KR102213360B1
KR102213360B1 KR1020200066404A KR20200066404A KR102213360B1 KR 102213360 B1 KR102213360 B1 KR 102213360B1 KR 1020200066404 A KR1020200066404 A KR 1020200066404A KR 20200066404 A KR20200066404 A KR 20200066404A KR 102213360 B1 KR102213360 B1 KR 102213360B1
Authority
KR
South Korea
Prior art keywords
pipe
rain gutter
crosswalk
space
grating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020200066404A
Other languages
Korean (ko)
Inventor
함대용
최근용
Original Assignee
서울특별시 영등포구
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 서울특별시 영등포구 filed Critical 서울특별시 영등포구
Priority to KR1020200066404A priority Critical patent/KR102213360B1/en
Application granted granted Critical
Publication of KR102213360B1 publication Critical patent/KR102213360B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/0401Gullies for use in roads or pavements
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/06Gully gratings

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

본 발명은 횡단보도 환경개선 빗물받이 및 그 시공방법에 관한 것으로서, 상세하게는 횡단보도와 접하는 측구 부분의 공간에 유공관을 설치하고, 유공관에 골재를 채운 다음 골재 상면에 투수가 가능한 천연 자갈 그레이팅을 설치하여 횡단보도 물고임을 방지하고, 횡단 보도 양 끝단에 위치한 빗물받이로 유공관을 통해 침투된 빗물을 유도하여 원활한 배수가 이루어져 횡단 보도 통행자들에 쾌적한 횡단 보도 통행을 제공을 제공하도록 하는 횡단보도 환경개선 빗물받이 및 그 시공방법에 관한 것이다.The present invention relates to a rain gutter for improving the environment of a crosswalk and a construction method thereof, and in detail, a perforated pipe is installed in the space of the side opening in contact with the crosswalk, and after filling the aggregate in the perforated pipe, natural gravel grating capable of permeating the upper surface of the aggregate is provided. A crosswalk environment that prevents the crosswalk from getting caught in the crosswalk by installing it, and induces rainwater that has penetrated through the merit pipe through rain gutters located at both ends of the crosswalk to provide a comfortable crosswalk passage for pedestrians at the crosswalk. It relates to an improved rain gutter and its construction method.

Description

횡단보도 환경개선 빗물받이 및 그 시공방법{STREET INLET FOR IMPROVING ENVIRONMENT OF CROSSWALK AND CONSTRUCTING METHOD THEREOF}Crosswalk environment improvement rain gutter and its construction method {STREET INLET FOR IMPROVING ENVIRONMENT OF CROSSWALK AND CONSTRUCTING METHOD THEREOF}

본 발명은 횡단보도 환경개선 빗물받이 및 그 시공방법에 관한 것으로서, 상세하게는 횡단보도와 접하는 측구 부분의 공간에 유공관을 설치하고, 유공관에 골재를 채운 다음 골재 상면에 투수가 가능한 천연 자갈 그레이팅을 설치하여 횡단보도 물고임을 방지하고, 횡단보도 양 끝단에 위치한 빗물받이로 유공관을 통해 침투된 빗물을 유도하여 원활한 배수가 이루어져 횡단보도 통행자들에 쾌적한 횡단 보도 통행을 제공을 제공하도록 하는 횡단보도 환경개선 빗물받이 및 그 시공방법에 관한 것이다.The present invention relates to a rain gutter for improving the environment of a crosswalk and a construction method thereof, and in detail, a perforated pipe is installed in the space of the side opening in contact with the crosswalk, and after filling the aggregate in the perforated pipe, natural gravel grating capable of permeating the upper surface of the aggregate is provided. A crosswalk environment that prevents the crosswalk from getting caught in the crosswalk by installing it, and induces rainwater that has penetrated through the merit pipe through rain gutters located at both ends of the crosswalk to provide a comfortable crosswalk passage for pedestrians at the crosswalk. It relates to an improved rain gutter and its construction method.

도로의 노면에 흐르는 빗물은 도로의 가장자리에 설치되는 측구로 유입된 후 빗물받이를 통하여 차집시킨 후 하수관으로 신속하게 배출시킴으로써 도로교통의 안전을 확보하고 인접지의 침수가 발생하지 않도록 한다.Rainwater flowing on the road surface of the road flows into the side opening installed at the edge of the road, is blocked through a rain gutter, and then quickly discharged to the sewer pipe to ensure the safety of road traffic and prevent flooding of adjacent areas.

이러한 빗물받이는 도 1에 도시된 바와 같이, 전체적으로 육면체 형상으로 이루어진 본체부(10)와; 상기 본체부(10)의 상부에 덮여지는 그레이팅(20)과; 상기 본체부(10)의 측면이 개구됨과 동시에 연결관(30)이 접속된 구조이다.As shown in FIG. 1, such a rain gutter includes a main body 10 made in a hexahedral shape as a whole; A grating 20 covered on the upper part of the main body 10; It is a structure in which the side surface of the main body 10 is opened and the connection pipe 30 is connected.

특히, 상기 연결관(30)의 관저 높이보다 본체부(10)의 저면의 높이가 낮게 위치된 구조이다.In particular, it is a structure in which the height of the bottom of the main body 10 is lower than the height of the bottom of the connection pipe 30.

상기한 바와 같은 구성으로 이루어진 종래의 빗물받이(S)는 도로에 강수된 빗물이 그레이팅(20)을 통해 유입될 때 그레이팅(20) 주변의 도로에 기 퇴적된 토사와 함께 빗물이 유입되며, 이와 같이 그레이팅(20)을 통해 유입된 토사 및 빗물은 토사는 본체부(10)의 저면에 자연적으로 퇴적되고, 토사와 함께 유입된 빗물은 연결관(30)을 통해 하수도로 배수시키는 방식으로 빗물을 처리하였다.In the conventional rain gutter (S) configured as described above, when rainwater from the road is introduced through the grating (20), rainwater flows in together with the soil that has previously been deposited on the road around the grating (20). Likewise, the soil and rainwater flowing in through the grating 20 are naturally deposited on the bottom of the main body 10, and the rainwater flowing in together with the soil is drained into the sewer through the connection pipe 30. Processed.

통상적으로 도로의 빗물이나 지표수 등은 빗물받이로부터 연결관을 통해 하수관으로 유출된다.Typically, rainwater or surface water from a road is discharged from a rain gutter to a sewage pipe through a connection pipe.

유출되는 과정을 살펴보면 하수관에 빗물받이로부터의 빗물이 쉽게 흘러내릴 수 있도록 빗물받이보다 지표면으로부터 더 아래쪽에 위치하게 된다. 이에 따라, 빗물받이의 유출구와 하수관을 연결하는 연결관은 경사지게 연결된다.Looking at the discharge process, the rainwater from the rain gutter is located lower from the ground than the rain gutter so that rainwater from the rain gutter can easily flow down into the sewer pipe. Accordingly, the connection pipe connecting the outlet of the rain gutter and the sewer pipe is connected obliquely.

하지만, 종래에는 빗물받이의 유출구와 연결관의 단부를 연결하는 작업은 매우 까다롭고 어려운 작업이었다.However, in the related art, the work of connecting the outlet of the rain gutter and the end of the connecting pipe has been very difficult and difficult.

이러한 문제점을 해결하기 위하여 국내 등록특허 제10-1902536호인 각도조절가능한 자바라를 구비한 빗물받이가 개시되어 있다.In order to solve this problem, a rain gutter having an angle-adjustable bellows, which is Korean Patent No. 10-1902536, is disclosed.

상기 각도조절가능한 자바라를 구비한 빗물받이는 도 2에 도시된 바와 같이 빗물받이 본체(100)는 빗물유출구(113)의 내측부에 자바라결합부(120)가 매립되도록 구성된다.The rain gutter having the angle-adjustable bellows, as shown in FIG. 2, the rain gutter main body 100 is configured such that the bellows coupling portion 120 is embedded in the inner portion of the rainwater outlet 113.

자바라결합부(120)는 플라스틱과 같은 합성수지 재질로 이루어질 수 있다. 이 자바라결합부(120)는 빗물받이 본체(100)에 일체형으로 결합된 형태로 제작될 수 있으며, 일예로 발명의 빗물받이 본체(100)는 거푸집에 자바라결합부(120)를 인서트한 상태에서 콘크리트를 거푸집에 타설하여 양생시켜 줌으로써 자바라결합부(120)가 빗물받이 본체(100)에 일체형으로 구성될 수 있다.The bellows coupling part 120 may be made of a synthetic resin material such as plastic. The bellows coupling part 120 may be manufactured in a form integrally coupled to the rain gutter body 100, and as an example, the rain gutter body 100 of the invention is in a state in which the bellows coupling part 120 is inserted into the formwork. By pouring concrete into a form and curing it, the bellows coupling part 120 may be integrally configured with the rain gutter main body 100.

그러나, 상기 각도조절가능한 자바라를 구비한 빗물받이는 횡단보도 측구 부분에 설치시 장애인 통행의 편리성을 위하여 경계석을 측구높이와 같이 시공하고, 측구 부분은 작은 물고임에도 통행자에게 물이 튀는 것을 방지하기 위하여 정밀하게 시공하여야 하나, 긴 횡단 보도 길이와 측구 넓이를 콘크리트 시공함에 있어서 5㎜의 오차가 발생시 5㎜ 깊이는 측구 물고임이 발생하여 횡단 보도 통행자에게 물튀김 피해를 발생 시킬 만큼 초정밀 시공을 하여야 하는데, 초정밀 시공에 이르지 못하고 비만오면 횡단 보도 통행자에 통행에 불편을 주고 있는 현실이다.However, when the rain gutter with the angle-adjustable bellows is installed at the side of the crosswalk, the boundary stone is constructed at the same height as the side of the side for the convenience of passage of the handicapped, and the side of the side is a small reservoir to prevent water from splashing on the passerby. In order to do so, it must be precisely constructed, but when an error of 5 mm occurs in concrete construction of the length of the long crosswalk and the width of the sideways, the 5mm depth is highly precise enough to cause water splash damage to pedestrians at the crosswalk. It should be done, but it is a reality that does not reach ultra-precise construction and causes inconvenience to pedestrians on the crosswalk when it is obese.

국내 등록특허 제10-1902536호Domestic registered patent No. 10-1902536

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 횡단보도와 접하는 측구 부분의 공간에 유공관을 설치하고, 유공관에 골재를 채운 다음 골재 상면에 투수가 가능한 천연 자갈 그레이팅을 설치하여 횡단보도 물고임을 방지하고, 횡단 보도 양 끝단에 위치한 빗물받이로 유공관을 통해 침투된 빗물을 유도하여 원활한 배수가 이루어져 횡단보도 통행자들에 쾌적한 횡단보도 통행을 제공하도록 하는 횡단보도 환경개선 빗물받이 및 그 시공방법을 제공하는데 그 목적이 있다.The present invention is to solve the above problems, by installing a perforated pipe in the space of the side opening in contact with the crosswalk, filling the aggregate in the perforated pipe, and then installing a permeable natural gravel grating on the upper surface of the aggregate to prevent biting of the crosswalk. Also, rain gutters located at both ends of the crosswalk guide rainwater that has penetrated through the merit pipe to facilitate drainage, and provide a crosswalk environment improvement rain gutter and its construction method to provide comfortable crosswalk passage to pedestrians at the crosswalk. It has its purpose.

또한, 본 발명은 굴착에 의해 노출된 하수관에 합성수지 엘보관을 연결시킨 상태에서 엘보관이 설치된 굴착 공간 내부에 초속경 몰탈을 타설하여 엘보관의 하부를 고정시킨 상태에서 프리캐스트로 제작된 빗물받이를 엘보관의 상부에 삽입 설치한 다음, 빗물받이와 굴착면 사이의 굴착 공간에 초속경 몰탈을 타설하여 단시간이 급속 시공이 가능함으로써 교통 체증 발생, 소음 등으로 민원 발생을 미연에 방지하도록 하는 횡단보도 환경개선 빗물받이 및 그 시공방법을 제공하는데 그 목적이 있다.In addition, the present invention is a rain gutter made of precast in a state in which a synthetic resin elbow pipe is connected to a sewage pipe exposed by excavation and an ultra-fast diameter mortar is placed inside the excavation space in which the elbow pipe is installed to fix the lower part of the elbow pipe. The cross section is designed to prevent civil complaints due to traffic congestion and noise by placing an ultra-fast diameter mortar in the excavation space between the rain gutter and the excavation surface after inserting and installing it into the upper part of the elbow pipe. Its purpose is to provide a rain gutter and its construction method to improve the sidewalk environment.

또한, 본 발명은 엘보관 중간에 주름관을 열융착하여 일체화시키고, 주름관 내부에 퇴적 방지 튜브를 설치함으로써 각도에 상관없이 엘보관과 하수관의 연결 설치가 용이하게 이루어지고, 주름관 내부에 퇴적물이 쌓이는 것을 방지하도록 하는 횡단보도 환경개선 빗물받이 및 그 시공방법을 제공하는데 다른 목적이 있다.In addition, the present invention integrates the corrugated pipe by heat fusion in the middle of the elbow pipe, and by installing a deposition preventing tube inside the corrugated pipe, it is easy to connect and install the elbow pipe and the sewage pipe regardless of the angle, and to prevent deposits from accumulating inside the corrugated pipe. There is another purpose to provide a rain gutter and a construction method for improving the environment of crosswalks to prevent.

또, 본 발명은 엘보관의 상부에 높이 조절관을 나사 결합하여 높이 조절관으로 빗물받이의 높이를 조절할 수 있어 시공성과 작업성을 향상시킬 수 있고, 작업 인원도 감축하여 공사 비용을 절감할 수 있도록 하는 횡단보도 환경개선 빗물받이 및 그 시공방법을 제공하는데 또 다른 목적이 있다.In addition, in the present invention, the height of the rain gutter can be adjusted with the height adjustment pipe by screwing the height adjustment pipe on the upper part of the elbow pipe, thereby improving workability and workability, and reducing the number of workforces to reduce construction costs. Another purpose is to provide a rain gutter for improving the environment of a crosswalk and its construction method.

상기와 같은 목적을 달성하기 위한 본 발명의 특징은,Features of the present invention for achieving the above object,

횡단보도에 설치되는 빗물받이에 있어서, 도로 경계석과 횡단보도 사이의 측구에 형성된 공간에 매립 설치되는 유공관과; 상기 측구에서 상기 유공관의 양단에 형성된 공간에 매립 설치되어 상기 유공관과 각각 연결되고, 하수관거와 연결되는 빗물받이 본체와; 상기 유공관이 설치된 공간에 충전되는 골재층과; 상기 골재층의 상면에 고정 설치되는 그레이팅 거치 프레임; 및 상기 그레이팅 거치 프레임에 거치되는 그레이팅을 포함하는 것을 특징으로 한다.A rain gutter installed on a crosswalk, comprising: a perforated pipe embedded in a space formed at a side opening between a road boundary and a crosswalk; A rain gutter main body which is embedded in the space formed at both ends of the perforated pipe at the side port and connected to the perforated pipes, respectively, and connected to a sewage pipe; An aggregate layer filled in the space in which the perforated pipes are installed; A grating mounting frame fixedly installed on the upper surface of the aggregate layer; And a grating mounted on the grating mounting frame.

여기에서, 상기 횡단보도 환경개선 빗물받이는 상기 유공관의 양단에 형성된 상기 측구의 공간에서 도로에 매립된 하수관과 연결되는 엘보관과; 상기 엘보관의 수평부와 하수관 사이에 설치되어 각도를 조절하는 각도 조절관; 및 상기 엘보관의 수직부에 설치되는 높이 조절관을 더 포함한다.Here, the crosswalk environment improvement rain gutter is an elbow pipe connected to a sewage pipe embedded in the road in the space of the side opening formed at both ends of the perforated pipe; An angle adjustment pipe installed between the horizontal portion of the elbow pipe and the sewer pipe to adjust the angle; And a height adjustment pipe installed on the vertical portion of the elbow pipe.

여기에서 또한, 상기 유공관은 외측면에 부직포가 감싸진다.Here, the perforated pipe is wrapped with a nonwoven fabric on the outer surface.

여기에서 또, 상기 빗물받이 본체는 빗물이 유입되는 공간을 가지도록 상단이 개구된 박스 형태로 형성되고, 측면에 상기 유공관이 삽입되는 제 1삽입구가 형성되고, 저면 중앙부에서 공간과 연통되도록 상기 높이 조절관이 삽입되는 제 2삽입구가 형성되며, 상기 삽입구로 우수가 수집되도록 상기 공간 바닥이 상기 삽입구 측으로 하향 경사를 가진다.Here, the rain gutter main body is formed in a box shape with an open top to have a space through which rainwater flows in, and a first insertion port into which the perforated pipe is inserted is formed on the side, and the height is in communication with the space at the center of the bottom surface. A second insertion port into which the control tube is inserted is formed, and the floor of the space has a downward slope toward the insertion port so that rainwater is collected through the insertion port.

여기에서 또, 상기 빗물받이 본체는 초경속 몰탈의 타설시 일체화되도록 측면에 연결핀이 구비된다.Here, the rain gutter main body is provided with a connection pin on the side to be integrated during the pouring of the ultra-light mortar.

여기에서 또, 상기 그레이팅 거치 프레임은 저면 테두리에 지면을 향하도록 수직으로 돌출되어 상기 골재층을 관통하여 지층에 삽입 고정되는 복수의 고정핀이 구비된다.Here, the grating mounting frame is provided with a plurality of fixing pins which are vertically protruded from the bottom edge to face the ground and penetrated through the aggregate layer to be inserted and fixed in the stratum.

여기에서 또, 상기 그레이팅 거치 프레임은 곡선 구간에서 레이저로 절단하여 현장에서 곡선 구간에 맞게 용접하여 설치한다.Here, the grating mounting frame is installed by cutting with a laser in the curved section and welding to fit the curved section at the site.

여기에서 또, 상기 그레이팅은 상면이 개방되고, 저면에 격자 형태의 받침대가 형성되는 사각 프레임 형태로 형성되는 프레임 본체와; 투수 시멘트로 제작되고, 내부에 철근망이 삽입되어 직육면체 형태로 제작되어 상기 프레임 본체 내부에 삽입 설치되는 투수 시멘트 블록; 및 상기 투수 시멘트 블록의 상면에 접합되는 천연 자갈로 구성된다.Here, the grating includes a frame body formed in the shape of a square frame in which an upper surface is opened and a grid-shaped pedestal is formed on a bottom surface; A permeable cement block made of permeable cement, a reinforcing bar mesh inserted therein, and manufactured in a rectangular parallelepiped shape to be inserted and installed inside the frame body; And natural gravel bonded to the upper surface of the permeable cement block.

여기에서 또, 상기 그레이팅은 상기 투수 시멘트 블록 측면에 아이 너트가 매립되고, 상기 프레임 본체 측면에 상기 아이 너트에 체결되는 접시 머리 볼트가 관통되며 수납되는 볼트홀이 구비되며, 상기 투수 시멘트 블록이 거푸집에서 상기 철근망이 노출되는 높이로 투수 시멘트 몰탈이 1차로 충전되어 제작되고, 양생이 완료되면, 상기 철근망을 덮는 높이로 2차로 투수 시멘트 몰탈이 2차로 충전된 다음 상면을 상기 천연 자갈로 덮어 일체화시킨다.Here, in the grating, an eye nut is embedded in the side of the permeable cement block, and a bolt hole through which a countersunk head bolt fastened to the eye nut is passed through the side of the frame body is provided, and the permeable cement block is formed. The permeable cement mortar is first filled to the height at which the reinforcing bar network is exposed, and when curing is completed, the permeable cement mortar is secondarily filled to the height to cover the reinforcing bar net, and then the upper surface is covered with the natural gravel. Integrate.

여기에서 또, 상기 천연 자갈은 접착제를 표면에 묻힌 상태에서 거푸집 내에 일정 높이로 덮은 상태에서 상기 천연 자갈 상면에 저면에 이형지가 부착된 거푸집 덮개를 놓고, 압력을 가한 상태로 경화시킨다.Here, the natural gravel is cured with a pressure applied by placing an adhesive on the surface and covering it with a certain height in the formwork, placing a formwork cover with a release paper attached to the bottom on the upper surface of the natural gravel.

여기에서 또, 상기 각도 조절관은 상기 하수관의 각도에 따라 용이하게 각도가 조절되도록 상기 엘보관과 밴드 클램프에 의해 연결되는 연성 재질의 연결관과, 금속 재질로 형성되어 일단이 상기 연결관에 리벳 결합되고, 타단이 상기 하수관에 삽입되는 금속관으로 이루어진다.Here, the angle adjustment pipe is formed of a flexible material connecting pipe connected by the elbow pipe and a band clamp so that the angle can be easily adjusted according to the angle of the sewer pipe, and one end is formed of a metal material, so that one end is riveted to the connection pipe. It is combined, and the other end is made of a metal pipe inserted into the sewer pipe.

여기에서 또, 상기 높이 조절관은 상기 엘보관의 수직부에 나사 결합되는 동일 지름의 높이 조절관을 구비한다.Here, the height adjustment pipe is provided with a height adjustment pipe of the same diameter that is screwed to the vertical portion of the elbow pipe.

본 발명의 다른 특징은,Another feature of the present invention,

상기의 횡단보도 환경개선 빗물받이 시공방법에 있어서, 도로 경계석과 횡단보도 사이의 측구에 유공관과, 빗물받이 본체가 매립 설치되는 공간을 형성하는 공간 형성 공정과; 상기 유공관이 설치되는 공간 바닥에 유공관을 매립 설치하는 유공관 설치 공정과; 상기 유공관이 설치된 공간에 골재를 충전하여 골재층을 형성하는 골재층 형성 공정과; 상기 골재층의 상면에 그레이팅 거치 프레임을 고정시키고, 상기 그레이팅 거치 프레임의 외측에 초속경 몰탈을 타설하여 양생하는 그레이팅 거치 프레임 설치 공정과; 상기 그레이팅 거치 프레임에 그레이팅을 거치시키는 그레이팅 설치 공정과; 상기 빗물받이 본체가 설치되는 공간에서 하수관에 각도 조절관이 결합된 엘보관을 결합하고, 상기 각도 조절관을 이용하여 각도를 조절하는 엘보관 결합 공정과; 상기 엘보관을 고정시키도록 빗물받이 본체가 설치되는 공간 내부에 건콘크리트를 충전하여 다짐하는 기초 다짐 공정과; 상기 높이 조절관의 높이를 조절해서 그레이팅이 설치된 빗물받이 본체를 상기 높이 조절관의 상단에 거치시키는 빗물받이 설치 공정; 및 상기 빗물받이 본체의 외측과 빗물받이가 설치되는 공간 사이에 초속경 몰탈을 타설하여 양생하는 타설 공정으로 이루어지는 것을 특징으로 한다.In the crosswalk environment improvement rain gutter construction method, comprising: a space forming process of forming a space in which a perforated pipe and a rain gutter main body are embedded and installed at a side opening between a road boundary stone and a crosswalk; A perforated pipe installation process of embedding and installing a perforated pipe in the floor of the space where the perforated pipe is installed; An aggregate layer forming step of forming an aggregate layer by filling an aggregate in the space where the perforated pipe is installed; A grating mounting frame installation step of fixing the grating mounting frame on the upper surface of the aggregate layer and placing an ultra-fast diameter mortar outside the grating mounting frame for curing; A grating installation process of mounting a grating on the grating mounting frame; An elbow pipe coupling step of coupling an elbow pipe to which an angle adjustment pipe is coupled to a sewer pipe in a space in which the rain gutter body is installed, and adjusting an angle using the angle adjustment pipe; A basic compaction step of filling and compacting dry concrete in a space in which a rain gutter body is installed to fix the elbow pipe; A rain gutter installation process of adjusting the height of the height control tube to mount the rain gutter body on which the grating is installed on the upper end of the height control tube; And it characterized in that it consists of a pouring process of curing by placing an ultra-fast mortar between the outside of the rain gutter body and the space in which the rain gutter is installed.

여기에서, 상기 엘보관 결합 공정은 상기 엘보관의 상단부가 빗물받이가 설치되는 공간에서 수직 상태를 유지하도록 스페이서를 이용하여 고정한다.Here, in the elbow pipe coupling process, the upper end of the elbow pipe is fixed using a spacer to maintain a vertical state in a space in which a rain gutter is installed.

여기에서 또한, 상기 스페이서는 상기 엘보관이 삽입되는 링 형태의 스페이서 본체와; 상기 엘보관을 상기 스페이서 본체에 고정시키도록 상기 스페이서 본체에 방사상으로 설치되는 고정 볼트; 및 상기 스페이서 본체를 빗물받이가 설치되는 공간에 고정시키도록 상기 스페이서 본체에 방사상으로 설치되고, 길이가 조정되는 지지대로 이루어진다.Here, also, the spacer includes a ring-shaped spacer body into which the elbow tube is inserted; A fixing bolt radially installed on the spacer body to fix the elbow pipe to the spacer body; And a support that is radially installed on the spacer body to fix the spacer body in the space where the rain gutter is installed, and the length is adjusted.

여기에서 또, 상기 그레이팅은 도로 경계석의 높이와 동일하거나 더 낮게 형성된다.Here again, the grating is formed equal to or lower than the height of the road curb.

상기와 같이 구성되는 본 발명인 횡단보도 환경개선 빗물받이 및 그 시공방법에 따르면, 횡단보도와 접하는 측구 부분의 공간에 유공관을 설치하고, 유공관에 골재를 채운 다음 골재 상면에 투수가 가능한 천연 자갈 그레이팅을 설치하여 횡단보도 물고임을 방지하고, 횡단 보도 양 끝단에 위치한 빗물받이로 유공관을 통해 침투된 빗물을 유도하여 원활한 배수가 이루어져 횡단 보도 통행자들에 쾌적한 횡단 보도 통행을 제공할 수 있다.According to the present inventors' crosswalk environment improvement rain gutter and its construction method configured as described above, a perforated pipe is installed in the space of the side opening in contact with the crosswalk, and after filling the aggregate in the perforated pipe, natural gravel grating that can be permeable is applied to the upper surface of the aggregate. By installing it, it is possible to prevent crosswalks from getting into the crosswalk, and to induce rainwater that has penetrated through the merit pipe through rain gutters located at both ends of the crosswalk, so that smooth drainage can be provided, thereby providing comfortable crosswalk passage for pedestrians on the crosswalk.

또한, 본 발명에 따르면 굴착에 의해 노출된 하수관에 합성수지 엘보관을 연결시킨 상태에서 엘보관이 설치된 굴착 공간 내부에 초속경 몰탈을 타설하여 엘보관의 하부를 고정시킨 상태에서 프리캐스트로 제작된 빗물받이를 엘보관의 상부에 삽입 설치한 다음, 빗물받이와 굴착면 사이의 굴착 공간에 초속경 몰탈을 타설하여 단시간이 급속 시공이 가능함으로써 교통 체증 발생, 소음 등으로 민원 발생을 미연에 방지할 수 있다.In addition, according to the present invention, in a state in which a synthetic resin elbow pipe is connected to a sewage pipe exposed by excavation, an ultra-fast diameter mortar is placed inside the excavation space in which the elbow pipe is installed, and the lower portion of the elbow pipe is fixed, After inserting and installing the receiver in the upper part of the elbow pipe, the ultra-fast mortar is placed in the excavation space between the rain gutter and the excavation surface to allow rapid construction in a short time, thereby preventing civil complaints due to traffic jams and noise. have.

또한, 본 발명에 따르면 엘보관 중간에 주름관을 열융착하여 일체화시키고, 주름관 내부에 퇴적 방지 튜브를 설치함으로써 각도에 상관없이 엘보관과 하수관의 연결 설치가 용이하게 이루어지고, 주름관 내부에 퇴적물이 쌓이는 것을 방지할 수 있다.In addition, according to the present invention, the corrugated pipe is integrated by heat fusion in the middle of the elbow pipe, and by installing the anti-deposition tube inside the corrugated pipe, the connection between the elbow pipe and the sewer pipe is made easy, regardless of angle, and sediment is accumulated inside the corrugated pipe. Can be prevented.

또, 본 발명에 따르면 엘보관의 상부에 높이 조절관을 나사 결합하여 높이 조절관으로 빗물받이의 높이를 조절할 수 있어 시공성과 작업성을 향상시킬 수 있고, 작업 인원도 감축하여 공사 비용을 절감할 수 있다.In addition, according to the present invention, the height of the rain gutter can be adjusted with the height adjustment pipe by screwing the height adjustment pipe on the upper part of the elbow pipe, thereby improving workability and workability, and reducing the number of working people to reduce construction costs. I can.

도 1은 일반적인 빗물받이의 구성을 나타낸 도면이다.
도 2는 종래의 각도조절가능한 자바라를 구비한 빗물받이의 구성을 나타낸 도면이다.
도 3은 본 발명에 따른 횡단보도 환경개선 빗물받이의 구성을 나타낸 사시도이다.
도 4는 도 3의 A-A 부분 단면도이다.
도 5는 도 3의 B-B 부분 단면도이다.
도 6은 본 발명에 따른 횡단보도 환경개선 빗물받이중 그레이팅의 구성을 나타낸 사시도이다.
도 7은 도 6의 C-C 부분 단면도이다.
도 8은 도 6의 부분 분해 사시도이다.
도 9는 본 발명에 따른 횡단보도 환경개선 빗물받이 시공방법을 설명하기 위한 공정도이다.
도 10은 본 발명에 따른 본 발명에 따른 횡단보도 환경개선 빗물받이 시공방법에 적용된 스페이서의 구성을 나타낸 사시도이다.
도 11a 내지 도 11i는 본 발명에 따른 급속 시공이 가능한 빗물받이를 이용한 시공방법의 각 공정을 설명하기 위한 설명도이다.
1 is a view showing the configuration of a general rain gutter.
2 is a view showing the configuration of a rain gutter having a conventional angle adjustable bellows.
Figure 3 is a perspective view showing the configuration of the crosswalk environment improvement rain gutter according to the present invention.
4 is a partial cross-sectional view taken along AA of FIG. 3.
5 is a cross-sectional view of a portion BB of FIG. 3.
6 is a perspective view showing the configuration of a grating among rain gutters for improving the crosswalk environment according to the present invention.
7 is a partial cross-sectional view of CC of FIG. 6.
8 is a partially exploded perspective view of FIG. 6.
9 is a process diagram for explaining a method of constructing a rain gutter for improving the crosswalk environment according to the present invention.
10 is a perspective view showing the configuration of a spacer applied to the crosswalk environment improvement rain gutter construction method according to the present invention according to the present invention.
11A to 11I are explanatory diagrams for explaining each process of a construction method using a rain gutter capable of rapid construction according to the present invention.

이하, 본 발명에 따른 횡단보도 환경개선 빗물받이의 구성을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, a configuration of a rain gutter for improving the environment of a crosswalk according to the present invention will be described in detail with reference to the accompanying drawings.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, a detailed description thereof will be omitted. In addition, terms to be described later are terms defined in consideration of functions in the present invention, which may vary depending on the intention or custom of users or operators. Therefore, the definition should be made based on the contents throughout this specification.

도 3은 본 발명에 따른 횡단보도 환경개선 빗물받이의 구성을 나타낸 사시도이고, 도 4는 도 3의 A-A 부분 단면도이며, 도 5는 도 3의 B-B 부분 단면도이고, 도 6은 본 발명에 따른 횡단보도 환경개선 빗물받이중 그레이팅의 구성을 나타낸 사시도이며, 도 7은 도 6의 C-C 부분 단면도이고, 도 8은 도 6의 부분 분해 사시도이다.Figure 3 is a perspective view showing the configuration of the crosswalk environment improvement rain gutter according to the present invention, Figure 4 is a partial cross-sectional view of Figure 3 AA, Figure 5 is a partial cross-sectional view BB of Figure 3, Figure 6 is a cross-sectional view according to the present invention It is a perspective view showing the configuration of the grating of the sidewalk environment improvement rain gutter, Figure 7 is a partial cross-sectional view CC of Figure 6, Figure 8 is a partial exploded perspective view of Figure 6.

도 3 내지 도 8을 참조하면, 본 발명에 따른 횡단보도 환경개선 빗물받이(200)는 유공관(210)과, 빗물받이 본체(220)와, 골재층(230)과, 그레이팅 거치 프레임(240)과, 그레이팅(250)과, 엘보관(260)과, 각도 조절관(270) 및 높이 조절관(280)으로 구성된다.3 to 8, the crosswalk environment improvement rain gutter 200 according to the present invention includes a perforated pipe 210, a rain gutter body 220, an aggregate layer 230, and a grating mounting frame 240. And, it is composed of a grating 250, an elbow pipe 260, an angle adjustment pipe 270 and a height adjustment pipe 280.

먼저, 유공관(210)은 PE, PVC와 같은 합성수지재질 또는 금속재질로 외측에 복수의 유입홀(211)이 형성되고, 도로 경계석(1)과 횡단보도(2) 사이의 측구(3)에 형성된 공간에 매립 설치된다. 이때, 유공관(210)은 내부로 이물질이 유입되는 것을 방지하도록 외측면에 부직포(213)가 감싸지는 것이 바람직하다.First, the perforated pipe 210 is made of a synthetic resin material such as PE, PVC or a metal material, and a plurality of inlet holes 211 are formed on the outside, and formed in the side opening 3 between the road curb (1) and the crosswalk (2). It is embedded in the space. At this time, it is preferable that the perforated pipe 210 is wrapped with a nonwoven fabric 213 on the outer surface to prevent foreign substances from flowing into the inside.

그리고, 빗물받이 본체(220)는 프리캐스트로 제작되어 엘보관(260)의 상단에 거치되는 데, 빗물이 유입되는 공간을 가지도록 박스 형태로 형성되고, 측면에 유공관(210)이 삽입되는 제 1삽입구(221)가 형성되고, 저면 중앙부에서 공간과 연통되도록 높이 조절관(280)이 삽입되는 제 2삽입구(223)가 형성되며, 제 2삽입구(223)로 우수가 수집되도록 공간 바닥이 제 2삽입구(221) 측으로 하향 경사면(225)을 가진다. 이때, 빗물받이 본체(220)는 엘보관(260)에 거치된 상태에서 빗물받이 본체(220)가 설치되는 공간에 다시 채워진 초속경 몰탈(M)과 일체화되도록 측면에 연결키(227)가 구비된다.In addition, the rain gutter main body 220 is made of a precast and mounted on the upper end of the elbow pipe 260. It is formed in a box shape to have a space through which rainwater flows in, and the perforated pipe 210 is inserted into the side surface. A first insertion port 221 is formed, a second insertion port 223 into which the height adjustment pipe 280 is inserted so as to communicate with the space at the center of the bottom is formed, and the space floor is formed so that rainwater is collected through the second insertion port 223. 2. It has a downward inclined surface 225 toward the insertion port 221. At this time, the rain gutter main body 220 is provided with a connection key 227 on the side so as to be integrated with the super fast-diameter mortar (M) refilled in the space where the rain gutter main body 220 is installed while being mounted on the elbow pipe 260 do.

또한, 골재층(230)은 유공관(210)이 설치된 공간에 일정 높이로 충전된다.In addition, the aggregate layer 230 is filled to a predetermined height in the space in which the perforated pipe 210 is installed.

또, 그레이팅 거치 프레임(240)은 골재층(230)의 상면에 고정 설치되는 데, 저면 테두리에 지면을 향하도록 수직으로 돌출되어 골재층(230)을 관통하여 지층에 삽입 고정되는 복수의 고정핀(241)이 구비된다. 이때, 그레이팅 거치 프레임(240)은 곡선 구간, 즉 교차로에서와 같이 인접하여 연속 설치되는 경우 레이저로 절단하여 현장에서 곡선 구간에 맞게 용접하여 설치한다.In addition, the grating mounting frame 240 is fixedly installed on the upper surface of the aggregate layer 230, a plurality of fixing pins which are vertically protruded toward the ground at the bottom edge and penetrated through the aggregate layer 230 to be inserted and fixed in the stratum. 241 is provided. At this time, when the grating mounting frame 240 is continuously installed adjacent to each other, such as in a curved section, that is, at an intersection, it is cut with a laser and welded to fit the curved section at the site and installed.

이어서, 그레이팅(250)은 도 5 내지 도 8에 도시된 바와 같이 프레임 본체(251)와, 투수 시멘트 블록(253) 및 천연 자갈(255)로 구성된다.Subsequently, the grating 250 is composed of a frame body 251, a permeable cement block 253, and natural gravel 255 as shown in FIGS. 5 to 8.

프레임 본체(251)는 알루미늄이나 강재와 같은 금속 재질로 상면이 개방되고, 저면에 격자 형태의 받침대(251a)가 형성되는 사각 프레임 형태로 형성된다. 이때, 프레임 본체(251)는 측면에 아이 너트(257)에 체결되는 접시 머리 볼트(259)가 관통되며 수납되는 볼트홀(251b)이 구비되는 것이 바람직하다.The frame body 251 is made of a metal material such as aluminum or steel, and is formed in the shape of a square frame in which an upper surface is opened and a grid-shaped pedestal 251a is formed on the lower surface. At this time, the frame body 251 is preferably provided with a bolt hole 251b through which the countersunk bolt 259 fastened to the eye nut 257 passes through the side surface of the frame body 251.

투수 시멘트 블록(253)은 투수 시멘트로 제작되고, 내부에 철근망(253a)이 삽입되어 직육면체 형태로 제작되어 프레임 본체(251) 내부에 삽입 설치된다. 이때, 투수 시멘트 블록(253)은 측면에 아이 너트(257)가 매립되는 바람직하다. 또한, 투수 시멘트 블록(253)은 거푸집(미도시)에서 철근망(253a)이 노출되는 높이로 투수 시멘트 몰탈이 1차로 충전되어 제작되고, 양생이 완료되면, 철근망(253a)을 덮는 높이로 2차로 투수 시멘트 몰탈이 2차로 충전된 다음 상면을 천연 자갈(255)로 덮어 일체화시킨다.The water-permeable cement block 253 is made of water-permeable cement, and a reinforcing bar network 253a is inserted therein to form a rectangular parallelepiped, and is inserted and installed in the frame body 251. At this time, the permeable cement block 253 is preferably an eye nut 257 embedded in the side. In addition, the permeable cement block 253 is manufactured by first filling the permeable cement mortar to the height at which the reinforcing bar net 253a is exposed in the formwork (not shown), and when curing is completed, it is at a height covering the reinforcing bar net 253a. Secondly, the water-permeable cement mortar is secondarily filled, and then the upper surface is covered with natural gravel 255 to be integrated.

천연 자갈(255)은 투수 시멘트 블록(253)의 상면에 접합되는 데, 접착제를 표면에 묻힌 상태에서 거푸집 내에 일정 높이로 덮은 상태에서 상면에 이형지가 저면에 부착된 거푸집 덮개(미도시)를 놓고, 압력을 가한 상태로 경화시킨다. 이때, 천연 자갈(255)이 외부 충격에 의해 손쉽게 이탈되는 것을 방지하도록 천연 자갈(255)의 상면에 복수의 투수공이 형성된 합성수지 재질의 시트(미도시)를 부착하고, 이를 고주파를 이용하여 열융착시켜 일체화시킬 수도 있다.The natural gravel 255 is bonded to the upper surface of the water permeable cement block 253. Place a cover (not shown) on the upper surface with a release paper attached to the lower surface with an adhesive on the surface and covered with a certain height in the formwork. , Cured under pressure. At this time, a sheet (not shown) made of synthetic resin having a plurality of perforated holes is attached to the upper surface of the natural gravel 255 to prevent the natural gravel 255 from being easily separated by external impact, and heat-sealing it using high frequency. It can also be integrated.

계속해서, 엘보관(260)은 PE와 같이 합성수지 재질로 도로의 측구에 형성된 빗물받이가 설치되는 공간에서 도로에 매립된 하수관(P)과 연결되고, 빗물받이가 설치되는 공간에 채워진 건콘크리트와 초속경 몰탈(M)에 의해 수직으로 고정된다.Subsequently, the elbow pipe 260 is connected to the sewer pipe (P) buried in the road in the space where the rain gutter formed at the side of the road made of synthetic resin such as PE is installed, and the dry concrete filled in the space where the rain gutter is installed. It is fixed vertically by the super fast diameter mortar (M).

그리고, 각도 조절관(270)는 하수관(P)의 각도에 따라 용이하게 각도가 조절되도록 엘보관(210)과 밴드 클램프에 의해 연결되는 연성 재질의 연결관(271)과, 금속 재질로 형성되어 일단이 연결관(271)에 리벳 결합되고, 타단이 하수관(P)에 삽입되는 금속관(273)로 구성된다.In addition, the angle adjustment pipe 270 is formed of a flexible material connection pipe 271 connected by an elbow pipe 210 and a band clamp so that the angle can be easily adjusted according to the angle of the sewer pipe (P), One end is riveted to the connection pipe 271, and the other end is composed of a metal pipe 273 inserted into the sewer pipe (P).

또한, 높이 조절관(280)은 엘보관(260)과 동일 지름을 가지고, 엘보관(260)의 수직부에 나사 결합된다.In addition, the height adjustment pipe 280 has the same diameter as the elbow pipe 260 and is screwed to the vertical portion of the elbow pipe 260.

이하, 본 발명에 따른 횡단보도 환경개선 빗물받이 시공방법을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, a method of constructing a rain gutter for improving the environment of a crosswalk according to the present invention will be described in detail with reference to the accompanying drawings.

도 9는 본 발명에 따른 횡단보도 환경개선 빗물받이 시공방법을 설명하기 위한 공정도이고, 도 10은 본 발명에 따른 본 발명에 따른 횡단보도 환경개선 빗물받이 시공방법에 적용된 스페이서의 구성을 나타낸 사시도이며, 도 11a 내지 도 11i는 본 발명에 따른 급속 시공이 가능한 빗물받이를 이용한 시공방법의 각 공정을 설명하기 위한 설명도이다.9 is a process chart for explaining a crosswalk environment improvement rain gutter construction method according to the present invention, FIG. 10 is a perspective view showing the configuration of a spacer applied to the crosswalk environment improvement rain gutter construction method according to the present invention 11A to 11I are explanatory diagrams for explaining each process of a construction method using a rain gutter capable of rapid construction according to the present invention.

도 9 내지 도 11i를 참조하면, 본 발명에 따른 횡단보도 환경개선 빗물받이 시공방법은 공간 형성 공정(S10)과, 유공관 설치 공정(S20)과, 골재층 형성 공정(S30)과, 그레이팅 거치 프레임 설치 공정(S40)과, 그레이팅 설치 공정(S50)과, 엘보관 결합 공정(S60)과, 다짐 공정(S70)과, 빗물받이 본체 설치 공정(S80) 및 타설 공정(S90)으로 이루어진다.9 to 11I, the crosswalk environment improvement rain gutter construction method according to the present invention includes a space formation process (S10), a perforated pipe installation process (S20), an aggregate layer formation process (S30), and a grating mounting frame. It consists of an installation process (S40), a grating installation process (S50), an elbow pipe coupling process (S60), a compaction process (S70), a rain gutter body installation process (S80), and a pouring process (S90).

《공간 형성 공정-S10》<< space formation process-S10 >>

먼저, 도 11a에 도시된 바와 같이 도로 경계석(1)과 횡단보도(2) 사이의 측구(3)에 유공관(210)과, 빗물받이 본체(220)가 매립 설치되는 공간을 형성한다.First, as shown in FIG. 11A, a space in which the perforated pipe 210 and the rain gutter main body 220 are embedded and installed in the side opening 3 between the road boundary 1 and the crosswalk 2 is formed.

《유공관 형성 공정-S20》《Mechanism pipe formation process-S20》

그리고, 도 11b에 도시된 바와 같이 유공관(210)이 설치되는 공간 바닥에 유공관(210)을 매립 설치한다. 이때, 공간 바닥에 유공관(210)이 안착되는 홈을 기형성하는 것이 바람직하다.In addition, as shown in FIG. 11B, the perforated pipe 210 is embedded in the space where the perforated pipe 210 is installed. At this time, it is preferable to form a groove in the space floor in which the perforated pipe 210 is seated.

《골재층 형성 공정-S30》《Aggregate Layer Formation Process-S30》

유공관(210) 설치가 완료되면, 도 11c에 도시된 바와 같이 유공관(210)이 설치된 공간에 골재를 충전하여 골재층(230)을 형성한다.When the installation of the perforated pipe 210 is completed, the aggregate layer 230 is formed by filling the aggregate in the space in which the perforated pipe 210 is installed, as shown in FIG. 11C.

《그레이팅 거치 프레임 설치 공정-S40》《Grating mounting frame installation process-S40》

골재층(230)의 형성이 완료되면, 도 11d에 도시된 바와 같이 골재층(230)의 상면에 그레이팅 거치 프레임(240)을 고정시키고, 그레이팅 거치 프레임(240)의 외측에 초속경 몰탈(M)을 타설하여 양생한다.When the formation of the aggregate layer 230 is completed, the grating mounting frame 240 is fixed to the upper surface of the aggregate layer 230 as shown in FIG. 11D, and a super fast diameter mortar (M) outside the grating mounting frame 240 ) Is poured to cure.

《그레이팅 설치 공정-S50》《Grating installation process-S50》

이어서, 도 11e에 도시된 바와 같이 그레이팅 거치 프레임(240)에 그레이팅(250)을 거치시킨다.Subsequently, the grating 250 is mounted on the grating mounting frame 240 as shown in FIG. 11E.

《엘보관 결합 공정-S60》《Elbow pipe joining process-S60》

그레이팅(250)의 설치가 완료되면, 도 11f에 도시된 바와 같이 도로의 측구(3)에 형성된 빗물받이가 설치되는 공간을 통해 하수관(P)에 엘보관(260)이 결합된 각도 조절관(270)을 결합하고, 각도 조절관(270)의 연결관(271)을 이용하여 각도를 조절한다. 이때, 엘보관(260)의 상단부가 빗물받이 본체(220)가 설치되는 공간에서 수직 상태를 유지하도록 스페이서(290)를 이용하여 고정하는 데, 스페이서(290)는 도 10에 도시된 바와 같이 엘보관(260)이 삽입되는 링 형태의 스페이서 본체(291)와, 엘보관(260)을 스페이서 본체(291)에 고정시키도록 스페이서 본체(291)에 방사상으로 설치되는 고정 볼트(293) 및 스페이서 본체(291)를 빗물받이 본체(220)가 설치되는 공간에 고정시키도록 스페이서 본체(291)에 방사상으로 설치되고, 길이가 조정되는 지지대(295)로 구성되며, 지지대(295)는 2개의 관이 볼트 결합되어 길이가 조절되는 방식이 적용되는 것이 바람직하다.When the installation of the grating 250 is completed, an angle adjustment pipe in which the elbow pipe 260 is coupled to the sewer pipe P through the space in which the rain gutter formed in the side opening 3 of the road is installed as shown in FIG. 11F ( Combine 270, and adjust the angle using the connection pipe 271 of the angle adjustment pipe 270. At this time, the upper end of the elbow pipe 260 is fixed using a spacer 290 to maintain a vertical state in the space in which the rain gutter main body 220 is installed, and the spacer 290 is an elbow as shown in FIG. A ring-shaped spacer body 291 into which the storage 260 is inserted, and a fixing bolt 293 and a spacer body radially installed on the spacer body 291 to fix the elbow pipe 260 to the spacer body 291 It is installed radially on the spacer body 291 to fix the 291 in the space where the rain gutter body 220 is installed, and consists of a support 295 whose length is adjusted, and the support 295 includes two tubes. It is preferable to apply a method of adjusting the length by bolting.

《다짐 공정-S70》<< compaction process-S70 >>

엘보관(210)의 설치가 완료되면, 도 11g에 도시된 바와 같이 엘보관(260)을 고정시키도록 빗물받이 본체(210)가 설치되는 공간 내부에 건콘크리트를 채워넣고 다짐한다. 이때, 건콘크리트를 채워넣을시 물을 뿌리면서 다짐을 반복 수행하여 엘보관(260)을 고정시키는 것이 바람직하다.When the installation of the elbow pipe 210 is completed, as shown in FIG. 11G, dry concrete is filled and compacted in the space in which the rain gutter body 210 is installed so as to fix the elbow pipe 260. At this time, it is preferable to fix the elbow pipe 260 by repeatedly performing compaction while sprinkling water when filling the dry concrete.

《빗물받이 본체 설치 공정-S80》<< rain gutter main body installation process-S80 >>

엘보관(260)의 고정이 완료되면, 도 11h에 도시된 바와 같이 높이 조절관(280)의 높이를 조절해서 빗물받이 본체(220)를 높이 조절관(280)의 상단에 거치시킨다.When the fixing of the elbow pipe 260 is completed, the rain gutter main body 220 is mounted on the upper end of the height adjustment pipe 280 by adjusting the height of the height adjustment pipe 280 as shown in FIG. 11H.

《타설 공정-S90》<< pouring process-S90 >>

빗물받이 본체(220)의 거치가 완료되면, 도 11i에 도시된 바와 같이 빗물받이 본체(220)의 외측과 빗물받이 본체(220)가 설치되는 공간 사이에 초속경 몰탈(M)을 타설하여 양생하여 설치를 완료한다.When the installation of the rain gutter main body 220 is completed, as shown in FIG. 11I, a super fast-diameter mortar (M) is placed between the outer side of the rain gutter main body 220 and the space in which the rain gutter main body 220 is installed to be cured. To complete the installation.

본 발명은 다양하게 변형될 수 있고 여러 가지 형태를 취할 수 있으며 상기 발명의 상세한 설명에서는 그에 따른 특별한 실시 예에 대해서만 기술하였다. 하지만 본 발명은 상세한 설명에서 언급되는 특별한 형태로 한정되는 것이 아닌 것으로 이해되어야 하며, 오히려 첨부된 청구범위에 의해 정의되는 본 발명의 정신과 범위 내에 있는 모든 변형물과 균등물 및 대체물을 포함하는 것으로 이해되어야 한다.The present invention may be variously modified and may take various forms, and in the detailed description of the present invention, only specific embodiments thereof have been described. However, it should be understood that the present invention is not limited to a particular form mentioned in the detailed description, but rather, it is understood to include all modifications, equivalents, and substitutes within the spirit and scope of the present invention as defined by the appended claims. Should be.

1 : 도로 경계석 2 : 횡단보도
3 : 측구 210 : 유공관
220 : 빗물받이 본체 230 : 골재층
240 : 그레이팅 거치 프레임 250 : 그레이팅
260 : 엘보관 270 : 각도 조절관
280 : 높이 조절관 290 : 스페이서
1: Road boundary 2: Crosswalk
3: side-gu 210: merit hall
220: rain gutter main body 230: aggregate layer
240: grating mounting frame 250: grating
260: elbow pipe 270: angle adjustment pipe
280: height adjustment pipe 290: spacer

Claims (16)

횡단보도에 설치되는 빗물받이에 있어서,
도로 경계석과 횡단보도 사이의 측구에 형성된 공간에 매립 설치되는 유공관과;
상기 측구에서 상기 유공관의 양단에 형성된 공간에 매립 설치되어 상기 유공관과 각각 연결되고, 하수관거와 연결되는 빗물받이 본체와;
상기 유공관이 설치된 공간에 충전되는 골재층과;
상기 골재층의 상면에 고정 설치되는 그레이팅 거치 프레임과;
상기 그레이팅 거치 프레임에 거치되는 그레이팅과;
상기 유공관의 양단에 형성된 상기 측구의 공간에서 도로에 매립된 하수관과 연결되는 엘보관과;
상기 엘보관의 수평부와 하수관 사이에 설치되어 각도를 조절하는 각도 조절관; 및
상기 엘보관의 수직부에 설치되는 높이 조절관을 포함하되,
상기 각도 조절관은,
상기 하수관의 각도에 따라 용이하게 각도가 조절되도록 상기 엘보관과 밴드 클램프에 의해 연결되는 연성 재질의 연결관과, 금속 재질로 형성되어 일단이 상기 연결관에 리벳 결합되고, 타단이 상기 하수관에 삽입되는 금속관으로 이루어지는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
In the rain gutter installed on the crosswalk,
A merit pipe embedded in a space formed at a side opening between a road boundary stone and a crosswalk;
A rain gutter main body which is embedded in the space formed at both ends of the perforated pipe at the side port and connected to the perforated pipe, respectively, and connected to a sewage pipe;
An aggregate layer filled in the space in which the perforated pipes are installed;
A grating mounting frame fixedly installed on the upper surface of the aggregate layer;
A grating mounted on the grating mounting frame;
An elbow pipe connected to a sewage pipe embedded in a road in the space of the side opening formed at both ends of the perforated pipe;
An angle adjustment pipe installed between the horizontal portion of the elbow pipe and the sewer pipe to adjust the angle; And
Including a height adjustment pipe installed on the vertical portion of the elbow pipe,
The angle adjustment tube,
A connection pipe made of a flexible material connected by the elbow pipe and a band clamp so that the angle can be easily adjusted according to the angle of the sewer pipe, and formed of a metal material so that one end is riveted to the connection pipe, and the other end is inserted into the sewer pipe. Crosswalk environment improvement rain gutter, characterized in that consisting of a metal pipe.
삭제delete 제 1 항에 있어서,
상기 유공관은,
외측면에 부직포가 감싸지는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 1,
The above merit tube,
Crosswalk environment improvement rain gutter, characterized in that the non-woven fabric is wrapped around the outer surface.
삭제delete 제 1 항에 있어서,
상기 빗물받이 본체는,
초경속 몰탈의 타설시 일체화되도록 측면에 연결핀이 구비되는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 1,
The rain gutter main body,
A rain gutter for improving the environment of a crosswalk, characterized in that a connection pin is provided on the side to be integrated when placing the ultra-light mortar.
제 1 항에 있어서,
상기 그레이팅 거치 프레임은,
저면 테두리에 지면을 향하도록 수직으로 돌출되어 상기 골재층을 관통하여 지층에 삽입 고정되는 복수의 고정핀이 구비되는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 1,
The grating mounting frame,
Crosswalk environment improvement rain gutter, characterized in that it is provided with a plurality of fixing pins protruding vertically toward the ground at the bottom edge and penetrating the aggregate layer to be inserted and fixed in the stratum.
제 1 항에 있어서,
상기 그레이팅 거치 프레임은,
곡선 구간에서 레이저로 절단하여 현장에서 곡선 구간에 맞게 용접하여 설치하는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 1,
The grating mounting frame,
A rain gutter for improving the crosswalk environment, characterized in that it is cut with a laser in the curved section and welded to fit the curved section at the site.
제 1 항에 있어서,
상기 그레이팅은,
상면이 개방되고, 저면에 격자 형태의 받침대가 형성되는 사각 프레임 형태로 형성되는 프레임 본체와;
투수 시멘트로 제작되고, 내부에 철근망이 삽입되어 직육면체 형태로 제작되어 상기 프레임 본체 내부에 삽입 설치되는 투수 시멘트 블록; 및
상기 투수 시멘트 블록의 상면에 접합되는 천연 자갈로 구성되는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 1,
The grating is,
A frame body formed in the shape of a square frame with an upper surface open and a grid-shaped pedestal formed on a lower surface;
A permeable cement block made of permeable cement, a reinforcing bar mesh inserted therein, and manufactured in a rectangular parallelepiped shape to be inserted and installed inside the frame body; And
Crosswalk environment improvement rain gutter, characterized in that consisting of natural gravel bonded to the upper surface of the permeable cement block.
제 8 항에 있어서,
상기 그레이팅은,
상기 투수 시멘트 블록 측면에 아이 너트가 매립되고, 상기 프레임 본체 측면에 상기 아이 너트에 체결되는 접시 머리 볼트가 관통되며 수납되는 볼트홀이 구비되며, 상기 투수 시멘트 블록이 거푸집에서 상기 철근망이 노출되는 높이로 투수 시멘트 몰탈이 1차로 충전되어 제작되고, 양생이 완료되면, 상기 철근망을 덮는 높이로 2차로 투수 시멘트 몰탈이 2차로 충전된 다음 상면을 상기 천연 자갈로 덮어 일체화시키는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 8,
The grating is,
An eye nut is embedded in the side of the permeable cement block, a bolt hole through which a countersunk bolt fastened to the eye nut is passed through the side of the frame body is provided, and the reinforcing bar net is exposed in the form of the permeable cement block. A cross-section, characterized in that the permeable cement mortar is first filled to the height and produced, and when curing is completed, the permeable cement mortar is secondly filled to the height to cover the reinforcing bar net, and then the upper surface is covered with the natural gravel and integrated. Rain gutter to improve sidewalk environment.
제 8 항에 있어서,
상기 천연 자갈은,
접착제를 표면에 묻힌 상태에서 거푸집 내에 일정 높이로 덮은 상태에서 상기 천연 자갈 상면에 저면에 이형지가 부착된 거푸집 덮개를 놓고, 압력을 가한 상태로 경화시키는 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 8,
The natural gravel,
An environmental improvement rain gutter for crosswalks, characterized in that a formwork cover with a release paper attached to the bottom surface is placed on the upper surface of the natural gravel while the adhesive is buried on the surface and covered with a certain height in the formwork, and cured under pressure.
삭제delete 제 1 항에 있어서,
상기 높이 조절관은,
상기 엘보관의 수직부에 나사 결합되는 동일 지름의 높이 조절관을 구비하는 것을 특징으로 하는 횡단보도 환경개선 빗물받이.
The method of claim 1,
The height adjustment tube,
Crosswalk environment improvement rain gutter, characterized in that it comprises a height adjustment pipe of the same diameter screwed to the vertical portion of the elbow pipe.
제 1 항의 횡단보도 환경개선 빗물받이 시공방법에 있어서,
도로 경계석과 횡단보도 사이의 측구에 유공관과, 빗물받이 본체가 매립 설치되는 공간을 형성하는 공간 형성 공정과;
상기 유공관이 설치되는 공간 바닥에 유공관을 매립 설치하는 유공관 설치 공정과;
상기 유공관이 설치된 공간에 골재를 충전하여 골재층을 형성하는 골재층 형성 공정과;
상기 골재층의 상면에 그레이팅 거치 프레임을 고정시키고, 상기 그레이팅 거치 프레임의 외측에 초속경 몰탈을 타설하여 양생하는 그레이팅 거치 프레임 설치 공정과;
상기 그레이팅 거치 프레임에 그레이팅을 거치시키는 그레이팅 설치 공정과;
상기 빗물받이 본체가 설치되는 공간에서 하수관에 각도 조절관이 결합된 엘보관을 결합하고, 상기 각도 조절관을 이용하여 각도를 조절하는 엘보관 결합 공정과;
상기 엘보관을 고정시키도록 빗물받이 본체가 설치되는 공간 내부에 건콘크리트를 충전하여 다짐하는 기초 다짐 공정과;
상기 높이 조절관의 높이를 조절해서 그레이팅이 설치된 빗물받이 본체를 상기 높이 조절관의 상단에 거치시키는 빗물받이 설치 공정; 및
상기 빗물받이 본체의 외측과 빗물받이가 설치되는 공간 사이에 초속경 몰탈을 타설하여 양생하는 타설 공정으로 이루어지는 것을 특징으로 하는 횡단보도 환경개선 빗물받이 시공방법.
In the crosswalk environment improvement rain gutter construction method of claim 1,
A space forming process of forming a space in which a perforated pipe and a rain gutter main body are buried and installed at a side opening between a road boundary stone and a crosswalk;
A perforated pipe installation process of embedding and installing a perforated pipe in the floor of the space where the perforated pipe is installed;
An aggregate layer forming step of forming an aggregate layer by filling an aggregate in the space where the perforated pipe is installed;
A grating mounting frame installation step of fixing a grating mounting frame on the upper surface of the aggregate layer and placing an ultra-fast diameter mortar outside the grating mounting frame for curing;
A grating installation process of mounting a grating on the grating mounting frame;
An elbow pipe coupling step of coupling an elbow pipe to which an angle adjustment pipe is coupled to a sewage pipe in a space where the rain gutter main body is installed, and adjusting an angle using the angle adjustment pipe;
A basic compaction step of filling and compacting dry concrete in a space in which a rain gutter body is installed to fix the elbow pipe;
A rain gutter installation process of adjusting the height of the height control tube to mount the rain gutter body on which the grating is installed on the upper end of the height control tube; And
A method of constructing a rain gutter for improving the environment of a crosswalk, characterized in that it consists of a pouring process of curing by placing an ultra-fast mortar between the outside of the rain gutter body and the space in which the rain gutter is installed.
제 13 항에 있어서,
상기 엘보관 결합 공정은,
상기 엘보관의 상단부가 빗물받이가 설치되는 공간에서 수직 상태를 유지하도록 스페이서를 이용하여 고정하는 것을 특징으로 하는 횡단보도 환경개선 빗물받이 시공방법.
The method of claim 13,
The elbow tube bonding process,
A crosswalk environment improvement rain gutter construction method, characterized in that the upper end of the elbow pipe is fixed using a spacer to maintain a vertical state in a space where the rain gutter is installed.
제 14 항에 있어서,
상기 스페이서는,
상기 엘보관이 삽입되는 링 형태의 스페이서 본체와;
상기 엘보관을 상기 스페이서 본체에 고정시키도록 상기 스페이서 본체에 방사상으로 설치되는 고정 볼트; 및
상기 스페이서 본체를 빗물받이가 설치되는 공간에 고정시키도록 상기 스페이서 본체에 방사상으로 설치되고, 길이가 조정되는 지지대로 이루어지는 것을 특징으로 하는 횡단보도 환경개선 빗물받이 시공방법.
The method of claim 14,
The spacer,
A ring-shaped spacer body into which the elbow tube is inserted;
A fixing bolt radially installed on the spacer body to fix the elbow pipe to the spacer body; And
A crosswalk environment improvement rain gutter construction method, characterized in that the spacer body is radially installed on the spacer body to fix the rain gutter in a space where the rain gutter is installed, and a length of a support member is adjusted.
제 13 항에 있어서,
상기 그레이팅은,
도로 경계석의 높이와 동일하거나 더 낮게 형성되는 것을 특징으로 하는 횡단보도 환경개선 빗물받이 시공방법.
The method of claim 13,
The grating is,
A rain gutter construction method for improving the environment of a crosswalk, characterized in that it is formed equal to or lower than the height of the road boundary stone.
KR1020200066404A 2020-06-02 2020-06-02 Street inlet for improving environment of crosswalk and constructing method thereof Active KR102213360B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200066404A KR102213360B1 (en) 2020-06-02 2020-06-02 Street inlet for improving environment of crosswalk and constructing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200066404A KR102213360B1 (en) 2020-06-02 2020-06-02 Street inlet for improving environment of crosswalk and constructing method thereof

Publications (1)

Publication Number Publication Date
KR102213360B1 true KR102213360B1 (en) 2021-02-08

Family

ID=74560059

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200066404A Active KR102213360B1 (en) 2020-06-02 2020-06-02 Street inlet for improving environment of crosswalk and constructing method thereof

Country Status (1)

Country Link
KR (1) KR102213360B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102599308B1 (en) 2023-01-30 2023-11-06 이세홍 LID combined heavy rain induction drainage device
KR20240095765A (en) 2022-12-19 2024-06-26 (주)한국알앤디 Street inlet for improving environment of crosswalk and constructing method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200300720Y1 (en) * 2002-10-01 2003-01-14 박점순 Pipe laying structure of elbow tube
KR20080045597A (en) * 2006-11-20 2008-05-23 박옥교 Double Composite Wall Sump Structure
KR20080099217A (en) * 2008-10-09 2008-11-12 신영기술개발(주) Angle adjustment device of bridge and overpass drainage
KR20090120986A (en) * 2008-05-21 2009-11-25 주식회사 자연과건설 Side mouth for treatment of nonpoint sources.
KR20100059051A (en) * 2008-11-25 2010-06-04 서일공영 주식회사 Construction method of support plate for grating
KR101606548B1 (en) * 2015-03-27 2016-03-25 김기로 Cover for the gutter with a pitcher features
KR101902536B1 (en) 2017-01-17 2018-09-28 이상섭 Street inlet having angle adjustable bellows and rainwater conduit construction method using this same

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200300720Y1 (en) * 2002-10-01 2003-01-14 박점순 Pipe laying structure of elbow tube
KR20080045597A (en) * 2006-11-20 2008-05-23 박옥교 Double Composite Wall Sump Structure
KR20090120986A (en) * 2008-05-21 2009-11-25 주식회사 자연과건설 Side mouth for treatment of nonpoint sources.
KR20080099217A (en) * 2008-10-09 2008-11-12 신영기술개발(주) Angle adjustment device of bridge and overpass drainage
KR20100059051A (en) * 2008-11-25 2010-06-04 서일공영 주식회사 Construction method of support plate for grating
KR101606548B1 (en) * 2015-03-27 2016-03-25 김기로 Cover for the gutter with a pitcher features
KR101902536B1 (en) 2017-01-17 2018-09-28 이상섭 Street inlet having angle adjustable bellows and rainwater conduit construction method using this same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20240095765A (en) 2022-12-19 2024-06-26 (주)한국알앤디 Street inlet for improving environment of crosswalk and constructing method thereof
KR102789970B1 (en) * 2022-12-19 2025-04-04 (주)한국알앤디 Street inlet for improving environment of crosswalk and constructing method thereof
KR102599308B1 (en) 2023-01-30 2023-11-06 이세홍 LID combined heavy rain induction drainage device

Similar Documents

Publication Publication Date Title
KR101509202B1 (en) Side Gutter Type Rain Collecting Well AND Eco-friendly Road Structure With Drainage System Using The Rain Collecting Wells
KR102213360B1 (en) Street inlet for improving environment of crosswalk and constructing method thereof
KR101822899B1 (en) Eco-friendly Surface Water Reservoir for Improvement of Groundwater Storage Function AND Eco-friendly Road Structure With Drainage System Using The Reservoir
KR102051860B1 (en) Drainage trench for pavement
CN114164846B (en) Permanent slope waterproof reinforcing construction method
CN208328601U (en) Drainage system for steep slope road section
KR20090105254A (en) Integral Penetration Sump
CN213653493U (en) Highway side slope retaining wall
JP2008267023A (en) Rainwater storage system
KR20050110305A (en) Drain board and method of basement floor construction using the same
KR102358432B1 (en) underground penetration type concrete structure and methode there of
KR102213359B1 (en) Street inlet with rapid construction and constructing method using thereof
KR101661520B1 (en) A Multifunctional infiltration drainage apparatus and a building method therof
KR100960655B1 (en) Road having the ability of street improvement and draining
JP4125834B2 (en) Gutter, gutter lid member, and boundary block
CN110983886B (en) Combined type town road
JP2662823B2 (en) Rainwater penetration structure
KR102789970B1 (en) Street inlet for improving environment of crosswalk and constructing method thereof
KR102571397B1 (en) Catch Basin for Height-Adjustable and Constructing Method Using The Same
JP4142949B2 (en) Drainage structure of paved road using drain block
JP7576248B2 (en) Drainage structure and construction method of drainage structure
JP2529892B2 (en) Road rainwater infiltration structure
JPH05339978A (en) Composite function type gutter
JPS6325141B2 (en)
KR102296988B1 (en) PC side ditch construction method for road line drainage

Legal Events

Date Code Title Description
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20200602

PA0201 Request for examination
PN2301 Change of applicant

Patent event date: 20200721

Comment text: Notification of Change of Applicant

Patent event code: PN23011R01D

PA0302 Request for accelerated examination

Patent event date: 20200723

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

Patent event date: 20200602

Patent event code: PA03021R01I

Comment text: Patent Application

PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20201111

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20210201

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20210202

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20210202

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
PR1001 Payment of annual fee

Payment date: 20240131

Start annual number: 4

End annual number: 4

PR1001 Payment of annual fee

Payment date: 20250203

Start annual number: 5

End annual number: 5