JPS63110399A - Method and device for carrying in material of tunnel excavation - Google Patents
Method and device for carrying in material of tunnel excavationInfo
- Publication number
- JPS63110399A JPS63110399A JP61256398A JP25639886A JPS63110399A JP S63110399 A JPS63110399 A JP S63110399A JP 61256398 A JP61256398 A JP 61256398A JP 25639886 A JP25639886 A JP 25639886A JP S63110399 A JPS63110399 A JP S63110399A
- Authority
- JP
- Japan
- Prior art keywords
- capsule
- shaft
- capsules
- materials
- tunnel excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000000463 material Substances 0.000 title claims description 67
- 238000009412 basement excavation Methods 0.000 title claims description 25
- 238000000034 method Methods 0.000 title claims description 11
- 239000002775 capsule Substances 0.000 claims description 122
- 230000032258 transport Effects 0.000 description 20
- 238000010304 firing Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 208000027418 Wounds and injury Diseases 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 238000002716 delivery method Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 230000034179 segment specification Effects 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は、シールドトンネル掘削時に、セグメント等
の資材をトンネル内セグメント組立地点まで主として空
気圧により搬入する方法およびその装置に関するもので
ある。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method and apparatus for transporting materials such as segments to a segment assembly point in a tunnel mainly by pneumatic pressure during excavation of a shield tunnel.
従来のこの種の資材搬入方法としては、立坑上でセグメ
ントなどの資材をホイスト等で吊って立坑底部に降ろし
、バフテリーカーで牽引される台車に資材を載せて、バ
フテリーカーおよび台車をトンネル内に敷設されたレー
ル上を走行させてセグメント組立地点まで資材を搬送す
る方法がある。The conventional method for bringing in materials of this type is to hang materials such as segments on a shaft using a hoist, lower them to the bottom of the shaft, place the materials on a cart pulled by a buff terry car, and then install the buff terry car and cart into the tunnel. There is a method of transporting materials to the segment assembly point by running them on rails.
しかしながら、このような従来の資材搬入方法の場合、
次のような種々の問題点がある。However, in the case of such conventional material delivery methods,
There are various problems as follows.
(i)ホイスト等で吊下げられてくる資材を、立坑下で
待ちかまえていた作業員が立坑上のホイスト運転員と連
絡をとりながら、台車上に載せるが、立坑の上と下とで
は15〜30mの高低差があり、この連係作業で台車上
に載せるには長時間を要する。(i) A worker who has been waiting below the shaft to place the materials suspended by a hoist, etc., onto a trolley while communicating with the hoist operator above the shaft. There is a difference in height, and it takes a long time to put it on the trolley.
(ii )前述の作業時に、資材が落下して人身事故を
含む重大災害につながる危険性も高い。(ii) During the above-mentioned work, there is a high risk that materials will fall, leading to serious accidents including personal injury.
(iii )現場によっては資材を台車に載せる前に仮
置することもあり、この場合には、さらに工数と人員が
増えざるを得ない。(iii) Depending on the site, materials may be temporarily stored before being placed on a trolley, and in this case, the number of man-hours and personnel will inevitably increase.
(iv )バッテリーカーと台車によるトンネル内の資
材搬入では、バッテリーカーの運転要員が必要となる。(iv) When carrying materials into the tunnel using a battery car and a trolley, a battery car operator is required.
(ν)搬送中にはトンネル内での歩行者との接触事故や
バッテリーカーの脱線事故などが予想される。(ν) During transport, collisions with pedestrians in tunnels and battery car derailment accidents are expected.
(vi)バッテリーカー走行のためにレールおよびレー
ル受材が必要となり、当然その搬入および設置にも工数
を要する。(vi) Rails and rail support materials are required for the battery car to run, and of course it takes a lot of man-hours to transport and install them.
この発明は、このような問題点を解消すべく提案された
もので、その目的は、安全かつ迅速に資材を搬入でき、
さらに省力化、低廉化を図れるトンネル掘削における資
材搬入方法およびその装置を提供することにある。This invention was proposed to solve these problems, and its purpose is to transport materials safely and quickly.
Furthermore, it is an object of the present invention to provide a method and apparatus for carrying in materials in tunnel excavation, which can save labor and reduce costs.
〔問題点を解決するための手段・作用〕この発明に係る
資材搬入方法は、水平坑の掘進に伴なってカプセル輸送
用管路を延長してゆき、立坑の上部でカプセルに資材を
積込み、立坑底部に搬送した後、この資材積載カプセル
を空気圧によりカプセル輸送用管路の始端に移送すると
ともにメインブロアの空気圧によりカプセル輸送用管路
内を水平項先端まで押送し、荷卸の終ったカプセルをメ
インブロアの空気圧により立坑まで搬出し、立坑上部の
積込部に移送し、安全かつ迅速にセグメント等の資材を
水平坑先端に搬入できるようにしたものである。[Means/effects for solving the problem] The method for carrying in materials according to the present invention extends the capsule transport conduit as the horizontal shaft is excavated, loads the materials into the capsules at the upper part of the shaft, and After being transported to the bottom of the shaft, the material-loaded capsules are pneumatically transferred to the starting end of the capsule transportation pipeline, and the main blower's air pressure is used to push the capsule transportation pipeline to the tip of the horizontal section, where the unloaded capsules are transported. The air pressure of the main blower is used to transport materials such as segments to the shaft and to the loading area at the top of the shaft, allowing materials such as segments to be safely and quickly transported to the tip of the horizontal shaft.
さらに、メインブロアは、立坑側、掘進側のどちらに設
置してもよく、立坑側と掘進側の両方に設置してもよい
。Furthermore, the main blower may be installed on either the shaft side or the excavation side, or may be installed on both the shaft side and the excavation side.
また、掘進側に不要物積込部を設けるとともに、立坑上
部に不要物荷卸部を設け、資材の荷卸の終ったカプセル
に積込んで搬出させることもできる。Further, it is also possible to provide an unnecessary material loading section on the excavation side and an unnecessary material unloading section at the upper part of the shaft, so that materials can be loaded into the capsule after unloading and carried out.
次に、この発明に係る資材搬入装置は、立坑上部から立
坑底部にかけて無端状に配設された搬送体に、カプセル
を積載し得るゴンドラが複数取付けられ、カプセルを昇
降させ得る鉛直搬送機と、
既設の水平坑内に水平坑の掘進に伴って延設され、前記
カプセルが通過し得るカプセル輸送用゛管路と、
前記鉛直搬送機のゴンドラ内の資材積載カプセルを空気
圧により前記カプセル輸送用管路の始端に移送するとと
もに空気圧によりカプセル輸送用管路内を水平坑先端ま
で押送し、かつ、水平坑先端の空カプセルを空気吸引に
より立坑まで返送し、鉛直搬送機の空ゴンドラに挿入し
得るカプセル発着装置とから構成し、資材を積載したカ
プセルの押送、空カプセルの回収が安全且つ迅速に行な
えるようにしたものである。Next, the material carrying device according to the present invention includes a vertical conveyor that can move the capsules up and down, in which a plurality of gondolas that can load capsules are attached to a conveyor that is arranged in an endless manner from the top of the shaft to the bottom of the shaft; A capsule transport pipeline that is extended as the horizontal shaft is excavated into an existing horizontal shaft, through which the capsules can pass; and a capsule transport pipeline that pneumatically transports the material-loaded capsules in the gondola of the vertical conveyor. A capsule that can be transferred to the starting end of the tunnel and pushed through the capsule transportation pipeline to the tip of the horizontal shaft using air pressure, and the empty capsule at the tip of the horizontal hole can be returned to the vertical shaft by air suction and inserted into the empty gondola of the vertical conveyor. It consists of a take-off and landing device, and is designed to safely and quickly transport capsules loaded with materials and retrieve empty capsules.
以下、この発明を図示する一実施例に基づいて説明する
。The present invention will be described below based on an illustrated embodiment.
第1図、第2図に示すように、立坑1内に鉛直搬送機2
およびカプセル発着装置3を設けるとともに、既設の水
平坑4内にカプセル輸送用管路5を設置し、水平坑4の
掘進に伴なってカプセル輸送用管路5を延長してゆき、
立坑1の上部でカプセル6にセグメント等の資材を積込
み、この資材積載カプセル6を鉛直搬送機2により立坑
1底部に搬送し、力、プセル発着装置3によりカプセル
6をカプセル輸送用管路5の始端に空気圧で移送すると
ともにカプセル輸送用管路5内を空気圧で押送し、セグ
メント組立装置7の手前までカプセル6を搬入する。As shown in Figures 1 and 2, a vertical conveyor 2 is installed inside the shaft 1.
In addition to installing a capsule arrival and departure device 3, a capsule transportation pipeline 5 is installed in the existing horizontal shaft 4, and as the horizontal shaft 4 is excavated, the capsule transportation pipeline 5 is extended.
Materials such as segments are loaded into the capsule 6 at the top of the shaft 1, and the material-loaded capsule 6 is transported to the bottom of the shaft 1 by the vertical conveyor 2. The capsule 6 is transferred to the starting end using pneumatic pressure and is also pushed through the capsule transport conduit 5 using pneumatic pressure to carry the capsule 6 up to the front of the segment assembly device 7.
カプセル輸送用管路5は単位短管を接続して構成され、
カプセル6は、この単位短管も搬送し、搬入された単位
短管を荷卸部8の手前に挿入・接続し、カプセル輸送用
管路5を延長する。The capsule transport conduit 5 is constructed by connecting unit short pipes,
The capsule 6 also transports this unit short tube, inserts and connects the carried unit short tube to the front of the unloading section 8, and extends the capsule transportation conduit 5.
資材が卸された空カプセル6′はカプセル発着装置3に
より吸引返送され、鉛直搬送機2により立坑1の上部に
移送され、資材が積込まれる0以上を繰り返すことによ
りセグメント、単位短管などの資材の搬入が行なわれる
。The empty capsule 6' loaded with materials is sucked back by the capsule loading/unloading device 3, transferred to the upper part of the shaft 1 by the vertical conveyor 2, and is loaded with materials. Materials will be brought in.
鉛直搬送a2は、第3図に示すように、観覧車タイプで
あり、立坑1内に鉛直に配設されたチェーンコンベア9
と、カプセル6を収納し得るゴンドラ10からなる。チ
ェーンコンベア9は、立坑1上部に設置されたスブロケ
ッ)9Aと、立坑1底部に設置された一対のスプロケッ
ト9Bと、これらスプロケットに無端状に巻掛けられた
チェーン9Cとからなり、チェーン9CにゴンドラlO
が接続部材11を介して複数取付けられている。As shown in FIG. 3, the vertical conveyance a2 is of a Ferris wheel type, and is a chain conveyor 9 disposed vertically within the shaft 1.
and a gondola 10 that can accommodate the capsule 6. The chain conveyor 9 consists of a sprocket 9A installed at the top of the shaft 1, a pair of sprockets 9B installed at the bottom of the shaft 1, and a chain 9C wound endlessly around these sprockets. lO
are attached via connecting members 11.
ゴンドラ10は、接続部材11の先端に上部が軸着され
て常に水平状態を維持することができ、また上部に上蓋
を有するとともに前後面が開口している。さらに、開口
部以外はカプセル6を覆う構造であり、資材の落下の心
配はない。The gondola 10 has an upper portion pivoted to the tip of the connecting member 11 so that it can maintain a horizontal state at all times, and has an upper lid on the upper portion and is open on the front and rear surfaces. Furthermore, the structure covers the capsule 6 except for the opening, so there is no fear of materials falling.
さらに、チェーンコンベア9の下部は、一対のスプロケ
ット9Bにより幅広とされ、後述するカプセル発着装置
3の発射ゾーン12と到着ゾーン13の手前にゴンドラ
10が位置できるようにされている。Further, the lower part of the chain conveyor 9 is widened by a pair of sprockets 9B, so that the gondola 10 can be positioned in front of a launch zone 12 and an arrival zone 13 of a capsule landing and landing device 3, which will be described later.
カプセル発着装置3は、第2図に示すように、本管用弁
V1、ゾーン切替装置14、発射ゾーン12、到着ゾー
ン13、ゾーン用弁V、、V。As shown in FIG. 2, the capsule landing and departure device 3 includes a main valve V1, a zone switching device 14, a launch zone 12, an arrival zone 13, and zone valves V, V.
サブブロア15、メインブロア16、ブロア吐出側の弁
1)IxI)!、ブロア吸引側の弁S、〜S、などから
なる。Sub blower 15, main blower 16, blower discharge side valve 1) IxI)! , valves S, ~S, etc. on the blower suction side.
サブブロア15は、ゴンドラ10内の資材積載カプセル
6を発射ゾーン12内に移送し、あるいは到着ゾーン1
3内の空カプセル6′を空のゴンドラ10内に挿入する
ために設けられている。The sub-blower 15 transports the material loading capsule 6 in the gondola 10 into the launch zone 12 or the arrival zone 1.
3 is provided for inserting the empty capsule 6' into the empty gondola 10.
メインブロア16は、後に詳述するように、弁■1〜■
1、D、〜D1、sl〜s、を適宜選択することにより
、吐出側で資材積載カプセル6を押送搬入し、吸引側で
空カプセル6′を吸引搬出するために設けられている。The main blower 16 has valves ■1 to ■, as will be explained in detail later.
1, D, ~D1, and sl~s, the material-loaded capsules 6 are pushed in on the discharge side, and the empty capsules 6' are suctioned out on the suction side.
カプセル輸送用管路5は、第4図に示すように、既設の
水平坑4の下部に支持架台17を介して設置され、断面
が長方形とされている。長方形としたのは、第5図に示
すような単位短管5Aが通過できるようにするためであ
り、単位短管5Aの断面寸法および長さは、第9図、第
10図に示すように、カプセル6に収容できるようにす
る。また、単位短管5Aの一方の端部には、係合部材5
Bを突設し、節単に継ぎ足せるようにされている。As shown in FIG. 4, the capsule transport conduit 5 is installed at the bottom of the existing horizontal shaft 4 via a support frame 17, and has a rectangular cross section. The reason why the rectangular shape is made is to allow the unit short tube 5A shown in FIG. 5 to pass through, and the cross-sectional dimensions and length of the unit short tube 5A are as shown in FIGS. 9 and 10. , so that it can be accommodated in the capsule 6. Further, an engaging member 5 is provided at one end of the unit short pipe 5A.
B is provided protrudingly so that joints can be easily added.
カプセル6は、第11図、第12図に示すように、断面
が長方形で上部が開口した直方体の容器であり、例えば
セグメントを1個あるいは2個の単位短管5Aと2個の
支持架台17を収納できる大きさとされている。As shown in FIGS. 11 and 12, the capsule 6 is a rectangular parallelepiped container with a rectangular cross section and an open top, and includes, for example, one or two segment short unit tubes 5A and two support frames 17. It is said to be large enough to store.
カプセル6の前後面には受圧板18が設けられ、前後の
差圧により推進し得るようにされ、受圧板18には一対
の主車輪19、一対のガイド車輪20.II街器21が
設けられている。また、側面および底面は、フレーム2
2により骨組みされ、資材の落下を防止すべく図示しな
い板が貼られている。なお、セグメント受架台を口約と
したカプセルの内部の前後にはセグメント受23、セグ
メント受架台24が取付けられている。A pressure receiving plate 18 is provided on the front and rear surfaces of the capsule 6 so that the capsule 6 can be propelled by a pressure difference between the front and rear surfaces, and the pressure receiving plate 18 has a pair of main wheels 19, a pair of guide wheels 20. A II street appliance 21 is provided. Also, the sides and bottom are frame 2
2, and a board (not shown) is attached to prevent materials from falling. Incidentally, a segment receiver 23 and a segment receiver 24 are attached to the front and rear of the inside of the capsule, which uses the segment receiver as an opening.
以上のような構成において継ぎのような順序で資材の搬
入・空カプセルの返送が行なわれる。In the above configuration, materials are carried in and empty capsules are returned in a sequential order.
(i)地上の積込場において、ゴンドラ10の上蓋を開
けて、中の空カプセル6′にセグメントなどの資材を積
込み、ゴンドラ10の上蓋を閉める。チェーンコンベア
9が第3図の矢印方向に動いて、資材積載カプセル6を
立坑底部に送り、空カプセル6′の入ったゴンドラ10
を積込場に移動させる。(i) At the loading area on the ground, the top cover of the gondola 10 is opened, materials such as segments are loaded into the empty capsule 6', and the top cover of the gondola 10 is closed. The chain conveyor 9 moves in the direction of the arrow in FIG.
be moved to the loading area.
資材積載カプセル6が発射ゾーン12に対応した位置に
くると、サブブロア15の吐出空気によりカプセル6が
発射ゾーン12に送り込まれる。こうして発射ゾーン1
2には、1両〜数両のカプセル6が送り込まれ、スタン
バイ状態となる。When the material loading capsule 6 comes to a position corresponding to the firing zone 12, the capsule 6 is sent into the firing zone 12 by the air discharged from the sub-blower 15. Thus, launch zone 1
2, one to several capsules 6 are sent to it, and it becomes a standby state.
(’ii )以下、次表のような弁の切換により、第1
3図に示すようにカプセルのハンドリングが行なわれる
。('ii) Hereafter, by switching the valves as shown in the following table, the first
Capsule handling is performed as shown in Figure 3.
弁 状 態
(0:開、S:閉、−:任意)
第13図(a)の状態で荷卸の終了したカプセル(群)
が到着ゾーン13へ完全に納まると、切替装置14が発
射ゾーン12に切替わり、メインブロア16の吐出空気
が発射ゾーン12に吹込まれてスタンバイ状態にあった
カプセル6 (群)が発射される(弁状Bk、第13図
(bl参照)。Valve status (0: open, S: closed, -: optional) Capsules (group) that have been unloaded in the state shown in Figure 13 (a)
When the capsules 6 are completely settled in the arrival zone 13, the switching device 14 switches to the firing zone 12, the air discharged from the main blower 16 is blown into the firing zone 12, and the capsules 6 (group) that were in the standby state are fired ( Valvular Bk, Fig. 13 (see bl).
カプセル6が完全に切替装置14を通過すると弁状態が
Bに変わり(第13図(C)参照)、空気圧による押送
によりカプセル6が掘進側の荷卸部8まで搬送される。When the capsule 6 completely passes through the switching device 14, the valve state changes to B (see FIG. 13(C)), and the capsule 6 is conveyed to the unloading section 8 on the excavation side by being pushed by air pressure.
(iii )荷卸部8は、第14図に示すように、先端
に向かって下り勾配のトラフ25.アンローダ26、ス
トッパー27からなり、カプセル6が到着するとアンロ
ーダ26によりセグメント等の資材が卸される。(iii) As shown in FIG. 14, the unloading section 8 has a trough 25. It consists of an unloader 26 and a stopper 27, and when the capsule 6 arrives, the unloader 26 unloads materials such as segments.
この間、メインプロア16はスタンバイ状態(遠心式ブ
ロアでは吐出側全閉、容積式ブロアでは吐出側全開)で
も、弁の状態をBにして空気を送り込んでもよい。空気
を送り込むようにすれば、換気設備をなくすことができ
る。During this time, the main blower 16 may be in a standby state (the discharge side is fully closed in the case of a centrifugal blower, and the discharge side is fully open in the case of a positive displacement blower), or the valve state may be set to B to send air. By pumping in air, you can eliminate the need for ventilation equipment.
(iv)荷卸が完了すると、空のカプセル6′をアンロ
ーダ26あるいは自走式のストッパー27によって管端
に押し込み、弁状態をCあるいはDとし、メインプロア
16の吸引により空カプセル6′が立坑1に向かって返
送される(第13図(d)参照)。(iv) When the unloading is completed, the empty capsule 6' is pushed into the pipe end by the unloader 26 or the self-propelled stopper 27, the valve state is set to C or D, and the empty capsule 6' is pushed into the shaft 1 by the suction of the main proar 16. (See Figure 13(d)).
単位短管5Aが1人された場合には、返送後、挿入・接
続を行なう。If one person inserts the unit short pipe 5A, insert and connect it after returning it.
到着ゾーン13に未だ空カプセルが残っている場合には
、切替装置14が発射側めままで弁がCの状態にあり、
到着ゾーン13が空になると、切替え装置14が到着側
に切替わって弁がDの状態となり、空カプセル6′が到
着ゾーン13に挿入される。If there are still empty capsules remaining in the arrival zone 13, the switching device 14 is on the launch side and the valve is in the C position,
When the arrival zone 13 is empty, the switching device 14 is switched to the arrival side, the valve is in the state D, and the empty capsule 6' is inserted into the arrival zone 13.
(v)到着ゾーン13内に収納された空カプセル6′は
空のゴンドラ10が到着側に位置した時、サブプロア1
5の吸引力でゴンドラ10内に送り込まれ、チェーンコ
ンベア9により地上の積込場まで運ばれる。(v) When the empty gondola 10 is located on the arrival side, the empty capsule 6' stored in the arrival zone 13
It is sent into the gondola 10 by the suction force of 5, and is transported to the loading area on the ground by the chain conveyor 9.
通常の運転状態では、水平の空気カプセル輸送部分が(
ii)〜(iv )を連続して行ない、鉛直搬送機部分
がこれとマツチングするように、(i)と(v)の作業
を繰り返す。Under normal operating conditions, the horizontal air capsule transport part (
Steps ii) to (iv) are performed continuously, and steps (i) and (v) are repeated so that the vertical conveyor section matches this.
なお、工事が完了すれば、単位短管5Aを先端側から取
外し順次カプセルで返送し、支持架台17はその後不要
部分を撤去する。When the construction is completed, the unit short pipes 5A are removed from the tip side and sent back in capsule form, and the unnecessary parts of the support frame 17 are then removed.
また、本発明では、レール、ルール受材がないのでシー
ルド掘進を行なっている後方で、二次覆工作業を容易に
行なうこと−ができる。Further, in the present invention, since there are no rails or rule supports, secondary lining work can be easily performed behind the shield excavation.
以上の記述はメインブロアを立坑部に置き、その吐出側
でカプセルを搬入し、吸引側でカプセルを搬出すること
を前提としているが、メインブロアをシールド掘進部に
置いてその吸引側でカプセルを搬入し、吐出側でカプセ
ルを搬出することも可能であり、また、メインブロアを
立坑部とシールド掘進部の両側に置いてそれぞれのブロ
アでカプセル搬入と搬出とを行なうことも可能である。The above description assumes that the main blower is placed in the shaft section, and the capsules are carried in on the discharge side, and the capsules are taken out on the suction side. It is also possible to carry the capsules in and carry them out on the discharge side, or it is also possible to place main blowers on both sides of the shaft part and the shield excavation part and carry out capsule carrying and carrying out with each blower.
また、本発明と同様の構成において、積込部と荷卸部と
を反対に設置して(立坑上部に荷卸部を、シールド掘進
部に積込部)掘進によって生じた不要物(ずりなど)を
搬出することもでき、立坑上部に資材の積込装置と不要
物の荷卸装置とを設け、シールド掘進部に資材の荷卸装
置と不要物の積込装置とを設けることにより、資材の搬
入と不要物の搬出とを行なうこともできる。 次に具体
例について説明する。これは外径14mのシールドトン
ネルに適用し例で、各諸元は次のとおりである。In addition, in the same configuration as the present invention, the loading section and the unloading section are installed oppositely (the unloading section is at the top of the shaft, and the loading section is at the shield excavation section) to remove unnecessary materials (such as shear) caused by excavation. By installing a material loading device and an unloading device for unnecessary materials at the top of the shaft, and a material unloading device and an unnecessary material loading device in the shield excavation section, it is possible to carry in and remove unnecessary materials. It is also possible to carry out items. Next, a specific example will be explained. This is an example applied to a shield tunnel with an outer diameter of 14 m, and each specification is as follows.
(i)セグメント諸元(13分割)
外径 14m Wさ 0,6m
幅 1.2m 長さ 3.6m
重量 6700kg
(ii)カプセル諸元
第1表 カプセル積載部寸法
カプセル重量: 1600 (kg)
カプセル受圧面積: 1.34 Cn()カプセルもれ
率* : 0.0236
*カプセルを通過して流れる空気量を管路の断面積で除
してみかけの空気速度とし、これをカプセル前後の差圧
を用いて無次元化した量をもれ率と称する。(i) Segment specifications (13 divisions) Outer diameter 14m Width 0.6m Width 1.2m Length 3.6m Weight 6700kg (ii) Capsule specifications Table 1 Capsule loading area dimensions Capsule weight: 1600 (kg) Capsule Pressure-receiving area: 1.34 Cn () Capsule leakage rate*: 0.0236 *The amount of air flowing through the capsule is divided by the cross-sectional area of the pipe line to obtain the apparent air velocity, and this is the differential pressure before and after the capsule. The quantity made dimensionless using is called the leakage rate.
カプセルころがり抵抗数: o、oi。Capsule rolling resistance number: o, oi.
(iii )管路諸元
管路長辺内寸: 1.39 (m)
管路短辺内寸: 1.01 (m)
単位短管長さ:0.6 (m) (有効長)管路長
:2.3 (km)
以上のような諸元において、1リング掘進するのに必要
なものは、
セグメント13個(カプセル13両)
単位短管2本、架台2個(カプセル1両)その他の資材
(カプセル1両)
であり、15両のカプセルを必要とする。(iii) Pipe specifications Pipe long side inner dimension: 1.39 (m) Pipe short side inner dimension: 1.01 (m) Unit short pipe length: 0.6 (m) (Effective length) Pipe Length: 2.3 (km) Based on the above specifications, what is required to excavate one ring is: 13 segments (13 capsules), 2 unit short pipes, 2 frames (1 capsule), etc. of materials (1 capsule), and 15 capsules are required.
一方、掘進速度を8リング/ day (9,6m/d
ay)とすると、1リング分の資材を3時間で輸送する
必要がある。すなわち、所要輸送量は5両/hとなる。On the other hand, the digging speed was set to 8 rings/day (9.6 m/d
ay), it is necessary to transport one ring of materials in three hours. In other words, the required transportation amount is 5 cars/h.
5両単位で輸送すると1サイクルが60分となり、ハン
ドリング等の余裕をみると走行時間が50分となる。When transported in units of 5 cars, one cycle takes 60 minutes, and taking into consideration handling margins, the running time becomes 50 minutes.
このような走行時間でブロアを選定すれば、第2表のよ
うな仕様となる。If a blower is selected based on such running time, the specifications will be as shown in Table 2.
第2表 ブロアの仕様例
2.3km全て水平のラインAでは、カプセル速度が搬
入時1.37m/s、排出時1.79+m/sとなる。Table 2 Blower Specification Example On Line A, which is 2.3 km completely horizontal, the capsule speed is 1.37 m/s at the time of loading and 1.79+m/s at the time of discharge.
搬入側に1k111の4%下り傾斜を有する2、31u
nのラインBでは、到着速度1.11m/s 、 IM
入側傾斜部で4.11m/s 、 fjt出側水平部で
1.87m/sとなる。2,31u with a 4% downward slope of 1k111 on the loading side
On line B of n, the arrival speed is 1.11 m/s, IM
The speed is 4.11 m/s at the entrance slope and 1.87 m/s at the fjt exit horizontal section.
走行時間を短縮したい場合には、例えば、カプセルの最
高速度を5m/sとし、到着側200m区間の速度を1
.5m/sとする。この時間の走行時間は片道553秒
となり、往復で1107秒(18,4分)、1サイクル
は28.4分、1リング分の資材搬入には、合計85.
3分となる。If you want to shorten the travel time, for example, set the maximum speed of the capsule to 5 m/s and set the speed in the 200 m section on the arrival side to 1.
.. It is assumed to be 5 m/s. The running time for this time is 553 seconds one way, 1107 seconds (18.4 minutes) round trip, 28.4 minutes per cycle, and a total of 85.
It will be 3 minutes.
この場合のブロアは、風ffi 400 tri /m
in以上のものを使用する。The blower in this case has a wind ffi of 400 tri/m
Use more than in.
前述のとおり、この発明によれば資材を積載したカプセ
ルあるいは空カプセルを立坑内で鉛直搬送し、この鉛直
搬送と連動する空気カプセル輸送により資材積載カプセ
ルの押送あるいは空カプセルの返送を行なうようにして
構成したため、次のような効果を奏する。As described above, according to the present invention, capsules loaded with materials or empty capsules are conveyed vertically in a shaft, and the capsules loaded with materials are transported or the empty capsules are returned by air capsule transportation linked to this vertical conveyance. Due to this configuration, the following effects are achieved.
(i)立坑下でのホイスト運転員、作業員が不要となり
、省力化を図れ、資材落下による事故を解消できる。(i) Hoist operators and workers under the shaft are no longer required, saving labor and eliminating accidents caused by falling materials.
(ii)立坑下の資材仮置場が不要となる。(ii) Temporary materials storage under the shaft becomes unnecessary.
(iii )従来のバッテリーカーおよび台車の資材搬
入中の事故がなくなり、安全性の向上を図れる。(iii) Accidents during material transport using conventional battery cars and trolleys are eliminated, and safety can be improved.
(iv)バッテリーカー運転要員が不要になる。さらに
、レールおよびレール受材が不要となり、その搬入にか
かる作業員も不要となり、省力化を図れる。(iv) Battery car operating personnel become unnecessary. Furthermore, there is no need for rails or rail receiving materials, and there is no need for workers to carry them in, resulting in labor savings.
(v)速度を大きくできるので、短時間に搬入できる。(v) Since the speed can be increased, transportation can be carried out in a short time.
(vi)空気の送入・排出が可能となり、工事用換気設
備をなくすことができる。(vi) Air can be introduced and discharged, eliminating the need for construction ventilation equipment.
(vii )以上から、資材搬入工費の低廉化を図れる
。(vii) From the above, it is possible to reduce the cost of bringing in materials.
(viii ) レール、レール受材がないのでシー
ルド掘進を行なっている後方で二次覆工作業を容易に行
なうことができる。(viii) Since there are no rails or rail supports, secondary lining work can be easily carried out behind the shield excavation.
(j×)空カプセルに、すり等の不要物を積込んで搬出
させることができる。(j×) It is possible to load unnecessary items such as pickpockets into empty capsules and transport them.
第1図、第2図は、この発明に係る資材搬入工費を示す
正面図、平面図、第3図は鉛直確送機を示す正面図、第
4図はカプセル輸送用管路の設置状態を示す部分断面図
、第5図は単位短管を示す斜視図、第6図は単位短管の
底部を示す斜視図、第7図、第8図は単位短管を架台に
乗せた状況の側面図および正面図、第9図、第10図は
単位短管のカプセルへの積載状態を示す平面図、側面図
、第11図、第12図はカプセルを示す斜視図、正面図
、第13図(al〜(81はカプセルの発着状況を順に
示した概略図、第14図は荷卸し部を示す概略図である
。
1〜−〜−−−−・立坑、2−・・・・・鉛直殿送機、
3−・−カプセル発着WE、4−・・・−水平坑、5−
・・−カプセル輸送用管路、5A・・−一一一一単位短
管、5B−・−・係合部材、6・−−−−一−カプセル
、6電・−一一一一空のカプセル、7・−・−・−セグ
メント組立装置、8−・・・−荷卸部、9−−−−一・
チェーンコンベア、9A、913−・−スプロケット、
9 C−−−−−−−−チェーン、i o−−−−−−
−ゴンドラ、11−−一−−・−接続部材、12−・−
・・発射ゾーン、13−−−−−−一到着ゾーン、14
−−−−−−−ゾーン切替装置、1′5・・・・−サブ
プロア、16−・・−・−メインブロア、17−・・−
・支持架台、i 5−−−−・・受圧板、19−・・−
主車輪、20−・・−ガイド車輪、21−・・・・・緩
衝器、22・−−一−−−フレーム、23−・・−セグ
メント受、24−−−−−−−セグメント受架台、25
−−−−−−一トラフ、26−・−・−アンローダ、2
7・−−ストッパー、28−・−・・−積込部。
第9図
第1012I
第14図Figures 1 and 2 are a front view and a plan view showing the cost of carrying in materials according to the present invention, Figure 3 is a front view showing a vertical feeder, and Figure 4 is a diagram showing the installation state of a pipeline for transporting capsules. 5 is a perspective view showing the unit short tube, FIG. 6 is a perspective view showing the bottom of the unit short tube, and FIGS. 7 and 8 are side views of the unit short tube placed on a stand. Figures 9 and 10 are plan views and side views showing how unit short tubes are loaded into the capsule, Figures 11 and 12 are perspective views, front views, and Figure 13 showing the capsule. (al ~ (81 is a schematic diagram showing the status of capsule arrival and departure in order, and Figure 14 is a schematic diagram showing the unloading section. 1 ~ - ~ - - Vertical shaft, 2 - Vertical Tono transport machine,
3-...-Capsule departure/arrival WE, 4-...-Horizontal shaft, 5-
...-Capsule transport conduit, 5A...-1111 unit short pipe, 5B--Engaging member, 6----1-capsule, 6 electric--1111 empty Capsule, 7.--Segment assembly device, 8--Unloading section, 9.--1.
Chain conveyor, 9A, 913--sprocket,
9 C---------Chain, i o---------
-Gondola, 11--1--・-Connection member, 12--
...Launch zone, 13--Arrival zone, 14
--------Zone switching device, 1'5...-Sub blower, 16-...-Main blower, 17-...-
・Support frame, i 5----...Pressure plate, 19-...-
Main wheel, 20--Guide wheel, 21--Buffer, 22--1--Frame, 23--Segment support, 24--Segment support frame , 25
−−−−−−1 trough, 26−・−・−unloader, 2
7.--stopper, 28-.--loading section. Figure 9 1012I Figure 14
Claims (7)
おいて、掘進中の水平坑先端に資材を搬入する資材搬入
方法であって、 水平坑の掘進に伴ってカプセル輸送用管路 を延長してゆき、立坑の上部でカプセルに資材を積込み
、立坑底部に搬送した後、この資材積載カプセルを空気
圧により前記カプセル輸送用管路の始端に移送するとと
もにメインブロアの空気圧によりカプセル輸送用管路内
を水平坑先端まで押送し、荷卸の終ったカプセルをメイ
ンブロアの空気圧により立坑まで搬出し、立坑上部の積
込部に移送することを特徴とするトンネル掘削の資材搬
入方法。(1) In tunnel excavation in which a horizontal shaft is excavated from the bottom of a shaft, materials are brought into the tip of the horizontal shaft being excavated, and the capsule transport conduit is extended as the horizontal shaft is excavated. After loading materials into capsules at the top of the shaft and transporting them to the bottom of the shaft, the material-laden capsules are transferred to the starting end of the capsule transportation pipeline using air pressure, and the inside of the capsule transportation pipeline is moved using the air pressure of the main blower. A method for transporting materials for tunnel excavation, characterized by pushing the capsules to the tip of a horizontal shaft, carrying the unloaded capsules to the shaft using air pressure from a main blower, and transferring them to a loading section at the top of the shaft.
プセルを押送搬入し、吸引側でカプセルを吸引搬出する
ことを特徴とする特許請求の範囲第1項記載のトンネル
掘削の資材搬入方法。(2) A method for transporting materials for tunnel excavation according to claim 1, characterized in that a main blower is installed on the shaft side, the capsules are pushed in on the discharge side, and the capsules are sucked out on the suction side. .
プセルを吸引搬入し、吐出側でカプセルを押送搬出する
ことを特徴とする特許請求の範囲第1項記載のトンネル
掘削の資材搬入方法。(3) A method for transporting materials for tunnel excavation according to claim 1, characterized in that a main blower is installed on the excavation side, the suction side carries in the capsules, and the discharge side pushes the capsules out. .
ことを特徴とする特許請求の範囲第1項記載のトンネル
掘削の資材搬入方法。(4) The method for transporting materials for tunnel excavation according to claim 1, characterized in that main blowers are installed on both the shaft side and the excavation side.
部に不要物荷卸部を設け、カプセルに不要物を積込んで
搬出させることを特徴とする特許請求の範囲第2項、第
3項、第4項記載のトンネル掘削の資材搬入方法。(5) An unnecessary material loading section is provided on the excavation side, and an unnecessary material unloading section is provided at the upper part of the shaft, and the unnecessary material is loaded into the capsule and carried out.Claims 2 and 3 4. Method of transporting materials for tunnel excavation as described in Section 4.
た搬送体に、カプセルを積載し得るゴンドラが複数取付
けられ、カプセルを昇降させ得る鉛直搬送機と、 既設の水平坑内に水平坑の掘進に伴なって 延設され、前記カプセルが通過し得るカプセル輸送用管
路と、前記鉛直搬送機のゴンドラ内の資材積載カプセル
を空気圧により前記カプセル輸送用管路の始端に移送す
るとともに空気圧によりカプセル輸送用管路内を水平坑
先端まで押送し、かつ、水平坑先端の空カプセルを空気
吸引により立坑まで返送し、鉛直搬送機の空ゴンドラに
挿入し得るカプセル発着装置とからなることを特徴とす
るトンネル掘削の資材搬入装置。(6) A plurality of gondolas capable of loading capsules are attached to a conveyor arranged endlessly from the top of the shaft to the bottom of the shaft, a vertical conveyor capable of raising and lowering the capsules, and excavation of a horizontal shaft within an existing horizontal shaft. A capsule transportation pipeline is extended along with the capsule transportation, through which the capsules can pass, and the material-loaded capsules in the gondola of the vertical conveyor are pneumatically transferred to the starting end of the capsule transportation pipeline, and the capsules are transported by pneumatic pressure. It is characterized by comprising a capsule loading and unloading device that can push the capsule through the transportation pipeline to the tip of the horizontal shaft, return the empty capsule at the tip of the horizontal shaft to the vertical shaft by air suction, and insert it into the empty gondola of the vertical conveyor. Equipment for transporting materials for tunnel excavation.
メインブロア、カプセルのゴンドラへの出し入れ用サブ
ブロア、発射ゾーン、到着ゾーン、ゾーン切替装置を有
していることを特徴とする特許請求の範囲第3項記載の
トンネル掘削の資材搬入装置。(7) Claims characterized in that the capsule landing/departing device has a main blower for pushing and suctioning the capsule, a sub-blower for taking the capsule in and out of the gondola, a launch zone, an arrival zone, and a zone switching device. The material carrying device for tunnel excavation described in paragraph 3.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61256398A JPH0646000B2 (en) | 1986-10-28 | 1986-10-28 | Material loading method and device for tunnel excavation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61256398A JPH0646000B2 (en) | 1986-10-28 | 1986-10-28 | Material loading method and device for tunnel excavation |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63110399A true JPS63110399A (en) | 1988-05-14 |
JPH0646000B2 JPH0646000B2 (en) | 1994-06-15 |
Family
ID=17292121
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP61256398A Expired - Fee Related JPH0646000B2 (en) | 1986-10-28 | 1986-10-28 | Material loading method and device for tunnel excavation |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0646000B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02194297A (en) * | 1989-01-20 | 1990-07-31 | Shimizu Corp | Automatic material transport method in shield construction method |
JP2016008436A (en) * | 2014-06-25 | 2016-01-18 | 西松建設株式会社 | Rotary carry-in device for materials and equipment |
-
1986
- 1986-10-28 JP JP61256398A patent/JPH0646000B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02194297A (en) * | 1989-01-20 | 1990-07-31 | Shimizu Corp | Automatic material transport method in shield construction method |
JP2016008436A (en) * | 2014-06-25 | 2016-01-18 | 西松建設株式会社 | Rotary carry-in device for materials and equipment |
Also Published As
Publication number | Publication date |
---|---|
JPH0646000B2 (en) | 1994-06-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8182190B2 (en) | Unloading system and method for continuously moving rapid discharge railcars | |
CN106458440A (en) | System and method for delivery of oilfield materials | |
US3521565A (en) | Apparatus for replacing an old track by a new track | |
CN115217500B (en) | Shield segment conveying device and shield segment conveying method | |
US4784257A (en) | Conveyor system including a re-railer | |
US5129761A (en) | Pipe placement method and apparatus | |
CN110219661A (en) | Applied to minimum starting well separate launching corollary apparatus and originate construction method | |
CN207192134U (en) | A kind of shield dregs transportation device | |
US2832297A (en) | Arrangement for warehousing merchandise | |
US3734027A (en) | Intra-factory system and method for utilizing powered and free conveyor systems | |
JPS63110399A (en) | Method and device for carrying in material of tunnel excavation | |
CN221722800U (en) | A system of unearthing that is used for tunnel that entrance to a cave has obstacle | |
CN205953062U (en) | Waste material transportation changes row device | |
JPH07102898A (en) | Vertical transport device and vertical transport method for tunnel construction vehicles | |
RU2208168C2 (en) | Vehicle applicable in mines | |
CN218967873U (en) | Train coal sample slideway conveying device | |
CN105378221B (en) | The method for making component or material be moved to the height of mine drilling system and move in its height | |
CN207416830U (en) | A kind of running gear and stream carrier vehicle | |
JP3031535B2 (en) | Conveyed object transfer device for shield excavation | |
JP2001152789A (en) | Method and device for carrying out muck capable of realizing double track in tunnel having small cross section | |
CN217708593U (en) | Reciprocating slide rail vehicle device | |
JPH0414598A (en) | Excavated soil carrying-out method in tunnel excavation and device thereof | |
CN222137714U (en) | Pipe and rod storage, emission, receiving and transmitting integrated system | |
JPH0414597A (en) | Excavated soil carrying-out method in tunnel excavation and device thereof | |
RU2151873C1 (en) | Railway mobile power plant-gantry and method of its movement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |