[go: up one dir, main page]

KR20100074829A - Breaker for high tension power board - Google Patents

Breaker for high tension power board Download PDF

Info

Publication number
KR20100074829A
KR20100074829A KR1020080133360A KR20080133360A KR20100074829A KR 20100074829 A KR20100074829 A KR 20100074829A KR 1020080133360 A KR1020080133360 A KR 1020080133360A KR 20080133360 A KR20080133360 A KR 20080133360A KR 20100074829 A KR20100074829 A KR 20100074829A
Authority
KR
South Korea
Prior art keywords
relay
breaker
response
por
uvr
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
KR1020080133360A
Other languages
Korean (ko)
Inventor
모종명
Original Assignee
한국전력공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전력공사 filed Critical 한국전력공사
Priority to KR1020080133360A priority Critical patent/KR20100074829A/en
Publication of KR20100074829A publication Critical patent/KR20100074829A/en
Ceased legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01HELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES
    • H01H33/00High-tension or heavy-current switches with arc-extinguishing or arc-preventing means
    • H01H33/02Details
    • H01H33/26Means for detecting the presence of an arc or other discharge
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01HELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES
    • H01H71/00Details of the protective switches or relays covered by groups H01H73/00 - H01H83/00
    • H01H71/10Operating or release mechanisms
    • H01H71/12Automatic release mechanisms with or without manual release
    • H01H71/123Automatic release mechanisms with or without manual release using a solid-state trip unit
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B13/00Arrangement of switchgear in which switches are enclosed in, or structurally associated with, a casing, e.g. cubicle
    • H02B13/02Arrangement of switchgear in which switches are enclosed in, or structurally associated with, a casing, e.g. cubicle with metal casing
    • H02B13/025Safety arrangements, e.g. in case of excessive pressure or fire due to electrical defect

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Emergency Protection Circuit Devices (AREA)

Abstract

발명은 공급전원을 수용가에 전달하는 배전선로 설치되는 고압 수전반 차단기에 있어서, 과전류 차단을 위해서, 고장의 발생에 응하여 작동되는 과전류 차단기들(51R, 51S, 51T) 및 이에 의해 상기 차단기를 트립 상태로 전환시키는 계전기(86X)를 구비하며; 저전압 발생시 이에 응하여 작동되는 부족전압 계전기(UVR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 부족전압 계전기와; 상기 공급전원의 3상 중 한 상이 결상의 발생시, 이에 응하여 작동되는 결상보호 계전기(POR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 결상보호 계전기(POR)와; 저전압 복구시 또는 결상 복구시 이에 응하여, 상기 UVR 또는 상기 POR이 복귀하여 이에 응하여 소정의 시간 후에 여자되어 상기 차단기를 자동으로 투입 시키는 계전기(27T)를 포함한다.The present invention provides a high-voltage switchgear breaker installed as a distribution line for delivering a supply power to a customer, wherein the overcurrent breakers 51R, 51S, 51T operated in response to the occurrence of a fault, and the breaker are tripped for the purpose of blocking the overcurrent. A relay 86X to switch to; An undervoltage relay (UVR) operating in response to a low voltage occurrence, the undervoltage relay in response to the relay (86X) operating to switch the breaker to a trip state; An image protection protection relay (POR) operated in response to one of three phases of the power supply, and in response to the image protection protection relay (POR) operating the relay 86X to switch the circuit breaker to a trip state; ; In response to the low voltage recovery or the phase recovery, the UVR or the POR is returned and excited in response to a predetermined time, and includes a relay 27T for automatically turning on the breaker.

Description

고압 수전반 차단기{Breaker for high tension power board}Breaker for high tension power board {Breaker for high tension power board}

본 발명은 고압 수전반 차단기에 관한 것으로, 특히 저전압 복구시 및 결상복구시 단시간 내에 자동으로 차단기가 복귀되도록 한 고압 수전반 차단기에 관한 것이다.The present invention relates to a high-voltage switchgear breaker, and more particularly, to a high-voltage switchgear breaker for automatically returning the breaker in a short time during low voltage recovery and phase recovery.

변전소에서 수용가로 전기를 공급하기 위해서는 배전선로가 필요하다. 이러한 배전선로에 정전이 발생하면 고압고객은 구내 기기를 보호하기 위해서 먼저 구내 차단기를 차단한다. 이어서, 구내 차단기를 차단한 이후 적절한 조치에 의해 배전선로가 정상으로 복구되면 고객 구내 전기담당자는 전압의 상태를 점검하여 이상이 없는 경우에 수동으로 투입하고 있다.Distribution lines are needed to supply electricity from substations to consumers. If a power outage occurs in such a distribution line, the high voltage customer first shuts down the premises breaker to protect the premises equipment. Subsequently, if the distribution line is restored to normal by appropriate measures after the premises breaker is shut off, the customer premises electrician checks the state of the voltage and inputs it manually when there is no error.

이와 같이 배전선로의 정전의 발생의 경우 먼저 구내 차단기가 차단되는데, 차단기가 동작한 경우 복구하는데 통상 20 분 내지 30 분 정도의 정전시간이 발생하게 된다.Thus, in the event of a power outage of the distribution line, the premises circuit breaker is first cut off, and when the breaker is operated, a power failure time of about 20 minutes to 30 minutes is generally generated.

더욱이, 전기 기술자가 퇴근 등 부재시에 배전선로 복구하기까지는 예를 들면 1시간 내지 3시간 혹은 그 이상의 시간동안 정전이 발생할 수 있게 된다.In addition, a power failure may occur, for example, from one hour to three hours or more until the electrician recovers to the power distribution line in the absence of work or the like.

본 발명은 전술한 문제점을 해결하기 위한 것으로, 적절한 상황하에서 차단기를 예를 들면 5초 내지 10 초 대기후 자동으로 투입되어 운전되도록 하고, 자동투입운전이 필요하지 않은 경우엔 수동조작이 가능하도록 한 자동투입을 가능하게 한 고압 수전반 차단기를 제공하는 것이다.The present invention is to solve the above-mentioned problems, under the appropriate circumstances, for example, 5 seconds to 10 seconds after the standby is automatically put into operation, and if the automatic input operation is not necessary to enable manual operation. It is to provide a high-voltage switchgear breaker that enables automatic injection.

본 발명의 목적은 공급전원을 수용가에 전달하는 배전선로 설치되는 고압 수전반 차단기에 있어서, 과전류 차단을 위해서, 고장의 발생에 응하여 작동되는 과전류 차단기들(51R, 51S, 51T) 및 이에 의해 상기 차단기를 트립 상태로 전환시키는 계전기(86X)를 구비하며; SUMMARY OF THE INVENTION An object of the present invention is a high voltage switchgear breaker installed as a distribution line for delivering supply power to a customer, for overcurrent blocking, overcurrent breakers 51R, 51S, 51T operated in response to the occurrence of a failure and thereby the breaker A relay 86X for switching the to trip state;

저전압 발생시 이에 응하여 작동되는 부족전압 계전기(UVR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 부족전압 계전기와, An undervoltage relay (UVR) operating in response to a low voltage occurrence, the undervoltage relay in response to the relay 86X operating to switch the breaker to a trip state;

상기 공급전원의 3상 중 한 상이 결상의 발생시, 이에 응하여 작동되는 결상보호 계전기(POR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 결상보호 계전기(POR)와, An image protection protection relay (POR) operated in response to one of three phases of the power supply, and in response to the image protection protection relay (POR) operating the relay 86X to switch the circuit breaker to a trip state; ,

저전압 복구시 또는 결상 복구시 이에 응하여, 상기 UVR 또는 상기 POR이 복귀하여 이에 응하여 소정의 시간 후에 여자되어 상기 차단기를 자동으로 투입 시키는 계전기(27T)를 포함하는, 고압 수전반 차단기에 의해 달성된다.In response to the low voltage recovery or the phase recovery, the UVR or POR is returned and, in response, is achieved by a high voltage switchgear breaker comprising a relay 27T which is excited after a predetermined time and automatically turns on the breaker.

상기 차단기는 상기 자동으로 투입 되는 계전기에 연관된 자동-수동 선택 스 위치를 더 포함하고, 상기 자동-수동 선택 스위치에 의해 상기 차단기를 자동 또는 수동으로 투입하도록 구성될 수 있다.The breaker further includes an auto-manual selection switch associated with the automatically-injected relay, and may be configured to automatically or manually open the breaker by the auto-manual selection switch.

상기 소정의 시간은 3 내지 10 초일 수 있다.The predetermined time may be 3 to 10 seconds.

본 발명에서, 저전압 발생으로 UVR이 동작한 후에도 전압이 아직 미복귀한 경우가 있을 수 있다. 그러면 앞에 기술된 바와 같이, 차단기는 트립 상태를 유지하고 있기 때문에 재투입은 되지 않아, 저전입이 공급될 우려는 없다. UVR이 동작 후 전압이 복귀한 후에는 언급된 바와 같이 10초 후에 자동으로 차단기가 투입 됨으로써 전력이 공급될 수 있다.In the present invention, there may be a case where the voltage is still returned even after the UVR is operated due to the low voltage generation. Then, as described above, since the breaker is kept in the trip state, no re-injection is performed, and there is no fear that the low-input is supplied. After the UVR returns, after the voltage returns, the breaker can be turned on automatically after 10 seconds as mentioned.

POR 동작후에도 결상상태에서 미복귀된 경우가 있을 수 있다. 그러면 앞에서 언급된 바와 같이 차단기를 트립 상태를 유지하고 있는 재투입은 되지 않는다. POR이 동작후 결상에서 복귀한 경우엔 10초 후 자동으로 전력이공급될 수 있다.Even after the POR operation, there may be a return from the open phase. Then, as mentioned above, the circuit breaker is not re-inserted while the trip state is maintained. If the POR returns from the open phase after operation, power can be automatically supplied after 10 seconds.

이러한 정전시간 단축은 전력판매측 입장에서는 판매전력량이 예를 들면 7,631,087kWH/년의 증가를 가져와 수입 증대로 이어질 수 있다. 물론 수용가 입장에서는 신속한 복구로 정전의 불편을 해소할 수 있다.This reduction in power outage time can lead to an increase in revenue, for example, due to an increase in sales power, for example, 7,631,087 kWH / year. Of course, the consumer can resolve the inconvenience of a power outage by prompt recovery.

본 발명에 따른 바람직한 실시예를 구체적인 회로도를 보인 첨부한 도면을 참조하여 설명한다.Preferred embodiments according to the present invention will be described with reference to the accompanying drawings showing a specific circuit diagram.

도 1은 본 발명에 따른 고압 수전반 차단기 자동투입 장치를 위한 회로 구성도이다.1 is a circuit diagram illustrating a device for automatically inserting a high voltage power board breaker according to the present invention.

도시된 바와 같이, 전압의 복구상태를 정확히 판단하게 하기 위해서 고객구내에 결상보호 계전기(POR) 및 부족전압 계전기(UVR)을 설치하고 있다.As shown, in order to accurately determine the recovery state of the voltage, an image protection relay (POR) and an undervoltage relay (UVR) are installed in the customer premises.

구내고장이 발생된 경우에 회로 동작 흐름을 이하 설명한다.The circuit operation flow will be described below in the event of a premises failure.

구내고장이 발생되면 본 차단기는 51R, 51S, 51T의 a 접점(도시되지 않음)이 투입 된다. 이들 과전류 계전기들이 작동됨에 따라 차단기는 오프가 된다.If a breakdown occurs, the breaker is fitted with contacts a (not shown) of 51R, 51S and 51T. The breaker turns off as these overcurrent relays are activated.

다음에, 51X의 코일이 여자되어 51X의 코일 a 접점이 투입 된다.Next, the 51X coil is excited and the coil a contact of 51X is input.

다음에 86X 코일이 여자되어 86X의 a 접점이 투입 된다.The 86X coil is then excited and the a contact of 86X is inserted.

상기의 86X의 a 접점이 투입 됨에 따라, 차단기가 트립 상태에 진입한다.As the contact a of the 86X is inputted, the breaker enters the trip state.

구내 고장발생시에는 재폐로는 되지 않으며 고장복구후에 차단기를 수동으로 투입하게 된다.In the event of a failure in the premises, reclosing is not possible and the breaker is manually inserted after the failure recovery.

본 발명에서는 자동-수동 선택 스위치를 설치함으로써, 선택에 따라 자동으로 혹은 수동으로 작동하게 하고 있다. 자동-수동 선택 스위치는 도 1에서 참조부호 1로 표시된 점선 박스 내 AUTO 기호로 표시한 부분에 해당한다. 도면에서 현재 상태는 자동 선택된 경우를 나타내고 있다.In the present invention, by providing an auto-manual selection switch, it is operated automatically or manually according to the selection. The auto-manual selection switch corresponds to the portion indicated by the AUTO symbol in the dashed box indicated by reference numeral 1 in FIG. 1. In the drawing, the current state represents a case where an automatic selection is made.

자동운전을 위해서 본 발명에서는 도면에 도시된 바와 같이, 결상보호 계전기(POR)가 참조부호 2, 3과 같이 설치된다.In the present invention, for the automatic operation, as shown in the figure, an imaging protection relay (POR) is provided as shown by the reference numerals 2 and 3.

먼저, 저전압 발생으로 부족전압 계전기(UVR)을 UVR에 관련하여 자동동작하는 경우에 대해 설명한다.First, the case where the undervoltage relay UVR automatically operates in relation to the UVR due to the low voltage generation will be described.

저전압이 발생하게 되면 도 1에 참조부호 2로 표시한 점선 박스 내 도시된 부족전압 계전기인 UVR의 a 접점이 투입 된다.When a low voltage is generated, a contact of UVR, which is the undervoltage relay shown in the dashed box indicated by reference numeral 2 in FIG. 1, is inputted.

이어서, UVR에 직렬접속된 27X 계전기 코일이 여자되어 27X의 a 접점이 투입 된다.Subsequently, the 27X relay coil connected in series with the UVR is excited to input the 27X contact a.

이어서, 86X 계전기의 코일이 여자되어 86X의 a 접점이 투입 된다.Subsequently, the coil of the 86X relay is excited and the contact a of 86X is input.

상기의 86X의 a 접점이 투입 됨에 따라, 차단기가 트립 상태에 진입한다. 즉, 저전압이 발생하면 UVR 계전기에 의해 차단기가 오프가 된다.As the contact a of the 86X is inputted, the breaker enters the trip state. That is, when a low voltage occurs, the breaker is turned off by the UVR relay.

여기서, 저전압 회복 전압 정상 복귀에 대해 설명한다.Here, the low voltage recovery voltage normal return will be described.

저전압이 정상전압으로 복귀하게 되면 UVR 접점은 자동으로 복귀하여 27X 계전기의 코일은 부쇄된다.When the low voltage returns to normal voltage, the UVR contact automatically returns and the coil of the 27X relay is broken.

그러면, 27X의 b 접점이 복귀하여 27T 계전기가 여자된다.Then, the b contact of 27X returns and the 27T relay is excited.

일정시간, 예를 들면 3 내지 10 초 후에, 27T 계전기의 a 접점이 투입 되어 27X1 계전기가 여자된다(도 1에 참조부호 1의 점선 박스 내 참조).After a certain time, for example, 3 to 10 seconds, the a contact of the 27T relay is turned on to excite the 27X1 relay (see in dashed box indicated by reference numeral 1 in FIG. 1).

27X1의 a 접점이 투입 됨으로써 차단기는 투입이 된다.The breaker is closed when the contact a of 27X1 is closed.

이와 같은 절차에 의해 저전압 상태가 복귀하면 일정시간 후 차단기는 자동으로 투입된다. 따라서 담당 인력은 필요하지 않게 되어, 이와 같은 적절한 조건만 갖추어지게 되면 인력의 수고 없이 자동으로 차단기가 투입 됨으로써 전력이 공급될 수 있게 된다.When the low voltage is restored by this procedure, the breaker is automatically turned on after a certain time. Therefore, the personnel in charge are not necessary, and if such proper conditions are met, the breaker can be automatically supplied without the labor of the personnel, so that electric power can be supplied.

다음에, 자동운전중 A, B, C 상 중 한 상에 결상이 발생한 경우에 동작을 설명한다.Next, the operation will be described when an image formation occurs in one of phases A, B, and C during automatic operation.

결상이 발생하게 되면 이에 응하여 도 1에 참조부호 3으로 표시한 점선박스 내 POR이 동작하여 POR 계전기의 a 접점이 투입 된다.If an image formation occurs, the POR in the dotted box indicated by reference numeral 3 in FIG. 1 operates in response to the contact point a of the POR relay.

이에 따라 47X 계전기가 여자하여 47X의 a 접점이 투입 된다.As a result, the 47X relay is excited and the a contact of 47X is input.

47X의 a 접점이 투입 되어 86X 계전기가 여자된다.The contact a of 47X is input and the 86X relay is excited.

상기의 86X의 a 접점이 투입 됨에 따라, 차단기가 트립 상태에 진입한다. 즉, 결상이 발생하면 POR 계전기에 의해 차단기가 오프가 된다.As the contact a of the 86X is inputted, the breaker enters the trip state. That is, when an open phase occurs, the breaker is turned off by the POR relay.

차단기가 오프된 상태에서 결상원인을 제거하여 복구가 이루어지고, 이에 이어 결상 회복 절차가 뒤따른다. 이것은 본 발명에 따라 다음과 같이 자동으로 이루어진다.Recovery is achieved by eliminating the cause of the missing phase with the breaker off, followed by the missing phase recovery procedure. This is done automatically according to the invention as follows.

결상이 복구가 됨에 따라, POR은 이에 응하여 POR 접점이 자동으로 복귀하여 47X 계전기의 코일이 부쇄된다.As the phase is restored, the POR will automatically return the POR contact in response and the coil of the 47X relay will break.

그러면, 47X의 a 접점이 복귀하여 86X가 부쇄되고 a 접점이 복귀한다.Then, the a contact of 47X returns, 86X is broken down, and the a contact returns.

이어서, 47X의 b 접점이 복귀하여 27T 계전기가 여자된다.Subsequently, the b contact of 47X returns and the 27T relay is excited.

일정시간, 예를 들면 3 내지 10 초 후에, 27T 계전기의 a 접점이 투입 되어 27X1 계전기가 여자된다(도 1에 참조부호 1의 점선 박스 내 참조).After a certain time, for example, 3 to 10 seconds, the a contact of the 27T relay is turned on to excite the 27X1 relay (see in dashed box indicated by reference numeral 1 in FIG. 1).

27X1의 a 접점이 투입 됨으로써 차단기는 투입이 된다.The breaker is closed when the contact a of 27X1 is closed.

이와 같은 절차에 의해 결상에서 복구되면 일정시간 후 차단기는 자동으로 투입된다. 따라서 담당 인력의 수고 없이 자동으로 차단기가 투입 됨으로써 전력이 공급될 수 있게 된다.When the phase is recovered from the phase loss, the breaker is automatically turned on after a certain time. Therefore, the breaker is automatically turned on without the labor of the person in charge, so that the power can be supplied.

본 발명에 따른 고압 수전반 차단기 자동투입 장치는, 예를 들면, 전원측 정전시에 구내 차단기가 동작하여 전원을 끊고 전원이 복구되면 자동투입 장치 내 계전기들의 동작으로 이상이 없는 경우 차단기는 전술한 바와 같이 예를 들면 3 채니 10초, 적합하게는 8초 후에 자동으로 투입될 수 있는 것이다.The automatic input device of the high-voltage switchgear breaker according to the present invention, for example, when the premises breaker operates when the power supply side power failure, and the power is restored, when the power is restored, the circuit breaker as described above when there is no abnormality due to the operation of the relays in the automatic input device. Likewise, for example, three channels of 10 seconds, suitably 8 seconds, can be added automatically.

본 발명의 차단기 자동투입장치에 의해 다음과 같은 결과를 얻을 수 있다.By the circuit breaker automatic injection device of the present invention can obtain the following results.

저전압 발생으로 UVR이 동작한 후에도 전압이 아직 미복귀한 경우가 있을 수 있다. 그러면 앞에 기술된 바와 같이, 차단기는 트립 상태를 유지하고 있기 때문에 재투입은 되지 않아, 저전입이 공급될 우려는 없다. UVR이 동작 후 전압이 복귀한 후에는 언급된 바와 같이 10초 후에 자동으로 차단기가 투입 됨으로써 전력이 공급될 수 있다.In some cases, the voltage may still return after the UVR is activated due to the low voltage. Then, as described above, since the breaker is kept in the trip state, no re-injection is performed, and there is no fear that low-input is supplied. After the UVR returns, after the voltage returns, the breaker can be turned on automatically after 10 seconds as mentioned.

POR 동작후에도 결상상태에서 미복귀된 경우가 있을 수 있다. 그러면 앞에서 언급된 바와 같이 차단기를 트립 상태를 유지하고 있는 재투입은 되지 않는다. POR이 동작후 결상에서 복귀한 경우엔 10초 후 자동으로 전력이공급될 수 있다.Even after the POR operation, there may be a return from the open phase. Then, as mentioned above, the circuit breaker is not re-inserted while the trip state is maintained. If the POR returns from the open phase after operation, power can be automatically supplied after 10 seconds.

이러한 정전시간 단축은 전력판매측 입장에서는 판매전력량이 예를 들면 7,631,087kWH/년의 증가를 가져와 수입 증대로 이어질 수 있다. 물론 수용가 입장에서는 신속한 복구로 정전의 불편을 해소할 수 있다.This reduction in power outage time can lead to an increase in revenue, for example, due to an increase in sales power, for example, 7,631,087 kWH / year. Of course, the consumer can resolve the inconvenience of a power outage by prompt recovery.

도 1은 본 발명에 따른 차단기의 자동투입 기능을 구비한 고압 수전반 차단기의 상세 회로구성도이다.1 is a detailed circuit diagram of a high-voltage switchgear breaker having an automatic input function of a breaker according to the present invention.

Claims (7)

공급전원을 수용가에 전달하는 배전선로 설치되는 고압 수전반 차단기 에 있어서,In the high-voltage switchgear breaker is installed as a distribution line for delivering the supply power to the customer, 과전류 차단을 위해서, 고장의 발생에 응하여 작동되는 과전류 차단기들(51R, 51S, 51T) 및 이에 의해 상기 차단기를 트립 상태로 전환시키는 계전기(86X)를 구비하며; For overcurrent blocking, overcurrent breakers 51R, 51S, 51T operated in response to the occurrence of a fault and a relay 86X thereby switching the breaker into a trip state; 저전압 발생시 이에 응하여 작동되는 부족전압 계전기(UVR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 부족전압 계전기와,An undervoltage relay (UVR) operating in response to a low voltage occurrence, the undervoltage relay in response to the relay 86X operating to switch the breaker to a trip state; 저전압 복구시 이에 응하여, 상기 UVR이 복귀하여 이에 응하여 소정의 시간 후에 여자되어 상기 차단기를 자동으로 투입 시키는 계전기(27T)In response to the low voltage recovery, the relay 27T is excited to return the UVR to be excited after a predetermined time and automatically turn on the circuit breaker. 를 포함하는, 고압 수전반 차단기.Including, high-voltage switchgear breaker. 공급전원을 수용가에 전달하는 배전선로 설치되는 고압 수전반 차단기 에 있어서,In the high-voltage switchgear breaker is installed as a distribution line for delivering the supply power to the customer, 과전류 차단을 위해서, 고장의 발생에 응하여 작동되는 과전류 차단기들(51R, 51S, 51T) 및 이에 의해 상기 차단기를 트립 상태로 전환시키는 계전기(86X)를 구비하며; For overcurrent blocking, overcurrent breakers 51R, 51S, 51T operated in response to the occurrence of a fault and a relay 86X thereby switching the breaker into a trip state; 상기 공급전원의 3상 중 한 상이 결상의 발생시, 이에 응하여 작동되는 결상 보호 계전기(POR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 결상보호 계전기(POR)와,An imaging protection relay (POR) operated in response to one of three phases of the power supply, and the imaging protection relay (POR) corresponding to the relay 86X operating to switch the circuit breaker to a tripping state. , 결상 복구시 이에 응하여, 상기 POR이 복귀하여 이에 응하여 소정의 시간 후에 여자되어 상기 차단기를 자동으로 투입 시키는 계전기(27T)In response to the phase recovery, in response to the POR, the relay 27T is excited after a predetermined time and automatically turns on the circuit breaker. 를 포함하는, 고압 수전반 차단기.Including, high-voltage switchgear breaker. 제1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 자동으로 투입 되는 계전기에 연관된 자동-수동 선택 스위치를 더 포함하고, 상기 자동-수동 선택 스위치에 의해 상기 차단기를 자동 또는 수동으로 투입하도록 된, 고압 수전반 차단기.And an auto-manual selection switch associated with the automatically input relay, adapted to automatically or manually input the breaker by the auto-manual selection switch. 제1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 소정의 시간은 3 내지 10 초인, 고압 수전반 차단기.The predetermined time is 3 to 10 seconds. 공급전원을 수용가에 전달하는 배전선로 설치되는 고압 수전반 차단기 에 있어서,In the high-voltage switchgear breaker is installed as a distribution line for delivering the supply power to the customer, 과전류 차단을 위해서, 고장의 발생에 응하여 작동되는 과전류 차단기들(51R, 51S, 51T) 및 이에 의해 상기 차단기를 트립 상태로 전환시키는 계전기(86X)를 구비하며;For overcurrent blocking, overcurrent breakers 51R, 51S, 51T operated in response to the occurrence of a fault and a relay 86X thereby switching the breaker into a trip state; 저전압 발생시 이에 응하여 작동되는 부족전압 계전기(UVR), 이에 응하여 상 기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 부족전압 계전기와,An undervoltage relay (UVR) operating in response to a low voltage occurrence, the undervoltage relay (86X) operating in response to the undervoltage relay for switching the breaker to a trip state; 상기 공급전원의 3상 중 한 상이 결상의 발생시, 이에 응하여 작동되는 결상보호 계전기(POR), 이에 응하여 상기 계전기(86X)가 작동하여 상기 차단기를 트립 상태로 전환시키는 상기 결상보호 계전기(POR)와,An image protection protection relay (POR) operated in response to one of three phases of the power supply, and in response to the image protection protection relay (POR) operating the relay 86X to switch the circuit breaker to a trip state; , 저전압 복구시 또는 결상 복구시 이에 응하여, 상기 UVR 또는 상기 POR이 복귀하여 이에 응하여 소정의 시간 후에 여자되어 상기 차단기를 자동으로 투입 시키는 계전기(27T)In response to a low voltage recovery or an image recovery, the relay 27T returns the UVR or the POR to excite after a predetermined time in response to the UVR or the POR. 를 포함하는, 고압 수전반 차단기.Including, high-voltage switchgear breaker. 제5항에 있어서,The method of claim 5, 상기 자동으로 투입 되는 계전기에 연관된 자동-수동 선택 스위치를 더 포함하고, 상기 자동-수동 선택 스위치에 의해 상기 차단기를 자동 또는 수동으로 투입하도록 된, 고압 수전반 차단기.And an auto-manual selection switch associated with the automatically input relay, adapted to automatically or manually input the breaker by the auto-manual selection switch. 제5항에 있어서,The method of claim 5, 상기 소정의 시간은 3 내지 10 초인, 고압 수전반 차단기.The predetermined time is 3 to 10 seconds.
KR1020080133360A 2008-12-24 2008-12-24 Breaker for high tension power board Ceased KR20100074829A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080133360A KR20100074829A (en) 2008-12-24 2008-12-24 Breaker for high tension power board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080133360A KR20100074829A (en) 2008-12-24 2008-12-24 Breaker for high tension power board

Publications (1)

Publication Number Publication Date
KR20100074829A true KR20100074829A (en) 2010-07-02

Family

ID=42637311

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080133360A Ceased KR20100074829A (en) 2008-12-24 2008-12-24 Breaker for high tension power board

Country Status (1)

Country Link
KR (1) KR20100074829A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101365706B1 (en) * 2012-07-13 2014-02-21 주식회사 베스텍 Load shut out protection function high and low voltage switch gear
US9249312B2 (en) 2012-12-26 2016-02-02 Hyeok Jung Kim Eco-friendly water-based paint composition for interior finishing materials of buildings
US10614985B2 (en) 2017-01-05 2020-04-07 Lsis Co., Ltd. 3 phase undervoltage trip device and molded case circuit breaker therewith

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101365706B1 (en) * 2012-07-13 2014-02-21 주식회사 베스텍 Load shut out protection function high and low voltage switch gear
US9249312B2 (en) 2012-12-26 2016-02-02 Hyeok Jung Kim Eco-friendly water-based paint composition for interior finishing materials of buildings
US10614985B2 (en) 2017-01-05 2020-04-07 Lsis Co., Ltd. 3 phase undervoltage trip device and molded case circuit breaker therewith

Similar Documents

Publication Publication Date Title
RU2572619C2 (en) Protective cutout device
RU2481666C2 (en) Automatic fault current shutdown device
US20240387118A1 (en) Circuit breaker
EP1569314B1 (en) Automatic reset device particularly for residual current-operated circuit breakers and the like
CN110474288B (en) Programmable microcomputer protection device
KR20100074829A (en) Breaker for high tension power board
CN111799749B (en) Electrical protection system and method
CN216134265U (en) Three-phase inconsistent protection circuit
JP2001135204A (en) Transient current prevention device in substation equipment.
JP3248962B2 (en) How to protect the inverter distribution system
JP2009177958A (en) Switchgear with exciting rush current suppressor
KR20080093400A (en) Multifunctional Motor Protection Relay
Brewis et al. Theory and practical performance of interlocked overcurrent busbar zone protection in distribution substations
JP4028521B2 (en) Distribution system protection device and distribution system protection method
JP7541300B2 (en) Uninterruptible power switching device
KR101580592B1 (en) Circuit breaker for uninterruptible power test and exchange
EP4404229B1 (en) Automated three-pole base with switching and protection device for low-voltage switchboard and low-voltage switchboard incorporating said automated three-pole base
KR102707295B1 (en) Solenoid burnout prevention type earth leakage circuit breaker due to reverse current
KR102794455B1 (en) A protection system of main transformer minimizing load not served and preventing wide-area power outages
KR100419261B1 (en) apparatus for protecting ground fault of low voltage bus in spot network system
JP2623933B2 (en) Gas switchgear
RU2695643C1 (en) Method of transforming power supply systems tn-cs and tt and power supply system for implementing method with protective input heterogeneous communication switching device
Fidigatti et al. Effect of harmonic pollution on low voltage overcurrent protection
Ajit et al. Design and Development of Automatic Mains Failure Panel for Diesel Generator
KR200192232Y1 (en) Latch type power magnet reset circuits at the power fail

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20081224

PA0201 Request for examination
PG1501 Laying open of application
E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20100830

Patent event code: PE09021S01D

E601 Decision to refuse application
PE0601 Decision on rejection of patent

Patent event date: 20110208

Comment text: Decision to Refuse Application

Patent event code: PE06012S01D

Patent event date: 20100830

Comment text: Notification of reason for refusal

Patent event code: PE06011S01I