JPS6134534B2 - - Google Patents
Info
- Publication number
- JPS6134534B2 JPS6134534B2 JP57032200A JP3220082A JPS6134534B2 JP S6134534 B2 JPS6134534 B2 JP S6134534B2 JP 57032200 A JP57032200 A JP 57032200A JP 3220082 A JP3220082 A JP 3220082A JP S6134534 B2 JPS6134534 B2 JP S6134534B2
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- spud
- rubble
- work boat
- mound
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/18—Foundations formed by making use of caissons
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Description
【発明の詳細な説明】
本発明は防波堤等のケーソン堤の築造方法に関
するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a caisson embankment such as a breakwater.
従来、防波堤あるいは護岸の構造形式として採
用されている代表的なものとしてケーソン式混成
堤がある。この種の重力式構造物の構築方法は一
般に次のような手順で行われる。 The caisson-type hybrid levee is a typical structural type of breakwater or revetment. A method for constructing this type of gravity structure is generally performed in the following steps.
(i) 石積船、ガツト船などによる捨石の投入
(ii) 潜水夫による捨石マウンドの均し
(iii) 単独に製作したケーソン函体の曳航、据付け
(iv) 中詰砂の充填及び上部工の施工
(v) 根固めブロツク、被覆ブロツク等の設置
上記作業工程のうち、(ii)の捨石マウンドの構築
方法は潜水夫に頼るところが非常に大きく、しか
も、潜水作業は海象条件、水深などの制約を受け
る場合が多い。一般に、潜水夫の能率等に極端に
影響のでない作業は水深−20〜−25m程度までが
限度で、それ以上になると作業性が極端に落ちて
実用的でないと言われている。(i) Loading of rubble by stone-loading ships, gatsuto ships, etc. (ii) Leveling of rubble mounds by divers (iii) Towing and installation of individually manufactured caisson boxes (iv) Filling with sand and construction of superstructures Construction (v) Installation of foot protection blocks, cover blocks, etc. Of the above work steps, (ii), the method of constructing rubble mounds, relies heavily on divers, and furthermore, diving work is subject to constraints such as sea conditions and water depth. is often received. In general, work that does not significantly affect the efficiency of the diver is limited to a depth of -20 to -25 m, and it is said that workability is extremely poor and impractical at depths greater than that.
特に、近年建設が叫ばれている沖合人工島建設
計画などにおける大水深構造物は対象水深が−30
〜−50mにも及んでいるので、このような海域に
ケーソン式混成堤を構築する際には、従来方法の
潜水夫によるマウンド構築が困難になつてくる。 In particular, the target water depth for deep-water structures such as offshore artificial island construction projects that have been called for in recent years is -30
Since the mounds are as deep as -50m, when constructing a caisson-type hybrid embankment in such sea areas, it becomes difficult to construct mounds using conventional methods by divers.
また、ケーソンの据付けに関しても従来プツシ
ヤーバージなどを使つて注水しながらゆつくり沈
設しているが、波によりケーソンが動揺するため
高い精度が望めないのが現状である。 In addition, conventional methods for installing caissons include using push barges to slowly sink them while injecting water, but the current situation is that high precision cannot be expected because the caissons are shaken by waves.
特に大型ケーソンになると付加重量が大きいの
で、浮体の制御が困難になり、大型の作業船を導
入しても据付け精度が問題になる。 Especially when it comes to large caissons, the added weight is large, making it difficult to control the floating body, and even if large work vessels are introduced, installation accuracy becomes a problem.
一方、大水深の重力式構造における問題点はマ
ウンドの地耐力である。従来の構築方法によるマ
ウンドの許容地耐力は、通常40〜50t/m2程度の値
が採用されているケースが多い。 On the other hand, the problem with gravity-type structures in deep water is the bearing capacity of the mound. The allowable soil bearing capacity of mounds created using conventional construction methods is usually around 40 to 50 t/m 2 in many cases.
