JPH0688347A - Constructing method of post - Google Patents

Constructing method of post

Info

Publication number
JPH0688347A
JPH0688347A JP4239784A JP23978492A JPH0688347A JP H0688347 A JPH0688347 A JP H0688347A JP 4239784 A JP4239784 A JP 4239784A JP 23978492 A JP23978492 A JP 23978492A JP H0688347 A JPH0688347 A JP H0688347A
Authority
JP
Japan
Prior art keywords
coupler
members
concrete
connection
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4239784A
Other languages
Japanese (ja)
Inventor
Jun Nomura
潤 野村
Etsunori Tamura
悦徳 田村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP4239784A priority Critical patent/JPH0688347A/en
Publication of JPH0688347A publication Critical patent/JPH0688347A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To connect a hollow PC member simply and efficiently. CONSTITUTION:Hollow PC members 1, 2 are connected in upper and lower sections, and concrete is placed, thus constructing a post. Hardware for temporary fixing is driven previously to the connecting sections of both PC members 1, 2 while post main reinforcements 5, 6 are driven to both PC members 1, 2, and a cylindrical coupler 7 a lower end of which is opened is installed to the lower section of the post main reinforcement 5 of the upper-section PC member 1. On the other hand, a blocking plate 9 blocking the lower-end opening of the coupler 7 and a nut 10 as a jig fixing the blocking plate 9 are mounted previously to a screw reinforcement as the post main reinforcement 6 of the lower-section PC member 2, the state, in which both PC members 1, 2 are fixed by the hardware for temporary fixing, is brought at the time of connection, the upper end of the post main reinforcement 6 of the lower-section PC member 2 is inserted into the coupler 7 of the upper-section PC member 1 while the lower-end opening of the coupler 7 is blocked by the blocking plate 9 and fastened by the nut 10, and the inside of the coupler 7 is filled with grout 11 and the connecting sections are sealed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、中空PC部材を用いて
柱主筋の接続を行う柱の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a column in which a column main bar is connected using a hollow PC member.

【0002】[0002]

【従来の技術】従来、鉄筋コンクリート建造物を構築す
るにあたり、柱構築用に先組みした柱鉄筋を施工場所に
取付けるとともに、この柱鉄筋を覆うように柱型枠をセ
ットし、その後コンクリートを打設して柱を構築するこ
とが行われている。
2. Description of the Related Art Conventionally, in constructing a reinforced concrete building, a column rebar previously assembled for building a column is attached to a construction site, a column form is set to cover the column rebar, and then concrete is poured. Then the pillars are being constructed.

【0003】なお、地下階の柱の構築に際しては一般
に、杭のコンクリート打設後、孔内を一度埋戻し、切梁
を架けながら根切を行い、その後、杭頭部の不良コンク
リートを斫った後、柱の鉄筋、型枠、コンクリート工事
を行っている。
[0003] Generally, when constructing a pillar on the basement floor, after the concrete is placed in the pile, the inside of the hole is backfilled once, root cutting is performed while the crossbeam is installed, and then the defective concrete at the pile head is removed. After that, the pillar rebar, formwork, and concrete work are being done.

【0004】また、逆打ち工法を採用する場合、中空P
C部材を使用し、杭のコンクリート打設後、中空PC部
材を杭コンクリート中に挿入設置することも知られてい
る。
When the reverse casting method is adopted, hollow P
It is also known to use a C member and insert a hollow PC member into the pile concrete after placing the concrete into the pile.

【0005】[0005]

【発明が解決しようとする課題】ところで、地下階が深
い場合において、中空PC部材を上下に接続し、該PC
部材の接続後にコンクリート打設を行って柱を構築する
方法が知られている。この場合、中空PC部材には予め
柱主筋が打込まれるが、その柱主筋の接続に比較的多く
の手間が掛かり、ひいては柱構築の工期が長くなる等の
問題がある。
By the way, when the basement is deep, the hollow PC members are connected vertically and the
A method is known in which concrete is poured after connecting members to construct columns. In this case, the column main bars are preliminarily driven into the hollow PC member, but there is a problem that connection of the column main bars takes a relatively large amount of time and, in turn, the construction period of the columns becomes long.

【0006】本発明は上記の問題を解決するためになさ
れたもので、その目的は、簡便で能率よく中空PC部材
の接続が行える柱の構築方法を提供することにある。
The present invention has been made to solve the above problems, and an object of the present invention is to provide a method of constructing a column which enables simple and efficient connection of hollow PC members.

【0007】[0007]

【課題を解決するための手段】前記の目的を達成するた
めに本発明は、中空PC部材を上下に接続し、該部材の
接続後にコンクリート打設を行って柱を構築する方法で
あって、予め両PC部材同士の接続部に仮固定用金物を
打込むとともに、両PC部材に柱主筋を打込み、かつ上
部PC部材の柱主筋の下部に下端が開口した筒状のカプ
ラを取付ける一方、下部PC部材の柱主筋に前記カプラ
の下端開口を閉塞する閉塞板とこれを止着する治具とを
装着しておき、接続時において、両PC部材を仮固定用
金物で固定した状態として、上部PC部材のカプラ内に
下部PC部材の柱主筋の上端を挿入するとともに、カプ
ラ下端開口を閉塞板で閉塞して治具で止着した後、カプ
ラ内にグラウトを充填して接続部を封止するものであ
る。
In order to achieve the above-mentioned object, the present invention is a method for constructing a pillar by connecting hollow PC members up and down, and then concrete-casting after connecting the members. In addition to driving the temporary fixing hardware into the connecting portion between both PC members in advance, driving the column main bar into both PC members, and attaching the tubular coupler with the lower end opened to the lower part of the column main bar of the upper PC member, while lower part An obstruction plate that obstructs the lower end opening of the coupler and a jig that fastens the obstruction plate are attached to the pillar main bars of the PC member, and at the time of connection, both PC members are fixed with a temporary fixing hardware, Insert the upper end of the column main bar of the lower PC member into the coupler of the PC member, close the lower end opening of the coupler with the closing plate and fix it with the jig, then fill the grout into the coupler and seal the connection part. To do.

【0008】[0008]

【作用】本発明によると、予め両PC部材同士の接続部
に打込んだ仮固定用金物で接続状態としておき、上部P
C部材の柱主筋のカプラ内に下部PC部材の柱主筋の上
端を挿入するとともに、カプラ下端開口を閉塞板で閉塞
して治具で止着した後、カプラ内にグラウトを充填して
接続部を封止するので、PC部材の接続が簡便かつ能率
よく行える。
According to the present invention, a temporary fixing metal member which has been previously driven into a connecting portion between both PC members is used to establish a connection state, and the upper portion P
Insert the upper end of the column main bar of the lower PC member into the coupler of the column main bar of the C member, close the lower end opening of the coupler with the closing plate and fix it with a jig, and then fill the inside of the coupler with grout to connect. Since it is sealed, the PC member can be connected easily and efficiently.

【0009】したがって、このようにして接続された中
空PC部材を使用して、杭の鉄筋設置後、杭のコンクリ
ートの打設に引続いてPC部材内でコンクリート打設を
行えば一回の打設で柱と杭が施工でき、工期の短縮等が
有効的に図れるようになる。
Therefore, if the hollow PC members thus connected are used, after the reinforcement of the pile is installed, if the concrete is placed in the PC member subsequent to the placement of the concrete in the pile, one shot is made. Pillars and piles can be constructed and the construction period can be shortened effectively.

【0010】[0010]

【実施例】以下、本発明の一実施例を図面を参照して説
明する。本実施例は上下一対のPC部材を接合して柱を
構築する場合についてのもので、図1は接続前の状態、
図2はその要部の拡大、図3は接続後の状態をそれぞれ
示し、さらに図4は現場組立ての他の例を示している。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. This embodiment relates to a case where a pair of upper and lower PC members are joined to construct a column, and FIG. 1 shows a state before connection.
FIG. 2 shows an enlarged view of the main part, FIG. 3 shows the state after connection, and FIG. 4 shows another example of on-site assembly.

【0011】図1に示すように、本実施例では予め、遠
心成形の両PC部材1,2の接続部1a,2aに、仮固
定用金物として塞ぎ型枠4保持用のエレクションピース
3を打込むとともに、両PC部材1,2に柱主筋5,6
を打込んでおく。
As shown in FIG. 1, in the present embodiment, the erection piece 3 for holding the closing mold 4 as a temporary fixing metal piece is previously struck on the connecting portions 1a, 2a of the centrifugally molded PC members 1, 2. While inserting, the pillar main bars 5, 6 on both PC members 1, 2
Type in.

【0012】また、図2に示すように、上部PC部材1
の柱主筋5の下部に、下端が開口した筒状のカプラ7を
取付けている。このカプラ7には、グラウト充填用の孔
8が開けてある。
Further, as shown in FIG. 2, the upper PC member 1
A cylindrical coupler 7 having an open lower end is attached to the lower portion of the column main bar 5. The coupler 7 has a hole 8 for filling grout.

【0013】一方、下部PC部材2の柱主筋6は、ねじ
鉄筋とし、このねじ鉄筋にカプラ7の下端開口を閉塞す
る閉塞板9とこれを止着するナット10とを装着してあ
る。しかして接続時においては、図3に示すように、両
PC部材1,2を仮固定用金物で固定した状態として、
上部PC部材1のカプラ7内に下部PC部材2の柱主筋
であるねじ鉄筋6の上端を挿入するとともに、カプラ7
下端開口を閉塞板9で閉塞してナット10で止着する。
この状態で、カプラ7内に孔8を介してグラウト11を
充填し、接続部を封止する。
On the other hand, the pillar main bar 6 of the lower PC member 2 is a threaded reinforcing bar, and a closing plate 9 for closing the lower end opening of the coupler 7 and a nut 10 for fixing the same are attached to the threaded reinforcing bar. Then, at the time of connection, as shown in FIG. 3, both the PC members 1 and 2 are fixed with the temporary fixing hardware,
The upper end of the screw reinforcing bar 6 which is the column main bar of the lower PC member 2 is inserted into the coupler 7 of the upper PC member 1, and the coupler 7
The lower end opening is closed with a closing plate 9 and fixed with a nut 10.
In this state, the grout 11 is filled in the coupler 7 through the hole 8 to seal the connection portion.

【0014】なお、本実施例では柱主筋6としてねじ鉄
筋を用いた場合を例にとって説明したが、柱主筋6とし
ては通常使用されている異形鉄筋であっても、勿論良
い。
In the present embodiment, the case where the screw reinforcing bars are used as the column main bars 6 has been described as an example, but the column main bars 6 may of course be deformed rebars that are normally used.

【0015】このようにして接続された中空PC部材
1,2を使用して、例えば杭の鉄筋設置後、杭のコンク
リートの打設に引続いてPC部材1,2内でコンクリー
ト打設を行うものである。
Using the hollow PC members 1 and 2 connected in this manner, for example, after the reinforcement of the pile is installed, the concrete is cast in the PC members 1 and 2 subsequently to the placing of the concrete in the pile. It is a thing.

【0016】したがって、本実施例の方法によると、予
め両PC部材1,2の接続部に打込んだ仮固定用金物で
接続状態としておき、上部PC部材1の柱主筋5のカプ
ラ7内に下部PC部材2のねじ鉄筋6の上端を挿入する
とともに、カプラ7下端開口を閉塞板9で閉塞してナッ
ト10で止着した後、カプラ7内にグラウト11を充填
して接続部を封止するので、PC部材の接続が簡便かつ
能率よく行える。
Therefore, according to the method of the present embodiment, the connection is made in advance by the provisional fixing hardware that has been driven into the connection portions of both PC members 1 and 2, and the connection is made in the coupler 7 of the column main bar 5 of the upper PC member 1. After inserting the upper end of the screw rebar 6 of the lower PC member 2 and closing the lower end opening of the coupler 7 with the closing plate 9 and fixing with the nut 10, the coupler 7 is filled with the grout 11 to seal the connection portion. Therefore, the PC members can be connected easily and efficiently.

【0017】そして、杭の鉄筋設置後、杭のコンクリー
トの打設に引続いてPC部材1,2内でコンクリート打
設を行えば一回の打設で柱と杭が施工でき、工期の短縮
等が有効的に図れるようになる。
After the pile reinforcement is installed, if the concrete is placed in the PC members 1 and 2 after the concrete is placed in the pile, the pillar and the pile can be constructed in one shot, which shortens the construction period. Etc. can be effectively achieved.

【0018】なお、現場施工に際しては、図4に示すよ
うに、予め地上等において、両PC部材1,2を横方向
で接続し、その後図3に示すように縦状態としてもよ
い。
At the time of on-site construction, both PC members 1 and 2 may be connected laterally in advance on the ground as shown in FIG. 4 and then put in a vertical state as shown in FIG.

【0019】[0019]

【発明の効果】以上で詳述したように、本発明によれ
ば、予め両PC部材の接続部に打込んだ仮固定用金物で
接続状態としておき、上部PC部材の柱主筋のカプラ内
に下部PC部材の柱主筋の上端を挿入するとともに、カ
プラ下端開口を閉塞板で閉塞して治具で止着した後、カ
プラ内にグラウトを充填して接続部を封止するので、P
C部材の接続が簡便かつ能率よく行える。
As described above in detail, according to the present invention, the connection is made in advance with the temporary fixing metal fittings that have been driven into the connection portions of both PC members, and the connection is made in the coupler of the column main bar of the upper PC member. Since the upper end of the column main bar of the lower PC member is inserted, the coupler lower end opening is closed with a closing plate and fixed by a jig, the coupler is filled with grout to seal the connection portion.
Connection of the C member can be performed easily and efficiently.

【0020】したがって、このようにして接続された中
空PC部材を使用して、杭の鉄筋設置後、杭のコンクリ
ートの打設に引続いてPC部材内でコンクリート打設を
行えば一回の打設で柱と杭が施工でき、工期の短縮等が
有効的に図れるようになる。
Therefore, when the hollow PC members thus connected are used, after placing the reinforcing bars of the pile, if the concrete is placed in the PC member subsequent to the placement of the concrete in the pile, one shot is made. Pillars and piles can be constructed and the construction period can be shortened effectively.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例を示すもので、接続前の状態
の説明図である。
FIG. 1 illustrates an embodiment of the present invention and is an explanatory diagram of a state before connection.

【図2】(A),(B)は図1における要部の拡大図で
ある。
2A and 2B are enlarged views of a main part in FIG.

【図3】接続後の状態を示す説明図である。FIG. 3 is an explanatory diagram showing a state after connection.

【図4】現場組立ての他の例を示す説明図である。FIG. 4 is an explanatory diagram showing another example of on-site assembly.

【符号の説明】[Explanation of symbols]

1,2 PC部材 5,6 柱主筋 7 カプラ 9 閉塞板 10 ナット 11 グラウト 1, 2 PC member 5, 6 Column main bar 7 Coupler 9 Closing plate 10 Nut 11 Grout

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 中空PC部材を上下に接続し、該部材の
接続後にコンクリート打設を行って柱を構築する方法で
あって、予め両PC部材同士の接続部に仮固定用金物を
打込むとともに、両PC部材に柱主筋を打込み、かつ上
部PC部材の柱主筋の下部に下端が開口した筒状のカプ
ラを取付ける一方、下部PC部材の柱主筋に前記カプラ
の下端開口を閉塞する閉塞板とこれを止着する治具とを
装着しておき、接続時において、両PC部材を仮固定用
金物で固定した状態として、上部PC部材のカプラ内に
下部PC部材の柱主筋の上端を挿入するとともに、カプ
ラ下端開口を閉塞板で閉塞して治具で止着した後、カプ
ラ内にグラウトを充填して接続部を封止することを特徴
とする柱の構築方法。
1. A method of constructing a pillar by connecting hollow PC members up and down and then concrete-placing after connecting the members, wherein a temporary fixing metal object is preliminarily driven into a connecting portion between both PC members. At the same time, a columnar bar is driven into both PC members, and a tubular coupler having an open lower end is attached to the lower part of the column main bar of the upper PC member, while a closing plate for closing the lower end opening of the coupler to the column main bar of the lower PC member. And a jig for fixing the same are attached, and at the time of connection, both the PC members are fixed by a temporary fixing metal object, and the upper end of the column main bar of the lower PC member is inserted into the coupler of the upper PC member. In addition, the method for constructing a column is characterized in that the coupler lower end opening is closed with a closing plate and fixed by a jig, and then the coupler is filled with grout to seal the connection portion.
JP4239784A 1992-09-08 1992-09-08 Constructing method of post Pending JPH0688347A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4239784A JPH0688347A (en) 1992-09-08 1992-09-08 Constructing method of post

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4239784A JPH0688347A (en) 1992-09-08 1992-09-08 Constructing method of post

Publications (1)

Publication Number Publication Date
JPH0688347A true JPH0688347A (en) 1994-03-29

Family

ID=17049836

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4239784A Pending JPH0688347A (en) 1992-09-08 1992-09-08 Constructing method of post

Country Status (1)

Country Link
JP (1) JPH0688347A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8959935B2 (en) 2009-04-17 2015-02-24 Leica Biosystems Nussloch Gmbh Freezing microtome and method for producing microscopable thin sections

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8959935B2 (en) 2009-04-17 2015-02-24 Leica Biosystems Nussloch Gmbh Freezing microtome and method for producing microscopable thin sections

Similar Documents

Publication Publication Date Title
JP3900344B2 (en) Column-to-pile connection structure of steel structure building and its construction method
JP4467881B2 (en) Pile head joint structure and pile head fitting cylinder
JPH0762753A (en) Method of joining skeleton and splice sleeve used therefor
US7165916B2 (en) Method of on-site construction of concrete column and panel fence system
JP3603130B2 (en) Root-wound reinforcement structure for column bases such as steel columns
US5806262A (en) Post and method of emplacing a post
JPH0688347A (en) Constructing method of post
JP4420697B2 (en) Standing structure of steel pipe columns
JP2004011203A (en) Precast SRC column joint structure
JP2000034732A (en) Steel column mounting hardware, steel column mounting structure and steel column building method
JPH0784764B2 (en) A cage formwork for removing the box of the steel column base fixing part in the SRC building
JP3029343U (en) Form tool for mortar material injection in exposed elastic fixed column base method
JPH0232417B2 (en)
JPH0329929B2 (en)
JP2000034733A (en) Footing structure
JPH116162A (en) Construction method for reinforced concrete underground external wall
JPH10252144A (en) Erection method for steel pipe column
JP3232487B2 (en) Construction method of column base and column base structure
JPH06280271A (en) Cast-in-place steel pipe concrete pile-column construction and construction method thereof
JPH11181807A (en) Construction method for underground story
JPH04353125A (en) Foundation constructing method for building
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JPH028089B2 (en)
JPS59653B2 (en) Foundation construction method for main pillars such as fences