KR200318935Y1 - Precasting block for foundation of house - Google Patents
Precasting block for foundation of house Download PDFInfo
- Publication number
- KR200318935Y1 KR200318935Y1 KR20-2003-0009220U KR20030009220U KR200318935Y1 KR 200318935 Y1 KR200318935 Y1 KR 200318935Y1 KR 20030009220 U KR20030009220 U KR 20030009220U KR 200318935 Y1 KR200318935 Y1 KR 200318935Y1
- Authority
- KR
- South Korea
- Prior art keywords
- vertical wall
- block
- shaped block
- lower support
- shaped
- Prior art date
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims abstract description 28
- 229910052742 iron Inorganic materials 0.000 claims abstract description 14
- 230000008878 coupling Effects 0.000 claims description 10
- 238000010168 coupling process Methods 0.000 claims description 10
- 238000005859 coupling reaction Methods 0.000 claims description 10
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 238000005266 casting Methods 0.000 claims description 2
- 229910001018 Cast iron Inorganic materials 0.000 abstract description 4
- 238000005304 joining Methods 0.000 abstract description 4
- 238000009415 formwork Methods 0.000 description 12
- 238000010276 construction Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 229910001208 Crucible steel Inorganic materials 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 244000118350 Andrographis paniculata Species 0.000 description 1
- BQCADISMDOOEFD-UHFFFAOYSA-N Silver Chemical compound [Ag] BQCADISMDOOEFD-UHFFFAOYSA-N 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/48—Foundations inserted underneath existing buildings or constructions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
- E02D2300/0032—Steel; Iron in sheet form, i.e. bent or deformed plate-material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Abstract
본 고안은 수직으로 세워진 세로 벽체가 ㄱ자 형상을 이루며, 상기 세로 벽체를 하부에서 지지하도록 상기 세로 벽체의 하부에 일정 각도를 이루어서 2가닥으로 벌어진 하부지지체를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체의 상부에 서로 일정간격을 두고 역U자 형상의 고리가 설치됨과 동시에, 일정간격을 두고 다수의 주철근이 설치되고, 결합 철판을 너트에 의해 결합시키도록 상기 세로 벽체의 상부 양단부 근처에 볼트가 각각 설치된 ㄱ자 형상의 블록체와, 수직으로 세워진 세로 벽체가 -자 형상을 이루며, 상기 세로 벽체를 하부에서 지지하도록 상기 세로 벽체의 하부에 일정 각도를 이루어서 2가닥으로 벌어진 하부지지체를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체의 상부에 서로 일정간격을 두고 역U자 형상의 고리가 설치됨과 동시에, 일정간격을 두고 다수의 주철근이 설치되고, 결합 철판을 너트에 의해 결합시키도록 상기 세로 벽체의 상부 양단부 근처에 볼트가 각각 수직으로 설치된 -자 형상의 블록체로 구성되어 있다.The present invention has a vertical wall vertically formed in the L-shape, and at the same time to support the vertical wall at the bottom of the vertical wall at a certain angle with a lower support that is spread in two strands, so as to lift and move the At the same time, the inverted U-shaped rings are installed on the upper part of the vertical wall at the same time, and at the same time, a plurality of cast iron bars are installed at a predetermined distance, and bolts near the upper both ends of the vertical wall to couple the joining iron plate by nuts. And each of which is provided with a block having a U-shape, the vertical wall vertically erected in the form of a --shape, and the lower support is opened in two strands at an angle to the lower portion of the vertical wall to support the vertical wall from the bottom and At the same time, inverted U-shaped spaced apart from each other on top of the vertical wall to be moved and moved At the same time, a plurality of cast iron bars are installed at regular intervals, and bolts are installed vertically near upper upper ends of the vertical walls to couple the joining iron plates by nuts. have.
따라서, 본 고안은 하부 지지체내의 공간에 콘크리트가 완전히 채워져서 하중을 받아도 파손을 방지할 수 있고, 기초 공사의 공기를 단축할 수 있을 뿐만 아니라, 공기를 단축할 수 있어 기초 공사 비용을 절감할 수 있다.Therefore, the present invention can prevent the breakage even when the concrete is completely filled in the space of the lower support under load, and not only shorten the air of the foundation work, but also shorten the air, thereby reducing the cost of the foundation work. Can be.
Description
본 고안은 주택 기초용 프리캐스팅 블록에 관한 것으로서, 특히 하부 지지체내의 공간에 콘크리트가 완전히 채워져서 하중을 받아도 파손을 방지할 수 있고, 기초 공사의 공기를 단축할 수 있는 주택 기초용 프리캐스팅 블록에 관한 것이다.The present invention relates to a precast block for a house foundation, and in particular, a precast block for a house foundation that can prevent damage even when a concrete is completely filled in the space in the lower support under load, and shorten the air of the foundation work. It is about.
종래로 부터 주택(조립식 건축물 포함)을 건축할려면 기초공사를 하기 위하여 땅을 일정 폭과 깊이로 굴삭한 다음, 그 내부에 거푸집을 설치하고, 이들 거푸집에 의해 형성되는 공간내에 콘크리트를 일정 높이까지 타설하여 양생시켜서 기초공사를 하고 있었다.Conventionally, in the construction of houses (including prefabricated buildings), the ground is excavated to a certain width and depth for foundation work, and then, formwork is installed therein, and concrete is cast to a certain height in the space formed by these formwork. Was cured and the foundation was doing.
그런데, 이와 같이 기초공사를 하면, 땅을 일정 폭과 깊이로 굴삭한 다음, 그 내부에 거푸집을 설치하고, 이들 거푸집에 의해 형성되는 공간내에 콘크리트를 일정 높이까지 타설하여 양생시켜야 하므로, 기초공사의 공기를 단축시킬 수 없을 뿐만 아니라, 기초공사를 위하여 거푸집을 조립하여야 하고, 거푸집 내에 타설된 콘크리트가 양생된 후에는 거푸집을 해체하여 일정 장소에 모아 두었다가 다른 공사현장으로 이동하여 다시 사용하여야 하므로, 거푸집의 운반과 유지/관리에 많은 경비가 소요되고, 또한 현장에서 콘크리트를 혼합하여야 하므로 콘크리트의 품질을 일정한 강도로 혼합할 수 없어 품질을 일정하게 유지할 수 없고, 또한 콘크리트 및 콘크리트의 원재료 낭비가 심하여 기초 공사 비용을 증가시킨다는 등의 여러가지 문제점이 있었다.However, when the foundation works in this way, the ground must be excavated to a certain width and depth, and then the formwork must be installed in the interior thereof, and concrete must be poured to a certain height in the space formed by these formwork to cure. Not only can the air be shortened, but the formwork must be assembled for the foundation work, and after the concrete poured in the formwork is cured, the formwork must be dismantled, collected at a certain place, moved to another construction site, and used again. It is very costly to transport and maintain and maintain the concrete. Also, the concrete must be mixed in the field, so the quality of concrete cannot be mixed with a certain strength. Therefore, the quality cannot be maintained constantly. There were various problems such as increasing the construction cost.
따라서, 본 고안은 상기 여러가지 문제점을 해결하기 위하여 이루어진 것으로서, 본 고안의 목적은 하부 지지체내의 공간에 콘크리트가 완전히 채워져서 하중을 받아도 파손을 방지할 수 있는 주택 기초용 프리캐스팅 블록을 제공하는데 있다.Accordingly, the present invention has been made to solve the various problems described above, and an object of the present invention is to provide a precast cast block for a foundation of a house that can prevent damage even when a load is completely filled with concrete in a lower support. .
본 고안의 다른 목적은 기초 공사의 공기를 단축할 수 있는 주택 기초용 프리캐스팅 블록을 제공하는데 있다.Another object of the present invention is to provide a precast block for a home foundation that can shorten the air of the foundation work.
본 고안의 또 다른 목적은 기초 공사 비용을 절감할 수 있는 주택 기초용 프리캐스팅 블록을 제공하는데 있다.Another object of the present invention is to provide a precast block for the foundation of the house that can reduce the cost of foundation work.
상기의 목적을 달성하기 위하여 본 고안은 수직으로 세워진 세로 벽체가 ㄱ자 형상을 이루며, 상기 세로 벽체를 하부에서 지지하도록 상기 세로 벽체의 하부에 일정 각도를 이루어서 2가닥으로 벌어진 하부지지체를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체의 상부에 서로 일정간격을 두고 역U자 형상의 고리가 설치됨과 동시에, 일정간격을 두고 다수의 주철근이 설치되고, 결합 철판을 너트에 의해 결합시키도록 상기 세로 벽체의 상부 양단부 근처에 볼트가 각각 설치된 ㄱ자 형상의 블록체와, 수직으로 세워진 세로 벽체가 -자 형상을 이루며, 상기 세로 벽체를 하부에서 지지하도록 상기 세로 벽체의 하부에 일정 각도를 이루어서 2가닥으로 벌어진 하부지지체를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체의 상부에 서로 일정간격을 두고 역U자 형상의 고리가 설치됨과 동시에, 일정간격을 두고 다수의 주철근이 설치되고, 결합 철판을 너트에 의해 결합시키도록 상기 세로 벽체의 상부 양단부 근처에 볼트가 각각 수직으로 설치된 -자 형상의 블록체로 구성되어 있는 것을 특징으로 한다.In order to achieve the above object, the present invention has a vertical wall erected vertically to form an L-shape, and at the same time having a lower support opened in two strands at an angle to the lower portion of the vertical wall to support the vertical wall from the bottom. In order to lift and move the upper portion of the vertical wall to each other at a predetermined interval to the inverted U-shaped ring is installed, at the same time a plurality of cast steel bars are installed at a predetermined interval, the vertical to couple the coupling iron plate by a nut The L-shaped block body with bolts installed near each upper end of the wall, and the vertical wall vertically formed in the shape of a-, and at a lower angle of the vertical wall so as to support the vertical wall at a lower angle into two strands The upper wall of the vertical wall is provided so that it can be lifted and moved at the same time At the same time, inverted U-shaped rings are installed at regular intervals, and at the same time, a plurality of main reinforcing bars are installed at regular intervals, and bolts are disposed vertically near the upper both ends of the vertical wall so as to couple the joining iron plates by nuts. It is characterized by consisting of the block-shaped block body provided.
도 1은 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체를 개략적으로 도시한 사시도,1 is a perspective view schematically showing a block-shaped block body in the precast block for the foundation of a house according to an embodiment of the present invention,
도 2는 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 -자 형상의 블록체를 개략적으로 도시한 사시도,2 is a perspective view schematically showing a block-shaped block body in a precast block for a foundation of a house according to an embodiment of the present invention;
도 3은 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체와 -자 형상의 블록체를 결합하는 방법을 설명하는 설명도,3 is an explanatory diagram for explaining a method of combining an L-shaped block body and a -shaped block body in a precast block for housing foundation according to an embodiment of the present invention;
도 4는 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체와 -자 형상의 블록체를 결합한 상태를 설명하는 설명도,4 is an explanatory diagram illustrating a state in which a block-shaped block body and a block-shaped block body are combined in a precast block for housing foundation according to an embodiment of the present invention;
도 5는 도 4에서 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체와 -자 형상의 블록체에 의해 형성된 공간내에 토사를 메운 후, 바닥공사를 한 상태를 도시한 단면도이다.FIG. 5 is a state in which a ground construction is performed after filling earth and sand in a space formed by a L-shaped block and a -shaped block in a precast block for a foundation of a house according to an embodiment of the present invention in FIG. 4. It is sectional drawing.
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
10:ㄱ자 형상의 블록체 11:세로 벽체10: A-shaped block 11: vertical wall
11a:홈 12:하부지지체11a: groove 12: lower support
12a:공기배출구멍 13:고리12a: Air exhaust hole 13: ring
14:주철근 15:볼트14: cast iron 15: bolt
20:-자 형상의 블록체 21:세로 벽체20: -shaped block 21: vertical wall
22:하부지지체 23:고리22: lower support 23: ring
24:주철근 25:볼트(25)24: cast iron 25: bolt (25)
30:결합 철판 32:너트30: bonding iron plate 32: nut
22a:공기배출구멍 21a:홈22a: air exhaust hole 21a: groove
34:세로철근 36:가로철근34: vertical rebar 36: horizontal rebar
42:가로 철근 44:세로 철근42: horizontal rebar 44: vertical rebar
46:바닥면46: bottom
이하, 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 관하여 첨부 도면에 의거하여 상세히 설명한다.Hereinafter, a precast block for a foundation for a house according to an embodiment of the present invention will be described in detail with reference to the accompanying drawings.
도 1은 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체를 개략적으로 도시한 사시도이고, 도 2는 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 -자 형상의 블록체를 개략적으로도시한 사시도이고, 도 3은 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체와 -자 형상의 블록체를 결합하는 방법을 설명하는 설명도이고, 도 4는 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체와 -자 형상의 블록체를 결합한 상태를 설명하는 설명도이고, 도 5는 도 4에서 본 고안의 일실시예에 의한 주택 기초용 프리캐스팅 블록에 있어서 ㄱ자 형상의 블록체와 -자 형상의 블록체에 의해 형성된 공간내에 토사를 메운 후, 바닥공사를 한 상태를 도시한 단면도이다.1 is a perspective view schematically showing an L-shaped block body in a housing-based precasting block according to an embodiment of the present invention, Figure 2 is a housing-based precasting block according to an embodiment of the present invention In Figure 3 is a perspective view schematically showing a block-shaped block, Figure 3 is a method of combining the block-shaped block and the block-shaped body of the pre-casting block for the housing foundation according to an embodiment of the present invention 4 is an explanatory diagram illustrating a state in which a L-shaped block body and a -shaped block body are combined in a precast building block for a housing foundation according to an embodiment of the present invention, and FIG. 5. In FIG. 4, in the precast block for the foundation of a house according to an embodiment of the present invention, after filling the soil in the space formed by the L-shaped block body and the -shaped block body, the ground work was performed. It is sectional drawing which shows the state.
도 1 내지 도 5에 도시한 바와 같이 본 고안의 일실시예에 따른 주택 기초용 프리캐스팅 블록은 수직으로 세워진 세로 벽체(11)가 ㄱ자 형상을 이루며, 상기 세로 벽체(11)를 하부에서 지지하도록 상기 세로 벽체(11)의 하부에 일정 각도(θ)를 이루어서 2가닥으로 벌어진 하부지지체(12)를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체(11)의 상부에 서로 일정간격을 두고 역U자 형상의 고리(13)가 설치됨과 동시에, 일정간격을 두고 다수의 주철근(14)이 설치되고, 결합 철판(30)을 너트(32)에 의해 결합시키도록 상기 세로 벽체(11)의 상부 양단부 근처에 볼트(15)가 각각 설치된 ㄱ자 형상의 블록체(10)와, 수직으로 세워진 세로 벽체(21)가 -자 형상을 이루며, 상기 세로 벽체(21)를 하부에서 지지하도록 상기 세로 벽체(21)의 하부에 일정 각도(θ)를 이루어서 2가닥으로 벌어진 하부지지체(22)를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체(21)의 상부에 서로 일정간격을 두고 역U자 형상의 고리(23)가 설치됨과 동시에, 일정간격을 두고 다수의 주철근(24)이 설치되고, 결합 철판(30)을 너트(32)에의해 결합시키도록 상기 세로 벽체(21)의 상부 양단부 근처에 볼트(25)가 각각 수직으로 설치된 -자 형상의 블록체(20)로 구성되어 있다.As shown in FIGS. 1 to 5, in the housing foundation precasting block according to an embodiment of the present invention, a vertical wall 11 vertically oriented forms an L-shape, and supports the vertical wall 11 from below. At the bottom of the vertical wall (11) to form a predetermined angle (θ) with a lower support 12 opened in two strands, at the same time with a predetermined interval on the upper portion of the vertical wall (11) to be moved. While the inverted U-shaped ring 13 is installed, a plurality of main reinforcing bars 14 are installed at regular intervals, and the vertical wall 11 of the vertical wall 11 is coupled to the coupling iron plate 30 by a nut 32. The L-shaped block body 10, each of which has bolts 15 installed near the upper ends, and the vertical wall 21 standing vertically form a '-' shape, so that the vertical wall 21 is supported to support the vertical wall 21 from the bottom. Make a certain angle θ at the lower part of 21 At the same time having a lower support 22 is opened in two strands, while the inverted U-shaped ring 23 is installed at regular intervals on the upper portion of the vertical wall 21 to be moved, and at the same time, A plurality of main reinforcing bars 24 are provided at intervals, and the bolts 25 are installed vertically near the upper both ends of the vertical wall 21 so as to couple the coupling iron plate 30 by the nuts 32. It is comprised by the block 20 of a shape.
상기 ㄱ자 형상의 블록체(10)의 하부지지체(12)에는 상기 인접하는 -자 형상의 블록체(20)에 의해 형성되는 공간 및 하부지지체(12)에 의해 형성되는 공간에 콘크리트를 주입할 경우에 콘크리트가 완전히 채워지도록 다수개의 공기배출구멍(12a)이 형성되어 있다.When the concrete is injected into the lower support 12 of the L-shaped block 10, the space formed by the adjacent -shaped block 20 and the space formed by the lower support 12 A plurality of air discharge holes 12a are formed to completely fill the concrete.
상기 -자 형상의 블록체(20)의 하부지지체(22)에는 상기 인접하는 ㄱ자 형상의 블록체(10)에 의해 형성되는 공간, 하부지지체(22)에 의해 형성되는 공간 및 인접하는 상기 -자 형상의 블록체(20)에 의해 형성되는 공간 크리트를 주입할 경우에 콘크리트가 완전히 채워지도록 다수개의 공기배출구멍(22a)이 형성되어 있다.The lower support 22 of the block-shaped block 20 has a space formed by the adjacent L-shaped block 10, a space formed by the lower support 22, and the adjacent block-shaped. In the case of injecting the space creats formed by the block 20 having a shape, a plurality of air discharge holes 22a are formed to completely fill the concrete.
상기 하부지지체(12) 및 하부지지체(22)에 의해 각각 형성되는 일정 각도(θ)는 50도 내지 70도인 것이 바람직하다.It is preferable that the predetermined angle θ formed by the lower support 12 and the lower support 22 is 50 to 70 degrees, respectively.
상기 ㄱ자 형상의 블록체(10)의 세로 벽체(11)의 상부 양단부 근처에 설치된 볼트(15) 둘레에는 상기 결합 철판(30)을 수용할 수 있도록 상기 ㄱ자 형상의 블록체(10)의 세로 벽체(11)의 상부면에 직방체 형상의 홈(11a)이 형성되어 있고, 상기 -자 형상의 블록체(20)의 세로 벽체(21)의 상부 양단부 근처에 설치된 볼트(25) 둘레에는 상기 결합 철판(30)을 수용할 수 있도록 상기 -자 형상의 블록체(20)의 세로 벽체(21)의 상부면에 직방체 형상의 홈(21a)이 형성되어 있다.Vertical wall of the L-shaped block 10 to accommodate the coupling iron plate 30 around the bolt 15 installed near the upper both ends of the vertical wall 11 of the L-shaped block 10 A rectangular parallelepiped groove 11a is formed in the upper surface of the 11, and around the bolt 25 provided near the upper ends of the vertical wall 21 of the block-shaped block 20, the coupling iron plate is formed. A rectangular parallelepiped groove 21a is formed in the upper surface of the vertical wall 21 of the block-shaped block body 20 to accommodate the 30.
도 5에서 미설명 부호 34는 ㅅ자 형상으로 절곡한 세로철근이고, 36은 상기 세로철근(34)에 직각으로 배설되어 도시하지 않은 와이어에 의해 고정된 가로철근이다.In FIG. 5, reference numeral 34 denotes a longitudinal reinforcing bar bent in a s-shaped shape, and 36 is a horizontal rebar that is disposed at right angles to the longitudinal rebar 34 and fixed by a wire (not shown).
다음에, 이와 같이 구성된 본 고안의 일실시예에 따른 주택 기초용 프리캐스팅 블록의 작용 및 효과에 대하여 설명한다.Next, a description will be given of the operation and effects of the housing foundation precasting block according to the embodiment of the present invention.
먼저, 기초공사를 위하여 땅을 일정 폭과 깊이로 굴삭한 다음, 그 내부에 제조 공장에서 제조된 ㄱ자 형상의 블록체(10)의 세로 벽체(11)의 상부에 서로 일정간격을 두고 역U자 형상의 고리(13)에 체인, 로프 또는 와이어를 걸어서 체인블록 또는 크레인으로 들어서 수평으로 재치시킨다.First, the ground is excavated with a predetermined width and depth for the foundation work, and then inverted U-shaped at a predetermined interval on the upper part of the vertical wall 11 of the L-shaped block 10 manufactured in the manufacturing plant therein. Hook the chain, rope or wire to the ring 13 of the shape into a chain block or crane to be mounted horizontally.
다음에, ㄱ자 형상의 블록체(10)의 양단부에 일정간격(L)을 두고 -자 형상의 블록체(20)를 수평을 맞추어서 재치시킨 후, ㄱ자 형상의 블록체(10)의 세로 벽체(11)의 상부 양단부 근처에 설치된 볼트(15)와 상기 -자 형상의 블록체(20)의 세로 벽체(21)의 일측단부 근처에 설치된 볼트(25)에 결합 철판(30)의 양측에 각각 형성된 장공(30a)을 끼우고, 너트(32)로 조인다.Next, after placing the -shaped block 20 in a horizontal manner at both ends of the L-shaped block 10, the vertical wall of the L-shaped block 10 11 are respectively formed on both sides of the coupling iron plate 30 to the bolts 15 installed near the upper ends of the upper end and the bolts 25 installed near one end of the vertical wall 21 of the block-shaped block 20. Insert the long hole (30a) and tighten with the nut (32).
이와 같이 상기 ㄱ자 형상의 블록체(10)의 양단부에 -자 형상의 블록체(20)를 일정간격(L)을 두고 서로 수평으로 배설한 다음에, 상기 ㄱ자 형상의 블록체(10)의 양단부에 -자 형상의 블록체(20) 사이에 형성된 일정간격(L)의 외측면, 즉 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 및 하부벽체(12)의 좌우 외측면과 -자 형상의 블록체(20)의 세로벽체(21) 및 하부벽체(22)의 좌우 외측면에 도시하지 않은 거푸집을 설치한 후, 상기 결합 철판(30)의 상부에서 도시하지 않은 콘크리트 펌프에 의해 콘크리트를 주입한다.As described above, the two-shaped block bodies 20 are horizontally disposed at both ends of the L-shaped block body 10 at a predetermined interval L, and then both ends of the L-shaped block body 10 are disposed. On the outer surface of the predetermined interval (L) formed between the block-shaped block body 20, that is, the left and right outer surface of the vertical wall 11 and the lower wall 12 of the L-shaped block body 10 and- After installing the formwork (not shown) on the left and right outer surfaces of the vertical wall (21) and the lower wall (22) of the block-shaped block body 20, by means of a concrete pump (not shown) on the upper portion of the coupling iron plate (30). Inject the concrete.
이때, 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 및 하부벽체(12), 상기-자 형상의 블록체(20)의 세로벽체(21) 및 하부벽체(22)와 상기 도시하지 않은 거푸집에 의해 형성된 공간을 통해 상기 ㄱ자 형상의 블록체(10)의 하부벽체(12)와 상기 -자 형상의 블록체(20)의 하부벽체(22)에 의해 형성되는 공간내로 콘크리트가 주입되면서 이들 공간내에 잔류하는 공기가 상기 ㄱ자 형상의 블록체(10)의 하부벽체(12)에 형성된 공기배출구(12a) 및 상기 -자 형상의 블록체(20)의 하부벽체(22)에 형성된 공기배출구(12a)를 통해서 배출되므로, 용이하게 이들 공간내에 콘크리트를 주입할 수 있을 뿐만 아니라, 콘크리트가 완전히 채워져서 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 및 상기 -자 형상의 블록체(20)의 세로벽체(21) 상부에 하중이 건축물(주택, 건물)에 인가되어도 파손되지 않는다.At this time, the vertical wall 11 and the lower wall 12 of the L-shaped block 10, the vertical wall 21 and the lower wall 22 of the block-shaped block 20 and the not shown As concrete is injected into the space formed by the lower wall 12 of the L-shaped block body 10 and the lower wall 22 of the -shaped block body 20 through the space formed by the unformed formwork. Air remaining in these spaces is formed in the air outlet 12a formed in the lower wall 12 of the L-shaped block 10, and the air outlet formed in the lower wall 22 of the -shaped block 20. Since it is discharged through 12a, not only concrete can be easily injected into these spaces, but also the concrete is completely filled so that the vertical wall 11 of the L-shaped block body 10 and the -shaped block body are formed. Even if a load is applied to the building (house, building) on the vertical wall 21 of 20, No.
이와 같이 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 및 하부벽체(12), 상기 -자 형상의 블록체(20)의 세로벽체(21) 및 하부벽체(22), 도시하지 않은 거푸집에 의해 형성된 공간내에 주입된 콘크리트양생된 후에, 상기 ㄱ자 형상의 블록체(10)의 하부벽체(12)와 상기 -자 형상의 블록체(20)에 의해 형성되는 내측 공간에 토사를 보충하여 평탄하게 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 외측 및 상기 -자 형상의 블록체(20)의 세로벽체(21) 외측 둘레에 거푸집을 설치한 후에, 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 상부로 돌출된 주철근(14), 역U자 형상의 고리(13) 및 볼트(15)와 상기 -자 형상의 블록체(20)의 세로벽체(21) 상부로 돌출된 주철근(24), 역U자 형상의 고리(23) 및 볼트(25)에 가로 철금(42) 및 세로 철근(44)을 일정 간격을 두고 배근하고 나서 도시하지 않은 와이어로 묶어서 고정한 후, 상기 거푸집, 상기 ㄱ자 형상의 블록체(10)의 세로벽체(11) 상부 및상기 -자 형상의 블록체(20)의 세로벽체(21) 상부에 의해 형성된 공간내에 콘크리트를 타설하여 도 5에 도시한 바와 같이 건축물의 바닥면(46)을 시공한다.Thus, the vertical wall 11 and the lower wall 12 of the L-shaped block 10, the vertical wall 21 and the lower wall 22 of the -shaped block 20, not shown After the concrete is injected into the space formed by the formwork, the soil is replenished in the inner space formed by the lower wall 12 of the L-shaped block 10 and the -shaped block 20 After the formwork is installed on the outer circumference of the vertical wall 11 of the L-shaped block 10 and the outer circumference of the vertical wall 21 of the -shaped block 20, the block-shaped block is formed. The main reinforcing bar 14 protruding from the upper vertical wall 11 of the 10, the inverted U-shaped ring 13 and the bolt 15 and the upper vertical wall 21 of the -shaped block 20 It is not shown after the horizontal reinforcing bar 42 and the vertical reinforcing bars 44 are arranged at regular intervals in the main reinforcing bars 24, the inverted U-shaped rings 23, and the bolts 25 protruding from each other. After binding and fixing with silver wire, concrete is formed in the space formed by the formwork, the upper part of the vertical wall 11 of the L-shaped block 10, and the upper part of the vertical wall 21 of the -shaped block 20. To construct the floor surface 46 of the building as shown in FIG.
따라서, 본 고안은 하부 지지체내의 공간에 콘크리트가 완전히 채워져서 하중을 받아도 파손을 방지할 수 있고, 기초 공사의 공기를 단축할 수 있음과 동시에, 공기를 단축할 수 있어 기초 공사 비용을 절감할 수 있다.Therefore, the present invention can prevent the breakage even when the concrete is completely filled in the space of the lower support under load, and can shorten the air of the foundation work, and can shorten the air, thereby reducing the cost of the foundation work. Can be.
상기 설명에 있어서, 특정 실시예를 들어서 도시하고 설명하였으나, 본 고안은 이에 한정되는 것은 아니며, 예를 들면 본 고안의 개념을 이탈하지 않는 범위내에서 이 기술 분야의 통상의 지식을 가진 자에 의해 여러가지로 설계변경할 수 있음은 물론이다.In the above description, although illustrated and described with reference to specific embodiments, the present invention is not limited to this, for example, by those of ordinary skill in the art without departing from the concept of the present invention Of course, the design can be changed in various ways.
앞에서 설명한 바와 같이 본 고안의 주택 기초용 프리캐스팅 블록에 의하면, 수직으로 세워진 세로 벽체가 ㄱ자 형상을 이루며, 상기 세로 벽체를 하부에서 지지하도록 상기 세로 벽체의 하부에 일정 각도를 이루어서 2가닥으로 벌어진 하부지지체를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체의 상부에 서로 일정간격을 두고 역U자 형상의 고리가 설치됨과 동시에, 일정간격을 두고 다수의 주철근이 설치되고, 결합 철판을 너트에 의해 결합시키도록 상기 세로 벽체의 상부 양단부 근처에 볼트가 각각 설치된 ㄱ자 형상의 블록체와, 수직으로 세워진 세로 벽체가 -자 형상을 이루며, 상기 세로 벽체를 하부에서 지지하도록 상기 세로 벽체의 하부에 일정 각도를 이루어서 2가닥으로 벌어진 하부지지체를 구비함과 동시에, 들어서 이동시킬 수 있도록 상기 세로 벽체의 상부에 서로 일정간격을 두고 역U자 형상의 고리가 설치됨과 동시에, 일정간격을 두고 다수의 주철근이 설치되고, 결합 철판을 너트에 의해 결합시키도록 상기 세로 벽체의 상부 양단부 근처에 볼트가 각각 수직으로 설치된 -자 형상의 블록체로 구성되어 있으므로, 하부 지지체내의 공간에 콘크리트가 완전히 채워져서 하중을 받아도 파손을 방지할 수 있고, 기초 공사의 공기를 단축할 수 있을 뿐만 아니라, 공기를 단축할 수 있어 기초 공사 비용을 절감할 수 있다는 매우 뛰어난 효과가 있다.As described above, according to the housing foundation precasting block of the present invention, a vertical wall vertically erected to form an L-shape, and the lower part which is divided into two strands at an angle to the lower part of the vertical wall so as to support the vertical wall from below. In addition to having a support, the upper U-shaped ring is installed at a predetermined distance from each other on the upper part of the vertical wall so that it can be moved, and at the same time, a plurality of cast steel bars are installed at a predetermined interval, and the joining iron plate is connected to the nut. The L-shaped block bodies each of which bolts are installed near the upper both ends of the vertical wall and the vertical wall vertically formed to have a-shape to be coupled by each other are fixed to a lower portion of the vertical wall to support the vertical wall from below. At the same time having a lower support that is open in two strands at an angle, The inverted U-shaped ring is installed at a predetermined interval on the upper part of the vertical wall so that a plurality of cast bars are installed at a predetermined interval, and both ends of the upper part of the upper vertical wall are joined to each other by a nut. Since the bolts are installed in the form of a block-shaped block body installed vertically, the space in the lower support can be completely filled with concrete to prevent breakage even under load and shorten the air of the foundation construction. In addition, the air can be shortened and the cost of foundation work can be reduced.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20-2003-0009220U KR200318935Y1 (en) | 2003-03-27 | 2003-03-27 | Precasting block for foundation of house |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20-2003-0009220U KR200318935Y1 (en) | 2003-03-27 | 2003-03-27 | Precasting block for foundation of house |
Publications (1)
Publication Number | Publication Date |
---|---|
KR200318935Y1 true KR200318935Y1 (en) | 2003-07-04 |
Family
ID=49410259
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR20-2003-0009220U KR200318935Y1 (en) | 2003-03-27 | 2003-03-27 | Precasting block for foundation of house |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR200318935Y1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102198307B1 (en) | 2020-01-17 | 2021-01-05 | 씨엔피씨 주식회사 | Foundation structure for buliding |
-
2003
- 2003-03-27 KR KR20-2003-0009220U patent/KR200318935Y1/en not_active IP Right Cessation
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102198307B1 (en) | 2020-01-17 | 2021-01-05 | 씨엔피씨 주식회사 | Foundation structure for buliding |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2475872B1 (en) | Foundation for windturbine tower | |
US9175493B2 (en) | Core component and tower assembly for a tower structure | |
KR20120011043A (en) | Half precast floor board and slab construction method using it | |
CN113529956A (en) | Shear wall box type assembly type building structure and construction method thereof | |
JP2013159929A (en) | Building foundation construction method and raised block for use in the same | |
KR20130006420A (en) | Method of constructing underground structure to be newly built | |
KR101013235B1 (en) | Manufacturing method of rainwater storage tank | |
KR101036177B1 (en) | Construction method of building structure using PPC composite method | |
KR102197107B1 (en) | Slab unit implanted with means for pressing pile and the method for carrying out the construction of the reinforced concrete column using it | |
KR200318935Y1 (en) | Precasting block for foundation of house | |
KR101576224B1 (en) | Prefabricated precast concrete girder for building construction | |
JPH11241311A (en) | Construction method of concrete bridge pier | |
CN216198677U (en) | Tower section, tower and wind power tower | |
CN214272076U (en) | Lattice beam | |
CN214833491U (en) | Prefabricated component of assembled building | |
KR200387408Y1 (en) | Knockdown basic-block | |
KR102012481B1 (en) | Connection structure of large-sized precast double-wall panel and middle accouplement | |
KR20090066562A (en) | Vertical prestressing precast retaining wall and its construction method | |
JPH10219708A (en) | Precast concrete block for continuous footing and continuous footing method by use thereof | |
KR20170051018A (en) | A twin wall structure using a PC panel and method for manufacturing of it | |
JPH11172964A (en) | Tower-shaped structure construction method | |
KR102682632B1 (en) | Permanant form panel for buliding foundation work | |
JP4902377B2 (en) | Basic structure of concrete block fence and its construction method | |
KR200398769Y1 (en) | prefabricated arched tunnel with cross section of T-type | |
CN219196044U (en) | Assembled prefabricated electric power well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
UA0108 | Application for utility model registration |
Comment text: Application for Utility Model Registration Patent event code: UA01011R08D Patent event date: 20030327 |
|
REGI | Registration of establishment | ||
UR0701 | Registration of establishment |
Patent event date: 20030624 Patent event code: UR07011E01D Comment text: Registration of Establishment |
|
UR1002 | Payment of registration fee |
Start annual number: 1 End annual number: 1 Payment date: 20030328 |
|
UG1601 | Publication of registration | ||
LAPS | Lapse due to unpaid annual fee | ||
UC1903 | Unpaid annual fee |