JPH11172710A - Method for constructing underground part of steel encased reinforced concrete building - Google Patents
Method for constructing underground part of steel encased reinforced concrete buildingInfo
- Publication number
- JPH11172710A JPH11172710A JP9363311A JP36331197A JPH11172710A JP H11172710 A JPH11172710 A JP H11172710A JP 9363311 A JP9363311 A JP 9363311A JP 36331197 A JP36331197 A JP 36331197A JP H11172710 A JPH11172710 A JP H11172710A
- Authority
- JP
- Japan
- Prior art keywords
- steel
- outer peripheral
- foundation
- building
- reinforced concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、鉄骨鉄筋コンクリ
ート造の建築物の地下部分を施工する方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground part of a steel reinforced concrete building.
【0002】[0002]
【従来の技術】鉄骨鉄筋コンクリート造の建築物の建築
施工において、その地階部分を施工する場合は、例えば
図5に示すように、根切掘削による周囲の地盤100の
崩壊を防止するための山留架構が施される。2. Description of the Related Art In the construction of a steel-framed reinforced concrete building, when the basement is to be constructed, for example, as shown in FIG. A frame is applied.
【0003】すなわち従来技術においては、地盤の根切
掘削の際に、その外周(建築物の地下部分の施工外周)
に沿ってシートパイル等からなる山留壁101を鉛直に
打ち込んでその内側の地盤を所要深さだけ掘削してか
ら、前記山留壁101の内側面に腹起し102を水平に
取り付け、この腹起し102に切梁103をほぼ垂直に
かつ水平に架設してその長手方向中間を棚杭(図示省
略)に取り付けて支持する。前記腹起し102、切梁1
03及び棚杭はそれぞれ例えばH型鋼等の鉄骨材からな
る。[0003] In other words, in the prior art, when excavating the ground, the outer periphery (construction outer periphery of the underground portion of the building).
A mountain retaining wall 101 made of a sheet pile or the like is driven vertically along the ground, and the ground inside the mountain is excavated to a required depth. A cutting beam 103 is erected substantially vertically and horizontally on the belly 102, and a longitudinally intermediate portion thereof is attached to and supported by a shelf pile (not shown). The prow 102, the cutting beam 1
03 and the shelf pile are each made of a steel frame material such as an H-beam.
【0004】山留架構における切梁103は、建築物の
地下部分における基礎104及び外周立上り壁105の
コンクリートを打設した後に解体される。このため、山
留壁101、腹起し102及び切梁103等による山留
架構を行った後、前記基礎104及び外周立上り壁10
5を施工する際には、前記建築物の鉄骨建方のうち、ま
ず前記外周立上り壁105における外周鉄骨柱の建方作
業を先行して行うが、この鉄骨柱の取合いを確保するた
めに、腹起し102を水平方向に連続したものとせず、
各鉄骨柱の建て込み位置で寸断された構造としている。[0004] The cutting beams 103 in the mountain retaining structure are dismantled after the concrete of the foundation 104 and the outer peripheral rising wall 105 in the underground part of the building is cast. For this reason, after the pier is constructed by the pier 101, the bulge 102, the cutting beam 103, and the like, the base 104 and the outer rising wall 10 are formed.
When constructing 5, among the steel frame construction methods of the building, first, the construction work of the outer peripheral steel columns on the outer peripheral rising wall 105 is performed in advance, but in order to secure the connection of the steel columns, The hunger 102 is not assumed to be continuous in the horizontal direction,
The structure is cut off at the position where each steel column is erected.
【0005】[0005]
【発明が解決しようとする課題】上記従来工法において
は次のような問題が指摘される。 (1) 建築物の鉄骨建方のうち、外周立上り壁105にお
ける外周鉄骨柱の建方のみを先行して行うため、この外
周鉄骨柱の建方の施工精度の確保が難しく、しかもこの
外周鉄骨柱の建方が切梁103が架設された空間での作
業となるため、作業性が悪く、危険性も伴う。 (2) 建築物の鉄骨建方が、外周立上り壁105における
外周鉄骨柱の建方と、基礎104及び外周立上り壁10
5の施工後の建物内部鉄骨の建方とに分けて行われるた
め、施工手順が煩雑である。 (3) 腹起し102が水平方向に連続したものではなく、
外周鉄骨柱の建て込み位置で寸断された構造であるた
め、山留架構の剛性が低下し、山留壁101の外側地盤
100の変位量が大きくなってしまう。 (4) 腹起し102を外周鉄骨柱の建て込み位置で寸断さ
れた構造とするために、この腹起し102として多数の
短い鉄骨を用いなければならず、しかも前記剛性低下を
防止するための補強を行わなければならないため、施工
工数が多い。The following problems are pointed out in the above conventional method. (1) Of the steel frame construction methods for the building, since only the construction of the outer steel column on the outer rising wall 105 is performed in advance, it is difficult to ensure the construction accuracy of the construction of the outer steel column. Since the columns are constructed in the space where the cutting beams 103 are erected, the workability is poor and involves risks. (2) The construction of the steel frame of the building is the same as the construction of the outer steel column on the outer rising wall 105, the foundation 104 and the outer rising wall 10.
5 is performed separately from the construction of the steel frame inside the building after the construction, so that the construction procedure is complicated. (3) The belly 102 is not continuous in the horizontal direction,
Since the structure is cut off at the position where the outer peripheral steel column is erected, the rigidity of the pier is reduced, and the displacement of the outer ground 100 of the pier 101 is increased. (4) In order to form the structure in which the bulge 102 is cut at the position where the outer peripheral steel column is erected, a large number of short steel frames must be used as the bulge 102, and in order to prevent the rigidity from being reduced. The construction man-hours are large because the reinforcement of
【0006】本発明は、上記のような事情のもとになさ
れたもので、その技術的課題とするところは、鉄骨鉄筋
コンクリート建築物の地下部分の施工における山留架構
の剛性を高め、かつ施工の簡素化を図ることにある。The present invention has been made in view of the above circumstances, and a technical problem thereof is to increase the rigidity of a buckling frame structure in the construction of an underground portion of a steel-framed reinforced concrete building, and to improve the construction. Is to simplify.
【0007】[0007]
【課題を解決するための手段】上述した技術的課題を有
効に解決するための手段として、本発明に係る鉄骨鉄筋
コンクリート建築物の地下部分の施工方法は、地盤に打
ち込んだ山留壁の内側を根切掘削し、前記山留壁を腹起
しを介して切梁により支保する山留架構を行ってから、
前記根切掘削による基礎地盤上に建築物の基礎及びこの
基礎の外周から前記山留壁の内側に沿って前記切梁の下
側位置へ立ち上る外周立上り壁を鉄筋コンクリートで施
工し、前記鉄筋コンクリートの強度が発現した後で前記
切梁を解体し、前記外周立上り壁の頂部上に前記建築物
の外周鉄骨柱を建て込んで鉄骨建方を行うものである。
したがって、このようにして構築される建築物は、前記
基礎及び外周立上り壁が鉄筋コンクリート造であり、そ
の上の部分が鉄骨鉄筋コンクリート造となる。Means for Solving the Problems As a means for effectively solving the above-mentioned technical problems, a method for constructing an underground portion of a steel-framed reinforced concrete building according to the present invention comprises the steps of: After excavating the excavation and performing a retaining structure that supports the retaining wall with cutting beams through the belly,
On the foundation ground by the excavation excavation, a foundation of a building and an outer peripheral rising wall rising from the outer periphery of the foundation to the lower position of the girder along the inside of the retaining wall are constructed with reinforced concrete, and the strength of the reinforced concrete. After the occurrence of the above, the cutting beam is dismantled, and an outer peripheral steel column of the building is erected on the top of the outer peripheral rising wall to perform steel frame construction.
Therefore, in the building constructed in this manner, the foundation and the outer rising wall are made of reinforced concrete, and the upper part thereof is made of steel reinforced concrete.
【0008】本発明の施工方法によれば、建築物の地下
部分の外周立上り壁を鉄筋コンクリートで施工するた
め、前記地下部分の施工の際に外周鉄骨柱の建方は行わ
ない。したがって、山留架構における腹起しを、外周鉄
骨柱の建て込みのための寸断された構造とする必要はな
く、水平方向に連続したものとすることができる。前記
地下部分の外周立上り壁の施工後に、山留架構における
切梁を解体して、躯体施工のための鉄骨建方を行うが、
この時には山留壁に対する支保が前記外周立上り壁によ
って行われる。前記切梁の解体後は、外周鉄骨柱を外周
立上り壁の頂部上に建て込むが、この建て込みは前記建
築物における他の鉄骨柱や鉄骨梁による鉄骨建方と並行
して行うことができる。According to the construction method of the present invention, since the outer peripheral rising wall of the underground portion of the building is constructed of reinforced concrete, the construction of the outer peripheral steel column is not performed when constructing the underground portion. Therefore, it is not necessary to make the bulging in the mountain retaining structure a shredded structure for embedding the outer steel column, and it can be continuous in the horizontal direction. After construction of the perimeter rising wall of the underground part, dismantle the beam in the mountain retaining structure, perform the steel frame construction for building construction,
At this time, support for the retaining wall is performed by the outer peripheral rising wall. After the disassembly of the cut beam, the outer steel column is built on the top of the outer rising wall, and this can be performed in parallel with the steel frame construction by other steel columns and steel beams in the building. .
【0009】本発明において一層好ましくは、山留壁に
おける基礎及び外周立上り壁との接合面に多数の突起部
を設ける。この突起部は、典型的にはスタッドジベル等
からなるものである。このようにすれば、山留壁は前記
基礎及び外周立上り壁のコンクリートと確実に一体接合
され、周囲地盤の変位力を山留壁と外周立上り壁が一体
となって支持する強固な山留構造となる。In the present invention, more preferably, a number of protrusions are provided on the joint surface between the foundation and the outer peripheral rising wall of the retaining wall. The protrusion is typically made of a stud dowel or the like. In this way, the ridge wall is securely joined integrally with the concrete of the foundation and the outer peripheral rising wall, and a strong ridge structure that integrally supports the displacement force of the surrounding ground and the outer peripheral rising wall. Becomes
【0010】[0010]
【発明の実施の形態】図1乃至図4は、本発明に係る鉄
骨鉄筋コンクリート建築物の地下部分の施工方法の好適
な一実施形態を工程順に示すものである。まず図1に示
す根切掘削及び山留架構工程においては、建築物の地下
部分の施工外周に沿って例えばシートパイル等からなる
山留壁11を鉛直に打ち込み、その内側の地盤G1 を掘
削して行く。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIGS. 1 to 4 show a preferred embodiment of a method for constructing an underground portion of a steel reinforced concrete building according to the present invention in the order of steps. First, in the excavation excavation and mountain retaining frame process shown in FIG. 1, a mountain retaining wall 11 made of, for example, a sheet pile is driven vertically along a construction outer periphery of an underground portion of a building, and an inner ground G 1 is excavated. Go.
【0011】この根切掘削過程においては、山留壁11
の内側面に腹起し12を水平に取り付け、この腹起し1
2に対して切梁13をほぼ垂直にかつ水平に取り付けて
その長手方向中間を棚杭14に取り付けて支持すること
により、山留壁11の外側の地盤G2 の崩壊を防止する
山留架構1を構築する。そして図2に示すように、その
後更に山留壁11の内側の地盤G1 を所定の深さまで掘
削することによって根切を完了する。In the excavation process, the retaining wall 11
The belly 12 is mounted horizontally on the inner surface of the
2 is mounted substantially vertically and horizontally with respect to 2, and the longitudinal middle thereof is mounted and supported on a shelf pile 14 to prevent collapse of the ground G 2 outside the retaining wall 11. Build 1. Then, as shown in FIG. 2, completing the root switching by digging up and then further inside of the ground G 1 a predetermined depth mountain Tomekabe 11.
【0012】腹起し12は、山留壁11に対して図示の
断面と直交する方向へ連続的に延びるH型鋼等の鉄骨材
からなり、切梁13及び棚杭14もH型鋼等の鉄骨材か
らなる。このため、腹起しを各鉄骨柱の建て込み位置で
寸断された構造としていた従来工法に比較して施工工数
が少なくなる。しかも連続した腹起し12によって山留
架構1の剛性が高くなるので、山留壁11の外側の地盤
G2 が、例えば図示の断面と直交する方向に鉄道の軌道
(図示省略)が敷設された道床地盤であるような場合で
あっても、前記軌道上の車両の通過に伴う振動等による
地盤G2 の変位に対する支持力が向上する。The bulge 12 is made of a steel material such as H-shaped steel which continuously extends in a direction perpendicular to the cross section shown in the figure with respect to the retaining wall 11. Made of wood. For this reason, the number of construction steps is reduced as compared with the conventional construction method in which the bulge is cut at the position where each steel column is erected. Moreover, since the rigidity of YamaTome Frame 1 by wale 12 consecutive increases, the outside of the ground G 2 of YamaTomekabe 11, for example, railroad track in a direction perpendicular to the illustrated cross section (not shown) is laid even when an such that the track bed soil, the supporting force against the displacement of the ground G 2 due to vibration or the like caused by the passage of the vehicle on the track is improved.
【0013】次に、図3に示すように、根切掘削された
地盤G1 上に、建築物の地下部分となる基礎2及びこの
基礎2の外周から山留壁11の内側に沿って腹起し12
の下側位置へ立ち上る外周立上り壁3を鉄筋コンクリー
トで施工する。施工に際しては、型枠の組み立てや鉄筋
の配設(図示省略)等の作業を行い、前記型枠内にコン
クリートを打設する。また、山留壁11における基礎2
及び外周立上り壁3との接合部となる範囲には、予め多
数のスタッドジベル15が所定間隔で、打ち込み又はね
じ込み等によって突設される。このため基礎2及び外周
立上り壁3のコンクリートは、打設後硬化するのに伴い
前記スタッドジベル15を介して山留壁11と一体化
し、強固な接合状態となる。Next, as shown in FIG. 3, on the ground G 1 excavated and excavated, a ground 2 is formed along the inside of the retaining wall 11 from the outer periphery of the foundation 2 and the outer periphery of the foundation 2. Raising 12
The outer peripheral rising wall 3 that rises to the lower position is constructed of reinforced concrete. At the time of construction, work such as assembling a formwork and arranging reinforcing bars (not shown) is performed, and concrete is poured into the formwork. Also, the foundation 2 on the retaining wall 11
A large number of stud dowels 15 are previously provided at predetermined intervals in a range to be joined to the outer peripheral rising wall 3 by driving or screwing. For this reason, the concrete of the foundation 2 and the outer peripheral rising wall 3 is integrated with the retaining wall 11 via the stud dowels 15 as the concrete is hardened after the casting, and is in a strong joint state.
【0014】基礎2及び外周立上り壁3の鉄筋コンクリ
ートの強度が発現したら、図4に示すように山留架構1
における腹起し12、切梁13及び棚杭14を解体・撤
去する。切梁13の撤去後は、山留壁11の支保はこれ
に一体化された外周立上り壁3及び基礎2で行われる。When the strength of the reinforced concrete of the foundation 2 and the outer peripheral rising wall 3 has developed, the pier 1 is installed as shown in FIG.
The belly 12, the cutting beam 13 and the shelf pile 14 are dismantled and removed. After removal of the cutting beam 13, the retaining wall 11 is supported by the outer peripheral rising wall 3 and the foundation 2 integrated with the retaining wall 11.
【0015】次に、前記外周立上り壁3の頂部3a上
に、建築物外周部の柱となる外周鉄骨柱4を所定間隔で
鉛直に建て込み、基礎2上に建築物内部の柱となる鉄骨
柱5を所定間隔で鉛直に建て込み、これら鉄骨柱4,5
間に所定高さで鉄骨梁6を縦横に架設するといった鉄骨
建方を行う。すなわち、外周鉄骨柱4の柱脚下端レベル
は、他の鉄骨柱5の柱脚下端レベルよりも高くなる。Next, on the top 3a of the outer peripheral rising wall 3, an outer peripheral steel column 4 which is a column of the outer peripheral portion of the building is vertically erected at a predetermined interval, and a steel frame which becomes a column of the inner portion of the building is formed on the foundation 2. Pillars 5 are erected vertically at predetermined intervals, and these steel
A steel frame is constructed such that a steel beam 6 is vertically and horizontally erected at a predetermined height. That is, the lower end of the column base of the outer steel column 4 is higher than the lower end of the column base of the other steel columns 5.
【0016】この施工方法によれば、建築物外周部の柱
となる外周鉄骨柱4の建て込みが建築物内部の柱となる
鉄骨柱5及び鉄骨梁6の建方と並行して行われるので、
外周鉄骨柱4の建方を他の鉄骨建方に先行させる従来工
法に比較して施工精度を向上させることができる。According to this construction method, the outer peripheral steel columns 4 serving as pillars at the outer peripheral portion of the building are built in parallel with the steel columns 5 and the steel beams 6 serving as pillars inside the building. ,
The construction accuracy can be improved as compared with the conventional construction method in which the construction of the outer steel column 4 precedes the construction of another steel frame.
【0017】鉄骨建方の後は、従来と同様の工程で躯体
の施工を行う。したがって、この実施形態の方法により
構築される建築物は、基礎2及び外周立上り壁3が鉄筋
コンクリート(RC)造であり、その上の躯体部分が鉄
骨鉄筋コンクリート(SRC)造となる。After the steel frame is constructed, the skeleton is constructed in the same process as in the prior art. Therefore, in the building constructed by the method of this embodiment, the foundation 2 and the outer peripheral rising wall 3 are made of reinforced concrete (RC), and the skeleton thereon is made of steel reinforced concrete (SRC).
【0018】[0018]
【発明の効果】本発明によると、次のような効果が実現
される。 (1) 鉄骨建方作業が、切梁の解体・撤去後に行われるた
め作業性及び安全性が向上する。 (2) 外周鉄骨柱の建方を他の鉄骨柱や鉄骨梁の建方と並
行して行うことができ、しかも上述のように鉄骨建方の
作業性が向上するので、建築物の施工精度を向上させる
ことができる。 (3) 腹起しを外周鉄骨柱の建て込み位置で寸断された構
造とする必要がないので山留架構の剛性が向上する。 (4) 外周鉄骨柱の建方を他の鉄骨柱の建方に先行させる
必要がないので、施工手順が簡素化され、施工工数も削
減され、工期が短縮される。According to the present invention, the following effects are realized. (1) Workability and safety are improved because the steel frame construction work is performed after dismantling and removing the girder. (2) The construction of the outer steel columns can be performed in parallel with the construction of other steel columns and steel beams, and the workability of the steel frame construction is improved as described above. Can be improved. (3) The rigidity of the buckling frame is improved because it is not necessary to employ a structure in which the bulge is cut off at the position where the outer steel column is erected. (4) Since there is no need to precede the construction of the outer steel columns with the construction of other steel columns, the construction procedure is simplified, the number of construction steps is reduced, and the construction period is shortened.
【図1】本発明の施工方法の好適な一実施形態における
根切掘削及び山留架構工程を示す説明図である。FIG. 1 is an explanatory view showing a root excavation and a pier construction process in a preferred embodiment of a construction method of the present invention.
【図2】上記一実施形態における根切掘削完了状態を示
す説明図である。FIG. 2 is an explanatory diagram showing a root excavation completion state in the embodiment.
【図3】上記一実施形態における鉄骨鉄筋コンクリート
建築物の地下部分の基礎及び外周立上り壁の施工工程を
示す説明図である。FIG. 3 is an explanatory view showing a construction process of a foundation and an outer rising wall of an underground portion of a steel reinforced concrete building in the embodiment.
【図4】上記一実施形態における鉄骨鉄筋コンクリート
建築物の鉄骨建方工程を示す説明図である。FIG. 4 is an explanatory diagram showing a steel frame building process of the steel frame reinforced concrete building in the embodiment.
【図5】従来技術による施工方法を示す説明図である。FIG. 5 is an explanatory view showing a construction method according to a conventional technique.
1 山留架構 11 山留壁 12 腹起し 13 切梁 15 スタッドジベル 2 基礎 3 外周立上り壁 4 外周鉄骨柱 DESCRIPTION OF REFERENCE NUMERALS 1 mountain retaining frame 11 mountain retaining wall 12 bulging 13 cutting beam 15 stud dowel 2 foundation 3 outer rising wall 4 outer steel column
Claims (2)
削し、前記山留壁を腹起しを介して切梁により支保する
山留架構を行う工程と、 前記根切掘削による基礎地盤上に建築物の基礎及びこの
基礎の外周から前記山留壁の内側に沿って前記切梁の下
側位置へ立ち上る外周立上り壁を鉄筋コンクリートで施
工する工程と、 前記鉄筋コンクリートの強度が発現した後で前記切梁を
解体し、前記外周立上り壁の頂部上に前記建築物の外周
鉄骨柱を建て込んで鉄骨建方を行う工程と、からなるこ
とを特徴とする鉄骨鉄筋コンクリート建築物の地下部分
の施工方法。1. A step of excavating the inside of a retaining wall driven into the ground, and performing a retaining structure supporting the retaining wall with a cutting beam via a flank, and a foundation by the excavation. A step of constructing a foundation of the building on the ground and an outer peripheral rising wall rising from the outer periphery of the foundation to the lower position of the girder along the inside of the retaining wall with reinforced concrete, after the strength of the reinforced concrete is developed Dismantling the girder at the top of the perimeter rising wall, erection of the steel frame by erection of the outer peripheral steel columns of the building, comprising: Construction method.
及び外周立上り壁との接合面に多数の突起部を設けるこ
とを特徴とする鉄骨鉄筋コンクリート建築物の地下部分
の施工方法。2. The method according to claim 1, wherein a number of protrusions are provided on the joint surface between the foundation of the retaining wall and the outer peripheral rising wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP36331197A JP4050816B2 (en) | 1997-12-16 | 1997-12-16 | Construction method of underground part of steel reinforced concrete building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP36331197A JP4050816B2 (en) | 1997-12-16 | 1997-12-16 | Construction method of underground part of steel reinforced concrete building |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11172710A true JPH11172710A (en) | 1999-06-29 |
JP4050816B2 JP4050816B2 (en) | 2008-02-20 |
Family
ID=18479019
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP36331197A Expired - Fee Related JP4050816B2 (en) | 1997-12-16 | 1997-12-16 | Construction method of underground part of steel reinforced concrete building |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4050816B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101011805B1 (en) | 2010-09-08 | 2011-02-07 | 김진수 | Method of constructing underground structures crossing the pile foundation and underground structures constructed using the same |
CN103266624A (en) * | 2013-06-02 | 2013-08-28 | 中国石油集团工程设计有限责任公司 | Method for supporting oil and gas pipeline penetrating through karst active zone |
CN106758852A (en) * | 2017-02-21 | 2017-05-31 | 浙江浙耀建设集团有限公司 | Across foundation pit enclosure to support beam trestle construction technology |
CN106894421A (en) * | 2017-01-19 | 2017-06-27 | 中国建筑第八工程局有限公司 | The method for dismounting of internal support of foundation pit beam |
CN109356167A (en) * | 2018-11-22 | 2019-02-19 | 深圳市福田建安建设集团有限公司 | Brace in Deep Footing Groove removes system and construction method |
CN110820530A (en) * | 2019-10-18 | 2020-02-21 | 北京市第三建筑工程有限公司 | Concrete trestle and foundation pit connecting node structure and construction method thereof |
CN111519634A (en) * | 2020-04-30 | 2020-08-11 | 中国一冶集团有限公司 | Temporary support replacing structure and support disassembling and replacing construction method |
JP2021134522A (en) * | 2020-02-26 | 2021-09-13 | 株式会社竹中工務店 | Underground structure construction method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102425172B (en) * | 2011-12-05 | 2013-12-11 | 中冶天工集团有限公司 | Support method for excavating deep foundation pit closely adjacent to high-rise building |
CN111456032B (en) * | 2020-04-28 | 2022-02-15 | 中铁工程装备集团有限公司 | Foundation pit supporting system and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6294617A (en) * | 1985-10-18 | 1987-05-01 | Fujita Corp | Reinforcing of outer wall of body using sheathing wall |
JPH06272267A (en) * | 1993-03-25 | 1994-09-27 | Takenaka Komuten Co Ltd | Method for utilizing soil cement post lined wall to built composite underground skeleton |
JPH07150580A (en) * | 1993-11-30 | 1995-06-13 | Takenaka Komuten Co Ltd | Building construction method for medium and small-scale building having underground floor |
JPH0841913A (en) * | 1994-08-03 | 1996-02-13 | Takenaka Komuten Co Ltd | Underground structure of building having no internal column at underground floor and below and its construction method |
JPH0881964A (en) * | 1994-09-07 | 1996-03-26 | Asahi Chem Ind Co Ltd | Body structure of building with underground section and execution method thereof |
-
1997
- 1997-12-16 JP JP36331197A patent/JP4050816B2/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6294617A (en) * | 1985-10-18 | 1987-05-01 | Fujita Corp | Reinforcing of outer wall of body using sheathing wall |
JPH06272267A (en) * | 1993-03-25 | 1994-09-27 | Takenaka Komuten Co Ltd | Method for utilizing soil cement post lined wall to built composite underground skeleton |
JPH07150580A (en) * | 1993-11-30 | 1995-06-13 | Takenaka Komuten Co Ltd | Building construction method for medium and small-scale building having underground floor |
JPH0841913A (en) * | 1994-08-03 | 1996-02-13 | Takenaka Komuten Co Ltd | Underground structure of building having no internal column at underground floor and below and its construction method |
JPH0881964A (en) * | 1994-09-07 | 1996-03-26 | Asahi Chem Ind Co Ltd | Body structure of building with underground section and execution method thereof |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101011805B1 (en) | 2010-09-08 | 2011-02-07 | 김진수 | Method of constructing underground structures crossing the pile foundation and underground structures constructed using the same |
CN103266624A (en) * | 2013-06-02 | 2013-08-28 | 中国石油集团工程设计有限责任公司 | Method for supporting oil and gas pipeline penetrating through karst active zone |
CN106894421A (en) * | 2017-01-19 | 2017-06-27 | 中国建筑第八工程局有限公司 | The method for dismounting of internal support of foundation pit beam |
CN106758852A (en) * | 2017-02-21 | 2017-05-31 | 浙江浙耀建设集团有限公司 | Across foundation pit enclosure to support beam trestle construction technology |
CN109356167A (en) * | 2018-11-22 | 2019-02-19 | 深圳市福田建安建设集团有限公司 | Brace in Deep Footing Groove removes system and construction method |
CN110820530A (en) * | 2019-10-18 | 2020-02-21 | 北京市第三建筑工程有限公司 | Concrete trestle and foundation pit connecting node structure and construction method thereof |
JP2021134522A (en) * | 2020-02-26 | 2021-09-13 | 株式会社竹中工務店 | Underground structure construction method |
CN111519634A (en) * | 2020-04-30 | 2020-08-11 | 中国一冶集团有限公司 | Temporary support replacing structure and support disassembling and replacing construction method |
CN111519634B (en) * | 2020-04-30 | 2022-05-10 | 中国一冶集团有限公司 | Support removing and replacing construction method of temporary support replacing structure |
Also Published As
Publication number | Publication date |
---|---|
JP4050816B2 (en) | 2008-02-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH11172710A (en) | Method for constructing underground part of steel encased reinforced concrete building | |
JP3724320B2 (en) | Construction method for underground structures | |
KR101428540B1 (en) | Soundproof walls basis structure | |
JPH102126A (en) | Seismic isolated building | |
JP4115095B2 (en) | Reverse strike method | |
KR200370107Y1 (en) | Forms for edge girder construction | |
KR101296856B1 (en) | Reinforcement structure for wall of underground structure and construction method of underground structure using the same | |
JP3159141B2 (en) | Construction method of building frame using existing outer wall | |
JP2964295B2 (en) | Basement floor construction method | |
JPH04330168A (en) | Construction method for building with basement equipped with steel pipe pile foundation | |
JP3109038B2 (en) | Underground skeleton structure and construction method | |
JP2769937B2 (en) | Steel tube concrete column in underground reverse driving method | |
JPS63280153A (en) | Underground inverted lining method | |
KR102364887B1 (en) | Non-open cut construction method for a tunnel and temporary structure | |
JP3767347B2 (en) | Reverse strike method | |
JP2894217B2 (en) | Building structural frame | |
JPH101957A (en) | Underground construction method for building | |
JPH08291526A (en) | Construction method for underground structure | |
JPH03147926A (en) | construction method for basement | |
JPH08302689A (en) | Construction method for underground wall structure | |
JPH04366229A (en) | Temporary corresponding standard used for method of reverse driving construction | |
JP2002275921A (en) | Reverse construction method | |
KR20240177474A (en) | Retaining wall construction method using strip type steel plate inserting PHC Pile | |
JPH03253613A (en) | Underground excavation mountain stop construction method | |
KR200369485Y1 (en) | a deck supportframe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041111 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20061130 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070808 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071002 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20071031 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071130 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101207 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111207 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121207 Year of fee payment: 5 |
|
LAPS | Cancellation because of no payment of annual fees |