JPH0941645A - Connecting construction of drain pipe for building - Google Patents

Connecting construction of drain pipe for building

Info

Publication number
JPH0941645A
JPH0941645A JP7215221A JP21522195A JPH0941645A JP H0941645 A JPH0941645 A JP H0941645A JP 7215221 A JP7215221 A JP 7215221A JP 21522195 A JP21522195 A JP 21522195A JP H0941645 A JPH0941645 A JP H0941645A
Authority
JP
Japan
Prior art keywords
pipe
flare
drain pipe
drainage
drainage pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7215221A
Other languages
Japanese (ja)
Other versions
JP2906224B2 (en
Inventor
Yoshio Urabe
良雄 占部
Masao Kanazawa
政夫 金沢
Kazuhiro Fujita
和弘 藤田
Toshio Itagaki
登志雄 板垣
Yukio Kumakura
幸雄 熊倉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIYUNESU KK
KANTO KIKO KK
Benkan Corp
Original Assignee
JIYUNESU KK
KANTO KIKO KK
Benkan Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIYUNESU KK, KANTO KIKO KK, Benkan Corp filed Critical JIYUNESU KK
Priority to JP7215221A priority Critical patent/JP2906224B2/en
Publication of JPH0941645A publication Critical patent/JPH0941645A/en
Application granted granted Critical
Publication of JP2906224B2 publication Critical patent/JP2906224B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L21/00Joints with sleeve or socket

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Sink And Installation For Waste Water (AREA)
  • Flanged Joints, Insulating Joints, And Other Joints (AREA)

Abstract

PROBLEM TO BE SOLVED: To facilitate a repairing work by connecting connections on the upper stream side of drain pipes penetrating floors of respective stories with insert flare joints, and connecting connections on the lower stream side of drain pipes with flare flange joints. SOLUTION: Connection on the upper stream side of a drain pipe 3 provided between drain pipes 1 penetrating the floors of respective stories of a building is connected to the lower stream side of the of the drain pipe 1 of the upper story through an insert flare joint 4. Further, connection on the lower stream side of the drain pipe 3 is connected to the upper stream side of the drain pipe 1 of the lower story through a flare flange joint 12, a hing band is fitted so as to fasten through bolt/nut. Next, in the case of a cleaning and improving work, the insert flare joint on the upper stream side and the hinge band of the flare flange joint 12 on the lower stream side are detached, and packing 16 is detached so as to detach the drain pipe 3. Consequently, the drain pipe can be fitted and detached only in a specified story so as to execute a piping work.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、建築用排水管の接
続構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a connecting structure for a drainage pipe for construction.

【0002】[0002]

【従来の技術】一般に排水管は、自然重力による流送法
を採用しており、管内部に突起物が出ない図7に示すよ
うな差込み継手Jによって排水管Pが接続されている。
然し乍ら、上記のような差込み継手Jによる排水管Pの
接続では、差込み代分の管長Lが重複する為、排水管P
を一部切断しなければ容易に取り出すことができず、復
旧の際にもこれまでと同じ寸法の排水管Pを使用するこ
とができず、図8のaに示すように短い排水管P′の上
端の拡径部Wを上階の排水管Pの下端部に嵌装し、下階
の排水管Pの上端の拡径部Wに図8のbに示すように短
管Sの下端部を嵌入し、この短管Sの上端部と短い排水
管P′の下端部とをバンド型継手Bにて接続する手段が
採られていた。従って、復旧の手間暇がかかるばかりで
なく、新たな資材を必要としていた。
2. Description of the Related Art Generally, a drainage pipe adopts a natural gravity flow method, and a drainage pipe P is connected by a plug-in joint J as shown in FIG.
However, in the connection of the drainage pipe P by the insertion joint J as described above, since the pipe length L for the insertion allowance overlaps, the drainage pipe P
It cannot be easily taken out unless a part of it is cut, and the drain pipe P of the same size as before can not be used at the time of restoration, and as shown in FIG. The enlarged diameter portion W of the upper end of the short pipe S is fitted to the lower end portion of the drainage pipe P of the upper floor, and the enlarged diameter portion W of the upper end of the drainage pipe P of the lower floor is fitted to the lower end portion of the short pipe S as shown in FIG. A means for connecting the upper end portion of the short pipe S and the lower end portion of the short drain pipe P ′ with the band type joint B has been adopted. Therefore, it not only takes time and effort for recovery, but also requires new materials.

【0003】[0003]

【発明が解決しようとする課題】そこで本発明は、建築
用排水管の施工に際し、新設時には任意の階からの施工
ができ、改修,清掃工事の際には、特定の階のみ容易に
排水管の脱着が可能な接続構造を提供しようとするもの
である。
SUMMARY OF THE INVENTION Therefore, in the present invention, when constructing a drainage pipe for construction, it can be constructed from any floor at the time of new construction, and at the time of renovation and cleaning work, only the drainage pipe can be easily drained. It is intended to provide a connection structure that can be attached and detached.

【0004】[0004]

【課題を解決するための手段】上記課題を解決するため
の本発明の建築用排水管の接続構造は、建物の各階の床
を貫通している排水管の間に配設する排水管の上流側の
接続を、差込みフレアー継手により接続し、下流側の接
続を、フレアーフランジ継手により接続したことを特徴
とするものである。
In order to solve the above-mentioned problems, the connection structure for a drainage pipe for construction according to the present invention is an upstream drainage pipe arranged between drainage pipes penetrating a floor of each floor of a building. The connection on the side is connected by a plug-in flare joint, and the connection on the downstream side is connected by a flare flange joint.

【0005】[0005]

【発明の実施の形態】上記のような本発明の建築用排水
管の接続構造によると、排水管の上流側が差込みフレア
ー継手用のフレアー加工されている為、建物の床を貫通
している排水管の下流側は無加工の管端となり、また排
水管の下流側がフレアーフランジ継手用のフレアーフラ
ンジ加工されている為、建物の床を貫通している排水管
の上流側はフレアーフランジ加工されている。
BEST MODE FOR CARRYING OUT THE INVENTION According to the drainage pipe connecting structure of the present invention as described above, since the upstream side of the drainage pipe is flared for the insertion flare joint, the drainage that penetrates the floor of the building The downstream side of the pipe is an unprocessed pipe end, and the downstream side of the drainage pipe is flared for flare flange joints, so the upstream side of the drainage pipe that penetrates the floor of the building is flared. There is.

【0006】従って、排水管は、上流側の差込みフレア
ー継手及び下流側のフレアーフランジ継手のバンドを外
し、下流側のパッキンを取り出せるだけの高さを上方に
押し上げ、パッキンを取り出した後、該排水管を横に振
ることにより、下方に引抜いて取り外すことができる。
また、復旧の際は、上記とは逆の手順により排水管を接
続して取り付けることができる。かくして、建築用排水
管は施工に際し、新設時、任意の階から施工することが
でき、改修,清掃工事する時は、特定の階のみ容易に排
水管を脱着することができる。
Therefore, for the drainage pipe, the bands of the upstream flare joint and the downstream flare flange joint are removed, the height at which the downstream packing can be taken out is raised upward, and after the packing is taken out, the drainage is removed. It can be removed by pulling it down by shaking the tube sideways.
In addition, at the time of restoration, the drainage pipe can be connected and attached in the reverse order of the above. Thus, when constructing a drainage pipe for construction, it can be constructed from any floor at the time of new construction, and at the time of renovation or cleaning work, the drainage pipe can be easily attached and detached only on a specific floor.

【0007】[0007]

【実施例】本発明の建築用排水管の接続構造の一実施例
を図によって説明すると、図1において、1は建物の各
階の床2を貫通し、管保持具(図示省略)にて簡易に固
定した排水管で、その排水管1の間に配設した排水管3
は、その上流側の接続を差込みフレアー継手4により上
階の排水管1の下流側に接続している。即ち、図2に示
すように排水管3の上端部のフレアー加工した拡径部5
を、無加工の排水管1の下端部に嵌装し、拡径部5の上
端のフレアーフランジ加工して得たフレアーフランジ6
に、予め排水管1の下端部外周に嵌装しておいたパッキ
ン7及びスペーサー8を重合して、パッキン7をフレア
ーフランジ6に嵌着し、これらフレアーフランジ6,パ
ッキン7,スペーサー8に蝶番バンド9を嵌着し、ボル
ト10,ナット11にて締付けて、気密に排水管3の上
流側と排水管1の下流側とを接続している。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the construction of a drainage pipe for construction according to the present invention will be described with reference to the drawing. In FIG. 1, reference numeral 1 indicates a floor 2 on each floor of the building, and a pipe holder (not shown) simplifies the construction. The drain pipe fixed to the drain pipe 3 disposed between the drain pipes 1.
Connects the upstream side thereof to the downstream side of the drainage pipe 1 on the upper floor by the insertion flare joint 4. That is, as shown in FIG. 2, the flared expanded portion 5 of the drain pipe 3 is flared.
Is fitted to the lower end of the unprocessed drain pipe 1, and the flare flange 6 obtained by processing the flare flange of the upper end of the expanded diameter portion 5
, The packing 7 and the spacer 8 which have been fitted on the outer periphery of the lower end portion of the drainage pipe 1 in advance are overlapped, and the packing 7 is fitted to the flare flange 6, and the flare flange 6, the packing 7 and the spacer 8 are hinged. The band 9 is fitted and tightened with bolts 10 and nuts 11 to hermetically connect the upstream side of the drainage pipe 3 and the downstream side of the drainage pipe 1.

【0008】また、排水管3は、その下流側の接続を図
1に示すようにフレアーフランジ継手12により下階の
排水管1の上流側に接続している。即ち、図3に示すよ
うに排水管3の下端のフレアーフランジ加工して得たフ
レアーフランジ13と、排水管1の上端のフレアーフラ
ンジ加工して得たフレアーフランジ14との間に、補強
リング15の外周面に固着して保持したパッキン16を
介在し、これらフレアーフランジ13,パッキン16,
フレアーフランジ14に蝶番バンド9を嵌着し、ボルト
10,ナット11にて締付けて、気密に排水管3の下流
側と排水管1の上流側とを接続している。
Further, the drainage pipe 3 is connected at its downstream side to the upstream side of the drainage pipe 1 on the lower floor by a flare flange joint 12 as shown in FIG. That is, as shown in FIG. 3, the reinforcing ring 15 is provided between the flare flange 13 obtained by processing the flare flange at the lower end of the drainage pipe 3 and the flare flange 14 obtained by processing the flare flange at the upper end of the drainage pipe 1. The flaring flange 13, packing 16,
The hinge band 9 is fitted to the flare flange 14 and is tightened with bolts 10 and nuts 11 to hermetically connect the downstream side of the drain pipe 3 and the upstream side of the drain pipe 1.

【0009】この実施例の建築用排水管の接続構造によ
ると、排水管3は、上流側の差込みフレアー継手4及び
下流側のフレアーフランジ継手12の各蝶番バンド9を
取り外し、下流側のフレアーフランジ継手12における
パッキン16を取り出せるだけの高さを上方に押し上
げ、パッキン16を取り出した後、該排水管3を図4に
示すように横に振ることにより、下方に引抜いて取り外
せる。こうして各階の床2を貫通固定した排水管1間に
配設した排水管3を引抜いて取り外すことにより、床2
を貫通固定した排水管1も、その固定を解いて、上方に
引き上げることにより取り外せる。また、復旧の際は、
上記とは逆の手順により排水管1,排水管3を接続して
取り付けることができる。勿論、新設の際も同様であ
る。
According to the construction drainage pipe connection structure of this embodiment, the drainage pipe 3 has the upstream flare joint 4 and the downstream flare flange joint 12 with the hinge bands 9 removed, and the downstream flare flange. After the packing 16 of the joint 12 is pushed up to a height high enough to take out the packing 16 and the packing 16 is taken out, the drain pipe 3 is shaken sideways as shown in FIG. In this way, the drain pipes 3 arranged between the drain pipes 1 that penetrate and fix the floor 2 of each floor are pulled out and removed to remove the floor 2
The drainage pipe 1 that has been fixed through can also be removed by releasing the fixation and pulling it upward. Also, at the time of restoration,
The drain pipe 1 and the drain pipe 3 can be connected and attached in the reverse order of the above. Of course, the same applies when a new installation is made.

【0010】次に本発明の建築用排水管の接続構造の他
の実施例を図によって説明すると、図5において、1′
は建物の各階の床2を貫通し、床2上に立設した管保持
具17に保持した排水集合管で、この排水集合管1′の
外周には床2の直上で分岐導入口18が横向きに一体に
形成されている。各階の排水集合管1′の間に上下二段
に排水管3′,3″が配設されている。上段の排水管
3′は、その上流側を前述の図2に示される差込みフレ
アー継手4により上階の排水集合管1′の下流側に接続
している。また、上段の排水管3′は、その下流側を前
述の図3に示されるフレアーフランジ継手12により下
段の排水管3″の上流側に接続している。そして下段の
排水管3″はその下流側を前述の図3に示されるフレア
ーフランジ継手12により下階の排水集合管1′の上流
側に接続している。
Next, another embodiment of the construction of the drainage pipe for construction according to the present invention will be described with reference to the drawing.
Is a drainage collecting pipe that passes through the floor 2 of each floor of the building and is held by a pipe holder 17 standing on the floor 2, and a branch inlet 18 is provided on the outer periphery of the drainage collecting pipe 1 ′ immediately above the floor 2. It is integrally formed laterally. The drainage pipes 3 ', 3 "are arranged in upper and lower two stages between the drainage collection pipes 1'on each floor. The drainage pipe 3'of the upper stage has its upstream side inserted into the insertion flare joint shown in FIG. 4 is connected to the downstream side of the drainage collecting pipe 1'of the upper floor. Further, the drainage pipe 3'of the upper stage has its downstream side connected to the drainage pipe 3 of the lower stage by the flare flange joint 12 shown in FIG. ″ Is connected to the upstream side. The downstream side drainage pipe 3 ″ is connected to the upstream side of the drainage collection pipe 1 ′ on the lower floor by the flare flange joint 12 shown in FIG.

【0011】この実施例の建築用排水管の接続構造によ
ると、上段の排水管3′は、上流側の差込みフレアー継
手4及び下流側のフレアーフランジ継手12の各蝶番バ
ンド9を取り外し、下流側のフレアーフランジ継手12
におけるパッキン16を取り出せるだけの高さを上方に
押し上げ、パッキン16を取り出した後、該排水管3′
を図6に示すように横に振ることにより下方に引抜いて
取り出せる。また、下段の排水管3″は、下流側のフレ
アーフランジ継手12の蝶番バンド9を取り出すことに
より排水集合管1′との結合が解かれ、取り外せる。こ
うして各階の床2を貫通し、床2上の管保持具17に保
持した排水集合管1′間に配設した上下二段の排水管
3′,3″を取り外すことにより、管保持具17に保持
した排水集合管1′も管保持具17から解放して、上方
に引き上げることにより取り外せる。また、復旧の際
は、上記とは逆の手順により排水集合管1′、排水管
3″、排水管3′を接続して取り付けることができる。
勿論新設の場合も同様である。
According to the connection structure for the drainage pipe for construction of this embodiment, the upper drainage pipe 3'has the hinge bands 9 of the insert flare joint 4 on the upstream side and the flare flange joint 12 on the downstream side, and the downstream side. Flare Flange Joint 12
After the packing 16 is taken out, the drain pipe 3 '
6 can be pulled out and taken out by shaking it horizontally as shown in FIG. The lower drainage pipe 3 ″ can be removed by removing the hinge band 9 of the flare flange joint 12 on the downstream side, so that the drainage drainage pipe 3 ″ can be removed from the drainage collection pipe 1 ′. By removing the upper and lower two-stage drainage pipes 3 ', 3 "arranged between the drainage collecting pipes 1'held in the upper pipe holder 17, the drainage collecting pipe 1'held in the pipe holder 17 is also pipe-held. It can be removed by releasing it from the tool 17 and pulling it upward. Further, at the time of restoration, the drainage collecting pipe 1 ′, the drainage pipe 3 ″, and the drainage pipe 3 ′ can be connected and attached in the reverse order of the above.
Of course, the same applies to the case of new installation.

【0012】[0012]

【発明の効果】以上の説明で判るように本発明の建築用
排水管の接続構造によれば、排水管内の清掃、排水管の
改修において、所要の特定の階のみ排水管の脱着が容易
にできるので、清掃及び改修工事が簡単化し、工期を短
縮できる。また、新設、復旧において、他の階の排水管
に影響されずに、任意の階から排水管の配管施工ができ
るので、建築工程に左右されずに独立して配管施工工程
を組むことができ、工期を短縮できる。
As can be seen from the above description, according to the construction structure of the drainage pipe for construction of the present invention, the drainage pipe can be easily attached / detached only on the required specific floor in cleaning the drainage pipe or repairing the drainage pipe. As a result, cleaning and repair work can be simplified and the construction period can be shortened. Also, in new construction and restoration, drainage pipes can be installed from any floor without being affected by drainage pipes on other floors, so it is possible to independently construct a pipe construction process regardless of the construction process. , The construction period can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の建築用排水管の接続構造の一実施例を
示す図である。
FIG. 1 is a diagram showing an embodiment of a connection structure for a drainage pipe for construction according to the present invention.

【図2】図1のA部拡大断面図である。FIG. 2 is an enlarged cross-sectional view of part A in FIG.

【図3】図1のB部拡大断面図である。FIG. 3 is an enlarged sectional view of a portion B in FIG. 1;

【図4】図1の建築用排水管の接続構造に於いて、排水
管を取外す時の状態を示す図である。
FIG. 4 is a view showing a state when the drainage pipe is removed in the construction drainage pipe connection structure of FIG. 1;

【図5】本発明の建築用排水管の接続構造の他の実施例
を示す図である。
FIG. 5 is a view showing another embodiment of the connection structure for the drainage pipe for construction according to the present invention.

【図6】図5の建築用排水管の接続構造に於いて、排水
管を取外す時の状態を示す図である。
FIG. 6 is a view showing a state when the drainage pipe is removed in the construction drainage pipe connection structure of FIG. 5;

【図7】差込み継手を示す縦断面図である。FIG. 7 is a vertical cross-sectional view showing a plug joint.

【図8】従来の排水管の復旧接続方法を示すもので、a
は復旧開始時の状態、bは復旧後の状態を示すものであ
る。
FIG. 8 shows a conventional drainage pipe restoration connection method.
Indicates a state at the start of restoration, and b indicates a state after restoration.

【符号の説明】[Explanation of symbols]

1 各階の床に貫通した排水管 1′ 各階の床に貫通した排水集合管 2 床 3,3′,3″ 排水管 4 差込みフレアー継手 5 拡径部 6 フレアーフランジ 7 パッキン 8 スペーサー 9 蝶番バンド 10 ボルト 11 ナット 12 フレアーフランジ継手 13,14 フレアーフランジ 15 補強リング 16 パッキン 17 管保持具 18 分岐導入口 1 Drain pipe penetrating the floor of each floor 1'Drainage collecting pipe penetrating the floor of each floor 2 Floors 3, 3 ', 3 "Drain pipe 4 Insert flare joint 5 Expanding part 6 Flare flange 7 Packing 8 Spacer 9 Hinge band 10 Bolt 11 Nut 12 Flare flange joint 13,14 Flare flange 15 Reinforcement ring 16 Packing 17 Pipe holder 18 Branch inlet

───────────────────────────────────────────────────── フロントページの続き (72)発明者 金沢 政夫 東京都大田区山王2丁目5番13号 株式会 社ベンカン内 (72)発明者 藤田 和弘 東京都大田区山王2丁目5番13号 株式会 社ベンカン内 (72)発明者 板垣 登志雄 群馬県桐生市相生町2丁目889番地3 関 東機工株式会社内 (72)発明者 熊倉 幸雄 新潟県新潟市弁天橋通1丁目2番34号 ジ ュネス株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Masao Kanazawa 2-5-13 Sanno, Ota-ku, Tokyo Stock company Benkan (72) Inventor Kazuhiro Fujita 2-5-13 Sanno, Ota-ku, Tokyo Stock association Company Benkan (72) Inventor Toshio Itagaki 2-889, Aioi-cho, Kiryu-shi, Gunma Kanto Kiko Co., Ltd. (72) Inventor Yukio Kumakura 1-2-34 Bentenbashi Dori, Niigata City, Niigata Prefecture In the company

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 建物の各階の床を貫通している排水管の
間に配設する排水管の上流側の接続を、差込みフレアー
継手により接続し、下流側の接続を、フレアーフランジ
継手により接続したことを特徴とする建築用排水管の接
続構造。
1. A drainage pipe, which is disposed between drainage pipes that penetrate the floors of each floor of a building, is connected at the upstream side by a plug flare joint, and at the downstream side by a flare flange joint. The connection structure of the drainage pipe for construction characterized by the above.
JP7215221A 1995-08-01 1995-08-01 Construction drainage pipe connection structure Expired - Fee Related JP2906224B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7215221A JP2906224B2 (en) 1995-08-01 1995-08-01 Construction drainage pipe connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7215221A JP2906224B2 (en) 1995-08-01 1995-08-01 Construction drainage pipe connection structure

Publications (2)

Publication Number Publication Date
JPH0941645A true JPH0941645A (en) 1997-02-10
JP2906224B2 JP2906224B2 (en) 1999-06-14

Family

ID=16668713

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7215221A Expired - Fee Related JP2906224B2 (en) 1995-08-01 1995-08-01 Construction drainage pipe connection structure

Country Status (1)

Country Link
JP (1) JP2906224B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013087513A (en) * 2011-10-19 2013-05-13 Sankyotateyama Inc Simple building
JP2019007136A (en) * 2017-06-20 2019-01-17 積水化学工業株式会社 Rainwater draining device
JP2021028539A (en) * 2019-08-09 2021-02-25 株式会社三五 Construction piping system and construction method of the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013087513A (en) * 2011-10-19 2013-05-13 Sankyotateyama Inc Simple building
JP2019007136A (en) * 2017-06-20 2019-01-17 積水化学工業株式会社 Rainwater draining device
JP2021028539A (en) * 2019-08-09 2021-02-25 株式会社三五 Construction piping system and construction method of the same

Also Published As

Publication number Publication date
JP2906224B2 (en) 1999-06-14

Similar Documents

Publication Publication Date Title
RU2157481C1 (en) Lining pipe
CA2051258A1 (en) Flexible drainage trap
JPH0941645A (en) Connecting construction of drain pipe for building
US6739800B2 (en) Self-flushing gutter pipe
KR20190094676A (en) A connecting device for drainpipe of the bridge
KR101903658B1 (en) sedimentation tank construction method
US6701965B1 (en) Waste pipe repair insert
AU2006100723A4 (en) Rainhead Arrangement
JP4010844B2 (en) Pipe-in-pipe method and pipe-in-pipe method execution device
JPH09217887A (en) Water removal method in gas pipe
JP3372817B2 (en) Drainage collecting pipe
JP2002121791A (en) Method for forming drainage channel and drainage channel device
CN215802116U (en) Sewage pipes
JPH08105086A (en) Connecting structure of vertical drain pipe
JPS62194336A (en) Gathering pipe joint of drain system
JPS638252B2 (en)
JP7590276B2 (en) Drainage device and drainage method
JP3178594B2 (en) Outer auxiliary pipe member for manhole
CN206845164U (en) A kind of simple change flow velocity deslagging device
CN216007190U (en) Conveniently dismantle water supply and drainage pipeline of taking filter equipment
JPH0813520A (en) Slope reinforcement drainage pipe
JP2523699B2 (en) Drainage system for buildings
CN211772818U (en) Municipal administration bridge drainage structures
JP2005171483A (en) Method for connecting draining member in bathtub with divided wash place
JP4088113B2 (en) Sewage with vacuum valve

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees