[go: up one dir, main page]

JPH0781355B2 - Construction method of joist slab using precast concrete girder - Google Patents

Construction method of joist slab using precast concrete girder

Info

Publication number
JPH0781355B2
JPH0781355B2 JP7865189A JP7865189A JPH0781355B2 JP H0781355 B2 JPH0781355 B2 JP H0781355B2 JP 7865189 A JP7865189 A JP 7865189A JP 7865189 A JP7865189 A JP 7865189A JP H0781355 B2 JPH0781355 B2 JP H0781355B2
Authority
JP
Japan
Prior art keywords
joist
slab
girder
precast concrete
semi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7865189A
Other languages
Japanese (ja)
Other versions
JPH02261145A (en
Inventor
宗吉 柳澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP7865189A priority Critical patent/JPH0781355B2/en
Publication of JPH02261145A publication Critical patent/JPH02261145A/en
Publication of JPH0781355B2 publication Critical patent/JPH0781355B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Floor Finish (AREA)
  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明はプレキャストコンクリート大梁を用いたジョイ
ストスラブの架構工法に係るものである。
TECHNICAL FIELD The present invention relates to a method for constructing a joist slab structure using a precast concrete girder.

(従来の技術) 建造物の構造は、柱、梁、、床、壁等から構成され、構
造は鉄筋コンクリート、鉄筋鉄骨コンクリート造、鉄骨
造等があり、その施工は、現場施工によるもの、工業化
工法によって行われている。前記した構造や工業化工法
においては、一定間隔に柱を立設し、同柱間に大梁を架
け、さらに大梁間に小梁を架け大梁、小梁に床版を平面
的に支持して施工している。前記した床版を形成するの
に当たっては、一部工業化工法を採用して行なわれてい
る。
(Conventional technology) The structure of a building is composed of columns, beams, floors, walls, etc., and the structure includes reinforced concrete, reinforced steel-framed concrete construction, steel-framed construction, etc. Is done by. In the above-mentioned structure and industrialized construction method, pillars are erected at regular intervals, large beams are bridged between the pillars, small beams are bridged between the large beams, and the floor slab is supported flatly on the large beams and small beams. ing. In forming the floor slab, a part of industrialized construction method is adopted.

例えば、プレストレスを導入した半プレキャストコンク
リートジョイストスラブを大梁に架構し前記半プレキャ
ストコンクリートジョイストスラブ上面に現場打コンク
リートを打設して一体にしたスラブ工法がある。
For example, there is a slab construction method in which a prestressed semi-precast concrete joist slab is framed on a large beam and in-situ concrete is cast on the upper surface of the semi-precast concrete joist slab to be integrated.

前記スラブの架構は第10図及び第11図に示すように、大
梁の梁成hよりジョイストスラブの厚さh1を引いた残り
の梁成h2を断面とする大梁Gを形成するための大梁型枠
を組み立てる。
As shown in FIGS. 10 and 11, the frame structure of the slab is used to form a girder G having a cross section of the remaining girder h 2 obtained by subtracting the thickness h 1 of the joist slab from the girder h of the girder. Assemble the cross beam formwork.

前記半プレキャストコンクリートジョイストスラブb
1(以下半PCジョイストスラブという)は、スラブ下面
に一定間隔で逆台形に突出した小梁(ジョイスト)b3
所定のスラブ厚h0から現場打設するスラブコンクリート
の厚さhrを引いた半PCスラブb2とが一体に成形された半
プレキャストコンクリートジョイストスラブb1(以下半
PCジョイストスラブという)としている。この半PCジョ
イストスラブb1は、その製造過程において小梁(ジョイ
スト)にトラス筋を配して同トラス筋に起り(むくり)
を生起させてコンクリートを打設し成形しており、大梁
1に架設する場合に支保工を不用とするものである。な
お、第10図において中心線X−Xより左側は第11図のイ
−イ矢視の断面図で、右側は第11図のロ−ロ矢視の断面
図である。
The semi-precast concrete joist slab b
1 (hereinafter referred to as semi PC Joyce Tosurabu) is subtracted thickness h r of the joists (joists) b 3 and field hitting set to slab concrete of a predetermined slab thickness h 0 projecting inverted trapezoid at regular intervals on the slab bottom surface semi PC slab b 2 and the half precast concrete Joyce Tosurabu b 1 (hereinafter half formed integrally
It is called PC Joyst Slab). The semi PC Joyce Tosurabu b 1 is caused to the truss muscle arranged truss muscle joists (joists) in its production process (Mukuri)
The concrete is placed and molded by raising the above, and the support work is unnecessary when the concrete is erected on the girder 1. In addition, in FIG. 10, the left side of the center line XX is a cross-sectional view taken along the line EE of FIG. 11, and the right side is the cross-sectional view taken along the line of FIG.

前記大梁とジョイストスラブの架構は、大梁の梁成hよ
りジョイストスラブの厚さh1を引いた残りの梁成h2断面
の底型枠a2と側型枠a1とによって型枠を形成し、対向す
る大梁間の前記側型枠a1に前記半PCジョイストスラブb1
を截架し、側型枠a1とジョイストb3と半PCスラブb2との
間に形成された隙間をふさぐ型枠a3(第11図の斜線部
分)、又はその他の手段で閉塞し大梁に梁筋、現場打ス
ラブrにスラブ補強筋を配筋し、コンクリートを打設し
て、大梁Gと半PCジョイストスラブb1に現場打スラブr
が一体になって大梁とジョイストスラブが架構される。
The frame structure of the girder and the joist slab forms a form by the bottom form a 2 and side form a 1 of the remaining beam formation h 2 cross-section obtained by subtracting the thickness h 1 of the joist slab from the beam formation h of the girder. The half PC joist slab b 1 on the side form a 1 between the facing girders.
And close the gap formed between the side mold a 1 , joist b 3 and half PC slab b 2 with a form a 3 (shaded area in Fig. 11) or other means. Beam reinforcement on the girder, slab reinforcement on the cast-in-place slab r, concrete is placed, and cast-in-place slab r is applied to the cross beam G and the semi-PC joist slab b 1.
The large beam and the joist slab are framed together.

(発明が解決しようとする課題) 前記従来の方法では、大梁の梁成よりジョイストスラブ
の厚さを引いた残りの梁成断面の型枠組と解体に手間が
掛り、前記型枠に支保工を必要とし、階高が高くなると
支保工の架設が大掛かりになる。
(Problems to be solved by the invention) In the conventional method, it takes a lot of time to form and dismantle the beam forming section of the remaining beam formed by subtracting the thickness of the joist slab from the beam forming of the large beam, and the supporting work is performed on the form. It is necessary, and as the floor height rises, the construction of shoring work becomes a large scale.

また、梁間が長スパンになると半PCジョイストスラブの
ジョイスト(小梁)の成(前記ジョイストb3と半PCスラ
ブb2との間に形成された隙間を型枠の高さに相当する)
が高くなり型枠a3部分の閉塞がますます煩雑となり工費
が嵩む。更に前記ジョイストスラブを架構する梁間が長
スパンになるとジョイストスラブの床積載荷重に対応す
るため、同スラブのジョイストの成を大きくしたり、半
PCジョイストスラブの組み立てトラス筋に大きく起りを
つけてプレストレス量を大きくするため、現場コンクリ
ート打設後のスラブ変形量が大きく、大梁とジョイスト
スラブ端部に曲げ応力がかかりひび割れの要因となる。
Also, when the span between beams becomes long span, the joist (small beam) of the half PC joist slab is formed (the gap formed between the joist b 3 and the half PC slab b 2 corresponds to the height of the formwork).
Occlusion of higher becomes mold a 3 part is increase the construction cost becomes increasingly complicated. Furthermore, if the span between the beams constructing the joist slab becomes a long span, it will correspond to the floor load of the joist slab.
Assembling of the PC joist slab The prestress amount is greatly increased by increasing the truss reinforcement, so the amount of slab deformation after placing concrete on site is large, and bending stress is applied to the large beams and the ends of the joist slab, causing cracking.

本発明は前記従来技術の有する問題点に鑑みて提案され
るもので、その目的とするところは、ジョイストスラブ
の半PCジョイストスラブを載架する大梁をプレキャスト
コンクリート梁として型枠と支保工を省略し、現場施工
の省力化と工期の短縮を図り、さらには大梁とジョイス
トスラブの接合部を補強してひび割れを防止するプレキ
ャストコンクリート大梁とジョイストスラブの架構方法
を提供する点にある。
The present invention is proposed in view of the above problems of the prior art, and its object is to omit a formwork and a supporting work as a precast concrete beam for a large beam on which a half PC joist slab of a joist slab is mounted. However, the purpose is to reduce the labor required for on-site construction and shorten the construction period, and further to provide a method of framing the precast concrete girder and joist slab that reinforces the joint between the girder and joist slab to prevent cracking.

(課題を解決するための手段) 前記の目的を達成するために、本発明に係るプレキャス
トコンクリート大梁を用いたジョイストスラブの架構方
法によれば、構造物の一階の高さSから大梁断面の成高
さS2を除く高さS1のプレキャストコンクリート柱または
現場打コンクリート柱C間に、前記大梁断面の梁成高さ
S2からジョイストスラブRのスラブ高さS41を除く断面
の梁成高さS3を有し、且つ梁側面に半プレキャストコン
クリートジョイストスラブBのジョイスト部4の各端部
が掛架する掛架用凹部1を欠截してなるプレキャストコ
ンクリート大梁Aを架設し、次いで対向する同大梁A間
に半プレキャストコンクリートスラブ部4aとスラブ下面
のジョイスト部4とで形成される半プレキャストコンク
リートジョイストスラブBの前記ジョイスト部4の各端
部を前記大梁Aの掛架用凹部に嵌合して架設し、前記大
梁Aの梁長手方向の上面に梁上主筋11を配筋し、前記大
梁A頂部長手方向の上面と、半プレキャストコンクリー
トジョイストスラブB上面で現場打コンクリートを補強
するスラブ補強筋12を配筋したのち、ジョイスト部4の
各端部にある欠截部5と半プレキャストコンクリートジ
ョイストスラブBの上面とプレキャストコンクリート大
梁Aの上面にスラブコンクリート13を打設するものであ
る。
(Means for Solving the Problems) In order to achieve the above-mentioned object, according to the method for framing a joist slab using a precast concrete girder according to the present invention, the cross section of the girder from the height S of the first floor of the structure Between the precast concrete columns or cast-in-place concrete columns C of height S 1 excluding the growth height S 2 , the beam growth height of the large beam section
A hanging recess having a beam height S 3 of a cross section excluding the slab height S 41 of the joist slab R from S 2 and each end of the joist portion 4 of the semi-precast concrete joist slab B hanging on the beam side surface. The precast concrete joist slab B is constructed by constructing a precast concrete girder A lacking 1 and then forming a semiprecast concrete slab part 4a and a joist part 4 on the lower surface of the slab between the facing girders A. Each end of the portion 4 is fitted and erected in the hanging recess of the girder A, and a beam upper main bar 11 is arranged on the upper surface of the girder A in the beam longitudinal direction. And the slab reinforcement bar 12 for reinforcing the in-situ concrete on the upper surface of the semi-precast concrete joist slab B, and then the cutout part 5 at each end of the joist part 4 The slab concrete 13 is placed on the upper surface of the semi-precast concrete joist slab B and the upper surface of the precast concrete girder A.

請求項2の発明は、前記大梁側面に掛架用凹部1を設け
たプレキャストコンクリート大梁Aを挟んで相対する半
プレキャストコンクリートジョイストスラブBにおける
ジョイスト部4の各端部箇所に、半プレキャストコンク
リートジョイストスラブB上面及び端部が開口する欠截
部5を設け、前記欠截部5間に、前記大梁A頂部を跨い
で門形の補強筋10を配筋するものである。
According to the invention of claim 2, a semi-precast concrete joist slab is provided at each end portion of the joist portion 4 in the semi-precast concrete joist slab B facing each other with a precast concrete joist A having a recess 1 for hanging on the side surface of the girder. A notched portion 5 having an open upper surface and an end portion is provided, and a gate-shaped reinforcing bar 10 is arranged between the notched portions 5 so as to straddle the top portion of the girder A.

請求項3の発明によれば、前記プレキャストコンクリー
ト大梁Aは、梁側面に前記半プレキャストコンクリート
ジョイストスラブBのジョイスト部の各端部が掛架する
掛架用凹部1を欠截するとともに、梁下主筋及びU字形
肋筋3を埋設し、同U字形の助筋の上端フック部31を梁
頂面より突設せしめるものである。
According to the invention of claim 3, the precast concrete girder A is provided with a recessed portion for hanging 1 on which each end of the joist portion of the semi-precast concrete joist slab B is hooked on the side surface of the beam, and The main bar and the U-shaped ribs 3 are buried, and the upper end hook portion 31 of the U-shaped auxiliary bar is projected from the beam top surface.

請求項4の発明によれば、前記半プレキャストコンクリ
ートジョイストスラブBは、ジョイスト部に組立トラス
筋を配筋し、同トラス筋の上弦材6が上端部より突出す
るように埋設するとともに、前記トラス筋の下弦材8の
折り曲げ端部を前記ジョイスト部4の各端部の欠截部5
内にアンカー8aとして突出するものである。
According to the invention of claim 4, in the semi-precast concrete joist slab B, an assembled truss reinforcement is arranged in the joist portion, and the upper chord member 6 of the truss reinforcement is embedded so as to project from the upper end and the truss is provided. The bent end portions of the lower chord member 8 of the muscle are connected to the cutout portions 5 at the respective end portions of the joist portion 4.
Anchor 8a projects inside.

(作用) 本発明は前記したように構成されているので、プレキャ
ストコンクリート柱、または現場打コンクリート柱間
に、プレキャストコンクリート大梁(以下、PC大梁とい
う)を架設し、同PC大梁の側面に掛架用凹部を設けて半
PCジョイストスラブのジョイスト部を同掛架用凹部に掛
架して、PC大梁の梁長手方向の上面に梁主筋を配筋し、
前記梁長手方向の上面と半PCジョイストスラブ上面で現
場打コンクリートを補強するスラブ補強筋を配筋した
後、半PCジョイストスラブの上面と各ジョイスト端部欠
截部とPC大梁の頂部を同時にコンクリートを打設するこ
とによって、半PCジョイストスラブとPC大梁が一体に接
合されて、このようにPC大梁を用いてジョイストスラブ
が架構されて、大梁のPC化によるジョイスト部の填隙用
型枠を含む型枠の組立、解体が省略され、さらには梁下
の支保工を架設することなく半PCジョイストスラブをPC
大梁に架設しうるものである。
(Operation) Since the present invention is configured as described above, a precast concrete girder (hereinafter referred to as a PC girder) is erected between precast concrete columns or cast-in-place concrete columns, and is hung on the side surface of the PC girder. Half with a recess for
The joist part of the PC joist slab is hung on the same recess for hanging, and the beam main bar is arranged on the upper surface in the beam longitudinal direction of the PC girder.
After arranging the slab reinforcing bars that reinforce the cast-in-place concrete on the upper surface in the longitudinal direction of the beam and the upper surface of the semi-PC joist slab, the upper surface of the semi-PC joist slab, each joist end groove and the top of the PC girder are simultaneously concreted. By joining, the semi-PC joist slab and the PC girder are integrally joined, and the joist slab is constructed using the PC girder in this way, and the form frame for filling the joist part by PC conversion of the girder is formed. Assembling and dismantling of the formwork including is omitted, and furthermore, half-PC joist slab is made into PC without erection of support under the beam
It can be installed on a large beam.

請求項2によれば、PC大梁側面に半PCショイストスラブ
のジョイスト部を掛架する掛架用凹部を設け、半PCジョ
イストスラブのジョイスト部に設けた欠截部が大梁Aの
掛架用凹部1に嵌合するように載架して、同部に嵌合
し、PC大梁を挟んで対向する前記半PCジョイストスラブ
の各ジョイスト端部欠截部間に、前記PC大梁の頂部を跨
いで門形の補強筋を配筋し欠截部に定着し、半PCジョイ
ストスラブの上面と各ジョイスト端部欠截部とPC大梁の
頂部を同時にコンクリートを打設することによって、半
PCジョイストスラブとPC大梁が一体に接合されて、PC大
梁とジョイストスラブが架構されてPCジョイストスラブ
の各ジョイスト間が剛に接合され、ジョイストスラブの
水平剛性の性能が向上して、ジョイストスラブとPC大梁
の接合部においてひび割れを防止する。
According to claim 2, a hanging concave portion for hanging the joist portion of the half-PC shoist slab is provided on the side surface of the PC girder, and the cutout portion provided in the joist portion of the half-PC joist slab is for hanging the girder A. It is mounted so that it fits in the concave portion 1, fits in the same portion, and straddles the top of the PC girder between the joist end cutouts of the semi-PC joist slabs that face each other across the PC girder. By arranging a gate-shaped reinforcing bar with and fixing it in the cutout part, by placing concrete on the upper surface of the half PC joist slab, each joist end cutout part and the top of the PC girder at the same time,
The PC joist slab and the PC girder are integrally joined, the PC girder and the joist slab are framed, and the joists of the PC joist slab are rigidly joined, and the horizontal rigidity performance of the joist slab is improved, and the joist slab and Prevents cracking at the joints of PC girders.

請求項3によえば、PC大梁に半PCジョイストスラブのジ
ョイスト部を掛架する掛架用凹部を設けて半PCジョイス
トスラブのジョイスト部が載架でき、また、梁下主筋及
びU字形の肋筋を埋設し、前記肋筋のU字形の上端部フ
ックを突設することによって前記上端部フックの梁長手
方向に梁上主筋が配筋され、上端部フックに門形の肋筋
を配筋し拘束して梁鉄筋を形成し、後刻打設されるコン
クリートと一体になる。
According to claim 3, the joist part of the half-PC joist slab can be mounted by providing a hanging recess for hanging the joist part of the half-PC joist slab on the PC girder. By embedding the ribs and projecting the U-shaped upper end hooks of the ribs, the beam upper main bars are arranged in the beam longitudinal direction of the upper end hooks, and the portal-shaped ribs are arranged on the upper end hooks. Then, they are restrained to form beam rebars and become integral with the concrete that will be placed later.

請求項4によれば、半PCジョイストスラブのジョイスト
部に配筋した組み立てトラス筋においては、トラス筋の
上弦材が半PCジョイストスラブ上端面に突出しているた
め、半PCジョイストスラブ上面の後刻打設される現場打
によって施工されるスラブコンクリートのシャキーとな
り半PCTジョイストスラブと現場打スラブコンクリート
が一体になり剛性が確保でき、さらには、トラス筋の下
弦材がジョイスト部端部の欠截部で露出してアンカーと
なり、PC大梁の頂部を跨いで配筋した門形の補強筋とが
定着されて後刻打設されるコンクリートと一体になり、
従来はピン接合であった相隣る半PCジョイストスラブの
ジョイスト部同志が剛になり床荷重の応力を負担する。
According to claim 4, in the assembled truss reinforcement arranged in the joist portion of the half-PC joist slab, the upper chord member of the truss muscle projects to the upper end surface of the half-PC joist slab, so that the half-PC joist slab upper surface is punched later. The half PCT joist slab and the cast-in-place slab concrete become integral as a shaky concrete of the slab concrete that is constructed by the cast in-situ to secure the rigidity, and further, the lower chord of the truss muscle is in the cutout part of the end of the joist part. It becomes exposed and becomes an anchor, and the gate-shaped reinforcing bar arranged across the top of the PC girder is fixed and becomes integral with the concrete that will be placed later,
Conventionally, the joint parts of adjacent half-PC joist slabs, which used to be pin joints, become rigid and bear the stress of floor load.

(実施例) 以下本発明を図示の実施例について説明する。(Examples) The present invention will be described below with reference to illustrated examples.

第5図は建造物の一階に相当する縦断面図で、同建造物
は柱C間に横架されたPC大梁Aと、相対する同大梁A間
に架構された半PCジョイストスラブBと、同半PCジョイ
ストスラブBに現場打コンクリートスラブ13で一体とな
ったジョイストスラブRとより構成されている。
Fig. 5 is a vertical sectional view corresponding to the first floor of the building. The building consists of a PC girder A horizontally mounted between pillars C and a half-PC joist slab B erected between opposite girders A. , Consists of the Joyst Slab R, which is an integral part of the concrete cast concrete slab 13 on the same half PC Joist Slab B.

前記柱Cの高さS1は、1階の高さSから大梁Aの梁成高
さS2を引いた高さで、プレキャストコンクリート柱又は
現場打コンクリート柱で構成されている。(第5図参
照) 第4図は第5図の平面図で、一部、ジョイストスラブR
面が示されていて、相対する柱C間にPC大梁Aが架設さ
れ、相対する同PC大梁A間に、所要数に分割された半PC
ジョイストスラブBが架設され前述のように同各半PCジ
ョイストスラブB上に現場打コンクリートスラブ13が一
体化されてジョイストスラブRが構成されている。
The height S 1 of the pillar C is a height obtained by subtracting the height S 2 of the girder A from the height S of the first floor, and is composed of a precast concrete pillar or a cast-in-place concrete pillar. (See FIG. 5) FIG. 4 is a plan view of FIG.
The surface is shown, PC girder A is erected between the opposing pillars C, and half the number of PCs are divided between the opposing PC girders A.
The joist slab B is erected, and the joist slab R is constructed by integrating the cast-in-place concrete slab 13 on each half-PC joist slab B as described above.

第6図は前記柱C間に架設されるPC大梁Aの部分拡大斜
視図で、第2図に示す如く、梁断面はジョイストスラブ
Rのスラブ厚S41を引いた梁成高さS3を有し、梁側面に
は半PCジョイストスラブBにおけるジョイスト部4の掛
架用凹部1が欠截されている。(第1図乃至第4図参
照)2は梁下主筋、3は上端面が開放されたU字形の肋
筋で、一定間隔で梁上面に突出され、上端部がフック状
に曲成されている。図中31は肋筋フック部である。
FIG. 6 is a partially enlarged perspective view of the PC girder A installed between the pillars C. As shown in FIG. 2, the beam cross section has a beam height S 3 obtained by subtracting the slab thickness S 41 of the joist slab R. The side surface of the beam has a recess 1 for hanging the joist portion 4 in the half-PC joist slab B. (See FIGS. 1 to 4) 2 is a beam lower main bar, 3 is a U-shaped rib having an open upper end surface, which is projected on the upper surface of the beam at regular intervals, and the upper end is bent like a hook. There is. In the figure, 31 is a rib bar hook.

第7図乃至第9図はジョイストスラブRの構成を示し、
半PCジョイストスラブBと現場打コンクリートスラブ13
で構成されている。
7 to 9 show the structure of the joist slab R,
Half-PC joist slab B and cast-in-place concrete slab 13
It is composed of.

半PCジョイストスラブBは半PCスラブ4aとスラブ下面の
ジョイスト部4とで形成され、同ジョイスト部4にはそ
の長さ方向に亘ってトラス筋が埋設され、同トラス筋は
上弦材6と下弦材8及び上下弦材間を連結する斜材7と
からなるトラス状に形成され、上弦材6と斜材7の一部
が半PCスラブ4a面より上面に突出している。図中2は現
場打コンクリートスラブ13の補強筋である。また9は互
いに配設された一双の上弦材と斜材7の接合金物、4bは
半PCスラブ4aの補強筋である。
The half-PC joist slab B is formed of a half-PC slab 4a and a joist portion 4 on the lower surface of the slab. The joist portion 4 is embedded with truss reinforcements along its length, and the truss reinforcements are the upper chord members 6 and the lower chords. It is formed in a truss shape composed of a member 8 and a diagonal member 7 connecting the upper and lower chord members, and a part of the upper chord member 6 and the diagonal member 7 protrudes above the half PC slab 4a surface. In the figure, 2 is a reinforcing bar of the cast-in-place concrete slab 13. Further, 9 is a metal fitting for joining the upper chord member and the diagonal member 7 arranged to each other, and 4b is a reinforcing bar of the half PC slab 4a.

更に半PCジョイストスラブBのジョイスト部4における
端部に、上面及び先端部に開口する欠截部5が設けら
れ、周欠截部5に前記トラス筋の下弦材8の端部8aが垂
直方上方に曲成され、アンカー部材が構成されている。
Further, the semi-PC joist slab B is provided at the end of the joist part 4 with a cutout 5 that opens to the upper surface and the tip, and the peripheral cutout 5 has the end 8a of the lower chord member 8 of the truss line in a vertical direction. It is bent upward to form an anchor member.

而して前記PC大梁Aを建物の1階の高さSから大梁の成
S2を引いた高さS1のPC柱または現場打コンクリート柱C
間に架設し、相対する前記PC大梁A間に前記半PCジョイ
ストスラブBを、同スラブBのジョイスト部4の欠截部
5がPC大梁の係止用凹部1に嵌合するように載架し、第
1図に示すように前記PC大梁Aを挟んで相対する半PCジ
ョイストスラブBの端部の欠截部間に亘って、前記PC大
梁Aの頂部を跨いで門形の補強筋10を配設し、欠截部5
の下弦材8のアンカーを構成する端部8aと定着する。
Then, the PC girder A is formed from the height S of the first floor of the building to the girder.
PC column or cast-in-place concrete column C with height S 1 minus S 2
The semi-PC joist slab B is mounted between the opposing PC girders A so that the cutout portion 5 of the joist portion 4 of the slab B fits into the locking recess 1 of the PC girder. Then, as shown in FIG. 1, the gate-shaped reinforcing bar 10 straddles the apex of the PC girder A across the cutouts at the ends of the half-PC joist slab B facing each other across the PC girder A. Is provided, and the missing portion 5
The lower chord member 8 is fixed to the end portion 8a constituting the anchor.

次に第3図に示すようにPC大梁Aの上面が開放された一
定間隔で突出する肋筋フック部31端部にPC大梁Aの長手
方向に大梁の梁上主筋11を配筋し、肋筋3の上端面開放
部間に門形の肋筋32を配設して肋筋3の上面開放部分を
閉じ前記半PCスラブ4a面とPC大梁A上面とに跨がって直
交するX、Y方向に現場打コンクリートスラブの補強筋
12を配筋したのち、半PCスラブ4aとジョイスト部4の欠
截部5とPC大梁Aの上部に、同時にコンクリートを打設
して現場打コンクリートスラブ13を施工し、半PCジョイ
ストスラブBとPC大梁Aとが一体に接合されたジョイス
トスラブRとPC大梁Aを施工する。
Next, as shown in FIG. 3, the upper main bars 11 of the girders of the girders are arranged in the longitudinal direction of the PC girder A at the ends of the rib bar hooks 31 projecting at regular intervals with the upper surface of the PC girder A open. A gate-shaped rib 32 is arranged between the open upper end portions of the muscles 3 to close the upper open portion of the ribs 3 and is orthogonal to the half PC slab 4a surface and the PC girder A upper surface X, Reinforcing bars for cast-in-place concrete slabs in Y direction
After arranging 12, half-PC slab 4a, joist part 4 missing part 5 and the upper part of PC girder A, at the same time, concrete is poured, and on-site concrete slab 13 is installed, and half-PC joist slab B and The joist slab R and the PC girder A, which are integrally joined to the PC girder A, are constructed.

このように前記実施例によれば、大梁をPC大梁Aとし
て、半PCジョイストスラブBのジョイスト部が前記PC大
梁Aの掛架用凹部1に掛架するようにしたので、従来の
大梁をPC化したことにより、ジョイスト部の填隙用型枠
を含む大梁の型枠が省略され、また支保工も不用とな
り、更に半PCジョイストスラブBのジョイスト部4に欠
截部5を設けてPC大梁Aを跨いで相対する前記欠截部5
に補強筋10でジョイスト部4の下弦材8の端部8aと定着
し、PC大梁Aの上面を含む現場打コンクリートスラブ13
に同スラブ補強筋12を配筋し、同部に現場打コンクリー
トスラブ13を施工することによって半PCジョイストスラ
ブBとPC大梁Aとが一体に接合され、ジョイストスラブ
RとPC大梁Aが架構され、同ジョイストスラブRの水平
剛性の性能が向上し、ジョイストスラブRとPC大梁Aと
の接合部におけるひび割れの発生を防止する。
As described above, according to the embodiment, the girder is the PC girder A, and the joist portion of the half-PC joist slab B is hung in the hanging recess 1 of the PC girder A. As a result, the formwork of the girder including the formwork for filling the joist part is omitted, and the supporting work is also unnecessary, and the joist part 4 of the half-PC joist slab B is further provided with the cutout part 5 to form the PC girder. The aforesaid cut-out portion 5 facing across A
In addition to the end 8a of the lower chord member 8 of the joist part 4 with the reinforcing bar 10, the cast-in-place concrete slab 13 including the upper surface of the PC girder A is fixed.
By arranging the slab reinforcement bar 12 on the above, and by constructing a cast-in-place concrete slab 13 in the same part, the half-PC joist slab B and the PC girder A are integrally joined, and the joist slab R and the PC girder A are framed. , The horizontal rigidity performance of the joist slab R is improved, and the occurrence of cracks at the joint between the joist slab R and the PC girder A is prevented.

(発明の効果) 本発明によれば前記したように、建造物の1階の高さS
から大梁断面の梁成高さS2を除いた高さS1のプレキャス
トコンクリート柱または現場打コンクリート柱間に架設
された大梁断面の梁成高さS2を除く高さS1の相対するプ
レキャストコンクリート大梁Aの側面に欠截された掛架
用凹部に、同大梁A間に配設された半プレキャストコン
クリートジョイストスラブにおけるジョイスト部の端部
を嵌合することによって、同ジョイストスラブを前記大
梁Aに架設するように構成されているので、従来のよう
に大梁の型枠の組立や解体がなく、更にサポートの架設
が不要となり、現場作業の大幅な省力化が図られ、工費
が節減される。
(Effect of the invention) According to the present invention, as described above, the height S of the first floor of the building is
From the girder section RyoNaru height S 2 the height S 1 except for girder cross-section bridges the precast concrete column or field hitting concrete pillars RyoNaru height relative precast concrete girders A height S 1 except for S 2 The joist slab is erected on the girder A by fitting the ends of the joist portion of the semi-precast concrete joist slab arranged between the girders A into the hanging recesses formed on the side surfaces. Since it is configured as above, there is no need to assemble and dismantle the girder formwork as in the prior art, and further, it is not necessary to erect a support, which greatly saves on-site work and saves construction cost.

また前記半PCジョイストスラブにおける大梁A側面の掛
架用凹部に嵌合されるジョイスト部の端部に、上面及び
端面に開口する欠截部が設けられているので、同欠截部
に補強筋を配筋し、コンクリートを打設することによ
り、前記大梁Aと半PCジョイストスラブとをより確実
に、一体的に接合しうるものである。
Further, since the end portion of the joist portion fitted into the hanging concave portion on the side surface of the girder A in the half-PC joist slab is provided with a cutout portion that is open to the upper surface and the end surface, a reinforcement bar is provided in the cutout portion. By arranging and arranging concrete, the large beam A and the semi-PC joist slab can be more surely and integrally joined.

請求項2の発明は、前記半PCジョイストスラブにおける
ジョイスト部の端部の欠截部を利用し、前記大梁Aを挟
んで対向する一対の半PCジョイストスラブにおける前記
各欠截部間に、前記大梁Aを頂部を跨ぐ補強筋を配筋す
るとともに、前記半PCジョイストスラブ間にスラブ補強
筋を配筋したのち、前記大梁A上部およびジョイスト部
の各端部欠截部及び前記半PCジョイストスラブ上部にコ
ンクリートを打設することによって、前記大梁Aと半PC
ジョイストスラブを一体に接合し、スラブの水平剛性を
向上するとともに、ひび割れの発生を、防止しうるもの
である。
The invention of claim 2 uses the cutout portions at the ends of the joist portion of the half-PC joist slab, and between the cutout portions of the pair of half-PC joist slabs facing each other across the girder A. After arranging reinforcing bars straddling the girder A over the apex and arranging slab reinforcing bars between the half PC joist slabs, each upper end of the girder A and the joist part are provided with a cutout portion and the half PC joist slab. By placing concrete on the top, the large beam A and half PC
By joining the joist slabs together, the horizontal rigidity of the slab can be improved and the occurrence of cracks can be prevented.

請求項3の発明は、前記大梁Aに梁下端筋及びU字形肋
筋を埋設し、同肋筋の上端フック部を梁頂面より突出さ
せて、後打ちコンクリートとの一体化を図るとともに、
部材側面に前記半PCジョイストスラブにおけるジョイス
ト端部の掛架用凹部を欠截したことによって、半PCジョ
イストスラブを大梁Aにサポートなしで架設しるように
したものである。
In the invention of claim 3, a beam lower end bar and a U-shaped rib are embedded in the girder A, and an upper end hook portion of the rib is projected from the beam top surface to achieve integration with post-cast concrete,
The semi-PC joist slab is erected on the girder A without support because the recess for hanging the joist end of the semi-PC joist slab is omitted on the side surface of the member.

請求項4の発明は、前記半プレキャストコンクリートジ
ョイストスラブのジョイスト部に埋設した組立トラス筋
の上弦材を、スラブ上面に突出せしめることによって、
後打ちコンクリートとの一体化を図り、前記組立トラス
筋の下弦材をジョイスト端部の欠截部内に突出させるこ
とによって、同ジョイスト部と前記大梁Aとを一体的に
接合せしめるようにしたものである。
According to the invention of claim 4, the upper chord member of the assembled truss reinforcement embedded in the joist portion of the semi-precast concrete joist slab is made to project to the upper surface of the slab,
By integrating the post-casting concrete with the lower truss member of the assembled truss bar, the joist part and the girder A can be integrally joined by projecting the lower chord member into the cutout part of the joist end. is there.

【図面の簡単な説明】[Brief description of drawings]

第1図及び第2図は本発明に係るプレキャストコンクリ
ート大梁を用いたジョイストスラブの架構工法の一実施
例の工程を示す縦断面図、第3図は第1図の平面図、第
4図は半プレキャストコンクリートジョイストスラブの
架設が完了した状態を示す平面図で一部床面を表す、第
5図は第4図の矢視V−V図、第6図はプレキャストコ
ンクリート大梁Aの部分斜視図、第7図は半プレキャス
トコンクリートジョイストスラブと現場打コンクリート
スラブの縦断面図、第8図及び第9図は夫々そのジョイ
スト部の端部を示す斜視図並びに正面図、第10図及び第
11図は夫々従来工法の実施状況を示す縦断面図並びに縦
断側面図で、第10図左半部及び右半部は夫々第11図の矢
視イ−イ図並びに矢視ロ−ロ図である。 A……プレキャストコンクリート大梁、 B……半プレキャストコンクリートジョイストスラブ、 C……プレキャストコンクリート柱または現場打コンク
リート柱、 R……ジョイストスラブ、 1……掛架用凹部、2……梁下主筋、3……肋筋、 31……肋筋フック部、4……ジョイスト部、 4a……半プレキャストコンクリートスラブ、 5……ジョイスト端部の欠截部、 6……上弦材、7……斜材、8……下弦材、 8a……下弦材の端部、9……接合金物、10……補強筋 11……梁上主筋、 12……現場打コンクリートスラブ補強筋、 13……現場打コンクリートスラブ。
1 and 2 are vertical cross-sectional views showing the steps of an embodiment of a method for constructing a joist slab frame structure using a precast concrete girder according to the present invention, FIG. 3 is a plan view of FIG. 1, and FIG. FIG. 5 is a partial perspective view of the precast concrete girder A, and FIG. 5 is a view showing a part of the floor surface in a plan view showing a state where the semi-precast concrete joist slab has been installed. , FIG. 7 is a longitudinal sectional view of a semi-precast concrete joist slab and a cast-in-place concrete slab, and FIGS. 8 and 9 are a perspective view and a front view showing the end of the joist portion, FIG. 10 and FIG.
Fig. 11 is a longitudinal sectional view and a longitudinal side view showing the state of implementation of the conventional method, respectively. Fig. 10 shows the left half part and the right half part in the arrow ii diagram and the arrow roll diagram of Fig. 11, respectively. is there. A: precast concrete girder, B: semi-precast concrete joist slab, C: precast concrete column or cast-in-place concrete column, R: joist slab, 1 ... hanging recess, 2 ... beam main bar, 3 ... ribs, 31 ... rib hooks, 4 ... joist part, 4a ... semi-precast concrete slab, 5 ... joist end cutout part, 6 ... upper chord member, 7 ... diagonal member, 8 …… Lower chord material, 8a …… End of lower chord material, 9 …… Joint hardware, 10 …… Reinforcing bar 11 …… Main bar of beam, 12 …… Reinforcing concrete slab reinforcing bar, 13 …… In-situ concrete slab .

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】建造物の一階の高さSから大梁断面の成高
さS2を除く高さS1のプレキャストコンクリート柱または
現場打コンクリート柱C間に、前記大梁断面の梁成高さ
S2からジョイストスラブRのスラブ高さS41を除く断面
の梁成高さS3を有し、且つ梁側面に半プレキャストコン
クリートジョイストスラブBのジョイスト部4の各端部
が掛架する掛架用凹部1を欠截してなるプレキャストコ
ンクリート大梁Aを架設し、次いで対向する同大梁A間
に半プレキャストコンクリートスラブ部4aとスラブ下面
のジョイスト部4とで形成される半プレキャストコンク
リートジョイストスラブBの前記ジョイスト部4の各端
部を前記大梁Aの掛架用凹部1に嵌合して架設し、前記
大梁Aの梁長手方向の上面に梁上主筋11を配筋し、前記
大梁A頂部長手方向の上面と、半プレキャストコンクリ
ートジョイストスラブB上面で現場打コンクリートを補
強するスラブ補強筋12を配筋したのち、ジョイスト部4
の各端部にある欠截部5と半プレキャストコンクリート
ジョイストスラブBの上面とプレキャストコンクリート
大梁Aの上面にスラブコンクリート13を打設することを
特徴とするプレキャストコンクリート大梁を用いたジョ
イストスラブの架構工法。
1. A one-story precast concrete column height S 1 except Narudaka of S 2 of the girder section from S or inter-site punch concrete column C of buildings, RyoNaru height of the girder section
A hanging recess having a beam height S 3 of a cross section excluding the slab height S 41 of the joist slab R from S 2 and each end of the joist portion 4 of the semi-precast concrete joist slab B hanging on the beam side surface. The precast concrete joist slab B is constructed by constructing a precast concrete girder A lacking 1 and then forming a semiprecast concrete slab part 4a and a joist part 4 on the lower surface of the slab between the facing girders A. Each end of the portion 4 is fitted and installed in the hanging recess 1 of the girder A, and a beam upper main bar 11 is arranged on the upper surface of the girder A in the beam longitudinal direction. After arranging slab reinforcement bars 12 for reinforcing in-situ cast concrete on the upper surface and the upper surface of the semi-precast concrete joist slab B, the joist portion 4
The construction method of the joist slab using the precast concrete girder characterized by placing the slab concrete 13 on the upper surface of the semi-precast concrete joist slab B and the upper surface of the precast concrete girder A at each end of the .
【請求項2】前記大梁側面に掛架用凹部1を設けたプレ
キャストコンクリート大梁Aを挟んで相対する半プレキ
ャストコンクリートジョイストスラブBにおけるジョイ
スト部4の各端部箇所に、半プレキャストコンクリート
ジョイストスラブB上面及び端部が開口する欠截部5を
設け、同欠截部5間に、前記大梁A頂部を跨いで門形の
補強筋10を配設する請求項1記載のプレキャストコンク
リート大梁を用いたジョイストスラブの架構工法。
2. An upper surface of a semi-precast concrete joist slab B at each end portion of the joist part 4 in the semi-precast concrete joist slab B facing each other with a precast concrete girder A having a recess 1 for hanging on the side surface of the girder. A joyce using a precast concrete girder according to claim 1, further comprising: a cutout portion 5 having an open end, and a gate-shaped reinforcing bar 10 is provided between the cutout portions 5 so as to straddle the top of the girder A. Toslab frame construction method.
【請求項3】前記プレキャストコンクリート大梁Aは、
梁側面に前記半プレキャストコンクリートジョイストス
ラブBのジョイスト部の各端部が掛架する掛架用凹部1
を欠截するとともに、梁下主筋及びU字形肋筋3を埋設
し、同U字形の肋筋の上端フック部31を梁頂面より突設
せしめる請求項1記載のプレキャストコンクリート大梁
を用いたジョイストスラブの架構工法。
3. The precast concrete girder A comprises:
Hanging recess 1 for hanging each end of the joist portion of the semi-precast concrete joist slab B on the beam side surface
The joystick using the precast concrete girder according to claim 1, wherein the main beam under the beam and the U-shaped rib 3 are embedded, and the upper end hook portion 31 of the U-shaped rib is projected from the top surface of the beam. Toslab frame construction method.
【請求項4】前記半プレキャストコンクリートジョイス
トスラブBは、ジョイスト部に組立トラス筋を配筋し、
同トラス筋の上弦材6が上端面より突出するように埋設
するとともに、前記トラス筋の下弦材8の折り曲げ端部
を前記ジョイスト部4の各端部の欠截部5内にアンカー
8aとして突出せしめる請求項1記載のプレキャストコン
クリート大梁を用いたジョイストスラブの架構工法。
4. The semi-precast concrete joist slab B has an assembly truss bar arranged in a joist portion,
The upper chord member 6 of the truss reinforcement is embedded so as to project from the upper end surface, and the bent end portions of the lower chord member 8 of the truss reinforcement are anchored in the cutout portions 5 of the respective end portions of the joist portion 4.
The method for constructing a joist slab using a precast concrete girder according to claim 1, which is made to project as 8a.
JP7865189A 1989-03-31 1989-03-31 Construction method of joist slab using precast concrete girder Expired - Lifetime JPH0781355B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7865189A JPH0781355B2 (en) 1989-03-31 1989-03-31 Construction method of joist slab using precast concrete girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7865189A JPH0781355B2 (en) 1989-03-31 1989-03-31 Construction method of joist slab using precast concrete girder

Publications (2)

Publication Number Publication Date
JPH02261145A JPH02261145A (en) 1990-10-23
JPH0781355B2 true JPH0781355B2 (en) 1995-08-30

Family

ID=13667766

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7865189A Expired - Lifetime JPH0781355B2 (en) 1989-03-31 1989-03-31 Construction method of joist slab using precast concrete girder

Country Status (1)

Country Link
JP (1) JPH0781355B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180052835A (en) * 2016-11-10 2018-05-21 동서 피, 씨, 씨 주식회사 PC double beam-column joint structure for securing of seismic performance

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100763979B1 (en) * 2007-05-07 2007-10-05 정도건설 주식회사 Underground Parking Lot Multi Slab
CN106948548A (en) * 2017-04-26 2017-07-14 广西大学 A kind of precast concrete frame beam structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180052835A (en) * 2016-11-10 2018-05-21 동서 피, 씨, 씨 주식회사 PC double beam-column joint structure for securing of seismic performance

Also Published As

Publication number Publication date
JPH02261145A (en) 1990-10-23

Similar Documents

Publication Publication Date Title
JP3701078B2 (en) Road slab construction method
JPH0781355B2 (en) Construction method of joist slab using precast concrete girder
JPH10227010A (en) Steel form with main reinforcement for bridge floor panel and bridge floor panel construction method using it
JP2622013B2 (en) Reinforced concrete shear wall structure
JP2758208B2 (en) Joint method between column and steel reinforced concrete beam
JPH084196A (en) Building panel
JPH084195A (en) Building panel
JPH0380946B2 (en)
JPS6195136A (en) Construction of multistoried building skeletal by precast reinforced concrete unit
JP2972955B2 (en) Column and beam joining method and its structure
JPH03279533A (en) Construction method for rigid-frame RC high-rise building
JPH10227011A (en) Steel form with main reinforcement for bridge floor, and construction of bridge floor using the form
JPS5926001Y2 (en) Precast beam and girder joint structure
JPS6335773B2 (en)
JPS6035638Y2 (en) panel foundation
JPH0650010B2 (en) Precast version
JPH0715177B2 (en) How to build a reinforced concrete structure
JPH0522777B2 (en)
JPH0588331B2 (en)
JPS62182329A (en) Method of constructing concrete structures
JPH1113015A (en) Arch slab type viaduct, and its execution method
JPH0742755B2 (en) Construction method of PC synthetic flat slab
JPS63297643A (en) Construction of precast reinforced concrete structure
JPH01137033A (en) Framework of composite building construction
JPH07139068A (en) Floor slab with half-PC beam