[go: up one dir, main page]

JPS62153407A - Construction of artificial land in water - Google Patents

Construction of artificial land in water

Info

Publication number
JPS62153407A
JPS62153407A JP29513785A JP29513785A JPS62153407A JP S62153407 A JPS62153407 A JP S62153407A JP 29513785 A JP29513785 A JP 29513785A JP 29513785 A JP29513785 A JP 29513785A JP S62153407 A JPS62153407 A JP S62153407A
Authority
JP
Japan
Prior art keywords
sand
earth
water
artificial land
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP29513785A
Other languages
Japanese (ja)
Other versions
JPH0619130B2 (en
Inventor
Takehiko Hashimoto
武彦 橋本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitani Sekisan Co Ltd
Original Assignee
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitani Sekisan Co Ltd filed Critical Mitani Sekisan Co Ltd
Priority to JP60295137A priority Critical patent/JPH0619130B2/en
Publication of JPS62153407A publication Critical patent/JPS62153407A/en
Publication of JPH0619130B2 publication Critical patent/JPH0619130B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

PURPOSE:To construct an artificial land in a short time without the needs for coffering work with sheet piles, etc., by a method in which a place where an artificial land is to be constructed is surrounded by a cloth formwork, soil is heaped up in the water area surrounded, and a cloth formwork is set on the slope of the banking. CONSTITUTION:Cloth formworks 2 and 2a are vertically set on the outside of a place where an artificial land is to be constructed and supported by a float 1. A small amount of soil and sand 14 is dumped into the formworks 2 and 2a, and water with soil and sand is charged through a hose 6 into the central part of the left and right-handed cloth formworks 2 and 2a to heap up soil and sand 8. Soil and sand is also charged into the formworks 2 and 2a, the upper parts of the formworks 2 and 2a are made to come near each other, and the slope of the banking is covered with the formworks 2 and 2a. The needs for coffering work with sheet piles, etc., can thus be eliminated, and an artificial land can be constructed.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は水中に人工土地を造築することを目的どした
もので、人工土地造築に関する産業分野に属する。
[Detailed Description of the Invention] (Industrial Application Field) This invention is aimed at constructing artificial land underwater, and belongs to the industrial field related to artificial land construction.

(従来の技術) 従来海岸等の埋立てに際しては、所定の位置へ矢板等を
植設して締切工事を行った後、外側から締切回内へ1ナ
ンドポンプで土砂を送り込み、土地を造成していた。
(Conventional technology) Conventionally, when reclamation on the coast, etc., after constructing a cofferdam by planting sheet piles etc. in predetermined locations, earth and sand was pumped from the outside into the cofferdam pronination using a Nando pump to create the land. Ta.

(発明により解決すべき問題点) 従来技術によれば水中土地の造築に際しては、先づ外囲
を構築する為に、鋼、矢板又はコンクリートシートパイ
ルなどを外囲位置に密接打設しなければならなかったの
で、打設工事に多大の工費、労力および日数を必要とす
るのみならず、浚渫船を出し入れするには、出入口設備
を完備しなりればならず、矢板等を自立させる為には、
水深に比例した打込み深さを必要とし、かつ地盤が耐え
1qるものでなければならないなど、早多の問題点があ
った。
(Problems to be Solved by the Invention) According to the prior art, when constructing underwater land, in order to construct the outer enclosure, steel, sheet piles, or concrete sheet piles must be placed closely at the outer enclosure position. Therefore, not only did the pouring work require a large amount of work cost, labor, and time, but in order to bring in and take out the dredger, it was necessary to have complete entrance and exit facilities, and in order to make the sheet piles stand up on their own. teeth,
Hayata had some problems, such as requiring a driving depth proportional to the water depth, and the ground had to be able to withstand 1q.

(問題点を解決する為の手段) 然るにこの発明は矢板等に代えて布型枠を用い、布型枠
内に充填物を充填することによって逐次締切りしたもの
で、比較的簡単容易に広範囲の締切りが可能であり、前
記問題点を解決したのである。
(Means for solving the problem) However, this invention uses a fabric form instead of sheet piles, etc., and sequentially closes the fabric form by filling it with filler. It is possible to set a deadline, and the above problem has been solved.

即ちこの発明は、人工土地造築予定位置の外囲に布型枠
を縦設し、前記布型枠内へ充填物を送入して当該型枠の
下端部を水底に定着させる。ついで前記型枠で囲まれた
地域の内側へ土砂を送り込んでこれを水中へ盛り上げる
。前記土砂の盛り上げにつれて、盛土砂の斜面を形成し
、所定の高さまで盛土すると共に、外面を補強して人工
土地を造築する。前記にJ3いて、盛土砂に際し斜面に
アンカーを設けて布型枠の傾斜を変えると、安息角より
も著しい大ぎい鮮度で斜面を形成することができる。ま
た土砂の盛上げに際して凝集材を混入すれば、盛土基礎
を一層堅固にすることができる。
That is, in this invention, a fabric form is vertically installed around the outer circumference of a planned artificial land construction position, and a filler is fed into the fabric form to fix the lower end of the form to the water bottom. Then, earth and sand are sent inside the area surrounded by the formwork and raised into the water. As the earth and sand are piled up, a slope of the earth and sand is formed, the earth is banked to a predetermined height, and the outer surface is reinforced to construct artificial land. In J3 mentioned above, if anchors are provided on the slope during embankment sand and the inclination of the fabric form is changed, the slope can be formed with significantly greater freshness than the angle of repose. Furthermore, if an agglomerate is mixed in when the earth and sand is heaped up, the embankment foundation can be made even stronger.

また布型枠の布は、例えば合成樹脂繊維によって織成し
た布を用い、織目は適宜定める。然して型枠にする為に
は、所定間隔(例えば30cm)に二枚の布を並設し、
各対向布間に所定間隔で引張材を設け、土砂等を充填し
た際に並設した布間が過度に聞かないようにしな(プれ
ばならない。また充填材を入れつつ布型枠を繰り出すと
、布型枠の下端側が水底に沿って定置されるので、布型
枠の下端側は自然に定着されることなる。また土砂の盛
土に際し形成される斜面には、前記充填物を入れた布型
枠を被覆すれば、きわめて堅固に補強できると共に、必
要に応じ、前記被覆布型枠上へコンクリートブロックを
敷設すれば、一層堅固に補強される。
Further, the fabric of the fabric form is, for example, a fabric woven from synthetic resin fibers, and the weave is determined as appropriate. However, in order to make a formwork, two pieces of cloth are placed side by side at a predetermined interval (for example, 30 cm),
Place tensile materials at a predetermined interval between each opposing fabric, and make sure that the gap between the parallel fabrics does not become excessive when filling with earth and sand. Then, the lower end of the cloth form is placed along the water bottom, so the lower end of the cloth form is naturally settled.Also, the slope formed when embanking earth and sand is filled with the above-mentioned filler. By covering the cloth formwork, it can be reinforced very firmly, and if necessary, by laying concrete blocks on the covered cloth formwork, it can be reinforced even more firmly.

前記布型枠への充填物としては、土砂、砂利又はコンク
リートなどが考えられる。また盛土は土砂をサンドポン
プで放出し、或いは搬送船を使用して採取地から必要箇
所に運ぶのである。通常布型枠は環状に配設して外囲を
構成し、又は海岸等へ弧状に外囲を作り、或いは海岸と
、沖合の島との間を結びその中間へ土砂を盛り上げるな
ど、従来矢板等の締切で知られている工事に代えて用い
ることができる。
Possible fillers for the cloth formwork include earth and sand, gravel, or concrete. In addition, for embankments, earth and sand are pumped out using sand pumps or transported from the extraction site to the required location using transport vessels. Normally, cloth formwork is arranged in a ring shape to form an outer enclosure, or an arcuate outer enclosure is created toward the coast, or the coast and an offshore island are connected and earth and sand is piled up in the middle. It can be used in place of construction works that are known to have deadlines such as.

(発明の作用) この発明は、布型枠を用いたので、型枠を水底に定着し
、又は盛土の斜面に被覆する際には、単に布を繰り出し
、必要な充填材を充填し、又は浮子を移動するのみで所
定の位置に布型枠が設置される。また布型枠の上端部は
浮子によって支持されている為に、浮子から切り放した
り、又は重錘を連結して、型枠上端部を水中へ沈下させ
ることができる。
(Function of the invention) This invention uses a cloth formwork, so when fixing the formwork on the bottom of the water or covering the slope of an embankment, simply unroll the cloth, fill it with the necessary filler, or The cloth formwork is installed in a predetermined position simply by moving the float. Further, since the upper end of the fabric form is supported by the float, it can be cut off from the float or connected with a weight to sink the upper end of the form into the water.

(実施例) 人工土地造築予定位置を中心にして、その外側へ多数の
浮子1.1aを連結して布型枠2の一側を支持させる。
(Example) A large number of floats 1.1a are connected to the outside of the planned artificial land construction position to support one side of the fabric form 2.

布型枠2には、合成樹脂製の織布3.3aを所定間隔〈
例えば30 cm )に対向させると共に、一定間隔角
に引張線13を定着して、過度の膨化を阻止している。
The cloth formwork 2 is covered with synthetic resin woven cloth 3.3a at predetermined intervals.
For example, 30 cm 2 ) are opposed to each other, and tension lines 13 are fixed at regular intervals to prevent excessive expansion.

前記織布3.3aの上端部は必要長さ宛巻軸4.4aに
巻ぎ込まれており、必要に応じて巻き出すようにしであ
る。前記のようにして布型枠2.2aを予定水域へ敷設
したならば、先づ布型枠2.2a内へ浚渫船5からホー
ス6で土砂14を水と共に布型枠2.2a内へ圧送する
。イ5型枠2.2a内へ入った土砂水の水は布目から外
部へ排出されるので、結局土砂14だけ第2図のように
缶型枠2.2aの下方へ溜る。そこで浮子1.1aを若
干移動すると共に、缶型枠2.2aを必要長さだけ繰り
出し、その下端土砂部を水底7上へ定置する。このよう
にしC1外囲が保定されたならば、浚渫船5からのホー
ス6端を第3図のように左右右型枠2.2aの中央部に
位置させ、土砂水を移送すれば、土砂8は第3図のよう
に盛り上げられる。前記のようにして、土砂盛りの外側
下部が前記缶型枠2.2aの定着部に達したならば、缶
型枠2.2aにも土砂水を供給すると共に、缶型枠2.
2a若干を繰り出し乍ら、若干近接させて、土砂の詰っ
た部分を土砂盛斜面上へ被覆する。前記操作を繰り返し
て、第4図のようにほぼ予定高さに達したならば、前記
土砂入り缶型枠2.2aの上部へコンクリートブロック
9を敷設し、必要に応じ護岸ブロック10を構築し、更
に土砂を盛り上げて人工土地11を完成する。
The upper end of the woven fabric 3.3a is wound onto a winding shaft 4.4a to a required length, and is unwound as required. Once the fabric form 2.2a is laid in the planned water area as described above, first, the dredger 5 uses a hose 6 to force the earth and sand 14 together with water into the fabric form 2.2a. do. (5) The water that has entered the formwork 2.2a is discharged to the outside through the fabric, so that only the sand 14 eventually accumulates below the can formwork 2.2a as shown in FIG. Then, the float 1.1a is moved slightly, the can form 2.2a is let out by the required length, and the lower end of the earth and sand part is placed on the water bottom 7. Once the outer circumference of C1 has been secured in this way, the ends of the hose 6 from the dredger 5 are positioned at the center of the left and right formworks 2.2a as shown in Figure 3, and the earth and sand water is transferred. is excited as shown in Figure 3. As described above, when the outer lower part of the earth and sand embankment reaches the fixed part of the can form 2.2a, earth and sand water is also supplied to the can form 2.2a, and the can form 2.2a is also supplied with earth and sand water.
While paying out some of 2a, move it slightly closer to cover the part filled with earth and sand onto the earth and sand embankment slope. By repeating the above operations, when the planned height is almost reached as shown in Fig. 4, concrete blocks 9 are laid on top of the earth and sand can formwork 2.2a, and bank protection blocks 10 are constructed as necessary. Then, the earth and sand are piled up to complete artificial land 11.

前記において、第3図中鎖線図示のように、缶型枠の一
部へアンカー12を設置し、その被覆角度を急にするこ
ともできる。また土砂中へ凝集材又はセメントモルタル
を注入して土砂の固結化を促進することもできる。前記
実施例においては、浚渫船からホースで土砂を移送した
が、土砂の搬送船を使用し、水上輸送することもできる
。また砂利等をコンベア(フロート支持)で予定位置ま
で運ぶこともできる。このような場合に浮子を沈降すれ
ば容易に水路ができる。即ちこの発明の方法は、人工島
の造築又は水中築堤その他必要な面積と高さに建造物を
構築する際の人工土地造築に用いることができる。
In the above, as shown by the chain line in FIG. 3, the anchor 12 can be installed in a part of the can form to make the covering angle steeper. Further, it is also possible to promote the consolidation of the earth and sand by injecting an agglomerate or cement mortar into the earth and sand. In the embodiments described above, the earth and sand were transferred from a dredger using a hose, but it is also possible to use an earth and sand transport vessel to transport the earth and sand by water. It is also possible to transport gravel, etc. to a predetermined location using a conveyor (float support). In such cases, a waterway can be easily created by letting the float sink. That is, the method of the present invention can be used for artificial land construction when constructing artificial islands, underwater embankments, and other structures of required area and height.

(発明の効果) 即ちこの発明は、缶型枠を使用して水中へ外囲を構築し
、外囲内へ土砂等を放出して人工土地としたので、外囲
の構築が簡単容易で比較的短期間に長大な構築ができる
などの諸効果がある。また缶型枠であるから、定着およ
び移動がきわめて容易であり、造築終期には缶型枠をそ
のまま補強被覆になし得るなどの実用上路効果もある。
(Effects of the Invention) That is, in this invention, an outer enclosure is constructed underwater using a can form, and earth and sand are discharged into the outer enclosure to create an artificial land. It has various effects such as being able to build a large scale in a short period of time. Furthermore, since it is a can form, it is extremely easy to fix and move, and there are also practical benefits such as the can form can be used as a reinforcing coating at the end of construction.

次にこの発明の方法は、高度の技術を必要としないので
、従来技術を習得している作業者ならば、容易かつ急速
に熟練技術者どなって作業に従事することができる。
Secondly, since the method of the present invention does not require a high level of skill, any worker who has mastered the prior art can easily and quickly carry out the work.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の実施例における外囲構築の平面図、
第2図乃至第5図はこの発明の施工順序を示す図で、第
2図は缶型枠設置の側面図、第3図は土砂盛開始の側面
図、第4図は土砂盛斜面に補強を施した側面図、第5図
は人工土地完成時の側面図、第6図はこの発明の缶型枠
の支持状態を示す一部拡大側面図、第7図は同じく缶型
枠の一部拡大斜視図、第8図は同じく缶型枠に土砂を充
填した際の一部拡大斜視図である。 1.1a・・・浮子    2.2a・・・缶型枠4.
4a・・・巻軸    5・・・浚渫船7・・・水底 
      8・・・土砂9・・・コンクリートブロッ
ク 第2図 73143a 第4図 第5図
FIG. 1 is a plan view of the construction of an outer enclosure in an embodiment of the present invention;
Figures 2 to 5 are diagrams showing the construction sequence of the present invention, where Figure 2 is a side view of can formwork installation, Figure 3 is a side view of the start of earth and sand embankment, and Figure 4 is reinforcement on earth and sand embankment slope. Figure 5 is a side view of the completed artificial land, Figure 6 is a partially enlarged side view showing the support state of the can form according to the present invention, and Figure 7 is a part of the same can form. The enlarged perspective view and FIG. 8 are also partially enlarged perspective views when the can form is filled with earth and sand. 1.1a... Float 2.2a... Can formwork 4.
4a... Winding shaft 5... Dredger 7... Underwater
8... Earth and sand 9... Concrete block Figure 2 73143a Figure 4 Figure 5

Claims (1)

【特許請求の範囲】 1 人工土地造築予定位置の外囲に布型枠を縦設し、前
記布型枠内へ充填物を送入して当該型枠の下端部を水底
に定着させる。ついで前記型枠で囲まれた地域の内側へ
土砂を送り込んでこれを水中へ盛り上げる。前記土砂の
盛り上げにつれて、盛土砂の斜面を形成し、所定の高さ
まで盛土すると共に、外面を補強することを特徴とした
水中における人工土地造築方法 2 斜面の形成は、型枠にアンカーを設置して、安息角
以上の急傾斜とした特許請求の範囲第1項記載の水中に
おける人工土地造築方法 3 土砂の盛上げに際し、凝集材を混入した特許請求の
範囲第1項記載の水中における人工土地造築方法 4 布型枠は合成樹脂繊維よりなる織布であって、所定
間隔で対向設置し、下端部は互に連結すると共に、対向
布には所定間隔で引張材を固定した特許請求の範囲第1
項記載の水中における人工土地造築方法 5 外面補強は型枠に土砂を充填した物を被覆し、又は
当該被覆物上にコンクリートブロックを敷設した特許請
求の範囲第1項記載の水中における人工土地造築方法 6 充填物は土砂、砂利又はコンクリートとした特許請
求の範囲第1項記載の水中における人工土地造築方法 7 盛上げる為の土砂の移送はサンドポンプによる圧送
又は運搬船による輸送とした特許請求の範囲第1項記載
の水中における人工土地造築方法8 布型枠の設置は環
状又は包囲状とした特許請求の範囲第1項記載の水中に
おける人工土地造築方法
[Scope of Claims] 1. A fabric form is installed vertically around the planned location of artificial land construction, and a filler is introduced into the fabric form to fix the lower end of the form to the water bottom. Then, earth and sand are sent inside the area surrounded by the formwork and raised into the water. An underwater artificial land construction method 2 characterized by forming a slope of embankment sand as the earth and sand is piled up, embanking to a predetermined height, and reinforcing the outer surface.For forming the slope, anchors are installed in the formwork. 3. A method for constructing artificial land in water according to claim 1, in which the slope is steeper than the angle of repose. Land construction method 4: A patent claim in which the fabric formwork is a woven fabric made of synthetic resin fibers, which are placed facing each other at a predetermined interval, their lower ends are connected to each other, and tension members are fixed to the opposing fabric at a predetermined interval. range 1
Underwater artificial land construction method 5 according to Claim 5 The underwater artificial land according to Claim 1, wherein the external reinforcement is performed by covering a formwork filled with earth and sand, or by laying concrete blocks on the covering. Construction method 6 A method for constructing artificial land in water according to claim 1, in which the filler is earth, sand, gravel, or concrete 7 A patent in which the earth and sand for heaving is transported by force using a sand pump or transported by a carrier ship 8. Method for constructing artificial land in water as described in claim 1 8. Method for constructing artificial land in water as described in claim 1, in which the fabric form is installed in a circular or encircling shape.
JP60295137A 1985-12-26 1985-12-26 Method of constructing artificial land underwater Expired - Fee Related JPH0619130B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60295137A JPH0619130B2 (en) 1985-12-26 1985-12-26 Method of constructing artificial land underwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60295137A JPH0619130B2 (en) 1985-12-26 1985-12-26 Method of constructing artificial land underwater

Publications (2)

Publication Number Publication Date
JPS62153407A true JPS62153407A (en) 1987-07-08
JPH0619130B2 JPH0619130B2 (en) 1994-03-16

Family

ID=17816756

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60295137A Expired - Fee Related JPH0619130B2 (en) 1985-12-26 1985-12-26 Method of constructing artificial land underwater

Country Status (1)

Country Link
JP (1) JPH0619130B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5766216A (en) * 1980-10-07 1982-04-22 Mitsui Constr Co Ltd Artificial islet and its construction work
JPS57104707A (en) * 1980-12-16 1982-06-29 Hitachi Zosen Corp Treatment of sludge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5766216A (en) * 1980-10-07 1982-04-22 Mitsui Constr Co Ltd Artificial islet and its construction work
JPS57104707A (en) * 1980-12-16 1982-06-29 Hitachi Zosen Corp Treatment of sludge

Also Published As

Publication number Publication date
JPH0619130B2 (en) 1994-03-16

Similar Documents

Publication Publication Date Title
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
ES442290A1 (en) Pile splicing apparatus and method
CN108505529A (en) A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge
US6616380B1 (en) Subterranean structures and methods for constructing subterranean structures
US3938342A (en) Method and a device for building immersed foundations
CN111119219A (en) Reinforced foundation tire membrane structure and construction method thereof
CN221218671U (en) Frame type framework slope protection device
CN107938594A (en) Deep water mixing dike construction method
CN111778922A (en) Construction method of river basin flood control dam
JPS62153407A (en) Construction of artificial land in water
CN111676893A (en) Temporary wharf structure and construction method thereof
KR940002457B1 (en) Method and device for strengthening bearing capacity of soft ground and forming barrier wall
CN1446988A (en) Construction method for structure of reinforced concrete underwater
BE1003521A3 (en) Prefabricated element basement.
JP3209502B2 (en) Water intake / discharge equipment underwater construction method
RU2783072C1 (en) Method for preparing the base of a cylindrical tank on soft soils
JPH07292648A (en) Artificial island construction method
Ponomaryev et al. Experience of geosynthetical material application for karst danger reduction of building base
JPH1077624A (en) Underwater construction method and prefabricated intake and discharge device
JP2868339B2 (en) Lightweight embankment and embankment creation method
JP2626427B2 (en) Construction method of multi-layer bag and embankment for embankment using excavated sludge
JP2000240059A (en) Banking method
Pilarczyk Novel systems in coastal engineering
CN113430989A (en) Lifting construction method for sea pond
Cuthbert et al. THE THAMES-LEE WATER MAIN.

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees