JPS5911007B2 - Construction method for water intakes and water outlets in waterway tunnels in underground ground - Google Patents
Construction method for water intakes and water outlets in waterway tunnels in underground groundInfo
- Publication number
- JPS5911007B2 JPS5911007B2 JP50118970A JP11897075A JPS5911007B2 JP S5911007 B2 JPS5911007 B2 JP S5911007B2 JP 50118970 A JP50118970 A JP 50118970A JP 11897075 A JP11897075 A JP 11897075A JP S5911007 B2 JPS5911007 B2 JP S5911007B2
- Authority
- JP
- Japan
- Prior art keywords
- water
- steel pipe
- underwater ground
- construction method
- shafts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
Description
【発明の詳細な説明】
一般に潜水作業の困難な35yn以上の水深で、岩盤地
帯水域において水底地盤内の水路トンネルにおける用水
の大規模な取水口または放水口を築造する場合、従来多
く行なわれている方法では、水底地盤下部にトンネルを
掘深し、同トンネルよシ取水口まだは放水口の竪坑をケ
ーソン工法か築島工法によって構築している。DETAILED DESCRIPTION OF THE INVENTION When constructing a large-scale intake or outlet for water in a waterway tunnel in the underwater ground in a rocky area at a depth of 35 yn or more, where diving is generally difficult, this has not been done in many cases. In this method, a tunnel is dug deep beneath the waterbed, and a vertical shaft for the water intake and water outlet is constructed using the caisson method or the Tsukishima method.
しかしながら前記従来の工法は何れも施工が大規模とな
り、圧気作業、止水作業が困難で、工期が延引し工費が
嵩む憾みがあった。However, all of the conventional construction methods described above require large-scale construction, are difficult to perform air pressure work and water shutoff work, and have the disadvantage of prolonging the construction period and increasing construction costs.
本発明はこのような実隋に鑑みて提案されたもので、所
要位置毎に水底地盤の所定深度にまで鋼管を貫入して鋼
管による竪坑を形成し、次いで同各鋼管内の水を排出し
、次いで前記各鋼管竪坑下部の水底地盤に水平坑を掘進
して、同水平坑を前記各鋼管竪坑と連通せしめることを
特徴とする水底地盤内の水路トンネルにおける用水の取
水口、放水口の築造工法に係シ、その目的とする処は、
作業が簡単で潜水作業を必要とせず、工事の最終段階ま
で湧水のない空間内での作業が行なわれ、潜函作業の如
く圧気内作業を要せず、水底地盤内の水路トンネルにお
ける用水の大規模々多孔式取水口、放水口を築造しつる
改良された工法を供する点にある。The present invention was proposed in view of the above-mentioned circumstances, and involves penetrating steel pipes to a predetermined depth in the underwater ground at each required location to form a shaft made of steel pipes, and then draining the water inside each steel pipe. , Next, a horizontal shaft is excavated into the underwater ground below each of the steel pipe shafts, and the horizontal shaft is communicated with each of the steel pipe shafts.Construction of water intake and water outlet in a waterway tunnel in the underwater ground, characterized by: Regarding the construction method, its purpose is:
The work is easy and does not require diving, the work is carried out in a space without spring water until the final stage of construction, and work in pressurized air is not required as in submersible work, and water supply in canal tunnels in the underwater ground is easy. The purpose is to provide an improved construction method for constructing large-scale, perforated water intakes and water outlets.
本発明においては鋼管を水底地盤の所要深度まで貫入し
たのち、鋼管内を排水して竪坑を構築するようにしたの
で、竪坑の構築が簡単に行なわれ、水深に左右されるこ
とが少なく、かくして構築された鋼管竪坑に、前記水底
地盤を掘進した水平坑を連通せしめるようにしたので、
工事開始から完了まで湧水のない空間内で工事が進めら
れ、潜水作業及び潜函作業がないので特殊作業員を必要
とせず、従って容易に水底地盤内の水路トンネルにおけ
る用水の大規模の多孔式取水口、放水口が築造されるも
のである。In the present invention, after penetrating the steel pipe to the required depth of the underwater ground, the inside of the steel pipe is drained to construct a shaft. Therefore, the construction of the shaft is easy and is less dependent on the water depth. Since the constructed steel pipe shaft was connected to the horizontal shaft dug through the underwater ground,
Since the construction work is carried out in a space without spring water from the start to the completion, and there is no diving or submersible work, there is no need for special workers, and therefore it is easy to use a large-scale porous system for irrigation water in waterway tunnels in the underwater ground. Water intake and water outlet will be constructed.
また本発明によれば、前記竪坑は所要の横断面積が得ら
れるように、数本まだは数十本築造することができるの
で、特に超犬型竪坑を必要としない等、本発明は多くの
利点を有するものである。Furthermore, according to the present invention, several or even dozens of shafts can be constructed so as to obtain the required cross-sectional area, so there is no need for a super-dog-shaped shaft. It has advantages.
以下本発明を図示の実施例について説明する。The present invention will be described below with reference to the illustrated embodiments.
先ず前記水底地盤内の水路トンネルにおける用水の取水
口、放水口の位置において、水底地盤1の所定深度に達
する竪穴2を掘削し、同竪穴2に鋼管3を挿入する。First, a vertical hole 2 reaching a predetermined depth in the underwater ground 1 is excavated at the location of the water intake and water outlet in the waterway tunnel in the underwater ground, and a steel pipe 3 is inserted into the vertical hole 2.
なお同鋼管3には所要位置において着脱自在なように上
部鋼管3′がボルト4等によって連結されている。An upper steel pipe 3' is connected to the steel pipe 3 by bolts 4 or the like so that it can be attached and detached at desired positions.
(第1図参照)次いで前記鋼管3と竪穴2との間隙にモ
ルタル5を充填し、(第2図参照)同モルタル5の硬化
後鋼管3内の水を排出する。(See FIG. 1) Next, the gap between the steel pipe 3 and the vertical hole 2 is filled with mortar 5, and after the mortar 5 has hardened (see FIG. 2), the water in the steel pipe 3 is drained.
(第3図参照)この状態で鋼管3の水底地盤1内の部分
に数個の湧水検知穴を穿設し、湧水の有無を調べる。(See Figure 3) In this state, several spring water detection holes are drilled in the portion of the steel pipe 3 in the water bottom ground 1 to check for the presence of spring water.
而して湧水があるとこの検知穴を利用するか、または鋼
管3の外部から止水のためのモルタルグラウトを行い、
かくして竪坑としての鋼管3内に湧水のない空間を形成
する。If there is spring water, use this detection hole or apply mortar grout from the outside of the steel pipe 3 to stop the water.
In this way, a space without spring water is formed within the steel pipe 3 serving as the shaft.
前記したよう々鋼管竪坑を所妾数築造したのち、水底地
盤1内に取水トンネル、放水トンネルの水平坑6を掘進
し、前記鋼管竪坑と水平坑6とを連通させる。After constructing the above-described steel pipe shafts, horizontal shafts 6 for water intake tunnels and water discharge tunnels are excavated in the underwater ground 1, and the steel pipe shafts and horizontal shafts 6 are communicated with each other.
(第4図参照)この際水平坑6の掘進は、竪坑の鋼管3
挿入とグラウト止水とによって湧水のないことが確認さ
れているので、湧水のない空間における施工が可能とな
る。(See Figure 4) At this time, the horizontal shaft 6 is excavated by the steel pipe 3 of the vertical shaft.
Since it has been confirmed that there is no spring water by insertion and grout water stop, construction can be carried out in a space without spring water.
前記したように鋼管竪坑と水平坑6とが連通したのち、
竪坑の鋼管3を利用して同鋼管3内の水位が外部の水位
と同一水位になるまで注水し、前記ボルト4を外して接
合部上部の鋼管3′を取外し、取水口、送水口のマンホ
ール7を取付けて全工程を完了するものである。After the steel pipe shaft and the horizontal shaft 6 are connected as described above,
Using the steel pipe 3 in the shaft, inject water until the water level inside the steel pipe 3 is the same as the water level outside, remove the bolt 4, remove the steel pipe 3' at the top of the joint, and open the manholes at the water intake and water supply ports. 7 to complete the entire process.
(、第5図参照)以上本発明を実施例について説明した
が、本発明は勿論このような実施例にだけ局限さハるも
のではなく、本発明の精神を逸脱しない範囲内で種種の
設計の改変を施しうるものである。(See FIG. 5.) Although the present invention has been described above with reference to embodiments, the present invention is of course not limited to such embodiments, and various designs may be made without departing from the spirit of the present invention. It is possible to make the following modifications.
第1図乃至第5図は本発明に係る取水口、放水口の築造
工法の一実施例の工程を示す縦断面図である。
1・・・・・・水底地盤、2・・・・・・竪坑、3・・
・・・・鋼管、6・・・・・・水平坑。FIGS. 1 to 5 are longitudinal sectional views showing steps of an embodiment of the construction method for water intakes and water outlets according to the present invention. 1... Underwater ground, 2... Vertical shaft, 3...
...Steel pipe, 6...Horizontal pit.
Claims (1)
して鋼管による竪坑を形成し、次いで同各鋼管内の水を
排出し、次いで前記各鋼管竪坑下部の水底地盤に水平坑
を掘進して、同水平坑を前記各鋼管竪坑と連通せしめる
ことを特徴とする水底地盤内の水路トンネルにおける用
水の取水口、放水口の築造工法。1. Piercing steel pipes to a predetermined depth in the underwater ground at each required location to form steel pipe shafts, then draining the water inside each steel pipe, and then digging horizontal shafts into the underwater ground below each of the steel pipe shafts. A method for constructing a water intake and a water outlet in a waterway tunnel in the underwater ground, characterized in that the horizontal shaft is communicated with each of the steel pipe shafts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP50118970A JPS5911007B2 (en) | 1975-10-03 | 1975-10-03 | Construction method for water intakes and water outlets in waterway tunnels in underground ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP50118970A JPS5911007B2 (en) | 1975-10-03 | 1975-10-03 | Construction method for water intakes and water outlets in waterway tunnels in underground ground |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5244040A JPS5244040A (en) | 1977-04-06 |
JPS5911007B2 true JPS5911007B2 (en) | 1984-03-13 |
Family
ID=14749778
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP50118970A Expired JPS5911007B2 (en) | 1975-10-03 | 1975-10-03 | Construction method for water intakes and water outlets in waterway tunnels in underground ground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5911007B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0180570U (en) * | 1987-11-20 | 1989-05-30 |
-
1975
- 1975-10-03 JP JP50118970A patent/JPS5911007B2/en not_active Expired
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0180570U (en) * | 1987-11-20 | 1989-05-30 |
Also Published As
Publication number | Publication date |
---|---|
JPS5244040A (en) | 1977-04-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209636826U (en) | Water-stop structure of foundation pit in water-rich sand and gravel stratum | |
CN110318410A (en) | A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method | |
CN105863648A (en) | Underground-excavation shallow-covering large-cross-section tunnel construction method | |
JP2014009465A (en) | Structure and construction method for intake and discharge channel | |
JP2009068213A (en) | Construction method for underground structure using caisson, and caisson with cut-off device | |
JPS5911007B2 (en) | Construction method for water intakes and water outlets in waterway tunnels in underground ground | |
CN203475453U (en) | Deeply-buried type bearing platform curtain structure of bridge | |
JPH08189030A (en) | Method for constructing self-supporting earth-retaining wall | |
JPH03275812A (en) | Foundation construction method for soft sea bottom ground | |
CN208294522U (en) | Waterproof of man in a kind of pilot tunnel of rich water sand-pebble layer | |
CN206941573U (en) | Artificial digging pile | |
JP2876265B2 (en) | Sheet pile for underground continuous wall and underground continuous wall method | |
JPS57155432A (en) | Method of erecting construction of existing pile | |
JP2874906B2 (en) | Shaft construction method | |
JPS5664028A (en) | Sheathing construction work by antecedent support framework | |
GB348204A (en) | An improved method of driving headings and tunnels in waterbearing strata | |
JPS5991228A (en) | Pit excavation work using caisson | |
CN107130622A (en) | Pool Bridge cushion cap foundation ditch subregion vacuum precipitation system and precipitation method | |
CN111074900A (en) | A kind of foundation pit construction method | |
DE640008C (en) | Process for the construction of tunnels, galleries and other underground structures in loose, possibly water-bearing mountains | |
JPS5820870A (en) | Construction method of underground storage tank | |
JPS57140421A (en) | Construction of large-diameter in-situ cast pile | |
JPH01198915A (en) | Catchment well and capsule therewith as well as embedding method thereof | |
CN116291604A (en) | Sand blocking and water stopping structure for hole opening of push pipe receiving well and construction method | |
JP3969619B2 (en) | Reconstruction method of groundwater vein in steel column wall retaining wall |