KR100411530B1 - Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof - Google Patents
Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof Download PDFInfo
- Publication number
- KR100411530B1 KR100411530B1 KR10-2001-0059666A KR20010059666A KR100411530B1 KR 100411530 B1 KR100411530 B1 KR 100411530B1 KR 20010059666 A KR20010059666 A KR 20010059666A KR 100411530 B1 KR100411530 B1 KR 100411530B1
- Authority
- KR
- South Korea
- Prior art keywords
- scour prevention
- scour
- construction
- prevention net
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 26
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title description 9
- 230000002265 prevention Effects 0.000 claims abstract description 62
- 239000004745 nonwoven fabric Substances 0.000 claims abstract description 15
- 239000004575 stone Substances 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims description 14
- 238000009991 scouring Methods 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 5
- 239000011435 rock Substances 0.000 abstract description 4
- 239000002699 waste material Substances 0.000 abstract description 4
- 230000007774 longterm Effects 0.000 abstract description 3
- 239000002689 soil Substances 0.000 abstract description 3
- 230000003628 erosive effect Effects 0.000 abstract description 2
- 238000009434 installation Methods 0.000 abstract description 2
- 238000004904 shortening Methods 0.000 abstract description 2
- 241001455273 Tetrapoda Species 0.000 description 5
- 238000004519 manufacturing process Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 230000006378 damage Effects 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000010485 coping Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0208—Gabions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Revetment (AREA)
Abstract
본 발명은 수중 구조물의 세굴방지공 및 이를 이용한 시공방법을 개시한다.The present invention discloses a scour prevention hole and a construction method using the same.
이러한 본 발명의 목적은 잡석이나 폐콘크리트 조각을 채운 세굴방지망 다수개를 일체화하여 시공에 따른 기간과 비용을 절감시키고 바닥이 세굴되는 현상을 효과적으로 방지하기 위한 것으로, 상측에 커버가 형성된 세굴방지망의 내부에 보형편과 U볼트가이드가 형성된 형틀을 삽입 설치하고, 그 내측으로 잡석이나 호박돌크기로 분쇄된 콘크리트를 채운 후 커버를 씌워 세굴방지망의 상측을 폐쇄하며, 수중구조물의 바닥에 부직포와 상기 세굴방지망을 설치한 다음 U볼트로 세굴방지망을 연결하여서 되는 수중 구조물의 세굴방지공 및 이를 이용한 시공방법을 제안한다.The purpose of the present invention is to reduce the duration and cost of construction by effectively integrating a plurality of scour prevention nets filled with rubble or waste concrete pieces, and to effectively prevent the phenomenon of floor scour, the inside of the scour prevention net with a cover formed on the upper side Insert and install the mold with the prosthetic piece and the U bolt guide formed in it, and fill the crushed concrete with rubble or amber stone inside and close the upper side of the scour prevention net with a cover.The nonwoven fabric and the scour prevention net at the bottom of the underwater structure After the installation, we propose a scour prevention hole and construction method using the same by connecting the scour prevention net with U bolt.
상기와 같은 본 발명은 시공현장에서 제작이 가능하고 자원을 재활용할 수 있으며, 광범위한 범위에 걸친 세굴방지 또는 국부적인 세굴방지 등 필요한 크기로 제작과 시공이 가능한 장점이 있어 시공의 용이성, 시공비용의 절감, 공사기간 단축 등의 경제적 효과와, 수중 구조물의 바닥침식이나 세굴방지, 장기적인 장갑화 현상으로 토사 또는 암반의 유실현상을 방지하는 효과가 있다.The present invention as described above can be manufactured at the construction site and resources can be recycled, there is an advantage that can be manufactured and constructed in the required size, such as scour prevention or local scour prevention over a wide range of ease of construction, construction cost Economic effects such as saving, shortening of construction period, and prevention of floor erosion or scour, and long-term armoring of the underwater structure prevent the loss of soil or rock.
Description
본 발명은 수중 구조물의 세굴방지공 및 이를 이용한 시공방법에 관한 것이다.The present invention relates to a scour prevention hole and a construction method using the same.
