KR101066243B1 - 주탑 설치장치 및 이를 이용한 주탑 가설공법 - Google Patents
주탑 설치장치 및 이를 이용한 주탑 가설공법 Download PDFInfo
- Publication number
- KR101066243B1 KR101066243B1 KR1020110042078A KR20110042078A KR101066243B1 KR 101066243 B1 KR101066243 B1 KR 101066243B1 KR 1020110042078 A KR1020110042078 A KR 1020110042078A KR 20110042078 A KR20110042078 A KR 20110042078A KR 101066243 B1 KR101066243 B1 KR 101066243B1
- Authority
- KR
- South Korea
- Prior art keywords
- tower
- main
- lifting
- strand
- wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009434 installation Methods 0.000 title claims abstract description 27
- 238000010276 construction Methods 0.000 title claims abstract description 23
- 238000000034 method Methods 0.000 claims description 7
- 238000010586 diagram Methods 0.000 description 3
- 238000003912 environmental pollution Methods 0.000 description 3
- 238000006073 displacement reaction Methods 0.000 description 2
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 239000000383 hazardous chemical Substances 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/14—Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
도 2 내지 도 8은 본 발명의 작동상태도
도 9는 본 발명에 의한 주탑의 설치상태도
120: 탑기부 130: 리프팅 타워
140: 주탑 150: 스트랜드 잭 리프트부
151,151': 하,상부 러그 152: 연결보
153: 와이어 정착구 154: 스트랜드 와이어
155: 스트랜드 잭 156: 잭 하우징
160: 연결부재
Claims (6)
- 주탑을 지지하는 기초부와;
상기 기초부의 양측에 대향하게 설치되어 주탑이 안착되도록 하는 탑기부와;
상기 기초부의 전,후방에 대향하게 설치되어 주탑의 인양을 지지하도록 설치되며, 주탑의 설치 후, 해체되는 리프팅 타워와;
상기 기초부의 양측에 대향하게 형성된 탑기부와 동일 선상으로 설치되는 한 쌍의 주탑과;
상기 주탑과 리프팅 타워를 연결하여 주탑을 인양시키고, 주탑의 설치 후, 해체되는 스트랜드 잭 리프트부와;
상기 스트랜드 잭 리프트부의 작동으로 탑기부에 설치면이 면접촉되도록 인양된 한 쌍의 주탑을 연결하는 연결부재를 포함하여 구성되는 것을 특징으로 하는 주탑 설치장치.
- 청구항 1에 있어서, 리프팅 타워는,
상기 기초부의 전,후면에 설치되는 수직 리프팅 타워와;
상기 수직 리프팅 타워와 직교되도록 기초부의 양측에 탑기부와 동일 선상으로 설치되어 한 쌍의 주탑을 각각 지지하는 수평 리프팅 타워를 포함하여 구비되는 것을 특징으로 하는 주탑 설치장치.
- 청구항 1에 있어서, 스트랜드 잭 리프트부는,
상기 주탑과 리프팅 타워의 수직 리프팅 타워에 각각 설치되는 한 쌍의 하,상부 러그와;
상기 한 쌍의 하부 러그에 축을 중심으로 회전가능하게 장착되면서 와이어 정착구에 연결되는 연결보와;
상기 연결보에 연결되어 스트랜드 와이어의 단부를 회전가능하게 고정하는 와이어 정착구와;
상기 와이어 정착구에 단부가 결합되어 고정되는 스트랜드 와이어와;
상기 스트랜드 와이어에 결합되어 제어부의 제어에 따라 스트랜드 와이어를 잡아당기고, 잡아당겨진 스트랜드 와이어의 복원을 방지하는 스트랜드 잭과;
상기 스트랜드 잭을 수용하여 한 쌍의 상부 러그에 축을 중심으로 회전가능하게 연결되면서 스트랜드 와이어가 이동할 수 있도록 이동공간이 관통된 잭 하우징을 포함하여 구비되는 것을 특징으로 하는 주탑 설치장치.
- 청구항 3에 있어서, 연결보는,
상기 한 쌍의 하부 러그를 수용하는 하부보와;
상기 와이어 정착구를 수용하는 상부보와;
상기 하,상부보의 축공에 결합하는 연결축을 포함하여 구비되는 것을 특징으로 하는 주탑 연결장치.
- 주탑을 지지하는 기초부를 설치하는 단계와;
상기 기초부의 양측에 대향하게 탑기부를 설치하는 단계와;
상기 기초부의 전,후방에 주탑의 인양을 지지하도록 리프팅 타워를 설치하는 단계와;
상기 탑기부와 동일 선상으로 상기 리프팅 타워의 수평 리프팅 타워에 주탑을 안착시키는 단계와;
상기 주탑과 리프팅 타워의 수직 리프팅 타워에 스트랜드 잭 리프트부를 설치하는 단계와;
상기 스트랜드 잭 리프트부의 작동으로 주탑의 설치면이 탑기부에 면접촉되도록 주탑을 인양시키는 단계와;
상기 탑기부에 설치면이 면접촉되도록 인양된 주탑을 연결부재로 연결하여 고정하는 단계와;
상기 연결부재로 주탑이 연결고정되면, 스트랜드 잭 리프트부와 리프팅 타워를 해체하는 단계를 포함하여 이루어지는 것을 특징으로 하는 주탑 설치장치를 이용한 주탑 가설공법.
- 청구항 5에 있어서, 스트랜드 잭 리프트부 설치 단계는,
상기 주탑과 리프팅 타워의 수직 리프팅 타워에 한 쌍의 하,상부 러그를 각각 설치하는 단계와;
상기 한 쌍의 하부 러그에 결합된 하부보에 와이어 정착구가 연결되는 상부보가 연결축으로 결합되는 연결보를 연결하는 단계와;
상기 연결보의 상부보에 와이어 정착구를 회전가능하게 연결하는 단계와;
상기 수직 리프팅 타워에 형성된 한 쌍의 상부 러그에 스트랜드 와이어의 일측단부가 결합된 스트랜드 잭이 장착되는 잭 하우징을 설치하는 단계와;
상기 스트랜드 잭으로 결합된 스트랜드 와이어의 일측단부를 상기 와이어 정착구에 결합고정하는 단계를 포함하여 이루어지는 것을 특징으로 하는 주탑 설치장치를 이용한 주탑 가설공법.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110042078A KR101066243B1 (ko) | 2011-05-03 | 2011-05-03 | 주탑 설치장치 및 이를 이용한 주탑 가설공법 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110042078A KR101066243B1 (ko) | 2011-05-03 | 2011-05-03 | 주탑 설치장치 및 이를 이용한 주탑 가설공법 |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101066243B1 true KR101066243B1 (ko) | 2011-09-20 |
Family
ID=44957623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020110042078A Expired - Fee Related KR101066243B1 (ko) | 2011-05-03 | 2011-05-03 | 주탑 설치장치 및 이를 이용한 주탑 가설공법 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101066243B1 (ko) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102774745A (zh) * | 2012-06-26 | 2012-11-14 | 河北金环钢结构工程有限公司 | 拉索桥索塔安装用组合式起重塔及其安装方法 |
CN104088231A (zh) * | 2014-08-01 | 2014-10-08 | 武船重型工程股份有限公司 | 一种重型桥梁钢塔节段的翻身方法 |
CN107313350A (zh) * | 2017-06-14 | 2017-11-03 | 广东省长大公路工程有限公司 | 一种异形钢索塔海上整体吊装方法 |
CN114960465A (zh) * | 2022-07-18 | 2022-08-30 | 中交路桥建设有限公司 | 链条提升式斜拉桥钢塔转体施工方法 |
CN116516820A (zh) * | 2023-04-17 | 2023-08-01 | 宁波通途投资开发有限公司 | 一种矮塔混合梁斜拉桥v型主塔竖转结构体系及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4027441A (en) | 1975-10-02 | 1977-06-07 | Grigory Vasilievich Pitelyaev | Arrangement for erecting and dismounting an elongate object having one end articulated to a foundation |
US6955025B2 (en) | 2002-09-11 | 2005-10-18 | Clipper Windpower Technology, Inc. | Self-erecting tower and method for raising the tower |
KR100829062B1 (ko) | 2007-03-21 | 2008-05-16 | 삼성물산 주식회사 | 콘크리트 압송파이프 지지대 및 이를 이용한 사장교 주탑시공방법 |
KR20100070505A (ko) * | 2008-12-18 | 2010-06-28 | 재단법인 포항산업과학연구원 | 현수교 케이블 가설장치 및 이를 이용한 가설 공법 |
-
2011
- 2011-05-03 KR KR1020110042078A patent/KR101066243B1/ko not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4027441A (en) | 1975-10-02 | 1977-06-07 | Grigory Vasilievich Pitelyaev | Arrangement for erecting and dismounting an elongate object having one end articulated to a foundation |
US6955025B2 (en) | 2002-09-11 | 2005-10-18 | Clipper Windpower Technology, Inc. | Self-erecting tower and method for raising the tower |
KR100829062B1 (ko) | 2007-03-21 | 2008-05-16 | 삼성물산 주식회사 | 콘크리트 압송파이프 지지대 및 이를 이용한 사장교 주탑시공방법 |
KR20100070505A (ko) * | 2008-12-18 | 2010-06-28 | 재단법인 포항산업과학연구원 | 현수교 케이블 가설장치 및 이를 이용한 가설 공법 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102774745A (zh) * | 2012-06-26 | 2012-11-14 | 河北金环钢结构工程有限公司 | 拉索桥索塔安装用组合式起重塔及其安装方法 |
CN104088231A (zh) * | 2014-08-01 | 2014-10-08 | 武船重型工程股份有限公司 | 一种重型桥梁钢塔节段的翻身方法 |
CN107313350A (zh) * | 2017-06-14 | 2017-11-03 | 广东省长大公路工程有限公司 | 一种异形钢索塔海上整体吊装方法 |
CN114960465A (zh) * | 2022-07-18 | 2022-08-30 | 中交路桥建设有限公司 | 链条提升式斜拉桥钢塔转体施工方法 |
CN114960465B (zh) * | 2022-07-18 | 2023-10-31 | 中交路桥建设有限公司 | 链条提升式斜拉桥钢塔转体施工方法 |
CN116516820A (zh) * | 2023-04-17 | 2023-08-01 | 宁波通途投资开发有限公司 | 一种矮塔混合梁斜拉桥v型主塔竖转结构体系及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101066243B1 (ko) | 주탑 설치장치 및 이를 이용한 주탑 가설공법 | |
JP5572668B2 (ja) | 斜ケーブルの取り替え方法及び斜ケーブル取り替え用仮ハンガー | |
CN102071651B (zh) | 悬索桥吊索换索方法 | |
EP2982862B1 (en) | Method and device for blade replacement in wind turbines | |
KR101553966B1 (ko) | 외벽설치 타워크레인 등반장치 | |
MX2011002576A (es) | Aparato de desmantelamiento y metodo de desmantelamiento de maquina electrica giratoria. | |
EP2969884A1 (en) | Self erecting jacking tower | |
CA2759307A1 (en) | Installing method for anchor cage and installing method for industrial equipment | |
CN106012852A (zh) | 支架整体落架施工方法 | |
KR101090451B1 (ko) | 사장교 주탑 시공 방법. | |
CN112664034B (zh) | 一种风力发电塔的整体安装方法 | |
CN103754772B (zh) | 风力发电机的部件更换装置、系统及方法 | |
JP6545965B2 (ja) | クライミングクレーン | |
JP2011225336A (ja) | クライミングエレベータの機械台装置 | |
CN103863924A (zh) | 无机械室电梯 | |
KR20100103177A (ko) | 타워 크레인 작업 지지 장치 | |
CN110965641A (zh) | 一种装配式建筑预制钢结构构件的安装施工方法 | |
JP3905103B2 (ja) | 塔状建造物の架設方法および架設装置 | |
CN105417422B (zh) | 一种可移动式独立扒杆吊装装置及其吊装方法 | |
CN112125143B (zh) | 一种电力铁塔安装施工多点式支撑吊升装置 | |
CN115306395A (zh) | 一种管件精确对接装置及控制方法 | |
CN101973491A (zh) | 使用双塔式低塔架自平衡提升装置起重吊装的施工方法 | |
JP4978218B2 (ja) | エレベータの据付装置及び据付方法 | |
CN221971134U (zh) | 一种钢结构厂棚内部隔断安装用提升机构 | |
CN220414909U (zh) | 一种后增钢梁安装提升架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20110503 |
|
PA0201 | Request for examination | ||
A302 | Request for accelerated examination | ||
PA0302 | Request for accelerated examination |
Patent event date: 20110504 Patent event code: PA03022R01D Comment text: Request for Accelerated Examination Patent event date: 20110503 Patent event code: PA03021R01I Comment text: Patent Application |
|
E701 | Decision to grant or registration of patent right | ||
PE0701 | Decision of registration |
Patent event code: PE07011S01D Comment text: Decision to Grant Registration Patent event date: 20110906 |
|
GRNT | Written decision to grant | ||
PR0701 | Registration of establishment |
Comment text: Registration of Establishment Patent event date: 20110914 Patent event code: PR07011E01D |
|
PR1002 | Payment of registration fee |
Payment date: 20110915 End annual number: 3 Start annual number: 1 |
|
PG1601 | Publication of registration | ||
FPAY | Annual fee payment |
Payment date: 20140912 Year of fee payment: 4 |
|
PR1001 | Payment of annual fee |
Payment date: 20140912 Start annual number: 4 End annual number: 4 |
|
FPAY | Annual fee payment |
Payment date: 20150914 Year of fee payment: 5 |
|
PR1001 | Payment of annual fee |
Payment date: 20150914 Start annual number: 5 End annual number: 5 |
|
FPAY | Annual fee payment |
Payment date: 20160919 Year of fee payment: 6 |
|
PR1001 | Payment of annual fee |
Payment date: 20160919 Start annual number: 6 End annual number: 6 |
|
PR1001 | Payment of annual fee |
Payment date: 20200914 Start annual number: 10 End annual number: 10 |
|
PC1903 | Unpaid annual fee |
Termination category: Default of registration fee Termination date: 20220625 |