[go: up one dir, main page]

JPS6213659A - Steel bar construction method of building - Google Patents

Steel bar construction method of building

Info

Publication number
JPS6213659A
JPS6213659A JP15383085A JP15383085A JPS6213659A JP S6213659 A JPS6213659 A JP S6213659A JP 15383085 A JP15383085 A JP 15383085A JP 15383085 A JP15383085 A JP 15383085A JP S6213659 A JPS6213659 A JP S6213659A
Authority
JP
Japan
Prior art keywords
steel
accuracy
column
construction
columns
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15383085A
Other languages
Japanese (ja)
Other versions
JPH0543833B2 (en
Inventor
佐藤 光寿
裕 柳川
建夫 川村
雅典 護
隆義 東藤
卓美 藤井
敏明 土屋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP15383085A priority Critical patent/JPS6213659A/en
Publication of JPS6213659A publication Critical patent/JPS6213659A/en
Publication of JPH0543833B2 publication Critical patent/JPH0543833B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、鉄骨造又は鉄骨鉄筋コンクリート造建物を
建設する分、野における柱梁鉄骨の建方工法に関する。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention relates to a method for constructing a column and beam steel frame in the field of constructing a steel frame or steel reinforced concrete building.

従来の技術 従来の鉄骨建方工法は、もともと鉄骨柱を垂直に建てる
ことは至難であること、及び鉄骨自体の精度にも工場に
おける加工誤差や現場の環境(温度、日射等による曲り
)に基く誤差が複雑にからみ合うので安易に信頼し難い
ことを前提とし、このため警6図、瞬示した如く例えば
−隅の4本の鉄骨柱1・・・とこれに付随する鉄骨梁2
・・・をそれぞれ相前後して組立て、仮締めボルトで仮
に締めてワンブロックの軸組の形を作る。しかる後にス
パン及び建入精度の調整を目的とした歪直しを行ない、
その後ハイテンションボルトによる本締め又は本溶接を
行なうというのが一般的な手順であった。
Conventional technology Conventional steel frame construction methods are based on the fact that it is extremely difficult to build steel columns vertically, and the accuracy of the steel frame itself is dependent on processing errors at the factory and the site environment (curving due to temperature, solar radiation, etc.). It is assumed that errors are complicatedly intertwined and it is difficult to rely on them easily. Therefore, as shown in Figure 6, for example, the four steel columns 1 at the corner and the steel beams 2 attached to them...
Assemble them one after the other and temporarily tighten them with temporary bolts to form a one-block frame assembly. After that, distortion correction was carried out for the purpose of adjusting the span and construction accuracy.
The general procedure was then to perform final tightening with high tension bolts or final welding.

発明が解決しようとする問題点 ■上記従来の鉄骨建方工法の場合、鉄骨柱梁1.2はあ
る程度まとまったブロック毎の単位で歪直しの工程を消
化しなければならず、その間は鉄骨工事の次工程に進む
、ことができないので、作業手順が悪く、ひいては工程
が長びくという問題点があった゛。
Problems to be Solved by the Invention ■ In the case of the conventional steel frame construction method described above, the steel frame columns and beams 1.2 must undergo the process of straightening the distortion in units of blocks that are organized to a certain extent, and during that time, the steel frame construction Since it is not possible to proceed to the next process, there is a problem that the work procedure is poor and the process becomes longer.

