onderframe (31) wordtA method of adapting an existing offshore drilling vessel (1) to perform subsea well related activities along a vertical firing line, the existing offshore drilling vessel having a floating hull (3) provided with a moonpool (4), and wherein the hull has a plurality, e.g. four, derrick support structures (5) arranged in a grid, e.g. in a rectangular grid, around the moon pool, each derrick support structure being arranged to support thereon a base portion (7a) of a derrick (7) , and wherein the existing offshore drilling vessel has a derrick (7) located above and over the moonpool, the derrick having four foot sections, each foot section (7a) resting on a respective derrick support structure (5) of the hull, the method includes: - removing the derrick (7) from the existing offshore drilling vessel, - after removing the bo on the rig, the installation of a rig (20) on the existing offshore drilling vessel such that the four rig support structures (5) of the hull support the rig, the rig comprising: - a rig structure comprising: a subframe (31) which is arranged to rest on the derrick support structures (5) of the hull of the existing offshore drilling vessel, o a pair of first and second vertical tower legs (35, 36) erected on said lower frame (31), said first and second tower legs separated horizontally are at diametrically opposite locations with respect to a vertical firing line (2), o a crown block cross structure (37) supported by said pair of first and second vertical tower legs (35, 36), a crown block assembly (40) being carried by said crown block cross structure , and wherein the derrick structure is arranged so that a vertical load on the crown block assembly ( 4) through the pair of tower legs (35, 36) to the bottom frame (31) 232. overgedragen en daardoor naar de boortorenondersteuningsstructuren (5) van de romp van het bestaande offshore boorvaartuig, waarbij de boorinstallatie verder omvat: - een buisstring-hoofdhijsinrichting omvattende: o een of meer hoofdhijslieren (51, 52) die op het boortorenstructuur zijn aangebracht, o een of meer hoofdkabels (53) die worden aangedreven door genoemde een of meer hoofdhijslieren en die zich uitstrekken naar genoemd kroonbloksamenstel (40),232. and thereby transferred to the derrick support structures (5) of the hull of the existing offshore drilling vessel, the rig further comprising: - a tubular string main hoist comprising: o one or more main hoist winches (51, 52) mounted on the derrick structure, o one or more main ropes (53) powered by said one or more main hoist winches and extending to said crown block assembly (40), co een bewegend blok (60) dat opgehangen is aan genoemd kroonbloksamenstel via genoemde een of meer hoofdkabels (53), welk bewegend blok is ingericht om een buisstring langs een vuurlijn door genoemde moonpool (4) daaraan op te hangen,co a moving block (60) suspended from said crown block assembly via said one or more main cables (53), the moving block adapted to suspend a tube string along a firing line through said moon pole (4) thereto, waarbij de boorinstallatie omvat:wherein the rig comprises: - een verticaal mobiel werkdek (70) dat is aangebracht tussen het paar van torenbenen (35, 38) en dat verticaal beweegbaar is ten opzichte van de torenbenen langs genoemde vuurlijn (2) binnen een bewegingsbereik omvattende een deiningscompensatiebewegingsbereik, waarbij, bij voorkeur, een slipinrichting (75) op het werkdek (70) verschaft is dat is ingericht om daarvan een buisstring in de vuurlijn (2) af te hangen, bijvoorbeeld gedurende een tripping operatie waarbij de buisstring in of uit een boorput getript wordt,- a vertically mobile work deck (70) disposed between the pair of turret legs (35, 38) and movable vertically relative to the turret legs along said firing line (2) within a range of motion including a heave compensation range of motion, wherein, preferably, a slipping device (75) is provided on the working deck (70) which is adapted to suspend therefrom a tubular string in the firing line (2), for example during a tripping operation where the tubular string is stripped into or out of a wellbore, waarbij de boorinstallatie omvat:wherein the rig comprises: - een geïntegreerd deiningscompensatiesysteem dat is ingericht om een deiningscompensatie van het bewegend blok (60) en van het mobiele werkdek (70) te verschaffen,- an integrated swell compensation system arranged to provide swell compensation of the moving block (60) and of the mobile working deck (70), waarbij het geïntegreerde deiningscompensatiesysteem een hydraulische hoofdkabelcompensator (80, 81) omvat die op de een of meer hoofdkabels (53) aangrijpt en die is ingericht om een deining compenserende beweging van het bewegende blok (60) te verschaffen,wherein the integrated heave compensation system comprises a main hydraulic cable compensator (80, 81) that engages the one or more main cables (53) and is configured to provide a heave compensating movement of the moving block (60), waarbij het geïntegreerde deiningscompensatiesysteem verder een hydraulische dekcompensator (90, 91, 92) omvat, welk hydraulische dekcompensator met de boortorenstructuur (35, 38) en met het mobiele werkdek (70) verbonden is en welke iswherein the integrated heave compensation system further comprises a hydraulic deck compensator (90, 91, 92), which hydraulic deck compensator is connected to the derrick structure (35, 38) and to the mobile work deck (70) and which is -33. ingericht om een deining gecompenseerde beweging van het werkdek ten opzichte van de boortorenstructuur binnen een deiningscompensatiebewegingsbereik te verschaffen, waarbij het geïntegreerde deiningscompensatiesysteem zo is ingericht dat, in bedrijf, genoemde hydraulische dekcompensator (90, 91, 92) en genoemde hydraulische hoofdkabelcompensator (80, 81) synchroon bewegen om deiningscompensatie van zowel het bewegende blok (60) als het mobiele werkdek (70) te verschaffen.-33. arranged to provide a swell compensated movement of the working deck relative to the derrick structure within a swell compensation range of motion, the integrated swell compensation system being arranged such that, in operation, said hydraulic deck compensator (90, 91, 92) and said main hydraulic cable compensator (80, 81) ) move synchronously to provide swell compensation of both the moving block (60) and the mobile work deck (70). 2. Werkwijze volgens conclusie 1, waarbij het onderframe (31) een paar van horizontale steunbalken (32, 33) omvat, bijvoorbeeld als onderdeel van een rechthoekig onderframe, waarbij de horizontale steunbalken langs tegenoverliggende zijden van de moonpool (4) gelegen zijn, waarbij elke horizontale steunbalk van genoemd paar op twee of meer boortorenondersteuningsstructuren (5) rust, bijvoorbeeld waarbij elk torenbeen (35, 36) is opgericht midden tussen de locaties waar de horizontale steunbalk op de twee boortorenondersteuningsstructuren (5) rust.A method according to claim 1, wherein the bottom frame (31) comprises a pair of horizontal support beams (32, 33), for example as part of a rectangular bottom frame, the horizontal support beams being located along opposite sides of the moon pole (4), wherein each horizontal strut of said pair rests on two or more derrick support structures (5), for example with each turret leg (35, 36) erected midway between the locations where the horizontal strut rests on the two derrick support structures (5). 3. Werkwijze volgens conclusies 1-2, waarbij de boortorenstructuur twee enkele kolomtorenbenen (35, 36) heeft, waarbij elke een enkele kolom heeft die is opgericht op het onderframe (31), waarbij de twee enkele kolomtorenbenen in een verticaal vlak zijn aangebracht dat de vuurlijn (2) omvat, bijvoorbeeld waarbij elk enkele kolomtorenbeen is opgericht op een respectieve horizontale steunbalk (32, 33) van het onderframe, bijvoorbeeld waarbij elk torenbeen is opgericht in het midden tussen de locaties waar de horizontale steunbalk op de twee boortorenondersteuningsstructuren (5) rust, en waarbij de kroonblokdwarsstructuur (37) door genoemde twee enkele kolomtorenbenen (35, 36) wordt ondersteund, bij voorkeur waarbij elk enkel kolomtorenbeen is uitgevoerd als een holle doostype torenbeen (35, 36).The method of claims 1-2, wherein the derrick structure has two single column tower legs (35, 36), each having a single column erected on the lower frame (31), the two single column tower legs being disposed in a vertical plane that includes the firing line (2), for example, each single column turret being erected on a respective horizontal support beam (32, 33) of the lower frame, for example, each turret being erected at the center between the locations where the horizontal support beam on the two derrick support structures (5 ), and wherein the crown block cross-structure (37) is supported by said two single column tower legs (35, 36), preferably each single column tower leg being configured as a hollow box type tower leg (35, 36). 4. Werkwijze volgens een of meer van de conclusies 1-3, waarbij de een of meer hoofdhijslieren (51, 52) aan het eerste torenbeen zijn aangebracht, bijvoorbeeld waarbij twee hoofdhijslieren (51, 52) elk een roteerbare liertrommel hebben, waarbij elke liertrommel verbonden is met een respectief eind van een enkele hoofdkabel (53) die zich langs het kroonblok en het bewegende blok uitstrekt.A method according to any one of claims 1 to 3, wherein the one or more main hoist winches (51, 52) are arranged on the first tower leg, for example wherein two main hoist winches (51, 52) each have a rotatable winch drum, each winch drum is connected to a respective end of a single main cable (53) that extends along the crown block and the moving block. 5. Werkwijze volgens een of meer van de conclusies 1-4, waarbij de hydraulische hoofdkabelcompensator (80, 81) op het tweede torenbeen is aangebracht, bijvoorbeeld binnenin genoemd tweede torenbeen, bijvoorbeeld binnenin een holle doostype tweede torenbeen (36).A method according to any one of claims 1 to 4, wherein the main hydraulic cable compensator (80, 81) is mounted on the second tower leg, for example inside said second tower leg, for example inside a hollow box type second tower leg (36). -34--34- 6. Werkwijze volgens een of meer van de conclusies 1-5, waarbij de hydraulische dekcompensator een eerste hydraulische cilinder (91) die is aangebracht op en langs het eerste torenbeen (35) en een tweede hydraulische cilinder (36) die is aangebracht op en langs het tweede torenbeen (36) omvat.The method of any of claims 1 to 5, wherein the hydraulic deck compensator has a first hydraulic cylinder (91) mounted on and along the first turret leg (35) and a second hydraulic cylinder (36) mounted on and along the second tower leg (36). 7. Werkwijze volgens een of meer van de conclusies 1-6, waarbij de hydraulische dekcompensator een hydraulische cilinder (91, 92) omvat die verticaal op een respectief torenbeen (35, 36) is aangebracht, met een cilinderbehuizing (91a, 92a) daarvan aan het respectieve torenbeen vastgemaakt en met een zuigerstang (91b, 92b) daarvan naar beneden uitstrekbaar ten opzichte van de cilinderbehuizing, waarbij het mobiele werkdek (70) met het ondereind van de zuigerstang verbonden is.The method of any one of claims 1 to 6, wherein the hydraulic deck compensator comprises a hydraulic cylinder (91, 92) mounted vertically on a respective tower leg (35, 36), with a cylinder housing (91a, 92a) thereof. attached to the respective turret leg and extensible downwardly from the cylinder housing by a piston rod (91b, 92b) thereof, the mobile working deck (70) being connected to the lower end of the piston rod. 8. Werkwijze volgens een of meer van de conclusies 1-7, waarbij genoemde hydraulische hoofdkabelcompensator een hydraulische cilinder (81) omvat met een cilinderbehuizing (81a), een zuigerstang (81b), en een zuiger (81c) die een ringvormige kamer (82) rond de zuigerstang scheidt van een andere, tweede kamer (83) in de cilinderbehuizing, waarbij een hoofdkabeldeiningscompensatiekatrol (88) met genoemde zuigerstang verbonden is, waarbij genoemde ringvormige kamer (82) van genoemde hydraulische cilinder van de hydraulische hoofdkabelcompensator met een kamer (85a) van een hydraulische vloeistof/gas scheidingscilinder (85) verbonden is, waarbij genoemde hydraulische vloeistof/gas scheidingscilinder een andere kamer (85b) heeft die met een gasbuffer (86) verbonden is die een aanpasbare gasdruk heeft.The method of any of claims 1 to 7, wherein said main hydraulic cable compensator comprises a hydraulic cylinder (81) having a cylinder housing (81a), a piston rod (81b), and a piston (81c) containing an annular chamber (82). ) around the piston rod separates from another, second chamber (83) in the cylinder housing, a main cable rupture compensation pulley (88) being connected to said piston rod, said annular chamber (82) of said main hydraulic cable compensator hydraulic cylinder having a chamber (85a). ) of a hydraulic fluid / gas separation cylinder (85), said hydraulic fluid / gas separation cylinder having another chamber (85b) connected to a gas buffer (86) having an adjustable gas pressure. 9. Werkwijze volgens conclusie 7-8, waarbij elke hydraulische dekcompensatorcilinder (91, 92) een zuiger heeft die een ringvormige kamer rond de zuigerstang en onder de zuiger (91c, 92c) afscheidt van een andere, tweede kamer (91e, 92e), waarbij genoemde ringvormige kamer (91d, 92d) verbonden is met genoemde andere, tweede kamer (83) van de hydraulische hoofdkamercompensatorcilinder (81).The method of claims 7-8, wherein each hydraulic deck compensator cylinder (91, 92) has a piston separating an annular chamber around the piston rod and below the piston (91c, 92c) from another, second chamber (91e, 92e), wherein said annular chamber (91d, 92d) is connected to said other, second chamber (83) of the main hydraulic chamber compensator cylinder (81). 10. Werkwijze volgens een of meer van de conclusies 1-9, waarbij het vaartuig (1) van een horizontale buisopslag voorzien is die is ingericht om buizen in een horizontale oriëntatie op te slaan, bij voorkeur waarbij genoemde opslag op een dek van het schip op een locatie naast de moonpool gelegen is, en waarbij het vaartuig voorzien is van een transportinrichting die is ingericht voor transport van een buis van genoemde horizontale buisopslag naar een horizontale overdrachtspositie,A method according to any one of claims 1 to 9, wherein the vessel (1) is provided with a horizontal tube store adapted to store tubes in a horizontal orientation, preferably wherein said store is on a deck of the ship is located at a location adjacent to the moon pool, and wherein the vessel is provided with a transport device adapted to transport a tube from said horizontal tube store to a horizontal transfer position, -35. en waarbij de boorinstallatie een buishanteerinrichting (120) omvat, welk buishanteerinrichting bij voorkeur aangebracht is op de boortorenstructuur, waarbij de buishanteerinrichting is ingericht om een buis (101) te verplaatsen tussen genoemde horizontale overdrachtspositie (T horizontaal), waar een buis voor hanteren wordt opgepakt of teruggeplaatst, en ten minste een verticale overdrachtspositie, waarin de buis parallel is aan de vuurlijn, bijvoorbeeld verticaal uitgelijnd met de vuurline of parallel aan en offset van de vuurline (T offset).-35. and wherein the rig comprises a pipe handling device (120), the pipe handling device being preferably mounted on the derrick structure, the pipe handling device being arranged to move a pipe (101) between said horizontal transfer position (T horizontal), where a pipe is picked up for handling. or placed back, and at least one vertical transfer position, in which the tube is parallel to the firing line, e.g., vertically aligned with the firing line or parallel to and offset from the firing line (T offset). 11. Werkwijze volgens conclusie 10, waarbij de buishanteerinrichting (120) omvat: - een basis (121) geïntegreerd met de boortorenstructuur, - een giek (122) die draaibaar is ten opzicht van de basis tussen een lagere positie en een hogere positie door een giekaandrijving, - een grijper (123) die ondersteund wordt door de giek en ingericht is voor het grijpen van een buis, bijvoorbeeld waarbij de grijper ten opzichte van de giek roteerbaar is door een grijperrotatie-aandrijving, bijvoorbeeld waarbij de grijper roteerbaar is rond een grijperrotatie- as die parallel is aan en verwijderd van een horizontale giekrotatie-as, waarbij de giek en grijper bestuurbaar zijn zodanig dat, met de giek in de lagere positie daarvan, de grijper gepositioneerd is om een buis in de horizontale overdrachtspositie op te pakken, en met giek in de hogere positie daarvan, de buis in genoemde ten minste ene verticale overdrachtspositie is.The method of claim 10, wherein the pipe handling device (120) comprises: - a base (121) integrated with the derrick structure, - a boom (122) rotatable with respect to the base between a lower position and an upper position by a boom drive, - a grab (123) supported by the boom and adapted to grip a tube, for example, the grab being rotatable relative to the boom by a grab rotation drive, for example, the grab being rotatable about a grab rotation axis parallel to and remote from a horizontal boom rotational axis, the boom and grapple being steerable such that, with the boom in its lowered position, the grapple is positioned to pick up a tube in the horizontal transfer position, and with boom in its elevated position, the tube is in said at least one vertical transfer position. 12. Werkwijze volgens conclusie 11, waarbij de giek (122) twee parallelle balken omvat waartussen de grijper (123) en een gegrepen buis passeren terwijl de giek roteert tussen de lagere en de hogere positie daarvan.The method of claim 11, wherein the boom (122) includes two parallel beams between which the grab (123) and a gripped tube pass as the boom rotates between its lower and upper positions. 13. Werkwijze volgens een of meer van de conclusies 1-12, waarbij de boorinstallatie verder omvat: - ten minste een eerste verticale rail (65) die zich langs het eerste torenbeen (35) uitstrekt, - een trolley (110), waarbij genoemde trolley langs genoemde eerste verticale rail geleid wordt, - een top drive inrichting (115) die aan de trolley vastzit, waarbij genoemde top drive inrichting een of meer top drive motoren omvat die zijn ingericht om een rotatiebeweging te verlenen aan een buisstring in de vuurlijn wanneer deze verbonden is met genoemde top drive inrichting, waarbij de trolley en/of de top drive inrichting aan het bewegende blok is opgehangen.A method according to any of claims 1 to 12, wherein the drilling rig further comprises: - at least one first vertical rail (65) extending along the first tower leg (35), - a trolley (110), said trolley is guided along said first vertical rail, - a top drive device (115) attached to the trolley, said top drive device comprising one or more top drive motors arranged to impart rotational motion to a tubular string in the firing line when it is connected to said top drive device, the trolley and / or top drive device being suspended from the moving block. - 36 -- 36 - 14. Werkwijze volgens een of meer van de conclusies 10-12, waarbij de buishanteerinrichting (120) is ingericht om een buis (100) in een verticale en geoffsette overdrachtspositie (T offset) te brengen die parallel is aan en offset van de vuurlijn, buiten een verticaal pad van het verticale mobiele werkdek (70), en waarbij de boorinstallatie verder een rackerinrichting (130) omvat die is aangebracht op de boortorenstructuur en die is ingericht om een buis (100) over te nemen van de buishanteerinrichting wanneer deze op genoemde verticale en geoffsette overdrachtspositie (T offset) aangeboden wordt en om vervolgens de genoemde buis van genoemde verticale en geoffsette positie naar een verticale positie te bewegen die verticaal uitgelijnd is met genoemde vuurlijn {2) en die tussen het mobiele werkdek en het bewegende blok of de top drive inrichting (110) is.A method according to any one of claims 10 to 12, wherein the tube handling device (120) is arranged to bring a tube (100) into a vertical and offset transfer position (T offset) that is parallel to and offset from the firing line, outside a vertical path of the vertical mobile work deck (70), and wherein the rig further comprises a racker device (130) mounted on the derrick structure and adapted to take over a pipe (100) from the pipe handling device when mounted on said vertical and offsetted transfer position (T offset) and to then move said tube from said vertical and offsetted position to a vertical position vertically aligned with said firing line (2) and between the mobile working deck and the moving block or top drive device (110). 15. Werkwijze volgens conclusie 14, waarbij de rackerinrichting (130) is voorzien van een deiningsbewegingssynchronisatiesysteem dat is ingericht om een buis, die overgenomen is van de buishanteerinrichting op genoemde verticale en geoffsette overdrachtspositie, in een verticale beweging te brengen die synchroon is met een deiningsbeweging van het mobiele werkdek relatief aan de romp.The method of claim 14, wherein the racker device (130) includes a heave motion synchronization system configured to cause a tube inherited from the tube handling machine at said vertical and offsetted transfer position into a vertical motion synchronized with a heave motion of the mobile working deck relative to the hull. 18. Werkwijze volgens conclusies 14-15, waarbij de boorinstallatie omvat: - ten minste een eerste verticale rail (65) dat zich langs het eerste torenbeen uitstrekt en waarbij de rackerinrichting omvat: - een eerste bewegingsarminrichting (135) die een basis (136) en een beweegbare bewegingsarm (137) omvat, bijvoorbeeld een uittrekbare en intrekbare bewegingsarm, waarbij de basis door genoemde ten minste eerste verticale rail (65) geleid wordt, en waarbij de bewegingsarm een werkzaam bereik heeft dat de vuurlijn (2) en genoemde verticale en geoffsette overdrachtspositie (T offset) omvat, waarbij genoemd eerste bewegingsarmsamenstel een buisgrijplid (138) ondersteund dat is ingericht voor het grijpen van een buis, waarbij genoemde bewegingsarm het mogelijk maakt om een gegrepen buis tussen genoemde vuurlijn en genoemde verticale en geoffsette overdrachtspositie te bewegen.A method according to claims 14-15, wherein the drilling rig comprises: - at least one first vertical rail (65) extending along the first tower leg and wherein the racker device comprises: - a first movement arm device (135) that includes a base (136) and a movable motion arm (137), for example an extendable and retractable motion arm, the base being guided by said at least first vertical rail (65), and the motion arm having an operative range that extends the firing line (2) and said vertical and offset transfer position (T offset), said first movement arm assembly supporting a tube gripping member (138) adapted to grip a tube, said movement arm permitting a gripped tube to be moved between said firing line and said vertical and offset transfer position. 17. Werkwijze volgens een of meer van de conclusies 1-16, waarbij het verticale mobiele werkdek is voorzien van een opening (71) daarin dat is uitgelijnd met genoemde vuurlijn (2) en van een buisstring ondersteunende slipinrichting (75) dat is ingericht om een buisstring, bijvoorbeeld een boorbuisstring of een productiebuisstring, in genoemde vuurlijn {2) en binnen een riser (101) op te hangen die zich naar een onderzeese boorput uitstrekt wanneerA method according to any one of claims 1 to 16, wherein the vertical mobile work deck includes an opening (71) therein aligned with said firing line (2) and a tube string supporting slip device (75) adapted to suspend a tubing string, for example a casing string or a production tubing string, in said firing line (2) and within a riser (101) extending to a subsea wellbore when -37- de buisstring losgekoppeld is van het bewegende blok voor de verbinding van een nieuwe buis aan de opgehangen string.-37- the pipe string is disconnected from the moving block for the connection of a new pipe to the suspended string. 18. Werkwijze volgens een of meer van de conclusies 1-17, waarbij de boorinstallatie een boorputcenterwerktuighanteerinrichting (140) omvat, welke boorputcenterwerktuighanteerinrichting omvat: - ten minste een tweede verticale rail (141) die zich langs het tweede torenbeen uitstrekt, - een tweede bewegingsarminrichting (145) dat een basis (146) en een beweegbare bewegingsarm (147) omvat, bijvoorbeeld een uittrekbare en intrekbare bewegingsarm, waarbij de basis door genoemde ten minste ene tweede verticale rail geleid wordt en waarbij de bewegingsarm een werkzaam bereik heeft dat de vuurlijn omvat, waarbij genoemd bewegingsarmsamenstel is ingericht om ten minste een boorputcenterwerktuig (148) te ondersteunen, bijvoorbeeld een iron roughneck werktuig, en om het mogelijk te maken genoemd boorputcenterwerktuig in de vuurlijn te brengen.The method of any one of claims 1 to 17, wherein the drilling rig comprises a well center tool handling device (140), said well center tool handling device comprising: - at least one second vertical rail (141) extending along the second tower leg, - a second motion arm device (145) comprising a base (146) and a movable movement arm (147), for example an extendable and retractable movement arm, the base being guided by said at least one second vertical rail and the movement arm having an operative range including the firing line wherein said motion arm assembly is adapted to support at least one well center tool (148), e.g., an iron roughneck tool, and to permit said well center tool to be brought into the firing line. 19. Werkwijze volgens conclusie 18, waarbij de boorputcenterwerktuighanteerinrichting (140) is voorzien van een deiningsbewegingssynchronisatiesysteem dat is ingericht om de bewegingsarm daarvan en het boorputcenterwerktuig ondersteund daardoor in een verticale beweging te brengen die synchroon is met een deiningsbeweging van het mobiele werkdek en van een buisstring ondersteunende slipinrichting dat daarop verschaft is, bijvoorbeeld waarbij het boorputcenterwerktuig een iron roughneck inrichting is die gedurende een tripping operatie bestuurd wordt om een verbinding tussen buizen van de buisstring te maken of te verbreken.The method of claim 18, wherein the well center tool handling device (140) includes a swell motion synchronization system configured to cause its motion arm and the well center tool supported thereby to be in vertical motion synchronized with a swell motion of the mobile working deck and a tubing string. auxiliary slip device provided thereon, for example, wherein the well center tool is an iron roughneck device that is controlled during a tripping operation to make or break a connection between tubes of the tubing string. 20. Werkwijze volgens een of meer van de conclusies 1-19, waarbij genoemd bewegingsbereik van het verticale mobiele werkdek (70) een lagere stationaire positie omvat, waarbij het werkdek bruikbaar is als een boorvloerdek dat stationair is ten opzichte van de romp en bij voorkeur uitgelijnd is met een dekstructuur van de romp, en waarbij het deiningscompensatiebewegingsbereik (B,C) hoger ligt dan genoemde lager stationaire positie.A method according to any one of claims 1-19, wherein said range of motion of the vertical mobile work deck (70) comprises a lower stationary position, the work deck being useful as a drill floor deck that is stationary with respect to the hull and preferably is aligned with a deck structure of the hull, and wherein the heave compensation range of motion (B, C) is higher than said lower stationary position. 21. Boorinstallatie die is ingericht voor gebruik aan boord van een offshore boorvaartuig voor het uitvoeren van onderzeese boorput gerelateerde activiteiten langs een verticale vuurlijn, die bijvoorbeeld is ingericht voor aanpassen van een bestaand offshore boorvaartuig, waarbij het offshore boorvaartuig een drijvende romp heeft die voorzien is van een moonpool, waarbij de boorinstallatie omvat:21. Drilling rig configured for use on board an offshore drilling vessel for performing subsea well related activities along a vertical firing line, for example adapted for retrofitting an existing offshore drilling vessel, the offshore drilling vessel having a floating hull provided of a moonpool, where the rig includes: -38--38- - een boortorenstructuur omvattende:- a derrick structure comprising: o een onderframe dat is ingericht om op de romp van het offshore boorvaartuig te rusten,o a lower frame that is arranged to rest on the hull of the offshore drilling vessel, co een paar van eerste en tweede verticale torenbenen die op genoemd onderframe zijn opgericht, waarbij genoemde eerste en tweede torenbenen horizontaal gescheiden zijn op diametraal tegenoverliggende locaties ten opzichte van een verticale vuurlijn,co a pair of first and second vertical tower legs erected on said lower frame, said first and second tower legs being horizontally separated at diametrically opposite locations from a vertical firing line, o een kroonblokdwarsstructuur dat ondersteund wordt door genoemd paar van eerste een tweede verticale torenbenen, waarbij een kroonbloksamenstel ondersteund wordt door genoemd kroonblokdwarsstructuur, en waarbij de boortorenstructuur zo is ingericht dat een verticale last op het kroonbloksamenstel via het paar van torenbenen naar het onderframe wordt overgedragen en daardoor naar de romp van het offshore boorvaartuig,o a crown block cross structure supported by said pair of first and second vertical tower legs, wherein a crown block assembly is supported by said crown block cross structure, and wherein the derrick structure is arranged such that a vertical load on the crown block assembly is transferred to the lower frame via the pair of tower legs and thereby to the hull of the offshore drilling vessel, waarbij de boorinstallatie verder omvat:the rig further comprising: - een buisstringhoofdhijsinrichting omvattende:a tubular string main hoist comprising: o een of meer hoofdhijslieren die op het boortorenstructuur zijn aangebracht,o one or more main hoisting winches mounted on the derrick structure, o een of meer hoofdkabels die worden aangedreven door genoemde een of meer hoofdhijslieren en die zich uitstrekken naar genoemd kroonbloksamenstel,o one or more main ropes powered by said one or more main hoisting winches and extending to said crown block assembly, o een bewegend blok dat opgehangen is aan genoemd kroonbloksamenstel via genoemde een of meer hoofdkabels, welk bewegend blok is ingericht om een buisstring langs een vuurlijn door genoemde moonpool daaraan op te hangen,o a moving block suspended from said crown block assembly via said one or more main cables, the moving block being arranged to suspend a tube string along a firing line through said moonpool thereto, waarbij de boorinstallatie omvat:wherein the rig comprises: - een verticaal mobiel werkdek dat is aangebracht tussen het paar van torenbenen en dat verticaal beweegbaar is ten opzichte van de torenbenen langs genoemde vuurlijn binnen een bewegingsbereik omvattende een deiningscompensatiebewegingsbereik,a vertically mobile work deck disposed between the pair of tower legs and movable vertically with respect to the tower legs along said firing line within a range of motion including a swell compensation range of motion, waarbij, bij voorkeur, een slipinrichting op het werkdek verschaft is dat is ingericht om daarvan een buisstring in de vuurlijn (2) op te hangen, bijvoorbeeld gedurende een tripping operatie waarbij de buisstring in of uit een boorput getript wordt,wherein, preferably, a slip device is provided on the working deck adapted to suspend therefrom a tubular string in the firing line (2), for example during a tripping operation in which the tubular string is stripped into or out of a wellbore, waarbij de boorinstallatie omvat:wherein the rig comprises: - een geïntegreerd deiningscompensatiesysteem dat is ingericht om een deiningscompensatie van het bewegend blok en van het mobiele werkdek te verschaffen,- an integrated swell compensation system arranged to provide swell compensation of the moving block and of the mobile working deck, -39.- waarbij het geintegreerde deiningscompensatiesysteem een hydraulische hoofdkabelcompensator omvat die op de een of meer hoofdkabels aangrijpt en die is ingericht om een deining compenserende beweging van het bewegende blok te verschaffen, waarbij het geïntegreerde deiningscompensatiesysteem verder een hydraulische dekcompensator omvat, welk hydraulische dekcompensator met de boortorenstructuur en met het mobiele werkdek verbonden is en welke is ingericht om een deining gecompenseerde beweging van het werkdek relatief aan de boortorenstructuur binnen een deiningscompensatiebewegingsbereik te verschaffen, waarbij het geïntegreerde deiningscompensatiesysteem zo is ingericht dat, in bedrijf, genoemde hydraulische dekcompensator en genoemde hydraulische hoofdkabelcompensator synchroon bewegen om deiningscompensatie van zowel het bewegende blok als het mobiele werkdek te verschaffen.-39.- wherein the integrated heave compensation system comprises a hydraulic main rope compensator which engages the one or more main cables and is arranged to provide a swell compensating movement of the moving block, the integrated heave compensation system further comprising a hydraulic deck compensator, said hydraulic deck compensator having the derrick structure and is connected to the mobile working deck and which is arranged to provide a swell compensated movement of the working deck relative to the derrick structure within a swell compensation movement range, the integrated swell compensation system being arranged such that, in operation, said hydraulic deck compensator and said main hydraulic cable compensator move synchronously to provide swell compensation of both the moving block and mobile work deck. 22. Offshore boorvaartuig voor het uitvoeren van boorput gerelateerde activiteiten langs een verticale vuurlijn, waarbij het offshore boorvaartuig een drijvende romp heeft die voorzien is van een moonpool, waarbij het offshore boorvaartuig een boorinstallatie heeft omvattende: - een boortorenstructuur omvattende: o een paar van eerste en tweede verticale torenbenen, die bijvoorbeeld op een onderframe zijn opgericht dat op de romp van het offshore boorvaartuig ligt, waarbij genoemde eerste en tweede torenbenen horizontaal gescheiden zijn op diametraal tegenoverliggende locaties ten opzichte van een verticale vuurlijn, co een kroonblokdwarsstructuur dat ondersteund wordt door genoemd paar van eerste een tweede verticale torenbenen, waarbij een kroonbloksamenstel ondersteund wordt door genoemd kroonblokdwarsstructuur, en waarbij de boortorenstructuur zo is ingericht dat een