[go: up one dir, main page]

KR20110046209A - Bridge bridge foundation reinforcement and scour prevention construction method and structure - Google Patents

Bridge bridge foundation reinforcement and scour prevention construction method and structure Download PDF

Info

Publication number
KR20110046209A
KR20110046209A KR1020090116266A KR20090116266A KR20110046209A KR 20110046209 A KR20110046209 A KR 20110046209A KR 1020090116266 A KR1020090116266 A KR 1020090116266A KR 20090116266 A KR20090116266 A KR 20090116266A KR 20110046209 A KR20110046209 A KR 20110046209A
Authority
KR
South Korea
Prior art keywords
bridge
scour prevention
foundation
bag
foundation reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
KR1020090116266A
Other languages
Korean (ko)
Inventor
남봉수
Original Assignee
남봉수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 남봉수 filed Critical 남봉수
Priority to KR1020090116266A priority Critical patent/KR20110046209A/en
Publication of KR20110046209A publication Critical patent/KR20110046209A/en
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물에 관한 것으로, 현지의 준설사토를 채운 포대를 교각기초 주위에 거치한 후 로프로 하나로 결속시킴으로써, 시공이 간편하고 공사기간 및 공사비용을 획기적으로 줄일 수 있으며, 녹 발생에 의한 수질 오염을 방지할 수 있고 영구적으로 사용할 수 있다. 그리고 현지 준설토를 활용하여 교각기초를 보강하고 동시에 세굴을 방지시킬 수 있고 하천 바닥에 쌓인 토사를 함께 제거할 수 있다. 또한, 교각기초 주위에 준설사토 포대를 쌓은 후 로프로 하나로 결속시킴으로써 연결성을 강화하고 시공품질 확인이 용이하며, 자중 증대로 홍수나 집중호우시 유실될 염려가 없고 수중공사가 가능하며, 준설사토 포대의 파손시 보수 및 교체가 용이하다.

이를 위한 본 발명의 교량 교각기초 보강 및 세굴방지 시공 방법은, (a) 기초지반 위에 교각을 시공하는 단계와; (b) 교량 공사 주변의 준설 사토를 포대에 채우는 단계와; (c) 상기 교각의 하부 둘레에 상기 포대를 복수 개로 설치하는 단계; 및 (d) 상기 포대를 로프로 연결하여 상기 교각과 하나로 결속하는 단계;를 포함하고 있다.

Figure P1020090116266

교량, 교각, 보강, 세굴 방지, 포대, 사토, 토목섬유, 보호막, 로프

The present invention relates to a bridge bridge foundation reinforcement and scour prevention construction method and its structure, by mounting a bag filled with local dredging sand around the bridge foundation, and then tied with a rope, the construction is simple and the construction period and construction cost It can be drastically reduced, can prevent water pollution caused by rust and can be used permanently. Local dredged soils can be used to reinforce bridge foundations and prevent scours, and to remove soil piled up in riverbeds. In addition, by building a dredging sand bag around the foundation of the bridge, it is easy to reinforce the connection by checking the quality of construction by binding it with one rope. Easy repair and replacement in case of breakage.

Bridge bridge foundation reinforcement and scour prevention construction method of the present invention for this purpose, (a) constructing a bridge on the foundation ground; (b) filling the turret with dredge sato around the bridge construction; (c) installing a plurality of the bags around the lower portion of the piers; And (d) connecting the bag with a rope and binding the bag with one of the piers.

Figure P1020090116266

Bridges, Piers, Reinforcement, Scour Prevention, Bags, Sato, Geotextiles, Shields, Ropes

Description

교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물{Method Of Construction For Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same}Method of Construction for Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same}

본 발명은 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물에 관한 것으로, 보다 상세하게는 현지 준설사토를 채운 포대를 교각기초 주위에 거치한 후 로프로 하나로 결속시킴으로써, 시공이 간편하고 공사기간 및 공사비용을 획기적으로 줄일 수 있을 뿐만 아니라 영구적 사용이 가능한 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물에 관한 것이다.The present invention relates to a bridge bridge foundation reinforcement and scrubbing prevention construction method and structure thereof, and more specifically, by mounting a bag filled with local dredging soil around the bridge foundation, and then bound by one rope, construction is simple and construction period and The present invention relates to a bridge bridge foundation reinforcement and scour prevention construction method and structure thereof that can not only drastically reduce construction cost but also can be permanently used.

일반적으로, 강이나 하천 등을 가로질러 설치되는 교량의 교각 하부에는 우물통 형상이나 사각기둥 형상으로 기초가 형성된다.In general, the foundation is formed in the bottom of the bridge piers across the river, river, etc. in a well shape or a square pillar shape.

상기한 교량의 교각기초는 대부분 물속에 일부 또는 전부가 잠긴 상태로 설치되고, 시간이 지남에 따라 흐르는 물에 의하여 점점 침식되거나 주위지반이 세굴되는 현상이 발생한다. 따라서 여러가지 보강장치 및 이를 이용한 보강공법을 통하 여 보강을 행하게 된다.Most of the bridge foundations of the bridges are installed in a state where some or all of them are submerged in water, and as time passes, erosion or erosion of the surrounding ground occurs by the flowing water. Therefore, the reinforcement is performed through various reinforcement devices and reinforcement methods using the same.

상기한 교량의 교각기초를 보강하기 위한 공법은 교각기초의 외부와 일정간격을 유지하도록 거푸집을 설치하고, 상기한 거푸집과 우물통의 중간에 철근을 배근한 후 콘크리트를 타설하게 되며, 상기한 거푸집의 설치전에는 물의 접근을 막기 위하여 교각기초의 주변에 제방을 쌓거나 시트파일(sheet pile)을 박는 가물막이 공사를 하는 것으로 이루어진다.The method for reinforcing the bridge foundation of the bridge is to install the formwork to maintain a certain distance from the outside of the bridge foundation, and to reinforce the reinforcing bar in the middle of the formwork and the well, and then cast concrete, Prior to the installation, the construction of temporary screening works is carried out to build banks around the piers or to embed sheet piles to prevent water access.

상기와 같이 이루어지는 종래의 교량의 교각기초 보강공법은 가물막이와 별도로 거푸집 설치공사를 하게 되므로, 작업이 번거롭고 설치에 필요한 부대장비 및 비용의 낭비가 심하다.The bridge foundation reinforcement method of the conventional bridge made as described above is a formwork installation work separately from the temporary barrier, the work is cumbersome and waste of additional equipment and cost required for installation.

그리고 상기한 가물막이 작업 후에 설치되는 거푸집은 교각기초의 외면과 일정거리를 유지시켜서 고정하기 어려우므로, 먼저 배근되는 철근에 전기용접하여 고정시킨다. 따라서 상기한 거푸집의 해체작업이 복잡하고 어려우며, 해체를 하지 않는 경우에는 거푸집이 부식되어 수질오염 등을 초래한다.In addition, since the formwork installed after the temporary film work is difficult to fix by maintaining a certain distance from the outer surface of the bridge foundation, it is first fixed by electric welding to the reinforcing bars. Therefore, the dismantling operation of the formwork is complicated and difficult, and if it is not dismantled, the formwork is corroded, resulting in water pollution.

또 상기와 같이 이루어지는 종래의 교량의 교각기초 보강공법에서 시트파일을 통하여 가물막이를 경우에는 교각기초의 주변 지형에 상관없이 수중에 위치한 바닥에 시트파일의 박히는 길이가 일정하므로 일부분이 취약해질 수 있다.In addition, in the conventional bridge foundation reinforcement method of the bridges made as described above, if the clogging through the seat pile, the length of the pile pile is constant on the floor located in the water regardless of the surrounding topography of the bridge foundation may be a weak part. .

그러면, 첨부된 도면을 참조하여 종래의 교량 교각기초 세굴방지 공법과 그 문제점에 대해 더 자세히 알아보기로 한다.Then, with reference to the accompanying drawings will be described in more detail for the conventional bridge bridge foundation scrubbing method and its problems.

도 1 내지 도 4는 종래의 교량 교각기초 세굴방지 공법을 나타낸 도면으로서, 도 1은 사석을 이용한 세굴방지 공법을 나타낸 단면도이고, 도 2는 돌망태공을 이용한 세굴방지 공법을 나타낸 단면도이고, 도 3은 시트파일(sheet pile)을 이용한 세굴방지 공법을 나타낸 단면도이고, 도 4는 콘크리트 블록 매트를 이용한 세굴방지 공법을 나타낸 단면도이다.1 to 4 is a view showing a conventional bridge bridge foundation scour prevention method, Figure 1 is a cross-sectional view showing a scour prevention method using sandstone, Figure 2 is a cross-sectional view showing a scour prevention method using a gabion hole, Figure 3 Is a cross-sectional view showing a scour prevention method using a sheet pile, Figure 4 is a cross-sectional view showing a scour prevention method using a concrete block mat.

먼저, 도 1의 사석을 이용한 세굴방지 공법은 임시 및 응급공사에 용이하고 수중공사가 가능하지만, 수중투하시 시공효율이 낮고 시공결과(시공품질)를 확인하기 어려운 단점이 있다. 그리고 사석과 사석 사이에 상호 연결성이 없고 타원형에 가까운 형상으로 시공되기 때문에 홍수나 집중호우시 전도 유실될 염려가 있으며, 이때 전도된 사석이 하류 교량의 교각에 부딪쳐서 안전사고 및 하자 요인을 발생시킬 우려가 있다.First, the scour prevention method using the sandstone of Figure 1 is easy for temporary and emergency construction and can be underwater construction, there is a disadvantage in the construction efficiency (construction quality) is low and the construction efficiency when dropped underwater. And since there is no interconnection between the sandstone and the sandstone, the construction is close to elliptical shape, so there is a risk of falling in the event of flooding or heavy rain.At this time, the felled sandstone may collide with the lower bridge and cause safety accident and defect There is.

그리고 도 2의 돌망태공을 이용한 세굴방지 공법은 사석식 공법과 같이 임시 및 응급공사에 용이하고 수중공사가 가능하지만, 수중투하시 시공효율이 낮고 시공결과(시공품질)를 확인하기 어려우며 철망의 부식으로 수명이 짧은 단점이 있다. 그리고 홍수나 집중호우시 세굴에 의한 변위로 유실 발생이 우려되고, 유실된 돌망태가 하류측에 쌓이면서 제2의 국부세굴이 진행될 우려가 있다.And the scour prevention method using the gabion perforation of FIG. 2 is easy for temporary and emergency construction and can be underwater construction like the four stone method, it is difficult to confirm the construction efficiency (construction quality) when the water is dropped and the corrosion of the wire mesh This has a short lifespan. In addition, there is a fear of loss due to displacement due to scour in flooding or heavy rain, and there is a fear that a second local scour may proceed as the lost gabions accumulate downstream.

또한, 도 3의 시트파일(sheet pile)을 이용한 세굴방지 공법은 지지기반이 깊을 경우에 시공되는 공법으로서, 다수의 말뚝을 항타하여 지지기반까지 도달되도록 하므로써 충분한 하중전달이 이루어 질 수 있게 한 후 다수의 말뚝 위에 푸팅을 설치하고 상기 푸팅에 교각 기둥을 설치한다. In addition, the scour prevention method using a sheet pile of FIG. 3 is a construction method when the support base is deep, so that sufficient load transfer can be achieved by driving a plurality of piles to reach the support base. A footing is installed over a plurality of piles and a pier column is installed in the footing.

상기 시트파일을 이용한 세굴방지 공법은 반영구적이며, 강성이 뛰어나고 하부구조의 안전성이 좋은 장점은 있지만, 수중 공사가 불가능하고 시공 효율성이 낮 으며 가물막이가 필요하고 파일외부에 세굴이 발생될 염려가 있다. 그리고 시공시 과도한 터파기량이 발생되어 터파기 잔존물의 후처리 문제도 있으며, 많은 작업공간을 필요로 하여 작업의 동시 진행이 힘들어 공사 기간이 많이 소요되는 단점이 있다. 또한, 소구경의 말뚝 항타시에는 소음 및 진동이 심하게 발생되어 주변의 민원을 야기시키며, 기초하부지반이 자갈층일 경우 말뚝의 항타및 관입이 곤란하고, 교각에 파일에 의해서만 지지되어 횡압력에 취약한 문제점이 있다.The scour prevention method using the sheet pile is semi-permanent, has excellent rigidity and good safety of the substructure, but underwater construction is impossible, construction efficiency is low, temporary screening is required, and scour may occur outside the pile. . In addition, there is a problem of post-treatment of the residue of the trench due to excessive amount of excavation during construction, and it requires a lot of work space, so it is difficult to simultaneously proceed with the work, and thus a lot of construction period is required. In addition, when driving small piles, noise and vibration are severely generated, causing civil complaints, and when foundation foundation is gravel layer, the driving and penetration of piles are difficult, and only the piles are supported by piles, making them vulnerable to lateral pressure. There is this.

마지막으로, 도 4의 콘크리트 블록 매트를 이용한 세굴방지 공법은 콘크리트 블록 매트의 연결성 등 품질확인이 용이하고 육상에서 조립하므로 시공효율이 높고 표설면적에 맞게 설치할 수 있다. 그리고, 저중심 평면형이며, 모든 블록이 연결되어 홍사나 집중호우시 전도유실될 염려가 없고, 수중공사가 가능한 장점이 있다. 그러나, 상기 콘크리트 블록 매트를 이용한 세굴방지 공법은 다른 공법에 비해 공사 비용이 많이 들고, 대형 크레인을 사용하여 공사를 해야 하는 단점이 있다.Finally, the scour prevention method using the concrete block mat of Figure 4 is easy to check the quality, such as the connection of the concrete block mat and assembled on the land, the construction efficiency is high and can be installed according to the surface area. In addition, the low center of gravity planar, all the blocks are connected, there is no fear of loss of conduction in the case of red sand or heavy rain, there is an advantage that can be underwater construction. However, the scour prevention method using the concrete block mat has a disadvantage in that the construction cost is much higher than the other construction methods, the construction using a large crane.

또한, 이와 같은 종래의 세굴방지 공법들은 기존 교각의 기초 구조물, 특히 수중 기초부위가 항상 물과 접촉하고 있기 때문에 흐르는 물의 산도나 알카리도, 염분 그리고 유수를 타고 이동되는 바위 등과의 충돌 등에 의한 영향을 받아 세월이 지나면서 표면이 부식 손상되는 세굴 현상을 일으키게 된다. 이때 세굴현상은 수중에서 서서히 진행되는 것이기 때문에 쉽게 발견되지 않아 오랜 시간이 흐르면 교량의 안전도를 저해하는 수준으로 발전되기도 한다. 이와 같이 훼손된 교각의 기초는 세굴된 부위로 수중 콘크리트를 타설하고 메꾸는 수중 작업을 통해 보수하거나 또는 교각 기초 주변에 물막이를 설치하고 구획된 공간의 물을 배수시킨 다음 보수작업을 행하는 방법으로 작업하고 있다.In addition, the conventional scour prevention methods are affected by the impact of acidity, alkalinity, salinity and flowing rocks of the flowing water because the foundation structure of the existing piers, especially underwater foundations are always in contact with the water Over time, it causes scour, the surface of which is corroded and damaged. At this time, the scour phenomenon is progressed slowly in the water, so it is not easily detected, and may develop to a level that hinders the safety of the bridge after a long time. The foundation of the damaged pier is repaired by underwater work by placing and filling underwater concrete with scoured areas, or by installing water barriers around the pier foundation, draining the water in the partitioned space, and performing repair work. have.

그렇지만 주지된 바와 같이, 수중 작업은 장시간 수행하기가 어려워서 공사 기간이 필요 이상으로 길어지는 문제가 있고, 물막이는 수압에 견딜 수 있도록 견고하게 설치되어야 하기 때문에 이를 설비하고 공사 종료 후에 해체 제거하는 작업이 수반되어야 하는 문제를 안고 있다. 게다가, 종래의 보수 방법은 세굴된 부위를 메꾸고 있는 콘크리트층이 다시 떨어져 나가게 되므로 보수 효과도 크게 기대할 수 없었다.However, as is well known, underwater work is difficult to carry out for a long time, so the construction period is longer than necessary, and the water barrier must be installed firmly to withstand the water pressure, so the work of dismantling and removing it after completion of construction There is a problem that must be accompanied. In addition, in the conventional repair method, since the concrete layer filling the scoured site falls off again, the repair effect could not be greatly expected.

전술한 문제점을 해결하기 위하여 본 발명이 이루고자 하는 기술적 과제는, 현지의 준설사토를 채운 포대를 교각기초 주위에 1단 또는 2단 이상 거치한 후 로프로 하나로 결속시킴으로써, 시공이 간편하고 공사기간 및 공사비용을 획기적으로 줄일 수 있는 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하는데 있다.Technical problem to be solved by the present invention in order to solve the above-mentioned problems, by mounting a bag or a two or more steps around the pier foundation filled with local dredging soil, and binds with one rope, construction is easy and construction period and The purpose of this study is to present a bridge bridge foundation reinforcement and scour prevention construction method and structure that can drastically reduce construction cost.

또한, 본 발명이 이루고자 하는 다른 기술적 과제는 녹 발생에 의한 수질 오염을 방지할 수 있고 영구적으로 사용할 수 있는 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하는데 있다.In addition, another technical problem to be achieved by the present invention is to propose a bridge bridge foundation reinforcement and scour prevention construction method and its structure that can prevent water pollution due to rust generation and can be used permanently.

또한, 본 발명이 이루고자 하는 또 다른 기술적 과제는 현지 준설토를 활용하여 교각기초를 보강하고 동시에 세굴을 방지시킬 수 있는 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하는데 있다.In addition, another technical problem to be achieved by the present invention is to propose a bridge bridge foundation reinforcement and scour prevention construction method and structure that can be used to reinforce the bridge foundation and at the same time prevent scour using local dredged soil.

또한, 본 발명이 이루고자 하는 또 다른 기술적 과제는 교량 교각의 기초 보강 및 세굴 방지를 가능하게 할 뿐만 아니라 하천 바닥에 쌓인 토사를 함께 제거할 수 있는 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하는데 있다.In addition, another technical problem to be achieved by the present invention is to not only enable the foundation reinforcement and scour prevention of bridge bridges, but also the bridge bridge foundation reinforcement and scrubbing construction method and structure that can remove the soil piled up on the river floor together with the structure To present.

또한, 본 발명이 이루고자 하는 또 다른 기술적 과제는 교각기초 주위에 준설사토 포대를 쌓은 후 로프로 하나로 결속시킴으로써 연결성을 강화하고 시공품질 확인이 용이한 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하 는데 있다.In addition, another technical problem to be achieved by the present invention is to build a dredged sanding bag around the bridge foundation and bind it together with a rope to strengthen the connectivity and easy construction of bridge bridge foundation reinforcement and scour prevention construction method and its structure To present.

또한, 본 발명이 이루고자 하는 또 다른 기술적 과제는 자중증대(350톤 이상)로 홍수나 집중호우시 유실될 염려가 없고 수중공사가 가능한 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하는데 있다.In addition, another technical problem to be achieved by the present invention is to propose a bridge bridge foundation reinforcement and scour prevention construction method and structure there is no fear of loss in flood or heavy rain due to self-weight increase (350 tons or more) .

또한, 본 발명이 이루고자 하는 또 다른 기술적 과제는 파손시 보수 및 교체가 용이한 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물을 제시하는데 있다.In addition, another technical problem to be achieved by the present invention is to propose a bridge bridge foundation reinforcement and scour prevention construction method and its structure that is easy to repair and replace when broken.

전술한 기술적 과제를 해결하기 위한 수단으로서, 청구항 1에 기재된 발명은, 「교량 교각기초 보강 및 세굴방지 시공 방법에 있어서, (a) 기초지반 위에 교각을 시공하는 단계와; (b) 교량 공사 주변의 준설 사토를 포대에 채우는 단계와; (c) 상기 교각의 하부 둘레에 상기 포대를 복수 개로 설치하는 단계; 및 (d) 상기 포대를 로프로 연결하여 상기 교각과 하나로 결속하는 단계;를 포함하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.As a means for solving the above-described technical problem, the invention as set forth in claim 1, "In the bridge bridge foundation reinforcement and scour prevention construction method, (a) constructing a bridge on the foundation ground; (b) filling the turret with dredge sato around the bridge construction; (c) installing a plurality of the bags around the lower portion of the piers; And (d) connecting the bag with a rope and binding the bag with one of the bridge piers.

청구항 2에 기재된 발명은, 「제 1 항에 있어서, 상기 교량 교각기초 보강 및 세굴방지 시공 방법은: 상기 포대가 설치되는 상기 교각의 하부 둘레에 보호막을 설치하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.According to the invention of claim 2, "The bridge bridge foundation reinforcement and scour prevention construction method is a bridge bridge foundation reinforcement of Claim 1 characterized by providing a protective film around the lower part of the bridge in which the bag is installed. Scrubbing prevention construction method.

청구항 3에 기재된 발명은, 「제 2 항에 있어서, 상기 보호막은: PE 쿠션 시 트 또는 PE 쿠션 패드를 사용하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention according to claim 3 provides the method according to claim 2, wherein the protective film is a PE cushion sheet or a PE cushion pad.

청구항 4에 기재된 발명은, 「제 1 항에 있어서, 상기 교각은: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention according to claim 4 provides "the method according to claim 1, wherein the pier is constructed at a site in which the foundation ground is dug to a predetermined depth. '

청구항 5에 기재된 발명은, 「제 1 항에 있어서, 상기 교각 및 포대는: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention according to claim 5 provides "the method of claim 1, wherein the pier and the bag are constructed in a position in which the foundation ground is dug to a predetermined depth. do.

청구항 6에 기재된 발명은, 「제 4 항 또는 제 5 항에 있어서, 상기 소정의 깊이는: 2 내지 7m 범위를 갖는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention according to claim 6 provides "the method according to claim 4 or 5, wherein the predetermined depth has a range of 2 to 7 m.

청구항 7에 기재된 발명은, 「제 1 항에 있어서, 상기 포대 및 로프는: 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene)으로 구성된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention as set forth in claim 7, wherein the bag and the rope is: Geosynthetic material or polyethylene terephthalate (PET) or polypropylene (polypropylene), bridge bridge foundation reinforcement and scour prevention construction Method.

청구항 8에 기재된 발명은, 「제 1 항 또는 제 7 항에 있어서, 상기 포대는: 외측면에 상기 로프를 연결하기 위한 연결고리가 복수개로 설치된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention according to claim 8, "The method according to claim 1 or 7, wherein the bag: a bridge bridge foundation reinforcement and scour prevention construction method characterized in that a plurality of connecting rings for connecting the rope on the outer surface is provided. .

청구항 9에 기재된 발명은, 「제 1 항에 있어서, 상기 교량 교각기초 보강 및 세굴방지 시공 방법은: 상기 교각의 하부 둘레에 상기 포대를 1단 또는 2단 이 상으로 설치하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.According to the ninth aspect of the present invention, "The bridge bridge foundation reinforcement and scour prevention construction method according to claim 1 includes: a bridge provided with one or two or more stages of the bag around the lower portion of the bridge. Bridge foundation reinforcement and scour prevention construction method.

청구항 10에 기재된 발명은, 「제 1 항에 있어서, 상기 기초지반은: 하천, 강, 육지 중 어느 한 곳인 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.」을 제공한다.The invention according to claim 10 provides "The method of claim 1, wherein the foundation ground is any one of a river, a river, and a land. '

전술한 기술적 과제를 해결하기 위한 수단으로서, 청구항 11에 기재된 발명은, 「교량 교각기초 보강 및 세굴방지 시공 구조물에 있어서, 기초지반 위에 시공된 교각과; 상기 교각의 하부 둘레에 1단 또는 2단 이상 설치되며 내부에 준설 사토로 채워진 복수 개의 포대; 및 상기 복수 개의 포대를 단별로 상기 교각과 하나로 결속하는 로프;를 포함하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.As a means for solving the above-described technical problem, the invention described in claim 11, "In the bridge bridge foundation reinforcement and scour prevention construction structure, bridge piers constructed on the foundation ground; A plurality of bags installed in one or two or more stages around the lower portion of the pier and filled with dredged soil; And a bridge for binding the plurality of bags to the bridge and one by one stage. Bridge foundation reinforcement and scour prevention construction structure comprising a.

청구항 12에 기재된 발명은, 「제 11 항에 있어서, 상기 교량 교각기초 보강 및 세굴방지 시공 구조물은: 상기 포대가 설치되는 상기 교각의 하부 둘레에 보호막이 설치된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention according to claim 12, "The bridge bridge foundation reinforcement and scour prevention construction structure of Claim 11: The bridge bridge foundation reinforcement and scour of the bridge bridge characterized by the above-mentioned. Prevent construction structures.

청구항 13에 기재된 발명은, 「제 12 항에 있어서, 상기 보호막은: PE 쿠션 시트 또는 PE 쿠션 패드를 사용하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention according to claim 13 provides "The bridge pier foundation reinforcement and scour prevention construction structure according to claim 12, wherein the protective film is a PE cushion sheet or a PE cushion pad.

청구항 14에 기재된 발명은, 「제 11 항에 있어서, 상기 교각은: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention as set forth in claim 14 provides the bridge bridge foundation reinforcement and scour prevention construction structure according to claim 11, wherein the bridge is constructed in a position in which the foundation ground is dug to a predetermined depth.

청구항 15에 기재된 발명은, 「제 11 항에 있어서, 상기 교각 및 포대는: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention as set forth in claim 15, wherein the bridge and the bag are constructed in a position in which the foundation ground is dug to a predetermined depth. Bridge bridge foundation reinforcement and scour prevention construction structure. do.

청구항 16에 기재된 발명은, 「제 14 항 또는 제 15 항에 있어서, 상기 소정의 깊이는: 2 내지 7m 범위를 갖는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention according to claim 16 provides "The bridge bridge foundation reinforcement and scour prevention construction structure according to claim 14 or 15, wherein the predetermined depth is in the range of 2 to 7 m.

청구항 17에 기재된 발명은, 「제 11 항에 있어서, 상기 포대 및 로프는: 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene)으로 구성된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention as set forth in claim 17, wherein the bag and rope are made of geosynthetic material or polyethylene terephthalate (PET) or polypropylene. Structure. ”

청구항 18에 기재된 발명은, 「제 11 항 또는 제 17 항에 있어서, 상기 포대는: 외측면에 상기 로프를 연결하기 위한 연결고리가 복수개로 설치된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention as set forth in claim 18, wherein the bag is provided with: a plurality of linking rings for connecting the rope to an outer side of the bridge bridge foundation reinforcement and scour prevention construction structure .

청구항 19에 기재된 발명은, 「제 11 항 또는 제 17 항에 있어서, 상기 포대는: 높이가 2.0m 정도이고, 폭(길이)이 20m 내지 50m 정도의 범위를 갖는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.」을 제공한다.The invention as set forth in claim 19, wherein the bag is characterized in that: the height is about 2.0 m and the width (length) is in the range of about 20 m to 50 m. And anti-washing construction structure.

본 발명에 따르면, 현지의 준설사토를 채운 포대를 교각기초 주위에 쌓은 후 로프로 하나로 결속시킴으로써, 시공이 간편하고 공사기간 및 공사비용을 획기적으로 줄일 수 있으며, 녹 발생에 의한 수질 오염을 방지할 수 있고 영구적으로 사용할 수 있는 효과가 있다.According to the present invention, by stacking the turret filled with local dredging sand around the bridge foundation and binding with one rope, it is easy to construct, significantly reduce the construction period and construction cost, and prevent water pollution by rust generation It has the effect that it can and can be used permanently.

또한, 현지 준설토를 활용하여 교각기초를 보강하고 동시에 세굴을 방지시킬 수 있고 하천 바닥에 쌓인 토사를 함께 제거할 수 있는 효과가 있다.In addition, it is possible to reinforce the piers foundation and prevent scour at the same time by using local dredged soil and to remove the soil piled up on the bottom of the river.

또한, 교각기초 주위에 준설사토 포대를 쌓은 후 로프로 하나로 결속시킴으로써 연결성을 강화하고 시공품질 확인이 용이하며, 자중증대(350톤 이상)로 홍수나 집중호우시 유실될 염려가 없고 수중공사가 가능한 효과가 있다.In addition, by building dredging sand bags around the bridge foundations and binding them together with a rope, it is possible to strengthen the connection and check the construction quality, and it is possible to underwater construction without fear of loss due to flooding or heavy rain due to self weight increase (350 tons or more). It works.

또한, 준설사토 포대의 파손시 보수 및 교체가 용이하다.In addition, it is easy to repair and replace the dredged sandbag.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙여 설명하기로 한다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. As those skilled in the art would realize, the described embodiments may be modified in various different ways, all without departing from the spirit or scope of the present invention. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

이하, 본 발명에서 실시하고자 하는 구체적인 기술내용에 대해 첨부도면을 참조하여 상세하게 설명하기로 한다. Hereinafter, specific technical contents to be implemented in the present invention will be described in detail with reference to the accompanying drawings.

교량 교각기초 보강 및 세굴방지 시공 구조물의 실시예Embodiment of Bridge Bridge Foundation Reinforcement and Scour Prevention Construction Structure

도 5 및 도 6은 본 발명의 바람직한 실시예에 의한 교량 교각기초 보강 및 세굴방지 시공 구조물을 나타낸 단면도 및 평면도이다.5 and 6 are a cross-sectional view and a plan view showing a bridge bridge foundation reinforcement and scour prevention construction structure according to a preferred embodiment of the present invention.

본 발명의 교량 교각기초 보강 및 세굴방지 시공 구조물은 도 5 및 도 6에 도시된 바와 같이, 하천이나 강의 기초지반(10) 위에 시공된 교각(100)과, 상기 교각(100)의 하부 둘레에 1단 또는 2단 이상 설치된 복수 개의 포대(200)와, 상기 복수 개의 포대(200)를 단별로 상기 교각과 하나로 결속하는 로프(210)로 구성된다.Bridge bridge foundation reinforcement and scour prevention construction structure of the present invention, as shown in Figure 5 and 6, the pier 100 constructed on the foundation ground 10 of the river or river, and the lower circumference of the pier 100 It is composed of a plurality of bags 200 installed in one or two or more stages, and the rope 210 for binding the plurality of bags 200 to the piers one by one.

상기 교각(100)은 교량을 받치고 있는 기둥으로서, 하부 교각(도 12의 110 참조), 교각 기둥(도 12의 120 참조), 상부 교각(도 12의 130)으로 구성되어 있다. The pier 100 is a pillar supporting the bridge, and is composed of a lower pier (see 110 in FIG. 12), a pier pillar (see 120 in FIG. 12), and an upper pier (130 in FIG. 12).

종래의 일반적인 교량 시공 방법은 지반에 매입된 말뚝에 기초 콘크리트부를 가설하여 이루어지는 교량 기초 위에 교각을 가설하는 방식으로서 시공되지만, 본 발명에서는 지반에 매입되는 말뚝 없이 상기 기초지반(10)을 소정의 깊이(L)로 파낸 자리에 콘크리트로 시공된다. 이때, 상기 교각(100)을 설치하기 위해 상기 기초지반(10)을 파내는 깊이(L)는 상기 기초지반(10)이 사토로 형성되어 있는 경우 보통 2 내지 7m 범위를 갖는 것이 바람직하다. 하지만, 반드시 이 수치에 한정된 것은 아니며, 교각의 설치 장소와 기초지반의 종류 즉, 기초지반 아래에 암반층이 형성되어 있거나 기초지반이 암반층으로 형성된 경우에는 각각 다를 수 있다.Conventional general bridge construction method is constructed as a method of laying the bridge on the bridge foundation formed by laying the foundation concrete part in the pile embedded in the ground, in the present invention, the foundation ground 10 without a pile embedded in the ground to a predetermined depth It is constructed of concrete at the site of digging with (L). At this time, the depth (L) to dig the foundation ground 10 to install the pier 100 is preferably in the range of 2 to 7m when the foundation ground 10 is formed of sand. However, it is not necessarily limited to this value, and may be different in the case where the pier is installed and the type of the foundation ground, that is, when the rock layer is formed under the foundation ground or the foundation ground is formed as the rock layer.

상기 교각(100)이 시공된 후, 상기 포대(200)가 설치되는 상기 교각(200)의 하부 둘레에는 보호막(도 13의 140 참조)이 설치되어 있다. 상기 보호막(140)은 상기 포대(200)의 무게로부터 전달되는 충격을 완화시키기 위해 설치되는 것으로, PE 쿠션 시트 또는 PE 쿠션 패드 등을 포함한 충격 완충재를 사용한다. 여기서, 사용된 PE 쿠션 시트 또는 PE 쿠션 패드는 고밀도로 발포시킨 무가교 폴리에틸렌 발포체로서 완충, 보온, 단열, 방습, 방음효과가 뛰어나며 산업전반에 걸쳐 용도에 따라 광범위 하게 쓰여지고 있다.After the pier 100 is constructed, a protective film (see 140 in FIG. 13) is installed around the lower circumference of the pier 200 where the bag 200 is installed. The protective layer 140 is installed to mitigate the impact transmitted from the weight of the bag 200, and uses a shock absorbing material including a PE cushion sheet or a PE cushion pad. Here, the used PE cushion sheet or PE cushion pad is a high density foamed non-crosslinked polyethylene foam, which has excellent buffering, insulating, heat insulation, moisture proofing, and soundproofing effects, and is widely used depending on the application throughout the industry.

상기 교각(200)의 하부 둘레에 설치된 상기 포대(200) 및 이를 둘러싼 로프(210)는 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene) 재질로 구성되어 있으며, 상기 포대(200)의 내부에 준설사토를 가득 채우고 있다. 이때, 준설사토는 교량을 시공하는 주변에서 채취한 준설사토를 사용하는 것이 바람직하며, 상기 포대(200)의 크기에 따라 적절한 무게(예를 들면, 40m 포대의 경우 350ton/EA)로 채워야 한다. The bag 200 installed around the lower portion of the pier 200 and the ropes 210 surrounding the bag 200 are made of geotextile material, polyethylene terephthalate (PET), or polypropylene material, and the bag 200 It is filled with dredging sand inside. At this time, it is preferable to use dredging sand collected from the surroundings of the bridge construction, and should be filled with an appropriate weight (for example, 350ton / EA in the case of a 40m bag) according to the size of the bag 200.

상기 교량 공사 주변에서 채취된 준설사토를 상기 포대(200) 속에 채우는 이유는 작업이 용이할 뿐만 아니라 건설 비용과 공사 기간을 획기적으로 줄일 수 있기 때문이다. 아울러, 상기 교량 공사 주변의 하천이나 강에서 준설사토를 채취하게 되면 하천이나 강 바닥에 적재된 사토를 제거할 수 있어 집중호우시 하천이나 강 수위를 낮출 수 있어 홍수를 예방할 수 있는 효과도 있다.The reason for filling the bag 200 in the dredged soil collected around the bridge construction is not only easy to work, but also significantly reduce the construction cost and construction period. In addition, if the dredging sand is collected from the river or river around the bridge construction can remove the soil on the bottom of the river or river can reduce the river or river level during heavy rains can prevent the flood.

상기 포대(200)는 외측면에 상기 로프를 연결하기 위한 연결고리(도 8의 201,202 참조)가 복수개로 설치되어 있으며, 자세한 구성에 대해서는 후술하는 도 8에서 상세히 설명하기로 한다.The bag 200 is provided with a plurality of connecting rings (see 201, 202 of FIG. 8) for connecting the rope on the outer side, and the detailed configuration will be described in detail later in FIG.

다시 도 5를 참조하여 설명하면, 상기 교각(200)이 시공된 이후에, 상기 교각(200)의 하부 둘레에 상기 보호막(140)을 설치한 다음, 상기 보호막(140)으로 둘 러쌓인 상기 교각(200)의 하부 둘레에 준설사토로 채워 진 준설사토 포대(200)를 설치한다. 이때, 설치 방법은 상기 준설사토 포대(200)를 서로 맞물려서 시공하여야 하며, 세굴방지공의 경우 국부 세굴 요인을 최소화하여 굴요성이 작용될 수 있는 구조로 설치하여야 한다. Referring back to FIG. 5, after the piers 200 are constructed, the protective film 140 is installed around the lower portion of the piers 200, and then the piers are enclosed with the protective film 140. Install the dredged sanding bag 200 filled with dredged sand around the bottom of the (200). At this time, the installation method should be constructed by interlocking the dredged sand bags 200, and in the case of scour prevention ball should be installed in a structure that can be applied to minimize local scour factor.

또한, 상기 교각(200)의 하부 둘레에 상기 준설사토 포대(200)를 시공할 때 평균 하상고까지 되메우기를 하고, 터파기 면적 외곽은 주변 평균 하상고에 맞추어 정지한 후 설치하여야 한다.In addition, when constructing the dredged sanding bag 200 around the lower periphery of the pier 200, backfilled to the average bottom elevation, and the perforated area outside the trench area should be installed after stopping in accordance with the surrounding average bottom elevation.

상기 준설사토 포대(200)는 보통 저단(1단)에서 서로 붙여 매트화 하며, 포대(200)와 포대(200) 사이의 간격이 1mm의 오차도 없도록 서로 맞물려서 시공한다. 그리고 상기 준설사토 포대(200)가 설치되는 상기 기초지반(10)은 상기 준설사토 포대(200)의 시공 후 토사 유출이 없도록 평활하게 포설하여야 한다.The dredging satin turret 200 is usually mated at the bottom end (stage 1) and mated, and is constructed by interlocking each other so that the gap between the turret 200 and the turret 200 does not have an error of 1 mm. In addition, the foundation ground 10 on which the dredging sand bag 200 is installed should be smoothly installed so that there is no leakage of soil after construction of the dredging sand bag 200.

상기 준설사토 포대(200)를 2단 이상으로 시공할 경우 2단이 높여지기 전에 제1 단을 어느 범위까지 설치해야 할 것인지를 현장의 조건, 공사의 진행 및 예상되는 기상조건, 수면조건에 따라서 결정하여 시공한다. 이때, 상기 준설사토 포대(200)를 2단 이상 거치할 경우에는 1단만을 계속 진행하여서는 안되며, 단과 단 사이가 잘 짜여지도록 거치하여야 한다. 그리고 수류에 의한 접지면 하단의 토사 유출을 방지하기 위하여 선별적으로 포설하되 하상재료 입도에 따라 선별 사용 여부를 판단한다.When the dredging sand bag 200 is constructed in two or more stages, depending on the conditions of the site, the progress of the construction and the expected weather conditions, and the sleep conditions, to what extent the first stage should be installed before the second stage is increased. Determine and construct. In this case, when the dredge sato bag 200 is mounted more than two stages, only one stage should not be continued, and it should be mounted so that the stage is well woven. And in order to prevent the outflow of sediment at the bottom of the ground plane by the water flow, it is selectively installed, it is determined whether to use the sorting according to the particle size of the bed.

상기 준설사토 포대(200)를 거치한 후 시공자 또는 작업자는 상기 준설사토 포대(200)가 정위치에 설치되었는지, 외관에 대해 국부적인 공백은 없는지, 배치 및 맞물린 상태와 근접시공 등이 양호한지를 확인한다. 이때, 이상이 없으면 상기 상기 준설사토 포대(200)의 연결고리(201,202)에 상기 로프(210)를 끼워서 상기 교각(100)과 하나로 결속한다. 만약, 상기 준설사토 포대(200)가 잘못 시공이 된 경우에는 감리자 또는 발주자의 지시에 따라 재설치 하여야 한다.After mounting the dredging sand bag 200, the contractor or worker checks whether the dredging sand bag 200 is installed in the correct position, there is no local space for the appearance, the arrangement and interlocking state and the proximity construction is good do. In this case, if there is no abnormality, the rope 210 is inserted into the connecting rings 201 and 202 of the dredged sand bag 200 and the pier 100 is coupled to one. If the dredge sato bag 200 is incorrectly installed, it must be reinstalled according to the supervisor or orderer's instructions.

이와 같이, 상기 교각(100)의 하부 둘레에 설치된 상기 준설사토 포대(200)는 2m(높이)×40m(폭)인 경우 개당 350톤(ton)/EA 가량의 무게를 가지고 있고 로프(210)에 의해 상기 교각(100)과 하나로 결속되어 있기 때문에 상기 교각(100)을 충분히 지지 및 보강 할 수가 있고 교각기초의 세굴을 방지할 수 있다. As such, the dredged sand bag 200 installed around the lower portion of the pier 100 has a weight of about 350 tons / EA per rope when it is 2 m (height) x 40 m (width) and the rope 210 Since the pier 100 and the one is bound by one, it is possible to fully support and reinforce the pier 100 and to prevent the scour of the bridge foundation.

그리고, 상기 교각(200)의 하부 둘레에 설치된 상기 포대(200) 및 이를 둘러싼 로프(210)가 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene) 재질로 구성되어 있기 때문에 영구적으로 사용할 수 있다,In addition, the bag 200 installed around the lower portion of the pier 200 and the rope 210 surrounding it are made of geosynthetic material, polyethylene terephthalate (PET), or polypropylene material. You can,

또한, 상기 교량 공사 주변의 준설사토를 이용하여 상기 교각(100)을 보강 및 세굴방지 하도록 시공하기 때문에 시공이 간편하고 공사기간 및 공사비용을 획기적으로 줄일 수 있으며, 녹 발생에 의한 수질 오염을 방지할 수 있다.In addition, since the construction to reinforce and prevent scouring the pier 100 by using the dredging sand around the bridge construction, the construction is simple and can significantly reduce the construction period and construction costs, and prevent water pollution due to rust generation can do.

게다가, 교각기초 주위에 준설사토 포대를 쌓은 후 로프로 하나로 결속시킴으로써 연결성을 강화하고 시공품질 확인이 용이하며, 자중증대(350톤 이상)로 홍수나 집중호우시 유실될 염려가 없고 수중공사가 가능하다.In addition, by building dredging sand bags around the bridge foundations and binding them together with a rope, it is possible to strengthen the connection and check the construction quality. Do.

덧붙여, 상기 준설사토 포대(200)가 남파선 등에 의해 파손되었다고 하여도 파손된 부분을 보수하거나 파손된 포대를 교체해 주면 되기 때문에 보수 및 교체가 용이하다.In addition, even if the dredged sand bag 200 is damaged by a south wave line or the like, it is easy to repair and replace the damaged part or replace the broken bag.

교량 교각기초 보강 및 세굴방지 시공 구조물의 다른 실시예Another embodiment of bridge bridge foundation reinforcement and scour prevention construction structure

도 7은 본 발명의 바람직한 다른 실시예에 의한 교량 교각기초 보강 및 세굴방지 시공 구조물을 나타낸 단면도이다.7 is a cross-sectional view showing the bridge bridge foundation reinforcement and scour prevention construction structure according to another embodiment of the present invention.

도 7에 도시된 교량 교각기초 보강 및 세굴방지 시공 구조물은 상기 교각(100)과 상기 준설사토 포대(200)를 상기 기초지반(10)을 소정의 깊이(L)로 파낸 자리에 함께 시공한 예를 나타낸 것이다. 이때, 상기 교각(100)을 설치하기 위해 상기 기초지반(10)을 파내는 깊이(L)는 도 5에서와 마찬가지로, 상기 기초지반(10)이 사토로 형성되어 있는 경우 보통 2 내지 7m 범위를 갖는 것이 바람직하다. 하지만, 반드시 이 수치에 한정된 것은 아니며, 교각의 설치 장소와 기초지반의 종류 즉, 기초지반 아래에 암반층이 형성되어 있거나 기초지반이 암반층으로 형성된 경우에는 각각 다를 수 있다.Bridge pier foundation reinforcement and scour prevention construction structure shown in Figure 7 is an example in which the bridge 100 and the dredged sand bag 200 is installed together in a position to dig the foundation ground 10 to a predetermined depth (L) It is shown. At this time, the depth (L) of digging the foundation ground 10 to install the pier 100, as in Figure 5, when the foundation ground 10 is formed of Sato usually has a range of 2 to 7m It is preferable. However, it is not necessarily limited to this value, and may be different in the case where the pier is installed and the type of the foundation ground, that is, when the rock layer is formed under the foundation ground or the foundation ground is formed as the rock layer.

준설사토 포대(200)의 실시예Embodiment of the dredging sand bag 200

도 8은 본 발명에서 사용된 준설사토 포대(200)를 나타낸 도면이다.8 is a view showing a dredging sand bag 200 used in the present invention.

상기 포대(200)는 앞에서 설명한 바와 같이, 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene) 재질로 구성되며, 외측면에 상기 로프(210)를 연결하기 위한 연결고리(201,202)가 2줄로 복수개가 설치되어 있고, 내부 공간에 준설사토를 적재하게 된다. 이때, 준설사토는 교량을 시공하는 주변에서 채취한 준설사토를 사용하는 것이 바람직하다.As described above, the bag 200 is composed of a geotextile material or polyethylene terephthalate (PET) or polypropylene (polypropylene) material, the connecting ring (201, 202) for connecting the rope 210 to the outer surface Two rows are installed, and dredged sand is loaded in the interior space. At this time, it is preferable to use dredging sand collected at the periphery of bridge construction.

상기 포대(200)의 크기는 2.0m(높이)×20m(폭=길이), 2.0m×30m, 2.0m×40m, 2.0m×50m 등이 있으며, 시공 장소에 따라 크기를 조절할 수 있다. 상기 포대(200)의 인장강도는 250KN/M 정도이며, 준설사토를 적재했을 때 중량은 2.0m×40m의 경우 350톤(ton)/EA 정도이다.The bag 200 has a size of 2.0m (height) × 20m (width = length), 2.0m × 30m, 2.0m × 40m, 2.0m × 50m, and the like. Tensile strength of the bag 200 is about 250KN / M, the weight is about 350 tons / EA in the case of loading 2.0m × 40m when dredged sand.

도 9는 교량 교각(100) 주위에 쌓은 준설사토 포대(200)를 로프(201)를 이용하여 하나로 결속시킨 모습을 나타낸 일부 확대도이다.FIG. 9 is a partially enlarged view illustrating a mode in which the dredged sandbags 200 stacked around the bridge piers 100 are bound together using a rope 201.

상기 준설사토 포대(200)는 사이사이에 공간이 생기지 않도록 서로 맞물려서 시공해야 하며, 배치 및 맞물린 상태와 근접시공 등이 양호하면 상기 연결고리(201,202)에 로프(210)를 단별(1단, 2단)로 끼워서 상기 교각(100)과 하나로 결속한다. 상기 준설사토 포대(200)와 상기 교각(100)이 하나로 결속된 구조물에 의해 상기 교각(100)을 지지 및 보강 할 수가 있고 교각기초의 세굴을 방지할 수 있다. The dredged sandbags 200 should be constructed by interlocking each other so as not to create a space therebetween, and if the arrangement and interlocking state and close construction are good, the rope 210 is separated into the connecting rings 201 and 202 by one step (one step, two steps). End) and bind to one of the piers 100. By the structure in which the dredged sandbag 200 and the pier 100 are bound to one, the pier 100 may be supported and reinforced, and the scour of the pier foundation may be prevented.

교량 교각기초 보강 및 세굴방지 시공 방법의 실시예Embodiment of bridge bridge foundation reinforcement and scour prevention construction method

도 10 내지 도 15는 본 발명의 바람직한 실시예에 의한 교량 교각기초 보강 및 세굴방지 시공 방법을 공정 순서대로 나타낸 공정 단면도이다.10 to 15 are cross-sectional views showing the bridge bridge foundation reinforcement and scour prevention construction method according to a preferred embodiment of the present invention in the order of process.

먼저, 도 10을 참조하여 설명하면, 하천이나 강(20)의 기초지반(10)에 교각을 시공하기 위한 구멍(터파기)을 소정의 깊이(L)로 형성한다. 이때, 깊이(L)는 상기 기초지반(10)이 사토로 형성되어 있는 경우 보통 2 내지 7m 범위를 갖는 것이 바람직하다.First, referring to FIG. 10, a hole (peg) for constructing a pier in the foundation ground 10 of a river or river 20 is formed to a predetermined depth L. At this time, the depth (L) is preferably having a range of 2 to 7m when the foundation ground 10 is formed of sand.

상기 기초지반(10)을 소정의 깊이(L)로 파낸 자리에 공지의 방법으로 콘크리트를 시공하여 하부 교각(110)을 형성한 다음(도 11 참조), 교각 기둥(120)과 상부 교각(130)을 순차적으로 형성한다(도 12 참조).After the foundation is dug to the predetermined depth (L) to the concrete by a known method to form a lower pier (110) (see Fig. 11), the pier pillar 120 and the upper pier 130 ) Are formed sequentially (see FIG. 12).

상기 교각(100)이 완성된 후, 상기 준설사토 포대(200)가 설치되는 상기 교각(100)의 하부 둘레에 보호막(140)을 설치한다(도 13 참조). 이때, 상기 보호막(140)은 완충재 및 방수 기능을 갖는 소재 즉, PE 쿠션 시트 또는 PE 쿠션 패드 등을 사용하는 것이 바람직하다.After the pier 100 is completed, a protective film 140 is installed around the lower circumference of the pier 100 where the dredged sand bag 200 is installed (see FIG. 13). At this time, the protective layer 140 is preferably a material having a cushioning material and a waterproof function, that is, PE cushion sheet or PE cushion pad.

그 후, 상기 보호막(140)이 설치된 상기 교각(100)의 하부 둘레에 준설사토가 적재된 포대(200)를 서로 맞물리게 1단 또는 2단 이상 쌓아서 거치한다(도 14 참조). 여기서, 상기 포대(200)에 적재된 준설사토는 교량 공사 주변에서 채취한 준설사토를 사용하여 적재한다. Subsequently, the bag 200 loaded with dredged sand is mounted on one or two or more stages so as to interlock with each other. Here, the dredged sand soil loaded on the bag 200 is loaded using the dredged sand soil collected around the bridge construction.

상기 준설사토 포대(200)를 거치한 후 시공자 또는 작업자는 상기 준설사토 포대(200)가 정위치에 설치되었는지, 외관에 대해 국부적인 공백은 없는지, 배치 및 맞물린 상태와 근접시공 등이 양호한지를 확인한 다음, 이상이 없으면 상기 상기 준설사토 포대(200)의 연결고리(201,202)에 상기 로프(210)를 끼워서 상기 교각(100)과 하나로 결속한다(도 15 참조). 만약, 상기 준설사토 포대(200)가 잘못 시공이 된 경우에는 감리자 또는 발주자의 지시에 따라 재설치 한다.After mounting the dredging sand bag 200, the contractor or worker has checked whether the dredging sand bag 200 is installed in place, there is no local space for the appearance, the arrangement and interlocking state and close construction is good. Next, if there is no abnormality, the rope 210 is inserted into the linking rings 201 and 202 of the dredging sand bag 200, and the pier 100 is coupled to one (see FIG. 15). If the dredge sato bag 200 is incorrectly installed, it is reinstalled according to the supervisor or orderer's instructions.

이와 같이, 본 발명의 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물은 현지 준설사토를 채운 포대를 교각기초 주위에 쌓은 후 로프로 하나로 결속시킴으로써, 본 발명의 기술적 과제를 해결할 수가 있다.As described above, the bridge bridge foundation reinforcement and scour prevention construction method and the structure of the present invention can solve the technical problem of the present invention by stacking a bag filled with local dredging soil around the bridge foundation, and then binding it with a rope.

이상에서 설명한 본 발명의 바람직한 실시 예들은 기술적 과제를 해결하기 위해 개시된 것으로, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자(당업자)라면 본 발명의 사상과 범위 안에서 다양한 수정, 변경, 부가 등이 가능할 것이며, 이러한 수정 변경 등은 이하의 특허청구범위에 속하는 것으로 보아야 할 것이다.It will be apparent to those skilled in the art that various modifications and changes can be made in the present invention without departing from the spirit or scope of the present invention as defined by the appended claims. It will be appreciated that such modifications and variations are intended to fall within the scope of the following claims.

본 발명의 교량 교각기초 보강 및 세굴방지 시공 방법 및 그 구조물은 하천이나 강에서 시공되는 경우를 예로 들어 설명하고 있으나, 이에 한정되지 않고 육지 등에서도 동일하게 적용하여 실시할 수 있다.Bridge bridge foundation reinforcement and scour prevention construction method and the structure of the present invention has been described taking the case of construction in rivers or rivers as an example, but is not limited to this can be applied to the same land.

도 1 내지 도 4는 종래의 교량 교각기초 세굴방지 공법을 나타낸 도면으로서,1 to 4 is a view showing a conventional bridge bridge foundation scour prevention method,

도 1은 사석을 이용한 세굴방지 공법을 나타낸 단면도이고,1 is a cross-sectional view showing a scour prevention method using sandstone,

도 2는 돌망태공을 이용한 세굴방지 공법을 나타낸 단면도이고,2 is a cross-sectional view showing a scour prevention method using a gabion hole,

도 3은 시트파일(sheet pile)을 이용한 세굴방지 공법을 나타낸 단면도이고,3 is a cross-sectional view showing a scour prevention method using a sheet pile (sheet pile),

도 4는 콘크리트 블록 매트를 이용한 세굴방지 공법을 나타낸 단면도이다.Figure 4 is a cross-sectional view showing a scour prevention method using a concrete block mat.

도 5 및 도 6은 본 발명의 바람직한 실시예에 의한 교량 교각기초 보강 및 세굴방지 시공 구조물을 나타낸 단면도 및 평면도5 and 6 are a cross-sectional view and a plan view showing the bridge bridge foundation reinforcement and scour prevention construction structure according to a preferred embodiment of the present invention

도 7은 본 발명의 바람직한 다른 실시예에 의한 교량 교각기초 보강 및 세굴방지 시공 구조물을 나타낸 단면도7 is a cross-sectional view showing the bridge bridge foundation reinforcement and scour prevention construction structure according to another embodiment of the present invention

도 8은 본 발명에서 사용된 준설사토 포대(200)를 나타낸 도면8 is a view showing a dredge sand bag 200 used in the present invention.

도 9는 교량 교각(100) 주위에 쌓은 준설사토 포대(200)를 로프(201)를 이용하여 하나로 결속시킨 모습을 나타낸 일부 확대도 9 is a partially enlarged view showing a state in which the dredged sandbags 200 stacked around the bridge piers 100 are bound together using a rope 201.

도 10 내지 도 15는 본 발명의 바람직한 실시예에 의한 교량 교각기초 보강 및 세굴방지 시공 방법을 공정 순서대로 나타낸 공정 단면도10 to 15 is a cross-sectional view showing the bridge bridge foundation reinforcement and scour prevention construction method according to a preferred embodiment of the present invention in the order of process

[ 도면의 주요 부분에 대한 부호의 설명 ][Description of Code for Major Parts of Drawing]

10 : 지반(기초지반) 20 : 하천이나 강 10: ground (foundation ground) 20: river or river

100 : 교각 200 : 준설사토 포대100: pier 200: dredge sato turret

201, 202 : 연결고리 210 : 로프201, 202: Hook 210: Rope

110 : 하부 교각 120 : 교각 기둥110: lower piers 120: piers

130 : 상부 교각 140 : 보호막130: upper pier 140: protective film

Claims (19)

교량 교각기초 보강 및 세굴방지 시공 방법에 있어서,In bridge bridge foundation reinforcement and scour prevention construction method, (a) 기초지반 위에 교각을 시공하는 단계와;(a) constructing a pier on the foundation ground; (b) 교량 공사 주변의 준설 사토를 포대에 채우는 단계와;(b) filling the turret with dredge sato around the bridge construction; (c) 상기 교각의 하부 둘레에 상기 포대를 복수 개로 설치하는 단계; 및(c) installing a plurality of the bags around the lower portion of the piers; And (d) 상기 포대를 로프로 연결하여 상기 교각과 하나로 결속하는 단계; (d) connecting the bag with a rope to bind the pier to one; 를 포함하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge piers foundation reinforcement and scour prevention construction method comprising a. 제 1 항에 있어서, 상기 교량 교각기초 보강 및 세굴방지 시공 방법은:The method of claim 1, wherein the bridge bridge foundation reinforcement and scour prevention construction method is: 상기 포대가 설치되는 상기 교각의 하부 둘레에 보호막을 설치하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge bridge foundation reinforcement and scour prevention construction method characterized in that the protective film is installed around the lower portion of the bridge where the bag is installed. 제 2 항에 있어서, 상기 보호막은:The method of claim 2, wherein the protective film is: PE 쿠션 시트 또는 PE 쿠션 패드를 사용하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge bridge foundation reinforcement and scour prevention construction method characterized by using a PE cushion sheet or PE cushion pad. 제 1 항에 있어서, 상기 교각은:The pier of claim 1, wherein the piers are: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge piling foundation reinforcement and scrubbing construction method, characterized in that the construction of the foundation ground to a predetermined depth. 제 1 항에 있어서, 상기 교각 및 포대는:The method of claim 1, wherein the piers and bags are: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge piling foundation reinforcement and scrubbing construction method, characterized in that the construction of the foundation ground to a predetermined depth. 제 4 항 또는 제 5 항에 있어서, 상기 소정의 깊이는:6. The method of claim 4 or 5, wherein the predetermined depth is: 2 내지 7m 범위를 갖는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge piers foundation reinforcement and scrubbing construction method characterized in that it has a range of 2 to 7m. 제 1 항에 있어서, 상기 포대 및 로프는:The method of claim 1, wherein the bag and rope are: 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene) 재질로 구성된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge bridge foundation reinforcement and scour prevention construction method characterized in that consisting of geotextile material or polyethylene terephthalate (PET) or polypropylene (polypropylene) material. 제 1 항 또는 제 7 항에 있어서, 상기 포대는:8. The bag of claim 1 or 7, wherein the bag is: 외측면에 상기 로프를 연결하기 위한 연결고리가 복수개로 설치된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge bridge foundation reinforcement and scour prevention construction method characterized in that a plurality of connecting rings are installed on the outer surface for connecting the rope. 제 1 항에 있어서, 상기 교량 교각기초 보강 및 세굴방지 시공 방법은:The method of claim 1, wherein the bridge bridge foundation reinforcement and scour prevention construction method is: 상기 교각의 하부 둘레에 상기 포대를 1단 또는 2단 이상으로 설치하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge piers foundation reinforcement and scour prevention construction method characterized in that the bag is installed in one or two or more stages around the lower circumference of the bridge. 제 1 항에 있어서, 상기 기초지반은:The method of claim 1, wherein the foundation ground is: 하천, 강, 육지 중 어느 한 곳인 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 방법.Bridge bridge foundation reinforcement and scour prevention construction method characterized in that any one of the river, river, land. 교량 교각기초 보강 및 세굴방지 시공 구조물에 있어서,In bridge bridge foundation reinforcement and scour prevention construction structure, 기초지반 위에 시공된 교각과;Piers constructed on foundation ground; 상기 교각의 하부 둘레에 1단 또는 2단 이상 설치되며 내부에 준설 사토로 채워진 복수 개의 포대; 및A plurality of bags installed in one or two or more stages around the lower portion of the pier and filled with dredged soil; And 상기 복수 개의 포대를 단별로 상기 교각과 하나로 결속하는 로프;A rope that binds the plurality of bags to each of the piers one by one; 를 포함하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge piers foundation reinforcement and scour prevention construction structure comprising a. 제 11 항에 있어서, 상기 교량 교각기초 보강 및 세굴방지 시공 구조물은:12. The method of claim 11, wherein the bridge bridge foundation reinforcement and scour prevention construction structure is: 상기 포대가 설치되는 상기 교각의 하부 둘레에 보호막이 설치된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge piers foundation reinforcement and scour prevention construction structure, characterized in that the protective film is installed around the lower portion of the bridge where the bag is installed. 제 12 항에 있어서, 상기 보호막은:The method of claim 12, wherein the protective film is: PE 쿠션 시트 또는 PE 쿠션 패드를 사용하는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge pier foundation reinforcement and scour prevention construction structure using PE cushion seat or PE cushion pad. 제 11 항에 있어서, 상기 교각은:The method of claim 11, wherein the piers are: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge piers foundation reinforcement and scour prevention construction structure, characterized in that the foundation was constructed in the excavated to a predetermined depth. 제 11 항에 있어서, 상기 교각 및 포대는:The method of claim 11, wherein the piers and bags are: 상기 기초지반을 소정의 깊이로 파낸 자리에 시공된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge piers foundation reinforcement and scour prevention construction structure, characterized in that the foundation was constructed in the excavated to a predetermined depth. 제 14 항 또는 제 15 항에 있어서, 상기 소정의 깊이는:The method of claim 14 or 15, wherein the predetermined depth is: 2 내지 7m 범위를 갖는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge piers foundation reinforcement and scour prevention construction structure having a range of 2 to 7m. 제 11 항에 있어서, 상기 포대 및 로프는:12. The bag of claim 11, wherein the bag and rope are: 토목섬유 재질 또는 폴리에틸렌텔레프탈레이트(PET) 또는 폴리프로필렌(polypropylene) 재질로 구성된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge bridge foundation reinforcement and scour prevention construction structure consisting of geosynthetic material or polyethylene terephthalate (PET) or polypropylene (polypropylene) material. 제 11 항 또는 제 17 항에 있어서, 상기 포대는:18. The bag of claim 11 or 17, wherein the bag is: 외측면에 상기 로프를 연결하기 위한 연결고리가 복수개로 설치된 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge pier foundation reinforcement and scour prevention construction structure, characterized in that a plurality of connecting rings are installed on the outer surface for connecting the rope. 제 11 항 또는 제 17 항에 있어서, 상기 포대는:18. The bag of claim 11 or 17, wherein the bag is: 높이가 2.0m 정도이고, 폭(길이)이 20m 내지 50m 정도의 범위를 갖는 것을 특징으로 하는 교량 교각기초 보강 및 세굴방지 시공 구조물.Bridge bridge foundation reinforcement and scour prevention construction structure characterized in that the height is about 2.0m, the width (length) has a range of about 20m to 50m.
KR1020090116266A 2009-10-26 2009-11-28 Bridge bridge foundation reinforcement and scour prevention construction method and structure Ceased KR20110046209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090116266A KR20110046209A (en) 2009-10-26 2009-11-28 Bridge bridge foundation reinforcement and scour prevention construction method and structure

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020090101585 2009-10-26
KR1020090116266A KR20110046209A (en) 2009-10-26 2009-11-28 Bridge bridge foundation reinforcement and scour prevention construction method and structure

Publications (1)

Publication Number Publication Date
KR20110046209A true KR20110046209A (en) 2011-05-04

Family

ID=44241127

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090116266A Ceased KR20110046209A (en) 2009-10-26 2009-11-28 Bridge bridge foundation reinforcement and scour prevention construction method and structure

Country Status (1)

Country Link
KR (1) KR20110046209A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160057198A (en) 2014-11-13 2016-05-23 목포해양대학교 산학협력단 Apparatus and Method of Scouring of Foundation
KR101662063B1 (en) 2016-05-18 2016-10-04 이신원 Bridges and bridge scour scour prevention methods to prevent the ball
CN110847123A (en) * 2019-12-20 2020-02-28 福建永福电力设计股份有限公司 Sleeve cage type anti-scouring structure and construction method
CN112031043A (en) * 2020-09-16 2020-12-04 浙江世润建创科技发展有限公司 Anti-scouring protection structure for increasing cross section of bridge pier column by wrapping bulk material and construction method
CN113266034A (en) * 2021-06-25 2021-08-17 盛东如东海上风力发电有限责任公司 Scouring protection reinforcing structure and method for offshore wind power single-pile foundation
KR20220053750A (en) 2020-10-22 2022-05-02 한국철도기술연구원 Foundation structures using strut-tie reinforcement and its construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160057198A (en) 2014-11-13 2016-05-23 목포해양대학교 산학협력단 Apparatus and Method of Scouring of Foundation
KR101662063B1 (en) 2016-05-18 2016-10-04 이신원 Bridges and bridge scour scour prevention methods to prevent the ball
CN110847123A (en) * 2019-12-20 2020-02-28 福建永福电力设计股份有限公司 Sleeve cage type anti-scouring structure and construction method
CN112031043A (en) * 2020-09-16 2020-12-04 浙江世润建创科技发展有限公司 Anti-scouring protection structure for increasing cross section of bridge pier column by wrapping bulk material and construction method
CN112031043B (en) * 2020-09-16 2022-01-28 浙江世润建创科技发展有限公司 Anti-scouring protection structure for increasing cross section of bridge pier column by wrapping bulk material and construction method
KR20220053750A (en) 2020-10-22 2022-05-02 한국철도기술연구원 Foundation structures using strut-tie reinforcement and its construction method
CN113266034A (en) * 2021-06-25 2021-08-17 盛东如东海上风力发电有限责任公司 Scouring protection reinforcing structure and method for offshore wind power single-pile foundation

Similar Documents

Publication Publication Date Title
US7708495B1 (en) Levee system
JP5052872B2 (en) Retaining wall construction method
KR20110046209A (en) Bridge bridge foundation reinforcement and scour prevention construction method and structure
KR20160027646A (en) Bank and method for the same using the geotextiles tube law for preventing coastal erosion
KR101253410B1 (en) Connection structure of wall steel pipe pile
CN111945657B (en) A dock upgrading and reconstruction structure and a dock upgrading and reconstruction construction method
CN103233444A (en) Underwater riprap foundation bed and side slope erosion resisting structure and construction method thereof
JP5846150B2 (en) Construction method of river revetment structure
JP5407995B2 (en) Filling reinforcement structure
JP6676462B2 (en) Embankment reinforcement method
CN220486172U (en) Reinforcing structure suitable for mountain area highway bank section disaster damage roadbed
CN103343541B (en) Pile-plate combined type foundation pit excavation protective structure and construction method thereof
CN217378975U (en) Compound foundation structure of tide gate is kept off to soft foundation of facing sea
CN213625433U (en) A link up transition structure that is used for gravity type and sheet pile formula combination pier
KR102152085B1 (en) Open Cell Caisson Structure and a Construction Method thereof
KR200387407Y1 (en) Marine civil granular structure reinforced with floating geo-mat contained granulars on bottom and slopes of structure and floating geo-mat
KR102138839B1 (en) Cast-in-place concrete blocks using large scales and revetment methods using them
KR101020217B1 (en) Rock construction using anchor and construction method
KR100704460B1 (en) Harbor Restoration and Auxiliary Construction Equipment
CN107059888B (en) Reinforcing bar gabion side slope supporting construction
KR20150105891A (en) The underground facilities for offshore airfield of semi land reclamation type
KR102706845B1 (en) Reclamation outflow prevention structure and the construction method thereof
JP4504864B2 (en) Dam body reinforcement structure with wave-dissipating function
Hawkswood et al. Foundations to precast marine structures
CN222666700U (en) Side slope structure for river course scour prevention

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20091128

PA0201 Request for examination
PG1501 Laying open of application
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20111104

Patent event code: PE09021S01D

E601 Decision to refuse application
PE0601 Decision on rejection of patent

Patent event date: 20120629

Comment text: Decision to Refuse Application

Patent event code: PE06012S01D

Patent event date: 20111104

Comment text: Notification of reason for refusal

Patent event code: PE06011S01I