■従来、鉄骨軸組のスパン調整は、例えば第7図に示し
た如く鉄骨軸組の柱頭に斜めにワイヤロープ4.4を張
り、ターンバックル(又はヒラパラ−など)5.5で締
付けたり、あるいは鉄骨が大きい場合には第8図に示し
た如くワイヤロープ4に滑車6、ウィンチ7を使用して
締付け、もって前後左右に柱1をゆり動かしながら鉄火
と呼ばれるクサビ、を梁−梁間または梁−柱間に固定さ
せる方法で行なってきた。しかし、ワイヤロープ4の段
取りが柱1本につき4本必要となるし、また張力をかけ
るターンバックル5やヒラパラ−も多数必要となり、こ
うした仮設資材類の保管、運搬の管理が面倒でコスト高
になるという問題点があった・ ■また、スパン調節後に行なう柱の建直しは、やはり第
7図又は第8図に示した如くに準備して、鉄骨軸組のブ
ロック全体をゆさぶることによって行なっているが、・
個々の柱の建入れ精度は、結局のところ鉄骨の製作(加
工)精度に大きく影響されるのであり、実際にはおよそ
良好であると思われる範囲内のいわば偶然に定まった値
に決めているのが実情である。即ち、建入れ精度を高め
ることにも限度があるという問題点があった。
■ Conventionally, the span adjustment of a steel framework was carried out by, for example, stretching a wire rope 4.4 diagonally around the column head of the steel framework and tightening it with a turnbuckle (or a hinge, etc.) 5.5, as shown in Figure 7. Alternatively, if the steel frame is large, as shown in Figure 8, tighten the wire rope 4 using a pulley 6 and winch 7, and while swinging the column 1 back and forth and left and right, insert a wedge called a tekka between the beams or between the beams. -I've been doing this by fixing it between Hashirama. However, four wire ropes 4 are required for each pillar, and a large number of turnbuckles 5 and hinges are required to apply tension, making storage and transportation management of these temporary materials cumbersome and costly. In addition, the rebuilding of the columns after span adjustment is done by preparing as shown in Figures 7 or 8 and shaking the entire steel frame block. There is, but...
The erection accuracy of each column is ultimately greatly influenced by the manufacturing (processing) accuracy of the steel frame, and in reality it is set to a value determined by chance within a range that is considered to be approximately good. That is the reality. That is, there is a problem in that there is a limit to increasing the accuracy of construction.

■上述の如く鉄骨建方の建入れ精度は鉄骨の製作精度に
大きく影響される上にその鉄骨製作誤差を吸収するため
の歪直し操作の労力を多く必要とし、多ぐの時間と熟練
した技術を要するという問題点があった。
■As mentioned above, the erection accuracy of steel frame erection is greatly influenced by the manufacturing accuracy of the steel frame, and it requires a lot of effort to correct the distortion in order to absorb the steel frame manufacturing error, which requires a lot of time and skilled technology. There was a problem in that it required

■第7図と第8図に示した如くワイヤロープ4は鉄骨軸
組のブロック毎に複数階にまたがって張られ、このワイ
ヤロープ部分がスラブ工事のダメ工事となり、工事の作
業手順を非常に複雑なものとなし、よって■で述べたよ
うに工程が長びくという問題点があった。
■As shown in Figures 7 and 8, the wire rope 4 is stretched across multiple floors for each block of the steel framework, and this wire rope portion becomes a failure in slab construction, making the work procedure extremely difficult. The process is complicated, and therefore, as mentioned in ①, there is a problem that the process takes a long time.

問題点を解決するための手段 上記問題点を解決するための手段として、この発明の鉄
骨建方工法は、第1図〜第5図に実施例を示しているよ
うに、 (イ)まず鉄骨柱1を建込み、これを仮締めボルトで仮
゛に締め付け固定する工程と、 (ロ)引きつづき当該鉄骨柱(1)にその建入精度の拘
束(調整及び拘束)手段を付設し、同鉄骨柱(1)につ
いて建入精度を測定して垂直に立てると共に励記拘束手
段により同鉄骨柱(1)の垂直精度が狂わないように強
固に拘束保持する工程と、 (ハ)鉄骨柱(1)を前記の如く拘束した状態でボルト
本締め又は本溶接をし固定する工程と、(ニ)前記のよ
うにして垂直に建方し固定された柱と柱の間に梁(2)
を組入れボルト本締め又は本溶接で固定する工程と、 より成るものとした。
Means for Solving the Problems As a means for solving the above-mentioned problems, the steel frame construction method of the present invention, as shown in the embodiments in Figs. The process of erecting Column 1 and temporarily tightening and fixing it with temporary bolts; (B) Continuing to attach means to constrain (adjust and constrain) the erection accuracy of the steel column (1); A step of measuring the erection accuracy of the steel column (1), standing it vertically, and firmly restraining it using excitation restraint means so that the vertical accuracy of the steel column (1) does not go out of order; (1) fixing the beam (2) by fully tightening bolts or welding it while restrained as described above, and (d) attaching the beam (2) between the columns that have been vertically erected and fixed as described above.
The process of assembling the parts and fixing them by final tightening of bolts or final welding.