verticale last op het kroonbloksamenstel via het paar van torenbenen naar de romp wordt overgedragen, bijvoorbeeld via een onderframe en daarbij naar vier boortorenondersteuningsstructuren van de romp van het offshore boorvaartuig, waarbij de boorinstallatie verder omvat: - een buisstring hoofdhijsinrichting omvattende:22. Offshore drilling vessel for performing well related activities along a vertical firing line, wherein the offshore drilling vessel has a floating hull provided with a moon pool, the offshore drilling vessel having a drilling rig comprising: a derrick structure comprising: a pair of first and second vertical tower legs erected, for example, on a lower frame resting on the hull of the offshore drilling vessel, said first and second tower legs being horizontally separated at diametrically opposite locations from a vertical firing line, co a crown block cross structure supported by said pair of first and second vertical tower legs, wherein a crown block assembly is supported by said crown block cross structure, and wherein the derrick structure is arranged so that a vertical load on the crown block assembly is transferred to the hull via the pair of tower legs, e.g. ia a lower frame and thereby to four derrick support structures of the hull of the offshore drilling vessel, the rig further comprising: a tubular string main hoist comprising: - 40 - o een of meer hoofdhijslieren die op het boortorenstructuur zijn aangebracht, o een of meer hoofdkabels die worden aangedreven door genoemde een of meer hoofdhijslieren en die zich uitstrekken naar genoemde kroonbloksamenstel, o een bewegend blok dat opgehangen is aan genoemd kroonbloksamenstel via genoemde een of meer hoofdkabels, welk bewegend blok is ingericht om een buisstring langs een vuurlijn door genoemde moonpool daaraan op te hangen, waarbij de boorinstallatie omvat: - een verticaal mobiel werkdek dat is aangebracht tussen het paar van torenbenen en dat verticaal beweegbaar is ten opzichte van de torenbenen langs genoemde vuurlijn binnen een bewegingsbereik omvattende een deiningscompensatiebewegingsbereik, waarbij, bij voorkeur, een slipinrichting op het werkdek verschaft is dat is ingericht om daarvan een buisstring in de vuurlijn op te hangen, bijvoorbeeld gedurende een tripping operatie waarbij de buisstring in of uit een boorput getript wordt, waarbij de boorinstallatie omvat: - een geïntegreerd deiningscompensatiesysteem dat is ingericht om een deiningscompensatie van het bewegend blok en van het mobiele werkdek te verschaffen, waarbij het geïntegreerde deiningscompensatiesysteem een hydraulische hoofdkabelcompensator omvat die op de een of meer hoofdkabels aangrijpt en die is ingericht om een deining compenserende beweging van het bewegende blok te verschaffen, waarbij het geïntegreerde deiningscompensatiesysteem verder een hydraulische dekcompensator omvat, welk hydraulische dekcompensator met de boortorenstructuur en met het mobiele werkdek verbonden is en welke is ingericht om een deining gecompenseerde beweging van het werkdek relatief aan de boortorenstructuur binnen een deiningscompensatiebewegingsbereik te verschaffen, waarbij het geïntegreerde deiningscompensatiesysteem is ingericht zo dat, in bedrijf, genoemde hydraulische dekcompensator en genoemde hydraulische hoofdkabelcompensator synchroon bewegen om deiningscompensatie van zowel het bewegende blok als het mobiele werkdek te verschaffen.- 40 - o one or more main hoist winches mounted on the derrick structure, o one or more main ropes driven by said one or more main hoist winches and which extend to said crown block assembly, o a moving block suspended from said crown block assembly via said one or more main ropes, the moving block adapted to suspend a tubular string along a firing line through said moonpool thereto, the drilling rig comprising: a vertically mobile working deck disposed between the pair of turret legs and vertically movable with respect to the tower legs along said firing line within a range of motion including a swell compensation range of motion, preferably providing a skid device on the working deck adapted to suspend therefrom a tubing string in the firing line, for example during a tripping operation where the tubing string is in or out of a wellbore trip, whereby the drill insta llation comprises: an integrated heave compensation system arranged to provide swell compensation of the moving block and of the mobile work deck, the integrated heave compensation system comprising a hydraulic main cable compensator which engages the one or more main cables and which is adapted to provide a swell compensating movement. of the moving block, the integrated heave compensation system further comprising a hydraulic deck compensator, the hydraulic deck compensator connected to the derrick structure and to the mobile working deck and adapted to provide a swell compensated movement of the working deck relative to the derrick structure within a heave compensation range of motion. wherein the integrated heave compensation system is arranged such that, in operation, said hydraulic deck compensator and said main hydraulic cable compensator move synchronously to compensate for heave of both provide the moving block as the mobile working deck. 23. Werkwijze voor het uitvoeren van onderzeese boorput gerelateerde activiteiten langs een verticale vuurlijn, waarbij gebruik wordt gemaakt van een boorvaartuig verkregen volgens een23. A method of conducting subsea well related activities along a vertical firing line using a drilling vessel obtained in accordance with a -41- of meer van de conclusies 1-20, een boorinstallatie volgens conclusie 21, en/of een offshore boorvaartuig volgens conclusie 22.-41- or more of claims 1-20, a drilling rig according to claim 21, and / or an offshore drilling vessel according to claim 22.
NL2023277A 2019-06-07 2019-06-07 Retrofitting an existing offshore drilling vessel NL2023277B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
NL2023277A NL2023277B1 (en) 2019-06-07 2019-06-07 Retrofitting an existing offshore drilling vessel
PCT/EP2020/065702 WO2020245408A1 (en) 2019-06-07 2020-06-05 Retrofitting an existing offshore drilling vessel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NL2023277A NL2023277B1 (en) 2019-06-07 2019-06-07 Retrofitting an existing offshore drilling vessel

Publications (1)

Publication Number Publication Date
NL2023277B1 true NL2023277B1 (en) 2021-01-11

Family

ID=67742896

Family Applications (1)

Application Number Title Priority Date Filing Date
NL2023277A NL2023277B1 (en) 2019-06-07 2019-06-07 Retrofitting an existing offshore drilling vessel

Country Status (2)

Country Link
NL (1) NL2023277B1 (en)
WO (1) WO2020245408A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2028189B1 (en) * 2021-05-11 2022-11-29 Itrec Bv Offloading an object from a heave motion compensated carrier of a vessel.
CN115092858B (en) * 2022-06-17 2023-09-19 中国舰船研究设计中心 Ship underwater test operation system and method
CN115162986B (en) * 2022-08-23 2023-04-28 四川省金钻地质矿产勘探工程有限责任公司 Wave balance rope coring drilling device and drilling method thereof
NL2033170B1 (en) * 2022-09-28 2024-04-05 Itrec Bv Offshore drilling vessel and installation for perforing subsea wellbore related activities

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6000480A (en) * 1997-10-01 1999-12-14 Mercur Slimhole Drilling Intervention As Arrangement in connection with drilling of oil wells especially with coil tubing
WO2011034422A2 (en) 2009-09-18 2011-03-24 Itrec B.V. Hoisting device
WO2013169099A2 (en) 2012-05-11 2013-11-14 Itrec B.V. Offshore vessel and method of operation of such an offshore vessel
WO2014209131A1 (en) 2013-06-25 2014-12-31 National Oilwell Varco Norway As System for hoisting a load on an offshore rig
US20150008382A1 (en) 2013-07-03 2015-01-08 Cameron International Corporation Motion Compensation System
CN105507827A (en) * 2015-12-23 2016-04-20 宝鸡石油机械有限责任公司 Lifting oil cylinder type well drilling device
WO2016062812A1 (en) 2014-10-24 2016-04-28 Itrec B.V. Offshore drilling system, vessel and method
US20170152716A1 (en) * 2013-05-27 2017-06-01 Itrec B.V. Drilling vessel
WO2018151593A1 (en) 2017-02-14 2018-08-23 Itrec B.V. Heave motion compensation system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6000480A (en) * 1997-10-01 1999-12-14 Mercur Slimhole Drilling Intervention As Arrangement in connection with drilling of oil wells especially with coil tubing
WO2011034422A2 (en) 2009-09-18 2011-03-24 Itrec B.V. Hoisting device
WO2013169099A2 (en) 2012-05-11 2013-11-14 Itrec B.V. Offshore vessel and method of operation of such an offshore vessel
US20170152716A1 (en) * 2013-05-27 2017-06-01 Itrec B.V. Drilling vessel
WO2014209131A1 (en) 2013-06-25 2014-12-31 National Oilwell Varco Norway As System for hoisting a load on an offshore rig
US20150008382A1 (en) 2013-07-03 2015-01-08 Cameron International Corporation Motion Compensation System
WO2016062812A1 (en) 2014-10-24 2016-04-28 Itrec B.V. Offshore drilling system, vessel and method
CN105507827A (en) * 2015-12-23 2016-04-20 宝鸡石油机械有限责任公司 Lifting oil cylinder type well drilling device
WO2018151593A1 (en) 2017-02-14 2018-08-23 Itrec B.V. Heave motion compensation system

Also Published As

Publication number Publication date
WO2020245408A1 (en) 2020-12-10

Similar Documents

Publication Publication Date Title
NL2023277B1 (en) Retrofitting an existing offshore drilling vessel
US6857483B1 (en) Drilling device and method for drilling a well
US11781384B2 (en) Drilling installation: handling system, method for independent operations
US6988459B2 (en) Multipurpose tower for monohull with moveable hatch
US9624739B2 (en) Drilling rig
EP3710351B1 (en) Vessel and method for performing subsea wellbore related activities
NO347452B1 (en) An offshore drilling rig and a method of operating the same
WO2014108542A2 (en) Drilling rig
EP4107359B1 (en) Offshore drilling vessel and installation for performing subsea wellbore related activities
EP3938274B1 (en) Offshore system, vessel and method for performing subsea wellbore related activities
US11377172B2 (en) Semi-submersible drilling vessel, e.g. for use in a harsh environment
CN214397139U (en) Vessels used to perform subsea wellbore related activities such as workover activities, well maintenance, installation of objects on subsea wellbore
EP3829967B1 (en) Semi-submersible
NL2020457B1 (en) Semi-submersible drilling vessel, e.g. for use in a harsh environment
NL2016059B1 (en) Drilling installation; Handling system, method for independent operations.
WO2024068366A1 (en) Offshore drilling vessel and installation for performing subsea wellbore related activities