[go: up one dir, main page]

JPS58204227A - Foundation work of structure - Google Patents

Foundation work of structure

Info

Publication number
JPS58204227A
JPS58204227A JP8747082A JP8747082A JPS58204227A JP S58204227 A JPS58204227 A JP S58204227A JP 8747082 A JP8747082 A JP 8747082A JP 8747082 A JP8747082 A JP 8747082A JP S58204227 A JPS58204227 A JP S58204227A
Authority
JP
Japan
Prior art keywords
foundation
concrete
excavated
soil
aggregate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8747082A
Other languages
Japanese (ja)
Other versions
JPS6030817B2 (en
Inventor
Yoshiaki Yoshimi
吉見 吉昭
Kenji Konno
今野 健司
Hideyoshi Takahashi
高橋 秀吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TOMOEGUMI IRON WORKS Ltd
Tokyo Electric Power Co Holdings Inc
Original Assignee
TOMOEGUMI IRON WORKS Ltd
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TOMOEGUMI IRON WORKS Ltd, Tokyo Electric Power Co Inc filed Critical TOMOEGUMI IRON WORKS Ltd
Priority to JP8747082A priority Critical patent/JPS6030817B2/en
Publication of JPS58204227A publication Critical patent/JPS58204227A/en
Publication of JPS6030817B2 publication Critical patent/JPS6030817B2/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

PURPOSE:To effectively utilize excavated soil by a method in which usual concrete is placed to the bottom of an excavated pit to form the bottom of foundation to fix steel skeletons, and a concrete mixed with soil generated at the site as aggregate is placed around the steel skeletons. CONSTITUTION:Usual concrete is placed to the bottom reinforced with iron bars of an excavated pit 1 to form the bottom of foundation. Also, steel skeletons 2 are hung down into the excavated pit 1, the fixing part 21 is set on the lower part 31 of the foundation bottom, and concrete is placed until the fixing part 21 is buried to form the upper part 32 of the foundation bottom. In forming the excavated pit 1 on the foundation bottom 3, the aggregate is selected from the excavated soil and packed on the foundation bottom 3 and then cement mortar is poured by a prepacked concrete method to form the intermediate portion 4 of the bottom. Then, the ordinary concrete is placed on the foundation intermediate portion 4 to form the bottom 5 of the foundation. Thus, the foundation of a structure is completed.

Description

【発明の詳細な説明】 この発明は鉄浴、橋梁、ビル等の構造物の基礎工法に関
するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a foundation construction method for structures such as iron baths, bridges, and buildings.

ればならない。さらに注目されている問題として、現場
発生土の有効利用がある。これは掘削土等の処分地が少
なくなっていること、運搬費が高騰していることに起因
している。
Must be. Another issue that is attracting attention is the effective use of soil generated on-site. This is due to the fact that there is less land available for disposal of excavated soil, etc., and transportation costs are rising.

ここに搭状構造物等の基礎を山岳地等に建設する場合、
1)搬出入路が整備されていないことが多い、2)大き
な引揚力を受けるので、これに対する基礎重量が必要と
なる。S)山岳地は岩盤地帯であることが多いなどの特
徴がある。
When constructing a foundation for a tower-shaped structure, etc. in a mountainous area,
1) Loading and unloading routes are often not maintained, and 2) Since they are subject to large lifting forces, foundation weight is required to support this. S) Mountainous areas are characterized by the fact that they are often bedrock areas.

したがって、現場施工の深礎杭のよさな工法が多く採用
されているが、この場合でもなお多量な掘削土の搬出、
およびコンクリート材料等の搬入が必要となる。
Therefore, the method of on-site construction of deep foundation piles is often adopted, but even in this case, a large amount of excavated soil still needs to be carried out.
It will also be necessary to bring in concrete materials, etc.

この発明は、現場発生土を選別して、骨材等に利用する
ことにより、掘削土の搬出蓋およびコンクリート材料の
搬入量を大巾に減少させることが可能であり、大きな引
揚力に対しても充分抵抗できる信頼性の高い構造物の基
礎工法を提供することを目的とする。
This invention makes it possible to greatly reduce the amount of excavated soil to be carried in and the amount of concrete materials brought in by sorting the soil generated on site and using it as aggregate. The purpose is to provide a highly reliable foundation construction method for structures that can sufficiently resist

次に、この発明Kかかる構造物の基礎工法を図1に示す
プレパツクドコンクリートを用いた実施例に基づき、施
工順序に従って詳細に説明する。
Next, the foundation construction method for a structure according to the present invention will be described in detail in accordance with the construction order based on an example using prepacked concrete shown in FIG.

(1)掘削 地盤を人力または機械力によって掘削し、掘削孔1を形
成する。図中OAは表土、Bは中間層、Cは支持層を示
す。
(1) Excavation Ground is excavated manually or mechanically to form the excavation hole 1. In the figure, OA indicates the topsoil, B indicates the middle layer, and C indicates the supporting layer.

(2)鉄骨部材の組立 工場等で生産された鉄骨部材2を地上で組立てる。鉄骨
部材の下端には、軸直角方向に突出した定着部21があ
り、この定着部21にはめらかじめ鉄筋等を取付けるこ
とができる。また、鉄骨部材2の任意の位置にコンクリ
ートとの付着を増強するための突出部および注入管等を
保持するための突出部などを設けることがある。
(2) Steel frame members 2 produced at a steel frame assembly factory or the like are assembled on the ground. At the lower end of the steel frame member, there is a fixing section 21 that protrudes in the direction perpendicular to the axis, and a smooth reinforcing bar or the like can be attached to this fixing section 21. Further, a protrusion for enhancing adhesion to concrete, a protrusion for holding an injection pipe, etc. may be provided at any position on the steel frame member 2.

尚、地盤条件や粗骨材等の状態等により鉄骨部材に溶融
亜鉛メッキまたはモルタル等を付着させて、防錆処理を
行うことがめる。
Note that depending on the ground conditions, the condition of the coarse aggregate, etc., rust prevention treatment may be performed by applying hot-dip galvanizing or mortar to the steel frame members.

(3)基礎底部の形成 掘削孔1下底に鉄筋を配して通常のコンクリ−載置する
。さらに、支持部21がはは埋まる程度にコンフリート
ラ打設して、基礎底上部32を形成し、基礎底部乙の形
成全完了する。これによって鉄骨部材2は基礎底部3ま
で到達し、実に一体化されていることになり、圧縮力や
引揚力を確実に基礎底部に伝達できる。
(3) Formation of the bottom of the foundation Reinforcing bars are placed at the bottom of the excavated hole 1 and ordinary concrete is placed. Furthermore, a concrete slab is poured to such an extent that the support part 21 is fully buried to form the foundation bottom upper part 32, and the formation of the foundation bottom part B is completely completed. As a result, the steel frame member 2 reaches the foundation bottom 3 and is truly integrated, so that compressive force and lifting force can be reliably transmitted to the foundation bottom.

また、基礎底部6の形状は段差状の係止部35を形成し
、引揚力に有効に対抗させることもある。
Further, the shape of the base bottom 6 may form a stepped locking portion 35 to effectively counter the lifting force.

(4)基礎中間部の形成 基礎底部3上に基礎中間部4を形成する。(4) Formation of the intermediate part of the foundation A foundation intermediate portion 4 is formed on the foundation bottom portion 3.

基礎中間部4は掘削土から選出した骨材を充填し、プレ
パツクドコンクリートの手法などでモルタル等の固着剤
を注入して形成する。
The intermediate portion 4 of the foundation is formed by filling aggregate selected from excavated soil and injecting a fixing agent such as mortar using a prepacked concrete method.

尚、粗骨材41の充填に際しては、あらかじめ鉄骨部材
2の外周に鉄筋を配筋しておくこともあり、更にモルタ
ル等の充填用の注入管42やモルタルの充填状態を確認
する検査管を設置する。そして、…削土のうち、径15
〜75−y程度の礫状のもの、およびこれより大きな岩
片をクラッシャー等で粉砕したものを粗骨材41として
径2.5鮎程度以下の細粒分をモルタル用細骨材とし【
使用する。
In addition, when filling the coarse aggregate 41, reinforcing bars may be placed around the outer periphery of the steel frame member 2 in advance, and an injection pipe 42 for filling with mortar or the like and an inspection pipe for checking the state of mortar filling are also installed. Install. And... out of the excavated soil, diameter 15
Gravels of ~75-y size and larger rock pieces crushed with a crusher etc. are used as coarse aggregate 41, and fine particles with a diameter of about 2.5 mm or less are used as fine aggregate for mortar.
use.

(6) また、鉄骨部材2が鋼管である場合は外周に注入孔22
を設け、鉄骨部材を通してそのまわりにモルタル等を注
入することが可能である。
(6) In addition, if the steel frame member 2 is a steel pipe, there are injection holes 22 on the outer periphery.
It is possible to inject mortar etc. through the steel member and around it.