作用 鉄骨柱1は、その建込みに引き続く作業として各々の柱
1についてその都度建入れ精度を出しボルト本締め又は
本溶接までを行なうので、従来の如く建入れ精度の調整
を目的とした仮設資材類は一切必要でなく、勿論その取
り付け、取り外しの作業も一切ない。
Working steel columns 1 are constructed using temporary materials for the purpose of adjusting the erection accuracy, as in the past, as the work following the erection of each column 1 involves checking the erection accuracy and performing final tightening or welding of the bolts. There is no need for any type of equipment, and of course there is no work involved in installing or removing it.

また゛、梁2の組入れを完成すると直ちに次工程の床版
工事に移ることができ、工期の短縮が図れる。特に鉄骨
造の場合は、梁組み込みと並行して床版工事が早期に可
能なので、柱lの本溶接にある程度の大型段取りができ
る。
In addition, once the installation of the beams 2 is completed, the next process of floor slab construction can be started immediately, thereby shortening the construction period. Particularly in the case of a steel frame structure, it is possible to construct the floor slab at an early stage in parallel with the installation of the beams, so it is possible to make some large-scale preparations for the actual welding of the columns.

なお、柱の建入れ精度の限界により梁2を組入れうにも
収まらない場合に対処する方法として、梁の継手部の間
隔を鉄骨柱の限界精度に合わせて広げ、その広げた部分
はスプライスプレートでカバーする。
In addition, as a method to deal with the case where beam 2 cannot be installed due to the limit of the erection accuracy of the column, the interval between the joints of the beam is widened to match the limit accuracy of the steel column, and the widened part is covered with a splice plate. Cover.

実施例 次に、第1・図〜第5図に示したこの発明の好適な実施
例を説明する。
Embodiment Next, a preferred embodiment of the present invention shown in FIGS. 1 to 5 will be described.

第1図は、2階分相当の高さの鉄骨柱1を建込み、その
建入精度を測定して垂直に立てた状況を示している。
Fig. 1 shows a situation in which a steel frame column 1 with a height equivalent to two floors has been erected, the accuracy of the erecting has been measured, and the column is erected vertically.

即ち、鉄骨柱1は、その建込みを行なった際、その接合
部10を仮締めボルトで仮に締付け固定する。
That is, when the steel column 1 is erected, its joint portion 10 is temporarily tightened and fixed with temporary bolts.

と同時に、当該鉄骨柱1の周囲にはその建入精度を調節
し、かつ拘束を可能ならしめる手段として、直角4方向
の位置に対する4台(又は最小限2台でも可)の軽量ジ
ヤツキ11.11・・・が設置されている。各軽量ジャ
7キ11は、既設の鉄骨梁2に反力をとり、鉄骨柱1に
おける階高位置のガゼツトプレート12に取り付けた状
態で設置されている。
At the same time, around the steel column 1, four (or at least two is acceptable) lightweight jacks 11. 11... are installed. Each lightweight jack 11 is installed in a state in which it takes a reaction force to the existing steel beam 2 and is attached to a gazette plate 12 at a floor height position on the steel column 1.

従って、建入精度の調整は、例えば当該鉄骨柱1の天端
から下げ振りを下げ、垂直精度を測定すると共に、直角
4方向に対をなす軽量ジヤツキ11・・・で押すか又は
引くことにより歪の建直しを行なう、そして目標の垂直
精度が得られた状態で、そのまま各軽量ジヤツキ11・
・・により当該柱1は垂直精度が狂わないように強固に
拘束(固)    定)保持する。
Therefore, the construction accuracy can be adjusted by, for example, lowering a plumb bob from the top of the steel column 1, measuring the vertical accuracy, and pushing or pulling it with light jacks 11 arranged in four directions at right angles. After rebuilding the distortion and achieving the target vertical accuracy, each lightweight jack 11.
The column 1 will be firmly restrained (fixed) so that its vertical accuracy will not be disturbed.

この拘束保持の状態において、前記接合部lOはハイテ
ンションボルトの本締め又は本溶接の方法により完全に
固定する。
In this restrained state, the joint lO is completely fixed by final tightening of high tension bolts or final welding.

以下同様の工程を、くり返すことにより、第2図のよう
に必要とする全部の鉄骨柱1・・・の建方を行なつって
ゆく。
By repeating the same process, all the required steel columns 1 are erected as shown in Fig. 2.

他方、垂直に建入れし本固定をした柱と柱1.1の間に
梁2を組入れ、これもハイテンションボルトによる本締
め又は本溶接の方法でその都度固定する。
On the other hand, a beam 2 is assembled between the vertically erected and permanently fixed columns and the column 1.1, and this is also fixed each time by the method of final tightening with high tension bolts or final welding.

この梁2の組入れ固定作業の時期は、■全ての柱1・・
・−9建方6を終了した後、又は■ある程度まとまった
本数の柱1・・・9建方を行なった後にこれに追従する
作業として行なう。
The timing for installing and fixing beam 2 is as follows:■ All columns 1...
・This is done as a follow-up work after completing -9 construction 6 or after a certain number of columns 1...9 construction has been completed.

ところで、本発明方法の実施においても柱1の建入れ精
度には勿論限度があり、梁2を組入れようとしても納ま
らない場合も予測されるが、この柔2の納まりをスムー
ズに行なうための対処法の一例を第3図〜第5図に示し
た。
By the way, even in the implementation of the method of the present invention, there is a limit to the accuracy of building the column 1, and it is predicted that even if you try to incorporate the beam 2, it may not fit, but there are some countermeasures to ensure that the beam 2 fits smoothly. An example of the method is shown in FIGS. 3 to 5.

即ち、梁2の継手部の間隔Sを鉄骨柱1の限界建入精度
に合わせて数mm位のオーダーで広くとり、その広げた
部分はスプライスプレート13゜14でカバーする。ス
プライスプレート13゜14には、その片側半分のボル
ト孔13b。
That is, the spacing S between the joints of the beams 2 is widened by several millimeters in accordance with the limited construction precision of the steel column 1, and the widened portions are covered with splice plates 13 and 14. The splice plates 13 and 14 have bolt holes 13b on one half of the splice plates.

14bは鉄骨柱1の建入精度を吸収する長さの長孔とし
て設け、他側半分のボルト孔13a、14aは丸孔とし
て設けられている。従って、梁2と柱lのガゼツトブレ
ー)1aとはスプライスプレート13.14を介してハ
イテンションボルトの本締めで強固に固定することがで
きる。
14b is provided as a long hole with a length that accommodates the erection accuracy of the steel column 1, and the bolt holes 13a and 14a on the other half are provided as round holes. Therefore, the beam 2 and the gazette brake (1a) of the column 1 can be firmly fixed via the splice plates 13, 14 by fully tightening the high tension bolts.

かくして鉄骨柱1、梁2の建方は、歪直しロープやター
ンバックル、ヒラパラ−を使用することなく、1ピース
毎の本締め又は本溶接の工程により整然と手順よく行な
うことができる。そして、梁2が納まると同時に次工程
である床版工事に入ることができ、工期の短縮が図れる
のである。
In this way, the steel columns 1 and beams 2 can be erected in an orderly and step-by-step manner by fully tightening or welding each piece without using straightening ropes, turnbuckles, or hinges. As soon as the beams 2 are installed, the next step, the floor slab construction, can begin, which shortens the construction period.

なお、上記のようにして柱l、梁の本締又は本溶接によ
る建方を行なった後にも、建入精度測定、レベル測定は
行ない、その測定結果は鉄骨製作へフィードバックする
。即ち、次上階の鉄骨建方に際して、当階の建入精度及
びレベルの誤差を修正する内容の鉄骨製作を行なわしめ
るためである。
Furthermore, even after the columns 1 and beams are completely tightened or erected by welding as described above, erection accuracy measurements and level measurements are performed, and the measurement results are fed back to the steel frame fabrication. In other words, when constructing the steel frame for the next upper floor, the steel frame will be fabricated to correct errors in the construction accuracy and level of the current floor.

発明が奏°する効果 ■ 以、上に実施例と併せて詳述したとおりであって、
この発明の鉄骨建方工法は、鉄骨柱1、梁2が1ピース
毎に本締め、本溶接が行なわれるので作業手順が至極簡
素化される。その上、梁2が納まると直ちに次工程の床
版工事に進めるので、工期の大幅な短縮が図れる。
Effects achieved by the invention■ As described above in conjunction with the embodiments,
In the steel frame construction method of the present invention, the steel columns 1 and beams 2 are fully tightened and welded piece by piece, so the work procedure is extremely simplified. Furthermore, as soon as the beams 2 are installed, the next process of floor slab construction can be started, so the construction period can be significantly shortened.

■ とりわけ、鉄骨造の場合は、梁組み込みと並行して
床版工°水ができ、ロニリング系足場の活用を期待でき
、仮設足場の少量化が図れる。
■ In particular, in the case of steel structures, the floor slab construction can be done in parallel with the installation of beams, making it possible to utilize RoniRing type scaffolding and reducing the amount of temporary scaffolding required.

■ かくして、床版工事が早期に可能となるため、柱の
溶接にある程度の大形段取りが可能となり将来溶接のロ
ボット化へと進むことが可能となる。
■ In this way, floor slab work can be completed early, making it possible to make some large-scale preparations for welding columns, making it possible to move forward to robotizing welding in the future.

■ 歪み直しを日時とするワイヤロープやヒラパラ−、
ターンバックル等の扱いにくい仮設資材類が大幅に少な
くなり、仮設費の低減に大きく寄与する。
■ Wire ropes and fliers that need to be straightened out,
The amount of difficult-to-handle temporary construction materials such as turnbuckles is greatly reduced, greatly contributing to the reduction of temporary construction costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明の建方工法における鉄骨柱の建入精度
調節及び・拘束保持の状況を示した斜視図、第2図は柱
を建て梁を組入れる状況の斜視図、第3図は柱梁接合部
の正面図、第4図と第5図はスプライスプレートの正面
図、第6図は従来の鉄骨建方工法の施工状況を示した斜
視図−1第7図と第8図は従来の歪直しのやり方を示し
た立面図である。 第2篇 第3WJ II4F!m スフ・ライス7@レート 13 第5図 14t)     14a 第61!! 第7図 第8B
Fig. 1 is a perspective view showing the construction accuracy adjustment and restraint maintenance of steel columns in the construction method of this invention, Fig. 2 is a perspective view of the situation in which the columns are erected and beams are assembled, and Fig. 3 is the columnar construction method. A front view of the beam joint, Figures 4 and 5 are front views of the splice plate, and Figure 6 is a perspective view showing the construction status of the conventional steel frame construction method.-1 Figures 7 and 8 are the conventional FIG. Part 2 Part 3 WJ II4F! m Sukh Rice 7 @ Rate 13 Figure 5 14t) 14a 61st! ! Figure 7 8B

Claims (1)

【特許請求の範囲】 [1](イ)鉄骨柱を建込み、これを仮締めボルトで仮
に締め付け固定する工程と、 (ロ)当該鉄骨柱(1)にその建入精度の拘束手段を付
設し、同鉄骨柱(1)について建入精度を測定して垂直
に立てると共に前記拘束手段により同鉄骨柱(1)の垂
直精度が狂わないように拘束保持する工程と、 (ハ)鉄骨柱(1)を前記の如く拘束した状態でボルト
本締め又は本溶接をし固定する工程と、(ニ)前記のよ
うにして垂直に建方し固定した柱と柱の間に梁(2)を
組入れボルト本締め又は本溶接をし固定する工程と、 より成ることを特徴とする建物の鉄骨建方工法。
[Scope of Claims] [1] (a) A step of erecting a steel column and temporarily tightening and fixing it with temporary tightening bolts, and (b) attaching means to restrict the erection accuracy to the steel column (1). (c) measuring the erection accuracy of the steel column (1), standing it vertically, and restraining and holding the steel column (1) using the restraining means so that the vertical accuracy of the steel column (1) does not go out of order; 1) The process of fully tightening or welding the bolts while restrained as described above, and (d) incorporating the beam (2) between the columns that have been erected and fixed vertically as described above. A method of constructing a steel frame for a building, which is characterized by comprising the steps of fixing by final tightening or welding of bolts.
JP15383085A 1985-07-12 1985-07-12 Steel bar construction method of building Granted JPS6213659A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15383085A JPS6213659A (en) 1985-07-12 1985-07-12 Steel bar construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15383085A JPS6213659A (en) 1985-07-12 1985-07-12 Steel bar construction method of building

Publications (2)

Publication Number Publication Date
JPS6213659A true JPS6213659A (en) 1987-01-22
JPH0543833B2 JPH0543833B2 (en) 1993-07-02

Family

ID=15571020

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15383085A Granted JPS6213659A (en) 1985-07-12 1985-07-12 Steel bar construction method of building

Country Status (1)

Country Link
JP (1) JPS6213659A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6490368A (en) * 1987-10-01 1989-04-06 Taisei Corp Method of steel frame construction of welding steel frame structure
JPH01239268A (en) * 1988-03-17 1989-09-25 Takenaka Komuten Co Ltd Erection of steel work
JPH06101349A (en) * 1992-09-16 1994-04-12 Kajima Corp Steel frame insertion correction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6490368A (en) * 1987-10-01 1989-04-06 Taisei Corp Method of steel frame construction of welding steel frame structure
JPH01239268A (en) * 1988-03-17 1989-09-25 Takenaka Komuten Co Ltd Erection of steel work
JPH06101349A (en) * 1992-09-16 1994-04-12 Kajima Corp Steel frame insertion correction method

Also Published As

Publication number Publication date
JPH0543833B2 (en) 1993-07-02

Similar Documents

Publication Publication Date Title
US3875710A (en) Structural system and method employed therein
JPH04111829A (en) Construction method for large span roofs
JP3015910B2 (en) Adjustment method for steel columns
CN115419277B (en) Construction method of heavy steel box type diagonal column
JP5183606B2 (en) Unit structure of anchor bolt used for foundation construction of equipment and foundation construction method of equipment using it
CN102817482A (en) Steel column correcting device and correcting construction method thereof
JPS6213659A (en) Steel bar construction method of building
JP3247749B2 (en) Construction method of long span truss beams
JPH09189132A (en) Fixing method of column base for steel frame column
JPH11131423A (en) Positioning method of steel pipe
CN111576891A (en) Construction method of bolt-connected criss-cross H-shaped steel truss
JP3103294B2 (en) Pillar steel frame, jig used for the connection, and steel frame connection method
JPH07150767A (en) Beam truss erecting method in building having overhead traveling crane
JP3303218B2 (en) Reconstruction method
JP3187618B2 (en) How to assemble beam reinforcement
JP3244102U (en) Steel house foundation structure and anchor set used therein
JP2690822B2 (en) Steel construction method for low-rise buildings
JP7129302B2 (en) building construction method
JPH01111937A (en) Opening structure and construction method of pillar and beam of building body
JPH0715923Y2 (en) Strut fastening device for wooden buildings
CN118621980A (en) Wall skin system installation method and wall skin system
JPS6397743A (en) Apparatus for mounting exterior material for building
JP2002155641A (en) Seismic isolation method
JPH04361986A (en) Installation structural base for tower crane
JP2677169B2 (en) Double beam steel beam

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees