JPH08239906A - Construction of building - Google Patents
Construction of buildingInfo
- Publication number
- JPH08239906A JPH08239906A JP4397095A JP4397095A JPH08239906A JP H08239906 A JPH08239906 A JP H08239906A JP 4397095 A JP4397095 A JP 4397095A JP 4397095 A JP4397095 A JP 4397095A JP H08239906 A JPH08239906 A JP H08239906A
- Authority
- JP
- Japan
- Prior art keywords
- slab
- floor
- lift
- roof
- jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、地上で組み立てた各
階のスラブ構造体および屋根版をリフトアップして下階
から上階へと順に据え付ける建物の構築工法に関するも
のである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for a building in which slab structures and roof slabs on each floor assembled on the ground are lifted up and installed in order from the lower floor to the upper floor.
【0002】[0002]
【従来の技術】最近、ビルの自動施工技術が種々開発さ
れており、全天候型構築工法と称し、最上階建物の全面
に屋根を架け、この最上階部分を先行上昇させ、この下
において雨天であっても工事を行い、建物の構築をロボ
ットで行うことが知られている。これらの殆どは、最上
階部分に設けられた大梁にホイストやクレーン等の揚重
機を設置し、この揚重機を使用して階下の柱や梁等の建
設資材を吊り上げながら、建設を進めて行くものであ
る。2. Description of the Related Art Recently, various automatic construction techniques for buildings have been developed. This is called an all-weather construction method. A roof is laid on the entire surface of the top floor building, and the top floor portion is raised in advance, and in the rain below it. It is known to perform construction even if there is, and to construct a building with a robot. For most of these, hoisting machines such as hoists and cranes are installed on the large beams installed on the top floor, and the hoisting machines are used to lift construction materials such as columns and beams downstairs while proceeding with the construction. It is a thing.
【0003】一方、従来から多層階の床面を構成するス
ラブを地上で組み立てて下階部分から上階部分へと積み
重ねておき、これを下階部分から順次リフトアップして
所定の位置に据え付ける技術があり、例えば次のような
工法がある。On the other hand, conventionally, the slabs constituting the floor surface of the multi-story floor are assembled on the ground and stacked from the lower floor portion to the upper floor portion, which are sequentially lifted up from the lower floor portion and installed at predetermined positions. There are technologies, for example, the following construction methods.
【0004】 特公昭54−28005号公報「ジャ
ッキ自送式リフトアップ工法」 順次継ぎ足される柱部分に沿って自昇可能なジャッキを
使用し、柱の一部・梁・スラブが一体化した単位スラブ
構造体を前記ジャッキで押し上げ、この単位スラブ構造
体の下に中間部分の柱を挿入する工法。Japanese Patent Publication No. 54-28005 "Jack self-feeding lift-up method" A unit slab in which a part of a pillar, a beam, and a slab are integrated by using a jack that can self-elevate along a pillar that is sequentially added. A construction method in which the structure is pushed up by the jack and the pillar of the intermediate portion is inserted under the unit slab structure.
【0005】 特公昭51−773号公報「建造物の
建設方法」 所定位置に予め柱を立設しておき、この柱間の地上にお
いて下から順に下階壁パネル・上階床スラブ・上階壁パ
ネル・屋根スラブを一体的に重層築造し、最上部の屋根
スラブに設置したウインチ等からなる昇降索巻取装置に
より柱を利用して前記重層体を吊り上げ、先ず下階壁パ
ネルを建て起こしてこの上に上階床スラブを取付け、次
いで上の部分を同様に施工する工法。Japanese Patent Publication No. S51-773 “Construction Method for Buildings” A pillar is erected at a predetermined position in advance, and a lower floor wall panel, an upper floor slab, and an upper floor are arranged in order from the bottom on the ground between the pillars. The wall panel and roof slab are integrally layered, and the multi-layer body is hoisted using the pillars by the hoisting and winding device, such as a winch, installed on the uppermost roof slab, and the lower floor wall panel is first erected. A construction method in which the upper floor slab is installed on the lever and then the upper part is constructed in the same way.
【0006】 特公昭53−23131号公報「多層
建物の構築方法およびそれに使用する吊上げ装置」 基床上に複数対のリフト用支柱を互いに対向させて立設
すると共に、このリフト用支柱を案内として昇降可能な
梁に、リフト棒を有するリフト手段を設け、壁材・スラ
ブ床を階数分だけ積層して形成し、この積層体をリフト
手段により段階的に吊り上げ、スラブ床の上昇に伴い壁
材を建て起こしていく工法。Japanese Patent Publication No. 53-23131 “Method of constructing multi-layer building and lifting device used therefor” A plurality of pairs of lift columns are erected on the base floor so as to face each other, and the lift columns are used as a guide to move up and down. A lift means with a lift bar is provided on a possible beam, and wall materials and slab floors are laminated by the number of floors, and the laminated body is hoisted in stages by the lift means. Construction method to build.
【0007】[0007]
【発明が解決しようとする課題】しかしながら、前述し
た従来の全天候型構築工法においては、順次上昇してい
く最上階部分の下で構築作業が行われるため、構築作業
は高所での作業が多く、資材の運搬や作業員の移動と、
その建設作業は能率的には決して良いものではなかっ
た。However, in the above-mentioned conventional all-weather construction method, since the construction work is performed under the gradually rising top floor portion, the construction work is often performed at high places. , Transportation of materials and movement of workers,
The construction work was by no means good in efficiency.
【0008】また、前述した従来からのリフトアップ構
築工法は、低層の建物を対象としたものであり、中高層
の建物に適用した場合、の工法では中間部柱をクレー
ンにより挿入する必要があり、地上での組み立てを行う
ことができず、また自昇式ジャッキでは能率が悪く、建
設コストが嵩むと共に、工期の短縮を図ることができな
い。また、,の工法でも、各階のスラブ構造体に壁
パネルを取付けておくため、積層体の重量が重くなり、
また柱を利用して昇降させる方式であるため、中高層の
建物には適用は困難である。Further, the above-mentioned conventional lift-up construction method is intended for low-rise buildings, and when it is applied to middle-high rise buildings, in the construction method, it is necessary to insert the middle pillar by a crane, It cannot be assembled on the ground, and the self-elevating jack is inefficient, which increases construction costs and shortens the construction period. Also, in the construction method of ,, since the wall panel is attached to the slab structure on each floor, the weight of the laminated body becomes heavy,
Moreover, since it is a method of going up and down using columns, it is difficult to apply it to middle- and high-rise buildings.
【0009】この発明は、前述のような問題点を解消す
べくなされたもので、その目的は、スラブ構造体,屋根
版および外壁材などのリフトアップ部材の組立作業を地
上で行うことができ、高所での作業を解消できると共
に、効率の良い構築作業を行うことができ、工期の短縮
および建設コストの低減等を図ることができ、さらに中
高層の建物にもリフトアップ工法を有効に適用できる建
物の構築工法を提供することにある。The present invention has been made to solve the above-mentioned problems, and an object thereof is to perform an assembling work of lift-up members such as a slab structure, a roof slab and an outer wall material on the ground. In addition to being able to eliminate work in high places, efficient construction work can be performed, which can shorten the construction period and construction cost, and effectively apply the lift-up method even to middle- and high-rise buildings. It is to provide a building construction method that can.
【0010】[0010]
【課題を解決するための手段】この発明に係る建物の第
1の構築工法は、建設場所に、最上部に張り出し部を設
けたコア柱を、対峙させて予め建設すると共に、前記張
り出し部に、吊上げロッドを昇降可能なリフトアップジ
ャッキを設置し、先ず前記コア柱間の地上において、各
階のスラブ構造体と屋根版を下階から上階へと順次組み
立てて積み上げ、これら各スラブ構造体および屋根版を
前記吊上げロッドにそれぞれ連結すると共に、前記スラ
ブ構造体および屋根版の開口部を外壁材で覆い、次いで
前記スラブ構造体および屋根版を前記リフトアップジャ
ッキで1階分ジャッキアップして所定の据付け位置で最
下位置のスラブ構造体をコア柱に据え付け、ジャッキア
ップにより開口した部分に外壁材を継ぎ足し、これら1
階分のジャッキアップ・外壁材の継足しを順次繰り返す
ことにより、スラブ構造体および屋根版を下階から上階
へと順次コア柱に据え付けることを特徴とする。A first construction method for a building according to the present invention is constructed in such a manner that a core pillar having a projecting portion at the uppermost part is confronted in advance at a construction site and the projecting portion is constructed on the projecting portion. , Installing a lift-up jack capable of ascending / descending the lifting rod, first, on the ground between the core pillars, sequentially assemble and stack the slab structure and the roof slab of each floor from the lower floor to the upper floor, and these slab structures and The roof slab is connected to each of the hoisting rods, the openings of the slab structure and the roof slab are covered with an outer wall material, and then the slab structure and the roof slab are jacked up for one floor with the lift-up jacks to be predetermined. Install the lowest slab structure in the installation position on the core column, and add the outer wall material to the part opened by jacking up.
The feature is that the slab structure and the roof slab are installed on the core pillars sequentially from the lower floor to the upper floor by sequentially repeating the jacking up of the floors and the addition of outer wall materials.
【0011】この発明に係る建物の第2の構築工法は、
建設場所に、最上部に張り出し部を設けたコア柱を、対
峙させて予め建設すると共に、前記張り出し部に、吊上
げロッドを昇降可能なリフトアップジャッキを設置し、
先ず前記コア柱間の地上において、屋根版を組み立てて
吊上げロッドに連結して前記リフトアップジャッキで所
定高さまでジャッキアップし、この屋根版の下で下階の
スラブ構造体を組み立てて吊上げロッドに連結し、これ
ら所定高さのジャッキアップ・下階のスラブ構造体の組
立を上階から下階へと順次繰り返すことにより、屋根版
の下へ各階のスラブ構造体を上階から下階へと積み込
み、これら屋根版および各スラブ構造体の開口部を外壁
材で覆い、次いで前記屋根版および各スラブ構造体を前
記リフトアップジャッキで1階分ジャッキアップして所
定の据付け位置で最下位置のスラブ構造体をコア柱に据
え付け、ジャッキアップにより開口した部分に外壁材を
継ぎ足し、これら1階分のジャッキアップ・外壁材の継
足しを順次繰り返すことにより、スラブ構造体および屋
根版を下階から上階へと順次コア柱に据え付けることを
特徴とする。A second building construction method according to the present invention is
At the construction site, the core pillar provided with the overhanging portion at the uppermost part is confronted with each other in advance, and at the overhanging portion, a lift-up jack capable of ascending and descending the lifting rod is installed,
First, on the ground between the core pillars, a roof slab is assembled, connected to a lifting rod, jacked up to a predetermined height with the lift-up jack, and a slab structure on the lower floor is assembled under the roof slab to be a lifting rod. By connecting and jacking up these predetermined heights and assembling the slab structure on the lower floor in order from the upper floor to the lower floor, the slab structure on each floor is moved from the upper floor to the lower floor under the roof slab. Loading, covering the openings of these roof slabs and each slab structure with an outer wall material, and then jacking up the roof slab and each slab structure by one floor with the lift-up jack, and at the predetermined installation position to the lowest position. Install the slab structure on the core pillar, add the outer wall material to the opening by jacking up, and repeat the jacking up of the first floor and the addition of the outer wall material in order. And by and characterized by mounting the slab structure and roof plate sequentially core pillar to the upper floor from the lower floor.
【0012】前記いずれの構築工法においても、1階か
ら最上階までのスラブ構造体を全てを地上に積み上げ
て、あるいは積み込んでリフトアップしてもよいし、1
階から最上階までを複数に分割し、分割した群毎に積み
上げ・リフトアップを行うようにしてもよい。In any of the above construction methods, all the slab structures from the first floor to the top floor may be piled up on the ground, or may be piled up and lifted up.
The floor to the top floor may be divided into a plurality of groups, and the groups may be stacked and lifted up.
【0013】[0013]
【作用】以上のような構成において、スラブ構造体およ
び屋根版が地上において下階部分から上階部分へと組み
立てられて積み上げられ、あるいは上階部分から下階部
分へと組み立てられて積み込まれ、これらスラブ構造体
および屋根版がリフトアップジャッキによりリフトアッ
プされ、下階部分から順次所定の据付け位置に据え付け
られ、また外壁材が地上において順次継ぎ足され、高所
での組立作業が解消され、効率の良い構築作業を行うこ
とができる。In the above structure, the slab structure and the roof slab are assembled and stacked on the ground from the lower floor portion to the upper floor portion, or assembled from the upper floor portion to the lower floor portion and loaded. These slab structures and roof slabs are lifted up by lift-up jacks and installed in predetermined installation positions from the lower floor part one by one, and outer wall materials are successively added on the ground, eliminating assembly work at high places and improving efficiency. You can do good construction work.