(5)基礎頭部の形成 基礎中間部4上に通常のコンクリートを打設して基礎底
部5を形成する。尚、この部分のコンクリート打設は、
基礎中間部4へのセルタル注入前であっても、注入後で
あってもいずれでもよい。
(5) Formation of the foundation head The foundation bottom 5 is formed by pouring ordinary concrete on the foundation middle part 4. In addition, concrete placement for this part is
The injection may be performed either before or after the injection of Sertal into the basal intermediate region 4.

その他の実施例: 第2図に示すごとく、鉄骨部材2が大径鋼管によって構
成されている場合は、鉄骨部材2内にも粗骨材41を充
填しモルタルを注入することも、また、現場発生土を充
填することも可能である。
Other Examples: As shown in Fig. 2, when the steel frame member 2 is made of a large diameter steel pipe, it is also possible to fill the steel frame member 2 with coarse aggregate 41 and inject mortar. It is also possible to fill with generated soil.

この発明にかかる構造物の基礎工法は以上のような構成
を有するため以下のような効果を得ることが可能である
Since the foundation construction method for a structure according to the present invention has the above configuration, it is possible to obtain the following effects.

(イ) 掘削孔を形成した後排出した掘削土な骨材とし
て使用するため、多蓋の構築材料の搬入および掘削土の
搬出がきわめて少なくなり工費を低廉化するととができ
る。
(b) Since the excavated soil discharged after forming the excavated hole is used as aggregate, the amount of carrying in construction materials for multiple lids and the carrying out of excavated soil is extremely reduced, which can reduce construction costs.

(ロ) 基礎頭部と基礎底部は密実な通常用いるコンク
リートによって形成し、基鉗中間部に施工するプレパツ
クドコンクリート等を上下から挾むことにより、信頼性
の高い基礎構造となる。すなわち基礎底部における構造
物脚部の定着が確実となり、脚部にかかる圧縮力も底部
内で均等に受けることになる。
(b) The foundation head and foundation bottom are made of dense, conventionally used concrete, and pre-packed concrete, etc., which is constructed in the middle of the foundation, is sandwiched from above and below to create a highly reliable foundation structure. In other words, the legs of the structure are securely anchored to the base bottom, and the compressive force applied to the legs is evenly received within the bottom.

(ハ) 基礎中間部にモルタルを注入して形成したプレ
パツクドコンクリート等は、掘削孔内周面との間に生ず
る摩擦によって、基礎にかかる引揚力に対し、基礎重量
とともに抵抗することが可能となる。また周辺地盤にモ
ルタルが浸透するため周辺地盤との一体化が図れること
となる。
(c) Prepacked concrete formed by injecting mortar into the intermediate part of the foundation can resist the lifting force applied to the foundation along with the weight of the foundation due to the friction generated between it and the inner peripheral surface of the excavation hole. becomes. Additionally, since the mortar permeates into the surrounding ground, it is possible to integrate it with the surrounding ground.

(ニ)  鉄骨部材を!!礎底部まで到達させコンクリ
ートによって一体化したため、上部構造からの圧縮力や
引揚力を確実に基礎底部に伝境できる。従って大きな引
揚力に対しても基礎中間部のプレパツクドコンクリート
には大きな引張応力が生ぜず、強度が若干低下したプレ
パツクドコンクリートであっても信頼性の高い基礎構造
が可能である。
(d) Steel members! ! By reaching the bottom of the foundation and integrating it with concrete, the compressive and uplifting forces from the superstructure can be reliably transmitted to the bottom of the foundation. Therefore, even with a large uplifting force, a large tensile stress does not occur in the prepacked concrete in the intermediate part of the foundation, and even with prepacked concrete whose strength is slightly reduced, a highly reliable foundation structure is possible.

更に鉄骨部材は基礎中間部のせん断、曲げ補強材を兼ね
ることとなり、基礎全体の強度向上が図れることになる
Furthermore, the steel frame members will also serve as shear and bending reinforcement for the middle part of the foundation, improving the strength of the entire foundation.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明にかかる構造物の基礎工法の施工状態
の一実施例の縦断面図、第2図は他の実施例の縦断面図
である。 1・・・掘削孔、2・・・鉄骨部材、6・・・基礎底部
、4・・・基礎中間部、5・・・基礎底部。 21・・・支持部、22・・・注入孔、31・・・基礎
底下部、62・・・基硯底上部、41・・・粗骨材。 42・・・注入管、ム・・・表土、B・・・中間層。 C・・・支持ノー。 (7) 第1図 第2図 手続補正書 昭和57年10月 15日 1、事件の表示 昭和57年特   願第87470号 2、発 明の名称 構造物の基礎工法 5、補正命令の日付 自発補正 昭和   年   月   日 (発送日)6、補正に
より増加する発明の数 t 明細書、第5頁第7行目の「基礎底部」を「基礎頭
部」と補正する。 2、明細書、第7頁lll5行目の「5・・・・・・基
礎底部」を「5・・・・・・基礎頭部」と補正する。
FIG. 1 is a longitudinal cross-sectional view of one embodiment of the construction state of the foundation construction method for a structure according to the present invention, and FIG. 2 is a longitudinal cross-sectional view of another embodiment. DESCRIPTION OF SYMBOLS 1... Excavation hole, 2... Steel frame member, 6... Foundation bottom, 4... Foundation intermediate part, 5... Foundation bottom. 21... Support part, 22... Injection hole, 31... Lower part of foundation bottom, 62... Upper part of base bottom, 41... Coarse aggregate. 42... Injection pipe, M... Topsoil, B... Middle layer. C...No support. (7) Figure 1 Figure 2 Procedural amendment October 15, 1981 1, Indication of the case, 1982 Patent Application No. 87470 2, Name of invention Method of foundation construction for structures 5, Date of amendment order Voluntary action Amendment Showa year, month, day (shipment date) 6, number of inventions increased by the amendment t The description, page 5, line 7, "base bottom" is amended to "base head". 2. In the specification, page 7, line 5, "5...base bottom" is corrected to "5...base head".

Claims (1)

【特許請求の範囲】 地盤を掘削して掘削孔を形成し、該掘削孔下底に築造す
る鉄骨部材を固定する 密実な通常用いるコンクリート
を打設して、基礎底部を形成し、該基礎底部上へ掘削土
等の現場発生土を選別等により骨材とし【有効に利用し
たプレパツクドコンクリートなどの手法による粗なコン
クリートによって前記鉄骨部材廻りに充填し、さらにそ
の上部へ通常のコンクリートを打設して基礎頭部を形成
してなる構造物の基礎工法。
[Scope of Claims] The ground is excavated to form an excavation hole, and a steel frame member to be constructed is fixed at the bottom of the excavation hole. A dense ordinarily used concrete is poured to form the bottom of the foundation, and the foundation is The soil generated on site, such as excavated soil, is sorted onto the bottom and used as aggregate. A foundation construction method for structures in which the foundation head is formed by pouring concrete.
JP8747082A 1982-05-24 1982-05-24 Foundation construction method for structures Expired JPS6030817B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8747082A JPS6030817B2 (en) 1982-05-24 1982-05-24 Foundation construction method for structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8747082A JPS6030817B2 (en) 1982-05-24 1982-05-24 Foundation construction method for structures

Publications (2)

Publication Number Publication Date
JPS58204227A true JPS58204227A (en) 1983-11-28
JPS6030817B2 JPS6030817B2 (en) 1985-07-18

Family

ID=13915788

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8747082A Expired JPS6030817B2 (en) 1982-05-24 1982-05-24 Foundation construction method for structures

Country Status (1)

Country Link
JP (1) JPS6030817B2 (en)

Also Published As

Publication number Publication date
JPS6030817B2 (en) 1985-07-18

Similar Documents

Publication Publication Date Title
CN106284341B (en) A kind of prestress anchorage cable hillside wall construction technology
US20080019779A1 (en) Steel-Cased Concrete Piers
JP2001342685A (en) Recycling type environmental protection construction method in restriction type discrete body arch (or dome) structure
JP3107716B2 (en) Soil retaining wall
JPS63233120A (en) Foundation work for wooden building
JPS62260919A (en) Small pile for reinforcing foundation ground to earthquake
JPS58204227A (en) Foundation work of structure
JP2021188354A (en) Precast prestressed concrete foundation structure and its construction method
JP2022068465A (en) Integrated construction method of reinforced ground improvement pile and upper structure
JPH07279184A (en) Floating underground beam foundation for building
JPH0525821A (en) Continuous underground wall and its construction method
KR200193612Y1 (en) Concrete repair of bridge well with transparent form panel
JPS58127822A (en) Liquefaction preventive structure of foundation ground
JPH0617414A (en) Drainage reinforcement pile
JPS6110622A (en) Method of constructing cast-in-place concrete pile
JP2810602B2 (en) Foundation construction method
JPH09100536A (en) Basic structure of building
JPH07286323A (en) Pile structure
Choudhury Metallurgical Production Plant—Civil and Structural Work
JPS58127823A (en) Liquefaction preventive structure of foundation ground
JPS62129420A (en) Reinforcing method for tank foundation ground
Cracknell THE RUNNYMEDE BRIDGE.
JPS62276119A (en) Composite piling work
GENERAL B. 2 MATERIALS
JPS60173215A (en) Construction work of cast-in-place pile