[go: up one dir, main page]

JPH10306593A - Execution method of waterproofing sheet in building construction and execution device - Google Patents

Execution method of waterproofing sheet in building construction and execution device

Info

Publication number
JPH10306593A
JPH10306593A JP12468097A JP12468097A JPH10306593A JP H10306593 A JPH10306593 A JP H10306593A JP 12468097 A JP12468097 A JP 12468097A JP 12468097 A JP12468097 A JP 12468097A JP H10306593 A JPH10306593 A JP H10306593A
Authority
JP
Japan
Prior art keywords
building
waterproof sheet
waterproofing sheet
hanger rail
lateral direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12468097A
Other languages
Japanese (ja)
Inventor
Ishiyuki Takai
石行 高井
Mikio Kihara
幹夫 木原
Takaaki Horaguchi
貴昭 洞口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanritsu Giken Kogyo KK
AGC Inc
Original Assignee
Asahi Glass Co Ltd
Sanritsu Giken Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Glass Co Ltd, Sanritsu Giken Kogyo KK filed Critical Asahi Glass Co Ltd
Priority to JP12468097A priority Critical patent/JPH10306593A/en
Publication of JPH10306593A publication Critical patent/JPH10306593A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an execution method and an execution device to enable a single person to speedily and certainly carry out installation work of a waterproofing sheet in the horizontal direction without a trouble and perfectly prevent intrusion of rainwater since conventionally it is impossible to carry out speedy work with a lot of troubles and to perfectly prevent intrusion of rainwater as a method of making a group of at least two persons on a scaffold board, with one person holding the waterproofing sheet in the vertical and longitudinal directions against a building side surface and the other person carrying out stitching work is extensively adopted at the time of installing the waterproofing sheet in the circumference of the building at a building construction site. SOLUTION: A suspension member is suspended free to move in the lateral direction on a hanger rail 6 installed on an upper part of a building under construction, and a waterproofing sheet fixture 26 is installed on this suspension member. Thereafter, this waterproofing sheet fixture 26 is stopped at optional height in the circumference of the building by a brake provided on the suspension member, and the rolled type waterproofing sheet prepared on the waterproofing sheet fixture 26 is spread in the lateral direction.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、建築工事における
防水シートの施工法及び施工装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for installing a waterproof sheet in building construction.

【0002】[0002]

【従来の技術】従来、建築工事の現場において防水シー
トを建物周囲に取付けるときは、足場板上に最低2人が
1組となり、建物に対して垂直方向に1人が防水シート
を持ち、他の1人がステッチ止め作業をする方法が広く
採られていたため、手数がかかり迅速な作業を行うこと
ができなかったし、雨水が侵入し易い張り付け状態にな
っていた。
2. Description of the Related Art Conventionally, when a waterproof sheet is attached around a building at a construction site, at least two persons are provided on a scaffold plate, and one person holds the waterproof sheet in a direction perpendicular to the building. Because the method of stitch stop work was widely adopted by one person, it was troublesome and could not be carried out quickly, and it was in a stuck state where rainwater easily penetrated.

【0003】[0003]

【発明が解決しようとする課題】そこで、本発明はこの
ような欠点を一掃し手数をかけることなく、1人で水平
方向に迅速かつ確実に防水シートの取付け作業を行うこ
とができるとともに雨水の侵入を完全に防止することが
できる施工方法と装置を提供することを目的とするもの
である。
SUMMARY OF THE INVENTION Accordingly, the present invention eliminates such disadvantages and allows a single person to quickly and reliably mount a waterproof sheet in the horizontal direction without trouble, while at the same time allowing rainwater to be removed. It is an object of the present invention to provide a construction method and apparatus capable of completely preventing intrusion.

【0004】[0004]

【課題を解決するための手段】本発明は、建築中の建物
の上位部に架設したハンガーレールに吊下部材を横方向
に移動可能に吊設し、この吊下部材に防水シート取付具
を取付け、この防水シート取付具を前記吊下部材に設け
たブレーキにより建物周囲の任意高さに停止し、前記防
水シート取付具に用意したロール状防水シートを横方向
に張付ける施工法である。
SUMMARY OF THE INVENTION According to the present invention, a suspension member is suspended on a hanger rail erected above a building under construction so as to be movable in a lateral direction, and a waterproof sheet mounting member is attached to the suspension member. This is a construction method in which the waterproof sheet mounting device is stopped at an arbitrary height around the building by a brake provided on the suspension member, and a roll-shaped waterproof sheet prepared for the waterproof sheet mounting device is laterally stretched.

【0005】また、本発明は、建物周囲に仮設した支柱
間の上位部に横方向にハンガーレールを架設し、このハ
ンガーレールに移動輪を設けたバランサー凾体を吊設
し、この凾体の内部に設けたドラムにロープを捲回する
とともにブレーキを併設し、前記ロープの下端部に防水
シート取付具を着脱し得るように設け、この防水シート
取付具にはロール状防水シートを横方向に張付けるよう
にする装置である。
Further, according to the present invention, a hanger rail is erected laterally on an upper portion between columns temporarily provided around a building, and a balancer housing provided with a moving wheel is hung on the hanger rail, and a hanger rail is provided. A rope is wound around a drum provided inside and a brake is also provided, and a waterproof sheet attachment is provided at the lower end of the rope so that a waterproof sheet attachment can be attached and detached. It is a device to be stuck.

【0006】さらに、本発明は、建物の各支柱間の上位
部に横方向にハンガーレールを架設し、このハンガーレ
ールに移動輪を設けたバランサー凾体を吊設し、この凾
体の内部に設けたホィールにチェーンを捲回するととも
にブレーキ機構を併設し、前記チェーンの両端部に防水
シート取付具を着脱し得るように設け、この防水シート
取付具にはロール状防水シートを横方向に張架するよう
にする装置である。
Further, according to the present invention, a hanger rail is erected laterally on an upper portion between the columns of a building, and a balancer housing provided with moving wheels is hung on the hanger rail, and the hanger rail is hung inside the housing. A chain is wound around the provided wheel and a brake mechanism is also provided.A waterproof sheet attachment is provided at both ends of the chain so that a waterproof sheet attachment can be attached to and detached from the chain. It is a device to be mounted.

【0007】[0007]

【発明の実施の形態】請求項2の装置においては、次の
ような作用を行う。(図1乃至図7参照)
DESCRIPTION OF THE PREFERRED EMBODIMENTS In the apparatus according to the second aspect, the following operation is performed. (See FIGS. 1 to 7)

【0008】ワイヤロープの引き上げは、ドラムとクラ
ッチが同時回転するから、バランサー凾体に内蔵される
コイル弾機によって巻き上げられるが、防水ロールシー
トの自重が使用前と使用後とでは変化するから、ある荷
重の範囲(例えば5〜10Kg)まではバランスするよう
に、前記ブレーキワイヤによるブレーキ作用を調節螺子
によって予め加減調節する。
When the wire rope is pulled up, the drum and the clutch rotate at the same time, so that the wire rope is wound up by a coil ammunition built in the balancer housing. However, the weight of the waterproof roll sheet changes between before and after use. The braking action of the brake wire is preliminarily adjusted by an adjusting screw so as to balance the load within a certain load range (for example, 5 to 10 kg).

【0009】ワイヤロープを引き下げるときは、クラッ
チとブレーキホィールが一体となりワイヤとの間で空転
するから、ブレーキ作用を調節螺子によって予め調整す
る。
When the wire rope is pulled down, the clutch and the brake wheel are integrated and idle with the wire, so that the braking action is adjusted in advance by adjusting screws.

【0010】前記防水ロールシートを上部可動軸と下部
固定軸との間で着脱するときは、前記調整螺子を弛緩し
上方の管体を下方の調整杆から抜き上げるようにすれ
ば、上部可動軸がロールシートの上端部から離脱し直に
取外せるようになり、またこの逆の作業をすれば取付け
られるようになる。
When the waterproof roll sheet is attached to and detached from the upper movable shaft and the lower fixed shaft, the adjusting screw is relaxed so that the upper tube is pulled up from the lower adjusting rod. Can be detached from the upper end of the roll sheet and can be directly removed, and can be mounted by performing the reverse operation.

【0011】前記したワイヤロープの引き上げと引き下
げの作業は、足場を建物周囲に設置した場合には足場上
で行うが、足場を設置できない場合には建物の内側にお
いて行うのである。
The above-described work of raising and lowering the wire rope is performed on the scaffold when the scaffold is installed around the building, but is performed inside the building when the scaffold cannot be installed.

【0012】請求項3の装置においては、次のような作
用を行う。(図9乃至図16参照)
According to the third aspect of the invention, the following operation is performed. (See FIGS. 9 to 16)

【0013】建物密集地における新築工事の場合には足
場を仮設することが困難であり、作業員は建物の内側に
おいて防水シートの張りつけをしなければならないの
で、まず各支柱の最上位部にレールブラケットを取付
け、このブラケット間にハンガーレールを架設する。
[0013] In the case of new construction work in a densely built area, it is difficult to temporarily set up a scaffold, and an operator must attach a waterproof sheet inside the building. Attach the brackets and install the hanger rail between the brackets.

【0014】しかる後に、ハンガーレールにハンガーロ
ールを介してロールブラケットを吊設し、このロールブ
ラケットにチェーンホィールブラケットの吊り部を連結
して固定する。
Thereafter, a roll bracket is hung on the hanger rail via a hanger roll, and the hanging portion of the chain wheel bracket is connected to the roll bracket and fixed.

【0015】前記チェーンホィールブラケットには、チ
ェーンを内蔵したチェーンホィールケースを設置し、チ
ェーンホィールに懸架したチェーンの両端部に防水シー
ト取付具を装着する。
The chain wheel bracket is provided with a chain wheel case with a built-in chain, and a waterproof sheet attachment is attached to both ends of the chain suspended on the chain wheel.

【0016】いま防水シートを張りつけるときは、建物
の内側からチェーンを操作して建物の所定場所にロール
シートを取付けたシート取付具を位置せしめておき、前
記ロールシートを横方向に引き延ばして張りわたすので
ある。
When attaching a waterproof sheet, a chain attachment is attached to a predetermined place in the building by operating a chain from the inside of the building, and the roll sheet is stretched in the lateral direction and stretched. It is.

【0017】チェーンを操作してのシート取付具の上下
位置移動は、チェーンホィールはワンウェークラッチと
共に回転するようになる。
The vertical movement of the seat fixture by operating the chain causes the chain wheel to rotate together with the one-way clutch.

【0018】前記防水ロールシートを上部可動軸と下部
固定軸との間で着脱するときは、前記調整螺子を弛緩し
上方の管体を下方の調整杆から抜き上げるようにすれ
ば、上部可動軸がロールシートの上端部から離脱し直に
取外せるようになり、またこの逆の作業をすれば取付け
られるようになる。
When attaching and detaching the waterproof roll sheet between the upper movable shaft and the lower fixed shaft, the adjusting screw is relaxed so that the upper tubular body is pulled up from the lower adjusting rod. Can be detached from the upper end of the roll sheet and can be directly removed, and can be mounted by performing the reverse operation.

【0019】[0019]

【実施例】まず図1乃至図7に示した装置例について説
明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS First, an example of the apparatus shown in FIGS. 1 to 7 will be described.

【0020】1は建築中の建物の周囲に仮設する足場装
置で、この足場装置の各支柱管材2・・の上端部には水平
方向と斜め方向に支軸管材3,4の一端部を取付ける。
Reference numeral 1 denotes a scaffolding device which is temporarily installed around a building under construction. One end of each of the supporting tube members 3 and 4 is attached to the upper end of each of the supporting tube members 2... .

【0021】5は前記支軸管材3,4の他端部を取付け
るブラケットで、このブラケットは前記支柱管材2と支
軸管材3,4の数だけ設ける。
Reference numeral 5 denotes a bracket for mounting the other end portions of the support tube members 3 and 4. The number of the brackets provided is equal to the number of the support tube members 2 and the support tube members 3 and 4.

【0022】6は前記各ブラケット5・・に取付けピン4
0にて連結して架設するハンガーレールで、このハンガ
ーレールは建物の屋根の軒先部に隣接する位置に設置す
る。
Reference numeral 6 denotes a mounting pin 4 for each of the brackets 5.
This is a hanger rail connected and erected at 0, and this hanger rail is installed at a position adjacent to the eaves of the roof of the building.

【0023】7,7は前記ハンガーレール6の内部を走
行するハンガーロールで、このハンガーロールはこれに
吊設するバランサー凾体8の上面部に設ける。
Numerals 7 and 7 denote hanger rolls running inside the hanger rail 6, and these hanger rolls are provided on the upper surface of a balancer box 8 suspended therefrom.

【0024】以上のハンガーレール部の取付け構造は、
建物の周囲に足場を仮設する余裕空間のある一般仕様の
場合である。
The above hanger rail mounting structure is as follows.
This is the case of general specifications with ample space for temporarily installing a scaffold around the building.

【0025】9は前記バランサー凾体8の内部の回転軸
10に取付けたドラム11に捲回したワイヤロープで、
このワイヤロープは前記バランサー凾体8の底面部に設
けた通口12より外出する。このワイヤロープの長さ
は、通常の建物の1階から3階程度までのシートを取付
けることができる長さとする。
Reference numeral 9 denotes a wire rope wound around a drum 11 attached to a rotating shaft 10 inside the balancer box 8.
The wire rope goes out of a through hole 12 provided on the bottom surface of the balancer box 8. The length of the wire rope is set to a length that allows seats on the first to third floors of a normal building to be attached.

【0026】13は前記ドラム11の中央部に形成した
中央壁で、この中央壁をはさんで一側部にはドラム回転
軸10と同軸にブレーキホィール14を設ける。このブ
レーキホィール14にはブレーキワイヤ15を懸架し、
このブレーキワイヤの一端部には弾機16を介して設け
た調節螺子17をバランサー凾体8の底面部8’の一部
に固着し、その他端部は凾体8の側面部の一部に固着す
る。
Reference numeral 13 denotes a center wall formed at the center of the drum 11. A brake wheel 14 is provided coaxially with the drum rotating shaft 10 on one side of the center wall with the center wall interposed therebetween. A brake wire 15 is suspended from the brake wheel 14,
At one end of the brake wire, an adjusting screw 17 provided via a spring 16 is fixed to a part of the bottom surface 8 ′ of the balancer housing 8, and the other end is connected to a part of the side surface of the housing 8. Stick.

【0027】18は前記ブレーキホィール14の中心軸
部14’に設けたクラッチで、このクラッチは一方向性
のものであり、ブレーキホィール14が図3の矢印方向
に回動すると、この一方向性クラッチ18が作用して前
記回転軸10を停止し、前記ドラム11にブレーキがか
かるようになる。
Reference numeral 18 denotes a clutch provided on the central shaft portion 14 'of the brake wheel 14, which is a one-way clutch. When the brake wheel 14 rotates in the direction of the arrow in FIG. The clutch 18 acts to stop the rotating shaft 10 and the drum 11 is braked.

【0028】19は前記ドラム11の中央壁13の他側
部にドラム回転軸10と同軸上に設けた巻取りリール
で、この巻取りリールの周囲には3個の小リール20・・
を前記中央壁13に軸支21して設けるとともに各小リ
ールには板発条22を捲回してその外端部を前記巻取り
リール19に固着23する。
Reference numeral 19 denotes a take-up reel provided on the other side of the center wall 13 of the drum 11 coaxially with the drum rotating shaft 10. Three small reels 20 are provided around the take-up reel.
Is provided on the central wall 13 as a pivot 21 and a plate reel 22 is wound around each of the small reels, and the outer end thereof is fixed to the take-up reel 19.

【0029】前記ワイヤロープ9の引き上げは、ドラム
11とクラッチ18が同時回転するから、バランサー凾
体8に内蔵されるコイル弾機によって巻き上げられる
が、後記する防水ロールシート37の自重が使用前と使
用後とでは変化するから、ある荷重の範囲(例えば5〜
10Kg)まではバランスするように、前記ブレーキワイ
ヤ15によるブレーキ作用を調節螺子17によって加減
調節する。
When the wire rope 9 is pulled up, the drum 11 and the clutch 18 rotate at the same time, so that the wire rope 9 is wound up by a coil ammunition built in the balancer housing 8. Since it changes after use, a certain load range (for example, 5 to 5)
The braking action of the brake wire 15 is adjusted by an adjusting screw 17 so as to balance up to 10 kg).

【0030】ワイヤロープ9を引き下げるときは、クラ
ッチ18とブレーキホィール14が一体となりワイヤ1
5との間で空転するから、ブレーキ作用を調節螺子17
によって調整する。
When the wire rope 9 is pulled down, the clutch 18 and the brake wheel 14 are integrated and the wire 1
5, the brake action is adjusted by the adjusting screw 17
Adjust by

【0031】24・・は前記支柱管材2・・の中間部及び下
端部に設けた支軸管材部で、この支軸管材部間に足場板
25を懸架する。
Reference numerals 24... Denote support shaft tube portions provided at the middle and lower end portions of the support tube members 2... A scaffold plate 25 is suspended between the support tube members.

【0032】26は防水シート取付具で、このシート取
付具は上端部に設けた取付管27に管体28の支杆29
を固着し、前記管体に嵌挿した調整杆30を調整螺子3
1により固定する。この調整杆30は断面六角形状に成
る。
Numeral 26 denotes a waterproof sheet attachment, which is attached to an attachment pipe 27 provided at the upper end by a support rod 29 of a pipe 28.
Is fixed, and the adjusting rod 30 inserted into the tube is adjusted with the adjusting screw 3.
Fix with 1. The adjusting rod 30 has a hexagonal cross section.

【0033】32は前記取付管27の下方に設けた端杆
33に座板34を介して下向きに突設した上部可動軸
で、この反対の前記調整杆30の端部には座板35を介
して下部固定軸36を上向きに突設する。前記調整杆3
0が断面六角形状に成るのは、前記上部可動軸32と下
部固定軸36との中心を合わせ易くするためである。
Reference numeral 32 denotes an upper movable shaft protruding downward from an end rod 33 provided below the mounting pipe 27 via a seat plate 34. A seat plate 35 is provided at the opposite end of the adjusting rod 30. The lower fixed shaft 36 is provided so as to protrude upward. The adjusting rod 3
The reason why 0 has a hexagonal cross section is to facilitate alignment of the center between the upper movable shaft 32 and the lower fixed shaft 36.

【0034】37は前記上部可動軸32と下部固定軸3
6との間に取付けるロール状の防水シートで、このロー
ルシートの縦巾の長さに違いがあるときは、前記調整螺
子31を弛緩して上部可動軸32と下部固定軸36との
間隔を長短に調整するようにする。
37 denotes the upper movable shaft 32 and the lower fixed shaft 3
When there is a difference in the length of the roll sheet between the upper movable shaft 32 and the lower fixed shaft 36, the adjusting screw 31 is loosened. Adjust the length.

【0035】前記防水ロールシート37部材を上部可動
軸32と下部固定軸36との間で着脱するときは、前記
調整螺子31を弛緩し上方の管体28を下方の調整杆3
0から抜き上げるようにすれば、上部可動軸32部がロ
ールシート37の上端部から離脱するから直に取外せる
ようになり、またこの逆の作業をすれば取付けられるよ
うになる。
When attaching and detaching the waterproof roll sheet 37 between the upper movable shaft 32 and the lower fixed shaft 36, the adjusting screw 31 is loosened and the upper tube 28 is moved to the lower adjusting rod 3.
If the upper movable shaft 32 is separated from the upper end of the roll sheet 37 if it is pulled up from 0, it can be directly removed, and can be mounted by performing the reverse operation.

【0036】38は前記取付管27の上端部に設けた吊
環で、この吊環には前記ワイヤロープ9のフック39を
掛止める。
Reference numeral 38 denotes a suspension ring provided at the upper end of the mounting tube 27, and the hook 39 of the wire rope 9 is hooked on the suspension ring.

【0037】ところで、ハンガーレール部の構造は、建
物が密集している工事現場において足場を仮設すること
が不可能な場所は、隣接仕様として次のように構成する
とよい。
By the way, the structure of the hanger rail section may be configured as follows as an adjacent specification in a construction site where buildings are densely located and where a scaffold cannot be temporarily provided.

【0038】図8に示した例は、建物の周囲に建築中で
むき出しになっている各支柱a間の上位部に取付枠材4
1を嵌合し、取付螺子42の先端の押圧子43を支柱a
面に押接して固定し、前記取付枠材41の外側部にはブ
ラケット44が固着する。
FIG. 8 shows an example in which the mounting frame member 4 is provided on the upper part between the columns a exposed around the building and exposed in the construction.
1 and the pressing element 43 at the tip of the mounting screw 42 is
The bracket 44 is fixed to the outside of the mounting frame member 41 by pressing against the surface.

【0039】前記ブラケット44間に架設したハンガー
レール6の上面通孔45とブラケット44の上部通孔4
6との間には、取付けピン40を着脱自在に嵌挿して取
付ける。
The upper through hole 45 of the hanger rail 6 and the upper through hole 4 of the bracket 44 are provided between the brackets 44.
A mounting pin 40 is removably fitted between the mounting pins 6 and 6 for mounting.

【0040】前記ハンガーレール6を走行するハンガー
ロール7には、バランサー凾体8が吊設するように成
る。
A balancer housing 8 is suspended from a hanger roll 7 running on the hanger rail 6.

【0041】次に、図9乃至図16に示した装置例につ
いて説明するが、この例も建物密集場所における隣接仕
様である。
Next, an example of the apparatus shown in FIGS. 9 to 16 will be described. This example is also an adjoining specification in a building dense place.

【0042】51は建物の各支柱aの最上位部に取付け
るレールブラケットで、このブラケット間にはハンガー
レール52を架設する。
Reference numeral 51 denotes a rail bracket attached to the uppermost portion of each pillar a of the building, and a hanger rail 52 is installed between the brackets.

【0043】53,53は前記ハンガーレール52内を
走行するハンガーロールで、このロールを吊設するロー
ルブラケット54にはチェーンホィールブラケット55
の吊り部55’を連結し、この吊り部はロールブラケッ
ト54の側面から螺子56にて固定する。
Reference numerals 53, 53 denote hanger rolls running on the hanger rail 52. A roll bracket 54 for suspending the rolls has a chain wheel bracket 55.
Of the roll bracket 54 is fixed by screws 56 from the side surface of the roll bracket 54.

【0044】57は前記ホィールブラケット55を上面
部に設けたチェーンホィールケースで、このホィールケ
ースの中心部に設けた支軸58には軸部59を介してチ
ェーンホィール60を軸架し、ここにチェーン61を懸
架する。
Reference numeral 57 denotes a chain wheel case provided with the wheel bracket 55 on the upper surface thereof. A chain wheel 60 is mounted on a support shaft 58 provided at the center of the wheel case via a shaft portion 59. The chain 61 is suspended.

【0045】62は前記チェーンホィール60の軸部5
9から外出している前記支軸58の一端部に嵌合したス
リーブで、このスリーブは前記チェーンホィール60の
軸部59の一側凹部に圧入固着する。
Reference numeral 62 denotes the shaft 5 of the chain wheel 60.
The sleeve is fitted to one end of the support shaft 58 which is outside of the shaft 9, and the sleeve is press-fitted and fixed to one side recess of the shaft portion 59 of the chain wheel 60.

【0046】63は前記支軸58上のスリーブ62の一
端部に取付けたワンウェークラッチで、このクラッチの
外周にはブレーキホィール64を取付ける。65はその
ブレーキホィール64の線材である。
Reference numeral 63 denotes a one-way clutch mounted on one end of the sleeve 62 on the support shaft 58. A brake wheel 64 is mounted on the outer periphery of the clutch. Reference numeral 65 denotes a wire rod of the brake wheel 64.

【0047】66は前記ブレーキホィール64部を被套
するブレーキホィールケースで、このケースは前記チェ
ーンホィールケース57の一側面部に固着する。
Reference numeral 66 denotes a brake wheel case which covers the brake wheel 64, and this case is fixed to one side surface of the chain wheel case 57.

【0048】前記ブレーキホィール64にはワンウェー
クラッチ63を設けているが、これに代えて爪車67と
爪片68と弾機69から成るワンウェーシステムによっ
て構成してもよい。(図15,図16参照)
The brake wheel 64 is provided with a one-way clutch 63. Alternatively, the brake wheel 64 may be constituted by a one-way system comprising a ratchet 67, a pawl 68, and a bullet 69. (See FIGS. 15 and 16)

【0049】70は防水シート取付具で、このシート取
付具は上端部に設けた取付管71に管体72の支杆73
を固着し、前記管体に嵌挿した調整杆74を調整螺子7
5により固定する。この調整杆74は断面六角形状に成
る。
Numeral 70 denotes a waterproof sheet mounting member, which is attached to a mounting tube 71 provided at an upper end portion by a support rod 73 of a tube 72.
Is fixed, and the adjusting rod 74 inserted into the tube is adjusted with the adjusting screw 7.
Fix with 5. The adjusting rod 74 has a hexagonal cross section.

【0050】76は前記取付管71の下端部に座板77
を介して下向きに突設した上部可動軸で、この反対の前
記調整杆74の端部には座板78を介して下部固定軸7
9を上向きに突設する。前記調整杆74が断面六角形状
に成るのは、前記上部可動軸76と下部固定軸79との
中心を合わせ易くするためである。
Reference numeral 76 denotes a seat plate 77 at the lower end of the mounting pipe 71.
An upper movable shaft protruding downward through the lower fixed shaft 7 via a seat plate 78 to the opposite end of the adjusting rod 74.
9 is projected upward. The reason why the adjusting rod 74 has a hexagonal cross section is to facilitate alignment of the center between the upper movable shaft 76 and the lower fixed shaft 79.

【0051】80は前記上部可動軸76と下部固定軸7
9との間に取付けるロール状の防水シートで、このロー
ルシートの縦巾の長さに違いがあるときは、前記調整螺
子75を弛緩して上部可動軸76と下部固定軸79との
間隔を長短に調整するようにする。
Reference numeral 80 denotes the upper movable shaft 76 and the lower fixed shaft 7
9, when there is a difference in the vertical width of the roll sheet, loosen the adjusting screw 75 to reduce the distance between the upper movable shaft 76 and the lower fixed shaft 79. Adjust the length.

【0052】前記防水ロールシート80を上部可動軸7
6と下部固定軸79との間で着脱するときは、前記調整
螺子75を弛緩し上方の管体72を下方の調整杆74か
ら抜き上げるようにすれば、上部可動軸76がロールシ
ート80の上端部から離脱し直に取外せるようになり、
またこの逆の作業をすれば取付けられるようになる。
The waterproof roll sheet 80 is moved to the upper movable shaft 7
When attaching and detaching between the lower fixed shaft 79 and the lower fixed shaft 79, the adjusting screw 75 is relaxed so that the upper tube 72 is pulled out from the lower adjusting rod 74, so that the upper movable shaft 76 It can be detached from the upper end and removed immediately,
In addition, by performing the reverse operation, it can be mounted.

【0053】81,81は前記取付管71の上下両端部
に設けた掛止め用フックで、このフックは前記チェーン
61の両端部にそれぞれ掛止める。
Reference numerals 81, 81 denote hooks provided on both upper and lower ends of the mounting tube 71. These hooks are hooked on both ends of the chain 61, respectively.

【0054】[0054]

【発明の効果】建築中の建物の周囲に防水シートを張架
する作業を行うときは、1人の作業員が迅速かつ確実に
横方向に何段にも張りめぐらすことができ、短時間のう
ちにシートの取付け作業を行うことができる。したがっ
て、工事コストも安価になる。
When a waterproof sheet is stretched around a building under construction, a single worker can quickly and reliably stretch a plurality of steps in the lateral direction, and a short time is required. The work of mounting the seat can be performed at home. Therefore, the construction cost is also reduced.

【0055】このような防水シートの取付けは、建物周
囲に足場を仮設した場合のみならず、足場を設置する空
間部がない建物の密集地域においても、室内から手を延
ばすことによって確実に行うことができるようになる。
The installation of such a waterproof sheet is ensured not only when a scaffold is temporarily provided around the building but also in a densely populated area of a building where there is no space for installing the scaffold, by extending a hand from the room. Will be able to

【0056】防水シートは建物の周囲の横方向に何段に
も張りつけるものであるから、各シート間の重なり合い
による間隙は左右両側にはできないようになり、雨水が
横方向から内部に侵入することを確実に防止することが
できる。
Since the waterproof sheet is attached in a number of steps in the horizontal direction around the building, a gap due to the overlapping between the sheets cannot be formed on both the left and right sides, and rainwater enters the inside from the horizontal direction. Can be reliably prevented.

【図面の簡単な説明】[Brief description of the drawings]

【図1】一装置による施工時の斜視図FIG. 1 is a perspective view at the time of construction by one device.

【図2】要部の拡大斜視図FIG. 2 is an enlarged perspective view of a main part.

【図3】要部の斜視図FIG. 3 is a perspective view of a main part.

【図4】要部の正断面図FIG. 4 is a front sectional view of a main part.

【図5】要部の側断面図FIG. 5 is a side sectional view of a main part.

【図6】要部の正面図FIG. 6 is a front view of a main part.

【図7】要部の斜視図FIG. 7 is a perspective view of a main part.

【図8】他例要部の平断面図FIG. 8 is a plan sectional view of a main part of another example.

【図9】他装置による施工時の建物の正面図FIG. 9 is a front view of a building during construction by another device.

【図10】要部の斜視図FIG. 10 is a perspective view of a main part.

【図11】要部の拡大斜視図FIG. 11 is an enlarged perspective view of a main part.

【図12】要部の側断面図FIG. 12 is a side sectional view of a main part.

【図13】要部の正面図FIG. 13 is a front view of a main part.

【図14】要部の斜視図FIG. 14 is a perspective view of a main part.

【図15】他例要部の正面図FIG. 15 is a front view of a main part of another example.

【図16】図15の側面図FIG. 16 is a side view of FIG.

【符号の説明】[Explanation of symbols]

1 足場装置 5 ブラケット 6 ハンガーレール 7,7 ハンガーロール 8 バランサー凾体 9 ワイヤロープ 11 ドラム 14 ブレーキホィール 15 ブレーキワイヤ 17 調節螺子 18 クラッチ 19 巻取リール 20・・ 小リール 26 防水シート取付具 28 管体 30 調整杆 31 調整螺子 32 上部可動軸 36 下部固定軸 37 ロール状防水シート 38 吊環 51 レールブラケット 52 ハンガーレール 53,53 ハンガーロール 55 チェーンホィールブラケット 57 チェーンホィールケース 58 支軸 60 チェーンホィール 61 チェーン 64 ブレーキホィール 70 防水シート取付具 72 管体 74 調整杆 75 調整螺子 76 上部可動軸 79 下部固定軸 80 ロール状防水シート 81,81 掛止め用フック DESCRIPTION OF SYMBOLS 1 Scaffolding device 5 Bracket 6 Hanger rail 7, 7 Hanger roll 8 Balancer housing 9 Wire rope 11 Drum 14 Brake wheel 15 Brake wire 17 Adjustment screw 18 Clutch 19 Take-up reel 20 Small reel 26 Waterproof sheet fixture 28 Pipe Reference Signs List 30 Adjusting rod 31 Adjusting screw 32 Upper movable shaft 36 Lower fixed shaft 37 Roll-shaped waterproof sheet 38 Suspension ring 51 Rail bracket 52 Hanger rail 53, 53 Hanger roll 55 Chain wheel bracket 57 Chain wheel case 58 Support shaft 60 Chain wheel 61 Chain 64 Brake Wheel 70 Waterproof sheet attachment 72 Pipe 74 Adjusting rod 75 Adjusting screw 76 Upper movable shaft 79 Lower fixed shaft 80 Rolled waterproof sheet 81, 81 Hook for hooking

───────────────────────────────────────────────────── フロントページの続き (72)発明者 洞口 貴昭 東京都千代田区丸の内2丁目1番2号 旭 硝子株式会社内 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Takaaki Doroguchi Asahi Glass Co., Ltd. 2-1-2 Marunouchi, Chiyoda-ku, Tokyo

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 建築中の建物の上位部に架設したハンガ
ーレールに吊下部材を横方向に移動可能に吊設し、この
吊下部材に防水シート取付具を取付け、この防水シート
取付具を前記吊下部材に設けたブレーキにより建物周囲
の任意高さに停止し、前記防水シート取付具に用意した
ロール状防水シートを横方向に張付けることを特徴とす
る建築工事における防水シート施工法。
1. A hanging member is suspended on a hanger rail erected above a building under construction so as to be movable in a lateral direction, and a waterproof sheet attachment is attached to the hanging member. A method of constructing a waterproof sheet in a construction work, comprising: stopping at an arbitrary height around a building by a brake provided on the suspension member, and attaching a roll-shaped waterproof sheet prepared on the waterproof sheet attachment in a lateral direction.
【請求項2】 建物周囲に仮設した支柱間の上位部に横
方向にハンガーレールを架設し、このハンガーレールに
移動輪を設けたバランサー凾体を吊設し、この凾体の内
部に設けたドラムにロープを捲回するとともにブレーキ
を併設し、前記ロープの下端部に防水シート取付具を着
脱し得るように設け、この防水シート取付具にはロール
状防水シートを横方向に張付けるようにする建築工事に
おける防水シートの施工装置。
2. A hanger rail is erected in a lateral direction on an upper portion between columns temporarily provided around the building, and a balancer housing provided with moving wheels is hung on the hanger rail, and provided inside the housing. A rope is wound around the drum and a brake is also provided.A waterproof sheet attachment is provided at the lower end of the rope so that a waterproof sheet attachment can be attached to and detached from the rope. Construction equipment for waterproof sheets in building construction.
【請求項3】 建物の各支柱間の上位部に横方向にハン
ガーレールを架設し、このハンガーレールに移動輪を設
けたバランサー凾体を吊設し、この凾体の内部に設けた
ホィールにチェーンを捲回するとともにブレーキ機構を
併設し、前記チェーンの両端部に防水シート取付具を着
脱し得るように設け、この防水シート取付具にはロール
状防水シートを横方向に張付けるようにする建築工事に
おける防水シート施工装置。
3. A hanger rail is laterally mounted on an upper portion between the columns of the building, and a balancer housing provided with moving wheels is hung on the hanger rail, and a wheel provided inside the housing is mounted on a hanger rail. A chain is wound and a brake mechanism is also provided, and a waterproof sheet attachment is provided at both ends of the chain so as to be detachable, and a roll-shaped waterproof sheet is attached to the waterproof sheet attachment in a lateral direction. Waterproof sheet construction equipment in building construction.
JP12468097A 1997-04-30 1997-04-30 Execution method of waterproofing sheet in building construction and execution device Pending JPH10306593A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12468097A JPH10306593A (en) 1997-04-30 1997-04-30 Execution method of waterproofing sheet in building construction and execution device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12468097A JPH10306593A (en) 1997-04-30 1997-04-30 Execution method of waterproofing sheet in building construction and execution device

Publications (1)

Publication Number Publication Date
JPH10306593A true JPH10306593A (en) 1998-11-17

Family

ID=14891421

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12468097A Pending JPH10306593A (en) 1997-04-30 1997-04-30 Execution method of waterproofing sheet in building construction and execution device

Country Status (1)

Country Link
JP (1) JPH10306593A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008088771A (en) * 2006-10-05 2008-04-17 Ykk Ap株式会社 Waterproof sheet construction tool, and construction method of waterproof sheet using the tool
GB2496579A (en) * 2011-10-24 2013-05-22 Jay Jones A device for holding and laying out sheeting for covering scaffolding
JP2013129526A (en) * 2011-12-22 2013-07-04 Ohbayashi Corp Drop device of wire rod of lift-up device and drop method of wire rod in lift-up technique
JP5577560B1 (en) * 2013-04-01 2014-08-27 株式会社ナカヤ Portable holder for tarpaulin roll
CN107642242A (en) * 2017-08-31 2018-01-30 中国建筑第六工程局有限公司 A kind of light instrument for being used to install seal ring or sealing piece

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008088771A (en) * 2006-10-05 2008-04-17 Ykk Ap株式会社 Waterproof sheet construction tool, and construction method of waterproof sheet using the tool
GB2496579A (en) * 2011-10-24 2013-05-22 Jay Jones A device for holding and laying out sheeting for covering scaffolding
JP2013129526A (en) * 2011-12-22 2013-07-04 Ohbayashi Corp Drop device of wire rod of lift-up device and drop method of wire rod in lift-up technique
JP5577560B1 (en) * 2013-04-01 2014-08-27 株式会社ナカヤ Portable holder for tarpaulin roll
CN107642242A (en) * 2017-08-31 2018-01-30 中国建筑第六工程局有限公司 A kind of light instrument for being used to install seal ring or sealing piece
CN107642242B (en) * 2017-08-31 2023-07-21 中国建筑第六工程局有限公司 Simple tool for installing water stop ring or water stop sheet

Similar Documents

Publication Publication Date Title
US6464190B1 (en) Self-winding-type fixture-lifting/lowering device
JP5771829B2 (en) Temporary guide rail fixing device
KR100877418B1 (en) Automatic wind pressure control banner
JPH10306593A (en) Execution method of waterproofing sheet in building construction and execution device
JP3203591B2 (en) Work floor temporary equipment
KR200392826Y1 (en) Safety net system for protecting falling
JP2001282131A (en) Pdp mounting device
JP3479734B2 (en) Method and apparatus for hanging installation of air conditioner outdoor unit
JPH11131959A (en) Wire rope suspension ladder device
CN219431324U (en) Tile roof assembly installation auxiliary structure
JP3051359B2 (en) Safe building work methods and safe building work tools
JPS6341008Y2 (en)
JPH09144327A (en) Outside protection system in construction of multistoried building
JP3632512B2 (en) Installation method of air conditioner outdoor unit
JP7560828B2 (en) Ceiling reinforcement structure and ceiling reinforcement method
KR100553666B1 (en) Steel plate mounting
JPH0341989A (en) Suspender used for large space construction
KR200237756Y1 (en) Placard A Rack System
JP2811279B2 (en) Work gondola
JP3231930B2 (en) Lifeline routing structure in a horizontally movable gondola device
JPH08280987A (en) Cloth drying structure
JP3472425B2 (en) Retractable baseball back net for large dome
CN212774105U (en) Escape ladder
JP2000213175A (en) All-weather outdoor scaffold and method of extending a sheet on the scaffold
JPH0570078U (en) Video projector with lifting device