【0014】一対のコア柱を使用し、この上部張り出し
部に設置したリフトアップジャッキによりリフトアップ
するため、またコア柱部分以外の開口部のみに外壁材を
設ける構成であると共に、外壁材を順次継ぎ足していく
ことにより、スラブ構造体等のリフトアップ部材を軽量
化できるため、中高層の建物にもリフトアップ工法を有
効に適用できる。In order to use a pair of core pillars and to lift up by a lift-up jack installed on the upper protruding portion, the outer wall material is provided only in the opening other than the core pillar portion, and the outer wall materials are sequentially arranged. Since the weight of the lift-up member such as the slab structure can be reduced by adding the lift-ups, the lift-up method can be effectively applied to middle- and high-rise buildings.
【0015】また、リフトアップ前におけるスラブ構造
体および屋根版の積層体の開口部が外壁材に完全に覆わ
れ、さらに地上で残りの外壁材が順次継ぎ足されるた
め、風雨等に建設工事が影響されることがなく、また安
全な構築作業が可能となる。Moreover, since the opening of the laminated body of the slab structure and the roof slab before the lift-up is completely covered with the outer wall material, and the remaining outer wall material is successively added on the ground, the construction work is affected by wind and rain. And a safe construction work can be performed.
【0016】[0016]
【実施例】以下、この発明を図示する実施例に基づいて
説明する。図1,図2に、この発明に係る建物の構築工
法の概要を示し、図3に、この発明の構築工法に使用す
る吊上げロッドと大梁との自動連結装置、図4に、この
発明の構築工法に使用するコア柱と大梁との自動固定装
置を示す。また、図5に、この発明に係る構築工法の前
半部分の2通りの工程を示し、図6に、その後半共通部
分の工程を示す。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to illustrated embodiments. 1 and 2 show an outline of a building construction method according to the present invention, FIG. 3 is an automatic connecting device between a hoisting rod and a girder used in the construction method of the present invention, and FIG. 4 is a construction of the present invention. The automatic fixing device for the core pillar and girder used in the construction method is shown. Further, FIG. 5 shows two steps of the first half of the construction method according to the present invention, and FIG. 6 shows steps of the latter half common part.
【0017】図1,図2に示すように、この発明に係る
建物は、建設場所に所定の間隔をおいて対峙して建設さ
れる左右一対のコア柱Aと、最上部の屋根版Bと、一対
のコア柱A間に架け渡される各階のスラブ構造体Cと、
コア柱Aに接する部分以外の開口部を覆う外壁材Dから
構成されている。As shown in FIGS. 1 and 2, a building according to the present invention comprises a pair of left and right core pillars A, which are constructed to face each other at a predetermined place, and a roof slab B at the top. , A slab structure C on each floor spanned between the pair of core pillars A,
It is composed of an outer wall material D that covers the openings other than the portion in contact with the core pillar A.
【0018】スラブ構造体Cは、複数の大梁aと、この
大梁上に設置されるデッキプレート・床配筋bと、リフ
トアップ後に打設されるコンクリートcからなる(図3
参照)。屋根版Bは、図1の実施例では、複数の大梁a
と屋根材b’とからなるトラス屋根であり、図2の実施
例では、スラブ構造体Cと同様に複数の大梁aとデッキ
プレート・床配筋bからなり、さらにこのデッキプレー
ト・床配筋b上にリフトアップ前に予め防水コンクリー
トcを打設して構成されている。The slab structure C is composed of a plurality of girders a, deck plates / floor reinforcements b installed on the girders, and concrete c placed after the lift-up (FIG. 3).
reference). In the embodiment shown in FIG. 1, the roof slab B has a plurality of girders a.
2 is a truss roof composed of a roof material b'and, in the embodiment of FIG. 2, like the slab structure C, it is composed of a plurality of girders a and deck plates / floor reinforcements b. It is constructed by placing a waterproof concrete c in advance on the b before lifting.
【0019】このような建物において、本発明において
は、コア柱Aの最上部に内側に向かって突出する張り出
し部1を設け、この張り出し部1にリフトアップジャッ
キ2をコア柱奥行き方向に間隔をおいて複数台設置し、
後に詳述するように、屋根版Bおよび各階のスラブ構造
体Cを地上において組立てて積層状態としておき、また
外壁材Dも地上において取付け、これら積層状態の屋根
版B・スラブ構造体Cをリフトアップジャッキ2の吊上
げロッド3により吊り上げて下から順に各階における所
定の据付け位置に据え付けていく。In such a building, according to the present invention, a projecting portion 1 projecting inward is provided at the uppermost portion of the core pillar A, and lift-up jacks 2 are provided on the projecting portion 1 at intervals in the core pillar depth direction. I installed multiple units in advance,
As will be described in detail later, the roof slab B and the slab structure C of each floor are assembled on the ground to be in a laminated state, and the outer wall material D is also mounted on the ground, and the roof slab B and the slab structure C in the laminated state are lifted. The hoisting rod 3 of the up jack 2 is hoisted, and the hoisting rods are sequentially installed from the bottom at predetermined installation positions on each floor.
【0020】リフトアップジャッキ2は、例えばピスト
ン中心部を挿通する吊上げロッド3を上部把持装置と下
部把持装置により交互に把持しつつ上昇させる所謂セン
ターホールジャッキとする。なお、このようなセンター
ホールジャッキに限らず、その他のジャッキでもよい。The lift-up jack 2 is, for example, a so-called center hole jack which lifts the lifting rod 3 which passes through the center of the piston while alternately gripping the lifting rod 3 and the lower gripping device. The jack is not limited to such a center hole jack, and other jacks may be used.
【0021】吊上げロッド3とスラブ構造体Cあるいは
屋根版Bとの連結には、図3に示すような、自動的に着
脱できる自動連結装置10を使用する。即ち、各吊上げ
ロッド3は、大梁a位置にそれぞれ配設し、各吊上げロ
ッド3に、切欠部11aが上下方向に所定のピッチで形
成された切欠部材11を設け、各階のスラブ構造体Cあ
るいは屋根版Bにおける大梁aに、前記切欠部11aに
噛合する噛合部材12を設ける。To connect the hoisting rod 3 to the slab structure C or the roof slab B, an automatic connecting device 10 as shown in FIG. That is, each hoisting rod 3 is arranged at the position of the girder a, and each hoisting rod 3 is provided with the notch member 11 in which the notch portions 11a are formed at a predetermined pitch in the vertical direction, and the slab structure C of each floor or On the girder a of the roof slab B, a meshing member 12 that meshes with the cutout portion 11a is provided.
【0022】切欠部材11は、吊上げロッド3の4隅に
大梁長手方向に突出するように一体的に取付け、吊上げ
ロッド3は、大梁aの横を通るように配設する。噛合部
材12は大梁幅方向に長い部材であり、大梁長手方向に
一対で配設し、一対の両ロッド形のシリンダ13により
相互に接近・離隔移動させ、切欠部11aに噛合し、か
つ切欠部11aから離脱できるようにする。シリンダ1
3は、モータとスクリューによりロッドが伸出する電動
シリンダ(パワーシリンダ)とし、制御装置により遠隔
操作する。The notch members 11 are integrally attached to the four corners of the hoisting rod 3 so as to project in the longitudinal direction of the girder, and the hoisting rod 3 is arranged so as to pass beside the girder a. The meshing members 12 are members that are long in the girder width direction, and are arranged in a pair in the girder longitudinal direction. The meshing members 12 are moved toward and away from each other by a pair of double rod-shaped cylinders 13 to mesh with the cutout portions 11a, and the cutout portions 11a. 11a can be separated. Cylinder 1
Reference numeral 3 is an electric cylinder (power cylinder) in which a rod is extended by a motor and a screw, and is remotely operated by a control device.
【0023】噛合部材12は、両端を一対の案内支持部
材14に移動可能に取付け、この案内支持部材14の中
間部に各シリンダ13の本体を固定する。また、この案
内支持部材14は、大梁aの上弦材に支持部材15を介
して固定する。Both ends of the meshing member 12 are movably attached to the pair of guide supporting members 14, and the main body of each cylinder 13 is fixed to an intermediate portion of the guide supporting member 14. The guide support member 14 is fixed to the upper chord member of the girder a via the support member 15.
【0024】コア柱Aと、各階における所定の据付け位
置に到達したスラブ構造体Cあるいは屋根版Bとの据え
付けには、図4に示すような自動固定装置20を使用す
る。For the installation of the core pillar A and the slab structure C or the roof slab B which has reached a predetermined installation position on each floor, an automatic fixing device 20 as shown in FIG. 4 is used.
【0025】この自動固定装置20は、各スラブ構造体
Cあるいは屋根版Bにおける大梁aの両端部の板部材2
1に形成した縦長の係止孔22と、コア柱Aの内側面の
所定据付け位置に取付けた固定金具23から構成する。The automatic fixing device 20 includes the plate members 2 at both ends of the girder a in each slab structure C or roof slab B.
It is composed of a vertically long locking hole 22 formed in No. 1 and a fixing fitting 23 attached to a predetermined installation position on the inner side surface of the core pillar A.
【0026】固定金具23は、図4(b)に示すよう
に、コア柱Aの内側面に形成した凹部24内に収納する
と共に、鉛直方向に傾動して先端が係止孔22に挿入さ
れるように基部をピン着する。また、凹部24には、固
定金具23の下方への傾動を阻止して固定金具23をほ
ぼ水平状態に保持するストッパ部24aを設ける。As shown in FIG. 4B, the fixing member 23 is housed in a recess 24 formed in the inner surface of the core column A, and is tilted in the vertical direction so that its tip is inserted into the locking hole 22. So that the base is pinned. Further, the recess 24 is provided with a stopper portion 24a that prevents the fixing metal fitting 23 from tilting downward and holds the fixing metal fitting 23 in a substantially horizontal state.
【0027】大梁aが上昇している場合には、固定金具
23は板部材21に押されて凹部24内に退避した状態
となり、また係止孔22内に固定金具23の先端が挿入
されても固定金具23の下面テーパ23aが係止孔22
の下縁により上に押し上げられ、凹部24内に押し戻さ
れる。そして、大梁aが所定の据付け位置に到達して固
定金具23がスプリングなどの押圧力により係止孔22
内に挿入されると、大梁aの上昇を停止した後、若干下
降させることにより、固定金具23が係止孔22に係止
めされ、大梁aがコア柱Aに据え付けられ、スラブ構造
体Cあるいは屋根版Bが自動的に簡易固定されることに
なる。When the girder a is raised, the fixing member 23 is pushed by the plate member 21 and retracted into the recess 24, and the tip of the fixing member 23 is inserted into the locking hole 22. Also, the lower surface taper 23a of the fixing bracket 23 has the locking hole 22.
The lower edge pushes it up and pushes it back into the recess 24. Then, the girder a reaches a predetermined installation position, and the fixing metal fitting 23 is pressed by the spring or the like so that the locking hole 22
When the girder a is inserted into the inside of the slab structure C or the slab structure C or the slab structure C or the slab structure C The roof slab B will be automatically and simply fixed.
【0028】また、自動固定装置20は、これに限ら
ず、図4(c)に示すようなものでもよい。これは、コ
ア柱A側に係止突起30を設け、大梁a側にフック状の
固定金具31を設けて構成している。固定金具31は基
部をピン着し、圧縮ばね32により大梁a側に押圧して
おく。また、固定金具31の基部には高さ調整装置33
を設ける。この場合も、大梁aの上昇方向では、固定金
具31が係止突起30から離脱し、若干の下降で固定金
具31が係止突起30に係止めされる。Further, the automatic fixing device 20 is not limited to this, and may be one as shown in FIG. 4 (c). This is configured by providing a locking projection 30 on the core pillar A side and a hook-shaped fixing fitting 31 on the girder a side. The base of the fixing member 31 is attached to the pin, and the compression spring 32 presses the fixing member 31 toward the girder a. In addition, the height adjusting device 33 is provided at the base of the fixing bracket 31.
To provide. In this case as well, in the upward direction of the girder a, the fixing metal fitting 31 is disengaged from the locking projection 30, and the fixing metal fitting 31 is locked to the locking projection 30 with a slight lowering.
【0029】以上のような構成において、本発明におい
ては、所定据付け位置へのリフトアップ前の段階におい
て屋根版Bおよびスラブ構造体Cを地上で積み上げる方
法に2通りの方法があり、第1工法では、次のような手
順で構築を行う(図5(I)および図6参照)。In the above-mentioned structure, in the present invention, there are two methods for stacking the roof slab B and the slab structure C on the ground before the lift-up to the predetermined installation position. Then, the construction is performed by the following procedure (see FIG. 5 (I) and FIG. 6).
【0030】(1) 最上部に張り出し部1を設けた一対の
コア柱Aを、所定の間隔をおいて対峙させて予め建設し
ておき、さらに張り出し部1には、リフトアップジャッ
キ2を配置固定しておく。(1) A pair of core pillars A provided with an overhanging portion 1 at the uppermost part are pre-constructed by facing each other at a predetermined interval, and a lift-up jack 2 is arranged on the overhanging portion 1. Keep it fixed.
【0031】(2-I) 図5(I)に示すように、一対のコ
ア柱A間の地上において、先ず最下階のスラブ構造体C
1 を組み立てる。この組立に際しては、支承部材40上
で大梁aを組立て、この大梁aの上にデッキプレート・
床鉄筋bを敷設して組立を終了し、コンクリートの打設
は行わない。(2-I) As shown in FIG. 5 (I), first, on the ground between the pair of core pillars A, the slab structure C at the lowest floor is first
Assemble 1 At the time of this assembly, the girder a is assembled on the support member 40, and the deck plate
The floor rebar b is laid, the assembly is completed, and the concrete is not placed.
【0032】(3-I) この最下階のスラブ構造体C1 上
に、前述と同様の支承部材40上における大梁aの組立
およびデッキプレート・床鉄筋bの敷設により、上階の
スラブ構造体C2 を組み立てる。以下、同様の作業を繰
り返すことにより、N階までのスラブ構造体CN が下階
部分から順に組み立てられて積み上げられる。(3-I) On the slab structure C 1 on the lowest floor, by assembling the large beam a on the supporting member 40 and laying the deck plate / floor rebar b on the slab structure C 1 on the lower floor, the slab structure on the upper floor is constructed. Assemble body C 2 . Hereinafter, by repeating the same operation, the slab structures C N up to the Nth floor are assembled and stacked in order from the lower floor portion.
【0033】(4-I) 最後は、屋根版Bを組立てて完成さ
せる。図1の実施例では、大梁aを組立て、この大梁a
の上に屋根材b’を取付け、図2の実施例では、大梁a
を組立てると共に、この大梁aの上にデッキプレート・
床鉄筋bを敷設し、さらにその上に防水コンクリートc
を打設する。(4-I) Finally, the roof slab B is assembled and completed. In the embodiment of FIG. 1, the girder a is assembled and the girder a is
A roofing material b'is attached on the top of the roof, and in the embodiment shown in FIG.
Assemble the deck plate and
Floor rebar b is laid and waterproof concrete c is placed on it.
To place.
【0034】(5-I) 一対のコア柱A間の地上には、下か
ら順にN階分のスラブ構造体Cおよび屋根版Bが積層状
態で積み上げられており、この積み重ねられた大梁aを
貫通するように、リフトアップジャッキ2から吊上げロ
ッド3を下げ降ろし、自動連結装置10により最下階か
ら屋根へと順次大梁aを吊上げロッド3に自動的に連結
し、吊り上げができる体制とする。(5-I) On the ground between the pair of core pillars A, slab structures C and roof slabs B for N floors are stacked in order from the bottom, and the stacked large beams a are The hoisting rod 3 is lowered and lowered from the lift-up jack 2 so as to penetrate, and the girder a is automatically connected to the hoisting rod 3 sequentially from the lowest floor to the roof by the automatic connecting device 10 so that the hoisting system can be hoisted.
【0035】(6) 図6に示すように、積み重ねられた屋
根版Bおよびスラブ構造体Cにできる限りの外壁材Dを
取付ける。図6の実施例の場合、最上階Nから途中階K
までの外壁材Dであり、屋根版Bに最上階の外壁材DN
を固定し、これに下階の外壁材を接合して連続構成とす
る。これにより、外周開口部が完全に覆われる。(6) As shown in FIG. 6, as much outer wall material D as possible is attached to the stacked roof slab B and slab structure C. In the case of the embodiment of FIG. 6, the uppermost floor N to the intermediate floor K
The outer wall material D up to and the outer wall material D N on the top floor on the roof slab B
Is fixed and the outer wall material of the lower floor is joined to this to form a continuous structure. As a result, the outer peripheral opening is completely covered.
【0036】(7) このような状態から、各階におけるス
ラブ構造体Cおよび屋根版Bの据え付けに入る。先ず、
最下階のスラブ構造体C1 を所定の据付け位置でコア柱
Aに固定する。この固定に際しては、リフトアップジャ
ッキ2により一階分ジャッキアップし、据付け位置で若
干ジャッキダウンさせることにより、自動固定装置20
により自動的に行われる。(7) From this state, the installation of the slab structure C and the roof slab B on each floor is started. First,
The slab structure C 1 on the bottom floor is fixed to the core pillar A at a predetermined installation position. At the time of this fixing, the lift-up jack 2 is used to jack up for one floor, and the jack is slightly lowered at the installation position so that the automatic fixing device 20
Is done automatically by.
【0037】(8)1階分のジャッキアップにより、1階
部分にできたスペースに外壁材DK-1を挿入し、上の外
壁材DK に接合する。吊上げロッド3と最下階のスラブ
構造体C1 の大梁aとの連結を自動的に解除する。(8) By jacking up the first floor, the outer wall material D K-1 is inserted into the space formed on the first floor and joined to the outer wall material D K above. The connection between the hoisting rod 3 and the girder a of the slab structure C 1 on the lowest floor is automatically released.
【0038】(9) スラブ構造体C2 〜CN に対しても、
前記(7),(8) の工程を行い、スラブ構造体C2 〜CN を
下から順に所定の据付け位置に据え付けていく。外壁材
Dも順次継ぎ足されていく。最後は、屋根版Bが据え付
けられることになる。(9) For the slab structures C 2 to C N ,
The above steps (7) and (8) are performed, and the slab structures C 2 to C N are installed at predetermined installation positions in order from the bottom. The outer wall material D is also added in sequence. At the end, the roof slab B will be installed.
【0039】(10)各階におけるスラブ構造体Cの据付
け、および外壁材Dの継ぎ足しが終了すると、コア柱A
とスラブ構造体Cおよび屋根版Bとの接続を完全な固定
(本締め)とし、各階におけるスラブ構造体C1 〜CN
のデッキプレート・床鉄筋b上にコンクリートcを打設
し、建物が完成する。(10) When the installation of the slab structure C on each floor and the addition of the outer wall material D are completed, the core pillar A
And the slab structure C and the roof slab B are completely fixed (finally tightened), and the slab structures C 1 to C N on each floor are fixed.
The building is completed by placing concrete c on the deck plate and the floor rebar b.
【0040】なお、以上は、1階から最上階Nまでのス
ラブ構造体Cおよび屋根版Bを組み立てて積み上げ、こ
れら全てをジャッキアップする例を示したが、図2に示
すように、1階から最上階Nまでを複数mに分割し、分
割した群毎に積上げとジャッキアップ据付けを行い、上
層部から中層部次いで下層部へと複数回に分けて行って
もよい。この場合には、1回でジャッキアップする数を
低減することができ、リフトアップジャッキの容量を小
さくすることができ、また、より地上近くでスラブ構造
体等の組み立てを行えるなどの利点がある。In the above, the example in which the slab structure C and the roof slab B from the first floor to the top floor N are assembled and piled up and all of them are jacked up is shown. As shown in FIG. To the top floor N may be divided into a plurality of m, stacking and jack-up installation may be performed for each divided group, and the upper layer portion to the middle layer portion and then the lower layer portion may be divided into a plurality of times. In this case, it is possible to reduce the number of jack-ups at one time, to reduce the capacity of the lift-up jack, and to assemble the slab structure or the like closer to the ground. .
【0041】次に、本発明の第2工法では、次のような
手順で構築を行う(図5(II)および図6参照)。Next, in the second method of the present invention, the construction is performed by the following procedure (see FIG. 5 (II) and FIG. 6).
【0042】(1) 前述の第1工法と同じようにコア柱A
を予め建設し、リフトアップジャッキ2を配置固定す
る。なお、リフトアップジャッキ2からは、吊上げロッ
ド3を垂下させておく。(1) Core pillar A as in the first method described above
Is previously constructed, and the lift-up jack 2 is arranged and fixed. The lifting rod 3 is hung from the lift-up jack 2.
【0043】(2-II) 図5(II)に示すように、一対の
コア柱A間の地上において、先ず屋根版Bを支承部材4
0上で組立てて完成させる。この場合も、第1工法と同
様に、図1の実施例では、大梁aを組立て、この大梁a
の上に屋根材b’を取付け、図2の実施例では、大梁a
を組立てると共に、この大梁aの上にデッキプレート・
床鉄筋bを敷設し、さらにその上に防水コンクリートc
を打設する。(2-II) As shown in FIG. 5 (II), first, on the ground between the pair of core columns A, the roof slab B is first supported by the support member 4.
Assemble on 0 to complete. Also in this case, similarly to the first construction method, in the embodiment of FIG.
A roofing material b'is attached on the top of the roof, and in the embodiment shown in FIG.
Assemble the deck plate and
Floor rebar b is laid and waterproof concrete c is placed on it.
To place.
【0044】(3-II) この屋根版Bの大梁aにリフトア
ップジャッキ2の吊上げロッド3の下端部を自動連結装
置10により連結し、屋根版Bを所定の高さまでジャッ
キアップする。このジャッキアップ高さは、地上との間
にスラブ構造体Cを組み立てることのできる高さとす
る。(3-II) The lower end of the lifting rod 3 of the lift-up jack 2 is connected to the girder a of the roof slab B by the automatic connecting device 10, and the roof slab B is jacked up to a predetermined height. This jack-up height is set to a height at which the slab structure C can be assembled with the ground.
【0045】(4-II) この屋根版Bの下における地上
で、最上階となるスラブ構造体CN を組み立てる。この
組立に際しては、支承部材40上で大梁aを組立て、こ
の大梁aの上にデッキプレート・床鉄筋bを敷設して組
立を終了し、コンクリートの打設は行わない。(4-II) On the ground below the roof slab B, the slab structure C N which is the top floor is assembled. At the time of this assembly, the girder a is assembled on the support member 40, the deck plate / floor rebar b is laid on the girder a, the assembly is completed, and concrete is not poured.
【0046】(5-II) 屋根版Bを支承部材40を介して
最上階のスラブ構造体CN により支承した状態で、この
屋根版Bと吊上げロッド3との連結を解除し、吊上げロ
ッド3をジャッキダウンさせて最上階のスラブ構造体C
N の大梁aに自動固定装置10により連結し、この最上
階のスラブ構造体CN を屋根版Bと共に所定の高さまで
ジャッキアップする。以下、同様の作業を繰り返すこと
により、順に上階部分から下階部分へとスラブ構造体C
が積み込まれる。(5-II) With the roof slab B supported by the slab structure C N on the uppermost floor via the support member 40, the connection between the roof slab B and the lifting rod 3 is released, and the lifting rod 3 is released. Jack down to slab structure C on the top floor
The slab structure C N on the uppermost floor is connected to the large beam a of N by the automatic fixing device 10 and the roof slab structure C is jacked up to a predetermined height. Hereinafter, by repeating the same operation, the slab structure C is sequentially transferred from the upper floor portion to the lower floor portion.
Is loaded.
【0047】第1工法と同様に、一対のコア柱A間の地
上には、下から順にN階分のスラブ構造体Cおよび屋根
版Bが積層状態で積み上げられる。以下の図6の工程
は、第1工法の(6) 〜(10)と同じであるので、説明を省
略する。Similar to the first construction method, on the ground between the pair of core columns A, N-story slab structures C and roof slabs B are stacked in order from the bottom. The following steps of FIG. 6 are the same as steps (6) to (10) of the first construction method, and therefore the description thereof will be omitted.
【0048】なお、この第2工法の場合も、1階から最
上階Nまでを複数に分割し、上層部から中層部次いで下
層部へと複数回に分けて行うことができる。Also in the case of this second construction method, it is possible to divide the first floor to the uppermost floor N into a plurality of parts and divide the upper part to the middle part and then to the lower part a plurality of times.
【0049】[0049]
【発明の効果】この発明に係る建物の構築工法は、以上
のような構成からなるので、次のような効果を奏する。The building construction method according to the present invention has the following effects because it has the above-mentioned structure.
【0050】(1) スラブ構造体および屋根版を地上にお
いて下階部分から上階部分へと組み立て、あるいは上階
部分から下階部分へと組み立てて積み込み、これらスラ
ブ構造体および屋根版をリフトアップジャッキによりリ
フトアップし、下階部分から順次所定の据付け位置に据
え付け、また外壁材を地上において順次継ぎ足すように
したため、高所での組立作業が解消され、効率の良い構
築作業を行うことができ、工期の大幅な短縮および建設
コストの大幅な低減を図ることができる。また、安全な
構築作業を行うことができる。(1) Assemble the slab structure and the roof slab from the lower floor portion to the upper floor portion on the ground, or assemble and load from the upper floor portion to the lower floor portion, and lift up the slab structure and the roof slab. Since it was lifted up by a jack, it was installed from the lower floor part to the predetermined installation position in sequence, and the outer wall material was sequentially added on the ground, so assembly work at high places can be eliminated and efficient construction work can be performed. Therefore, it is possible to significantly reduce the construction period and the construction cost. In addition, safe construction work can be performed.
【0051】(2) 一対のコア柱を使用し、この上部張り
出し部に設置したリフトアップジャッキによりリフトア
ップするため、またコア柱部分以外の開口部のみに外壁
材を設ける構成であると共に、外壁材を順次継ぎ足して
いくことにより、スラブ構造体等のリフトアップ部材を
軽量化できるため、中高層の建物にもリフトアップ工法
を適用できると共に、迅速にかつ安全に中高層建物を構
築することができる。(2) A pair of core pillars are used, and in order to lift up by a lift-up jack installed on this upper projecting portion, the outer wall material is provided only in the opening other than the core pillar portion, and the outer wall Since the weight of the lift-up member such as the slab structure can be reduced by sequentially adding the materials, the lift-up method can be applied to a middle-high-rise building and a middle-high-rise building can be constructed quickly and safely.
【0052】(3) リフトアップ前におけるスラブ構造体
および屋根版の積層体の開口部が外壁材に覆われ、さら
に地上で残りの外壁材が順次継ぎ足されるため、構築中
に完全に建物周囲を完全に覆うことができ、風雨等に建
設工事が影響されることなく工期のより短縮化を図れ、
またより安全な構築作業を行うことができる。(3) Since the openings of the laminated structure of the slab structure and the roof slab before the lift-up are covered with the outer wall material, and the remaining outer wall materials are sequentially added on the ground, the surroundings of the building are completely covered during construction. It can be completely covered, and the construction period can be shortened without the construction work being affected by wind and rain.
In addition, safer construction work can be performed.
【図1】この発明に係る建物の構築工法の概要を示す斜
視図である。FIG. 1 is a perspective view showing an outline of a building construction method according to the present invention.
【図2】図1と同じ構築工法において屋根版の構造の異
なる例を示す斜視図である。FIG. 2 is a perspective view showing a different example of the structure of the roof slab in the same construction method as in FIG.
【図3】この発明に係る吊上げロッドと大梁とを連結す
る自動連結装置であり、(a)は横断面図、(b)は正
面図である。FIG. 3 is an automatic connecting device for connecting a hoisting rod and a girder according to the present invention, in which (a) is a transverse sectional view and (b) is a front view.
【図4】この発明に係るコア柱と大梁との据え付けを行
う自動固定装置であり、(a)は部分断面全体図、
(b)はその部分断面詳細図、(c)は異なる構造の自
動固定装置を示す断面図である。FIG. 4 is an automatic fixing device for installing a core column and a girder according to the present invention, in which (a) is an overall partial sectional view,
(B) is a detailed partial sectional view, and (c) is a sectional view showing an automatic fixing device having a different structure.
【図5】この発明に係る構築工法の前半部分を順に示す
概略正面図であり、(I)は第1工法を、(II) は第2
工法を示す。FIG. 5 is a schematic front view sequentially showing the first half of the construction method according to the present invention, where (I) is the first construction method and (II) is the second construction method.
The construction method is shown.
【図6】この発明に係る構築工法の後半部分を順に示す
概略正面図である。FIG. 6 is a schematic front view sequentially showing the latter half of the construction method according to the present invention.
A…コア柱、B…屋根版、C…スラブ構造体、D…外壁
材、a…大梁、b…デッキプレート・床鉄筋、b’…屋
根材、c…コンクリート、1…張り出し部、2…リフト
アップジャッキ、3…吊上げロッド、10…自動連結装
置、11…切欠部材、11a…切欠部、12…噛合部
材、13…シリンダ、20…自動固定装置、21…板部
材、22…係止孔、23…固定金具、24…凹部、30
…係止突起、31…固定金具。A ... Core pillar, B ... Roof slab, C ... Slab structure, D ... Outer wall material, a ... Large beam, b ... Deck plate / floor rebar, b '... Roofing material, c ... Concrete, 1 ... Overhang part, 2 ... Lift-up jack, 3 ... Lifting rod, 10 ... Automatic connecting device, 11 ... Notch member, 11a ... Notch part, 12 ... Engaging member, 13 ... Cylinder, 20 ... Automatic fixing device, 21 ... Plate member, 22 ... Locking hole , 23 ... Fixing hardware, 24 ... Recess, 30
… Locking protrusions, 31… Fixing metal fittings.
Claims (2)
たコア柱を、対峙させて予め建設すると共に、前記張り
出し部に、吊上げロッドを昇降可能なリフトアップジャ
ッキを設置し、先ず前記コア柱間の地上において、各階
のスラブ構造体と屋根版を下階から上階へと順次組み立
てて積み上げ、これら各スラブ構造体および屋根版を前
記吊上げロッドにそれぞれ連結すると共に、前記スラブ
構造体および屋根版の開口部を外壁材で覆い、次いで前
記スラブ構造体および屋根版を前記リフトアップジャッ
キで1階分ジャッキアップして所定の据付け位置で最下
位置のスラブ構造体をコア柱に据え付け、ジャッキアッ
プにより開口した部分に外壁材を継ぎ足し、これら1階
分のジャッキアップ・外壁材の継足しを順次繰り返すこ
とにより、スラブ構造体および屋根版を下階から上階へ
と順次コア柱に据え付けることを特徴とする建物の構築
工法。1. A core pillar having a projecting portion at the top is confronted at a construction site in advance, and a lift-up jack capable of ascending and descending a lifting rod is installed on the projecting portion. On the ground between the pillars, the slab structure and the roof slab of each floor are sequentially assembled and stacked from the lower floor to the upper floor, and the slab structure and the roof slab are respectively connected to the lifting rod, and the slab structure and The opening of the roof slab is covered with an outer wall material, then the slab structure and the roof slab are jacked up for one floor with the lift-up jack, and the slab structure at the lowest position is installed on the core column at a predetermined installation position, An outer wall material is added to the part opened by jacking up, and the slab construction is repeated by sequentially repeating the jacking up of the first floor and the addition of the outer wall material. A building construction method characterized by sequentially installing the structure and roof slab from the lower floor to the upper floor on the core pillars.
たコア柱を、対峙させて予め建設すると共に、前記張り
出し部に、吊上げロッドを昇降可能なリフトアップジャ
ッキを設置し、先ず前記コア柱間の地上において、屋根
版を組み立てて吊上げロッドに連結し、前記リフトアッ
プジャッキで所定高さまでジャッキアップしてこの屋根
版の下で下階のスラブ構造体を組み立てて吊上げロッド
に連結し、これら所定高さのジャッキアップ・下階のス
ラブ構造体の組立を上階から下階へと順次繰り返すこと
により、屋根版の下へ各階のスラブ構造体を上階から下
階へと積み込み、これら屋根版および各スラブ構造体の
開口部を外壁材で覆い、次いで前記屋根版および各スラ
ブ構造体を前記リフトアップジャッキで1階分ジャッキ
アップして所定の据付け位置で最下位置のスラブ構造体
をコア柱に据え付け、ジャッキアップにより開口した部
分に外壁材を継ぎ足し、これら1階分のジャッキアップ
・外壁材の継足しを順次繰り返すことにより、スラブ構
造体および屋根版を下階から上階へと順次コア柱に据え
付けることを特徴とする建物の構築工法。2. A core pillar having a projecting portion at the top is confronted at the construction site in advance, and a lift-up jack capable of moving a lifting rod up and down is installed on the projecting portion. On the ground between the pillars, the roof slab is assembled and connected to the lifting rod, the lift-up jack is used to jack up to a predetermined height, and the lower slab structure is assembled and connected to the lifting rod under the roof slab, By repeating these jack-ups of a predetermined height and assembly of the lower slab structure from the upper floor to the lower floor, the slab structure of each floor is loaded under the roof slab from the upper floor to the lower floor. The openings of the roof slab and each slab structure are covered with an outer wall material, and then the roof slab and each slab structure are jacked up by one floor with the lift-up jack to perform a predetermined installation. By installing the slab structure at the lowest position in the mounting position on the core pillar, adding the outer wall material to the part opened by jacking up, and repeating the jacking up of the first floor and the addition of the outer wall material in sequence, the slab structure And the construction method of the building characterized by sequentially installing the roof slab from the lower floor to the upper floor on the core pillar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4397095A JPH08239906A (en) | 1995-03-03 | 1995-03-03 | Construction of building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4397095A JPH08239906A (en) | 1995-03-03 | 1995-03-03 | Construction of building |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH08239906A true JPH08239906A (en) | 1996-09-17 |
Family
ID=12678576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4397095A Pending JPH08239906A (en) | 1995-03-03 | 1995-03-03 | Construction of building |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH08239906A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008214932A (en) * | 2007-03-02 | 2008-09-18 | Takenaka Komuten Co Ltd | Construction method for building |
JP2008280679A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2008280681A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2008280680A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2008280678A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2014047547A (en) * | 2012-08-31 | 2014-03-17 | Kajima Corp | Construction method for multistory parking space |
-
1995
- 1995-03-03 JP JP4397095A patent/JPH08239906A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008214932A (en) * | 2007-03-02 | 2008-09-18 | Takenaka Komuten Co Ltd | Construction method for building |
JP2008280679A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2008280681A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2008280680A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2008280678A (en) * | 2007-05-08 | 2008-11-20 | Ohbayashi Corp | Construction method for hanging structure building, and hanging structure building |
JP2014047547A (en) * | 2012-08-31 | 2014-03-17 | Kajima Corp | Construction method for multistory parking space |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3921362A (en) | Method of and means for multi-story building construction | |
CA1329633C (en) | Construction apparatus and construction method | |
US10745919B1 (en) | Method and apparatus for installing a staircase assembly into a building | |
US10829927B2 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
KR102197689B1 (en) | Vertical core structure horizontally assembled and construction method therewith | |
ZA200503652B (en) | Method and apparatus for precast and framed block element construction | |
US3732655A (en) | Suspended building construction | |
JPH08239906A (en) | Construction of building | |
JPH0483060A (en) | Building construction | |
US3552080A (en) | Method for erecting multistory buildings | |
JP2957328B2 (en) | Peripheral holding self-elevating construction method | |
JP2009299346A (en) | Construction method of building | |
CN111608270B (en) | Prefabricated through long column concrete assembled frame structure and construction method thereof | |
US3892055A (en) | Method for manufacturing multi-story housing with floor-slabs, bearing walls and partitions cast on the ground level | |
JP6391134B2 (en) | Dismantling method and dismantling system | |
US3435583A (en) | Method of forming buildings | |
JPH08270081A (en) | Construction method of frame structure | |
JP2008214932A (en) | Construction method for building | |
JPH04161565A (en) | Construction of large space building | |
JP2761527B2 (en) | How to build structures | |
KR102394812B1 (en) | Method for constructing precast flat slab | |
SU962549A1 (en) | Method of erecting high-rise buildings by the lifting method | |
JPH0642184A (en) | Method of constructing a skeleton using half-PC floorboard | |
JPH08105229A (en) | How to build a building | |
WO2025062306A1 (en) | A method and system for constructing and/or deconstructing a multi-level building |