KR101293550B1 - 지중 구조물 시공방법 - Google Patents
지중 구조물 시공방법 Download PDFInfo
- Publication number
- KR101293550B1 KR101293550B1 KR1020120055504A KR20120055504A KR101293550B1 KR 101293550 B1 KR101293550 B1 KR 101293550B1 KR 1020120055504 A KR1020120055504 A KR 1020120055504A KR 20120055504 A KR20120055504 A KR 20120055504A KR 101293550 B1 KR101293550 B1 KR 101293550B1
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- pile
- construction
- underground structure
- stacking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0275—Retaining or protecting walls characterised by constructional features cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
도 2는 본 발명인 지중 구조물을 도시한 도면.
도 3은 본 발명인 지중 구조물 시공방법을 도시한 순서도.
도 4는 본 발명인 지중 구조물의 시공방법을 도시한 도면으로, 도 4A는 겹침식 주열말뚝의 작업을 나타낸 도면이고, 도 4B는 도로면의 하부를 굴착한 상태를 나타낸 도면이며, 도 4B는 상부 슬래브를 시공을 위한 거푸집을 설치한 나타낸 도면이고, 도 4D는 상부 슬래브를 시공한 상태를 나타낸 도면이며, 도 4E는 상부 슬래브의 상부를 되메우기 상태를 나타낸 도면이고, 도 4F는 상부 슬래브를 버팀보로 활용하여탑-다운 공법으로 굴착하는 상태를 나타낸 도면이며, 도 4G는 지중 구조물의 시공이 완료된 상태를 나타낸 도면이다.
도 5는 본 발명인 가이드월을 도시한 도면으로, 도 5a는 가이드월의 제1 실시예를 나타낸 도면이고, 도 5b는 가이드월의 제2 실시예를 도시한 도면이며, 도 5c는 가이드월의 제3 실시예를 도시한 도면이다.
도 6은 본 발명인 가이드월을 통해 겹침식 주열 말뚝의 시공 상태를 도시한 도면.
도 7은 본 발명인 상부 슬래브 시공상태를 도시한 도면.
도 8은 본 발명인 상부 슬래브의 다른 실시예를 도시한 도면.
도 9는 본 발명인 중간 슬래브 시공 상태를 도시한 도면.
도 10은 본 발명인 지중 구조물 시공방법의 제2 실시예를 나타낸 도면.
도 11은 본 발명인 지중 구조물 시공방법의 제3 실시예를 나타낸 도면.
도 12는 본 발명인 지중 구조물 시공방법의 제4 실시예를 나타낸 도면.
300: 도로면 400: 중간 버팀보
500: 하부 슬래브 600: 중간 슬래브
Claims (10)
- 도로면에 다수개의 겹침식 주열 말뚝을 시공하는 겹침식 주열 말뚝 시공단계(S10);
상기 겹침식 주열 말뚝 사이를 굴착하는 제1 굴착단계(S20);
상기 겹침식 주열 말뚝 사이의 굴착면에 프리캐스트빔을 설치하고, 상기 프리캐프스트 빔의 상부에 콘크리트를 타설하여 상부 슬래브를 시공하는 상부 슬래브 시공단계(S30);
상기 상부 슬래브의 상면을 되메우기하여 도로면을 복구하는 도로복구단계(S40);
상기 상부 슬래브를 버팀보로 활용하여 상부 슬래브 하부를 굴착하는 제2 굴착단계(S50); 및
상기 제2 굴착단계를 통해 굴착된 바닥면에 철근 콘크리트를 타설하여 하부 슬래브를 시공하는 하부 슬래브 시공단계(S70)를 포함하며,
상기 겹침식 주열 말뚝 시공단계(S10)는 겹침식 주열 말뚝을 설치하기 위한 도로면에 가시설 벽체를 각각 시공하고, 상기 가시설 벽체 사이를 굴착하며, 굴착된 바닥면에 콘크리트를 타설하고, 상기 콘크리트의 상면에 가이드월을 설치한 후, 상기 가이드월에 형성된 가이드홀을 통해 겹침식 주열 말뚝을 삽입 시공하는 지중 구조물 시공방법. - 삭제
- 삭제
- 청구항 1에 있어서,
상기 가이드월은 겹침식 주열 말뚝 형상이 다수개 연결된 스티로폼을 형성하고, 상기 스티로폼의 외측에 거푸집을 설치한 후 콘크리트를 타설하여 가이드월 벽체를 시공하여 제작하는 지중 구조물 시공방법. - 청구항 1에 있어서,
상기 가이드월은 한 쌍으로 이루어진 가이드월 강재를 구비하고, 상기 한 쌍의 가이드월 강재 사이에 간격재를 설치하여 제작하는 지중 구조물 시공방법. - 청구항 1에 있어서,
상기 상부 슬래브 시공단계(S30)는 상부 슬래브에 노출된 철근과 겹침식 주열 말뚝에 노출된 철근을 겹쳐서 연결하거나 또는 커플러를 사용하여 연결한 후 콘크리트를 타설하여 상부 슬래브와 겹침식 주열 말뚝을 일체화하는 지중 구조물 시공방법. - 청구항 1에 있어서,
상기 도로복구단계(S40)는 도로면을 복구하기 위한 되메우기 전에 상부 슬래브 상면에 방수재를 설치하는 지중 구조물 시공방법. - 청구항 1에 있어서,
상기 제2 굴착단계(S50)에서 겹침식 주열 말뚝으로부터 전달되는 토압이 클 경우 중간 버팀보를 설치하며,
상기 중간 버팀보는 하부 슬래브 시공 후 제거하는 지중 구조물 시공방법. - 청구항 1에 있어서,
상기 하부 슬래브 시공단계(S70)는 겹침식 주열 말뚝에 매립된 철근 중 일부를 인출한 철근과 바닥 슬래브로부터 노출된 철근을 연결하거나 또는 커플러를 사용하여 연결한 후 콘크리트를 타설하여 하부 슬래브와 겹침식 주열 말뚝을 일체화하며,
상기 하부 슬래브의 시공 전에 굴착된 바닥면에 방수재를 설치하는 지중 구조물 시공방법. - 청구항 1에 있어서,
상기 제2 굴착단계와 하부 슬래브 시공단계 사이에 중간 슬래브를 시공하는 중간 슬래브 시공단계를 포함할 수 있으며,
상기 중간 슬래브 시공단계(S60)는 제2 굴착단계를 통해 겹침식 주열 말뚝의 내부를 일부 굴착한 후, 라이닝 콘크리트를 타설하여 중간 슬래브를 시공하는 지중 구조물 시공방법.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020120055504A KR101293550B1 (ko) | 2012-05-24 | 2012-05-24 | 지중 구조물 시공방법 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020120055504A KR101293550B1 (ko) | 2012-05-24 | 2012-05-24 | 지중 구조물 시공방법 |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101293550B1 true KR101293550B1 (ko) | 2013-08-06 |
Family
ID=49219937
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020120055504A Active KR101293550B1 (ko) | 2012-05-24 | 2012-05-24 | 지중 구조물 시공방법 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101293550B1 (ko) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017206882A (ja) * | 2016-05-19 | 2017-11-24 | 鹿島建設株式会社 | 地下構造体の構築方法 |
KR102314838B1 (ko) * | 2021-04-01 | 2021-10-19 | 송관권 | 터널 비개착공법 |
KR20210154337A (ko) * | 2020-06-12 | 2021-12-21 | 정하동 | 지하구조물 시공방법 |
CN114775688A (zh) * | 2022-05-26 | 2022-07-22 | 中国建筑第五工程局有限公司 | 一种少模架支撑的叠合装配式地铁车站的施工方法 |
CN115404916A (zh) * | 2022-09-13 | 2022-11-29 | 中国一冶集团有限公司 | 穿河遇桥桩的分舱管廊的防水装置 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100892137B1 (ko) * | 2008-06-23 | 2009-04-08 | (주)비엔텍아이엔씨 | 보강이 가능한 횡방향 피에스씨 빔을 이용한 라멘식 지하차도 시공방법 |
KR20110122485A (ko) * | 2010-05-04 | 2011-11-10 | (주)나우이앤씨 | 씨아이피를 이용한 지하도로 시공방법 |
KR20110130196A (ko) * | 2010-05-27 | 2011-12-05 | 주식회사 코아이엔씨 | 지하철 정거장 및 지하철 정거장의 시공방법 |
-
2012
- 2012-05-24 KR KR1020120055504A patent/KR101293550B1/ko active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100892137B1 (ko) * | 2008-06-23 | 2009-04-08 | (주)비엔텍아이엔씨 | 보강이 가능한 횡방향 피에스씨 빔을 이용한 라멘식 지하차도 시공방법 |
KR20110122485A (ko) * | 2010-05-04 | 2011-11-10 | (주)나우이앤씨 | 씨아이피를 이용한 지하도로 시공방법 |
KR20110130196A (ko) * | 2010-05-27 | 2011-12-05 | 주식회사 코아이엔씨 | 지하철 정거장 및 지하철 정거장의 시공방법 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017206882A (ja) * | 2016-05-19 | 2017-11-24 | 鹿島建設株式会社 | 地下構造体の構築方法 |
KR20210154337A (ko) * | 2020-06-12 | 2021-12-21 | 정하동 | 지하구조물 시공방법 |
KR102431393B1 (ko) | 2020-06-12 | 2022-08-11 | 정하동 | 지하구조물 시공방법 |
KR102314838B1 (ko) * | 2021-04-01 | 2021-10-19 | 송관권 | 터널 비개착공법 |
CN114775688A (zh) * | 2022-05-26 | 2022-07-22 | 中国建筑第五工程局有限公司 | 一种少模架支撑的叠合装配式地铁车站的施工方法 |
CN114775688B (zh) * | 2022-05-26 | 2024-05-03 | 中国建筑第五工程局有限公司 | 一种少模架支撑的叠合装配式地铁车站的施工方法 |
CN115404916A (zh) * | 2022-09-13 | 2022-11-29 | 中国一冶集团有限公司 | 穿河遇桥桩的分舱管廊的防水装置 |
CN115404916B (zh) * | 2022-09-13 | 2023-07-18 | 中国一冶集团有限公司 | 穿河遇桥桩的分舱管廊的防水装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101344063B1 (ko) | 강합성 지하차도 시공 공법 | |
KR101640795B1 (ko) | 가시설용 차수식 흙막이 패널 구조체와 그 시공방법 | |
KR101274974B1 (ko) | 흙막이 겸용 옹벽 및 이의 시공방법 | |
KR20160131410A (ko) | Topdown 공법을 이용한 지하구조물 시공방법 | |
KR101288601B1 (ko) | 기성 콘크리트 말뚝과 바닥 슬래브를 이용한 지하차도 및 그의 시공방법 | |
KR101293550B1 (ko) | 지중 구조물 시공방법 | |
KR102136951B1 (ko) | 복층 터널 공법 | |
KR20180118009A (ko) | 복층터널공법 | |
JP4881555B2 (ja) | 地下構造物の構築方法 | |
KR101902786B1 (ko) | 합성쉬트파일을 이용한 지중구조물 시공방법 및 이를 이용하여 제작된 지중구조물 | |
KR101011805B1 (ko) | 파일기초부를 횡단하는 지중구조물 시공 방법 및 그를 이용하여 축조된 지중구조물 | |
KR101324231B1 (ko) | 소일 시멘트벽 가시설 구조 및 이의 시공 방법 | |
KR101467147B1 (ko) | 반강접 접합을 적용한 정거장 구조물의 시공방법 | |
JP2015117545A (ja) | 地下トンネルの構築方法 | |
KR101296857B1 (ko) | 토압 지지력이 강화된 바닥보를 구비하는 지하 구조물 및 그 시공방법 | |
KR101902791B1 (ko) | 합성강관파일을 이용한 지중구조물 시공방법 및 이를 이용하여 제작된 지중구조물 | |
KR102021496B1 (ko) | 하향식 계단형 흙막이 시공방법 및 이를 통해 시공된 흙막이 구조체 | |
JP4083334B2 (ja) | アーチ屋根を有する地下構造物およびその構築方法 | |
KR20060097891A (ko) | 강관루프 구조체 및 이 강관루프 구조체의 시공방법 | |
JP5915074B2 (ja) | 地上交通路の下に地下空間を形成する方法 | |
KR20210055980A (ko) | 우회도로와 교통통제 없이 시공이 가능한 강제지중 연속벽을 이용한 탑-다운 방식의 지하차도 및 그의 시공 방법 | |
KR101155155B1 (ko) | 미리 철거되는 중간파일을 이용한 지중구조물 시공방법 | |
KR101288602B1 (ko) | 결속밴드로 머리가 연결된 기성 콘크리트 말뚝을 이용한 지하차도 및 그의 시공방법 | |
KR102292152B1 (ko) | 지장구조물이 있는 경우의 탑다운공법 | |
KR20070052109A (ko) | 슬림형 합성 바닥 구조를 이용한 슬라브와 외벽의 동시 타설 및 지하 역타설 동시구축방법 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20120524 |
|
PA0201 | Request for examination | ||
A302 | Request for accelerated examination | ||
PA0302 | Request for accelerated examination |
Patent event date: 20120608 Patent event code: PA03022R01D Comment text: Request for Accelerated Examination Patent event date: 20120524 Patent event code: PA03021R01I Comment text: Patent Application |
|
E902 | Notification of reason for refusal | ||
PE0902 | Notice of grounds for rejection |
Comment text: Notification of reason for refusal Patent event date: 20120803 Patent event code: PE09021S01D |
|
E701 | Decision to grant or registration of patent right | ||
PE0701 | Decision of registration |
Patent event code: PE07011S01D Comment text: Decision to Grant Registration Patent event date: 20121108 |
|
N231 | Notification of change of applicant | ||
PN2301 | Change of applicant |
Patent event date: 20121128 Comment text: Notification of Change of Applicant Patent event code: PN23011R01D |
|
GRNT | Written decision to grant | ||
PR0701 | Registration of establishment |
Comment text: Registration of Establishment Patent event date: 20130731 Patent event code: PR07011E01D |
|
PR1002 | Payment of registration fee |
Payment date: 20130801 End annual number: 3 Start annual number: 1 |
|
PG1601 | Publication of registration | ||
FPAY | Annual fee payment |
Payment date: 20160706 Year of fee payment: 4 |
|
PR1001 | Payment of annual fee |
Payment date: 20160706 Start annual number: 4 End annual number: 4 |
|
FPAY | Annual fee payment |
Payment date: 20190730 Year of fee payment: 7 |
|
PR1001 | Payment of annual fee |
Payment date: 20190730 Start annual number: 7 End annual number: 7 |
|
PR1001 | Payment of annual fee |
Payment date: 20201006 Start annual number: 8 End annual number: 8 |
|
PR1001 | Payment of annual fee |
Payment date: 20210726 Start annual number: 9 End annual number: 9 |
|
PR1001 | Payment of annual fee |
Payment date: 20221130 Start annual number: 10 End annual number: 10 |
|
PR1001 | Payment of annual fee |
Payment date: 20230727 Start annual number: 11 End annual number: 11 |
|
PR1001 | Payment of annual fee |
Payment date: 20240520 Start annual number: 12 End annual number: 12 |
|
PR1001 | Payment of annual fee |
Payment date: 20250616 Start annual number: 13 End annual number: 13 |