[go: up one dir, main page]

JPH0684619B2 - Root cutting method - Google Patents

Root cutting method

Info

Publication number
JPH0684619B2
JPH0684619B2 JP17488190A JP17488190A JPH0684619B2 JP H0684619 B2 JPH0684619 B2 JP H0684619B2 JP 17488190 A JP17488190 A JP 17488190A JP 17488190 A JP17488190 A JP 17488190A JP H0684619 B2 JPH0684619 B2 JP H0684619B2
Authority
JP
Japan
Prior art keywords
root cutting
layer
impermeable layer
deeper
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP17488190A
Other languages
Japanese (ja)
Other versions
JPH0464618A (en
Inventor
明美 野尻
宏 吉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP17488190A priority Critical patent/JPH0684619B2/en
Publication of JPH0464618A publication Critical patent/JPH0464618A/en
Publication of JPH0684619B2 publication Critical patent/JPH0684619B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は建造物の基礎等を築造するための根切り工
法、より詳しくは20mを超すような大深度根切りに好適
な根切り工法に関する。
Description: TECHNICAL FIELD The present invention relates to a root cutting method for constructing a foundation or the like of a building, and more particularly to a root cutting method suitable for deep-depth root cutting exceeding 20 m. .

〔従来技術〕[Prior art]

一般に根切りを行なう場合は、周囲に不透水性層に達す
る連続壁などの土留壁を設け周囲の地盤沈下や、揚水量
の増大を防止して揚水を行ない根切りを行なっていた。
In general, when performing root cutting, a soil retaining wall such as a continuous wall reaching an impermeable layer is provided around the root to prevent ground subsidence around the surrounding area and increase the amount of pumped water, and perform root cutting.

しかし、20mを超すような大深度根切りの場合は、掘削
する深さ以上の深い山留壁が必要であるが、一般にヒー
ビング、あるいはボイリングと呼ばれる根切り底地盤の
破壊が起る恐れがあり、これを防止する必要があった。
However, in the case of deep root cutting exceeding 20 m, a deep retaining wall more than the depth to be excavated is required, but there is a possibility that the root cutting bottom ground generally called heaving or boiling will occur. , I needed to prevent this.

第4紀層は多くの場合、浅い処に粘土層があり、深い処
は砂、砂礫層が中心となり、大きな水圧が作用すること
になる。しかもこの砂層は一般に洪積層であって強度は
高いが、水を通し易いという性質があり、根切りする場
合に、この水処理が大きな問題となっていた。
In most cases, the Quaternary layer has a clay layer in the shallow area, and the deep layer mainly has sand and gravel layers, and a large water pressure is applied. Moreover, although this sand layer is generally a dip layer and has high strength, it has the property of allowing water to easily pass through, and this water treatment has been a major problem when root cutting.

〔発明の目的〕[Object of the Invention]

この発明は上記問題点に着目しなされたものである。そ
の目的は土留壁を著しく深くする必要がなく、比較的少
ない揚水量で、大深度の根切りが可能な根切り工法を提
案するにある。
The present invention has been made in view of the above problems. The purpose is to propose a root cutting method that enables deep root cutting with a relatively small pumping volume without the need to make the retaining wall extremely deep.

〔発明の構成〕[Structure of Invention]

(1)の発明になる根切り工法は、周囲を根切り底より
深い不透水性層に達する山留壁で囲み、内部を揚水して
根切りを行なう根切り工法において、根切りに先だち、
根切り底以深にある不透水性層とそれより以深にある硬
質層とをアンカー杭で連結することを特徴とする。
(2)の発明になる根切り工法は、根切り底以深の適当
深度に不透水性地層がない場合は、根切りに先だち、根
切り底以深に硬化材を注入して不透水性層を設け、この
不透水性層とより以深にある硬質層とをアンカー杭で連
結することを特徴とする。
The root cutting method that becomes the invention of (1) is a root cutting method in which the circumference is surrounded by a mountain retaining wall that reaches a water impermeable layer deeper than the bottom, and the inside is pumped to perform root cutting.
It is characterized in that the impermeable layer located deeper than the root cutting bottom and the hard layer located deeper than the root cutting are connected by anchor piles.
In the root cutting method of the invention of (2), when there is no impermeable stratum at an appropriate depth below the root cutting bottom, a hardener is injected into the depth below the root cutting bottom to cut the impermeable layer before root cutting. It is characterized in that this impermeable layer is connected to the hard layer located deeper by an anchor pile.

〔実施例〕〔Example〕

以下図示する実施例により説明する。第1,2図におい
て、根切りすべき地盤1の周囲に、硬質砂層にある根切
り底2より以深にある粘土層からなる不透水性層3に達
する連続壁4を建込む。地盤内に5〜10mの間隔で碁盤
目状に、場所打ちコンクリート杭打機で、先端が不透水
性層3より以深にある硬質層5に延び、根切り底付近で
最大径となる竪孔を削孔する。この竪孔内にタテ筋にPC
鋼線を使用し、先端部に支圧板6を取付け、長さが硬質
層5から根切り底2に達する鉄筋籠7を吊り下す。この
削孔内にコンクリートを注入し、根切り底2のある硬質
砂層8から不透水性層3を貫通し、その深層にある硬質
層5に達するアンカー杭9を形成する。このアンカー杭
9は、上端部が拡径し、根切り底2付近で最大径をな
し、不透水性層3と以深にある硬質層5とを連結する。
The embodiment will be described below. In FIGS. 1 and 2, a continuous wall 4 is built around the ground 1 to be root-cut and reaches a water-impermeable layer 3 made of a clay layer deeper than the root-cutting bottom 2 in the hard sand layer. With a cast-in-place concrete pile driving machine, the tip extends to the hard layer 5 which is deeper than the impermeable layer 3 and has the largest diameter near the root cutting bottom in a grid pattern at intervals of 5 to 10 m in the ground. Drill a hole. PC in the vertical muscle in this pit
A steel wire is used, a pressure bearing plate 6 is attached to the tip, and a reinforcing bar cage 7 whose length reaches the root cutting bottom 2 from the hard layer 5 is suspended. Concrete is poured into this drilled hole to form an anchor pile 9 which penetrates the impermeable layer 3 from the hard sand layer 8 having the root cutting bottom 2 and reaches the hard layer 5 in the deep layer. The anchor pile 9 has a diameter increased at the upper end, has a maximum diameter near the root cutting bottom 2, and connects the impermeable layer 3 and the hard layer 5 located below.

根切り底2より以浅の竪孔はソイルセメント等で埋戻
し、根切りの際に障害にならないようにする。この状態
で地盤内を揚水し、掘削し根切り底2まで根切りを行な
う。
The vertical holes shallower than the root cutting bottom 2 are backfilled with soil cement or the like so as not to obstruct the root cutting. In this state, the ground is pumped up, excavated, and root cutting is performed up to the root cutting bottom 2.

この実施例ではアンカー杭の上端部を不透水性層の上層
の硬質砂層に固着し、不透水性層と硬質層とを連結し比
較的強度が低い不透水性層との連結強度の向上を図った
がこのほか様々の態様をとることができる。
In this embodiment, the upper end of the anchor pile is fixed to the upper hard sand layer of the impermeable layer to connect the impermeable layer and the hard layer to improve the connection strength between the impermeable layer and the relatively impermeable layer. Although it is intended, various other modes can be adopted.

適当な深度位置に透水性層が存在しない場合は、第3図
のごとく、根切り底2より以深の、例えば硬質砂層8に
硬化材を注入し、不透水性と強度を備えた人工の不透水
性層3′を形成する。
When the water-permeable layer does not exist at an appropriate depth position, as shown in FIG. 3, a hardener is injected into the hard sand layer 8 deeper than the root cutting bottom 2, for example, to create an artificial impermeable material having water impermeability and strength. A water permeable layer 3'is formed.

この場合も、第1図の場合と同様に、所定の間隔で竪孔
を穿孔し、鉄筋籠7を吊り下し、硬質層5から、根切り
底2に達し、根切り底付近で最大径となるアンカー杭9
を形成し、不透水性層3′を以深にある硬質層5と連結
する。
Also in this case, as in the case of FIG. 1, vertical holes are drilled at a predetermined interval, the rebar cages 7 are suspended, the hard layer 5 reaches the root cutting bottom 2, and the maximum diameter near the root cutting bottom is reached. Anchor pile 9
And the impermeable layer 3 ′ is connected to the hard layer 5 located deeper.

〔作 用〕[Work]

この工法は以上の構成からなり、根切りに先だち、根切
り底より以深にある不透水性層あるいは硬化材を注入し
て形成した人工の不透水性層はそれより以深にある硬質
層とアンカー杭で連結する。従って第4図のごとく連結
壁4で囲まれた地盤1内を揚水し、根切りを行なうと、
不透水性層3′の下面には地下水圧Pが作用する。しか
し、アンカー杭9には自動的にこの水圧Pに見合う張力
Tが発生し、均合が保たれ、根切り底2の破壊が防止さ
れる。
This construction method consists of the above structure.Before root cutting, a water impermeable layer deeper than the root cutting bottom or an artificial water impermeable layer formed by injecting a hardening material is a hard layer and an anchor deeper than that. Connect with piles. Therefore, as shown in Fig. 4, when the ground 1 surrounded by the connecting walls 4 is pumped up and root cutting is performed,
The groundwater pressure P acts on the lower surface of the impermeable layer 3 '. However, tension T commensurate with this water pressure P is automatically generated in the anchor pile 9 to maintain the balance and prevent the root cutting bottom 2 from being broken.

実施例のアンカー杭は上端部が拡径しているため、不透
水性層の下面に作用する地下水圧はアンカー杭の逆テー
パー部分に圧縮力として作用することになるので、アン
カー杭周囲の硬質砂層5あるいは不透水性層3,3′はそ
れに耐える強度と遮水性が要求される。また、その結
果、アンカー杭と不透水性層あるいは硬質砂層との連結
強度を高めることができる。
Since the anchor pile of the example has an expanded upper end, the groundwater pressure acting on the lower surface of the impermeable layer acts as a compressive force on the reverse taper portion of the anchor pile, so the anchor pile surrounding hard The sand layer 5 or the water impermeable layer 3, 3'is required to have sufficient strength and water impermeability. Moreover, as a result, the connection strength between the anchor pile and the impermeable layer or the hard sand layer can be increased.

〔発明の効果〕〔The invention's effect〕

従来の根切り工法では、粘土層等の不透水性層がある場
合でも、その上面に作用する荷重とその下面に作用する
地下水圧との差に見合う水量の揚水が必要となり、大深
度の根切りでは深い土留壁と大量の揚水をしなければな
らなかったが、この工法によると比較的に浅い土留壁を
建込み、少量の揚水で大深度の根切りが可能となる。
In the conventional root cutting method, even if there is an impermeable layer such as a clay layer, it is necessary to pump water in an amount corresponding to the difference between the load acting on the upper surface and the groundwater pressure acting on the lower surface. For cutting, a deep soil retaining wall and a large amount of pumping had to be done, but this method allows a relatively shallow soil retaining wall to be built, and a small amount of pumping to deep root the soil.

また、適当な深度に不透水性層がない場合は、従来山留
壁を非常に深く下す必要があり、工期や工費が著しく高
価となり、工事が不可能なこともあったが、この工法に
よると、この様な場合でも能率よく大深度の根切りが可
能となる。
In addition, if there is no impermeable layer at an appropriate depth, it is necessary to go down the mountain retaining wall very deeply in the past, and the construction period and construction cost would be extremely expensive, and construction was sometimes impossible. Even in such a case, it is possible to efficiently perform deep root cutting.

【図面の簡単な説明】[Brief description of drawings]

図面は実施例の工法を示すものであり第1図、第2図は
不透水性層がある地盤の施工例を示す縦断面図および平
面図、第3図は硬化材を注入し不透水性層を形成した地
盤の施工例を示す断面図、第4図は根切り後の断面図で
ある。 1……根切り地盤、2……根切り底、3……不透水性
層、4……連続壁、5……硬質層、6……支圧板、7…
…鉄筋籠、8……硬質砂層、9……アンカー杭。
The drawings show the construction method of the embodiment, and FIG. 1 and FIG. 2 are a longitudinal sectional view and a plan view showing an example of construction of the ground having a water impermeable layer, and FIG. Sectional drawing which shows the construction example of the ground which formed the layer, FIG. 4 is sectional drawing after root cutting. 1 ... Root cutting ground, 2 ... Root cutting bottom, 3 ... Impermeable layer, 4 ... Continuous wall, 5 ... Hard layer, 6 ... Pressure plate, 7 ...
… Reinforcing cage, 8 …… Hard sand layer, 9 …… Anchor pile.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】周囲を根切り底より深い不透水性層に達す
る山留壁で囲み、内部を揚水し根切りを行なう根切り工
法において、根切りに先だち、根切り底以深にある不透
水性層とそれより以深にある硬質層とをアンカー杭で連
結することを特徴とする根切り工法。
1. A root cutting method in which the surrounding area is surrounded by a mountain retaining wall reaching a water impermeable layer deeper than the root cutting bottom and the inside is pumped to perform root cutting. A root cutting method characterized by connecting a flexible layer and a hard layer that is deeper than that with an anchor pile.
【請求項2】周囲を根切り底より深い不透水性層に達す
る山留壁で囲み、内部を揚水して根切りを行なう根切り
工法において、根切りに先だち根切り底以深に硬化材を
注入して不透水性層を設け、この不透水性層とより以深
にある硬質層とをアンカー杭で連結することを特徴とす
る根切り工法。
2. In a root cutting method in which the circumference is surrounded by a mountain retaining wall that reaches an impermeable layer deeper than the root cutting bottom, and the inside is pumped to perform root cutting, a hardening material is provided deeper than the root cutting bottom before root cutting. A root cutting method comprising injecting a water-impermeable layer and connecting the water-impermeable layer with a harder layer located deeper by an anchor pile.
JP17488190A 1990-07-02 1990-07-02 Root cutting method Expired - Lifetime JPH0684619B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17488190A JPH0684619B2 (en) 1990-07-02 1990-07-02 Root cutting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17488190A JPH0684619B2 (en) 1990-07-02 1990-07-02 Root cutting method

Publications (2)

Publication Number Publication Date
JPH0464618A JPH0464618A (en) 1992-02-28
JPH0684619B2 true JPH0684619B2 (en) 1994-10-26

Family

ID=15986296

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17488190A Expired - Lifetime JPH0684619B2 (en) 1990-07-02 1990-07-02 Root cutting method

Country Status (1)

Country Link
JP (1) JPH0684619B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660957A (en) * 2012-05-31 2012-09-12 中国二十二冶集团有限公司 Foundation pit supporting construction method for soft soil zone
CN104234062B (en) * 2014-09-18 2016-05-04 江西理工大学 A kind of in-situ ionic rare earth soaks the method for ore deposit stope preventing land slide
CN109440774A (en) * 2018-12-27 2019-03-08 上海建工七建集团有限公司 A kind of foundation pit structure and its construction method
CN112609706B (en) * 2020-12-09 2022-05-17 中铁二十局集团第六工程有限公司 Construction method of opposite-bracing angle brace concrete horizontal supporting structure of foundation pit in sea reclamation area
CN113737857A (en) * 2021-10-09 2021-12-03 中国建筑第二工程局有限公司 Be used for deep pipe gallery structure and major structure to build connection structure again and worker's method thereof

Also Published As

Publication number Publication date
JPH0464618A (en) 1992-02-28

Similar Documents

Publication Publication Date Title
WO2020175844A1 (en) Construction method for underwater concrete block structure
US5320452A (en) Cast-in-place concrete pile and method of constructing the same in the ground
JP4451553B2 (en) Buoyancy prevention structure and construction method thereof
JP3752560B2 (en) Basic structure for constructing a new building in an existing basement and its construction method
KR100975988B1 (en) Construction method of underwater structure
JP6158398B1 (en) Composite foundation pile
JPS5985028A (en) Steel pipe pile and laying work thereof
CN107288147A (en) Rock foundation pole and tower foundation construction method
JPH0684619B2 (en) Root cutting method
JP3385876B2 (en) Cast-in-place pile construction method just below the existing foundation
KR100360462B1 (en) Method to construct a structure on soft soil and the structure thereof
JPH0220720A (en) Underground construction method by muddy water excavation
US4588327A (en) Precast concrete pile and method of placing it in the ground
JP3760343B2 (en) Drilling bottom stabilization method and construction method of underground building
JP2604210B2 (en) Construction method of underground large-scale spatial structure
JPS5847823A (en) Construction of in-place concrete pile
JP2000130066A (en) Construction method for vertical shaft
JPH0776845A (en) How to lay open caisson
JPH07268878A (en) Method for immersing caisson and structure of cutting face of caisson
JPH02266015A (en) Constructing underground continuous wall
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPS649413B2 (en)
JPH0525828A (en) Floating prevention structure for grounded floor
GB2048999A (en) Improvements relating to the construction of in situ piles
JPH07119471B2 (en) Board blister prevention method using an earth anchor