JPS59433A - Steel manhole assembly and its construction - Google Patents
Steel manhole assembly and its constructionInfo
- Publication number
- JPS59433A JPS59433A JP57106728A JP10672882A JPS59433A JP S59433 A JPS59433 A JP S59433A JP 57106728 A JP57106728 A JP 57106728A JP 10672882 A JP10672882 A JP 10672882A JP S59433 A JPS59433 A JP S59433A
- Authority
- JP
- Japan
- Prior art keywords
- manhole
- unit
- units
- steel
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/121—Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は、鋼製マンホール組立体とその施工方法に関す
る。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a steel manhole assembly and a method of constructing the same.
従来、下水用マンホールを構築するにあたり、比較的浅
い場合は、素掘りをして既成品であるコンクリートブロ
ックを組み合せてマンホールを完成させていた。既成コ
ンクリートブロックでは充分でない大深度のマンホール
の場合は、セグメント等を利用しながら、所定深度まで
掘削し、底部から現場打ちコンクリートでマンホールを
築造していた。Conventionally, when constructing a sewage manhole, if it was relatively shallow, the manhole was dug and assembled with ready-made concrete blocks. In the case of deep manholes where ready-made concrete blocks were not sufficient, the manhole was excavated to a specified depth using segments, etc., and the manhole was constructed from the bottom with cast-in-place concrete.
本発明は、上記の施工方法のうち、後者に関するもので
あるが、従来は以下の問題点があった。The present invention relates to the latter of the above construction methods, but conventional methods have had the following problems.
(])、大深度であるため、掘削時または現場打ちコン
クIJ −ト打設時K、地下水の流入等忙対処する必賛
がある。()) Due to the large depth, it is necessary to deal with the inflow of groundwater during excavation or pouring concrete IJ-in-place.
(2)、市街地等でおこなう場合、作業範囲に多大な空
間を要する。(2) When carrying out work in urban areas, etc., a large amount of space is required for the work area.
また、現場作業が長期化した場合、周辺交通、住民生活
に対する影響が大きい。Additionally, if on-site work is prolonged, there will be a significant impact on surrounding traffic and residents' lives.
(3)、掘削作業に多大な労力を要し、作業スペースの
制約から長い工期が要求される。(3) Excavation work requires a great deal of labor and requires a long construction period due to limited work space.
(4)、現場打ちのコンクリート(側壁)等は、一度に
構築できる範囲が限定され、しかも、必要最小限の強度
になるまで、次工程へ進めないため、工期が長期化する
。また現場打ちコンクIJ −トのため施工管理が困難
である。(4) Cast-in-place concrete (side walls), etc., limits the area that can be constructed at one time, and furthermore, the construction period becomes longer because the next process cannot proceed until the required minimum strength is achieved. Also, construction management is difficult because it is a cast-in-place concrete IJ.
(5)、マンホール壁面がコンクリートのため、壁面の
老化、タラップ等の内面構造物の劣化などが起り易く、
寿命が短い。(5) Because the manhole walls are made of concrete, aging of the walls and deterioration of internal structures such as ramps are likely to occur.
It has a short lifespan.
(6)、マンホール施工後、周辺掘削部の埋戻し作業が
完全に期待できない。(6) After constructing the manhole, it is not possible to completely backfill the surrounding excavated area.
本発明は上記欠点を解決するためになされたもので、工
期の短縮化、作業空間の節約、周辺住民に対する騒音公
害の防止、等を目的とするものである。さらに本発明の
他の目的は、穴の深さに応じた任意の長さのマンホール
を得ることにある。The present invention has been made to solve the above-mentioned drawbacks, and aims to shorten the construction period, save work space, and prevent noise pollution to surrounding residents. Still another object of the present invention is to obtain a manhole of arbitrary length depending on the depth of the hole.
本発明は上記目的を達成するため、マンホール任意の長
さの鋼製マンホール組立体及びその施工方法を提供する
ものである。以下図面を用いて本発明を説明する。In order to achieve the above object, the present invention provides a steel manhole assembly with a manhole of arbitrary length and a method for constructing the same. The present invention will be explained below using the drawings.
第1図は、マンホールを、単数の頭部マンホールユニッ
トA1複数の腹部マンホール施工後)B及び単数の底部
マンホールユニットCの3種の組合せで所定の長さに構
成した組立状態を示す本発明実施例の断面図である。頭
部マンホールユニットAは、現場に、おいて長さを調整
するものとし、腹部マンホールユニットB及び底部マン
ホールユニットCは一定の長さ、例えば3m、4.5m
、6mとする。マンホール組立体を挿入する穴の深さに
応じて、腹部マンホール施工後)Hの員数を変更したり
、頭部マンホールユニットAの長さを変えたりする。A
−Cの各マンホールユニットハ、搬送及びクレーンでの
吊り下げが可能なように重量を比較的軽量にしである。FIG. 1 shows an assembled state in which a manhole is constructed to a predetermined length by three combinations of a single head manhole unit (A), a plurality of abdominal manholes (after construction) B, and a single bottom manhole unit C. FIG. 3 is an example cross-sectional view. The length of the head manhole unit A shall be adjusted on site, and the length of the abdomen manhole unit B and bottom manhole unit C shall be fixed, for example, 3 m, 4.5 m.
, 6m. Depending on the depth of the hole into which the manhole assembly is inserted, the number of members (after construction of the abdominal manhole) H or the length of the head manhole unit A may be changed. A
-C, each manhole unit is relatively light in weight so that it can be transported and suspended by a crane.
また現場作業においては、溶接作業のみで済むようK、
工場において全付属品を装着し、塗装済みの状態にして
お(。In addition, in field work, K, so that only welding work is required,
All accessories are installed at the factory and it is in a pre-painted condition (.
第2図は、本発明の要部を構成する各マンホールユニッ
ト実施例の平面図及びその部分断面図で、(、)は頭部
マンホールユニットA 、(b) ki ill 部マ
ンホール施工後) B 、(e)は底部マンホールユニ
ットCを示す。図において、5は鋼製のマンホールユニ
ット本体を示し、耐食性のために内面に防食塗料を塗覆
するか耐食性材質の鋼材を使用している。FIG. 2 is a plan view and a partial cross-sectional view of each manhole unit embodiment that constitutes the main part of the present invention, (,) is the head manhole unit A, (b) is the head manhole unit A, (b) is the ki ill part (after construction of the manhole) B, (e) shows the bottom manhole unit C. In the figure, reference numeral 5 indicates a manhole unit body made of steel, and the inner surface is coated with anticorrosive paint or made of corrosion-resistant steel material for corrosion resistance.
マンホールユニット本体5には以下にのべる附属物が設
けられている。すなわち各マンホールユニットには内周
面にグラウト用ソケット6を設け、マンホールの沈設後
周辺にモルタルを充填する。The manhole unit main body 5 is provided with the following accessories. That is, each manhole unit is provided with a grout socket 6 on its inner peripheral surface, and after the manhole is sunk, the surrounding area is filled with mortar.
また外周面には例えばSS材からなる吊り金具7を設け
、第6図に示すような簡易クレーン8によるマンホール
ユニットの吊り下げ時にクレーンのワイヤーをここに掛
け、中間段階では台座9に載置する。10は人の昇降用
タラップで、耐腐食性のためステンレス材としである。Furthermore, a hanging fitting 7 made of SS material, for example, is provided on the outer peripheral surface, and when the manhole unit is hung by a simple crane 8 as shown in FIG. . 10 is a ramp for lifting people up and down, and it is made of stainless steel because it is corrosion resistant.
タラップ10の固定のためには、SS材に防食塗装をほ
どこした支柱11が設けられ、ステンレス類のボルトで
固定しである。12はステンレス材よりなるグレーチン
グで安全基準に基づきほぼ6mに1個所の割合で設けで
ある。グレーチング12の、マンS −ルユニット本体
5への取り付けは、マンホールユニット本体5に溶接さ
れた受金具15にステンレス類のボルトで取り付けであ
る。またグレーチング12には、人の出入りのためiC
600aX 400鰭程度の開口部を設け、出入り以上
の時はステンレス類の蓋がしである。マンホールユニッ
ト本体5の端部には、現場での溶接接合をするための開
先14が設けられている。なお第2図(c)K示す底部
マンホール施工後)Cの附属物は第2図(cL)又は(
b)とほとんど同じであるが、必要本数のマンホールユ
ニットを接合後に所定位置への固定を容易にするため、
先端に鋸歯状の切り込みをもたせた固定リング15を取
付けてあり、マンホールユニットの自重により孔内のス
ライムに埋めこまれ、精度よく固定される。さらに盲板
16が設けられているが、これはベントナイトと清水と
の比重差を利用して、第6図(c)に示す簡易クレーン
8の負荷を軽減することに寄与している。この場合、マ
ンホール内に満たす清水量とベントナイト比重で適当に
バランスをとることにより、吊り込み用のクレーン8の
負荷を自由に変更できる。17は下水本管への継ぎ込み
のための横穴で、建込み時にはパツキンをかませた蓋を
ボルトで止めである。To fix the gangway 10, support columns 11 made of SS material with anti-corrosion coating are provided and fixed with stainless steel bolts. Reference numeral 12 is a grating made of stainless steel, and based on safety standards, it is installed approximately once every 6 meters. The grating 12 is attached to the manhole unit body 5 by attaching it to a receiving metal fitting 15 welded to the manhole unit body 5 using stainless steel bolts. In addition, grating 12 is equipped with an iC for people to enter and exit.
The opening is about 600a x 400 fins, and is covered with a stainless steel lid when access is required. A groove 14 is provided at the end of the manhole unit body 5 for on-site welding. In addition, the appendix of C) after construction of the bottom manhole shown in Fig. 2 (c) K is shown in Fig. 2 (cL) or (
This is almost the same as b), but in order to make it easier to fix the required number of manhole units in place after joining,
A fixing ring 15 with a serrated cut at the tip is attached, and is embedded in the slime in the hole by the weight of the manhole unit and fixed with high precision. Furthermore, a blind plate 16 is provided, which contributes to reducing the load on the simple crane 8 shown in FIG. 6(c) by utilizing the difference in specific gravity between bentonite and fresh water. In this case, by appropriately balancing the amount of fresh water filled in the manhole with the specific gravity of bentonite, the load on the lifting crane 8 can be freely changed. 17 is a side hole for connecting to the main sewage pipe, and when the building is installed, the lid with a gasket is secured with bolts.
この蓋は建込みグラウト後除かれ、ボルト孔にはステン
レスボルトがセットされる。This cover will be removed after grouting and stainless steel bolts will be set in the bolt holes.
本発明の施工方法の一実施例を第6図に示す。An embodiment of the construction method of the present invention is shown in FIG.
まず第3図(α)に示すようにマンホールの外径より3
’00 m〜400fl程度大きい内径で土壌1を削
孔し、(b)に示すように削孔部表面に簡易クレーン8
及びH形鋼の台座9を設置する。底部マンホールユニッ
トCを、(C)に示すように簡易クレーン8を用いて台
座9の所定の位置に置き、次に腹部マンホールユニット
Bを底mマンホールユニットC上で本体が重なる位置に
移動する。18は現場継手である。前記作業を所定の本
数分繰り返し、第1図に示すようなマンホール組立体を
形成する。First, as shown in Figure 3 (α),
A hole is drilled in the soil 1 with a larger inner diameter of about 00 m to 400 fl, and a simple crane 8 is placed on the surface of the hole as shown in (b).
and a pedestal 9 made of H-beam steel. The bottom manhole unit C is placed in a predetermined position on the pedestal 9 using a simple crane 8 as shown in (C), and then the abdominal manhole unit B is moved to a position where its main bodies overlap on the bottom m manhole unit C. 18 is an on-site joint. The above operation is repeated for a predetermined number of manholes to form a manhole assembly as shown in FIG.
作業終了後マンホール下部に底部コンクリート6を打設
したあと、マンホール組立体と孔壁の間隙忙モルタルグ
ラウト2を施す。マンホール組立体内部に防食塗装を施
こした後、既成の斜坑ブロック4を設ける。第4図は、
本発明に係る現場継手の詳細をあC)わし、(、)は等
厚継手部の場合、(b)は不等厚継手部の場合を示す。After the work is completed, bottom concrete 6 is placed at the bottom of the manhole, and then mortar grout 2 is applied to the gap between the manhole assembly and the hole wall. After applying anticorrosive coating to the inside of the manhole assembly, a prefabricated inclined shaft block 4 is installed. Figure 4 shows
The details of the on-site joint according to the present invention are shown in (C), (,) shows the case of a joint of equal thickness, and (b) shows the case of a joint of unequal thickness.
すなわちマンホール本体5aと5b (5c )は保護
金具19、裏当リング20゜20α、ストッパー21及
びルート間隔保持ビード22により定位置に固定される
。That is, the manhole bodies 5a and 5b (5c) are fixed in position by the protective metal fitting 19, the backing ring 20°20α, the stopper 21, and the root spacing bead 22.
以上の説明から明らかなように、本発明によれば次のよ
うな顕著な効果を挙げることができる。As is clear from the above description, according to the present invention, the following remarkable effects can be achieved.
(])、工場で精度良く製作されたマンホールユニット
を、現場で接続し沈設するだけでマンホールが形成され
るため、工期が知かく、工事設備も小規模でよい。()) Manholes are formed by simply connecting and sinking manhole units manufactured with high precision in a factory on-site, so the construction period is short and only small-scale construction equipment is required.
(2)、マンホールユニットの組み合せが基本となるた
め、マンホールの深さの変化、横管とのとり合いが容易
である。(2) Since it is basically a combination of manhole units, it is easy to change the depth of the manhole and to connect it with the horizontal pipe.
(3)、作業スペースがせまくてすむ。(3) The work space is small.
(4)、付属品関係がステンレスであるため、劣化が少
な(、メンテナンスが不要。(4) Since the accessories are made of stainless steel, there is little deterioration (no maintenance required.
(5)、現場作業の労務費が軽減できる。(5) Labor costs for on-site work can be reduced.
第1図は本発明実施例の縦断面図、第2図(α)。
(b)、 (e)は、本発明要部実施例の平面図及びそ
の部分断面図、第3図((1)、 (b)、 (c)及
び第4図(tx)! (b)は本発明の施工方法の一例
を示す断面図である。
A −i 部マンホール組立体)、B−[ISマンホー
ルユニツ) 、C−1jI 部マンホールユニット、8
− クレーン、9一台座。
代理人 弁理士 木 村 三 朗
第1図
第 3 商
(0)
第 4 図
(0)
(b)FIG. 1 is a longitudinal sectional view of an embodiment of the present invention, and FIG. 2 (α). (b) and (e) are a plan view and a partial sectional view of an embodiment of the main part of the present invention, and FIG. 3 ((1), (b), (c) and FIG. 4 (tx)! (b) are sectional views showing an example of the construction method of the present invention. A-i part manhole assembly), B-[IS manhole unit), C-1jI part manhole unit, 8
- Crane, 9-pedestal. Agent Patent Attorney Sanro Kimura Figure 1, Figure 3, Quotient (0) Figure 4 (0) (b)
Claims (2)
トを溶接しこれを積層した鋼製マンホール組立体であっ
て、該鋼製マンホール組立体が、最下部に設けた1個の
底部マンホールユニットと、ソノ上部に載置した複数の
腹部マンホールユニット及び最上部に設けた長さを調節
できる1個の頭部マンホールユニットより構成してなる
ことを特徴とする鋼製マンホール組立体。(1) A steel manhole assembly in which corrosion-resistant manhole units of a certain length are welded and stacked, and the steel manhole assembly has one bottom manhole unit provided at the lowest part. A steel manhole assembly comprising: a plurality of abdominal manhole units placed on the top of the manhole; and one head manhole unit with adjustable length provided on the top.
し穴の表面に載置した台座上の所定位置に重下セットし
たのち、吊持した腹部マンホールユニットを前記底部マ
ンホールユニット上に重ねて載置してこれらを接合し、
再度垂下して台座上の所定位置にセットし、前記作業を
腹部マンホールユニットについて所定の本数分繰り返し
、最後に長さを調節した頭部マンホールユニットを同様
に載置し接合することを特徴とするマンホール組立体の
施工方法。(2) After setting the bottom manhole unit in a predetermined position on the pedestal placed on the surface of the suspension hole using a crane or the like, place the suspended abdominal manhole unit on top of the bottom manhole unit. and join these together.
It is characterized by hanging again and setting it at a predetermined position on the pedestal, repeating the above operation for a predetermined number of abdominal manhole units, and finally placing and joining the head manhole unit whose length has been adjusted in the same way. Construction method of manhole assembly.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57106728A JPS59433A (en) | 1982-06-23 | 1982-06-23 | Steel manhole assembly and its construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57106728A JPS59433A (en) | 1982-06-23 | 1982-06-23 | Steel manhole assembly and its construction |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS59433A true JPS59433A (en) | 1984-01-05 |
Family
ID=14440991
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP57106728A Pending JPS59433A (en) | 1982-06-23 | 1982-06-23 | Steel manhole assembly and its construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS59433A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4503374A (en) * | 1982-07-15 | 1985-03-05 | Fanuc Ltd. | Speed detection apparatus and method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4944539A (en) * | 1972-09-04 | 1974-04-26 | ||
JPS53126706A (en) * | 1977-04-12 | 1978-11-06 | Tokyo Kenki Kougiyou Kk | Method of making pit |
-
1982
- 1982-06-23 JP JP57106728A patent/JPS59433A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4944539A (en) * | 1972-09-04 | 1974-04-26 | ||
JPS53126706A (en) * | 1977-04-12 | 1978-11-06 | Tokyo Kenki Kougiyou Kk | Method of making pit |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4503374A (en) * | 1982-07-15 | 1985-03-05 | Fanuc Ltd. | Speed detection apparatus and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100982827B1 (en) | Construction method of basement exterior wall applying the floor slab as the strut against the earth pressure from the temporary earth wall = TSW(Thrusting slabbed wall) method | |
CN110185061B (en) | Assembled integral type underground space retaining wall and construction method | |
CN107313454B (en) | Construction method of underground garage | |
CN109056844B (en) | Waterproof construction method for outer wall of basement of building | |
RU2131496C1 (en) | Underground structure constructed in foundation pit and method of concreting | |
JPS59433A (en) | Steel manhole assembly and its construction | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
JPS6137692Y2 (en) | ||
JP2001241052A (en) | Waterproof construction method for basement and waterproof structure of basement | |
JP2011236666A (en) | Building method of protection concrete body for septic tank | |
Goncharov et al. | Increasing the laying depth of the foundations fordeepened underground buildingsparts | |
JP7595244B2 (en) | Method for installing large bottomed pipe and large bottomed pipe | |
EP1348812A1 (en) | Building methods and apparatus | |
CN109680695A (en) | Bore forming technique is perfused in anhydrous thickness sand cobble stratum long auger | |
CN215669635U (en) | Steel-pipe column and steel-pipe pile integrated prefabricated assembled T type pipe frame | |
JPS5811754Y2 (en) | Earthquake-resistant steel underground tank | |
JPH10152853A (en) | Method of building underground structure and structure member used therein | |
RU207719U1 (en) | MODULAR BLOCK OF UNREMOVABLE FORMWORK OF PREFABRICATED-MONOLITHIC REINFORCED CONCRETE POST OF BRIDGE STRUCTURES | |
SU808603A1 (en) | Method of constructing pile foundation | |
CN221072748U (en) | Basement wall post-pouring strip assembled plugging plate | |
CN210263110U (en) | Prefabricated template device of basement cushion cap and grade beam | |
CN110848456B (en) | Construction method of large-diameter self-supporting overhead steel pipe | |
CN222413036U (en) | A circular foundation pit structure and system | |
JPS59154228A (en) | Construction of basement | |
JPH02132228A (en) | Process of building heavy-duty working floor using existing basement structure |