일반적으로 수중 구조물이 설치된 곳의 바닥은 물의 흐름이 빠르거나 와류현상이 발생되어 수중 구조물이 설치된 곳의 바닥이 패이는 세굴현상이 발생되는데, 이와 같은 세굴현상을 방지하기 위하여 상기 바닥에 사석을 일정 두께로 깔아 세굴을 방지하나, 사석은 일정 크기의 암석을 채취하여 구하기 때문에 자연파괴라는 문제가 따르고 홍수나 태풍 발생시 상기 사석이 유실되는 문제가 있어, 근래에는 첨부한 도면 도 1에 도시한 바와 같은 테트라포드(100)나 도 2로 도시한 콘크리트블럭(101) 또는 도 3으로 도시한 세굴방지망(102;일명 돌망태) 등을 이용하여 세굴을 방지한다.Generally, the bottom of the place where the underwater structure is installed has a rapid flow of water or a vortex occurs, so that the bottom of the place where the underwater structure is installed is scoured. To prevent scour, but because the stone is obtained by collecting rock of a certain size, there is a problem of natural destruction, and there is a problem that the stone is lost in case of flood or typhoon. In recent years, as shown in FIG. The tetrapod 100 or the concrete block 101 shown in FIG. 2 or the scour prevention net 102 (also called gabion) shown in FIG. 3 are used to prevent scour.
즉, 테트라포드(100)는 다수개를 수중 구조물의 바닥에 쌓아 시공하는 것이고, 콘크리트블럭(101)은 다수개를 수중 구조물의 바닥에 배열 설치하되, 서로 맞물림으로 결합되도록 하는 것이며, 세굴방지망(102)은 일자형 독립망태로 되어 내부에 잡석을 채우고 이를 수중 구조물의 바닥에 배열 설치하는 것이다.That is, the tetrapod 100 is to build a plurality of stacked on the bottom of the underwater structure, concrete block 101 is to install a plurality of arranged on the bottom of the underwater structure, to be coupled to each other, scour prevention net 102 ) Is a flat, self-contained mesh that fills rubble inside and arranges it on the bottom of the underwater structure.
그러나 이와 같은 테트라포드(100) 및 콘크리트블럭(101)은 철근을 배설하고 콘크리트를 타설하여 제조하기 때문에 제조원가가 비싸고 제조기간이 오래 걸린다.However, since the tetrapod 100 and the concrete block 101 are manufactured by placing reinforcing bars and placing concrete, the manufacturing cost is high and the manufacturing period takes a long time.
또한, 테트라포드(100)는 댐 낙차공이나 해상 파도에 의해 피해를 방지하는 방파제 등에 사용시 우수한 효과가 있으나 국부적인 세굴에 의한 단차침하가 발생되기 쉽고 유속에 의하여 형태가 변형 또는 파손되어 제 기능을 못하게 되는 문제가 있고, 콘크리트블럭(101)은 수중에서 배열 설치하는 공정이 까다롭고 시공기간이 오래 걸려 시공비가 증가된다는 문제가 있다.In addition, the tetrapod 100 has an excellent effect when used in the breakwater to prevent damage by dam drop hole or sea wave, but the step settlement is likely to occur due to local scour, and the shape is deformed or damaged by the flow rate to prevent its function. There is a problem, concrete block 101 has a problem that the installation process is difficult to install in water and the construction cost is long because the construction period is long.
이러한 문제를 해결하기 위한 본 발명의 목적은 잡석이나 폐콘크리트 조각을 채운 세굴방지망 다수개를 일체화하여 시공에 따른 기간과 비용을 절감시키고 바닥이 세굴되는 현상을 효과적으로 방지하는 수중 구조물의 세굴방지공 및 이를 이용한 시공방법을 제공함에 있다.An object of the present invention for solving this problem is to integrate a plurality of scour prevention nets filled with rubble or waste concrete pieces to reduce the time and cost of construction and to effectively prevent the phenomenon of floor scour and It is to provide a construction method using the same.
도 1은 종래 세굴방지용 테트라포드를 도시한 사시도.1 is a perspective view showing a conventional tetrapod for scour prevention.
도 2는 종래 세굴방지용 콘크리트블럭의 시공상태도.Figure 2 is a construction state of the conventional concrete block for scour prevention.
도 3은 종래의 세굴방지망을 도시한 사시도.Figure 3 is a perspective view showing a conventional scour prevention net.
도 4는 본 발명에 의한 세굴방지망을 도시한 사시도.Figure 4 is a perspective view showing a scour prevention net according to the present invention.
도 5는 본 발명에 의한 형틀을 도시한 사시도.5 is a perspective view showing a mold according to the present invention.
도 6 및 도 7은 본 발명에 의한 세굴방지공의 제작과정도.6 and 7 is a manufacturing process of the scour prevention ball according to the present invention.
도 8은 본 발명에 의한 부직포의 시공상태도.8 is a construction state of the nonwoven fabric according to the present invention.
도 9는 본 발명에 의한 세굴방지공의 시공상태도.Figure 9 is a construction state of the scour prevention hole according to the present invention.
도 10은 본 발명에 의한 세굴방지공의 시공 공정도.Figure 10 is a construction process of the scour prevention hole according to the present invention.
*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *
10 : 세굴방지공 11 : 세굴방지망 12 : 커버10: scour prevention ball 11: scour prevention net 12: cover
13 : 형틀 14 : 몸체 15 : 보형편13 mold 14 body 15 prosthesis
16 : U볼트가이드 17 : 철사 18 : 부직포16 U bolt guide 17 wire 18 nonwoven fabric
19 : 핀 20 : 와이어 21 : U볼트19: Pin 20: Wire 21: U bolt
22 : 수중 구조물 23 : 기중기22: underwater structure 23: crane
이러한 본 발명은 상측에 커버가 형성된 세굴방지망의 내부에 보형편과 U볼트가이드가 형성된 형틀을 삽입 설치하고, 그 내측으로 잡석이나 자갈크기로 분쇄된 콘크리트를 채운 후 커버를 씌워 세굴방지망의 상측을 폐쇄하며, 수중구조물의 바닥에 부직포와 상기 세굴방지망을 설치한 다음 U볼트로 세굴방지망을 연결하여서 되는 수중 구조물의 세굴방지공 및 이를 이용한 시공방법을 제안한다.The present invention is installed by inserting the mold formed with the prosthesis piece and the U bolt guide inside the scour prevention net having a cover formed on the upper side, and fill the top of the scour prevention net by filling the crushed concrete into rubble or gravel size inside the cover. The present invention proposes a scour prevention hole and a construction method using the same by closing a non-woven fabric and the scour prevention net at the bottom of the underwater structure and then connecting the scour net with a U bolt.
이로써 본 발명은 제조원가가 저렴하고 설치공정이 용이하며 우수한 세굴방지효과가 있다.As a result, the present invention has low manufacturing cost, easy installation process, and excellent scour prevention effect.
상기와 같은 본 발명의 구성 및 작용을 첨부한 도면에 의거 상세히 설명하면 다음과 같다.Referring to the configuration and operation of the present invention as described above in detail as follows.
도 4는 본 발명에 의한 세굴방지망을 도시한 사시도이고, 도 5는 본 발명에 의한 형틀을 도시한 사시도이며, 도 6 및 도 7은 본 발명에 의한 세굴방지공의 제작과정도, 도 8은 본 발명에 의한 부직포의 시공상태도, 도 9는 본 발명에 의한 세굴방지공의 시공상태도, 도 10은 본 발명에 의한 세굴방지공의 시공 공정도이다.4 is a perspective view showing a scour prevention net according to the present invention, Figure 5 is a perspective view showing a mold according to the present invention, Figures 6 and 7 is a manufacturing process of the scour prevention ball according to the present invention, Figure 8 is 9 is a construction state diagram of a nonwoven fabric according to the present invention, FIG. 9 is a construction state diagram of a scour prevention hole according to the present invention, and FIG. 10 is a construction process diagram of a scour prevention hole according to the present invention.
본 발명은 메쉬(철망)로 되며 상측에 커버(12)가 형성되어 내부에 잡석이나 호박돌 크기로 분쇄된 콘크리트를 채울 수 있는 세굴방지망(11)을 구비하고, 몸체(14) 하단에 보형편(15)이 형성되고 외주연에 U볼트(21)가 삽입되는 U볼트가이드(16)가 형성된 형틀(13)을 구비하며, 수중 구조물(22)의 바닥에 설치하기 위한 부직포(18)를 구비하여서 된다.The present invention is a mesh (wire mesh) and the cover 12 is formed on the upper side is provided with a scour prevention net 11 that can fill the crushed concrete to the size of rubble or amber stone therein, the prosthesis piece (below the body 14) 15) is formed and has a mold 13 formed with a U bolt guide 16, the U bolt 21 is inserted in the outer periphery, with a non-woven fabric 18 for installing on the bottom of the underwater structure 22 do.
이와 같이 구성된 세굴방지공(10)을 설치하는 공정은 세굴방지망(11)의 내부에 형틀(13)을 삽입 설치하는 공정(24)과, 상기 형틀(13)의 내측으로 잡석이나 호박돌크기로 분쇄된 콘크리트를 채우고 커버(12)를 씌워 세굴방지망(11)의 상측을 폐쇄하는 공정(25)과, 수중 구조물(22)의 바닥을 정돈하고 부직포(18)를 설치하는 공정(26)과, 수중 구조물(22)에 U볼트(21)가 결합된 와이어(20)를 체결하는 공정(27)과, 상기 부직포(18)의 상측에 세굴방지망(11)을 U볼트(21)로 연결 설치하는 공정(28)과, 세굴방지망(11)에서 형틀(13)을 탈거하는 공정(29)과, 너트로 U볼트(21)를 체결하는 공정(30)으로 된다.The step of installing the scour prevention hole 10 configured as described above is a step 24 of inserting and installing the mold 13 into the scour prevention net 11, and crushing the rubble or amber stone into the mold 13. Filling the concrete and covering the cover 12 to close the upper side of the scour prevention net 11, arranging the bottom of the underwater structure 22 and installing the nonwoven fabric 18, and underwater Process 27 for fastening the wire 20 coupled to the U bolt 21 to the structure 22, and the process of connecting the scour prevention net 11 to the upper side of the nonwoven fabric 18 by the U bolt 21 (28), the process 29 of removing the mold 13 from the scour prevention net 11, and the process 30 of fastening the U bolt 21 with a nut.
이러한 공정을 더욱 상세히 설명하면 다음과 같다.The process is described in more detail as follows.
세굴방지망(11)의 커버(12)를 개방시킨 상태에서 형틀(13)을 내부에 삽입 설치하고, 상기 형틀(13)의 내측으로 잡석이나 호박돌크기로 분쇄된 폐콘크리트 조각을 채워 넣은 다음, 커버(12)를 닫아 세굴방지망(11)의 상측을 폐쇄시키되, 첨부한 도면 도 7로 도시한 바와 같이 커버(12)가 개방되지 않도록 철사(17)나 와이어 등을이용하여 커버(12)와 세굴방지망(11)을 단단히 결속시킨다.The mold 13 is inserted into the mold 13 while the cover 12 of the scour prevention net 11 is opened, and the waste concrete crushed into rubble or amber stones is filled into the mold 13, and then the cover is filled. Closing (12) to close the upper side of the scour prevention net 11, as shown in the accompanying drawings, the cover 12 and the scour using a wire 17 or a wire, so as not to open the cover 12 as shown in FIG. Tighten the guard net 11 firmly.
이후, 세굴방지공(10)을 시공하고자 하는 수중 구조물(22)의 바닥을 정돈하고 부직포(18)를 설치하는데, 이러한 부직포(18)는 수중 구조물(22)의 바닥이 부등침하 되거나 국부 세굴되는 현상을 최소화하기 위한 것으로, 핀(19)으로 바닥에 고정시켜 이동되지 않도록 한다Subsequently, the bottom of the underwater structure 22 to construct the scour prevention hole 10 is arranged and the nonwoven fabric 18 is installed. The nonwoven fabric 18 is unevenly sedimented or locally scoured. To minimize the phenomenon, it is fixed to the floor with a pin (19) to prevent movement
상기 부직포(18)의 설치가 완료되면 U볼트(21)가 결합된 와이어(20)를 수중 구조물(22)에 체결시키고, 기중기(23)를 이용하여 상기 세굴방지망(11)을 부직포(18) 위에 설치하되, 작업자는 수중에서 미리 준비한 U볼트(21)와 수중 구조물(22)에 체결된 U볼트(21)가 형틀(13)의 U볼트가이드(16)에 삽입되도록 하여 인접하는 세굴방지망(11)끼리 연결되도록 하거나, 또는 수상에서 여러개의 세굴방지망(11)을 연결한 후 수평상태로 수중에 침하시키며, 이러한 과정에 의하여 세굴방지망(11)이 수중 구조물(22)의 바닥에 설치되면 상기 기중기(23)를 이용하여 형틀(13)을 위로 올려 세굴방지망(11)에서 제거되도록 한다.When the installation of the nonwoven fabric 18 is completed, the wire 20 coupled with the U bolt 21 is fastened to the underwater structure 22, and the scour prevention net 11 is nonwoven fabric 18 using the crane 23. Although installed above, the operator is to prepare the U-bolt 21 and the U-bolt 21 fastened to the underwater structure 22 prepared in the water to be inserted into the U-bolt guide 16 of the mold 13 to the adjacent scour prevention net ( 11) to be connected to each other, or to sink in the water in the horizontal state after connecting the several scour prevention net 11 in the water, if the scour prevention net 11 is installed on the bottom of the underwater structure 22 by the above process Using the crane 23 to raise the mold 13 to be removed from the scour prevention net (11).
상기 형틀(13)은 세굴방지망(11)을 일정한 형태로 유지시키기 위한 것이며, 철사(17)나 와이어가 각 보형편(15)의 사이에서 결속되기 때문에 상기 형틀(13)을 상측으로 당기면 세굴방지망(11)만 남고 형틀(13)은 들어올려져 제거되는 것이다.The mold 13 is for keeping the scour prevention net 11 in a constant shape, and the wire 17 or the wire is bound between the prosthetic pieces 15 so that the scuffing net is pulled upward. Only the mold 11 remains and the mold 13 is lifted and removed.
이와 같이 하여 형틀(13)이 제거되면 세굴방지망(11)이 U볼트(21)로 연결된 상태로 수중 구조물(22)의 바닥에 있게 되며, 이후 상기 U볼트(21)를 너트로 체결하여 고정시키면 작업이 완료된다.When the mold 13 is removed in this manner, the scour prevention net 11 is at the bottom of the underwater structure 22 in a state connected with the U bolt 21, and then the U bolt 21 is fixed by fastening with a nut. The task is complete.
이러한 공정으로 시공된 세굴방지공(10)은 여러개의 세굴방지망(11)이 연결되어 일체화되었기 때문에 유속이 빠르거나 와류현상에 의하여 국부적인 세굴이나 침하현상에 대처능력이 우수하고, 유실될 우려가 없어 장기적으로 장갑화현상 발생시 지반부등침하나 토사 또는 암반의 유실을 효과적으로 방지하게 된다.The scour prevention hole 10 constructed by such a process is excellent in coping with local scour or sinking phenomenon due to high flow rate or vortex due to multiple scour prevention nets 11 connected to each other, and may be lost. In the long term, when the glove formation occurs, it effectively prevents ground subsidence or loss of soil or rock.
상기한 바와 같이 본 발명은 버려지는 잡석이나 폐콘크리트 조각이 채워진 세굴방지망을 수상에서 일체화로 연결하여 일시 침하시키거나 수중에서 연결 설치하는 것으로, 시공현장에서 제작이 가능하고 자원을 재활용할 수 있으며, 광범위한 범위에 걸친 세굴방지 또는 국부적인 세굴방지 등 필요한 크기로 제작과 시공이 가능한 장점이 있어 시공의 용이성, 시공비용의 절감, 공사기간 단축 등의 경제적 효과와, 수중 구조물의 바닥침식이나 세굴방지, 장기적인 장갑화 현상으로 토사 또는 암반의 유실현상을 방지하는 효과가 있다.As described above, the present invention connects scour prevention nets filled with rubble or waste concrete to be integrated in the water and temporarily settles or connects in water, and can be manufactured at construction sites and recycle resources. It can be manufactured and constructed in the required size such as prevention of scour or local scour over a wide range, and economic effects such as ease of construction, reduction of construction cost, shortening construction period, prevention of floor erosion or scour of underwater structure, Long-term armored effect is to prevent the loss of soil or rock.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2001-0059666A KR100411530B1 (en) | 2001-09-26 | 2001-09-26 | Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2001-0059666A KR100411530B1 (en) | 2001-09-26 | 2001-09-26 | Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20030026611A KR20030026611A (en) | 2003-04-03 |
KR100411530B1 true KR100411530B1 (en) | 2003-12-18 |
Family
ID=29562335
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2001-0059666A Expired - Fee Related KR100411530B1 (en) | 2001-09-26 | 2001-09-26 | Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100411530B1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7345701B1 (en) * | 2023-07-26 | 2023-09-15 | 前田工繊株式会社 | How to remove the scour prevention unit |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62233318A (en) * | 1986-04-03 | 1987-10-13 | Nippon Kooken Kk | Concrete sink frame |
JPS6419623U (en) * | 1987-07-24 | 1989-01-31 | ||
JPH01120519U (en) * | 1988-02-09 | 1989-08-15 | ||
JPH03224906A (en) * | 1990-01-31 | 1991-10-03 | Nippon Kikai Kogyo Kk | Rotary corrosion-proof device |
JPH073801A (en) * | 1993-06-16 | 1995-01-06 | Koiwa Kanaami Kk | Box for simple earth retaining wall |
JPH0941342A (en) * | 1995-07-26 | 1997-02-10 | Nippon Steel Metal Prod Co Ltd | Beach stabilization structure |
US5762448A (en) * | 1996-05-29 | 1998-06-09 | Continuum Dynamics, Inc. | System for alleviating scouring around submerged structures |
JP2000144675A (en) * | 1998-11-04 | 2000-05-26 | Taisei Corp | Scour prevention method |
KR20000010719U (en) * | 1998-11-25 | 2000-06-26 | 김춘웅 | MESH GABION for wire mesh |
JP2000319842A (en) * | 1999-05-06 | 2000-11-21 | Seiritsu Shoko Kk | Scour preventive material |
KR200225654Y1 (en) * | 2000-12-23 | 2001-06-01 | 주식회사정도엔지니어링 | High density net lon for scour protection |
-
2001
- 2001-09-26 KR KR10-2001-0059666A patent/KR100411530B1/en not_active Expired - Fee Related
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62233318A (en) * | 1986-04-03 | 1987-10-13 | Nippon Kooken Kk | Concrete sink frame |
JPS6419623U (en) * | 1987-07-24 | 1989-01-31 | ||
JPH01120519U (en) * | 1988-02-09 | 1989-08-15 | ||
JPH03224906A (en) * | 1990-01-31 | 1991-10-03 | Nippon Kikai Kogyo Kk | Rotary corrosion-proof device |
JPH073801A (en) * | 1993-06-16 | 1995-01-06 | Koiwa Kanaami Kk | Box for simple earth retaining wall |
JPH0941342A (en) * | 1995-07-26 | 1997-02-10 | Nippon Steel Metal Prod Co Ltd | Beach stabilization structure |
US5762448A (en) * | 1996-05-29 | 1998-06-09 | Continuum Dynamics, Inc. | System for alleviating scouring around submerged structures |
JP2000144675A (en) * | 1998-11-04 | 2000-05-26 | Taisei Corp | Scour prevention method |
KR20000010719U (en) * | 1998-11-25 | 2000-06-26 | 김춘웅 | MESH GABION for wire mesh |
JP2000319842A (en) * | 1999-05-06 | 2000-11-21 | Seiritsu Shoko Kk | Scour preventive material |
KR200225654Y1 (en) * | 2000-12-23 | 2001-06-01 | 주식회사정도엔지니어링 | High density net lon for scour protection |
Also Published As
Publication number | Publication date |
---|---|
KR20030026611A (en) | 2003-04-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100919759B1 (en) | Eco-friendly vegetation mat method and vegetation mat for drainage and scour prevention | |
EP3736382B1 (en) | Erosion prevention unit and erosion prevention method | |
CN107859055B (en) | A kind of lattice guest's Retaining wall method applied to bank slope protection | |
CN109024481B (en) | River course bank slope protection structure and river course bank slope protection method | |
CN106192653A (en) | A kind of Duo Xue district road crossing avalanche slide rock body subgrade drainage system and construction method | |
KR100411530B1 (en) | Water Stream Tunnel Prevent Hole of Construction On The Water and Execution Methode Thereof | |
CN212452472U (en) | Waterfront river course slope protection structure | |
KR100950248B1 (en) | Method of constructing gabion and gabion | |
KR100884017B1 (en) | Construction method of slope for natural environment restoration type | |
CN214061478U (en) | Ecological wall of hydraulic engineering | |
KR200409161Y1 (en) | Assembly panel Gabion box suitable for the construction method of Gabion retaining wall | |
KR100461664B1 (en) | Structures and system of construction based on the use of plants growing block that protect a shore | |
KR101684340B1 (en) | Scour protection system for shore and its installation methods | |
KR200413124Y1 (en) | Hexapods to prevent scouring underwater structures | |
KR100560390B1 (en) | Scour prevention structure of a well well foundation for bridge using a scour prevention framework filled with beads | |
KR100992076B1 (en) | Structure of raising the ground level and excecution method thereof | |
KR100691502B1 (en) | Scour prevention device for underwater structures and repair method of scour site of underwater structure | |
CN218880907U (en) | Ecological bank protection of gabion | |
KR102533827B1 (en) | Natural grass turf vegetation bag for river shoreline vegetation netting and vegetation netting revetment method using the same | |
KR100519108B1 (en) | A bank protection for protecting river bank, having vegetating block | |
CN216339290U (en) | Ecological bank protection structure | |
KR102548639B1 (en) | Construction method of upper net binding type stone protection structure | |
CN214089884U (en) | Shallow karst cave that buries fills construction structures | |
KR20120008147A (en) | Gabion with dividing line and its installation method | |
KR100701299B1 (en) | Construction Method of Retaining Wall Using Assembly Panel Gabion Box |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20010926 |
|
PA0201 | Request for examination | ||
PG1501 | Laying open of application | ||
E701 | Decision to grant or registration of patent right | ||
PE0701 | Decision of registration |
Patent event code: PE07011S01D Comment text: Decision to Grant Registration Patent event date: 20031124 |
|
GRNT | Written decision to grant | ||
PR0701 | Registration of establishment |
Comment text: Registration of Establishment Patent event date: 20031204 Patent event code: PR07011E01D |
|
PR1002 | Payment of registration fee |
Payment date: 20031204 End annual number: 3 Start annual number: 1 |
|
PG1601 | Publication of registration | ||
PR1001 | Payment of annual fee |
Payment date: 20061204 Start annual number: 4 End annual number: 4 |
|
PR1001 | Payment of annual fee |
Payment date: 20071129 Start annual number: 5 End annual number: 5 |
|
PR1001 | Payment of annual fee |
Payment date: 20081201 Start annual number: 6 End annual number: 6 |
|
PR1001 | Payment of annual fee |
Payment date: 20091201 Start annual number: 7 End annual number: 7 |
|
PR1001 | Payment of annual fee |
Payment date: 20101206 Start annual number: 8 End annual number: 8 |
|
FPAY | Annual fee payment |
Payment date: 20111205 Year of fee payment: 9 |
|
PR1001 | Payment of annual fee |
Payment date: 20111205 Start annual number: 9 End annual number: 9 |
|
FPAY | Annual fee payment |
Payment date: 20121204 Year of fee payment: 10 |
|
PR1001 | Payment of annual fee |
Payment date: 20121204 Start annual number: 10 End annual number: 10 |
|
LAPS | Lapse due to unpaid annual fee | ||
PC1903 | Unpaid annual fee |