[go: up one dir, main page]

JPH08188373A - Support jig for installation of plant equipment - Google Patents

Support jig for installation of plant equipment

Info

Publication number
JPH08188373A
JPH08188373A JP235795A JP235795A JPH08188373A JP H08188373 A JPH08188373 A JP H08188373A JP 235795 A JP235795 A JP 235795A JP 235795 A JP235795 A JP 235795A JP H08188373 A JPH08188373 A JP H08188373A
Authority
JP
Japan
Prior art keywords
unit
jig
installation
plant equipment
support jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP235795A
Other languages
Japanese (ja)
Inventor
Kazuaki Kawakami
和昭 川上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji Electric Co Ltd
Original Assignee
Fuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji Electric Co Ltd filed Critical Fuji Electric Co Ltd
Priority to JP235795A priority Critical patent/JPH08188373A/en
Publication of JPH08188373A publication Critical patent/JPH08188373A/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

(57)【要約】 【目的】複数ユニットの集合組立体からなるプラント機
器を現地に据付ける際に、少ない種類のサポート治具を
適材適所に用いてユニットの搬入,据付け作業を能率よ
く進められるようにしたサポート治具を提供する。 【構成】サポート治具に、ワイヤ吊上げフック,横引き
フック,ジャッキ爪の受台,移動ローラの取付台座,転
倒防止アームの各要素のうち、少なくとも二つ以上の要
素を一つの治具に具備して構成する。その一例として、
ユニットの底部台枠10へボルト締結する取付板7に、
ジャッキ爪の受台9,および該受台の支持アームを兼ね
たワイヤ掛け用の吊上げフック8を連設してユニットの
ワイヤ吊り上げ,および基礎側に据付けたジャッキでユ
ニットを上げ,下げする。
(57) [Abstract] [Purpose] When installing plant equipment consisting of a collective assembly of multiple units on site, a small number of support jigs can be used in appropriate places to carry in and carry out the unit efficiently. To provide the support jig. [Structure] A support jig has at least two or more of the wire lifting hook, side pulling hook, jack claw pedestal, moving roller mounting pedestal, and fall prevention arm elements in one jig. And configure. As an example,
On the mounting plate 7 that is bolted to the bottom frame 10 of the unit,
A pedestal 9 for jack claws and a lifting hook 8 for hanging a wire which also serves as a support arm for the pedestal are continuously provided to lift the wire of the unit, and the unit is raised and lowered by a jack installed on the foundation side.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、燃料電池発電プラント
などを対象に、複数ユニットの集合組立体からなるプラ
ント機器を現地に据付ける際に、個々のユニットに取付
けて搬入,据付け作業を支援するためのサポート治具に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is intended for a fuel cell power plant or the like, and when a plant equipment consisting of a collective assembly of a plurality of units is installed on site, it is attached to each unit to support the carrying-in and installation work. Support jig for doing.

【0002】[0002]

【従来の技術】まず、プラント機器の一例として頭記し
た燃料電池発電プラントの構成を図6に示す。図におい
て、1は燃料電池ユニット、2は燃料改質ユニット、
3,4は燃料改質ユニット2の補機ユニット、5は直流
/交流変換のインバータユニット、6は制御盤ユニット
であり、これらユニット(四隅に立てた支柱と底部,天
井側の台枠からなる堅固なフレームの周面をパネルで覆
ったケースの中に機器を収容した構造)を図示のように
組合わせて燃料電池発電プラントを構築している。ま
た、かかる構成での個々のユニットは発電プラントの容
量によって大きさ,重量が様々であり、出力500KW
クラスのプラントでは、各ユニットの高さは3m前後
で、重量は数トンにもなる。
2. Description of the Related Art First, FIG. 6 shows the configuration of a fuel cell power plant described above as an example of plant equipment. In the figure, 1 is a fuel cell unit, 2 is a fuel reforming unit,
3 and 4 are auxiliary units of the fuel reforming unit 2, 5 is a DC / AC conversion inverter unit, and 6 is a control panel unit, and these units (consisting of columns and bottoms standing at the four corners and an underframe on the ceiling side) A structure in which devices are housed in a case in which a peripheral surface of a rigid frame is covered with panels is combined as shown to construct a fuel cell power plant. Moreover, the size and weight of each unit in such a configuration varies depending on the capacity of the power plant, and the output is 500 KW.
In a class plant, each unit is around 3 m high and weighs a few tons.

【0003】ところで、前記の燃料電池発電プラントは
自家発電用としてオフイスビルなどの建屋(地下室)に
設置して使用するケースが多いが、これらの建屋は工場
とは異なってクレーン設備を備えてない場合が殆どであ
る。そのために、工場で組立てた発電プラントを現地に
搬入して据付けるには、各ユニットごとにトレーラなど
に搭載して現地まで輸送した後、運搬用のローラ台車,
コロ,ジャッキ,現場に組立てた固定式のホイストなど
の道具を使って建屋内の据付位置まで人手作業により移
動し、また倒れ易いユニットには転倒防止用に木製の補
助枠(スリッパ)を仮設して搬入,据付けを行っている
のが現状である。
By the way, the above-mentioned fuel cell power plant is often installed and used in a building (basement) such as an office building for private power generation, but these buildings do not have crane equipment unlike a factory. In most cases. Therefore, in order to bring the power plant assembled in the factory to the site and install it, after mounting each unit on a trailer etc. and transporting it to the site, a roller cart for transportation,
Tools such as rollers, jacks, and fixed hoists assembled on-site are used to manually move to the installation position in the building, and a wooden auxiliary frame (slipper) is temporarily installed to prevent the unit from falling over. The current situation is that they are carried in and installed.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、コロな
どを使った搬入方法は作業能率が悪く、プラント機器の
搬入,据付け作業に多人数の作業員による手間と時間が
かかることから、現場からの要請として機器の搬入,据
付作業を安全,かつ能率よく進めるための改善策が強く
望まれている。
However, the carrying-in method using a roller or the like is inefficient in work, and a large number of workers need time and labor to carry in and install plant equipment. As a result, there is a strong demand for improvement measures to safely and efficiently carry in the installation and installation of equipment.

【0005】本発明は上記の点にかんがみなされたもの
であり、その目的は、複数ユニットの集合組立体からな
るプラント機器を現地に据付ける際に、少ない種類のサ
ポート治具を適材適所に用いてユニットの搬入,据付け
作業を能率よく進められるようにしたプラント機器の据
付用サポート治具を提供することにある。
The present invention has been made in view of the above points, and it is an object of the present invention to use a small number of support jigs in the right places when installing plant equipment consisting of a collective assembly of a plurality of units. The purpose of this is to provide a support jig for installation of plant equipment that enables efficient loading and unloading of units.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明のサポート治具は次記のように構成するもの
とする。 (1)ワイヤ吊上げフック,横引きフック,ジャッキ爪
の受台,移動ローラの取付台座,転倒防止アームの各要
素のうち、少なくとも二つ以上の要素を一つの治具に具
備して構成するものとし、具体的には用途,機能別にサ
ポート治具を次記のような種類に分けて実施するのがよ
い。
In order to achieve the above object, the support jig of the present invention is constructed as follows. (1) One jig is equipped with at least two or more of wire lifting hook, side pulling hook, jack claw pedestal, moving roller mounting pedestal, and fall prevention arm. Therefore, concretely, it is recommended to divide the support jig into the following types according to use and function.

【0007】a)ジャッキ操作,ワイヤ吊り上げ用のサ
ポート治具として、ユニットの底部台枠へボルト締結す
る取付板に、ジャッキ爪の受台,および受台の支持アー
ムを兼ねたワイヤ掛け用の吊上げフックを連設する。 b)ローラ移動,転倒防止用のサポート治具として、ユ
ニットの底部台枠へボルト締結する取付板に転倒防止ア
ームを連設し、かつ該転倒防止アームの先端底部に移動
ローラの取付台座を設ける。
A) As a support jig for jack operation and wire lifting, a mounting plate for bolting to a bottom underframe of a unit, a jack claw pedestal, and a wire hanging hoisting that also serves as a support arm of the pedestal. Line up hooks. b) As a support jig for roller movement and fall prevention, a fall prevention arm is connected to a mounting plate that is bolted to the bottom frame of the unit, and a movement roller attachment base is provided at the bottom of the tip of the fall prevention arm. .

【0008】c)前項b)のサポート治具において、転
倒防止アームの上面にワイヤ掛け用の吊上げフックを設
ける。 d)ローラ移動,転倒防止用のサポート治具として、ユ
ニットの底部台枠へボルト締結する横長な転倒防止アー
ムに対し、横引きフック,および左右両端の底部に移動
ローラの取付台座を設ける。
C) In the support jig of the above item b), a lifting hook for hanging a wire is provided on the upper surface of the fall prevention arm. d) As a support jig for roller movement and fall prevention, a horizontal pulling prevention arm that is bolted to the bottom base frame of the unit is provided with horizontal pulling hooks and mounting bases for the moving rollers at the bottoms at the left and right ends.

【0009】また、隣接するユニットの相互間でユニッ
トケースを上げ,下げする際に使用するサポート治具と
して、次記構成のものがある。 (2)ユニットの上縁にボルト締結する取付金具と、該
金具の側面に結合したジャッキ爪受台とからなり、隣接
するユニットの上に据付けたジャッキの操作でユニット
を上げ,降ろしを可能にする。
Further, as a support jig used when raising and lowering a unit case between adjacent units, there is the following structure. (2) It consists of a mounting bracket that is bolted to the upper edge of the unit, and a jack claw cradle that is connected to the side of the unit. The jack installed on the adjacent unit allows the unit to be raised and lowered. To do.

【0010】(3)隣り合う背丈寸法の異なるユニット
の相互間で、背丈の高いユニットの上面に固定するボル
ト座金付き取付金具と、前記ボルト座金と対をなして背
丈の低いユニットの上面に固定するボルト座金と、前記
各ボルト座金の間にまたがって架け渡した吊りボルトか
らなり、前記吊りボルトのねじ操作で背の低いユニット
を引き上げ,吊り降ろしを可能にする。
(3) Between adjacent units having different height dimensions, a mounting member with a bolt washer for fixing to the upper surface of a tall unit and a pair of the bolt washer to be fixed to the upper surface of a short unit. And a suspension bolt spanning between the bolt washers, and a screw operation of the suspension bolt allows a short unit to be pulled up and down.

【0011】[0011]

【作用】前記した各種のサポート治具を適材適所に採用
し、作業内容に応じて選択した治具をプラント機器のユ
ニットへ取付けることにより、次記のように設置現場へ
のユニットの搬入,据付け作業を安全,かつ能率よく進
めることができる。ここで、(1)−a)項のサポート
治具をユニットの底部台枠の四隅に取付けることによ
り、ユニットのワイヤ吊り上げ,吊り降ろし、およびジ
ャッキ操作による上げ,降ろし作業が行える。また、
b)あるいはd)項の治具を使うことにより、倒れ易い
ユニットを安定した姿勢に支えて据付現場の床面上をロ
ーラ移動することができるほか、該治具にc)項の吊り
上げフックを付設することでユニットのワイヤ吊り上げ
が、またd)項の治具ではワイヤ横引きが行える。
[Function] By adopting the above-mentioned various support jigs in the right places and mounting the jigs selected according to the work content to the plant equipment unit, the unit can be carried in and installed at the installation site as follows. Work can be carried out safely and efficiently. Here, by attaching the support jigs in the item (1) -a) to the four corners of the bottom underframe of the unit, the wire can be lifted and lowered, and the jack operation can be performed. Also,
By using the jig of item b) or d), the unit that is prone to fall can be supported in a stable posture to move the rollers on the floor surface of the installation site, and the jig of item c) can be used for the lifting hook. By attaching the unit, the wire of the unit can be lifted up, and with the jig in the item d), the wire can be pulled horizontally.

【0012】一方、先に据付けたユニットの隣に別なユ
ニットを隙間なく重ね合わせて設置する場合に、ユニッ
トの配列条件によっては隣接する既設のユニットが邪魔
になって基礎面側からジャッキを使用できない場合があ
るが、このような条件下でも(2),あるいは(3)の
サポート治具を採用することにより、ユニット上面側か
らのジャッキ,あるいは吊りボルトの操作でユニットの
引き上げたり、吊り降ろしが可能となる。
On the other hand, when another unit is installed next to the previously installed unit without a gap, depending on the arrangement condition of the units, the existing units adjacent to the unit interfere and the jack is used from the base side. Although it may not be possible, the support jig of (2) or (3) can be used under such conditions to lift or lower the unit by operating the jack or hanging bolt from the top of the unit. Is possible.

【0013】[0013]

【実施例】以下、本発明の実施例を図面に基づいて説明
する。 実施例1:図1(a),(b)は、本発明の請求項2に対
応するジャッキ操作,およびワイヤ吊り上げの二つの用
途に対応する機能を備えたサポート治具(治具の種類を
#1で表す)を示すものであり、当該治具#1は取付板
7と、取付板7に溶接して直角に突き出すワイヤ掛け穴
8aを穿孔した吊り上げフック8と、その先端下面に溶
接したジャッキ爪受台9からなり、使用時には(b)図
のように前記取付板7をユニット(図6に示した符号1
〜6の各ユニット)の底部側台枠(チャンネル鋼材)1
0の周域四隅にボルト11で締結する。
Embodiments of the present invention will be described below with reference to the drawings. Example 1 FIGS. 1 (a) and 1 (b) show a support jig (a type of jig is provided with a function corresponding to two applications of jack operation and wire lifting according to claim 2 of the present invention). The jig # 1 is welded to a mounting plate 7, a lifting hook 8 having a wire hooking hole 8a which is welded to the mounting plate 7 and protrudes at a right angle, and a tip lower surface thereof. It is composed of a jack claw support 9, and when used, the mounting plate 7 is a unit (reference numeral 1 shown in FIG. 6) as shown in FIG.
~ 6 units) bottom side underframe (channel steel) 1
Fasten with bolts 11 at the four corners of the 0 circumference.

【0014】このサポート治具を用いることにより、図
示のように基礎面に据付けたジャッキ12の爪12aを
治具#1の爪受台9に引っ掛けてユニットをジャッキ操
作で上げ,下げできるほか、吊り上げフック8の穴8a
にワイヤ13を掛けることでユニットのワイヤ吊り上げ
が行える。なお、ユニットの移動は、前記のようにユニ
ットをジャッキアップした状態で、ユニットの底部台枠
10に移動ローラ(方向転換自在てキャスタ)を直接取
付け、この移動ローラを床面上に転がして行うものとす
る。
By using this support jig, the claw 12a of the jack 12 installed on the foundation surface can be hooked on the claw receiving base 9 of the jig # 1 to raise and lower the unit by jacking as shown in the figure. Hole 8a for lifting hook 8
The wire of the unit can be lifted by hanging the wire 13 on. The movement of the unit is carried out by directly attaching the moving roller (direction changeable caster) to the bottom frame 10 of the unit with the unit being jacked up as described above, and rolling the moving roller on the floor surface. I shall.

【0015】実施例2:図2(a),(b)は本発明の請
求項3,4に対応する転倒防止,移動ローラ,ワイヤ吊
り上げの三つの用途に対応する機能を備えたサポート治
具(治具の種類を#2で表す)を示すものであり、当該
治具#2は取付板7と、取付板7に溶接したUチャンネ
ル鋼材製の転倒防止アーム14と、該アーム14の先端
側底部に設けた移動ローラ取付台座15と、アーム14
の上面側に設けた吊り上げフック8とから構成されてい
る。なお、14aはアーム14の補強リブである。
Embodiment 2 FIGS. 2 (a) and 2 (b) are support jigs having functions corresponding to three uses of falling prevention, moving rollers and wire hoisting according to claims 3 and 4 of the present invention. (The type of jig is represented by # 2), and the jig # 2 is a mounting plate 7, a U-channel steel fall prevention arm 14 welded to the mounting plate 7, and a tip of the arm 14. Moving roller mounting base 15 and arm 14 provided on the bottom of the side
And a lifting hook 8 provided on the upper surface side of the. Incidentally, 14a is a reinforcing rib of the arm 14.

【0016】かかる構造の治具#2は、(b)図のよう
にユニット(図6に示した各ユニットのうち転倒し易い
幅の狭いユニット4,5)に対し、その底部側台枠10
の周域四隅に転倒防止アーム14が前後へ突き出すよう
に治具をボルト11で締結するとともに、前記台座15
の下面に把手付きの移動ローラ16を取付け、この状態
でユニットを床面上で移動させる。また、作業を進める
上で必要により吊り上げフック8にワイヤ13を掛けて
ユニットをワイヤ吊り上げることもできる。
The jig # 2 having such a structure has a bottom side underframe 10 for a unit (a narrow unit 4 or 5 among the units shown in FIG. 6 which is easy to tip over) as shown in FIG.
The jig is fastened with bolts 11 so that the fall prevention arms 14 project forward and backward at the four corners of the circumference of the base 15.
A moving roller 16 with a handle is attached to the lower surface of the unit, and the unit is moved on the floor in this state. In addition, the wire 13 can be hung on the lifting hook 8 to lift the unit, if necessary in order to proceed with the work.

【0017】実施例3:図3(a),(b)は本発明の請
求項5に対応する転倒防止,および移動ローラの用途に
対応する機能を備えたサポート治具(治具の種類を#3
で表す)を示すものであり、当該治具#3はUチャンネ
ル鋼材で作られた横に長い長尺の転倒防止アーム17
と、該アーム17の中央に溶接接合した横引きフック1
8と、アーム17の左右両端の底部側に設けた一対の移
動ローラ取付台座15とからなる。なお、17aはアー
ム17の補強リブである。
Embodiment 3 FIGS. 3 (a) and 3 (b) show support jigs (with different types of jigs) equipped with functions for preventing fall and corresponding to the application of the moving roller according to claim 5 of the present invention. # 3
The jig # 3 is made of U-channel steel and has a long laterally long fall prevention arm 17.
And a horizontal pulling hook 1 welded to the center of the arm 17
8 and a pair of moving roller mounting pedestals 15 provided on the bottom side of the left and right ends of the arm 17. Reference numeral 17a is a reinforcing rib of the arm 17.

【0018】かかる構造の治具#3は、(b)図のよう
にユニット(図6に示した各ユニットのうち最も幅の狭
くて不安定な制御盤ユニット6)の底部側台枠10の左
右側面に添わせてボルト11で締結し、さらにローラ取
付台座15に移動ローラ16を取付けてユニットを床面
上に移動する。また、現場の状況により(a)図で示す
ように横引きフック18にワイヤ13を掛けてユニット
を牽引することもできる。
The jig # 3 having such a structure has the bottom side underframe 10 of the unit (the narrowest and unstable control panel unit 6 among the units shown in FIG. 6) as shown in FIG. The unit is moved to the floor surface by fastening it with bolts 11 along the left and right side surfaces and further attaching a moving roller 16 to the roller mounting base 15. Further, depending on the situation of the site, the unit can be pulled by hooking the wire 13 on the horizontal pull hook 18 as shown in FIG.

【0019】実施例4:図4(a),(b)は本発明の請
求項6に対応するサポート治具(治具の種類を#4で表
す)を示すものであり、当該治具#4はチャンネル鋼材
で作った取付金具19と、該金具の側面に溶接したジャ
ッキ爪受台20とからなるブロック体として構成されて
いる。
Embodiment 4 FIGS. 4 (a) and 4 (b) show a support jig (the kind of jig is represented by # 4) corresponding to claim 6 of the present invention. Reference numeral 4 is a block body composed of a mounting bracket 19 made of a channel steel material and a jack claw support 20 welded to the side surface of the mounting bracket.

【0020】このサポート治具#4は、図6に示した各
ユニットのうちユニット2,3を先に定位置に据付けた
後、ユニット2,3と重ね合わせてユニット4を据付け
る際に用いるものである。すなわち、ユニット4の周囲
四隅のうち外側に面しているコーナーでは基礎側からの
ジャッキ操作が可能であるが、ユニット2,3と重なり
合うコーナー部では隣接するユニットが邪魔になって基
礎側からジャッキ操作することができない。そこで、こ
の場合には(b)図で示すようにユニット4のケース上
面に前以て前記サポート治具#4の取付金具19をボル
ト締結しておき、隣接するユニット2の天井板の上に据
付けたジャッキ12の爪12aを治具の受座20に引っ
掛けてジャッキ操作することにより、ユニット4のこー
なー部を上げ,下げすることができる。
This support jig # 4 is used when the units 2 and 3 of the units shown in FIG. 6 are first installed in fixed positions and then the units 4 and 3 are superposed on each other. It is a thing. That is, of the four corners of the unit 4 which are facing the outside, the jack operation can be performed from the foundation side, but at the corners where the units 2 and 3 overlap, the adjacent units interfere with the jacking from the foundation side. Can't operate. Therefore, in this case, as shown in FIG. 6B, the mounting fixture 19 of the support jig # 4 is previously bolted to the upper surface of the case of the unit 4 and is mounted on the ceiling plate of the adjacent unit 2 in advance. By hooking the claw 12a of the installed jack 12 on the receiving seat 20 of the jig to perform the jack operation, the core portion of the unit 4 can be raised and lowered.

【0021】実施例5:図5は本発明の請求項7に対応
するサポート治具(治具の種類を#5で表す)の構成図
であり、当該治具#5はUチャンネル鋼材を組合わせて
製作した取付金具21,および該取付金具21に溶接し
たボルト座金22と、これと対をなすチャンネル状の取
付金具23,および該金具23に接合したボルト座金2
4と、前記のボルト座金22と24の間にまたがって架
け渡した吊りボルト25とからなる。なお、26は座金
25の回り止めボルトである。
Embodiment 5: FIG. 5 is a constitutional view of a support jig (the kind of jig is represented by # 5) corresponding to claim 7 of the present invention. The jig # 5 is made of a U channel steel material. The fitting 21 manufactured together, the bolt washer 22 welded to the fitting 21, the channel-shaped fitting 23 paired therewith, and the bolt washer 2 joined to the fitting 23
4 and a suspension bolt 25 spanned between the bolt washers 22 and 24. Incidentally, 26 is a rotation stop bolt for the washer 25.

【0022】このサポート治具#5は、図6に示したユ
ニット1〜5を所定位置に据付けた後、背丈の高い燃料
電池ユニット1と背中合わせに背丈の低い軽量な制御盤
ユニット6を搬入して据付ける際に用いるものである。
すなわち、制御盤ユニット6はその三方がユニット1,
2,5で囲まれているために、基礎側からジャッキ操作
することが困難である。そこで、この場合には図示のよ
うに治具#5の一方の取付金具21を背丈の高いユニッ
ト1の上縁に固定し、これと対をなす他方の取付金具2
3,ボルト座金24を背丈の低いユニット6の上端に固
定し、ここでボルト座金22と24の間に吊りボルト2
5をナット25aとともに架け渡す。この状態で、ナッ
ト25aを回して吊りボルト25をねじ送りすることに
より、ジャッキを使わずに取付台座21を支点にしてユ
ニット6を吊り上げ,吊り下げ操作することができる。
In this support jig # 5, the units 1 to 5 shown in FIG. 6 are installed at predetermined positions, and then the fuel cell unit 1 having a high height and the lightweight control panel unit 6 having a short height are carried back to back. It is used when installing.
That is, the control board unit 6 has three units 1,
Since it is surrounded by 2 and 5, it is difficult to operate the jack from the foundation side. Therefore, in this case, as shown in the figure, one mounting bracket 21 of the jig # 5 is fixed to the upper edge of the unit 1 having a high height, and the other mounting bracket 2 of the pair is fixed.
3. Fix the bolt washer 24 to the upper end of the unit 6 with a short height.
5 together with the nut 25a. In this state, by rotating the nut 25a and screw-feeding the suspension bolt 25, the unit 6 can be suspended and suspended using the mounting base 21 as a fulcrum without using a jack.

【0023】なお、図7は図6に示した各ユニット1〜
6を現地に搬入,据付ける際に使用する前記各実施例の
サポート治具#1〜#5の使用例を表した図である。
FIG. 7 shows each unit 1 to 1 shown in FIG.
It is a figure showing the usage example of the support jigs # 1 to # 5 of each said Example used when carrying in and installing 6 in the field.

【0024】[0024]

【発明の効果】以上述べたように、本発明のサポート治
具を適宜選択し、機器の搬入,据付けの現場作業に合わ
せて適材適所に取付けて使用することにより、燃料電池
発電プラントなどのように複数ユニットの集合組立体か
らなるプラント機器の据付現地への搬入,据付け作業を
安全,かつ作業能率よく進めることができる。
As described above, by appropriately selecting the support jig of the present invention and attaching it to the right material in the right place according to the on-site work of equipment loading and installation, it can be used as a fuel cell power plant. In addition, it is possible to safely and efficiently carry in the installation and installation work of the plant equipment consisting of a collective assembly of multiple units to the installation site.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例1に対応するサポート治具を示
し、(a)は治具の構成斜視図、(b)は使用状態図
1A and 1B show a support jig corresponding to a first embodiment of the present invention, in which FIG. 1A is a perspective view of the jig and FIG.

【図2】本発明の実施例2に対応するサポート治具を示
し、(a)は治具の構成斜視図、(b)は使用状態図
2A and 2B show a support jig corresponding to a second embodiment of the present invention, in which FIG. 2A is a perspective view of the jig, and FIG.

【図3】本発明の実施例3に対応するサポート治具を示
し、(a)は治具の構成斜視図、(b)は使用状態図
3A and 3B show a support jig corresponding to Example 3 of the present invention, in which FIG. 3A is a perspective view of the jig, and FIG.

【図4】本発明の実施例4に対応するサポート治具を示
し、(a)は治具の構成斜視図、(b)は使用状態図
4A and 4B show a support jig corresponding to Example 4 of the present invention, FIG. 4A is a perspective view of the jig, and FIG.

【図5】本発明の実施例5に対応するサポート治具の構
成斜視図
FIG. 5 is a perspective view showing the structure of a support jig corresponding to Example 5 of the invention.

【図6】プラント機器の一例として示した燃料電池発電
プラント機器の組立図
FIG. 6 is an assembly diagram of a fuel cell power generation plant device shown as an example of the plant device.

【図7】図6の各ユニットに適用した本発明実施例のサ
ポート治具の使用例を表す図
FIG. 7 is a view showing an example of use of a support jig of the embodiment of the present invention applied to each unit of FIG.

【符号の説明】[Explanation of symbols]

1〜6 プラント機器のユニット #1〜#5 種類別のサポート治具 7 取付金 8 吊り上げフック 9 ジャッキ爪受台 10 ユニットの底部台枠 11 ボルト 12 ジャッキ 13 ワイヤ 14 転倒防止アーム 15 移動ローラ取付台座 16 移動ローラ 17 転倒防止アーム 18 横引きフック 20 ジャッキ爪受台 21 取付金具 22,24 ボルト座金 25 吊りボルト 1 to 6 Units of plant equipment # 1 to # 5 Support jigs for each type 7 Mounting gold 8 Lifting hook 9 Jack claw support 10 Bottom frame of unit 11 Bolt 12 Jack 13 Wire 14 Fall prevention arm 15 Moving roller mounting base 16 Moving roller 17 Fall prevention arm 18 Side pulling hook 20 Jack claw support 21 Mounting bracket 22, 24 Bolt washer 25 Hanging bolt

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】複数ユニットの集合組立体としてなるプラ
ント機器の現地への据付けに際し、個々のユニットに取
付けて搬入,据付作業を支援するためのサポート治具で
あって、ワイヤ吊上げフック,横引きフック,ジャッキ
爪の受台,移動ローラの取付台座,転倒防止アームの各
要素のうち、少なくとも二つ以上の要素を一つの治具に
具備してなることを特徴とするプラント機器の据付用サ
ポート治具。
1. A support jig for supporting the carrying-in and installation work by attaching to individual units at the time of installing on-site a plant device which is a collective assembly of a plurality of units, such as wire lifting hooks and horizontal pulling. Support for installation of plant equipment, characterized in that one jig is equipped with at least two or more elements among hook, jack claw pedestal, moving roller mounting pedestal, and fall prevention arm elements. jig.
【請求項2】ユニットの底部台枠へボルト締結する取付
板に、ジャッキ爪の受台,および該受台の支持アームを
兼ねたワイヤ掛け用の吊上げフックを連設した請求項1
記載のプラント機器の据付用サポート治具。
2. A mounting plate for bolting to a bottom underframe of the unit, wherein a jack claw pedestal and a wire hooking hook that also serves as a support arm of the pedestal are consecutively provided.
Support jig for installation of the listed plant equipment.
【請求項3】ユニットの底部台枠へボルト締結する取付
板に転倒防止アームを連設し、かつ該転倒防止アームの
先端底部に移動ローラの取付台座を設けた請求項1記載
のプラント機器の据付用サポート治具。
3. The plant equipment according to claim 1, wherein a tipping prevention arm is continuously provided on a mounting plate which is bolted to the bottom frame of the unit, and a mounting base for the moving roller is provided at the bottom of the tip of the tipping prevention arm. Support jig for installation.
【請求項4】転倒防止アームの上面にワイヤ掛け用の吊
上げフックを設けた請求項3記載のプラント機器の据付
用サポート治具。
4. A support jig for installation of plant equipment according to claim 3, wherein a lifting hook for hanging a wire is provided on the upper surface of the fall prevention arm.
【請求項5】ユニットの底部台枠へボルト締結する横長
な転倒防止アームに対し、横引きフック,および左右両
端の底部に移動ローラの取付台座を設けてなる請求項1
記載のプラント機器の据付用サポート治具。
5. A horizontal pulling prevention arm for bolting to a bottom base frame of the unit, a horizontal pulling hook, and mounting bases for moving rollers provided at the bottoms of the left and right ends.
Support jig for installation of the listed plant equipment.
【請求項6】複数ユニットの集合組立体としてなるプラ
ント機器の現地への据付けに際し、個々のユニットに取
付けて搬入,据付作業を支援するためのサポート治具で
あって、ユニットの上縁にボルト締結する取付金具と、
該金具の側面に結合したジャッキ爪受台とからなり、隣
接するユニットの上に据付けたジャッキの操作でユニッ
トを上げ,降ろしすることを特徴とするプラント機器の
据付用サポート治具。
6. A support jig for supporting the carrying-in and installation work by attaching to individual units when installing plant equipment, which is a collective assembly of a plurality of units, on site, and bolts are provided at the upper edges of the units. A mounting bracket to fasten,
A support jig for installation of plant equipment, comprising a jack claw cradle connected to a side surface of the metal fitting, and raising and lowering a unit by operating a jack installed on an adjacent unit.
【請求項7】複数ユニットの集合組立体としてなるプラ
ント機器の現地への据付けに際し、個々のユニットに取
付けて搬入,据付作業を支援するためのサポート治具で
あって、隣り合う背丈寸法の異なるユニットの相互間
で、背丈の高いユニットの上面に固定するボルト座金付
き取付金具と、前記ボルト座金と対をなして背丈の低い
ユニットの上面に固定するボルト座金と、前記各ボルト
座金の間にまたがって架け渡した吊りボルトからなり、
前記吊りボルトのねじ操作で背の低いユニットを引き上
げ,吊り降ろしすることを特徴とするプラント機器の据
付用サポート治具。
7. A support jig for supporting the carrying-in and installation work by attaching to individual units when installing plant equipment as a collective assembly of a plurality of units on site, and having adjacent heights different from each other. Between the units, between the mounting units with bolt washers that secure to the upper surface of the tall unit, the bolt washers that pair with the bolt washers to secure to the upper surface of the short unit, and between each of the bolt washers. It consists of hanging bolts spanned over,
A support jig for installation of plant equipment, wherein a short unit is pulled up and down by operating a screw of the hanging bolt.
JP235795A 1995-01-11 1995-01-11 Support jig for installation of plant equipment Pending JPH08188373A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP235795A JPH08188373A (en) 1995-01-11 1995-01-11 Support jig for installation of plant equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP235795A JPH08188373A (en) 1995-01-11 1995-01-11 Support jig for installation of plant equipment

Publications (1)

Publication Number Publication Date
JPH08188373A true JPH08188373A (en) 1996-07-23

Family

ID=11527023

Family Applications (1)

Application Number Title Priority Date Filing Date
JP235795A Pending JPH08188373A (en) 1995-01-11 1995-01-11 Support jig for installation of plant equipment

Country Status (1)

Country Link
JP (1) JPH08188373A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009256057A (en) * 2008-04-17 2009-11-05 Asahi Biruto Kk Moving device and moving method
US8313131B2 (en) 2007-01-26 2012-11-20 Airbus Operations Limited Fitting, crane hook, and crane hook assembly
JP2013147254A (en) * 2012-01-17 2013-08-01 Toshiba Mitsubishi-Electric Industrial System Corp Transporting tool
KR20160001103U (en) * 2014-09-25 2016-04-05 한전케이피에스 주식회사 Leveling device for valve disk
JP2020192868A (en) * 2019-05-28 2020-12-03 株式会社竹中工務店 Transporter

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8313131B2 (en) 2007-01-26 2012-11-20 Airbus Operations Limited Fitting, crane hook, and crane hook assembly
US8662549B2 (en) 2007-01-26 2014-03-04 Airbus Operations Limited Fitting, crane hook, and crane hook assembly
JP2009256057A (en) * 2008-04-17 2009-11-05 Asahi Biruto Kk Moving device and moving method
JP2013147254A (en) * 2012-01-17 2013-08-01 Toshiba Mitsubishi-Electric Industrial System Corp Transporting tool
KR20160001103U (en) * 2014-09-25 2016-04-05 한전케이피에스 주식회사 Leveling device for valve disk
JP2020192868A (en) * 2019-05-28 2020-12-03 株式会社竹中工務店 Transporter

Similar Documents

Publication Publication Date Title
US20110147329A1 (en) Load transportation system
JP2010228827A (en) Mobile transfer device
JPH08188373A (en) Support jig for installation of plant equipment
CN114852883A (en) Hoisting device and control system thereof
JPH05178561A (en) Installation method for guide rail for elevator
JP2738254B2 (en) How to bring in the unit room
JP3220397B2 (en) Elevating scaffold
JPH07157274A (en) Hanging jig for ALC plate
CN222759416U (en) Building prefabricated wallboard installation appurtenance
CN216336297U (en) Simple tool for hoisting steel column
JPH0978840A (en) Hanging metal tool for building
CN220078360U (en) Concrete prefabricated section transfer device
CN220449559U (en) Hanging basket overhanging system for being installed in building
CN222253191U (en) ALC wallboard construction is with electric hoist fixing device
JPH09183595A (en) Indoor unloading method and device thereof
CN216038348U (en) Lifting frame
JP2002070314A (en) Floor panel installation method
JP2655237B2 (en) Small crane equipment
JP3004731U (en) Multi-point hanging jig
JP3086948B2 (en) Air conditioner outdoor unit lifting device and lifting method
JP3811419B2 (en) Building material lifting device and building material lifting method
JP2000247586A (en) Elevating method for heavy article and its device
JPH06227787A (en) Building method for heavy weight frame
JPH06240873A (en) Execution of work for ceiling
JP2526955Y2 (en) Gate type transport installation device