[go: up one dir, main page]

JPH11207574A - Production control system and method, and recording medium - Google Patents

Production control system and method, and recording medium

Info

Publication number
JPH11207574A
JPH11207574A JP965998A JP965998A JPH11207574A JP H11207574 A JPH11207574 A JP H11207574A JP 965998 A JP965998 A JP 965998A JP 965998 A JP965998 A JP 965998A JP H11207574 A JPH11207574 A JP H11207574A
Authority
JP
Japan
Prior art keywords
information
production plan
arrangement
production
parts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP965998A
Other languages
Japanese (ja)
Inventor
Kisuke Kenmori
起資 権守
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
NEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Corp filed Critical NEC Corp
Priority to JP965998A priority Critical patent/JPH11207574A/en
Publication of JPH11207574A publication Critical patent/JPH11207574A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

PROBLEM TO BE SOLVED: To coordinate an arrangement request for parts required for product production and a product production plan with each other. SOLUTION: Depending on the production standard information, stock information and production plan that storage parts 31, 32 and 33 store respectively, a required-quantity calculation part 21 calculates a prepared quantity of parts arranged for product production. The arranged quantity is stored in an arrangement request storage part 34, and also stored in a production plan-to- arrangement request relevant information storage part 35 with relevancy to the production plan. When a retrieval part 22 for production plans required to be altered retrieves any production plan required to be altered out from the production plan-to-arrangement request relevant information storage part 35, the operator operates an input device 1 to alter the part arranged quantity and the production plan with the help of the functions of an arrangement request alteration part 23 and production plan alteration part 24. Repeating this routine coordinates the part arrangement request and the production plan with each other.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、生産管理システ
ム、方法及び記録媒体に関し、特に生産計画と部品の手
配との調整を可能とするものに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production management system, a method, and a recording medium, and more particularly, to a production management system and method capable of adjusting a production plan and parts arrangement.

【0002】[0002]

【従来の技術】従来の生産管理システムにおいて、製品
の生産計画と、その製品の生産に必要となる部品の調達
のための指示(以下、手配指示という)とは、次のよう
にして調整されていた。すなわち、従来の生産管理シス
テムでは、製品の生産に必要となる階層的な部品の数
量、各部品の生産に必要となる期間及び各部品を手配す
るための単位となる数量からなる生産基準情報、各部品
の在庫情報並びに製品の生産計画を記憶しており、この
生産基準情報をもとに新たな部品がいつ、どれだけ必要
となるかの所要量を計算していた。
2. Description of the Related Art In a conventional production management system, a production plan of a product and an instruction for procuring parts required for the production of the product (hereinafter referred to as "arrangement instruction") are adjusted as follows. I was That is, in the conventional production management system, the number of hierarchical parts required for the production of products, the production period information required for the production of each part, and the production reference information including the unit quantity for arranging each part, The stock information of each part and the production plan of the product are stored, and the required quantity of when and how much new parts are required is calculated based on the production standard information.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記従
来の生産管理システムでは、製品の生産に必要となる部
品の手配指示を変更した場合に、どの製品のいつの生産
計画に影響がでるかわからないという問題点があった。
例えば、部品の手配指示の変更によって、特定の部品の
在庫量が必要以上に多くなり、在庫管理のためのコスト
が生じてしまうような事態が発生することがあった。す
なわち、従来の生産管理システムでは、部品の手配指示
を変更した場合に製品の生産計画との調整を図ることが
できず、効率的な生産管理を行い得なくなるという問題
があった。
However, in the above-mentioned conventional production management system, it is not possible to know which product is to be produced and which production schedule will be affected when the instructions for arranging parts required for producing the product are changed. There was a point.
For example, a change in the parts arrangement instruction may cause a situation in which the inventory amount of a specific part becomes unnecessarily large, and a cost for inventory management occurs. In other words, the conventional production management system has a problem in that when a part arrangement instruction is changed, adjustment with a product production plan cannot be performed, and efficient production management cannot be performed.

【0004】本発明は、上記の従来技術の問題点を解消
するためになされたものであり、製品の生産に必要とな
る部品の手配と製品の生産計画との調整を図ることを可
能とする生産管理システム及び方法、並びにこのような
生産管理の機能を実現すっるためのプログラムを記憶し
たコンピュータ読み取り可能な記録媒体を提供すること
を目的とする。
The present invention has been made to solve the above-mentioned problems of the prior art, and makes it possible to arrange parts necessary for the production of a product and to adjust a production plan of the product. An object of the present invention is to provide a production management system and method, and a computer-readable recording medium storing a program for realizing such a production management function.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するた
め、本発明の第1の観点にかかる生産管理システムは、
製品を生産するために必要となる部品に関する情報を記
憶する生産基準情報記憶手段と、前記生産基準情報記憶
手段に記憶されている前記部品のそれぞれについての在
庫情報を記憶する在庫情報記憶手段と、前記部品から前
記製品を生産するための生産計画を記憶する生産計画記
憶手段と、前記生産基準情報記憶手段に記憶されている
前記部品に関する情報、前記在庫情報記憶手段に記憶さ
れている在庫情報及び前記生産計画記憶手段に記憶され
ている生産計画に基づいて、前記製品を生産するために
必要となる部品の手配に関する情報と該情報のそれぞれ
に対応する生産計画の部分とを算出する手配情報算出手
段と、前記手配情報算出手段によって算出された前記部
品の手配に関する情報と該情報のそれぞれと対応する生
産計画の部分を関連付けて記憶する生産計画・手配情報
記憶手段と、前記手配情報算出手段によって算出された
前記部品の手配に関する情報を変更するための情報を入
力する手配情報変更手段と、前記生産計画・手配情報記
憶手段に前記部品の手配に関する情報とそれぞれ関連付
けられて記憶されている生産計画の部分のうちの変更を
要する部分を、前記手配情報変更手段によって入力され
た部品の手配に関する情報を変更するための情報に従っ
て抽出する要変更生産計画抽出手段と、前記生産計画記
憶手段に記憶されている前記生産計画を変更する生産計
画変更手段と、を備えることを特徴とする。
In order to achieve the above object, a production management system according to a first aspect of the present invention comprises:
A production reference information storage means for storing information relating to parts required for producing a product, and a stock information storage means for storing inventory information for each of the parts stored in the production reference information storage means, A production plan storage means for storing a production plan for producing the product from the parts, information on the parts stored in the production reference information storage means, inventory information stored in the inventory information storage means, Based on the production plan stored in the production plan storage means, arrangement information calculation for calculating information on the arrangement of parts necessary for producing the product and a part of the production plan corresponding to each of the information. Means and information on the arrangement of the parts calculated by the arrangement information calculating means and a part of the production plan corresponding to each of the information. Production plan / arrangement information storage means for attaching and storing; arrangement information change means for inputting information for changing information relating to the arrangement of parts calculated by the arrangement information calculation means; and the production plan / arrangement information storage Means for changing the part-related information input by the part-information changing means, for the part of the part of the production plan stored in association with the part-related information and stored in the means. And a production plan changing means for changing the production plan stored in the production plan storage means.

【0006】上記生産管理システムでは、前記要変更抽
出手段が抽出した生産計画のうちの変更を要する部分を
生産計画変更手段によって変更することができる。ここ
で、要変更抽出手段による変更を要する生産計画の部分
の抽出には、前記手配情報変更手段による前記部品の手
配に関する情報が反映される。さらに、手配情報算出手
段は、生産計画変更手段によって変更された生産計画に
基づいて、新たな手配情報の算出を行うことができる。
従って、上記生産管理システムでは、前記手配情報変更
手段による部品の手配に関する情報の変更及び前記生産
計画変更手段による生産計画の変更を繰り返すことによ
って、製品の生産に必要となる部品の手配に関する情報
と製品の生産計画との調整を図ることができ、効率的な
生産管理を行うことができる。
In the above-mentioned production management system, a part of the production plan extracted by the change-requiring extracting means, which needs to be changed, can be changed by the production-plan changing means. Here, the information on the arrangement of the parts by the arrangement information changing means is reflected in the extraction of the part of the production plan requiring the change by the change required extracting means. Further, the arrangement information calculating means can calculate new arrangement information based on the production plan changed by the production plan changing means.
Therefore, in the production management system, by repeating the change of the information on the part arrangement by the arrangement information changing means and the change of the production plan by the production plan changing means, the information on the part arrangement necessary for the production of the product is obtained. Coordination with the product production plan can be achieved, and efficient production management can be performed.

【0007】上記生産管理システムは、前記要変更生産
計画抽出手段によって抽出された変更を要する生産計画
の部分に関する情報を出力する第1の出力手段を備えて
もよい。
[0007] The production management system may include first output means for outputting information on a part of the production plan requiring change extracted by the change-necessary production plan extraction means.

【0008】また、上記生産管理システムにおいて、前
記生産計画変更手段は、前記要変更生産計画抽出手段に
よって抽出された変更を要する部分に対応する前記生産
計画記憶手段内の生産計画を変更する手段を備えるもの
とすることができる。
In the above-mentioned production management system, the production plan changing means includes means for changing a production plan in the production plan storage means corresponding to a portion requiring change extracted by the changed production plan extraction means. Can be provided.

【0009】上記生産管理システムは、さらに、前記手
配情報算出手段が算出した前記製品を生産するために必
要となる部品の手配に関する情報を出力する第2の出力
手段を備えてもよい。
[0009] The production management system may further include second output means for outputting information on arrangement of parts required for producing the product calculated by the arrangement information calculation means.

【0010】上記目的を達成するため、本発明の第2の
観点にかかる生産管理方法は、記憶装置に記憶されてい
る製品を生産するために必要となる部品に関する情報
と、前記部品のそれぞれについての在庫情報と、前記部
品から前記製品を生産するための生産計画とに基づい
て、前記製品を生産するために必要となる部品の手配に
関する情報を算出し、該算出された部品の手配に関する
情報に基づいて、前記製品の生産管理を行う生産管理方
法であって、前記算出された部品の手配に関する情報と
前記生産管理の部分との関連付けを算出する関連算出ス
テップと、前記算出された部品の手配に関する情報を変
更するための情報を入力する手配情報変更ステップと、
前記関連算出ステップで部品の手配に関する情報に関連
付けて算出された前記生産管理の部分のうち変更を要す
る部分を、前記手配情報変更ステップで入力された部品
の手配に関する情報を変更するための情報に従って抽出
する要変更生産計画抽出ステップと、前記記憶装置に記
憶されている生産計画のうちの前記要変更生産計画抽出
ステップで抽出された部分を変更する生産計画変更ステ
ップと、を含むことを特徴とする。
In order to achieve the above object, a production management method according to a second aspect of the present invention provides information on parts necessary for producing a product stored in a storage device and information on each of the parts. Based on the stock information and the production plan for producing the product from the parts, information on the arrangement of parts necessary for producing the product is calculated, and the information on the arrangement of the calculated parts is calculated. A production management method for performing production management of the product, based on the relationship, the association calculation step of calculating the association between the information on the calculated part arrangement and the part of the production management, An arrangement information change step of inputting information for changing information on the arrangement;
The part that needs to be changed among the parts of the production management calculated in association with the information about the parts arrangement in the association calculation step is determined according to the information for changing the parts arrangement information input in the arrangement information change step. A change-required production plan extraction step of extracting, and a production plan change step of changing a portion of the production plan stored in the storage device extracted in the change-required production plan extraction step. I do.

【0011】上記目的を達成するため、本発明の第3の
観点にかかるコンピュータ読み取り可能な記録媒体は、
製品を生産するために必要となる部品に関する情報を第
1の記憶装置に記憶させる生産基準情報記憶機能と、前
記部品のそれぞれについての在庫情報を第2の記憶装置
に記憶させる在庫情報記憶機能と、前記部品から前記製
品を生産するための生産計画を第3の記憶装置に記憶さ
せる生産計画記憶機能と、前記生産基準情報記憶機能に
よって前記第1の記憶装置に記憶された前記部品に関す
る情報、前記生産基準情報記憶機能によって前記第2の
記憶装置に記憶された前記在庫情報及び前記生産計画記
憶機能によって前記第3の記憶装置に記憶された生産計
画に基づいて、前記製品を生産するために必要となる部
品の手配に関する情報と該情報のそれぞれに対応する生
産計画の部分とを算出する手配情報算出機能と、前記手
配情報算出機能によって算出された前記部品の手配に関
する情報と該情報のそれぞれと対応する生産計画の部分
を関連付けて第4の記憶装置に記憶させる記憶する生産
計画・手配情報記憶機能と、前記生産計画・手配情報記
憶機能によって前記第4の記憶装置に前記部品の手配に
関する情報とそれぞれ関連付けられて記憶された生産計
画の部分のうちの変更を要する部分を、前記手配情報変
更機能によって入力された部品の手配に関する情報を変
更するための情報に従って抽出する要変更生産計画抽出
機能と、前記要変更生産計画抽出機能によって抽出され
た変更を要する部分に対応する前記第3の記憶装置内の
生産計画を変更する生産計画変更機能と、前記手配情報
算出機能によって算出された前記製品を生産するために
必要となる部品の手配に関する情報を外部に出力する出
力機能と、を実行するためのプログラムを記憶すること
を特徴とする。
In order to achieve the above object, a computer-readable recording medium according to a third aspect of the present invention comprises:
A production reference information storage function for storing information relating to parts required for producing a product in the first storage device, and a stock information storage function for storing inventory information for each of the components in the second storage device. A production plan storage function for storing a production plan for producing the product from the component in a third storage device, and information about the component stored in the first storage device by the production reference information storage function; To produce the product based on the inventory information stored in the second storage device by the production reference information storage function and the production plan stored in the third storage device by the production plan storage function An arrangement information calculation function for calculating information on arrangement of necessary parts and a part of a production plan corresponding to each of the information; A production plan / arrangement information storage function for storing information relating to the arrangement of the parts calculated in accordance with the above and a part of the production plan corresponding to each of the information and storing them in a fourth storage device; The part requiring the change among the parts of the production plan stored in the fourth storage device in association with the information on the arrangement of the parts in the fourth storage device by the information storage function is the arrangement of the parts input by the arrangement information change function. And the production plan in the third storage device corresponding to the part requiring the change extracted by the required production plan extraction function, which is extracted according to the information for changing the information related to the production plan. A production plan change function and information on arrangement of parts required for producing the product calculated by the arrangement information calculation function Characterized by storing a program for executing an output function of outputting to the outside.

【0012】[0012]

【発明の実施の形態】以下、添付図面を参照して、本発
明の実施の形態について説明する。
Embodiments of the present invention will be described below with reference to the accompanying drawings.

【0013】図1は、この実施の形態の生産管理システ
ムの構成を示す機能ブロック図である。この生産管理シ
ステムは、ワークステーションやパーソナルコンピュー
タなどの単一の情報処理装置によって実現されもので、
入力装置1と、データ処理装置2と、記憶装置3と、出
力装置4とから構成されている。
FIG. 1 is a functional block diagram showing the configuration of the production management system according to this embodiment. This production management system is realized by a single information processing device such as a workstation or personal computer.
It comprises an input device 1, a data processing device 2, a storage device 3, and an output device 4.

【0014】入力装置1は、キーボードなどによって構
成され、オペレータの操作によって各種情報の入力や、
データ処理装置2の各機能を実行させるためのコマンド
の投入に用いられる。
The input device 1 is composed of a keyboard or the like, and inputs various information by an operation of an operator.
It is used for inputting a command for executing each function of the data processing device 2.

【0015】データ処理装置2は、プログラム制御され
るCPU(中央処理装置)からなり、所要量計算部2
1、変更の必要な生産計画検索部22、手配指示変更部
23及び生産計画変更部24の各機能を含む。記憶装置
3は、主記憶装置及び補助記憶装置によって構成され、
生産基準情報記憶部31、在庫情報記憶部32、生産計
画記憶部33、手配指示記憶部34、生産計画・手配指
示関連情報記憶部35及び手配指示変更情報記憶部36
の各記憶領域を含む。
The data processing unit 2 comprises a CPU (central processing unit) controlled by a program.
1. Includes the functions of a production plan search unit 22, an arrangement instruction change unit 23, and a production plan change unit 24 that need to be changed. The storage device 3 includes a main storage device and an auxiliary storage device,
Production reference information storage unit 31, inventory information storage unit 32, production plan storage unit 33, arrangement instruction storage unit 34, production plan / arrangement instruction related information storage unit 35, and arrangement instruction change information storage unit 36
Of each storage area.

【0016】生産基準情報記憶部31は、製品を生産す
るために必要となる部品の階層的な数量(以下、単位数
量という)と、各部品の生産に必要となる期間(以下、
LTという)と、各部品を手配するための単位となる数
量(以下、ロット数量という)とからなる生産基準情報
を記憶する。
The production reference information storage unit 31 stores a hierarchical quantity of parts (hereinafter referred to as a unit quantity) required for producing a product and a period required for producing each part (hereinafter referred to as a unit quantity).
LT) and production reference information including a unit quantity (hereinafter, referred to as a lot quantity) for arranging each part.

【0017】在庫情報記憶部32は、製品を構成する各
部品、またはその部品を生産するための下位の部品につ
いて、部品名と在庫数からなる在庫情報を記憶する。生
産計画記憶部33は、生産計画の対象となる製品または
部品の部品名、納期及び納入数量を関連付ける生産計画
を記憶する。
The stock information storage unit 32 stores stock information including a part name and the number of stocks for each part constituting a product or a lower order part for producing the part. The production plan storage unit 33 stores a production plan that associates a part name, a delivery date, and a delivery quantity of a product or a part to be subjected to the production plan.

【0018】所要量計算部21は、生産基準情報記憶部
31に記憶されている生産基準情報と、生産計画記憶部
33に記憶されている生産計画とに基づいて、製品また
は部品を生産するのにいつ、どれだけの下位の部品が必
要になるかを示す情報(以下、所要量という)を計算す
る。所要量計算部21は、さらに計算した所要量と在庫
情報記憶部32に記憶されている在庫情報とに基づい
て、日付毎に手配すべき部品の数量(以下、手配量とい
う)を計算する。
The required quantity calculation unit 21 produces a product or a part based on the production standard information stored in the production standard information storage unit 31 and the production plan stored in the production plan storage unit 33. Then, information indicating when and how many lower-level parts are required (hereinafter referred to as a required amount) is calculated. The required amount calculation unit 21 further calculates the quantity of parts to be arranged for each date (hereinafter, referred to as an order amount) based on the calculated required amount and the stock information stored in the stock information storage unit 32.

【0019】手配指示記憶部34は、所要量計算部21
によって計算された各部品の手配量とその部品の調達が
必要となる日付とを関連付けて記憶する。生産計画・手
配指示関連情報記憶部35は、所要量計算部21によっ
て計算された各部品の手配量と、その手配量に対応する
生産計画とを関連付けて記憶する。ここで、手配すべき
各部品を生産するために必要となる下位の部品の手配日
も関連付けて記憶される。この記憶内容は、所要量計算
部21の計算結果に基づく。
The arrangement instruction storage unit 34 includes the required amount calculation unit 21
Are stored in association with the order quantity of each part calculated by the above and the date when the procurement of the part is required. The production plan / arrangement instruction related information storage unit 35 stores the arrangement amount of each component calculated by the required amount calculation unit 21 and the production plan corresponding to the arrangement amount in association with each other. Here, the arrangement date of the lower-order parts required for producing each part to be arranged is also stored in association with the parts. This storage content is based on the calculation result of the required amount calculation unit 21.

【0020】変更の必要な必要な生産計画検索部22
は、生産計画記憶部33、手配指示記憶部34、生産計
画・手配指示関連情報記憶部35及び後述する手配指示
変更情報記憶部36の記憶内容に基づいて、変更の必要
がある生産計画、例えば、部品の手配が間に合わない生
産計画を検索する。変更の必要がある生産計画が検索さ
れた場合には、変更の必要な生産計画検索部22は、検
索された生産計画と生産計画を変更すべきことを警告す
るアラームを出力装置4に出力する。
A necessary production plan search unit 22 that needs to be changed
Based on the storage contents of the production plan storage unit 33, the arrangement instruction storage unit 34, the production plan / arrangement instruction related information storage unit 35, and the arrangement instruction change information storage unit 36 described later, for example, Search for a production plan for which parts can not be arranged in time. When a production plan that needs to be changed is searched, the production plan searching unit 22 that needs to change outputs the searched production plan and an alarm that warns that the production plan should be changed to the output device 4. .

【0021】手配指示変更部23は、特に変更の必要な
生産計画部22で変更の必要な生産計画が検索されたと
きに、オペレータによる入力装置1の操作に従って手配
すべき部品を変更する手配指示変更情報を作成する。手
配指示変更部23によって作成された手配指示変更情報
は、手配変更情報記憶部36に記憶される。
The arrangement instruction change section 23 is an arrangement instruction for changing a part to be arranged in accordance with an operation of the input device 1 by an operator when a production plan requiring a change is searched by the production plan section 22 requiring a change. Create change information. The arrangement instruction change information created by the arrangement instruction change unit 23 is stored in the arrangement change information storage unit 36.

【0022】生産計画変更部24は、特に変更の必要な
生産計画部22で変更の必要な生産計画が検索されたと
きに、オペレータによる入力装置1の操作に従って生産
計画を変更する。変更された生産計画は、生産計画記憶
部33に上書きされる。
The production plan changing unit 24 changes the production plan in accordance with the operation of the input device 1 by the operator when the production plan which needs to be changed is searched by the production plan unit 22 which needs to be changed. The changed production plan is overwritten in the production plan storage unit 33.

【0023】出力装置4は、ディスプレイ装置、印刷装
置或いは音声出力装置によって構成され、所要量計算部
21によって計算された手配量と、変更の必要な生産計
画検索部22によって検索された変更の必要な生産計画
或いはその旨を示すアラームを出力して、オペレータに
提示する。
The output device 4 is composed of a display device, a printing device or a sound output device. The arrangement amount calculated by the required amount calculation unit 21 and the change required by the production plan search unit 22 needing change need to be changed. The production plan or an alarm indicating the production plan is output and presented to the operator.

【0024】以下、この実施の形態の生産管理システム
における処理について、具体的な例を参照しながら説明
する。この例では、生産管理の対象となっているものに
最終的な製品はなく、複数の部品からより大きな部品を
生産する場合について説明するものとする。
Hereinafter, processing in the production management system according to this embodiment will be described with reference to a specific example. In this example, there will be described a case where there is no final product as a target of production management and a larger part is produced from a plurality of parts.

【0025】ここで、この生産管理システムにおいて部
品の手配指示の変更を実行する前における生産情報記憶
部31、在庫情報記憶部32及び生産計画記憶部33に
は、例えば、オペレータによる入力装置1の操作によっ
て、図2〜図4に示す内容が予め記憶されているもので
あるとする。また、この生産管理システムにおいて部品
の手配指示の変更を実行する日付は、9月30日である
ものとする。
Here, the production information storage unit 31, the stock information storage unit 32, and the production plan storage unit 33 before the change of the part arrangement instruction in the production management system are stored in, for example, the input device 1 of the operator. It is assumed that the contents shown in FIGS. 2 to 4 are stored in advance by the operation. It is assumed that the date on which the change of the parts arrangement instruction is executed in this production management system is September 30.

【0026】生産情報記憶部31に記憶されている情報
は、図2に模式的に示すように、部品Aを生産するのに
部品Xと部品Dとが、部品Bを作るのに部品Yと部品E
とが、部品Cを生産するのに部品Zと部品Fとが、部品
D、E、Fを生産するのにそれぞれ部品Gが必要である
ことを示す。ここで、各部品を生産するのに必要となる
部品の単位数量は、すべて1個である。また、部品Gを
生産ためのLTは4日であり、は他の部品を作るための
LTは1日であることを示す。ロット数量は、部品D、
E、Gについてそれぞれ20個、他の部品については1
個であることを示す。
The information stored in the production information storage unit 31 includes, as schematically shown in FIG. 2, a part X and a part D for producing a part A, and a part Y and a part Y for producing a part B. Part E
Indicates that parts Z and F are required to produce part C, and parts G are required to produce parts D, E, and F, respectively. Here, the unit quantity of each component required to produce each component is one. Also, LT for producing the part G is 4 days, and LT for producing another part is 1 day. Lot quantity is part D,
20 for each of E and G, 1 for other parts
Indicates that there are

【0027】また、在庫情報記憶部32に記憶されてい
る情報は、図3に示すように、部品Dの在庫が10個あ
り、他の部品A〜C、E〜Gの在庫がいずれもないこと
を示す。なお、図には記載しないが、部品X、Y、Zに
ついては常に十分な在庫があるものとする。
As shown in FIG. 3, the information stored in the stock information storage section 32 has a stock of 10 parts D and no stock of other parts A to C and EG. Indicates that Although not shown in the drawing, it is assumed that parts X, Y, and Z are always in sufficient stock.

【0028】また、生産計画記憶部33に記憶されてい
る情報は、図4に示すように、10月3日には部品Aが
10個必要であり、10月4日には部品Aが10個必要
であり、10月5日には部品A、B、Cが10個ずつ必
要であり、10月6日には部品A、B、Cが10個ずつ
必要であることをそれぞれ示す。
As shown in FIG. 4, the information stored in the production plan storage unit 33 requires 10 parts A on October 3 and 10 parts A on October 4. This means that 10 parts A, B, and C are required on October 5, and 10 parts A, B, and C are required on October 6, respectively.

【0029】オペレータによる入力装置1の操作などに
よって処理の指示がなされると、上記のように生産基準
情報記憶部31、生産計画記憶部33にそれぞれ記憶さ
れている情報に基づいて、製品の生産に必要となる部品
の所要量が所要量計算部21によって計算される。さら
に、この所要量と在庫情報記憶部32に記憶されている
在庫情報とに基づいて、部品の手配量が所要量計算部2
1によって計算される。
When a processing instruction is given by an operation of the input device 1 by an operator or the like, the production of a product is performed based on the information stored in the production reference information storage unit 31 and the production plan storage unit 33 as described above. Is calculated by the required amount calculation unit 21. Further, based on the required amount and the inventory information stored in the inventory information storage unit 32, the order quantity of the part is calculated by the required amount calculation unit 2
Calculated by 1.

【0030】所要量計算部21は、部品の手配量を日付
と関連付けて手配指示記憶部34に、手配される部品と
生産計画とを関連付けて生産計画・手配指示関連情報記
憶部35にそれぞれ記憶させる。図2〜図4の例の情報
に基づいて、所要量計算部21が計算を行って手配指示
記憶部34と生産計画・手配指示関連情報記憶部35に
それぞれ記憶させた記憶内容の例を図5と図6に示す。
The required quantity calculation unit 21 stores the order quantity of the parts in the order instruction storage unit 34 in association with the date, and associates the parts to be arranged with the production plan in the production plan / order instruction related information storage unit 35. Let it. FIG. 4 shows an example of storage contents calculated by the required amount calculation unit 21 based on the information in the examples of FIGS. 2 to 4 and stored in the arrangement instruction storage unit 34 and the production plan / arrangement instruction related information storage unit 35, respectively. 5 and FIG.

【0031】図5に示す手配指示記憶部34の記憶内容
について説明する。例えば、図4に示したように10月
3日に部品Aを生産するためには、10月2日に部品D
が10個必要であるが、図3に示したように在庫が10
個あるため、10月2日での部品Dの手配はしない。1
0月3日にも部品Dが10個必要となるが、図2に示し
たように部品Dのロット数量が20個であるため、10
月3日に部品Dを20個手配する。10月4日にも部品
Dが必要となるが、10月3日に手配した分の残りがあ
るため、10月4日に部品Dを手配しない。以下、同様
にして他の部品についても手配量が計算され、図4に示
すような内容が手配指示記憶部34に記憶される。な
お、この内容は、出力装置4からも出力されて、オペレ
ータに提示される。
The storage contents of the arrangement instruction storage section 34 shown in FIG. 5 will be described. For example, as shown in FIG. 4, in order to produce a part A on October 3, a part D
Is required, but as shown in FIG.
Since there are individual parts, we will not arrange the parts D on October 2. 1
On October 3, ten parts D are required. However, since the lot quantity of the parts D is 20 as shown in FIG.
On March 3, 20 parts D are arranged. The part D is also required on October 4, but the part D is not arranged on October 4 because there is a remainder of the arrangement on October 3. Hereinafter, the order amount is calculated for other parts in the same manner, and the contents shown in FIG. 4 are stored in the order instruction storage unit 34. This content is also output from the output device 4 and presented to the operator.

【0032】図6に示す生産計画・手配指示関連情報記
憶部35の記憶内容について説明する。例えば、部品D
について、10月3日に手配した20個のうち10個が
10月3日に必要となり、残りの10個が10月4日に
必要となる。このように生産計画に従うと、手配日が同
じでも必要日が異なる場合には、手配される部品は、図
6に示すようにそれぞれ別々のレコードとして生産計画
・関連情報記憶部34に記憶される。
The storage contents of the production plan / arrangement instruction related information storage section 35 shown in FIG. 6 will be described. For example, part D
Regarding, 10 out of the 20 pieces arranged on October 3 are needed on October 3, and the remaining 10 pieces are needed on October 4. According to the production plan as described above, if the required dates are different even if the arrangement dates are the same, the arranged parts are stored in the production plan / related information storage unit 34 as separate records as shown in FIG. .

【0033】次に、変更の必要な生産計画検索部22
は、変更の必要な生産計画の部分を検索する。この例で
は、図2に示したように部品GのLTが4日であるた
め、10月2日と10月3日との部品Dの手配が間に合
わず、生産計画を変更しなければならない。そこで、変
更の必要な生産計画検索部22は、この生産計画の部分
と、該部分を変更すべきことを警告するアラームを出力
装置4に出力させる。
Next, the production plan search section 22 that needs to be changed
Finds the parts of the production plan that need to be changed. In this example, as shown in FIG. 2, since the LT of the part G is four days, the arrangement of the part D between October 2 and October 3 cannot be made in time, and the production plan must be changed. Therefore, the production plan search unit 22 that needs to be changed causes the output device 4 to output a part of the production plan and an alarm that warns that the part should be changed.

【0034】このアラームに応答して、オペレータは入
力装置1を操作して、部品の手配量を変更を入力する。
この入力に従って、手配指示変更部23は、図7に示す
ような部品の手配量を変更するための情報を作成し、手
配指示変更情報記憶部36に記憶させる。
In response to this alarm, the operator operates the input device 1 to input a change in the quantity of parts to be arranged.
In accordance with this input, the arrangement instruction change unit 23 creates information for changing the arrangement amount of the parts as shown in FIG. 7 and stores the information in the arrangement instruction change information storage unit 36.

【0035】さらに、変更の必要な生産計画検索部22
は、生産計画・手配指示関連情報記憶部35、手配指示
情報記憶部34、生産計画記憶部32、さらに手配指示
変更情報記憶部36に記憶された手配量を変更するため
の情報に従って、図8に示すように調整の必要な生産計
画の部分を出力装置4に出力する。
Further, the production plan search section 22 which needs to be changed
8 according to the information for changing the order quantity stored in the production plan / arrangement instruction related information storage unit 35, the arrangement instruction information storage unit 34, the production plan storage unit 32, and the arrangement instruction change information storage unit 36. The portion of the production plan requiring adjustment is output to the output device 4 as shown in FIG.

【0036】変更の必要な生産計画検索部22による図
8に示す結果を求める手順について、説明する。まず、
手配指示変更情報36の記憶内容(図7)から、10月
2日の部品Gの手配量が20個から0個に変更された情
報を取得する。次に、生産計画・手配指示関連情報記憶
部36の記憶内容(図6)を参照すると、部品Gの10
月2日の手配量を20個から0個に変更したことで、部
品Dの10月3日における手配量も20個から10個に
なり、影響が生じることが分かる。同様に、部品Aの1
0月3日、10月4日における生産計画も10個から0
個に変更しなければならないことが分かる。
The procedure for obtaining the results shown in FIG. 8 by the production plan search unit 22 that needs to be changed will be described. First,
From the stored contents of the arrangement instruction change information 36 (FIG. 7), information is obtained that the arrangement amount of the part G on October 2 has been changed from 20 to 0. Next, referring to the storage contents (FIG. 6) of the production plan / arrangement instruction related information storage unit 36, the 10
It can be seen that, by changing the order quantity of the month 2 from 20 pieces to 0 pieces, the order quantity of the part D on October 3 also changes from 20 pieces to 10 pieces, which has an effect. Similarly, 1 of part A
The production plan for October 3 and October 4 is also reduced from 10 to 0
It turns out that you have to change to individual.

【0037】また、部品Gの手配指示が10月3日に3
0個から20個への変更されたことにより、部品Eの1
0月4日の手配量及び部品Fの10月4日の手配量につ
いて、それぞれ20個から10個、10個から0個に変
更しなければならないことが分かる。同様にして、部品
Bの10月5日の生産計画及び部品Cの10月5日の生
産計画も、それぞれ10個から0個に変更しなければな
らないことが分かる。
Further, the order for arranging the part G is
By changing from 0 to 20 parts 1
It can be seen that the order quantity on October 4 and the order quantity on October 4 for part F must be changed from 20 to 10, and from 10 to 0, respectively. Similarly, it can be seen that the production plan for the part B on October 5 and the production plan for the part C on October 5 also need to be changed from ten to zero.

【0038】このようにして得られた図8に示す結果に
基づいて、オペレータは入力装置1を操作して、生産計
画変更部24に生産計画記憶部33に記憶されている生
産計画を変更させる。そして、生産計画が変更された後
に、再度所要量計算部21による実行させる。以上の処
理を繰返すことによって、最適な生産計画、部品の手配
量を決定していく。
On the basis of the results shown in FIG. 8 obtained in this way, the operator operates the input device 1 to cause the production plan change section 24 to change the production plan stored in the production plan storage section 33. . Then, after the production plan is changed, the required amount calculation unit 21 executes the production plan again. By repeating the above processing, the optimal production plan and the quantity of parts to be arranged are determined.

【0039】以上説明したように、この実施の形態の生
産管理システムでは、オペレータは、部品の手配量の変
更による製品(或いは部品)の生産計画への影響を知る
ことができる。この結果に基づいて、製品の生産に必要
となる部品の手配と製品の生産計画との調整を図ること
ができ、効率的な生産管理を行うことができる。
As described above, in the production management system according to the present embodiment, the operator can know the influence on the production plan of the product (or part) due to the change of the arranged quantity of the part. Based on this result, it is possible to arrange the parts necessary for the production of the product and adjust the production plan of the product, and it is possible to perform efficient production management.

【0040】上記の実施の形態では、生産計画変更部2
4は、オペレータによる入力装置1の操作に従って、生
産計画記憶部33に記憶されている生産計画を変更して
いた。しかしながら、生産計画変更部24は、変更の必
要な生産計画検索部22で検索された変更の必要な生産
計画の部分を自動的に変更して、生産計画記憶部33に
上書きするようにしてもよい。
In the above embodiment, the production plan changing unit 2
No. 4 changes the production plan stored in the production plan storage unit 33 according to the operation of the input device 1 by the operator. However, the production plan changing unit 24 may automatically change the part of the production plan that needs to be changed, which is searched by the production plan searching unit 22 that needs to change, and overwrite the part in the production plan storage unit 33. Good.

【0041】上記の実施の形態では、入力装置1からの
入力に従って手配指示変更部23で作成された変更され
た手配量は、手配指示変更情報記憶部36に記憶されて
いた。これに対して、手配指示変更情報記憶部36を設
けずに、手配指示変更部36で作成された変更された手
配量を手配指示記憶部34に上書きしてもよい。
In the above embodiment, the changed order amount created by the order instruction change unit 23 in accordance with the input from the input device 1 is stored in the order instruction change information storage unit 36. On the other hand, the arrangement amount changed by the arrangement instruction change unit 36 may be overwritten on the arrangement instruction storage unit 34 without providing the arrangement instruction change information storage unit 36.

【0042】上記の実施の形態では、本発明の生産管理
システムを単一の情報処理装置で実現した場合について
説明した。しかしながら、本発明の生産管理システム
は、クライアントサーバシステムによって実現すること
も可能である。この場合、サーバ側のコンピュータは、
クライアント側の端末から通信ネットワークを介して入
力された手配指示や生産計画の変更を処理し、その処理
結果を通信ネットワークを介してクライアント側の端末
に返せばよい。すなわち、サーバ側のコンピュータが、
図1のデータ処理装置2と記憶装置3の機能を持つこと
となる。
In the above embodiment, the case where the production management system of the present invention is realized by a single information processing device has been described. However, the production management system of the present invention can also be realized by a client server system. In this case, the server computer
Arrangement instructions and changes in the production plan input from the client terminal via the communication network may be processed, and the processing results may be returned to the client terminal via the communication network. That is, the computer on the server side
It has the functions of the data processing device 2 and the storage device 3 of FIG.

【0043】上記の実施の形態では、データ処理2にお
いて、CPUが所定の処理プログラムを実行することに
よって、所要量計算部21、変更の必要な生産計画検索
部22、手配指示変更部23及び生産計画変更部24の
各機能を実現していた。これらの機能を実現するための
処理プログラムは、CD−ROMやフロッピーディスク
などのコンピュータ読み取り可能な記録媒体に格納して
配布してもよい。この場合、当該記録媒体に格納されて
いる処理プログラムには、生産基準情報記憶部31、在
庫情報記憶部32、生産計画記憶部33、手配指示記憶
部34、生産計画・手配指示関連情報記憶部35及び手
配指示変更情報記憶部36のための記憶領域を記憶装置
内に確保する機能を含めればよい。
In the above-described embodiment, in data processing 2, the CPU executes a predetermined processing program, so that the required amount calculating unit 21, the production plan searching unit 22 that needs to be changed, the ordering instruction changing unit 23, and the production Each function of the plan changing unit 24 has been realized. A processing program for realizing these functions may be stored in a computer-readable recording medium such as a CD-ROM or a floppy disk and distributed. In this case, the processing programs stored in the recording medium include a production reference information storage unit 31, an inventory information storage unit 32, a production plan storage unit 33, an arrangement instruction storage unit 34, and a production plan / arrangement instruction related information storage unit. What is necessary is just to include the function which secures the storage area for 35 and the arrangement instruction change information storage part 36 in a storage device.

【0044】[0044]

【発明の効果】以上説明したように、本発明によれば、
製品の生産に必要となる部品の手配と製品の生産計画と
の調整を図ることができ、効率的な生産管理を行うこと
ができる。
As described above, according to the present invention,
Arrangement of parts necessary for product production and production plan of the product can be adjusted, and efficient production management can be performed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態にかかる生産管理システム
の構成を示す機能ブロック図である。
FIG. 1 is a functional block diagram showing a configuration of a production management system according to an embodiment of the present invention.

【図2】図1の生産基準情報記憶部の記憶内容の例を模
式的に示す図である。
FIG. 2 is a diagram schematically illustrating an example of contents stored in a production reference information storage unit in FIG. 1;

【図3】図1の在庫情報記憶部の記憶内容の例を示す図
である。
FIG. 3 is a diagram illustrating an example of storage contents of a stock information storage unit in FIG. 1;

【図4】図1の生産計画記憶部の記憶内容の例を示す図
である。
FIG. 4 is a diagram showing an example of contents stored in a production plan storage unit of FIG. 1;

【図5】図1の手配指示記憶部の記憶内容の例を示す図
である。
FIG. 5 is a diagram showing an example of contents stored in an arrangement instruction storage unit of FIG. 1;

【図6】図1の生産計画・手配指示関連情報記憶部の記
憶内容の例を示す図である。
FIG. 6 is a diagram showing an example of storage contents of a production plan / arrangement instruction related information storage unit of FIG. 1;

【図7】図1の手配指示変更情報記憶部の記憶内容の例
を示す図である。
FIG. 7 is a diagram showing an example of storage contents of an arrangement instruction change information storage unit of FIG. 1;

【図8】図1の出力装置から出力される調整の必要な生
産計画の例を示す図である。
FIG. 8 is a diagram showing an example of a production plan that needs adjustment and is output from the output device of FIG. 1;

【符号の説明】[Explanation of symbols]

1 入力装置 2 データ処理装置 3 記憶装置 4 出力装置 21 所要量計算部 22 変更の必要な生産計画検索部 23 手配指示変更部 24 生産計画変更部 31 生産基準情報記憶部 32 在庫情報記憶部 33 生産計画記憶部 34 手配指示記憶部 35 生産計画・手配指示関連情報記憶部 36 手配指示変更情報記憶部 REFERENCE SIGNS LIST 1 input device 2 data processing device 3 storage device 4 output device 21 required amount calculation unit 22 production plan search unit requiring change 23 arrangement instruction change unit 24 production plan change unit 31 production reference information storage unit 32 inventory information storage unit 33 production Plan storage unit 34 Arrangement instruction storage unit 35 Production plan / arrangement instruction related information storage unit 36 Arrangement instruction change information storage unit

【手続補正書】[Procedure amendment]

【提出日】平成11年2月3日[Submission date] February 3, 1999

【手続補正1】[Procedure amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】請求項1[Correction target item name] Claim 1

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【手続補正2】[Procedure amendment 2]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】請求項5[Correction target item name] Claim 5

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【手続補正3】[Procedure amendment 3]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】請求項6[Correction target item name] Claim 6

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【手続補正4】[Procedure amendment 4]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0004[Correction target item name] 0004

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0004】本発明は、上記の従来技術の問題点を解消
するためになされたものであり、製品の生産に必要とな
る部品の手配と製品の生産計画との調整を図ることを可
能とする生産管理システム及び方法、並びにこのような
生産管理の機能を実現するためのプログラムを記憶した
コンピュータ読み取り可能な記録媒体を提供することを
目的とする。
The present invention has been made to solve the above-mentioned problems of the prior art, and makes it possible to arrange parts necessary for the production of a product and to adjust a production plan of the product. production control system and method, and an object of the invention to provide a computer readable recording medium storing a program for realizing the functions of such production management.

【手続補正5】[Procedure amendment 5]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0005[Correction target item name] 0005

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0005】[0005]

【課題を解決するための手段】上記目的を達成するた
め、本発明の第1の観点にかかる生産管理システムは、
製品を生産するために必要となる部品に関する情報を記
憶する生産基準情報記憶手段と、前記生産基準情報記憶
手段に記憶されている前記部品のそれぞれについての在
庫情報を記憶する在庫情報記憶手段と、前記部品から前
記製品を生産するための生産計画を記憶する生産計画記
憶手段と、前記生産基準情報記憶手段に記憶されている
前記部品に関する情報、前記在庫情報記憶手段に記憶さ
れている在庫情報及び前記生産計画記憶手段に記憶され
ている生産計画に基づいて、前記製品を生産するために
必要となる部品の手配に関する情報と該情報のそれぞれ
に対応する生産計画の部分とを、前記部品の手配日及び
必要日毎に算出する手配情報算出手段と、前記手配情報
算出手段によって算出された前記部品の手配に関する情
報と該情報のそれぞれと対応する生産計画の部分を、前
記部品の手配日及び必要日毎に別々のレコードとして
連付けて記憶する生産計画・手配情報記憶手段と、前記
手配情報算出手段によって算出された前記部品の手配に
関する情報を変更するための情報を入力する手配情報変
更手段と、前記生産計画・手配情報記憶手段に、手配日
及び必要日毎に別々のレコードとして前記部品の手配に
関する情報とそれぞれ関連付けられて記憶されている生
産計画の部分のうちの変更を要する部分を、前記手配情
報変更手段から入力された部品の手配に関する情報を変
更するための情報に従って抽出する要変更生産計画抽出
手段と、前記生産計画記憶手段に記憶されている前記生
産計画を変更する生産計画変更手段と、を備えることを
特徴とする。
In order to achieve the above object, a production management system according to a first aspect of the present invention comprises:
A production reference information storage means for storing information relating to parts required for producing a product, and a stock information storage means for storing inventory information for each of the parts stored in the production reference information storage means, A production plan storage means for storing a production plan for producing the product from the parts, information on the parts stored in the production reference information storage means, inventory information stored in the inventory information storage means, On the basis of the production plan stored in the production plan storage means, information on the arrangement of parts necessary for producing the product and a part of the production plan corresponding to each of the information are arranged. Day and
Order information calculating means for calculating each required date ; information on the arrangement of the parts calculated by the order information calculating means; and a part of the production plan corresponding to each of the information ,
A production plan / arrangement information storage unit that stores the parts as a separate record for each of the arrangement date and the required date, and changes information relating to the arrangement of the parts calculated by the arrangement information calculation unit. Order information changing means for inputting information for the order and the production plan / arrangement information storing means ,
And a part of the part of the production plan, which is stored as a separate record for each necessary date in association with the information on the part arrangement, which needs to be changed, and the part arrangement information input from the arrangement information changing means. And a production plan changing means for changing the production plan stored in the production plan storage means.

【手続補正6】[Procedure amendment 6]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0006[Correction target item name] 0006

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0006】上記生産管理システムでは、前記要変更抽
出手段が抽出した生産計画のうちの変更を要する部分を
生産計画変更手段によって変更することができる。ここ
で、要変更抽出手段による変更を要する生産計画の部分
の抽出には、前記手配情報変更手段による前記部品の手
配に関する情報が反映される。さらに、手配情報算出手
段は、生産計画変更手段によって変更された生産計画に
基づいて、新たな手配情報の算出を行うことができる。
従って、上記生産管理システムでは、前記手配情報変更
手段による部品の手配に関する情報の変更及び前記生産
計画変更手段による生産計画の変更を繰り返すことによ
って、製品の生産に必要となる部品の手配に関する情報
と製品の生産計画との調整を図ることができ、効率的な
生産管理を行うことができる。
In the above-mentioned production management system, a part of the production plan extracted by the change-requiring extracting means, which needs to be changed, can be changed by the production-plan changing means. Here, the information on the arrangement of the parts by the arrangement information changing means is reflected in the extraction of the part of the production plan requiring the change by the change required extracting means. Further, the arrangement information calculating means can calculate new arrangement information based on the production plan changed by the production plan changing means.
Therefore, in the production management system, by repeating the change of the information on the part arrangement by the arrangement information changing means and the change of the production plan by the production plan changing means, the information on the part arrangement necessary for the production of the product is obtained. Coordination with the product production plan can be achieved, and efficient production management can be performed.

【手続補正7】[Procedure amendment 7]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0010[Correction target item name] 0010

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0010】上記目的を達成するため、本発明の第2の
観点にかかる生産管理方法は、記憶装置に記憶されてい
る製品を生産するために必要となる部品に関する情報
と、前記部品のそれぞれについての在庫情報と、前記部
品から前記製品を生産するための生産計画とに基づい
て、前記製品を生産するために必要となる部品の手配に
関する情報を算出し、該算出された部品の手配に関する
情報に基づいて、前記製品の生産管理を行う生産管理方
法であって、前記算出された部品の手配に関する情報と
前記生産計画の部分との関連付けを、前記部品の手配日
及び必要日毎に算出する関連算出ステップと、前記算出
された部品の手配に関する情報を変更するための情報を
入力する手配情報変更ステップと、前記関連算出ステッ
プで前記部品の手配日及び必要日毎に部品の手配に関す
る情報に関連付けて算出された前記生産計画の部分のう
ち変更を要する部分を、前記手配情報変更ステップで入
力された部品の手配に関する情報を変更するための情報
に従って抽出する要変更生産計画抽出ステップと、前記
記憶装置に記憶されている生産計画のうちの前記要変更
生産計画抽出ステップで抽出された部分を変更する生産
計画変更ステップと、を含むことを特徴とする。
In order to achieve the above object, a production management method according to a second aspect of the present invention provides information on parts necessary for producing a product stored in a storage device and information on each of the parts. Based on the stock information and the production plan for producing the product from the parts, information on the arrangement of parts necessary for producing the product is calculated, and the information on the arrangement of the calculated parts is calculated. A production management method for performing production management of the product, based on the relationship between the calculated information on the arrangement of parts and the part of the production plan , the arrangement date of the parts
And a related calculation step of calculating for each required date, an arrangement information changing step of inputting information for changing the information on the calculated part arrangement, and a part for each of the part arrangement date and the required date in the related calculation step. A change production plan which extracts a part of the production plan calculated in association with the information relating to the arrangement, which needs to be changed, in accordance with the information for changing the information relating to the part arrangement input in the arrangement information change step An extraction step, and a production plan change step of changing a portion of the production plan stored in the storage device, which is extracted in the required production plan extraction step, is included.

【手続補正8】[Procedure amendment 8]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0011[Correction target item name] 0011

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0011】上記目的を達成するため、本発明の第3の
観点にかかるコンピュータ読み取り可能な記録媒体は、
製品を生産するために必要となる部品に関する情報を第
1の記憶装置に記憶させる生産基準情報記憶機能と、前
記部品のそれぞれについての在庫情報を第2の記憶装置
に記憶させる在庫情報記憶機能と、前記部品から前記製
品を生産するための生産計画を第3の記憶装置に記憶さ
せる生産計画記憶機能と、前記生産基準情報記憶機能に
よって前記第1の記憶装置に記憶された前記部品に関す
る情報、前記生産基準情報記憶機能によって前記第2の
記憶装置に記憶された前記在庫情報及び前記生産計画記
憶機能によって前記第3の記憶装置に記憶された生産計
画に基づいて、前記製品を生産するために必要となる部
品の手配に関する情報と該情報のそれぞれに対応する生
産計画の部分とを、前記部品の手配日及び必要日毎に
出する手配情報算出機能と、前記手配情報算出機能によ
って算出された前記部品の手配に関する情報と該情報の
それぞれと対応する生産計画の部分を、前記部品の手配
日及び必要日毎に別々のレコードとして関連付けて第4
の記憶装置に記憶させる生産計画・手配情報記憶機能
と、前記生産計画・手配情報記憶機能によって前記第4
の記憶装置に、手配日及び必要日毎に別々のレコードと
して前記部品の手配に関する情報とそれぞれ関連付けら
れて記憶された生産計画の部分のうちの変更を要する部
分を、前記手配情報変更機能によって入力された部品の
手配に関する情報を変更するための情報に従って抽出す
る要変更生産計画抽出機能と、前記要変更生産計画抽出
機能によって抽出された変更を要する部分に対応する前
記第3の記憶装置内の生産計画を変更する生産計画変更
機能と、前記手配情報算出機能によって算出された前記
製品を生産するために必要となる部品の手配に関する情
報を外部に出力する出力機能と、を実行するためのプロ
グラムを記憶することを特徴とする。
In order to achieve the above object, a computer-readable recording medium according to a third aspect of the present invention comprises:
A production reference information storage function for storing information relating to parts required for producing a product in the first storage device, and a stock information storage function for storing inventory information for each of the components in the second storage device. A production plan storage function for storing a production plan for producing the product from the component in a third storage device, and information about the component stored in the first storage device by the production reference information storage function; To produce the product based on the inventory information stored in the second storage device by the production reference information storage function and the production plan stored in the third storage device by the production plan storage function arrange information for a portion of the production plan, to calculate out <br/> every arrange date and need date of the component corresponding to the respective information and the information about the components of the arrangements required A calculating function, a respectively corresponding portion of the production plan of the part of the information and the information about the arrangement that has been calculated by the order information calculation function, arrange the parts
4th by associating as a separate record for each day and required date
The storage device for storing the production plan / arrangement information, and the production plan / arrangement information storage function.
A separate record for each arrangement date and required date
According to the information for changing the information portion requiring a change to a part of the arrangements that have been entered by the arrangement information changing function of the portion of each information about arrangements associated with the stored production plan the component and A change-required production plan extraction function to be extracted; a production plan change function for changing a production plan in the third storage device corresponding to a portion requiring change extracted by the change-required production plan extraction function; A program for executing an output function of outputting information on arrangement of parts necessary for producing the product calculated by the calculation function to the outside, and a program for executing the program are stored.

【手続補正9】[Procedure amendment 9]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0020[Correction target item name] 0020

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0020】変更の必要な生産計画検索部22は、生産
計画記憶部33、手配指示記憶部34、生産計画・手配
指示関連情報記憶部35及び後述する手配指示変更情報
記憶部36の記憶内容に基づいて、変更の必要がある生
産計画、例えば、部品の手配が間に合わない生産計画を
検索する。変更の必要がある生産計画が検索された場合
には、変更の必要な生産計画検索部22は、検索された
生産計画と生産計画を変更すべきことを警告するアラー
ムを出力装置4に出力する。
The production plan search section 22 that needs to be changed stores the contents of the production plan storage section 33, the arrangement instruction storage section 34, the production plan / arrangement instruction related information storage section 35, and the arrangement instruction change information storage section 36 described later. Based on the search, a production plan that needs to be changed, for example, a production plan in which parts can not be arranged in time is searched. When a production plan that needs to be changed is searched, the production plan searching unit 22 that needs to change outputs the searched production plan and an alarm that warns that the production plan should be changed to the output device 4. .

【手続補正10】[Procedure amendment 10]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0032[Correction target item name] 0032

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0032】図6に示す生産計画・手配指示関連情報記
憶部35の記憶内容について説明する。例えば、部品D
について、10月3日に手配した20個のうち10個が
10月3日に必要となり、残りの10個が10月4日に
必要となる。このように生産計画に従うと、手配日が同
じでも必要日が異なる場合には、手配される部品は、図
6に示すようにそれぞれ別々のレコードとして生産計画
・手配指示関連情報記憶部35に記憶される。
The storage contents of the production plan / arrangement instruction related information storage section 35 shown in FIG. 6 will be described. For example, part D
Regarding, 10 out of the 20 pieces arranged on October 3 are needed on October 3, and the remaining 10 pieces are needed on October 4. According to the production plan in this way, if the necessary dates are different even if the arrangement date is the same, the parts to be arranged are stored as separate records in the production plan as shown in FIG.
-Stored in the ordering instruction related information storage unit 35 .

【手続補正11】[Procedure amendment 11]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0034[Correction target item name] 0034

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0034】このアラームに応答して、オペレータは入
力装置1を操作して、部品の手配量変更を入力する。
この入力に従って、手配指示変更部23は、図7に示す
ような部品の手配量を変更するための情報を作成し、手
配指示変更情報記憶部36に記憶させる。
In response to this alarm, the operator operates the input device 1 to input a change in the arranged quantity of parts.
In accordance with this input, the arrangement instruction change unit 23 creates information for changing the arrangement amount of the parts as shown in FIG. 7 and stores the information in the arrangement instruction change information storage unit 36.

【手続補正12】[Procedure amendment 12]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0036[Correction target item name] 0036

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0036】変更の必要な生産計画検索部22による図
8に示す結果を求める手順について、説明する。まず、
手配指示変更情報記憶部36の記憶内容(図7)から、
10月2日の部品Gの手配量が20個から0個に変更さ
れた情報を取得する。次に、生産計画・手配指示関連情
報記憶部35の記憶内容(図6)を参照すると、部品G
の10月2日の手配量を20個から0個に変更したこと
で、部品Dの10月3日における手配量も20個から1
0個になり、影響が生じることが分かる。同様に、部品
Aの10月3日、10月4日における生産計画も10個
から0個に変更しなければならないことが分かる。
The procedure for obtaining the results shown in FIG. 8 by the production plan search unit 22 that needs to be changed will be described. First,
From the contents stored in the arrangement instruction change information storage unit 36 (FIG. 7),
Information that the order quantity of the part G on October 2 has been changed from 20 pieces to 0 pieces is obtained. Next, referring to the storage contents (FIG. 6) of the production plan / arrangement instruction related information storage unit 35 ,
Has been changed from 20 pieces to 0 pieces on October 2, so that the order quantity of parts D on October 3 has also changed from 20 pieces to 1 piece.
It turns out to be 0, and it turns out that an influence arises. Similarly, it can be seen that the production plan of the parts A on October 3 and October 4 must be changed from 10 to 0.

【手続補正13】[Procedure amendment 13]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0038[Correction target item name] 0038

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【0038】このようにして得られた図8に示す結果に
基づいて、オペレータは入力装置1を操作して、生産計
画変更部24に生産計画記憶部33に記憶されている生
産計画を変更させる。そして、生産計画が変更された後
に、再度所要量計算部21による処理を実行させる。以
上の処理を繰返すことによって、最適な生産計画、部品
の手配量を決定していく。
On the basis of the results shown in FIG. 8 obtained in this way, the operator operates the input device 1 to cause the production plan change section 24 to change the production plan stored in the production plan storage section 33. . Then, after the production plan is changed, the processing by the required amount calculation unit 21 is executed again. By repeating the above processing, the optimal production plan and the quantity of parts to be arranged are determined.

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】製品を生産するために必要となる部品に関
する情報を記憶する生産基準情報記憶手段と、 前記生産基準情報記憶手段に記憶されている前記部品の
それぞれについての在庫情報を記憶する在庫情報記憶手
段と、 前記部品から前記製品を生産するための生産計画を記憶
する生産計画記憶手段と、 前記生産基準情報記憶手段に記憶されている前記部品に
関する情報、前記在庫情報記憶手段に記憶されている在
庫情報及び前記生産計画記憶手段に記憶されている生産
計画に基づいて、前記製品を生産するために必要となる
部品の手配に関する情報と該情報のそれぞれに対応する
生産計画の部分とを算出する手配情報算出手段と、 前記手配情報算出手段によって算出された前記部品の手
配に関する情報と該情報のそれぞれと対応する生産計画
の部分を関連付けて記憶する生産計画・手配情報記憶手
段と、 前記手配情報算出手段によって算出された前記部品の手
配に関する情報を変更するための情報を入力する手配情
報変更手段と、 前記生産計画・手配情報記憶手段に前記部品の手配に関
する情報とそれぞれ関連付けられて記憶されている生産
計画の部分のうちの変更を要する部分を、前記手配情報
変更手段から入力された部品の手配に関する情報を変更
するための情報に従って抽出する要変更生産計画抽出手
段と、 前記生産計画記憶手段に記憶されている前記生産計画を
変更する生産計画変更手段と、を備えることを特徴とす
る生産管理システム。
1. A production reference information storage means for storing information relating to parts required for producing a product, and an inventory for storing inventory information for each of the parts stored in the production reference information storage means. Information storage means, a production plan storage means for storing a production plan for producing the product from the parts, information on the parts stored in the production reference information storage means, stored in the inventory information storage means Based on the stock information and the production plan stored in the production plan storage means, information on the arrangement of parts necessary for producing the product and parts of the production plan corresponding to each of the information are obtained. Means for calculating arrangement information to be calculated; information relating to arrangement of the parts calculated by the means for calculating arrangement information; and production corresponding to each of the information. A production plan / arrangement information storage unit that associates and stores a part of the plan; an arrangement information change unit that inputs information for changing information on the arrangement of the parts calculated by the arrangement information calculation unit; Change the part of the part of the production plan stored in the arrangement information storage unit which is associated with the information on the arrangement of the part, and change the part arrangement information input from the arrangement information change unit; A production management system, comprising: a production plan change extracting means for extracting the production plan according to information for performing the production planning; and a production plan changing means for modifying the production plan stored in the production plan storage means.
【請求項2】前記要変更生産計画抽出手段によって抽出
された変更を要する生産計画の部分に関する情報を出力
する第1の出力手段を備えることを特徴とする請求項1
に記載の生産管理システム。
2. A system according to claim 1, further comprising first output means for outputting information relating to a part of the production plan requiring change extracted by said change-necessary production plan extracting means.
The production management system described in 1.
【請求項3】前記生産計画変更手段は、前記要変更生産
計画抽出手段によって抽出された変更を要する部分に対
応する前記生産計画記憶手段内の生産計画を変更する手
段を備えることを特徴とする請求項1または2に記載の
生産管理システム。
3. The production plan change means includes means for changing a production plan in the production plan storage means corresponding to a portion requiring change extracted by the change required production plan extraction means. The production management system according to claim 1.
【請求項4】前記手配情報算出手段が算出した前記製品
を生産するために必要となる部品の手配に関する情報を
出力する第2の出力手段を備えることを特徴とする請求
項1乃至3のいずれか1項に記載の生産管理システム。
4. The apparatus according to claim 1, further comprising second output means for outputting information relating to arrangement of parts necessary for producing said product, calculated by said arrangement information calculation means. 2. The production management system according to claim 1.
【請求項5】記憶装置に記憶されている製品を生産する
ために必要となる部品に関する情報と、前記部品のそれ
ぞれについての在庫情報と、前記部品から前記製品を生
産するための生産計画とに基づいて、前記製品を生産す
るために必要となる部品の手配に関する情報を算出し、
該算出された部品の手配に関する情報に基づいて、前記
製品の生産管理を行う生産管理方法であって、 前記算出された部品の手配に関する情報と前記生産管理
の部分との関連付けを算出する関連算出ステップと、 前記算出された部品の手配に関する情報を変更するため
の情報を入力する手配情報変更ステップと、 前記関連算出ステップで部品の手配に関する情報に関連
付けて算出された前記生産管理の部分のうち変更を要す
る部分を、前記手配情報変更ステップで入力された部品
の手配に関する情報を変更するための情報に従って抽出
する要変更生産計画抽出ステップと、 前記記憶装置に記憶されている生産計画のうちの前記要
変更生産計画抽出ステップで抽出された部分を変更する
生産計画変更ステップと、を含むことを特徴とする生産
管理方法。
5. Information on parts necessary for producing a product stored in a storage device, inventory information on each of said parts, and a production plan for producing said product from said parts. Based on, calculate information on the arrangement of parts required to produce the product,
A production management method for performing production management of the product based on the calculated information on parts arrangement, wherein a relation calculation for calculating an association between the calculated information on parts arrangement and the production management part. An order information change step of inputting information for changing the calculated information on the part arrangement; and a part of the production management calculated in association with the information on the part arrangement in the related calculation step. A changed production plan extraction step of extracting a part that needs to be changed in accordance with information for changing the information on the arrangement of parts input in the arrangement information change step; and a production plan stored in the storage device. A production plan change step of changing a part extracted in the change required production plan extraction step. Management method.
【請求項6】製品を生産するために必要となる部品に関
する情報を第1の記憶装置に記憶させる生産基準情報記
憶機能と、 前記部品のそれぞれについての在庫情報を第2の記憶装
置に記憶させる在庫情報記憶機能と、 前記部品から前記製品を生産するための生産計画を第3
の記憶装置に記憶させる生産計画記憶機能と、 前記生産基準情報記憶機能によって前記第1の記憶装置
に記憶された前記部品に関する情報、前記生産基準情報
記憶機能によって前記第2の記憶装置に記憶された前記
在庫情報及び前記生産計画記憶機能によって前記第3の
記憶装置に記憶された生産計画に基づいて、前記製品を
生産するために必要となる部品の手配に関する情報と該
情報のそれぞれに対応する生産計画の部分とを算出する
手配情報算出機能と、 前記手配情報算出機能によって算出された前記部品の手
配に関する情報と該情報のそれぞれと対応する生産計画
の部分を関連付けて第4の記憶装置に記憶させる記憶す
る生産計画・手配情報記憶機能と、 前記生産計画・手配情報記憶機能によって前記第4の記
憶装置に前記部品の手配に関する情報とそれぞれ関連付
けられて記憶された生産計画の部分のうちの変更を要す
る部分を、前記手配情報変更機能によって入力された部
品の手配に関する情報を変更するための情報に従って抽
出する要変更生産計画抽出機能と、 前記要変更生産計画抽出機能によって抽出された変更を
要する部分に対応する前記第3の記憶装置内の生産計画
を変更する生産計画変更機能と、前記手配情報算出機能
によって算出された前記製品を生産するために必要とな
る部品の手配に関する情報を外部に出力する出力機能
と、を実行するためのプログラムを記憶することを特徴
とするコンピュータ読み取り可能な記録媒体。
6. A production reference information storage function for storing information relating to parts required for producing a product in a first storage device, and storing inventory information for each of said parts in a second storage device. Inventory information storage function, and a production plan for producing the product from the parts
A production plan storage function to be stored in the storage device; information about the parts stored in the first storage device by the production reference information storage function; and information stored in the second storage device by the production reference information storage function. Based on the stock information and the production plan stored in the third storage device by the production plan storage function, the information corresponds to the information on the arrangement of parts necessary for producing the product and the information, respectively. An arrangement information calculation function for calculating a part of the production plan; information relating to the arrangement of the parts calculated by the arrangement information calculation function; and a part of the production plan corresponding to each of the pieces of information are stored in the fourth storage device. A production plan / arrangement information storage function to be stored; A production plan that needs to be changed among the parts of the production plan stored in association with the information relating to the parts according to the information for changing the information relating to the arrangement of parts input by the arrangement information change function. An extraction function, a production plan change function for changing a production plan in the third storage device corresponding to a portion requiring change extracted by the change required production plan extraction function, and a production plan calculation function. A computer-readable recording medium storing a program for executing an output function of outputting information relating to arrangement of parts necessary for producing the product to the outside, and a program for executing the function.
JP965998A 1998-01-21 1998-01-21 Production control system and method, and recording medium Pending JPH11207574A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP965998A JPH11207574A (en) 1998-01-21 1998-01-21 Production control system and method, and recording medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP965998A JPH11207574A (en) 1998-01-21 1998-01-21 Production control system and method, and recording medium

Publications (1)

Publication Number Publication Date
JPH11207574A true JPH11207574A (en) 1999-08-03

Family

ID=11726348

Family Applications (1)

Application Number Title Priority Date Filing Date
JP965998A Pending JPH11207574A (en) 1998-01-21 1998-01-21 Production control system and method, and recording medium

Country Status (1)

Country Link
JP (1) JPH11207574A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003105036A1 (en) * 2002-06-05 2003-12-18 本田技研工業株式会社 Order management system
JP2017182797A (en) * 2016-03-29 2017-10-05 株式会社オービック Requirements calculation device, requirements calculation method, and requirements calculation program

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003105036A1 (en) * 2002-06-05 2003-12-18 本田技研工業株式会社 Order management system
US7574384B2 (en) 2002-06-05 2009-08-11 Honda Giken Kogyo Kabushiki Kaisha Order management system
JP2017182797A (en) * 2016-03-29 2017-10-05 株式会社オービック Requirements calculation device, requirements calculation method, and requirements calculation program

Similar Documents

Publication Publication Date Title
US6434580B1 (en) System, method, and recording medium for drafting and preparing patent specifications
US9600792B2 (en) Method and apparatus for generating an engineering workflow
JP2001219341A (en) Joint support system of working sheet metal
US20060101052A1 (en) Method and system for sequencing and scheduling
US20050246244A1 (en) Parts management information system and parts management method, and storage medium
CN111382314A (en) Method for realizing flexible configuration of heterogeneous system service integration
US6345270B1 (en) Data management system
JP5160773B2 (en) Information processing apparatus and method
JP4101045B2 (en) Support method, support device, and computer program
JP2001318953A (en) Cost data management system, cost data management method and recording medium therefor
JPH11207574A (en) Production control system and method, and recording medium
Schuh et al. Operational implementation of digital production twins in single and small batch production
JP2001290525A (en) Recording medium with recorded lot size calculating program, lot size calculating method, and manufacturing method using lot size calculating method
JP2008009966A (en) Device and method for setting business process
JPH07271864A (en) Production control method
JPH08329142A (en) Insurance product management system
JPH10236612A (en) Stock control device and production control device
JP7621701B1 (en) Information processing device, information processing method, and program
JP2015225511A (en) Required amount calculation device, required amount calculation method, and program
JP2000322119A (en) Substitutive lot determination system
JPH08202541A (en) System designing method and system designing support device
JP3123400B2 (en) Automatic asset correction history generation system
TWI745620B (en) Method for dynamically generating customized picture, system thereof, and computer-readable storage device
JPH11328280A (en) Workflow system that defines and executes process rules
JP2002132570A (en) System and method for controlling website history, system and method for analyzing access pattern, and recording medium

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19990817