これが大水深になると、壁体安定に占める地耐
力の影響が大きくなる。即ち、壁体安定上必要最
小限の堤体幅は地耐力の大小によつて決定され
る。従つて、少しでもマウンドの地耐力を増加さ
せることが建設コストの廉価につながるが、従来
方法では上述の如くの値程度しか採用されていな
いのが現状である。 When the water becomes deep, the influence of the bearing capacity of the soil on wall stability increases. In other words, the minimum width of the embankment required for wall stability is determined by the bearing capacity of the ground. Therefore, increasing the bearing capacity of the mound by even a small amount will lead to lower construction costs, but at present, only the above-mentioned values are adopted in conventional methods.
又、近年大水深海域に防波堤等を築造するた
め、複数のケーソンを数段に積んだ構造の堤体築
造方法が提案されているが、この場合複数のケー
ソンの結合強度が問題となるがその結合は海面下
で行われるため十分な結合ができない状況であ
る。 In addition, in recent years, in order to construct breakwaters in deep water areas, a method of constructing breakwaters in which multiple caissons are stacked in several tiers has been proposed. Since the bonding takes place below the sea surface, sufficient bonding is not possible.
本発明は上記のような問題点、欠点を改善する
ようにしたものであつて本発明のケーソン堤の築
造方法は、荒均しされた捨石マウンドを形成する
工程と、この捨石マウンド上にケーソン据付用ス
パツド付き作業船をスパツドを利用して設置する
工程と、ケーソンを前記作業船により吊下する工
程と、このケーソンを前記捨石マウンドより所定
の高さに沈下しケーソンの下面に設けたその網目
よりモルタルが漏出する下部基布(帆布)中にモ
ルタルを注入し、これにより前記ケーソンの下面
と前記捨石マウンド間の隙間を充填せしめる工程
と、前記スパツド付き作業船を撤去する工程とよ
り成ることを特徴とする。 The present invention is intended to improve the above-mentioned problems and drawbacks, and the method for constructing a caisson embankment of the present invention includes a step of forming a roughly leveled rubble mound, and a step of forming a caisson embankment on the rubble mound. A step of installing a work boat with an installation spud using the spud, a step of suspending the caisson from the work boat, and a step of sinking the caisson to a predetermined height from the rubble mound and installing a work boat on the underside of the caisson. The process consists of a step of injecting mortar into the lower base fabric (canvas) from which mortar leaks through the mesh, thereby filling the gap between the lower surface of the caisson and the rubble mound, and a step of removing the spud-equipped work boat. It is characterized by
以下図面によつて本発明の実施例を説明する。 Embodiments of the present invention will be described below with reference to the drawings.
本発明においては、まず石積船などによつて投
入された捨石を捨石均し機械で表面の凹凸が30〜
50cm程度に荒均し、この捨石マウンド1の上にケ
ーソン据付用スパツド付き双胴船2を曳航してき
て設置する。スパツド付き双胴船2は主として船
体部3、ケーソンを吊り下すためのガーダー4、
スパツド5により構成され、スパツド5の昇降用
として油圧ジヤツキ、ケーソンの吊り下げ用とし
てガーダー4の上に配置した巻き上げ機を夫々装
備している。 In the present invention, the rubble thrown in by a stone carrier or the like is first processed by a rubble leveling machine to reduce the surface unevenness by 30 to 30 mm.
It is roughly leveled to about 50 cm, and a catamaran boat 2 with spuds for installing a caisson is towed and installed on top of this rubble mound 1. The catamaran 2 with spouts mainly includes a hull 3, a girder 4 for suspending a caisson,
It consists of a spud 5, and is equipped with a hydraulic jack for raising and lowering the spud 5, and a hoist placed on the girder 4 for suspending the caisson.
スパツド付双胴船2の設置は、次のような手順
で実施される。即ち、ケーソン設置予定位置に誘
導後、スパツド5を降し、船体全体の安定を保つ
ために、船体部3の中に注水を行う。 Installation of the catamaran 2 with spuds is carried out in the following steps. That is, after guiding the caisson to the planned installation position, the spud 5 is lowered and water is injected into the hull 3 in order to maintain the stability of the entire hull.
注水量を制御することによつて、スパツドに作
用させる鉛直荷重を任意に決めることができる。
通常、鉛直荷重として300〜400t程度を考慮すれ
ば、1m程度の波浪に対して安定性を保つことが
できるのがあまり大きい鉛直荷重を加えればマウ
ンドによつて支持できる限界を超えるようにな
る。従つて、直径1m程度のスパツド1本当りに
作用する荷重は100〜130t前後で一定ならしめる
ことが望ましい。 By controlling the amount of water injected, the vertical load applied to the spud can be arbitrarily determined.
Normally, considering a vertical load of about 300 to 400 tons, it is possible to maintain stability against waves of about 1 meter, but if a too large vertical load is applied, it will exceed the limit that can be supported by the mound. Therefore, it is desirable that the load acting on each spud with a diameter of about 1 m be constant at about 100 to 130 tons.
このように所定位置にスパツド付き双胴船2を
設置した後、フローテングドツク又は陸上ヤード
などで製作したその上部に通気塔6を形成した下
段ケーソン7を曳航し、スパツド付き双胴船に誘
導する。次に第1図に示すように下段ケーソン7
の上部とガーダー4とをワイヤー8で結び、船体
部3の中に予め調整注水しておいた海水をポンプ
により所望量下段ケーソン7内に移す。次に第1
図のような状態で下段ケーソン7を保持している
ところへ、第2図のように再び別個に曳航してき
た上段ケーソン9を双胴船2内に引き込み、この
上段ケーソン9内に多少の吊荷重が作用する程度
注水して下段ケーソン7の上面に形成した凹部1
0に接地するまで上段ケーソン9を下降させる。 After the catamaran 2 with spouts is installed at a predetermined position in this way, the lower caisson 7, which has a ventilation tower 6 formed on its upper part manufactured at a floating dock or a land yard, is towed and guided to the catamaran with spouts. do. Next, as shown in Figure 1, the lower caisson 7
The upper part of the vessel and the girder 4 are connected with a wire 8, and a desired amount of seawater, which has been adjusted and injected into the hull section 3, is transferred into the lower caisson 7 by a pump. Next, the first
While the lower caisson 7 is being held in the state shown in the figure, the upper caisson 9, which has been towed separately as shown in Fig. A recess 1 formed on the upper surface of the lower caisson 7 by pouring water to the extent that a load is applied.
The upper caisson 9 is lowered until it touches the ground at 0.
下段ケーソン7上に上段ケーソン9を接地させ
た後、第3図に示すように上、下段ケーソンの中
の海水を船体部3内に再びポンプで吸上げ、上、
下段ケーソンの接続面が海上に出るまで浮上させ
る。この時、吊荷重は殆んど変化しないように浮
上量、排水量、ポンプ運転等を制御する。 After the upper caisson 9 is grounded on the lower caisson 7, the seawater in the upper and lower caisson is pumped up again into the hull 3, as shown in FIG.
Raise the lower caisson until the connecting surface is above the sea. At this time, the floating height, displacement amount, pump operation, etc. are controlled so that the hanging load hardly changes.
接続面を大気中に出した状態で、上、下段のケ
ーソンを一体化する。一体化する方法は場所打コ
ンクリートで連結することもできるし、予め下段
ケーソン7にPC鋼棒11の一端を固定してお
き、カツプラーで上、下段ケーソン間のPC鋼棒
を接続してプレストレスを導入し、一体化するこ
ともできる。尚、上段ケーソンを下段ケーソンに
接地させるときの精度を高めるため、下段ケーソ
ン7には凹部10だけでなく、ガイド管(図示せ
ず)を設置しておき、上、下段ケーソンを確実に
PC鋼棒11で連結できるようにする。 The upper and lower caissons are integrated with the connecting surfaces exposed to the atmosphere. The integration can be done by connecting them with cast-in-place concrete, or by fixing one end of the PC steel bar 11 to the lower caisson 7 in advance and connecting the PC steel bars between the upper and lower caissons with a coupler to prestress them. It is also possible to introduce and integrate. In addition, in order to improve the accuracy when grounding the upper caisson to the lower caisson, not only the recess 10 but also a guide pipe (not shown) is installed in the lower caisson 7 to ensure that the upper and lower caissons are grounded securely.
It is possible to connect with PC steel rod 11.
上、下段ケーソンの一体化が完全に終了した
後、第4図に示すように船体部3にもどしておい
た海水を再度下段ケーソン7中へ注水しながらこ
れらを所定の高さ(設置深さ)まで下降させ、そ
して周辺の海底に投入したアンカー及び係留索
(図示せず)等によつてケーソンを保持しなが
ら、予め下段ケーソン7の下部に取付けておいた
ケーソン下部基布(帆布)12の中へ海上よりコ
ンクリートあるいはモルタルを注入する。注入孔
はケーソン隔壁等に前もつて設置しておく。 After the upper and lower caissons have been completely integrated, as shown in Fig. 4, the seawater that had been returned to the hull 3 is poured into the lower caisson 7 again, and the seawater is lowered to a predetermined height (installation depth). ), and while holding the caisson with anchors and mooring cables (not shown) thrown into the surrounding seabed, the caisson lower base cloth (canvas) 12 was previously attached to the lower part of the lower caisson 7. concrete or mortar is poured into the tank from the sea. The injection hole should be installed in advance on the caisson bulkhead, etc.
次いでケーソン下部基布12内に注入したコン
クリートにケーソンを保持できる強度が発現した
ら、通気塔6を利用して下段ケーソン7内にポン
プ等によつて砂等を中詰めし、さらに上段ケーソ
ン9内にも中詰めしてその上に通常のように上部
工を施して、その後ケーソンを吊つていた巻き上
げ機を徐々に緩め、油圧ジヤツキでスパツドを持
ち上げ、ケーソンからスパツド付き双胴船を分離
してケーソン堤を完成する。 Next, when the concrete poured into the lower caisson base fabric 12 has sufficient strength to hold the caisson, the lower caisson 7 is filled with sand, etc. using a pump or the like using the ventilation tower 6, and then the upper caisson 9 is filled with sand, etc. The caisson was then filled in and the superstructure was constructed as usual, and then the hoist that was suspending the caisson was gradually loosened, the spud was lifted with hydraulic jacks, and the catamaran with the spud was separated from the caisson. and completed the caisson embankment.
コンクリートの初期強度は、ケーソンの鉛直荷
重を支えるだけなので1Kg/cm2程度発現すれば十
分である。従つて、ケーソン据付け完了まで浮か
した状態でケーソンを保持するに要する時間は数
時間で済む。尚、さらに所要時間を短縮させたい
時には、硬化促進剤等を添加して調整することも
できる。 The initial strength of concrete is sufficient to support the vertical load of the caisson, so it is sufficient to develop around 1 kg/cm 2 . Therefore, it only takes a few hours to maintain the caisson in a floating state until the caisson installation is completed. In addition, when it is desired to further shorten the required time, it is possible to adjust by adding a curing accelerator or the like.
この後、船体部3内の水を排水し、浮上させて
双胴船2を撤去して、第5図に示すように二段ケ
ーソンは完成する。 Thereafter, the water in the hull section 3 is drained, floated, and the catamaran 2 is removed, completing the two-stage caisson as shown in FIG.
本発明による作用効果を列挙すれば以下の通り
である。 The effects of the present invention are listed below.
(1) スパツド付き双胴船と既設ケーソンを利用し
て浮かした状態で位置決めするので、敏速かつ
正確な位置決めができる。(1) Positioning is carried out in a floating state using a catamaran with spuds and an existing caisson, allowing for quick and accurate positioning.
(2) 通気塔を設けることにより蓋付きケーソンの
沈設を容易にすることができる。また、沈設後
は通気塔を中詰工法の注、排水管に利用するこ
とができる。(2) By providing a ventilation tower, it is possible to facilitate the installation of a covered caisson. In addition, after being submerged, the aeration tower can be used as a drainage pipe using the filling method.
(3) 浮力の利用と注、排水をくり返すことによ
り、スパツドにかかる荷重を一定にすることが
できる。(3) By using buoyancy and repeating drainage, the load on the spud can be kept constant.
(4) 浮力を利用するため大型のケーソンでも小さ
な吊り荷重で据付けが可能である。(4) Since buoyancy is used, even large caissons can be installed with a small lifting load.
(5) ケーソンを浮かした状態で隙間にコンクリー
ト等を充填するため、マウンドの天端均しが不
要でかつ正確なケーソン天端高を設定すること
ができる。(5) Since the gap is filled with concrete etc. while the caisson is floating, there is no need to level the top of the mound and the height of the caisson top can be set accurately.
(6) 機械均し程度のマウンド天端の仕上げで十分
なので、潜水作業の困難な大水深海域での施工
が可能となる。(6) Since finishing the top of the mound by mechanical leveling is sufficient, construction can be carried out in deep water areas where diving work is difficult.
(7) ケーソン下端と捨石とを帆布の網目から漏出
したコンクリート又はモルタルによつてで一体
化するため、従来方法と比べて地耐力を増大さ
せることができるので建設コストを廉価にする
ことができる。(7) Since the lower end of the caisson and the rubble are integrated using concrete or mortar leaked through the mesh of the canvas, the bearing capacity of the ground can be increased compared to conventional methods, and construction costs can be reduced. .
(8) 通常のケーソン及び蓋付きケーソンでも任意
に浮力調整ができるので、高精度に沈設するこ
とができる。(8) Since the buoyancy of ordinary caissons and caisson with lids can be adjusted as desired, they can be sunk with high precision.
(9) 上段ケーソンと下段ケーソンとの結合を海面
上で行うのでその結合強度を十分大きくでき
る。(9) Since the upper caisson and lower caisson are connected above sea level, the strength of the connection can be sufficiently increased.
第1図は双胴船の説明用平面図、第2図〜第6
図は夫々本発明方法の工程説明図である。
1……捨石マウンド、2……双胴船、3……船
体部、4……ガーダー、5……スパツド、6……
通気塔、7……下段ケーソン、8……ワイヤー、
9……上段ケーソン、10……凹部、11……鋼
棒、12……ケーソン下部基布。
Figure 1 is an explanatory plan view of the catamaran, Figures 2 to 6
Each figure is a process explanatory diagram of the method of the present invention. 1... Rubble mound, 2... Catamaran, 3... Hull, 4... Girder, 5... Spud, 6...
Ventilation tower, 7... lower caisson, 8... wire,
9...Upper caisson, 10...Recess, 11...Steel rod, 12...Caisson lower base fabric.
Claims (1)
と、この捨石マウンド上にケーソン据付用スパツ
ド付き作業船をスパツドを利用して設置する工程
と、ケーソンを前記作業船により吊下する工程
と、このケーソンを前記捨石マウンドより所定の
高さに沈下しケーソンの下面に設けたその網目よ
りモルタルが漏出する下部基布(帆布)中にモル
タルを注入し、これにより前記ケーソンの下面と
前記捨石マウンド間の隙間を充填せしめる工程
と、前記スパツド付き作業船を撤去する工程とよ
り成ることを特徴とするケーソン堤の築造方法。 2 荒均しされた捨石マウンドを形成する工程
と、この捨石マウンド上にケーソン据付用スパツ
ド付き作業船をスパツドを利用して設置する工程
と、下段ケーソンを前記作業船により吊下する工
程と、この下段ケーソン上に上段ケーソンを載置
する工程と、下段ケーソンと上段ケーソンを共に
浮上せしめその接続面が海面上に露出した状態で
両者の結合を行う工程と、前記上段及び下段ケー
ソンを前記捨石マウンドより所定の高さに沈下し
下段ケーソンの下面に設けたその網目よりモルタ
ルが漏出する下部基布(帆布)中にモルタルを注
入し、これにより前記下段ケーソンの下面と前記
捨石マウンド間の隙間を充填せしめる工程と、前
記スパツド付き作業船を撤去する工程とより成る
ことを特徴とするケーソン堤の築造方法。[Scope of Claims] 1. A step of forming a roughly leveled rubble mound, a step of installing a work boat with a spud for installing a caisson on the rubble mound using the spud, and a step of hoisting the caisson by the work boat. The caisson is lowered to a predetermined height from the rubble mound, and mortar is injected into the lower base fabric (canvas) from which the mortar leaks through the mesh provided on the lower surface of the caisson. A method for constructing a caisson embankment, comprising the steps of: filling a gap between the lower surface and the rubble mound; and removing the spudded work boat. 2. A step of forming a roughly leveled rubble mound, a step of installing a work boat with a spud for installing a caisson on the rubble mound using the spud, and a step of suspending the lower caisson by the work boat, A step of placing the upper caisson on top of the lower caisson, a step of floating the lower caisson and the upper caisson together and connecting them with their connecting surfaces exposed above the sea surface, and a step of moving the upper and lower caissons to the rubble. Mortar is injected into the lower base fabric (canvas) which sinks to a predetermined height from the mound and leaks through the mesh provided on the lower surface of the lower caisson, thereby creating a gap between the lower surface of the lower caisson and the rubble mound. 1. A method for constructing a caisson embankment, comprising the steps of: filling the work boat with spuds; and removing the spud-equipped work boat.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3220082A JPS58150629A (en) | 1982-03-03 | 1982-03-03 | Construction of caisson levee |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3220082A JPS58150629A (en) | 1982-03-03 | 1982-03-03 | Construction of caisson levee |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS58150629A JPS58150629A (en) | 1983-09-07 |
JPS6134534B2 true JPS6134534B2 (en) | 1986-08-08 |
Family
ID=12352262
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3220082A Granted JPS58150629A (en) | 1982-03-03 | 1982-03-03 | Construction of caisson levee |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS58150629A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60159224A (en) * | 1984-01-27 | 1985-08-20 | Toa Harbor Works Co Ltd | Method of installing caisson |
KR100642343B1 (en) | 2006-07-22 | 2006-11-02 | 주식회사 한국종합기술 | Large caisson launch platform for port work |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2235558B1 (en) * | 1973-06-26 | 1981-09-25 | Thomson Brandt | |
JPS5031367A (en) * | 1973-07-24 | 1975-03-27 |
-
1982
- 1982-03-03 JP JP3220082A patent/JPS58150629A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS58150629A (en) | 1983-09-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3896628A (en) | Marine structures | |
US4440527A (en) | Marine structure | |
US3528254A (en) | Offshore platform structure and construction method | |
CN108505529A (en) | A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge | |
CN102561379A (en) | Novel bridge installation foundation and construction method thereof | |
JP2019044566A (en) | Foundation post grouting method of submerged caisson | |
US3961489A (en) | Method for placing a floating structure on the sea bed | |
CN109518674B (en) | Artificial island segment, assembled artificial island and construction method of assembled artificial island | |
CN1036611A (en) | Manufacturing method and equipment for structural parts of river port engineering | |
JPS6134534B2 (en) | ||
JPH1046597A (en) | Execution work method of steel shell caisson | |
JP2815492B2 (en) | How to build an underwater foundation | |
US20220324540A1 (en) | A marine construction and a method for constructing the same | |
KR102169627B1 (en) | Installation method of concrete sinker for floating structure | |
JP2953823B2 (en) | Construction method of offshore substructure | |
JP2001003332A (en) | Caisson laying method and caisson laying floater | |
JPH11229404A (en) | Construction of bridge foundation in deep water | |
JPS6335766B2 (en) | ||
JPH05311667A (en) | Launching method for large caisson | |
JPH0213098B2 (en) | ||
JPH0469253B2 (en) | ||
JPH01240397A (en) | Working deck ship | |
Tsinker | Gravity-Type Quay Walls | |
JPH06286688A (en) | Method for building dock submerged for ship entering moat | |
JPS6256291B2 (en) |