[go: up one dir, main page]

JPS63277306A - Execution of floor panel joint of precast concreat beam - Google Patents

Execution of floor panel joint of precast concreat beam

Info

Publication number
JPS63277306A
JPS63277306A JP62110770A JP11077087A JPS63277306A JP S63277306 A JPS63277306 A JP S63277306A JP 62110770 A JP62110770 A JP 62110770A JP 11077087 A JP11077087 A JP 11077087A JP S63277306 A JPS63277306 A JP S63277306A
Authority
JP
Japan
Prior art keywords
joint
joints
covering material
construction
floor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP62110770A
Other languages
Japanese (ja)
Other versions
JPH0625454B2 (en
Inventor
広一 鈴木
田辺 大三郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PS Concrete Co Ltd
Original Assignee
PS Concrete Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PS Concrete Co Ltd filed Critical PS Concrete Co Ltd
Priority to JP62110770A priority Critical patent/JPH0625454B2/en
Publication of JPS63277306A publication Critical patent/JPS63277306A/en
Publication of JPH0625454B2 publication Critical patent/JPH0625454B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Road Paving Structures (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、プレキャストコンクリート桁の床版目地の施
工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Field of Application] The present invention relates to a method for constructing slab joints in precast concrete girders.

ざらに詳しくは、型枠支保工や足場を用いることなく、
また脱型を要することなく、プレキャストコンクリート
桁の床版の水密な目地を迅速に施工する方法に関し、例
えば落石や崩落の危険のある道路等に施設するロックシ
ェード等、長時間の交通遮断をすることができない作業
現場での床版の目地の施工に最適な施工方法を提供しよ
うとするものである。
In more detail, without using formwork or scaffolding,
We also describe a method for rapidly constructing watertight joints in precast concrete girder deck slabs without the need for demolding, such as lock shades installed on roads where there is a risk of falling rocks or collapses, to block traffic for long periods of time. The purpose is to provide an optimal construction method for constructing floor slab joints at work sites where it is impossible to do so.

〔従来の技術〕[Conventional technology]

以下山地におけるロックシェードの施工を例に挙げて説
明する。
The construction of rock shades in mountainous areas will be explained below as an example.

山地の斜面や沢または河川の斜面に沿う道路等では、落
石や崩落の危険のある個所が多く存在し、これらめ危険
を防止する゛ために、種々の施策が取られている。
Roads along the slopes of mountains, streams, or rivers are often at risk of falling rocks or collapses, and various measures are being taken to prevent these risks.

このような施策の一つとして、道路上を覆う構造物(ロ
ックシェード)を構築することが行われている。
One such measure is to construct structures (rock shades) that cover roads.

このような構造物は、 (イ)落石等に対して十分安全な強度を必要とする。Such structures are (b) Requires sufficient strength to be safe against falling rocks, etc.

(ロ)山地道路等であるため、外に通行路がないのが普
通であるから、施工に当っては交通遮断を避けるか、遮
断するとしても極小時間の遮断に制限しなければならな
い。
(b) Since the road is located in a mountainous area, there are usually no outside roads, so when constructing the road, it is necessary to avoid blocking traffic, or even if it is blocked, it must be limited to a minimum period of time.

(ハ)構造物の屋根に落石に対するクッション材として
土砂を載置するので、雨水の浸透によって泥水がロック
シェード内に流出しないように。
(c) Earth and sand will be placed on the roof of the structure as a cushioning material against falling rocks, so muddy water will not flow into the rock shade due to rainwater seepage.

水密なスラブを形成しなければならない。A watertight slab must be formed.

(ニ)ロックシェード構築現場への材料運搬や現場作業
機械が制限される。
(d) Transportation of materials to the rock shade construction site and on-site work machines will be restricted.

など構造上並びに施工上の制約が大きい。There are significant structural and construction constraints.

以上のような制約を満足する構造物として、強度が大き
く断面が小さく、組立施工が容易なプレキャストコンク
リート桁を、道路を横切って道路上を覆うように連設し
て施工するロックシェードが賞用されている。
As a structure that satisfies the above constraints, the award goes to the rock shade, which is constructed by constructing precast concrete girders that are strong, have a small cross section, and are easy to assemble, and are constructed in a row across the road so as to cover it. has been done.

しかしながら、このような構造物をプレキャスト部材で
構築する場合でも、プレキャストコンクリート桁の床版
の目地部の施工には、従来、ベニヤ板などを用いた型枠
を下方から支持し、この型枠内にコンクリートまたはモ
ルタルを打設し、固化した後この型枠を脱型していた。
However, even when such structures are constructed using precast members, conventionally, when constructing the joints of the deck slabs of precast concrete girders, a formwork made of plywood or the like is supported from below, and the work is carried out within this formwork. Concrete or mortar was poured and the formwork was removed after it had hardened.

従って、交通遮断を極力少じないような作業手順によっ
て施工するためには、目地の施工を小さい区分毎に区切
って短時間に施工するとか、夜間作業によって行うなど
、莫大な手間と工期を費すことが避けられなかった。
Therefore, in order to carry out construction according to a work procedure that minimizes traffic interruption, it is necessary to divide the joint construction into small sections and construct them in a short time, or to carry out work at night, which requires a huge amount of time and effort. It was inevitable.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

本発明はこのような場合に最も適した床版の目地部の施
工方法を提供することを目的とする。
The object of the present invention is to provide a construction method for floor slab joints that is most suitable for such cases.

すなわち、最小限の簡単な足場のみで施工することがで
きること、交通遮断あるいは交通制限を極小に止めるこ
と、目地施工後、短時間後に足場等の取外しを可能とす
ること、脱型手間を省略すること、防水構造の目地を容
易に形成すること等を達成するものである。
In other words, construction can be carried out using only a minimum of simple scaffolding, traffic interruptions or restrictions can be kept to a minimum, scaffolding etc. can be removed a short time after joint construction, and the need for demolding is omitted. In addition, it is possible to easily form joints in a waterproof structure.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は次の工程から成る。 The present invention consists of the following steps.

■ 予め床版の目地部の両表面を覆う細長い2本のブロ
ックを、目地内に埋込まれる鉄筋で連結して構成した目
地被覆材をプレキャストで製作しておく、この目地被覆
材は、2本のブロックの長手方向を平行に、その相互間
隔を床版の厚さより僅かに大きい距離を保って形成して
おく、この目地被覆材は取扱が容易なように、前記ブロ
ックの長さを0.5m〜1m程度に形成しておくとよい
■ A precast joint covering material is made in advance by connecting two elongated blocks that cover both surfaces of the joints of the floor slab with reinforcing bars embedded in the joints. This joint covering material is made by forming book blocks parallel to each other with a distance slightly larger than the thickness of the floor slab.In order to make this joint covering material easy to handle, the length of the blocks is set to 0. It is advisable to form it to about .5m to 1m.

■ 目地被覆材を、その鉄筋が目地内に入り、前記25
本のブロックが床版の目地の表面を覆うように、床版の
端面(桁の両端)から目地部に挿入する。
■ The reinforcing bars of the joint covering material enter the joint, and the
Insert the book block into the joint from the end face of the slab (both ends of the girder) so that it covers the surface of the joint of the slab.

■ 上記目地被覆材の2本のブロックと床版との間の隙
間および目地内にモルタルを打設する。この場合1モル
タルが漏れないようにシールしておく。
■ Place mortar in the gap between the two blocks of joint covering material and the floor slab and in the joint. In this case, seal the mortar to prevent it from leaking.

■ 目地モルタル打設により、床版、目地被覆材はモル
タルと鉄筋を介して一体化するので、そのまま残置すれ
ば、防水目地が完成する。
■ By placing joint mortar, the floor slab and joint covering material are integrated through the mortar and reinforcing bars, so if they are left in place, the waterproof joint is completed.

〔作用〕[Effect]

本発明方法によれば、目地型枠の代りにプレキャストの
目地被覆材を目地部に装着して目地モルタルを施工すれ
ばよく、型枠支持材を不要とし脱型手間も不要となる。
According to the method of the present invention, a precast joint covering material may be attached to the joint portion instead of the joint form, and joint mortar may be applied, thereby eliminating the need for a form support material and the need for demolding.

従って、迅速施工ができ省力的であり、プレキャストコ
ンクリート桁の下方の交通を妨げないで目地充填の施工
をすることができる。
Therefore, construction can be performed quickly and labor-savingly, and joint filling can be performed without interfering with traffic below the precast concrete girder.

また、この方法により施工した目地は、上記目地被覆材
のブロックが目地の外面を形成するので、化粧目地とし
て美観に富み、さらにこのブロックは床版上に一定の高
さとなるので、床コンクリートを施工する際の床コンク
リート上面の高さを決める定規として利用することもで
き便利である。
In addition, the joints constructed using this method are aesthetically pleasing as decorative joints because the blocks of the joint covering material form the outer surface of the joints.Furthermore, the blocks are at a certain height above the floor slab, so they do not require floor concrete. It can also be conveniently used as a ruler to determine the height of the top surface of the concrete floor during construction.

〔実施例〕〔Example〕

第6図に示すような、幅員6mの道路に、プレキャスト
コンクリート桁を用いた延長的120mのロックシェー
ドを施工し、その目地を本発明方法によって施工した。
As shown in FIG. 6, a 120 m long rock shade using precast concrete girders was constructed on a road with a width of 6 m, and its joints were constructed by the method of the present invention.

第6図(a)はロックシェードの正面図、第6図(b)
はその側面図でありその横方向延長は省略しである。第
6図のロックシェードの一部切欠斜視図を第5図に示し
た。また第6図(b)のA部拡大図を第7図に示した。
Figure 6(a) is a front view of the lock shade, Figure 6(b)
is a side view thereof, and its lateral extension is omitted. A partially cutaway perspective view of the lock shade shown in FIG. 6 is shown in FIG. Further, an enlarged view of part A in FIG. 6(b) is shown in FIG. 7.

第6図において、道路20は斜面11に隣接しており、
コンクリート擁壁12および柱13の上に桁14を架設
し、車両限界16を保持すると共に、これを道路長手方
向に連接し、その上にクッション材として土砂15を載
置した。このロックシェードは、必要な道路空間を保持
すると共に、斜面11の上方からの落石等があった場合
にこれを受けて道路20を保護し、道路通行者の安全を
図る。
In FIG. 6, the road 20 is adjacent to the slope 11,
A girder 14 was constructed on the concrete retaining wall 12 and pillars 13 to maintain a vehicle limit 16 and connected in the longitudinal direction of the road, and earth and sand 15 was placed thereon as a cushioning material. This rock shade not only maintains the necessary road space, but also protects the road 20 from falling rocks from above the slope 11, thereby ensuring the safety of road users.

第7図に示すように、ps接する桁14の床版17を目
地被覆具lで被覆して目地を形成した。また、桁14の
長手方向両端近傍お本び中央部には横桁15が設けられ
ており、その目地は別の目地被覆具5を用いて目地を形
成した。
As shown in FIG. 7, a joint was formed by covering the floor slab 17 of the girder 14 in contact with ps with a joint covering tool l. In addition, cross beams 15 are provided near both ends in the longitudinal direction of the beam 14 and at the center thereof, and the joints are formed using another joint cover 5.

使用した桁材は第7図に示す断面を有し、その寸法、仕
様は次の通りである。
The girder material used had the cross section shown in Figure 7, and its dimensions and specifications are as follows.

施工道路幅員:6m 施工道路車輌限界二幅6000mm 高さ4700mm プレキャスト桁: 型 式:ボックスタイプ・プレキャスト桁、補強横桁3
個所材き 断 面:幅1980mmX 桁高さ1000mm 長  さ: 9m 床版厚:140mm 目地開口寸法:20〜40mm このプレキャスト桁の目地部を施工する。に当り、第2
図に示すような、幅100mm、厚さ40mm、長さ1
mの細長い2本のブロック2を10本の4mmφの鉄筋
4で結合した第1の目地被覆材1を予め製作した。また
プレキャスト桁に設けた補強横桁14の目地部を施工す
るために。
Construction road width: 6m Construction road vehicle limit double width 6000mm Height 4700mm Precast girder: Model: Box type precast girder, reinforced cross girder 3
Cutting section: width 1980mm x girder height 1000mm length: 9m slab thickness: 140mm joint opening dimensions: 20-40mm The joints of this precast girder will be constructed. 2nd
As shown in the figure, width 100mm, thickness 40mm, length 1
A first joint covering material 1 was prepared in advance by connecting two long and thin blocks 2 of m length with ten reinforcing bars 4 of 4 mm diameter. Also, for constructing the joints of the reinforcing cross beams 14 provided on the precast girders.

第4図に示す第2の目地被覆材5も予め製作した。第2
の目地被覆材5は、補強横桁14の3面の目地露出部を
覆うため、第4図に示すように、断面が@100 m 
m 、厚さ40mmの対向する2本の鉛直被覆ブロック
6および同断面の底辺ブロック7を一体に成型したU字
形をなし、その内部に6 m mφの鉄筋4を配設した
The second joint covering material 5 shown in FIG. 4 was also manufactured in advance. Second
The joint covering material 5 covers the exposed joint parts on three sides of the reinforcing cross beam 14, so the cross section is @100 m as shown in FIG.
Two opposing vertical covering blocks 6 with a thickness of 40 mm and a bottom block 7 with the same cross section were integrally molded to form a U-shape, and reinforcing bars 4 with a diameter of 6 mm were disposed inside the U-shape.

第5図はこの目地の施工段階を説明する斜視図であって
、手前の桁14を一部切り取って、目地部に目地被覆材
l、5を装着した状態が解るように描いである。
FIG. 5 is a perspective view illustrating the construction stage of this joint, with the front girder 14 partially cut out to show the state in which the joint covering materials 1 and 5 are attached to the joint.

目地の施工は次の(I)、(II)、(m)の工程から
なる手順で行った。
Construction of the joints was carried out using the following steps (I), (II), and (m).

(I)  プレキャスト桁の中央部横桁の目地の施工 (II)  床版部目地の施工 (m)  プレキャスト桁端部の横桁目地の施工法に上
記CI)、(II)、(III)の工程のそれぞれの施
工手順は次の通りである。
(I) Construction of the joints of the cross girder at the center of the precast girder (II) Construction of the joints of the deck slab (m) The above CI), (II), and (III) are applied to the construction method of the cross girder joints at the end of the precast girder. The construction procedures for each stage are as follows.

(I)  中央部横桁の目地の施工 1) 擁壁12および柱13上に、桁14を架設する。(I) Construction of joints of central cross beam 1) Erection of girder 14 on retaining wall 12 and pillar 13.

2) 隣接する桁14の中央部横桁18の目地に第4図
に示す第2の目地被覆材5を装着する。まず目地被覆材
5のU字型の底部にシール材またはパツキン材を取り付
け、横桁部の上からロープをさげ目地被覆材5をこのロ
ープで引き上げ、横桁目地部に取り付ける。第3図は横
桁18の目地部に目地被覆材5を取り付けた状態を示す
もので、第3図(a)は水平断面図(第7図に示した■
−■矢視断面図)、第3図(b)は第3図Ca)のB−
B矢視図である。
2) Attach the second joint covering material 5 shown in FIG. 4 to the joints of the central cross beams 18 of the adjacent girders 14. First, a sealing material or packing material is attached to the U-shaped bottom of the joint covering material 5, a rope is placed over the crossbeam, the barb joint covering material 5 is pulled up with this rope, and is attached to the crossbeam joint. Fig. 3 shows the state in which the joint covering material 5 is attached to the joint part of the cross beam 18, and Fig. 3 (a) is a horizontal cross-sectional view (
-■ Cross-sectional view in the direction of arrows), Figure 3 (b) is B- of Figure 3 Ca)
It is a view from arrow B.

3) 床版に予め設けである4個の穴19から目地被覆
材5と横桁18との隙間にシール材8を打ち込み、目地
モルタル打設時のペースト漏れ防止にする。
3) A sealing material 8 is driven into the gap between the joint covering material 5 and the cross beam 18 through four holes 19 previously provided in the floor slab to prevent paste leakage when placing joint mortar.

4) 目地被覆材5の形成した目地空間にコンクリート
またはモルタルを打ち込む、目地被覆材5と横桁18は
モルタル9、ずれ止め用キイ18aおよび鉄筋4を介し
て一体化する。
4) Concrete or mortar is poured into the joint space formed by the joint covering material 5. The joint covering material 5 and the cross beam 18 are integrated via the mortar 9, the anti-slip key 18a, and the reinforcing bar 4.

5) 次に床版部目地の施工にうつる。5) Next, move on to construction of the floor slab joints.

(■) 床版部目地の施工 l) 第2図に示すような、長さ1mの2本の平板状の
コンクリートブロック2.3を鉄筋4で連結した目地被
覆材1を予め製作しておき、その下側のブロック3の上
面にシール材を貼る。
(■) Construction of joints in the floor slab l) As shown in Figure 2, a joint covering material 1 is made in advance by connecting two flat concrete blocks 2.3 with a length of 1 m with reinforcing bars 4. , a sealing material is pasted on the upper surface of the block 3 below it.

2) 隣接する桁14の床版17の目地部に、桁14の
両端から、目地被覆材1を順次目地部に挿入する。挿入
は上下のブロックがそれぞれ床版の上下面に沿い、鉄筋
4が床版の目地内に入るようにする。第1図はこの状態
を示す断面図で隣接する桁14の床版17が形成する目
地部に目地被覆材1が挿入されている。目地被覆材lは
上記A工程で施工した桁14の中央補強横桁部から桁1
4の端部方向へ隙間なく連接する。
2) The joint covering material 1 is sequentially inserted into the joints of the floor slabs 17 of adjacent girders 14 from both ends of the girders 14. The upper and lower blocks are inserted along the upper and lower surfaces of the floor slab, respectively, and the reinforcing bars 4 are inserted into the joints of the floor slab. FIG. 1 is a sectional view showing this state, and the joint covering material 1 is inserted into the joint formed by the floor slabs 17 of the adjacent girders 14. The joint covering material l is applied to the girder 1 from the central reinforced cross girder part of the girder 14 constructed in step A above.
Connects to the end of 4 without any gaps.

3) 桁14の両端部の横桁18部には長さを調整した
目地被覆材1を使用する。
3) Use joint covering material 1 whose length is adjusted for the crossbeams 18 at both ends of the girder 14.

4) 目地被覆材lの上側のブロック2と床版17の上
面との間に、シール材例えば木製キャンバを打込み、ブ
ロック2の高さを一定にする。
4) A sealing material such as wooden camber is placed between the block 2 above the joint covering material l and the upper surface of the floor slab 17 to keep the height of the block 2 constant.

5) 目地空間にコンクリートまたはモルタル9を打設
して密実な目地を施工すると共に、目地被覆材lと床版
17とをモルタル9、ずれ止め用キイ17aおよび鉄筋
4を介して一体化する。
5) Concrete or mortar 9 is poured into the joint space to create a tight joint, and the joint covering material 1 and the floor slab 17 are integrated via the mortar 9, the anti-slip key 17a, and the reinforcing bar 4. .

(III)  桁端部の横桁目地の施工1) 次に桁1
4の両端の端部横桁18の目地の施工を行う、端部横桁
18の目地の施工は、上記(II)の工程の中央部横桁
の施工と同様である。
(III) Construction of cross girder joints at girder ends 1) Next, girder 1
The construction of the joints of the end cross beams 18 at both ends of 4 is the same as the construction of the center cross beams in step (II) above.

〔発明の効果〕〔Effect of the invention〕

本発明方法によれば、支保工や足場が極めて簡単になり
、またすべての部材がプレキャスト化されるので場所打
ちコンクリートが少なく、型枠が不要で脱枠手間が無く
、型枠取付け、目地施工または目地手直しのための足場
も不要となり、目地からの落下物の危険も皆無となり、
支保工や足場を迅速に撒去することができる。従って、
施工期間が短縮され、交通遮断や交通制限を著しく短縮
することができる。
According to the method of the present invention, shoring and scaffolding are extremely simple, and since all parts are precast, there is less concrete cast in place, no formwork is required, there is no need to remove the frame, and there is no need for formwork installation or joint construction. Also, there is no need for scaffolding to repair the joints, and there is no danger of objects falling from the joints.
Shoring and scaffolding can be quickly removed. Therefore,
The construction period is shortened, and traffic closures and traffic restrictions can be significantly reduced.

また施工された目地は防水性能がよく、また化粧目地と
なり美観上優れている。さらに、梁の一部が破損したよ
うな場合でもその梁の交換が可能である。
In addition, the constructed joints have good waterproof performance and are decorative joints that are aesthetically pleasing. Furthermore, even if a part of the beam is damaged, that beam can be replaced.

なお、以上の説明では、ロックシェードを例に挙げて説
明したが、本発明方法はこれに限るものではなく、プレ
キャスト桁の目地部施工に、広く用いることができる。
In addition, in the above description, the rock shade was explained as an example, but the method of the present invention is not limited to this, and can be widely used for construction of joints of precast girders.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明方法の実施例を示す床版目地部の断面図
、第2図は目地被覆材の斜視図、第3図は横桁部の目地
部の断面図、第4図はU字状の目地被覆材の斜視図、第
5図はロックシェードの一部断面斜視図、第6図(a)
はロックシェードの正面図、第6図(b)はその側面図
、第7図は第6図(b)のA部拡大図である。 1.5・・・目地被覆材、2,3・・・ブロック、4・
・・鉄筋、9・・・モルタル、14・・・桁、17・・
・床版、18・・・横桁。
Fig. 1 is a sectional view of a floor slab joint showing an embodiment of the method of the present invention, Fig. 2 is a perspective view of a joint covering material, Fig. 3 is a sectional view of a joint of a crossbeam, and Fig. 4 is a U A perspective view of the letter-shaped joint covering material, Fig. 5 is a partially cross-sectional perspective view of the lock shade, Fig. 6 (a)
6 is a front view of the lock shade, FIG. 6(b) is a side view thereof, and FIG. 7 is an enlarged view of section A in FIG. 6(b). 1.5... Joint covering material, 2, 3... Block, 4.
・・Reinforcing bar, 9・mortar, 14・digit, 17・・
・Floor slab, 18... crossbeam.

Claims (1)

【特許請求の範囲】[Claims] 1 床版相互間の目地の両表面を覆う細長い2本のブロ
ックを鉄筋で平行に連結してなる目地被覆材を予め製作
しておき、該目地被覆材を床版の端面から目地部に挿入
し、前記鉄筋が目地内に位置し前記2本のブロックが床
版の目地の表面を覆うように配設し、上記目地被覆材の
2本のブロックと床版との間の隙間および目地内にモル
タルを打設し、前記目地被覆材を床版と一体化させるこ
とを特徴とするプレキャストコンクリート桁の床版目地
の施工方法
1. A joint covering material is made in advance by connecting two elongated blocks in parallel with reinforcing bars to cover both surfaces of the joint between the floor slabs, and the joint covering material is inserted into the joint from the end surface of the floor slab. The reinforcing bars are located within the joint and the two blocks are arranged so as to cover the surface of the joint of the floor slab, and the gap between the two blocks of the joint covering material and the floor slab and the inside of the joint are A method for constructing floor slab joints in precast concrete girders, characterized by placing mortar on the floor slab and integrating the joint covering material with the floor slab.
JP62110770A 1987-05-08 1987-05-08 Construction method of flange joint of precast concrete girder Expired - Lifetime JPH0625454B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62110770A JPH0625454B2 (en) 1987-05-08 1987-05-08 Construction method of flange joint of precast concrete girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62110770A JPH0625454B2 (en) 1987-05-08 1987-05-08 Construction method of flange joint of precast concrete girder

Publications (2)

Publication Number Publication Date
JPS63277306A true JPS63277306A (en) 1988-11-15
JPH0625454B2 JPH0625454B2 (en) 1994-04-06

Family

ID=14544143

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62110770A Expired - Lifetime JPH0625454B2 (en) 1987-05-08 1987-05-08 Construction method of flange joint of precast concrete girder

Country Status (1)

Country Link
JP (1) JPH0625454B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011069064A (en) * 2009-09-24 2011-04-07 Taisei Corp Joint structure of precast member, and construction method of the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011069064A (en) * 2009-09-24 2011-04-07 Taisei Corp Joint structure of precast member, and construction method of the same

Also Published As

Publication number Publication date
JPH0625454B2 (en) 1994-04-06

Similar Documents

Publication Publication Date Title
US5367845A (en) System for building a structure
US6098367A (en) Constructive system applied for buildings
KR102018767B1 (en) Precast concrete wall using cast in place concrete and concrete construction include this same
KR100784201B1 (en) Tunnel construction method using steel pipe loop structure in rock section
EP0079887B1 (en) Multi-purpose precast concrete panels, and methods of constructing concrete structures employing the same
JPS63277306A (en) Execution of floor panel joint of precast concreat beam
KR100510092B1 (en) A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it
KR100546432B1 (en) Covered arch composite structure using precast concrete panel and steel frame and construction method
JP2536376B2 (en) Foundation structure of shed for road protection
JP2979117B2 (en) Building foundation method
ATE37929T1 (en) TUNNEL PROCESS.
JP2656892B2 (en) Underground structure construction method and continuous underground wall construction method
JP2556772B2 (en) Construction method of precast concrete board and wall structure using precast concrete board
JP2579120B2 (en) garage
NL1025567C2 (en) Construction method for tunnel beneath road, by laying new road surface with concrete panels, forming support columns for these panels and excavating beneath panels
JPH04293824A (en) Construction method for large span underground structure
JPH06228979A (en) Inverted lining method for building-construction
KR100789990B1 (en) Prefabricated Panels for Structures
JPH02266016A (en) Structural process of underground concrete body of building
JPH04360908A (en) Underground wall construction method and underground wall construction formwork
JP4919079B2 (en) Protective structure
JPS6157731A (en) Construction of culvert
JPS59114313A (en) Construction of prestressed concrete floor panel in road bridge
CN117127999A (en) Synchronous construction method for double working surfaces of internal structure of single-pipe double-layer shield tunnel
JPH0523661Y2 (en)