JPH0877278A - Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule - Google Patents

Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule

Info

Publication number
JPH0877278A
JPH0877278A JP23600194A JP23600194A JPH0877278A JP H0877278 A JPH0877278 A JP H0877278A JP 23600194 A JP23600194 A JP 23600194A JP 23600194 A JP23600194 A JP 23600194A JP H0877278 A JPH0877278 A JP H0877278A
Authority
JP
Japan
Prior art keywords
plan
production
period
material procurement
follow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP23600194A
Other languages
Japanese (ja)
Inventor
Yoshio Ninomiya
ノ 宮 良 夫 二
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP23600194A priority Critical patent/JPH0877278A/en
Publication of JPH0877278A publication Critical patent/JPH0877278A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE: To make various activities, accompanying the production of the material preparation schedule, process schedule, etc., as stable as possible by providing a variation permissible range for absorbing variation of the material preparation schedule and process schedule accompanying variation of the product schedule of a product. CONSTITUTION: The volume of inventories in an ordering lead time period is calculated from the varying production schedule of the product, the preparation schedule for materials which are already ordered, and the process schedule, and compared with the 'variation permissible range of inventories' per day which is set by materials. Then when the daily volume of inventories is within the 'variation permissible range of the inventories' per day, the preparation schedule for the materials which are already ordered and the process schedule are unchanged. When the daily volume of inventories exceeds the 'variation permissible range of the inventories', on the other hand, the preparation schedule for the materials which are already ordered and the process schedule are varied on the day.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、資材調達計画や工程計
画等の生産に伴う諸活動を生産計画の変動に対して安定
化させる方法に関し、特に生産計画が変動する場合にあ
っても、それらの諸活動を可及的に安定化させる方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for stabilizing various activities associated with production, such as a material procurement plan and a process plan, against changes in the production plan, and particularly when the production plan changes. It relates to a method of stabilizing those activities as much as possible.

【0002】[0002]

【従来の技術】従来より、製造業にあっては、製品の生
産において、まず生産計画を作成して、この生産計画に
対応して、必要とする原材料や部品や加工完了品等の資
材を調達して、生産現場に供給する必要があった。 そ
こで、従来、必要な資材を供給する為、常に資材を計画
的に供給できるように、資材調達計画を作成していた。
2. Description of the Related Art Conventionally, in the manufacturing industry, in the production of products, first, a production plan is created, and in accordance with this production plan, necessary raw materials, parts, materials such as processed products are provided. It had to be procured and supplied to the production site. Therefore, conventionally, in order to supply the necessary materials, the material procurement plan has been prepared so that the materials can always be supplied systematically.

【0003】そして、従来、この資材調達計画を作成す
るための資材所要量の算出方法として、資材所要量計画
法(MRP=Material Requiremen
tsPlanning)が提案された。
[0003] Conventionally, as a method of calculating a material requirement amount for creating this material procurement plan, a material requirement amount planning method (MRP = Material Requirmen) is used.
tsPlanning) was proposed.

【0004】しかしながら、上記従来の「資材所要量の
算出方法」にあっては、個々の資材所要量の調達計画を
算出する場合、生産計画の変動を吸収するバッファの機
能を持たない為、生産計画が変動する度に資材調達計画
を変動させなければならないという問題点があった。
However, in the above-mentioned conventional "material requirement calculation method", when the procurement plan for each material requirement is calculated, since there is no buffer function for absorbing fluctuations in the production plan, There was a problem that the material procurement plan had to be changed every time the plan changed.

【0005】この方法を実例に基づいて例示すると、次
のようになる。 日付 1 2 3 4 5 6 7 8 9 10 Aの 生産計画 11 12 13 14 15 Aの 計画変更 +3 ー2 Xの 調達計画 11 12 13 14 15 Xの 変更計画 +3 ー2 上記実例の場合、説明を簡単にするため、製品Aは、X
とYとの2種類の部品からなり、しかも該2種類の部品
X、Yが製品Aを生産するために使用する当日の1日前
に入手する必要があるものとする。
This method will be illustrated below based on an actual example. Date 1 2 3 4 5 6 7 8 9 9 10 A production plan 11 12 13 14 15 A plan change + 3-2 X procurement plan 11 12 13 14 15 X change plan + 3-2 In the case of the above example, please explain. For simplicity, product A is X
It is assumed that it must be obtained one day before the day on which the two types of parts X and Y are used for producing the product A.

【0006】そして、そのうち該部品Xだけを取上げる
ものとする。
Then, only the part X is taken up.

【0007】また、該部品Xは、ロットまとめして発注
する必要はないものとする。
The parts X do not have to be ordered in a batch.

【0008】しかしながら、従来の「資材調達計画算出
方法」では、製品の生産計画の数量が増減すると、この
ように資材調達計画も変動させなければならないという
問題点があった。
However, the conventional “material procurement plan calculation method” has a problem that the material procurement plan must be changed in this way when the quantity of the product production plan increases or decreases.

【0009】また、製品の生産計画の時期が変化して
も、全く同様に資材調達計画も変動していた。
Further, even if the timing of the product production plan changes, the material procurement plan also changes in the same manner.

【0010】いまここで、「生産するために使用する時
期」を「必要時期」と呼ぶと、「必要時期に対して何日
か前に入手する必要がある期間」を「追上げ期間」と呼
ぶことにする。
Now, when the "time to use for production" is called the "necessary time", the "period necessary to obtain a few days before the required time" is referred to as the "chasing period". I will call it.

【0011】従来の計算方法の中にも、「必要時期」に
対して、「追上げ期間」遡り計算をして資材調達計画を
計算する機能があった。
Among the conventional calculation methods, there is a function of calculating a material procurement plan by performing a retroactive calculation of a "follow-up period" with respect to a "required time".

【0012】しかしながら、従来の「資材調達計画算出
方法」の中では、それを一律に扱っていた為、製品の生
産計画の時期が変動すると、資材調達計画の時期もそれ
に従って変動させなければならないという問題点があっ
た。
However, in the conventional "material procurement plan calculation method", since it is handled uniformly, if the time of the production plan of the product changes, the time of the material procurement plan must be changed accordingly. There was a problem.

【0013】それを実例で示すと、次のようになる。 日付 1 2 3 4 5 6 7 8 9 10 Aの 生産計画 11 12 13←13 14→14 15 Aの 計画変更 Xの 調達計画 11 12 13←13 14→14 15 Xの 変更計画 次に、従来の算出方法の中でも、「安全在庫」と言う概
念があり、設定された「安全在庫」を常に確保するよう
な「資材所要量の調達計画」を計算していた。
An example of this is as follows. Date 1 2 3 4 5 6 7 8 9 9 10 A production plan 11 12 13 ← 13 14 → 14 15 A plan change X procurement plan 11 12 13 ← 13 14 → 14 15 X change plan Next, conventional Among the calculation methods, there is the concept of "safety stock", and a "procurement plan for material requirements" that always secures the set "safety stock" was calculated.

【0014】この際、調達計画算出期間の「先頭在庫」
と、「安全在庫」とを比較して、「安全在庫」に近付け
るよう資材調達計画の数量を調整し、資材調達計画を算
出していた。
At this time, the "leading stock" in the procurement plan calculation period
And "safety stock" were compared, and the quantity of the material procurement plan was adjusted so as to approach "safety stock", and the material procurement plan was calculated.

【0015】この方法を実例に基づいて例示すると、次
のようになる。 日付 1 2 3 4 5 6 7 8 9 10 Aの 生産計画 11 12 13 14 15 Xの 必要数 11 12 13 14 15 Xの 調達計画 13 12 13 14 15 Xの初期在庫=8とすると Xの 在庫量 10 10 10 10 10 10 10 10 10 10 上記実例では、部品Xの「安全在庫」が10であり、
「初期在庫」が8の場合、第1日目に製品Xの在庫が
「安全在庫」になるように、製品Xの必要数に対して資
材調達数を+2分だけ調整して、資材調達計画を算出す
る。
This method will be illustrated below based on an actual example. Date 1 2 3 4 5 6 7 8 9 9 10 A production plan 11 12 13 14 15 X required quantity 11 12 13 14 15 X procurement plan 13 12 13 14 15 X initial inventory = 8 and X inventory quantity 10 10 10 10 10 10 10 10 10 10 10 In the above example, the “safety stock” of the part X is 10,
If the "initial stock" is 8, adjust the material procurement quantity by +2 minutes with respect to the required quantity of the product X so that the stock of the product X becomes "safety stock" on the first day. To calculate.

【0016】従来の計算方法では、資材の在庫を常に
「安全在庫」にするような資材調達計画を算出するだけ
であった。
In the conventional calculation method, the material procurement plan is always calculated so that the stock of the material is always "safe stock".

【0017】この為、前記実施例と同様に生産計画が変
動する度に資材調達計画を変動させなければならないと
いう問題点が依然としてあった。
Therefore, there is still a problem that the material procurement plan must be changed every time the production plan changes, as in the above-described embodiment.

【0018】上記説明の中の「資材所要量の調達計画」
は、材料を調達した後の様々な加工工程の工程計画にお
いても全く同じように言及することができ、生産計画の
変動によって資材調達計画も変動させなければならない
という問題点がある。
"Procurement plan for material requirements" in the above description
Can be referred to in the same manner even in the process plans of various processing steps after the material is procured, and there is a problem that the material procurement plan must be changed due to the change in the production plan.

【0019】この結果として、従来の方法の場合には、
製品の生産計画を変更し難く、需要の変動に迅速に対応
することが困難であるという問題点があった。
As a result of this, in the case of the conventional method,
There is a problem in that it is difficult to change the production plan of the product and it is difficult to quickly respond to changes in demand.

【0020】[0020]

【発明が解決しようとする課題】このような従来技術の
問題点に鑑み、本発明の主な目的は、原材料や部品等の
資材の手配を行う資材調達計画や加工工程の手配を行う
工程計画等の生産に伴う諸活動を行う場合にあって、製
品の生産計画が変動する場合にあっても、それら資材調
達計画や工程計画等のの生産に伴う諸活動を可及的に安
定化させることが出来る方法を提供することにある。
In view of the problems of the prior art, the main object of the present invention is to provide a material procurement plan for arranging materials such as raw materials and parts and a process plan for arranging processing steps. Even if the production plan of the product changes when various activities associated with production are performed, the various activities associated with production such as the material procurement plan and process plan are stabilized as much as possible. Is to provide a method that can.

【0021】[0021]

【課題を解決するための手段】このような目的は、本発
明によれば、製品を生産をするのに必要な原材料や部品
等の資材の手配を行う資材調達計画や製品を生産をする
のに必要な各加工工程の手配を行う工程計画等の生産に
伴う諸活動を行う場合にあって、該資材や工程等に変動
許容範囲を設け、資材や工程等を手配後に製品の生産計
画が変動する場合において、その変動により資材や工程
等に与える変化が、上記変動許容範囲の中に収まる場合
には、手配済の資材調達計画や工程計画等を変更せずに
そのままとする、ことを特徴とする資材調達計画や工程
計画等の生産に伴う諸活動を生産計画の変動に対して安
定化させる方法、を提供することにより達成される。
According to the present invention, such an object is to produce a material procurement plan and a product for arranging materials such as raw materials and parts necessary for producing a product. When carrying out various activities associated with production, such as a process plan for arranging each processing process required for the product, set a permissible range for fluctuations in the materials and processes, and make a production plan for the product after arranging the materials and processes. In the case of fluctuations, if the fluctuations that affect the materials and processes due to the fluctuations fall within the allowable range of fluctuations above, leave the material procurement plans and process plans that have already been arranged unchanged. This is achieved by providing a method for stabilizing various activities associated with production such as a characteristic material procurement plan and process plan against fluctuations in the production plan.

【0022】[0022]

【作用】本発明にあっては、製品の生産計画の変動に伴
う資材調達計画や工程計画の変動を吸収する「変動許容
範囲」(バッファ)を設けることで計算するものであ
る。
According to the present invention, the calculation is performed by providing a "variable allowable range" (buffer) that absorbs the variation of the material procurement plan and the process plan due to the variation of the production plan of the product.

【0023】本発明では、変動許容範囲を2種類設け
る。
In the present invention, two types of fluctuation allowable ranges are provided.

【0024】一つは、在庫に対する変動許容範囲であ
る。
One is a fluctuation allowable range for inventory.

【0025】これは、資材毎に最小在庫量(最低保持在
庫量)と、最大在庫量(許容最大在庫量)と言う基準値
を設け、計算の期間中資材の在庫が毎日最小在庫量以上
であり最大在庫量以下であれば、既に手配した資材調達
計画を変更しない。
This is to set a reference value such as a minimum inventory amount (minimum retained inventory amount) and a maximum inventory amount (allowable maximum inventory amount) for each material, and if the inventory of the material is more than the minimum inventory amount every day during the calculation period. Yes If it is less than the maximum inventory quantity, do not change the material procurement plan already arranged.

【0026】また、中間の加工工程が完了し、次の工程
に使用される前の状態を「仕掛り在庫」と呼ぶと、中間
の加工工程の工程計画においても、「仕掛り在庫」が計
算の期間中毎日最小在庫量と最大在庫量との範囲にあれ
ば、既に手配した工程計画を変更しない。
When the intermediate processing step is completed and the state before being used for the next step is called "work-in-process inventory", "work-in-process inventory" is calculated even in the process plan of the intermediate processing step. If it is within the range of the minimum inventory amount and the maximum inventory amount every day during the period, the process plan already arranged will not be changed.

【0027】二つ目は、「追上げ期間」に対する変動許
容範囲である。
The second is a fluctuation allowable range for the "follow-up period".

【0028】これは、資材毎に「手配前の追上げ期間」
と、「手配後の追上げ期間」と、2つの「追上げ期間」
を設ける。
This is the "follow-up period before arrangement" for each material.
And "the follow-up period after arrangement" and two "follow-up periods"
To provide.

【0029】該「手配後の追上げ期間」は、必要時期に
対して正味(最低限)必要な「追上げ期間」である。
The "follow-up period after arrangement" is a net (minimum) necessary "follow-up period" with respect to the required period.

【0030】また、「手配前の追上げ期間」は、「手配
後の追上げ期間」に対し、許容範囲分大きめな「追上げ
期間」とする。
Further, the "follow-up period before arrangement" is a "follow-up period" which is larger than the "follow-up period after arrangement" by an allowable range.

【0031】この為、資材調達計画や工程計画の手配を
するとき、許容範囲分余裕を持って追上げ計算をしてお
く。
Therefore, when arranging a material procurement plan or a process plan, a follow-up calculation should be made with a margin for the allowable range.

【0032】この際、手配後に製品の生産計画が前に繰
上がっても、その繰上げが許容範囲以下であれば、資材
調達計画を変更しない。
At this time, even if the production plan of the product is moved forward after the arrangement, if the advance is within the allowable range, the material procurement plan is not changed.

【0033】このように、本発明は、手配済の資材調達
計画や工程計画を製品の生産計画の変動に対して安定化
させる方法である。
As described above, the present invention is a method for stabilizing an arranged material procurement plan or process plan against fluctuations in the product production plan.

【0034】次に、これら2つの変動許容範囲の作用に
ついて説明する。
Next, the operation of these two allowable fluctuation ranges will be described.

【0035】まず、在庫に対する変動許容範囲の作用に
ついて説明する。
First, the effect of the fluctuation allowable range on the inventory will be described.

【0036】まず、既に資材調達計画や工程計画が手配
された後、製品の生産計画が変動して生産量が減少した
場合、資材や仕掛りの在庫は増加するが、最大在庫を越
えないときは、既に手配した資材調達計画や工程計画を
変更しない。
First, when the production plan of the product fluctuates and the production amount decreases after the material procurement plan and the process plan have already been arranged, the stock of materials and work-in-progress increases but the maximum stock is not exceeded. Does not change the already-procured material procurement plan or process plan.

【0037】なぜなら、それら資材や仕掛りは、次の生
産に使用すれば良く、一時的に在庫が増えるだけである
からである。
This is because these materials and work-in-process may be used for the next production, and the stock may temporarily increase.

【0038】次に、製品の生産計画が変動して生産量が
増大した場合、資材や仕掛りの在庫は減少するが、最小
在庫を下回らないときは、既に手配した資材調達計画や
工程計画を変更する必要はない。
Next, when the production plan of the product fluctuates and the production amount increases, the stock of materials and work-in-process decreases, but if the stock does not fall below the minimum stock, the already-procured material procurement plan or process plan is used. No need to change.

【0039】このようにして、製品の生産計画が変動し
て生産量が変動しても、それが変動許容範囲の範囲内な
らば既に手配した資材調達計画や工程計画を変更しない
ことが出来る。
In this way, even if the production plan of the product fluctuates and the production amount fluctuates, if it is within the fluctuation allowable range, the already-procured material procurement plan or process plan cannot be changed.

【0040】つづいて、「追上げ期間」に対する変動許
容範囲の作用について説明する。
Next, the operation of the fluctuation allowable range with respect to the "follow-up period" will be described.

【0041】まず、既に資材調達計画や工程計画が手配
された後、製品の生産計画が変動して生産時期が変動し
ても、後ろに繰下がる場合には、殆ど問題が発生しない
から、既に手配した資材調達計画や工程計画を変更しな
い。
First, after the material procurement plan and the process plan are already arranged, even if the production plan of the product fluctuates and the production time fluctuates, if it goes back, there will be almost no problem. Do not change the arranged material procurement plan or process plan.

【0042】なぜなら、資材や仕掛りの在庫が一時的に
増えるだけだから、後からそれを使えば良いだけだから
である。
This is because the stock of materials and work-in-process is only temporarily increased, and it is only necessary to use it later.

【0043】次に、製品の生産計画が変動して生産時期
が繰上がる場合には、資材の入手時期や工程の計画も早
めるように図らねばならない。
Next, when the production plan of the product fluctuates and the production period is advanced, it is necessary to plan the procurement period of the material and the process schedule.

【0044】しかし、本発明では、手配時に予め手配前
の追上げ期間分余裕を持って追上げ計算してあるから、
製品の生産計画の生産時期の繰上げ時期が変動許容範囲
(余裕期間)以下であれば、既に手配した資材調達計画
や工程計画を変更しない。
However, according to the present invention, since the follow-up calculation is made in advance with a margin for the follow-up period before the arrangement at the time of arrangement,
If the advancing time of the production time of the product production plan is equal to or less than the fluctuation allowable range (margin period), the material procurement plan or process plan already arranged is not changed.

【0045】このようにして、本発明は、在庫に対する
変動許容範囲と「追上げ期間」に対する変動許容範囲と
の2種類の変動許容範囲を設け、資材調達計画や工程計
画を手配した後、製品の生産計画が変動した場合にあっ
ても、それが許容範囲内であれば、資材調達計画や工程
計画を変更しない計算方法を用いることにより、資材調
達計画や工程計画を安定化させるのである。
In this way, the present invention provides two types of allowable fluctuation ranges, the allowable fluctuation range for the stock and the allowable fluctuation range for the "follow-up period", and after arranging the material procurement plan and the process plan, Even if the production plan fluctuates, if it is within the allowable range, the material procurement plan and the process plan are stabilized by using the calculation method that does not change the material procurement plan and the process plan.

【0046】[0046]

【実施例】次に、本発明の第一実施例について詳述す
る。
Next, the first embodiment of the present invention will be described in detail.

【0047】すなわち、本発明は、資材調達計画や工程
計画等の生産に伴う諸活動を生産計画の変動に対して安
定化させる方法である。
That is, the present invention is a method for stabilizing various activities associated with production such as a material procurement plan and a process plan against fluctuations in the production plan.

【0048】製造業においては、製品の生産計画に従
い、製品(生産物)を生産する場合、製品を生産をする
のに必要な原材料や部品等の資材を生産現場に常に過不
足なく供給することが必要であり、製品を生産をするの
に必要な原材料や部品等の資材の手配をタイミングよく
調達することが要求される。
In the manufacturing industry, when a product (product) is produced in accordance with a product production plan, raw materials and parts necessary for producing the product are always supplied to the production site without excess or deficiency. Therefore, it is required to procure raw materials and parts necessary for producing the product in a timely manner.

【0049】この際、原材料や部品等の資材を発注手配
してから現実に入手するまでには、「発注リードタイ
ム」と称する所定の期間が必要となる。
At this time, a predetermined period of time called "order lead time" is required from the time when the raw materials and parts are ordered to the time when they are actually obtained.

【0050】しかして、該「発注リードタイム」の間
に、製品の生産計画が変動する可能性がある。
However, the production plan of the product may change during the "ordering lead time".

【0051】該製品の生産計画が変動する要因として
は、次のようなものがある。 (1)新規顧客からの新しい注文。 (2)顧客からの出荷時期の繰上げ。 (3)販売実績の好調。 (4)出荷の変動。
The factors that change the production plan of the product are as follows. (1) New order from a new customer. (2) Advance shipment time from customers. (3) Strong sales results. (4) Fluctuations in shipping.

【0052】このような製品の生産計画が変動する場
合、タイムリに対応する必要があり、素早く対応しない
場合には次のような弊害を生ずる。 (1)販売チャンスを逃がす。 (2)顧客要求を満足できない。 (3)効率の良い生産ができない。
When the production plan of such a product fluctuates, it is necessary to deal with it in a timely manner. (1) Miss sales opportunities. (2) We cannot meet customer requirements. (3) Efficient production cannot be achieved.

【0053】この為、製品の生産計画が変動する場合に
は、該製品生産に必要な原材料や部品等の資材調達をタ
イミングよくすることが必要となる。
Therefore, when the production plan of the product changes, it is necessary to timely procure raw materials and parts necessary for the production of the product.

【0054】この際、本発明にあっては、製品を生産を
するのに必要な原材料や部品等の資材の手配を行う資材
調達計画や製品を生産をするのに必要な各加工工程の手
配を行う工程計画等の生産に伴う諸活動を行う場合にあ
って、該資材や工程等に「変動許容範囲」を設け、資材
や工程等を手配後に製品の生産計画が変動する場合にお
いて、その変動により資材や工程等に与える変化が、
「変動許容範囲」の中に収まる場合には、手配済の資材
調達計画や工程計画等を変更せずにそのままとすること
で、それらの変更に伴う処理の煩雑さや変更に伴う弊害
を回避するのである。
In this case, according to the present invention, a material procurement plan for arranging materials such as raw materials and parts necessary for producing the product and arrangement of each processing step necessary for producing the product When performing various activities associated with production such as a process plan, etc., when a "variable allowance range" is set for the material or process and the production plan of the product changes after arranging the material or process, Changes caused by changes in materials and processes,
If it falls within the "variable allowable range", the already-arranged material procurement plan and process plan are left unchanged, so that the complexity of the process and the adverse effects of the change are avoided. Of.

【0055】また、本発明にあっては、製品の生産計画
が変動しても、その変動により資材や工程等に与える変
化が、上記「変動許容範囲」を越える場合にあっても、
生産量が減少する場合や、生産時期が後ろに繰下る場合
には、資材や部材を次の生産に使用すれば良いから、手
配済みの資材調達計画や工程計画等を変更せずにそのま
まとすることで、事務処理の煩雑さを回避して、省力化
を図るのである。
Further, in the present invention, even if the production plan of the product fluctuates, even if the fluctuation causes changes in materials, processes and the like to exceed the above "variable allowable range",
When the production volume decreases or the production period is delayed, the materials and components can be used for the next production, so the arranged material procurement plan and process plan can be left unchanged. By doing so, the complexity of the paperwork is avoided and the labor is saved.

【0056】そして、製品の生産計画が変動して、その
変動により資材や工程等に与える変化が、上記「変動許
容範囲」を越える場合にあって、生産量が増大する場合
や、生産時期が前に繰上る場合には、初めて手配済みの
資材調達計画や工程計画等について、変更する必要性に
ついて検討するのである。
When the production plan of the product fluctuates, and the fluctuation causes changes in materials, processes, etc. to exceed the above "variable allowable range", the production amount increases or the production time is If it is carried forward, it is necessary to consider the need to change the material procurement plan, process plan, etc. that have been arranged for the first time.

【0057】すなわち、製品を生産をするのに必要な原
材料や部品等の資材の手配を行う資材調達計画や製品を
生産をするのに必要な各加工工程の手配を行う工程計画
等の生産に伴う諸活動を行う場合、製品の生産計画が変
動して、手配済の資材調達計画や工程計画に比べて、
「生産量が増大する場合」、または手配済の資材調達計
画や工程計画に比べて、「生産時期が前に繰上がる場
合」、手配済の資材調達計画や工程計画等について、変
更する必要性について検討するのである。
That is, for production of a material procurement plan for arranging materials such as raw materials and parts necessary for producing a product, and a process plan for arranging each processing step required for producing a product. When carrying out various activities that accompany it, the production plan of the product fluctuates, compared to the already-procured material procurement plan and process plan,
It is necessary to change "when the production volume increases" or "when the production period is advanced" compared to the arranged material procurement plan or process plan, the arranged material procurement plan or process plan, etc. Will be considered.

【0058】この際、本発明にあっては、製品の生産計
画の変動に伴う資材調達計画や工程計画の変動を吸収す
る「変動許容範囲」(バッファ)を設けることで対処す
る。
At this time, in the present invention, a "variation allowable range" (buffer) is provided to absorb the variation of the material procurement plan and the process plan due to the variation of the production plan of the product.

【0059】本発明では、この「変動許容範囲」を2種
類設けるのである。
In the present invention, two types of "variable allowable ranges" are provided.

【0060】一つは、「在庫に対する変動許容範囲(許
容在庫量)」である。
One is "variable allowable range (allowable stock amount) with respect to stock".

【0061】これは、資材毎に「最小在庫量(最低保持
在庫量)」と、「最大在庫量(許容最大在庫量)」と言
う基準値を設け、「資材の在庫量」が「所定期間中の毎
日」について「最小在庫量」以上であり「最大在庫量」
以下であれば、既に手配した資材調達計画を変更しな
い。
For this purpose, reference values such as "minimum stock amount (minimum holding stock amount)" and "maximum stock amount (allowable maximum stock amount)" are set for each material, and "stock amount of material" is "predetermined period". "Every day in" is greater than or equal to "Minimum inventory" and "Maximum inventory"
In the following cases, do not change the material procurement plan already arranged.

【0062】また、中間の加工工程が完了し、次の工程
に使用される前の状態を「仕掛り在庫」と呼ぶと、中間
の加工工程の工程計画においても、「仕掛り在庫」が
「所定期間中の毎日」について「最小在庫量」と「最大
在庫量」との範囲にあれば、既に手配した工程計画を変
更しない。
Further, when the state before the intermediate processing step is completed and used in the next step is called "work-in-process inventory", the "work-in-process inventory" is "in-process inventory" in the process plan of the intermediate processing step. If it is within the range of "minimum inventory amount" and "maximum inventory amount" for "every day in a predetermined period", the already arranged process plan is not changed.

【0063】このように、「最小在庫量と最大在庫量と
の間の範囲」である「許容在庫量」が、「在庫に対する
変動許容範囲」となる。
As described above, the "allowable stock amount" which is the "range between the minimum stock amount and the maximum stock amount" becomes the "variable allowable range for the stock".

【0064】上記変動許容範囲の二つ目は、「追上げ期
間に対する変動許容範囲(余裕期間)」である。
The second variation allowable range is the "variation allowable range (margin period) for the follow-up period".

【0065】この「追上げ期間」は、資材調達にあって
は、「生産時点に対して資材入手時点を遡らせた期間」
であり、工程手配にあっては、「生産時点に対して加工
時点を遡らせた期間」であり、各資材毎や各工程毎に設
ける。
In the case of material procurement, this "follow-up period" is "a period in which the time when the material is obtained is traced back from the time when the material is produced."
Therefore, in the process arrangement, it is a "period in which the processing time is traced back from the production time" and is provided for each material and each process.

【0066】そして、資材毎に「手配前の追上げ期間」
と、「手配後の追上げ期間」と、2つの「追上げ期間」
を設ける。
[Performance period before arrangement] for each material
And "the follow-up period after arrangement" and two "follow-up periods"
To provide.

【0067】該「手配後の追上げ期間」は、必要時期に
対して正味(最低限)必要な「追上げ期間」である。
The "follow-up period after arrangement" is a net (minimum) necessary "follow-up period" with respect to the required period.

【0068】また、「手配前の追上げ期間」は、「手配
後の追上げ期間」に対し、「許容範囲(余裕期間)」分
大きめな「追上げ期間」とする。
Further, the “follow-up period before arrangement” is a “follow-up period” which is larger than the “follow-up period after arrangement” by “allowable range (margin period)”.

【0069】この為、資材調達計画や工程計画の手配を
するとき、「追上げ期間に対する変動許容範囲(余裕期
間)」分余裕を持って「追上げ期間」の計算をしてお
く。
Therefore, when arranging a material procurement plan or a process plan, the “follow-up period” is calculated with a margin of “variable allowable range (margin period) with respect to the follow-up period”.

【0070】この際、手配後に製品の生産計画が前に繰
上がっても、その繰上げが許容範囲以下であれば、資材
調達計画を変更しないのである。
At this time, even if the production plan of the product is moved forward after the arrangement, if the advance is within the allowable range, the material procurement plan is not changed.

【0071】次に、この「在庫に対する変動許容範囲
(許容在庫量)」の作用について説明する。
Next, the operation of this "variable allowable range (allowable stock amount) with respect to inventory" will be described.

【0072】この際、上記変動した生産計画によって、
手配済の資材調達計画や工程計画に比べて、生産量が増
減する場合には、「最小在庫量」と「最大在庫量」との
間の範囲である「許容在庫量」を「在庫に対する変動許
容範囲」とすることで対処し、製品の生産計画が変動す
る場合にあっても、手配済みの資材調達計画や工程計画
等を変更せずに出来るだけそのままとすることで、それ
ら資材調達計画や工程計画等の生産に伴う諸活動を可及
的に安定化させ、それらの変更に伴う処理の煩雑さや変
更に伴う弊害を回避するのである。
At this time, according to the changed production plan,
If the production volume increases or decreases compared to the material procurement plan or process plan that has already been arranged, change the "allowable inventory amount", which is the range between the "minimum inventory amount" and the "maximum inventory amount", to "variation with respect to inventory". If the production plan of the product fluctuates, it is possible to deal with it by setting it as `` tolerance range '' and keep it as much as possible without changing the arranged material procurement plan or process plan. The various activities associated with production, such as process plans and process plans, are stabilized as much as possible, and the complication of processing due to those changes and the harmful effects due to the changes are avoided.

【0073】すなわち、資材や工程等を手配後に製品の
生産計画が変動する場合において、その変動により資材
や工程等に与える変化が、上記「変動許容範囲」を越え
る場合にあって、生産量が増減する場合には、直ちに手
配済みの資材調達計画や工程計画等を変更することな
く、 (1)まず、資材や工程等の最低限保持すべき在庫量で
ある「最小在庫量」と、最大限許容されるべき在庫量で
ある「最大在庫量」とを、日々の各資材毎や各工程毎に
設ける。 (2)次に、「最小在庫量」と「最大在庫量」との間の
範囲である「許容在庫量」を上記「変動許容範囲」とす
る。 (3)つづいて、増減する生産量が、上記「変動許容範
囲」である「許容在庫量」の範囲内であれば、手配済み
の資材調達計画や工程計画等を変更せずにそのままとす
る。 (4)さらに、増減する生産量が、上記「変動許容範
囲」である「許容在庫量」の範囲を越える場合には、手
配済みの資材調達計画や工程計画等を変更する。 (5)次に、上記「変動許容範囲」である「許容在庫
量」の範囲を越える場合において、「最小在庫量」を下
回る場合は、「最小在庫量」を確保するように手配済み
の資材調達計画や工程計画等の手配数量を増やす。 (6)次に、上記「変動許容範囲」である「許容在庫
量」の範囲を越える場合において、「最大在庫量」を上
回る場合は、「最大在庫量」を確保するように手配済み
の資材調達計画や工程計画等の手配数量を減らすか、該
手配を取消すのである。
That is, in the case where the production plan of a product fluctuates after arranging materials, processes, etc., when the change given to the materials, processes, etc. exceeds the above “variable allowable range”, the production amount is When increasing or decreasing, do not change the material procurement plan or process plan that has already been arranged immediately. (1) First, the minimum inventory amount of materials and processes that should be kept and the maximum inventory amount The "maximum inventory amount", which is the limited inventory amount, is provided for each daily material and each process. (2) Next, the "allowable inventory amount", which is a range between the "minimum inventory amount" and the "maximum inventory amount", is set as the "variable allowable range". (3) Then, if the increasing / decreasing production amount is within the "allowable stock amount" which is the "variable allowable range", the arranged material procurement plan and process plan are left unchanged. . (4) Further, when the increasing / decreasing production amount exceeds the range of the "allowable stock amount" which is the "variable allowable range", the arranged material procurement plan, process plan, etc. are changed. (5) Next, if the material exceeds the "allowable stock" range, which is the "variable allowance", and if it falls below the "minimum stock quantity", materials that have already been arranged to secure the "minimum stock quantity". Increase the number of procurement plans and process plans. (6) Next, if the material exceeds the "allowable stock" range, which is the "variable allowance", and if it exceeds the "maximum stock quantity," the materials that have already been arranged to secure the "maximum stock quantity" Either reduce the number of arrangements such as procurement plans or process plans, or cancel the arrangements.

【0074】このようにすることによって、資材調達計
画や工程計画等の生産に伴う諸活動を生産計画の変動に
対して安定化させるのである。
By doing so, various activities associated with the production such as the material procurement plan and the process plan are stabilized against the fluctuation of the production plan.

【0075】次に、この「追上げ期間に対する変動許容
範囲(余裕期間)」の作用について説明する。
Next, the operation of the "permissible fluctuation range (margin period) with respect to the follow-up period" will be described.

【0076】この際、上記変動した生産計画によって、
手配済の資材調達計画や工程計画に比べて、生産時期が
前に繰上る場合には、一義的には、「追上げ期間」を複
数設けることで対処し、製品の生産計画が変動する場合
にあっても、手配済みの資材調達計画や工程計画等を変
更せずに出来るだけそのままとし、しかも在庫を余分に
持つ手間を省き、在庫が増大することによる弊害を回避
すると共に、それら資材調達計画や工程計画等の生産に
伴う諸活動を可及的に安定化させ、それらの変更に伴う
処理の煩雑さや変更に伴う弊害を回避するのである。
At this time, according to the changed production plan,
When the production period is advanced earlier than the arranged material procurement plan or process plan, it is uniquely dealt with by setting multiple "chase period", and the production plan of the product changes Even if there is, the existing material procurement plan and process plan are left unchanged as much as possible, and the labor of having an extra inventory is saved, and the adverse effects of increasing inventory are avoided and the procurement of those materials The various activities associated with production, such as plans and process plans, are stabilized as much as possible, and the complexity of the processing associated with those changes and the adverse effects associated with the changes are avoided.

【0077】すなわち、資材や工程等を手配後に製品の
生産計画が変動する場合において、生産時期が前に繰上
る場合には、直ちに手配済みの資材調達計画や工程計画
等を変更することなく、 (1)まず、生産に伴う諸活動に応じて適切な「追上げ
期間」(資材調達にあっては、「生産時点に対して資材
入手時点を遡らせた期間」であり、工程手配にあって
は、「生産時点に対して加工時点を遡らせた期間」であ
る。)を、各資材毎や各工程毎に設ける。 (2)次に、この「追上げ期間」を、必要時期に対して
正味必要な追上げ期間である「手配後の追上げ期間」
や、該「手配後の追上げ期間」に対して「許容範囲」分
大きめな追上げ期間である「手配前の追上げ期間」等、
複数設ける。 (3)つづいて、上記「手配前の追上げ期間」と「手配
後の追上げ期間」等との差である「余裕期間」を上記
「変動許容範囲」とする。 (4)さらに、生産時期が前に繰上る期間が、上記「変
動許容範囲」である「余裕期間」の範囲内であれば、手
配済みの資材調達計画や工程計画等を変更せずにそのま
まとする。 (5)次に、生産時期が前に繰上る期間が、上記「変動
許容範囲」である「余裕期間」の範囲を越える場合に
は、手配済みの資材調達計画や工程計画等の変更を考慮
するのである。
That is, in the case where the production plan of a product fluctuates after arranging materials, processes, etc., and when the production period is advanced, immediately without changing the arranged material procurement plan, process plan, etc. (1) First, an appropriate “follow-up period” according to various activities involved in production (in the case of material procurement, it is “a period in which the point of time when the material was obtained is traced back from the point of production”) "Is a period in which the processing time is traced back from the production time") is provided for each material and each process. (2) Next, this "follow-up period" is the net necessary follow-up period, "the post-arrangement follow-up period".
Or a "follow-up period before arrangement", which is a larger follow-up period for the "allowable range" than the "follow-up period after arrangement".
Provide multiple. (3) Subsequently, the "margin period", which is the difference between the "follow-up period before arrangement" and the "follow-up period after arrangement", is defined as the "variable allowable range". (4) Furthermore, if the period in which the production period is moved forward is within the "margin period" which is the "variable allowance range" above, the arranged material procurement plan, process plan, etc. will not be changed. And (5) Next, if the period in which the production period is advanced earlier exceeds the "margin period", which is the "variable allowance" above, consider changes to the material procurement plan or process plan that has already been arranged. To do.

【0078】さらに、生産時期が前に繰上る期間が、上
記「変動許容範囲」である「余裕期間」の範囲を越える
場合には、直ちに手配済みの資材調達計画や工程計画等
を変更することなく、 (1)まず、上記「手配後の追上げ期間」より短い期間
である「緊急時の追上げ期間」を設けることで、「追上
げ期間」をさらに一つ増やす。 (2)次に、生産時期が前に繰上る期間が、上記「手配
前の追上げ期間」と該「緊急時の追上げ期間」との差で
ある「変動許容範囲」たる「最大余裕期間」の範囲内で
あれば、手配済みの資材調達計画や工程計画等を変更せ
ずにそのままとする。 (3)さらには、生産時期が前に繰上る期間が、上記
「手配前の追上げ期間」と該「緊急時の追上げ期間」と
の差である「変動許容範囲」たる「最大余裕期間」の範
囲を越える場合には、手配済みの資材調達計画や工程計
画等を変更するのである。
Furthermore, if the period in which the production period is advanced earlier exceeds the range of the "margin period" which is the "variable allowance range", the arranged material procurement plan or process plan should be immediately changed. No, (1) First, by further providing a “catch-up period in case of emergency” that is shorter than the “catch-up period after arrangement”, the “catch-up period” is further increased by one. (2) Next, the period during which the production period is moved forward is the "maximum margin period" which is the "variable allowable range" which is the difference between the "follow-up period before arrangement" and the "follow-up period in case of emergency". If it is within the range of “”, the material procurement plan and process plan that have already been arranged will remain unchanged. (3) Furthermore, the period during which the production period is moved forward is the "maximum margin period" which is the "variable allowance range", which is the difference between the "follow-up period before arrangement" and the "follow-up period in case of emergency". If it exceeds the range of “”, the arranged material procurement plan and process plan are changed.

【0079】このようにすることによって、資材調達計
画や工程計画等の生産に伴う諸活動を生産計画の変動に
対して安定化させるのである。
By doing so, various activities associated with production, such as the material procurement plan and the process plan, are stabilized against variations in the production plan.

【0080】実際には、これらの処理を数千点〜数万点
の部品や原材料等について一度に計算するのであるか
ら、従来のように必要以上に調達計画が変動する場合
と、必要最低限の変動だけに押さえて計算する場合とで
は、非常に大きな差が出る。
In practice, these processes are calculated at once for several thousand to tens of thousands of parts, raw materials, etc., so that there is a case where the procurement plan fluctuates more than necessary as in the past, and a case where the procurement plan changes to the minimum required. There is a very large difference between the case where only the fluctuation of is calculated and the calculation is performed.

【0081】データ量が多くなると、毎日の仕事として
人手ではチェック出来なくなり、実際的には、コンピュ
ータシステムが計算した通りに資材を調達することにな
る。
When the amount of data becomes large, it becomes impossible to check manually as a daily work, and in reality, materials are procured as calculated by the computer system.

【0082】また、逆にそれが出来なければ、コンピュ
ータシステムを使う意味がなくなってしまう。
On the contrary, if it cannot be done, there is no point in using the computer system.

【0083】実際の業務上のことから考えると、まして
や、その資材の調達そのものが簡単に変更できないもの
であるから、必要以上に調達計画が変わってしまう従来
の計算方法と、最低限必要な箇所だけ変更する本発明の
計算方法とでは、その差が如何に大きなものかが明かに
なる。
Considering from the viewpoint of actual business, much less can be easily changed in the procurement of the material itself. Therefore, the conventional calculation method in which the procurement plan is changed more than necessary and the minimum required location. With the calculation method of the present invention in which only the change is made, it becomes clear how large the difference is.

【0084】以下に図表を参照して、本発明を特定の実
施例について詳述する。
The present invention will be described in detail below with reference to the drawings for specific embodiments.

【0085】図3は、資材調達計画や工程計画の時系列
の中での動きを説明するものであり、ある特定の資材或
いは工程の仕掛りの在庫をグラフにして表示したもので
ある。 すなわち、まず、本日、発注リードタイム分先
(t1)の手配をする。
FIG. 3 is a diagram for explaining the movement of the material procurement plan and the process plan in time series, and is a graph showing the inventory of work in progress of a certain specific material or process. That is, first, today, the order lead time ahead (t1) is arranged.

【0086】その時、設定された基準在庫を満たすよう
手配数を算出して手配する。
At this time, the number of arrangements is calculated and arrangements are made so as to satisfy the set standard stock.

【0087】既に手配された期間内(t0からt1ま
で)は、製品の生産計画が変動し、該資材や仕掛りの在
庫が変動しても、「最小在庫量」と「最大在庫量」との
間の範囲である「許容在庫量」を前記「変動許容範囲」
とすれば、該「変動許容範囲」である「許容在庫量」の
範囲内であれば、既に手配した資材調達計画や工程計画
は変更しない。
Within the already arranged period (from t0 to t1), even if the production plan of the product fluctuates and the inventory of the material and work-in-process varies, the "minimum inventory amount" and the "maximum inventory amount" are "Allowable inventory", which is the range between
Then, if it is within the range of the "allowable stock amount" that is the "variable allowable range", the material procurement plan and process plan already arranged are not changed.

【0088】しかし、製品の生産計画の変動が大であ
り、この範囲を越える場合のみ、既に手配した資材調達
計画や工程計画を変更する。
However, the production plan of the product varies greatly, and only when the production plan exceeds this range, the already-procured material procurement plan or process plan is changed.

【0089】次の実施例は、製品の生産計画と、資材調
達計画や工程計画と、その在庫を表示したものである。
In the next embodiment, the production plan of the product, the material procurement plan and the process plan, and the inventory thereof are displayed.

【0090】本実施例の場合、説明を簡易にする為、製
品Aは、XとYとの2種類の部品からなり、しかも該2
種類の部品X、Yが製品Aを生産するために使用する当
日入手すれば良いものとするが、そのうちXだけを取上
げるものとする。
In the case of this embodiment, in order to simplify the explanation, the product A is made up of two kinds of parts, X and Y.
It suffices to obtain the same kind of parts X and Y used for producing the product A on the same day, but only X will be taken up.

【0091】また、Xは、ロットまとめして発注する必
要はないものとする。
Further, it is assumed that X does not have to be ordered in a lot.

【0092】この場合、基準在庫が5、最小在庫が1、
最大在庫が1,000とする。 日程 1 2 3 4 5 6 7 8 9 10 製品Aの 生産計画 5 3 1 0 3 5 2 0 2 4 部品Xの 調達計画 5 3 1 0 3 5 2 0 2 4 部品Xの 在庫量 8 8 8 8 8 8 8 8 8 8 8 ここで、7日迄は、既に資材調達等の手配が済んでいる
ものとする。
In this case, the standard stock is 5, the minimum stock is 1,
The maximum inventory is 1,000. Schedule 1 2 3 4 5 6 7 8 9 9 10 Production plan for product A 5 3 1 1 0 3 5 2 0 2 4 Procurement plan for parts X 5 3 1 0 3 5 2 2 0 2 4 Inventory for parts X 8 8 8 8 8 8 8 8 8 8 8 Here, it is assumed that arrangements such as material procurement have already been completed by the 7th.

【0093】次に、製品Aの生産計画が需要動向によ
り、3日に+5、6日はー2、変動させる。 すると、
本発明では、次のように資材調達計画を算出する。 日程 1 2 3 4 5 6 7 8 9 10 製品Aの +5 ー1 生産計画 5 3 6 0 3 4 2 0 2 4 部品Xの 調達計画 5 3 1 0 3 5 2 1 2 4 部品Xの 在庫量 8 8 8 3 3 3 4 4 5 5 5 この計算例は、3日に製品Aの必要数が増えた為、Xの
在庫が少なくなるが、最小在庫量を下回ってない為、3
日の資材調達計画は変更しない。
Next, the production plan of the product A is changed by +5 on the 3rd day and by -2 on the 6th day depending on the demand trend. Then
In the present invention, the material procurement plan is calculated as follows. Schedule 1 2 3 4 5 6 7 8 9 10 10 + 5-1 for product A 5 3 6 0 3 4 4 2 0 2 4 Parts X procurement plan 5 3 3 1 0 3 5 2 1 2 4 4 Parts X inventory 8 8 8 3 3 3 4 4 5 5 5 In this calculation example, the stock of X decreases because the required number of products A has increased on the 3rd, but it is not below the minimum stock quantity, so 3
The daily material procurement plan will not be changed.

【0094】また、6日に製品Aの必要数が減った為、
Xの在庫が5日と比べ1つ増えたが、最大在庫量を上回
らないので、6日の資材調達計画は変更しない。
Also, since the required number of product A decreased on the 6th,
The inventory of X increased by 1 compared to 5th, but since it does not exceed the maximum inventory, the material procurement plan on 6th will not be changed.

【0095】さらに、7日までは、既に手配が済んでい
るので、在庫が基準在庫を下回っているが、資材調達計
画や工程計画は変更しない。
Further, by 7th, since the arrangement has already been completed, the inventory is below the standard inventory, but the material procurement plan and the process plan are not changed.

【0096】しかし、8日は、まだ手配をしていない時
期の為、基準在庫になるべく資材調達計画を計算し、こ
の場合1の手配をする。
However, since the 8th is the time when no arrangement is made yet, the material procurement plan is calculated so as to become the standard stock, and the arrangement of 1 is made in this case.

【0097】すなわち、本発明にあっては、製品の生産
計画が変動しても、手配済の資材調達計画や工程計画に
比べて、生産量が減少する場合や、生産時期が後ろに繰
下がる場合には、手配済の資材調達計画や工程計画等に
ついては、そのままで変更しないことで、事務処理の煩
雑さを回避して、省力化を図り、手配済の資材調達計画
や工程計画に比べて、生産量が増大する場合には、資材
調達計画や工程計画等の生産に伴う諸活動の内容の変更
を検討するのである。
That is, in the present invention, even if the production plan of the product fluctuates, the production amount may decrease or the production period may be delayed as compared with the arranged material procurement plan or process plan. In this case, do not change the arranged material procurement plan, process plan, etc. as they are, avoiding the complexity of clerical work and saving labor, compared to the arranged material procurement plan or process plan. Then, when the production volume increases, it is considered to change the contents of various activities associated with the production such as the material procurement plan and the process plan.

【0098】すなわち、資材調達計画や工程計画を手配
した後、製品の生産計画が変動したときは、直ちに手配
済みの資材調達計画や工程計画等を変更することなく、 (1)まず、該変動した製品の生産計画と、既に手配し
た資材調達計画や工程計画から、発注リードタイム期間
内(t0からt1まで)の日々の在庫量を計算する。 (2)次に、その在庫量を資材毎に設定した一日当たり
の「在庫に対する変動許容範囲」と比較する。 (3)つづいて、日々の在庫量が上記一日当たりの「在
庫に対する変動許容範囲」内に収まる場合には、既に手
配した資材調達計画や工程計画は変更せずにそのままと
する。 (4)一方、日々の在庫量が、上記一日当たりの「在庫
に対する変動許容範囲」を越える場合には、既に手配し
た資材調達計画や工程計画をその日について変更する。
That is, if the production plan of the product changes after the material procurement plan or the process plan is arranged, immediately, without changing the arranged material procurement plan or the process plan, (1) The daily stock quantity within the order lead time period (from t0 to t1) is calculated from the production plan of the manufactured product and the already-arranged material procurement plan and process plan. (2) Next, the stock amount is compared with the “permissible fluctuation range with respect to the stock” per day set for each material. (3) Then, if the daily stock amount falls within the above-mentioned "permissible fluctuation range for stock" per day, the material procurement plan and process plan already arranged are left unchanged. (4) On the other hand, when the daily stock quantity exceeds the above-mentioned “permissible fluctuation range for stock” per day, the material procurement plan or process plan already arranged is changed for that day.

【0099】この場合、「在庫に対する変動許容範囲」
とは、前記「最小在庫量(最低保持在庫量)」と、「最
大在庫量(許容最大在庫量)」との間の範囲である「許
容在庫量」を指し、該「最小在庫量(最低保持在庫
量)」を下回ったときには、追加手配をするべく、既に
手配した資材調達計画や工程計画の数量を増大させる。
In this case, "allowable fluctuation range for stock"
The term "allowable stock amount", which is a range between the "minimum stock amount (minimum holding stock amount)" and the "maximum stock amount (allowable maximum stock amount)", means the "minimum stock amount (minimum stock amount)". If the quantity is less than the “holding stock amount”, the quantity of the material procurement plan or process plan that has already been arranged is increased to make an additional arrangement.

【0100】また、該「最大在庫量(許容最大在庫
量)」を上回ったときには、該上回った手配(注文)を
取り消すか、或いはその手配(注文)を変更する。
When the "maximum inventory amount (allowable maximum inventory amount)" is exceeded, the arrangement (order) that exceeds the above is canceled or the arrangement (order) is changed.

【0101】この方法をフローチャートで現すと、図1
に示すようになる。
A flowchart of this method is shown in FIG.
As shown in.

【0102】但し、このフローチャートは、上記計算例
と同じように、ある資材や工程の必要計画が算出されて
からの処理について記載する。
However, this flowchart describes the processing after the necessary plan for a certain material or process is calculated, as in the above calculation example.

【0103】次に、本発明の「追上げ期間」の許容範囲
について、その実施例を挙げて詳述する。
Next, the permissible range of the “chasing period” of the present invention will be described in detail with reference to its examples.

【0104】本実施例の場合、説明を簡単にする為、製
品Aは、材料Zを加工して作るものとする。 材料Z
は、製品Aの加工を始める1日前に入手していれば良い
ものとする。 この場合、本発明の手配後の「追上げ期
間」は、1である。
In the case of the present embodiment, in order to simplify the explanation, the product A is made by processing the material Z. Material Z
Should be obtained one day before the processing of the product A is started. In this case, the “tracking period” after the arrangement of the present invention is 1.

【0105】この際、「追上げ期間」の変動許容範囲を
2日とすると、手配前の「追上げ期間」は、3日であ
る。
At this time, assuming that the fluctuation allowable range of the "follow-up period" is 2 days, the "follow-up period" before arrangement is 3 days.

【0106】また、発注リードタイムを10日間とし
て、以下説明する。 日程 1 2 3 4 5 6 7 8 9 10 11 12 13 製品Aの 10個 生産計画 部品Zの 手配前の追上げ期間=3日 調達計画 10個 この方法は、13日に製品Aを生産する計画があり、そ
れに従った材料Zの調達計画である。 説明の簡略化の
ため、在庫は持たず、ロットまとめをしない場合を考え
る。
Further, the order lead time is set to 10 days in the following description. Schedule 1 2 3 4 5 6 7 8 8 9 10 11 12 12 13 10 pieces of product A Production plan Pursuit period before parts Z is arranged = 3 days Procurement plan 10 pieces This method plans to produce product A on the 13th And there is a material Z procurement plan in accordance with the above. For simplification of the explanation, let us consider a case where there is no inventory and lots are not grouped.

【0107】材料Zの発注リードタイムが10日である
から、1日に材料Zを10日を指定納期とする10個の
発注(手配)をする。
Since the order lead time for the material Z is 10 days, 10 pieces of the material Z are ordered (arranged) with the specified delivery date of 10 days per day.

【0108】次に、本日が4日になった時点で、13日
に生産する計画だったものを2日分繰上げて11日に生
産するよう変更するものとする。 日程 1 2 3 4 5 6 7 8 9 10 11 12 13 製品Aの 10個 ← 10個 生産計画 部品Zの 10個 ← 10個 調達計画 × このまま この計算例では、製品の計画を10日以前に繰上げる場
合のみ、材料Zの調達計画を変更する。 「追上げ期
間」の「変動許容範囲」である2日を越える場合に該当
するからである。
Next, at the time when today is the 4th, it is assumed that what was planned to be produced on the 13th is moved up by 2 days to produce on the 11th. Schedule 1 2 3 4 5 6 7 8 8 9 10 11 12 13 13 Product A 10 ← 10 pcs Production plan 10 parts Z ← 10 pcs Procurement plan × In this calculation example, the product plan is advanced 10 days before Only when it changes, the procurement plan of material Z is changed. This is because it corresponds to the case where it exceeds two days which is the “allowable range of fluctuation” of the “tracking period”.

【0109】しかし、「緊急時の追上げ期間」の設定を
0日にしておけば、10日に繰上がっても、材料Zの繰
上げを指示しなくても済む。
However, if the setting of the “urgent follow-up period” is set to 0 days, it is not necessary to give an instruction to advance the material Z even if it is advanced to 10 days.

【0110】本発明にあっては、変動した生産計画によ
って、手配済の資材調達計画や工程計画に比べて、生産
時期が前に繰上る場合には、一義的には、「追上げ期
間」を複数設けることで対処するのである。
According to the present invention, when the production period is advanced by the changed production plan as compared with the arranged material procurement plan or process plan, the "follow-up period" is uniquely set. It is dealt with by providing a plurality of.

【0111】すなわち、資材や工程等を手配後に製品の
生産計画が変動する場合において、生産時期が前に繰上
る場合には、直ちに手配済みの資材調達計画や工程計画
等を変更することなく、 (1)まず、各資材毎や各工程毎に、適切な「追上げ期
間」を設ける。 (2)次に、この「追上げ期間」を、正味必要な追上げ
期間である「手配後の追上げ期間」や、「許容範囲」分
大きめな追上げ期間である「手配前の追上げ期間」等、
複数設ける。 (3)つづいて、「手配前の追上げ期間」と「手配後の
追上げ期間」等との差である「余裕期間」を上記「変動
許容範囲」とする。 (4)さらに、生産時期が前に繰上る期間が、「変動許
容範囲」である「余裕期間」の範囲内であれば、手配済
みの資材調達計画や工程計画等を変更せずにそのままと
する。 (5)次に、生産時期が前に繰上る期間が、上記「変動
許容範囲」である「余裕期間」の範囲を越える場合に
は、初めて、手配済みの資材調達計画や工程計画等の変
更を考慮し、この場合にも、上記「手配後の追上げ期
間」より短い期間である「緊急時の追上げ期間」を設け
ることで、手配済みの資材調達計画や工程計画等を出来
るだけ変更せずにそのままとすることで、資材調達計画
や工程計画等の生産に伴う諸活動を生産計画の変動に対
して安定化させるのである。
That is, in the case where the production plan of a product fluctuates after arranging materials, processes, etc., and when the production time is advanced, immediately without changing the arranged material procurement plan, process plan, etc. (1) First, an appropriate “track-up period” is set for each material and each process. (2) Next, the "follow-up period" is a net necessary follow-up period "after-arrangement follow-up period" and a "permissible range" larger follow-up period "before-arrangement follow-up period". Period ", etc.
Provide multiple. (3) Subsequently, the "margin period" which is the difference between the "follow-up period before arrangement" and the "follow-up period after arrangement" is defined as the "variable allowance range". (4) Furthermore, if the period in which the production period is moved forward is within the “margin period” which is the “variable allowance range”, the arranged material procurement plan, process plan, etc. are left unchanged. To do. (5) Next, if the period in which the production period is moved forward exceeds the “margin period”, which is the “variable allowance”, change the arranged material procurement plan, process plan, etc. for the first time. In consideration of the above, in this case as well, by setting an "emergency follow-up period" that is shorter than the above "post-arrangement follow-up period", the arranged material procurement plan, process plan, etc. can be changed as much as possible. By leaving it as it is, various activities associated with production, such as material procurement plans and process plans, are stabilized against changes in production plans.

【0112】この方法をフローチャートで現すと、図2
に示すようになる。
A flowchart of this method is shown in FIG.
As shown in.

【0113】[0113]

【発明の効果】このように、本発明によれば、製品を生
産をするのに必要な原材料や部品等の資材の手配を行う
資材調達計画や製品を生産をするのに必要な各加工工程
の手配を行う工程計画等の生産に伴う諸活動を行う場合
にあって、資材や工程の手配をした後、製品の生産計画
が変動した場合にあっても、その変動が資材や工程毎に
設定した「変動許容範囲」の中であれば、手配済の資材
調達計画や工程計画を変更しないようにし、その変動が
資材や工程毎に設定した「変動許容範囲」を越えるもの
についてのみ変更するとする考え方であり、この「変動
許容範囲」を越える場合でも、生産時期が後に繰下がる
場合や、生産数量が減少する場合には、出来るだけその
ままとし、それらの諸活動を可及的に安定化させようと
するものである。
As described above, according to the present invention, a material procurement plan for arranging materials such as raw materials and parts necessary for producing a product and each processing step required for producing a product Even if the production plan of the product changes after making the arrangements of materials and processes when carrying out various activities associated with production, such as process planning, such fluctuations may occur for each material or process. Within the set "variable allowance", do not change the arranged material procurement plan or process plan, and change only those whose fluctuation exceeds the "variable allowance" set for each material or process. Even if it exceeds the "variable allowance range", if the production period is delayed or the production quantity decreases, keep it as much as possible and stabilize those activities as much as possible. It is the one to try.

【0114】従って、次のような優れた効果がある。 (1)製品の生産計画を変動させても、手配済の資材調
達計画や工程計画に影響を及ぼさないで済むから、それ
らを変更する為の混乱を招かない結果、生産計画を容易
に変更できるようになる。
Therefore, there are the following excellent effects. (1) Even if the production plan of the product is changed, it does not affect the arranged material procurement plan or process plan, so that the production plan can be easily changed as a result of not causing confusion. Like

【0115】従って、需要の変動に合わせて製品の生産
計画を変更できるようになり、製品在庫を持たなくて
も、需要に合わせタイムリに製品を供給することが出来
る為、製品在庫を可及的に減少できる結果、資金を無駄
に寝かせなくて済むようになり、在庫金利を小額に押さ
えることができ、また在庫期間内に発生する商品の劣化
を防ぐことができる利点がある。 (2)製品の生産計画を変更できることにより、品切れ
で販売チャンスを逃がすことが無くなる為、売上げが増
大し、利益が増大する他、製品の生産計画を生産現場の
混乱なしに変更できる結果、あらゆる面で非常に大きな
効果がある。 (3)製品を生産するために必要な沢山の部品や材料ま
たは沢山の加工工程の手配を可及的に変更することな
く、製品の生産計画を変動させることができる為、資材
調達計画や工程計画の変更に伴う生産活動の問題点の拡
散や管理の困難性を回避し、問題箇所に焦点を当てて適
切な管理できるようになり、安定した生産を行うことが
できる利点がある。 (4)手配後の製品の生産計画の変動に対して、従来方
法のように変動の都度、資材調達計画や工程計画を変更
する必要がなくなる為、変更に追随できない資材や工程
が生じる不具合や、計画作成時点で計画の実行性が不明
なことにより、発注される企業の生産活動に対する意欲
を失わせる不具合等の問題点をを解消して、製品の生産
計画の変更に伴う生産活動に対する意欲の低下を抑える
ことができる利点がある。 (5)本発明方法は、実際にはコンピュータを利用して
行われ、大量の部品や工程の計画を一度に計算するが、
一定の規則に従って問題点の切り分けをしながら製品の
生産計画の変動を処理できる為、事務の煩雑さが解消さ
れる等の大なる利点がある。 (6)余分な事務処理が排除されるので、事務効率が向
上する利点がある。 (7)在庫を余分に持たなくても、生産時期の繰上げに
対処できるので、在庫の増大に伴う弊害を解消できる利
点がある。
Therefore, the production plan of the product can be changed according to the fluctuation of the demand, and the product can be supplied in a timely manner according to the demand without having the product inventory. As a result, there is an advantage that the money does not need to be spent unnecessarily, the inventory interest rate can be held down to a small amount, and the deterioration of products that occur during the inventory period can be prevented. (2) Being able to change the production plan of a product will not let you miss a sales opportunity due to a product being out of stock, which will increase sales and profit, and as a result you can change the production plan of a product without confusion at the production site. It has a very large effect on the aspect. (3) Since the production plan of the product can be changed without changing the arrangement of the many parts and materials necessary for producing the product or the many processing steps as much as possible, the material procurement plan and the process. There is an advantage that stable production can be achieved by avoiding the diffusion of problems in production activities and the difficulty of management that accompany changes in plans, enabling proper management by focusing on problem areas. (4) It is not necessary to change the material procurement plan and the process plan every time when the production plan of the product after the arrangement is changed, unlike the conventional method. Therefore, there is a problem that a material or a process that cannot follow the change occurs. In addition, since the feasibility of the plan is unknown at the time of making the plan, problems such as problems that make the ordering company unmotivated for the production activity are solved, and the motivation for the production activity accompanying the change of the production plan of the product There is an advantage that the decrease of (5) The method of the present invention is actually performed using a computer and calculates a plan for a large number of parts and processes at one time.
Since it is possible to deal with the fluctuation of the production plan of the product while isolating the problem according to a certain rule, there is a great advantage that complexity of the office work is eliminated. (6) Since extra paperwork is eliminated, there is an advantage that the office work efficiency is improved. (7) Since it is possible to cope with the advance of the production period without having an extra inventory, there is an advantage that the adverse effects due to the increase in inventory can be eliminated.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に基づく一実施例の資材調達計画や工程
計画等の生産に伴う諸活動を生産計画の変動に対して安
定化させる方法の内、「在庫の変動許容範囲」を設ける
方法を示すフローチャートである。
FIG. 1 is a method for providing an “allowable range of inventory fluctuation” among methods for stabilizing various activities associated with production such as a material procurement plan and a process plan according to an embodiment of the present invention against variations in a production plan. It is a flowchart showing.

【図2】本発明に基づく一実施例の資材調達計画や工程
計画等の生産に伴う諸活動を生産計画の変動に対して安
定化させる方法の内、「追上げ期間」を複数設ける方法
を示すフローチャートである。
FIG. 2 shows a method of providing a plurality of “follow-up periods” among the methods for stabilizing various activities associated with production such as a material procurement plan and a process plan according to an embodiment of the present invention against variations in the production plan. It is a flowchart shown.

【図3】本発明に基づく一実施例の資材調達計画や工程
計画等の生産に伴う諸活動を生産計画の変動に対して安
定化させる方法の内、資材調達計画や工程計画の時系列
の中での特定の資材或いは工程の仕掛りの在庫量をグラ
フにして表示したものである。
[Fig. 3] Fig. 3 shows a time series of a material procurement plan and a process plan in a method for stabilizing various activities associated with production such as a material procurement plan and a process plan according to an embodiment of the present invention against variations in the production plan. It is a graphic representation of the inventory of in-process inventory of specific materials or processes.

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】製品を生産をするのに必要な原材料や部品
等の資材の手配を行う資材調達計画や製品を生産をする
のに必要な各加工工程の手配を行う工程計画等の生産に
伴う諸活動を行う場合にあって、該資材や工程等に「変
動許容範囲」を設け、資材や工程等を手配後に製品の生
産計画が変動する場合において、その変動により資材や
工程等に与える変化が、上記「変動許容範囲」の中に収
まる場合には、手配済の資材調達計画や工程計画等を変
更せずにそのままとする、ことを特徴とする資材調達計
画や工程計画等の生産に伴う諸活動を生産計画の変動に
対して安定化させる方法。
1. A material procurement plan for arranging materials such as raw materials and parts necessary for producing a product, and a process plan for arranging each processing step necessary for producing a product. When carrying out various activities that accompany it, if there is a "variable allowance" for the materials and processes, and the production plan of the product changes after the materials and processes are arranged, the changes will be given to the materials and processes. If the change is within the above-mentioned "variable tolerance range", the material procurement plan or process plan, etc., characterized in that the arranged material procurement plan or process plan is left unchanged. A method for stabilizing various activities associated with production against fluctuations in production plans.
【請求項2】資材や工程等を手配後に製品の生産計画が
変動する場合において、その変動により資材や工程等に
与える変化が、上記「変動許容範囲」を越える場合にあ
っても、生産量が減少する場合や、生産時期が後ろに繰
下る場合には、手配済みの資材調達計画や工程計画等を
変更せずにそのままとする、ことを特徴とする請求項1
記載の資材調達計画や工程計画等の生産に伴う諸活動を
生産計画の変動に対して安定化させる方法。
2. When the production plan of a product fluctuates after arranging materials, processes, etc., the amount of production is increased even if the fluctuation causes changes in the materials, processes, etc., above the "variable allowable range". In the case where the number of products is reduced or the production period is delayed, the already arranged material procurement plan, process plan, etc. are left unchanged.
A method to stabilize various activities associated with production such as the stated material procurement plan and process plan against fluctuations in the production plan.
【請求項3】資材や工程等を手配後に製品の生産計画が
変動する場合において、その変動により資材や工程等に
与える変化が、上記「変動許容範囲」を越える場合にあ
って、生産量が増大する場合や、生産時期が前に繰上る
場合には、手配済みの資材調達計画や工程計画等を変更
する、ことを特徴とする請求項1記載の資材調達計画や
工程計画等の生産に伴う諸活動を生産計画の変動に対し
て安定化させる方法。
3. When the production plan of a product fluctuates after arranging materials, processes, etc., and if the fluctuations in the materials, processes, etc. exceed the above "variable allowable range", the production volume The production of the material procurement plan or the process plan according to claim 1, wherein the arranged material procurement plan, the process plan, or the like is changed when the production time increases or when the production period is advanced. A method for stabilizing the accompanying activities against changes in production plans.
【請求項4】資材や工程等を手配後に製品の生産計画が
変動する場合において、その変動により資材や工程等に
与える変化が、上記「変動許容範囲」を越える場合にあ
って、生産量が増減する場合には、直ちに手配済みの資
材調達計画や工程計画等を変更することなく、 (1)まず、資材や工程等の最低限保持すべき在庫量で
ある「最小在庫量」と、最大限許容されるべき在庫量で
ある「最大在庫量」とを、日々の各資材毎や各工程毎に
設ける。 (2)次に、「最小在庫量」と「最大在庫量」との間の
範囲である「許容在庫量」を上記「変動許容範囲」とす
る。 (3)つづいて、増減する生産量が、上記「変動許容範
囲」である「許容在庫量」の範囲内であれば、手配済み
の資材調達計画や工程計画等を変更せずにそのままとす
る。 (4)さらに、増減する生産量が、上記「変動許容範
囲」である「許容在庫量」の範囲を越える場合には、手
配済みの資材調達計画や工程計画等を変更する。 (5)次に、上記「変動許容範囲」である「許容在庫
量」の範囲を越える場合において、「最小在庫量」を下
回る場合は、「最小在庫量」を確保するように手配済み
の資材調達計画や工程計画等の手配数量を増やす。 (6)次に、上記「変動許容範囲」である「許容在庫
量」の範囲を越える場合において、「最大在庫量」を上
回る場合は、「最大在庫量」を確保するように手配済み
の資材調達計画や工程計画等の手配数量を減らすか、該
手配を取消す。ことを特徴とする請求項1記載の資材調
達計画や工程計画等の生産に伴う諸活動を生産計画の変
動に対して安定化させる方法。
4. When the production plan of a product fluctuates after arranging materials, processes, etc., and when the change caused in the materials, processes, etc. exceeds the above "variable allowable range", the production amount is When increasing or decreasing, do not change the material procurement plan or process plan that has already been arranged immediately. (1) First, the minimum inventory amount of materials and processes that should be kept and the maximum inventory amount The "maximum inventory amount", which is the limited inventory amount, is provided for each daily material and each process. (2) Next, the “allowable inventory amount”, which is a range between the “minimum inventory amount” and the “maximum inventory amount”, is set as the “variable allowable range”. (3) Then, if the increasing / decreasing production amount is within the "allowable stock amount" which is the "variable allowable range", the arranged material procurement plan and process plan are left unchanged. . (4) Further, when the increasing / decreasing production amount exceeds the range of the "allowable stock amount" which is the "variable allowable range", the arranged material procurement plan, process plan, etc. are changed. (5) Next, if the material exceeds the "allowable stock" range, which is the "variable allowance", and if it falls below the "minimum stock quantity", materials that have already been arranged to secure the "minimum stock quantity". Increase the number of procurement plans and process plans. (6) Next, if the material exceeds the "allowable stock" range, which is the "variable allowance", and if it exceeds the "maximum stock quantity," the materials that have already been arranged to secure the "maximum stock quantity" Reduce the number of procurement plans or process plans, or cancel the order. A method for stabilizing various activities associated with production such as a material procurement plan and a process plan according to claim 1 against variations in the production plan.
【請求項5】資材や工程等を手配後に製品の生産計画が
変動する場合において、生産時期が前に繰上る場合に
は、直ちに手配済みの資材調達計画や工程計画等を変更
することなく、 (1)まず、生産に伴う諸活動に応じて適切な「追上げ
期間」(資材調達にあっては、「生産時点に対して資材
入手時点を遡らせた期間」であり、工程手配にあって
は、「生産時点に対して加工時点を遡らせた期間」であ
る。)を、各資材毎や各工程毎に設ける。 (2)次に、この「追上げ期間」を、必要時期に対して
正味必要な追上げ期間である「手配後の追上げ期間」
や、該「手配後の追上げ期間」に対して「許容範囲」分
大きめな追上げ期間である「手配前の追上げ期間」等、
複数設ける。 (3)つづいて、上記「手配前の追上げ期間」と「手配
後の追上げ期間」等との差である「余裕期間」を上記
「変動許容範囲」とする。 (4)さらに、生産時期が前に繰上る期間が、上記「変
動許容範囲」である「余裕期間」の範囲内であれば、手
配済みの資材調達計画や工程計画等を変更せずにそのま
まとする。 (5)次に、生産時期が前に繰上る期間が、上記「変動
許容範囲」である「余裕期間」の範囲を越える場合に
は、手配済みの資材調達計画や工程計画等の変更を考慮
する。ことを特徴とする請求項1記載の資材調達計画や
工程計画等の生産に伴う諸活動を生産計画の変動に対し
て安定化させる方法。
[Claim 5] When the production plan of a product fluctuates after arranging materials and processes, and when the production period is advanced, immediately without changing the arranged material procurement plan or process plan, (1) First, an appropriate “follow-up period” according to various activities involved in production (in the case of material procurement, it is “a period in which the point of time when the material was obtained is traced back from the point of production”) "Is a period in which the processing time is traced back from the production time") is provided for each material and each process. (2) Next, this "follow-up period" is the net necessary follow-up period, "the post-arrangement follow-up period".
Or a "follow-up period before arrangement", which is a larger follow-up period for the "allowable range" than the "follow-up period after arrangement".
Provide multiple. (3) Subsequently, the "margin period", which is the difference between the "follow-up period before arrangement" and the "follow-up period after arrangement", is defined as the "variable allowable range". (4) Furthermore, if the period in which the production period is moved forward is within the "margin period" which is the "variable allowance range" above, the arranged material procurement plan, process plan, etc. will not be changed. And (5) Next, if the period in which the production period is advanced earlier exceeds the "margin period", which is the "variable allowance" above, consider changes to the material procurement plan or process plan that has already been arranged. To do. A method for stabilizing various activities associated with production such as a material procurement plan and a process plan according to claim 1 against variations in the production plan.
【請求項6】生産時期が前に繰上る期間が、上記「変動
許容範囲」である「余裕期間」の範囲を越える場合に
は、直ちに手配済みの資材調達計画や工程計画等を変更
することなく、 (1)まず、上記「手配後の追上げ期間」より短い期間
である「緊急時の追上げ期間」を設けることで、「追上
げ期間」をさらに一つ増やす。 (2)次に、生産時期が前に繰上る期間が、上記「手配
前の追上げ期間」と該「緊急時の追上げ期間」との差で
ある「変動許容範囲」たる「最大余裕期間」の範囲内で
あれば、手配済みの資材調達計画や工程計画等を変更せ
ずにそのままとする。 (3)さらには、生産時期が前に繰上る期間が、上記
「手配前の追上げ期間」と該「緊急時の追上げ期間」と
の差である「変動許容範囲」たる「最大余裕期間」の範
囲を越える場合には、手配済みの資材調達計画や工程計
画等を変更する。ことを特徴とする請求項5記載の資材
調達計画や工程計画等の生産に伴う諸活動を生産計画の
変動に対して安定化させる方法。
6. When the production period is advanced earlier than the "margin period", which is the "variable allowance", the material procurement plan or process plan that has already been arranged should be changed immediately. No, (1) First, by further providing a “catch-up period in case of emergency” that is shorter than the “catch-up period after arrangement”, the “catch-up period” is further increased by one. (2) Next, the period during which the production period is moved forward is the "maximum margin period" which is the "variable allowable range" which is the difference between the "follow-up period before arrangement" and the "follow-up period in case of emergency". If it is within the range of “”, the material procurement plan and process plan that have already been arranged will remain unchanged. (3) Furthermore, the period during which the production period is moved forward is the "maximum margin period" which is the "variable allowance range", which is the difference between the "follow-up period before arrangement" and the "follow-up period in case of emergency". If it exceeds the range of “”, change the arranged material procurement plan or process plan. A method for stabilizing various activities associated with production such as a material procurement plan and a process plan according to claim 5 against variations in the production plan.
JP23600194A 1994-09-05 1994-09-05 Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule Pending JPH0877278A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23600194A JPH0877278A (en) 1994-09-05 1994-09-05 Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23600194A JPH0877278A (en) 1994-09-05 1994-09-05 Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule

Publications (1)

Publication Number Publication Date
JPH0877278A true JPH0877278A (en) 1996-03-22

Family

ID=16994336

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23600194A Pending JPH0877278A (en) 1994-09-05 1994-09-05 Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule

Country Status (1)

Country Link
JP (1) JPH0877278A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005135280A (en) * 2003-10-31 2005-05-26 Fujitsu Ltd Production planning method and apparatus
WO2006077930A1 (en) * 2005-01-20 2006-07-27 Kao Corporation Production scheduling system
JP2009129153A (en) * 2007-11-22 2009-06-11 Hitachi Ltd Material requirements planning device, material requirements planning method, and material requirements planning program
JP2016069104A (en) * 2014-09-26 2016-05-09 株式会社ダイフク Product storing facility

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01135452A (en) * 1987-11-19 1989-05-29 Toyota Motor Corp Production instruction system
JPH04264966A (en) * 1991-02-20 1992-09-21 Tokyo Electric Co Ltd Production plan data managing device
JPH05246514A (en) * 1991-07-23 1993-09-24 Yoshio Ninomiya Procurement of necessary material in accordance with stock in specified period
JPH06149779A (en) * 1992-11-10 1994-05-31 Fujitsu Ltd Knowledge prepresenting method and scheduling method of knowledge base system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01135452A (en) * 1987-11-19 1989-05-29 Toyota Motor Corp Production instruction system
JPH04264966A (en) * 1991-02-20 1992-09-21 Tokyo Electric Co Ltd Production plan data managing device
JPH05246514A (en) * 1991-07-23 1993-09-24 Yoshio Ninomiya Procurement of necessary material in accordance with stock in specified period
JPH06149779A (en) * 1992-11-10 1994-05-31 Fujitsu Ltd Knowledge prepresenting method and scheduling method of knowledge base system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005135280A (en) * 2003-10-31 2005-05-26 Fujitsu Ltd Production planning method and apparatus
WO2006077930A1 (en) * 2005-01-20 2006-07-27 Kao Corporation Production scheduling system
JP2006202038A (en) * 2005-01-20 2006-08-03 Kao Corp Production scheduling system
JP4648013B2 (en) * 2005-01-20 2011-03-09 花王株式会社 Production scheduling system
JP2009129153A (en) * 2007-11-22 2009-06-11 Hitachi Ltd Material requirements planning device, material requirements planning method, and material requirements planning program
JP2016069104A (en) * 2014-09-26 2016-05-09 株式会社ダイフク Product storing facility

Similar Documents

Publication Publication Date Title
USRE36360E (en) Method for determining flexible demand in a manufacturing process
US8655697B2 (en) Allocation table generation from assortment planning
US5971585A (en) Best can do matching of assets with demand in microelectronics manufacturing
JP2789801B2 (en) Production plan creation method
US7908186B2 (en) Distribution matrix in an allocation table
US20070219929A1 (en) Planning granularity in manufacturing computing systems
US20050246482A1 (en) Strategic employment of an allocation process in a procurement system
JPH096862A (en) Promise management system
US8046275B2 (en) Synchronizing an allocation table with a procurement system
JP2002333915A (en) Method for procurement of component and device for the same
CN101329746A (en) System and method for automatically arranging production plan
EP1701302A1 (en) Ordering/order receiving system
EP2610696A1 (en) Process design/production planning device
AU769097B2 (en) System and method of scheduling manufacturing resources
US8027857B2 (en) Rough-cut manufacturing operations for use in planning
US6415194B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
JPH0877278A (en) Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule
US6397118B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
JP3419216B2 (en) Production plan creation device
JP3119195B2 (en) Production planning device, method, and recording medium recording program for executing the same
JP3371596B2 (en) Production instruction system
Sato et al. Agile production planning and control with advance notification to change schedule
JPH1196242A (en) Supply and demand planning system, supply and demand planning method and recording medium therefor
JP2007128225A (en) Information formation device
EP1843232B1 (en) Production scheduling system