JPH0666095A - Tunnel covering device - Google Patents
Tunnel covering deviceInfo
- Publication number
- JPH0666095A JPH0666095A JP4245809A JP24580992A JPH0666095A JP H0666095 A JPH0666095 A JP H0666095A JP 4245809 A JP4245809 A JP 4245809A JP 24580992 A JP24580992 A JP 24580992A JP H0666095 A JPH0666095 A JP H0666095A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- wall surface
- concrete
- movable
- guide rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は掘削されたトンネル壁面
に急結性コンクリートの打設による所定厚みのトンネル
覆工を施工するためのトンネル覆工装置に関するもので
ある。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel lining apparatus for constructing a tunnel lining having a predetermined thickness by placing quick-setting concrete on an excavated tunnel wall surface.
【0002】[0002]
【従来の技術】従来から、岩盤などの地盤中にトンネル
を掘進していく場合、切羽部において発破孔穿設作業を
行い、該発破孔に爆薬を装填したのち爆破させ、その爆
破により発生したずりを排出したのち、トンネル壁面に
コンクリート覆工を施工している。このコンクリート覆
工としては、膨張性や崩壊性の地山にトンネルを掘削す
る場合には、掘削後、直ちにトンネル壁面に一次覆工を
施す必要があるために、急結剤を混合したコンクリート
を圧縮空気によりトンネル壁面に吹付けてコンクリート
を急激に硬化させるコンクリート吹付工法が採用されて
いる。2. Description of the Related Art Conventionally, when a tunnel is dug into the ground such as rock, a blast hole is drilled in the face of the rock, the blast hole is filled with explosive, and then blasted. After draining the sludge, a concrete lining is constructed on the tunnel wall. As this concrete lining, when excavating a tunnel in expansive or collapsible ground, it is necessary to immediately apply a primary lining to the tunnel wall surface immediately after the excavation. A concrete spraying method is used in which compressed air is sprayed onto the wall surface of the tunnel to rapidly harden the concrete.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、コンク
リート吹付け工法によれば、コンクリートをトンネル壁
面に対して高速で吹き付けるものであるから、充分に付
着することなく跳ね返りが生じて作業環境が悪くなる上
に、吹き付けたコンクリートがトンネル壁面から剥離す
る場合が生じて材料の損失を招く虞れがある。さらに、
このようなコンクリート吹付け作業はずりの排出作業や
発破孔の穿設作業が完了するのを待たなければ行うこと
ができない上に、吹付けたコンクリートがある程度硬化
したのち、再びその表面にコンクリートの吹き付けを行
わなければ、所要の厚さのコンクリート覆工を施工する
ことができなく、トンネル覆工の作業能率が著しく低下
するという問題点がある。However, according to the concrete spraying method, concrete is sprayed onto the wall surface of the tunnel at a high speed, so that the concrete does not adhere sufficiently and rebounds to cause a bad working environment. In addition, there is a possibility that the sprayed concrete may separate from the wall surface of the tunnel, resulting in loss of material. further,
Such concrete spraying work can be performed only after waiting for completion of the work of discharging the offset and the work of forming the blast hole, and after the sprayed concrete has hardened to a certain degree, the concrete is sprayed again on the surface. Without spraying, concrete lining with a required thickness cannot be constructed, and there is a problem that the work efficiency of tunnel lining is significantly reduced.
【0004】一方、吹付けコンクリートに代えて、型枠
によるトンネル覆工を行う場合においても、発破孔の穿
設作業等が完了したのちでなければ行うことができず、
作業能率の低下が免れないものである。本発明はこのよ
うな問題点に鑑みてなされたもので、掘削されたトンネ
ル壁面へのコンクリート覆工作業が能率よく行えると共
に該覆工作業と重複して次に掘削すべき切羽面への発破
孔の穿設作業等が可能にし得るトンネル覆工装置の提供
を目的とするものである。On the other hand, in the case of performing tunnel lining with a form instead of shotcrete, it can be done only after completion of the blast hole drilling work,
It is inevitable that work efficiency will decline. The present invention has been made in view of the above problems, and it is possible to efficiently perform concrete lining work on an excavated tunnel wall surface, and to blast the face face to be excavated next, overlapping with the lining work. An object of the present invention is to provide a tunnel lining device that enables a hole drilling operation and the like.
【0005】[0005]
【課題を解決するための手段】上記目的を達成するため
に、本発明のトンネル覆工装置は、トンネル内に移動台
車を配設し、この移動台車上に該移動台車から前方に向
かって突出移動可能な支持桁部材を配設し、該支持桁部
材上にトンネル壁面に沿う形状を有する前後一対のガイ
ドレールをジャッキを介して装架し、これらの前後ガイ
ドレールの両側部に該前後ガイドレール間に案内されて
トンネル壁面の周方向に移動する左右移動型枠装置を配
設し、さらに、移動型枠装置にノズル部を該移動型枠装
置とトンネル壁面との間に臨ませている急結性コンクリ
ート打設用配管を着脱自在に装着してなる構造を有して
いるものである。また、請求項2に記載した発明は、上
記移動台車上の数箇所にトンネル長さ方向に移動可能な
発破孔穿設装置を備えていることを特徴とするものであ
る。In order to achieve the above object, the tunnel lining device of the present invention has a movable carriage disposed in a tunnel, and projects forward from the movable carriage on the movable carriage. A movable support girder member is provided, and a pair of front and rear guide rails having a shape along the tunnel wall surface are mounted on the support girder member via jacks, and the front and rear guides are provided on both sides of the front and rear guide rails. A left-right moving formwork device which is guided between the rails and moves in the circumferential direction of the tunnel wall surface is provided, and further, a nozzle portion is made to face the moving formwork device between the moving formwork device and the tunnel wall surface. It has a structure in which a quick-setting concrete pouring pipe is detachably attached. The invention described in claim 2 is characterized in that a blast hole punching device that is movable in the tunnel length direction is provided at several locations on the movable carriage.
【0006】[0006]
【作用】発破孔に装填した爆薬を爆破させて適宜長さの
トンネル部分を掘削したのち、移動台車を前進させて、
まず、穿設装置によりトンネル切羽の外周部複数箇所に
発破孔を穿設する。しかるのち、支持桁部材を移動台車
から前方に突出させて該支持桁部材上に装架した前後ガ
イドレールを掘削されたトンネル壁面の位置まで移動さ
せ、ジャッキを操作してトンネル壁面からの間隔を所定
寸法に調整する。次いで、配管のノズル部から型枠装置
とトンネル壁面との間に急結性コンクリートを打設しな
がら、これらの型枠装置をガイドレールの両側下端から
上方に移動させてコンクリート覆工を形成していく。ま
た、このトンネル覆工の施工と同時に、ガイドレールで
囲まれている空間部を利用して穿設装置により上記切羽
外周部以外の切羽面に発破孔を穿設することができる。[Operation] After detonating the explosive charged in the blast hole and excavating the tunnel portion of an appropriate length, the moving carriage is moved forward,
First, blast holes are drilled at a plurality of locations on the outer peripheral portion of the tunnel face by a drilling device. After that, the supporting girder member is projected forward from the moving carriage and the front and rear guide rails mounted on the supporting girder member are moved to the position of the excavated tunnel wall surface, and the jack is operated to keep the distance from the tunnel wall surface. Adjust to the specified dimensions. Next, while pouring quick-setting concrete from the nozzle part of the pipe between the formwork device and the tunnel wall surface, move these formwork devices upward from both lower ends of the guide rails to form a concrete lining. To go. Simultaneously with the construction of the tunnel lining, a blasting hole can be formed in the face of the face other than the outer face of the face by using the space surrounded by the guide rails.
【0007】[0007]
【実施例】次に、本発明の実施例を図面について説明す
ると、図1、図2において、既に掘削されたトンネルT
の底面両側部にレール2、2を敷設し、このレール2、
2上に移動台車1を走行自在に配設し、該移動台車1上
に左右型枠装置3、3を設けた前後一対のガイドレール
4、4と複数個の発破孔穿設装置5とをトンネル長さ方
向に前後移動自在に配設してある。DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, referring to the drawings, an embodiment of the present invention will be described. In FIG. 1 and FIG.
Rails 2 and 2 are laid on both sides of the bottom of the rail.
A movable carriage 1 is movably disposed on the movable carriage 2, and a pair of front and rear guide rails 4 and 4 provided with left and right formwork devices 3 on the movable carriage 1 and a plurality of blast hole punching devices 5. It is arranged to be movable back and forth in the tunnel length direction.
【0008】上記移動台車1は正面門形形状に形成され
てあり、その上端台枠1aの両側部上に一定長さを有する
支持桁部材6、6を上端台枠1aの前端から突出可能とな
るようにトンネル長さ方向に移動自在に配設すると共に
これらの移動支持桁部材6、6の前部上に上記前後ガイ
ドレール4、4と同一間隔を存して左右一対のジャッキ
7a、7bの下端部を枢支し、これらのジャッキ7a、7bのロ
ッド端を上記前後ガイドレール4、4の湾曲部の内周面
に連結してガイドレール4、4をトンネル壁面tに対し
て接離自在に装架、支持しているものである。The movable carriage 1 is formed in a front gate shape, and support girder members 6, 6 having a certain length can be protruded from the front end of the upper end frame 1a on both sides of the upper end frame 1a. Are arranged so as to be movable in the tunnel length direction, and a pair of left and right jacks are provided on the front portions of these movable support girder members 6, 6 at the same intervals as the front and rear guide rails 4, 4.
The lower ends of 7a and 7b are pivotally supported, and the rod ends of these jacks 7a and 7b are connected to the inner peripheral surfaces of the curved portions of the front and rear guide rails 4 and 4 to connect the guide rails 4 and 4 to the tunnel wall surface t. It is mounted and supported so that it can be moved in and out freely.
【0009】ガイドレール4、4はI形鋼からなり、そ
の内周面に図10に示すようにラック8を全長に亘って刻
設してある。また、これらのガイドレール4、4はトン
ネル壁面tの上半部湾曲面に沿う湾曲ガイドレール部4a
と、トンネル壁面tの下半部垂直面に沿う垂直ガイドレ
ール部4b(図8参照)に分割されてあり、移動時には垂
直ガイドレール部4bを湾曲ガイドレール部4aの下端から
の連結を解いて移動台車1の適所に収納しておき、湾曲
ガイドレール部4aをジャッキ7a、7bに支持させておくよ
うに構成している。The guide rails 4 and 4 are made of I-shaped steel, and a rack 8 is formed on the inner peripheral surface of the guide rail 4 along the entire length thereof as shown in FIG. Further, these guide rails 4 and 4 are curved guide rail portions 4a along the upper half curved surface of the tunnel wall surface t.
And a vertical guide rail portion 4b (see FIG. 8) along the lower half vertical surface of the tunnel wall t, and the vertical guide rail portion 4b is disconnected from the lower end of the curved guide rail portion 4a during movement. The movable carriage 1 is housed in a proper place and the curved guide rail portion 4a is supported by the jacks 7a and 7b.
【0010】型枠装置3は、図10、図11に示すようにガ
イドレール4、4の対向内面に沿う前後側板31、31の上
端部間と下端部間とにローラ32、33を回転自在に軸支34
し、これらのローラ32、33間に無端の型枠ベルト35を巡
回自在に掛け渡していると共にローラ32、33の中心軸34
の両端に案内転子36、36を一体に固着して、これらの案
内転子36、36をガイドレール4、4の対向溝4c、4c内に
回転可能に嵌入、係止させて型枠装置3をガイドレール
4、4間に架設状態に支持させているものである。な
お、型枠ベルト35をその内面側から適宜な押圧手段によ
って積極的に打設コンクリート側に押圧するように構成
しておくことが望ましい。As shown in FIGS. 10 and 11, the formwork apparatus 3 has rollers 32 and 33 rotatable between upper and lower end portions of front and rear side plates 31 and 31 along opposing inner surfaces of guide rails 4 and 4, respectively. On shaft support 34
Then, an endless formwork belt 35 is circulated between these rollers 32 and 33 in a circulating manner, and a central shaft 34 of the rollers 32 and 33 is provided.
The guide rollers 36, 36 are integrally fixed to both ends of the guide roller 36, 36, and these guide rollers 36, 36 are rotatably fitted in and locked in the opposed grooves 4c, 4c of the guide rails 4, 4, respectively. 3 is supported between the guide rails 4 and 4 in a erected state. In addition, it is desirable that the form frame belt 35 is configured to be positively pressed from the inner surface side thereof to the concrete pouring side by an appropriate pressing means.
【0011】さらに、型枠装置3の前後側板31、31の上
端部適所間に回転軸38を軸支し、側板11から突出した該
回転軸38の端部にガイドレール4、4の前記ラック8に
噛合させたピニオン39を固着してある。9は回転軸38を
回転駆動するモータで、両側板31、31間の適所に配設し
てある。10はこの型枠装置3の型枠ベルト35とトンネル
壁面tとの間にコンクリートを打設する配管で、そのノ
ズル11の開口端を型枠ベルト35の上端側からトンネル壁
面tと型枠装置3との対向上端間に向けて臨ませている
と共に、型枠装置3に対してトンネルの長さ方向に前後
移動自在に設けられている。Further, the rotary shaft 38 is pivotally supported between the upper end portions of the front and rear side plates 31, 31 of the formwork apparatus 3, and the racks of the guide rails 4, 4 are attached to the ends of the rotary shaft 38 protruding from the side plate 11. The pinion 39 meshed with 8 is fixed. The reference numeral 9 designates a motor for rotating the rotary shaft 38, which is arranged at a suitable position between the both side plates 31, 31. Reference numeral 10 is a pipe for placing concrete between the formwork belt 35 of the formwork device 3 and the tunnel wall surface t, and the opening end of the nozzle 11 is arranged from the upper end side of the formwork belt 35 to the tunnel wall surface t and the formwork device. It is provided so as to face between the upper ends facing 3 and is movable in the longitudinal direction of the tunnel with respect to the formwork device 3.
【0012】この移動手段としては型枠装置3の型枠ベ
ルト背面側の両側板31、31間に案内棒12、12を架設し、
この案内棒12、12に往復移動部材13の下端部を固着させ
た取付部材14を摺動自在に取付け、往復移動部材13の先
端に配管10のノズル部11を着脱自在に挿嵌、支持してい
る支持体15を回転自在に軸支16してなるものである。17
は前側(切羽側)のガイドレール4の外周面に全長に亘
って装着しているゴムチューブとスポンジの互層よりな
る妻型枠部で、該妻型枠部17内に圧縮空気を供給して膨
張させることによりトンネル壁面tの内周面に圧接させ
るようにように構成しているものである。As this moving means, guide rods 12, 12 are installed between both side plates 31, 31 on the rear side of the form belt of the form device 3,
A mounting member 14 to which the lower end of the reciprocating member 13 is fixed is slidably attached to the guide rods 12, 12, and the nozzle portion 11 of the pipe 10 is detachably inserted and supported at the tip of the reciprocating member 13. The supporting body 15 is rotatably supported by a shaft 16. 17
Is a gable form part made up of alternating layers of a rubber tube and sponge, which is mounted on the outer peripheral surface of the guide rail 4 on the front side (cut face side) over the entire length, and supplies compressed air into the gable form part 17. It is configured to be brought into pressure contact with the inner peripheral surface of the tunnel wall surface t by being expanded.
【0013】一方、上記発破孔穿設装置5は、移動台車
1の台枠1a上の両側部と下部両側とにトンネル長さ方向
に向かって前後移動自在に配設されている。穿設装置5
をこのように移動させる手段としては、上記ガイドレー
ル支持桁部材6、6間における移動台車1の台枠1aの両
側部と、移動台車1の両側下部に突設している受梁部材
18、18上とに左右一対の平行レール19、19を敷設し、こ
れらの平行レール19、19上に台板20を図示しない適宜な
駆動機構によって前後移動自在に載置し、該台板20の前
部上に穿設装置5を設置してなるものである。On the other hand, the blast hole punching device 5 is arranged on both sides of the undercarriage 1a of the moving carriage 1 and on both lower sides thereof so as to be movable back and forth in the tunnel length direction. Punching device 5
As means for moving the carriage in this way, the beam receiving members which are provided on both sides of the underframe 1a of the moving carriage 1 between the guide rail supporting girder members 6, 6 and on the lower portions on both sides of the moving carriage 1.
A pair of left and right parallel rails 19 and 19 are laid on and above the parallel plate 18, and a base plate 20 is placed on these parallel rails 19 and 19 so as to be movable back and forth by an appropriate drive mechanism (not shown). The punching device 5 is installed on the front part of the.
【0014】穿設装置5は、台板20上に固着した固定台
51の前面にアーム部材52の基端部を上下左右旋回自在に
連結すると共にこのアーム部材52の先端側に穿孔具53を
取付けてなるもので、穿孔具53はその受台板54の後端を
アーム部材52の先端部に枢支させていると共に中間部と
アーム部材52の先端間をジャッキ55を介して上下回動自
在に連結してあり、穿孔具53の先端ドリル56は穿孔具内
に設けたモータ等の駆動機構によって回転させられ、且
つ、前後方向に移動自在に構成されている。57はアーム
部材52の中間部と受台板54間を連結しているアーム回動
用ジャッキである。The punching device 5 is a fixed base fixed on the base plate 20.
The front end of the arm member 52 is connected to the front surface of the arm member 51 so as to be vertically and horizontally rotatable, and the perforation tool 53 is attached to the tip end side of the arm member 52. The perforation tool 53 is the rear end of the pedestal plate 54. Is pivoted to the tip of the arm member 52, and the intermediate portion and the tip of the arm member 52 are vertically rotatably connected via a jack 55. It is configured to be rotated by a drive mechanism such as a motor provided in the above and movable in the front-rear direction. Reference numeral 57 is an arm rotating jack that connects the intermediate portion of the arm member 52 and the receiving plate 54.
【0015】このように構成した装置を使用してトンネ
ル壁面tにコンクリート覆工Cを施工するには、トンネ
ル切羽を発破によって掘削する際に、移動台車1をトン
ネルT内に後退させたおき、図3に示すように、切羽面
に穿設した発破孔21内に爆薬を装填して爆破することに
より所定長さのトンネル部を掘削後、該移動台車1を前
進させると共に穿設装置5の台板20を前進させて穿孔具
53のドリル56を切羽に接近させる。そして、まず、ジャ
ッキ55、57等の操作によって穿孔具53を切羽外周部側に
移動させ、図5、図6に示すように、ドリル56によって
切羽外周部に所定間隔毎に複数個の発破孔21を穿設す
る。この発破孔21の穿設作業中に、掘削されたずりの排
出を行う。なお、このずりの排出は発破孔21の穿設後に
おいても移動台車1下方の空間部を利用して行うことが
できる。In order to construct the concrete lining C on the tunnel wall surface t by using the apparatus constructed as described above, the movable carriage 1 is retracted into the tunnel T when the tunnel face is excavated by blasting, As shown in FIG. 3, after the tunnel portion of a predetermined length is excavated by loading and blasting explosives into the blast hole 21 formed in the face face, the movable carriage 1 is moved forward and the piercing device 5 is moved. Punch tool by advancing the base plate 20
Bring the drill 56 of 53 close to the face. Then, first, by operating the jacks 55, 57, etc., the perforating tool 53 is moved to the outer peripheral face of the face, and as shown in FIGS. 5 and 6, a plurality of blast holes are formed on the outer peripheral face of the face by a drill 56 at predetermined intervals. Drill 21. During the drilling work of the blast hole 21, the excavated shear is discharged. It should be noted that the displacement can be discharged in the space below the movable carriage 1 even after the blast hole 21 is formed.
【0016】上記発破孔21の穿設後、穿孔具53を切羽外
周部からトンネル中央部側に旋回移動させ、発破孔21を
穿設した切羽外周部と既に施工したトンネル覆工Cの前
端面間に型枠装置3のガイドレール4、4が配置可能な
空間部を設ける。次いで、移動台車1の台枠1a上の支持
桁部材6の前半部を図7に示すように、移動台車1から
トンネル切羽面近傍部に達する位置まで前進、突出させ
る。After the blast hole 21 is formed, the perforation tool 53 is pivotally moved from the outer peripheral portion of the face to the central part of the tunnel, and the outer peripheral portion of the face where the blast hole 21 is formed and the front end face of the tunnel lining C that has already been constructed. A space in which the guide rails 4 and 4 of the formwork device 3 can be placed is provided therebetween. Next, as shown in FIG. 7, the front half of the support girder member 6 on the underframe 1a of the moving carriage 1 is advanced and projected from the moving carriage 1 to a position near the tunnel facet.
【0017】しかるのち、ジャッキ7a、7bのロッドを適
宜に伸長させることにより前後湾曲ガイドレール部4a、
4aを掘削されたトンネル壁面t側に接近させ、後方側の
ガイドレール部4aの外周面を既に施工しているコンクリ
ート覆工Cの前端内周面に密接させる。しかるのち、前
後湾曲ガイドレール部4a、4aの下端に、図8に示すよう
に垂直ガイドレール部4b、4bの上端を連結、一体化さ
せ、これらのガイドレール4b、4b部の下端をトンネルT
の底面両側端部上に固定する。After that, the rods of the jacks 7a and 7b are appropriately extended so that the front and rear curved guide rail portions 4a,
4a is brought closer to the excavated tunnel wall surface t side, and the outer peripheral surface of the rear guide rail portion 4a is brought into close contact with the inner peripheral surface of the front end of the concrete lining C which has already been constructed. After that, the upper ends of the vertical guide rails 4b and 4b are connected and integrated with the lower ends of the front and rear curved guide rails 4a and 4a as shown in FIG. 8, and the lower ends of these guide rails 4b and 4b are connected to the tunnel T.
Fix it on both edges of the bottom of the.
【0018】次いで、図9に示すように、湾曲ガイドレ
ール部4aの両側端部に夫々配置しておいた左右型枠装置
3、3を垂直ガイドレール4b、4b部の下端にまで移動さ
せると共にジャッキ7a、7bとガイドレール4、4との連
結を解き、さらにこれらの湾曲、垂直ガイドレール部の
連結により構成された前側ガイドレール4の外周面に設
けている妻型枠部17を膨張させてトンネル壁面Cに密着
させる。この状態にすると、コンクリートを打設すべき
型枠装置3とトンネル壁面tとの間の空間部の前後両端
面は、既に施工されたコンクリート覆工Cの前端面と上
記妻型枠部17によって規制される。なお、ジャッキ9a、
9bによる支持を解くのは、型枠装置3、3を移動させな
がらコンクリートを打設する作業と平行して穿設装置5
により切羽面に発破孔を穿設する作業を行う際に、その
振動が移動台車1からガイドレール4、4に伝達するの
を防止するためである。Next, as shown in FIG. 9, the left and right formwork devices 3 and 3 arranged at both end portions of the curved guide rail portion 4a are moved to the lower ends of the vertical guide rails 4b and 4b, respectively. Release the connection between the jacks 7a, 7b and the guide rails 4, 4 and further inflate the end form frame portion 17 provided on the outer peripheral surface of the front guide rail 4 formed by the connection of these curved and vertical guide rail portions. The wall surface C of the tunnel. In this state, the front and rear end surfaces of the space portion between the formwork device 3 and the tunnel wall surface t where the concrete should be placed are formed by the front end face of the concrete lining C already constructed and the gable formwork portion 17. Regulated. In addition, jack 9a,
The support by 9b is released by moving the formwork devices 3 and 3 in parallel with the work of placing concrete and the drilling device 5
This is to prevent the vibration from being transmitted from the moving carriage 1 to the guide rails 4 and 4 when performing the work of forming the blast hole in the face face.
【0019】この状態にして、トンネル内の適所に設置
したコンクリート供給源から配管10内にコンクリートを
送り込むと共に配管10の先端部に取付けた圧縮空気供給
管25とコンクリート急結剤供給管26からミスト状のコン
クリート急結剤を供給し、ノズル部11に達するまで空気
流によってコンクリートと混合させたのち、図10、図11
に示すようにノズル部11からそれぞれの型枠装置3の型
枠ベルト35とトンネル壁面tとの間に噴出、打設する。
この際、ノズル部11を取付けた往復移動部材13を案内棒
12に沿って往復移動させると共にノズル部11を首振状態
に往復回動させて、型枠装置3とトンネル壁面tとの間
の上記空間部に均一な高さとなるように急結剤混入コン
クリート22を打設する。In this state, concrete is fed into the pipe 10 from the concrete supply source installed at a proper place in the tunnel, and the mist is supplied from the compressed air supply pipe 25 and the concrete quick-setting agent supply pipe 26 attached to the tip of the pipe 10. -Like concrete quick-setting admixture is supplied and mixed with the concrete by air flow until it reaches the nozzle part 11, and then, as shown in FIGS.
As shown in FIG. 5, the nozzle portion 11 ejects and drives between the form frame belts 35 of the respective form frame devices 3 and the tunnel wall surface t.
At this time, the reciprocating member 13 to which the nozzle portion 11 is attached is attached to the guide rod.
The reciprocating movement along 12 and the reciprocating rotation of the nozzle portion 11 in a swinging state make the height of the space between the formwork device 3 and the tunnel wall surface t uniform so that the concrete mixed with the quick-setting admixture. Place 22.
【0020】さらに、打設したコンクリート22が硬化し
始めるに従って、ガイドレール4、4のラック8に噛合
しているピニオン39を回転させることにより、左右の型
枠装置3、3を徐々にガイドレール4、4に沿って上昇
させ、トンネル覆工Cを施工していく。この際、型枠装
置3の型枠ベルト35はローラ32、33間に回転自在に掛け
渡されているので、既に打設されたトンネル覆工面上を
自走するようにして型枠装置3が移動し、トンネル覆工
面の平滑性が維持されるものである。このトンネル覆工
Cを施工中に、図7に示すように穿孔具53を切羽中央部
側に移動させ、上記切羽外周部に穿設した発破孔21で囲
まれている切羽面にドリル56によって図12、図13に示す
ように上下左右に所定間隔毎に発破孔21を穿設する。Further, as the poured concrete 22 begins to harden, the pinions 39 meshing with the racks 8 of the guide rails 4 and 4 are rotated to gradually move the left and right formwork units 3 and 3 into guide rails. Ascend along 4 and 4 to construct tunnel lining C. At this time, since the form frame belt 35 of the form device 3 is rotatably stretched between the rollers 32 and 33, the form device 3 is made to run on the already placed tunnel lining surface. It moves and maintains the smoothness of the tunnel lining surface. During the construction of this tunnel lining C, as shown in FIG. 7, the perforating tool 53 is moved to the center of the face, and the face of the face surrounded by the blast holes 21 formed in the outer periphery of the face is drilled by a drill 56. As shown in FIG. 12 and FIG. 13, blast holes 21 are drilled vertically and horizontally at predetermined intervals.
【0021】一方、急結剤混入コンクリート22を打設し
ながら型枠装置3、3を徐々に上昇させ、これらの型枠
装置3、3が図14に示すように、トンネル壁面tの天端
面近傍に達すると、一方の型枠装置3を他方の型枠装置
3よりもその移動速度を増大させて先にトンネル壁面t
の天端にその先端が達するまで移動させ、該一方の型枠
装置3内にコンクリート22を充分に打設したのち、その
ノズル部11を有する配管10を往復移動部材13と共に撤去
する。On the other hand, while the concrete 22 mixed with the quick-setting admixture is being poured, the formwork units 3 and 3 are gradually lifted up, and these formwork units 3 and 3 are, as shown in FIG. When reaching the vicinity, the moving speed of one formwork device 3 is made higher than that of the other formwork device 3, and the tunnel wall surface t
It is moved until its tip reaches the top end of (1), concrete 22 is sufficiently placed in the one mold device 3, and then the pipe 10 having the nozzle portion 11 is removed together with the reciprocating member 13.
【0022】続いて、他方の型枠装置3を該型枠装置3
とトンネル壁面tとの間にノズル部11からコンクリート
22を打設しながらトンネル壁面tの天端に向かって移動
させ、該ノズル部11が移動の支障となった時点で上記同
様にこのノズル11を撤去し、両方の型枠装置3、3の先
端同士を接合させて必要に応じてボルト等でそのドッキ
ング状態を保持すると共に、外部から妻型枠部17の天端
部等を通じて図15に示すように型枠装置3とトンネル壁
面tの天端間に残存する空間部に適宜な注入ノズル23を
通じて急結剤混入コンクリートを打設、充満させる。Subsequently, the other formwork device 3 is connected to the formwork device 3
Between the nozzle part 11 and the tunnel wall t
While driving 22 while moving toward the top of the tunnel wall surface t, when the nozzle portion 11 becomes a hindrance to the movement, the nozzle 11 is removed in the same manner as above, and both of the formwork devices 3 and 3 are removed. The tips are joined to each other to maintain the docked state with bolts or the like as needed, and the outside of the mold frame unit 17 and the top of the tunnel wall surface t as shown in FIG. Concrete containing a quick-setting agent is poured and filled into the space remaining between the ends through an appropriate injection nozzle 23.
【0023】こうして、トンネルTの長さ方向に前後ガ
イドレール4、4間に相当した幅を有するアーチ状のト
ンネル覆工Cが形成され、天端部のコンクリートの硬化
後、ジャッキ7a、7bによりガイドレール4の湾曲ガイド
レール部4aを支持させ、しかるのち、ガイドレール4の
垂直ガイドレール部4bを撤去し、支持桁部材6を後方に
移動させて湾曲ガイドレール部4aを台車7上に後退させ
ると共に各発破孔穿設装置5も元位置に復帰させる。Thus, an arch-shaped tunnel lining C having a width corresponding to the length between the front and rear guide rails 4 and 4 is formed in the length direction of the tunnel T, and after the concrete at the top end is hardened, the jacks 7a and 7b are used. The curved guide rail portion 4a of the guide rail 4 is supported, and then the vertical guide rail portion 4b of the guide rail 4 is removed, and the supporting girder member 6 is moved rearward so that the curved guide rail portion 4a is retracted onto the carriage 7. At the same time, each blast hole punching device 5 is also returned to its original position.
【0024】次いで、穿孔具53によって穿設された発破
孔21に爆薬を装填して爆破することにより切羽面に所定
長さのトンネル部を掘削後、移動台車1を前進させて上
記同様に切羽外周部の発破孔21の穿設作業とずり排出作
業、その穿設後における移動型枠装置3によるトンネル
覆工Cの施工作業、およびこの作業に平行して切羽中央
部に対する発破孔21の穿設作業とを順次繰り返し行うこ
とによりトンネル壁面tに連続した覆工Cを施工するも
のである。Next, after the explosive is loaded into the blast hole 21 formed by the perforation tool 53 to explode, a tunnel portion having a predetermined length is excavated on the face of the face, and then the movable carriage 1 is advanced to make the face like the face. Drilling work and blasting work of the blast hole 21 on the outer peripheral portion, construction work of the tunnel lining C by the movable formwork device 3 after the drilling work, and drilling of the blast hole 21 to the central portion of the face in parallel with this work. By continuously repeating the installation work, a continuous lining C is constructed on the tunnel wall surface t.
【0025】[0025]
【発明の効果】以上のように本発明のトンネル覆工装置
によれば、トンネル内に移動台車を配設し、この移動台
車上に該移動台車から前方に向かって突出移動可能な支
持桁部材を配設し、該支持桁部材上にトンネル壁面に沿
う形状を有する前後一対のガイドレールをジャッキを介
して装架し、これらの前後ガイドレールの両側部に該前
後ガイドレール間に案内されてトンネル壁面の周方向に
移動する左右移動型枠装置を配設し、さらに、移動型枠
装置にノズル部を該移動型枠装置とトンネル壁面との間
に臨ませている急結性コンクリート打設用配管を着脱自
在に装着してなるものであるから、掘削されたトンネル
壁面側に移動台車から支持桁部材を突出させてガイドレ
ールを切羽側に移動させるように構成しているので、切
羽部における作業空間を広く取ることができ、従って、
ずり等の排出作業が円滑且つ能率よく行えるものであ
り、その上、ジャッキによってトンネル壁面に対するガ
イドレールの位置を正確に調整することができて該ガイ
ドレールに配設した移動型枠装置とトンネル壁面間の間
隔によるトンネル覆工厚さを所望の寸法となるように設
定することができるものである。As described above, according to the tunnel lining device of the present invention, the movable carriage is disposed in the tunnel, and the support girder member which is movable on the movable carriage so as to project forward from the movable carriage. And a pair of front and rear guide rails having a shape along the tunnel wall surface are mounted on the support girder member via jacks, and are guided between the front and rear guide rails on both sides of the front and rear guide rails. A quick-setting concrete pouring system in which a left and right moving formwork device that moves in the circumferential direction of the tunnel wall surface is arranged, and the nozzle part is faced between the moving formwork device and the tunnel wall surface. Since the piping for use is detachably mounted, the supporting girder member is projected from the moving carriage to the wall surface side of the excavated tunnel to move the guide rail to the cutting face side. Work in While it is possible to take a wide, therefore,
It is capable of smoothly and efficiently discharging work such as shear, and moreover, the position of the guide rail with respect to the tunnel wall surface can be accurately adjusted by the jack, and the movable formwork device and the tunnel wall surface arranged on the guide rail. The thickness of the tunnel lining can be set to a desired dimension depending on the interval.
【0026】さらに、ガイドレールにはその両側部に移
動型枠装置を設けているので、これらの移動型枠装置を
ガイドレールの両側下端部から夫々上方に移動させなが
ら該型枠装置とトンネル壁面との間にノズル部を通じて
急結性コンクリートを打設することにより、トンネル壁
面に一定幅と一定厚みを有するトンネル覆工部を周方向
に連続的に施工することができ、しかも、トンネル天端
面においては両型枠装置を結合した状態にして急結性コ
ンクリートの打設が可能となり、剥離や脱落の生じない
一連のトンネル覆工を形成し得るものである。Further, since the guide rails are provided with movable formwork devices on both sides thereof, the movable formwork devices and the tunnel wall surface are moved while moving these movable formwork devices from the lower end portions on both sides of the guide rail respectively. By placing quick-setting concrete through the nozzle between the and, it is possible to continuously construct a tunnel lining part with a constant width and a constant thickness on the tunnel wall in the circumferential direction. In the above, it is possible to place the quick-setting concrete in a state where both formwork devices are connected, and it is possible to form a series of tunnel linings that do not cause peeling or falling.
【0027】また、移動台車の数箇所に発破孔穿設装置
をトンネルの長さ方向に移動自在に配設しておくことに
よって、まず、発破によって掘削されたトンネル切羽の
外周部に該穿設装置によって複数個の発破孔を穿設した
のち、上記のようにトンネル壁面にガイドレールを配設
させて移動型枠装置によるトンネル覆工作業を行いなが
ら穿設装置による切羽中央部に対する発破孔の穿設作業
を行うことができ、従って、トンネル覆工後、直ちに次
の発破によるトンネル掘削が可能となって、発破による
所定長さのトンネル部の掘削から型枠装置によるトンネ
ル覆工作業開始までの作業工程が著しく短縮させること
ができると共に、切羽外周部に発破孔を穿設する作業中
に、掘削されたずりの排出作業等が行えトンネル築造工
期を大幅に短縮することができるものである。By disposing blast hole punching devices at several positions of the movable carriage so as to be movable in the length direction of the tunnel, first, the blast hole punching device is provided on the outer peripheral portion of the tunnel face excavated by blasting. After drilling a plurality of blast holes by the device, the guide rails are placed on the tunnel wall as described above and the tunnel lining work is performed by the piercing device while the tunnel lining work is performed by the moving form device. It is possible to perform drilling work, so immediately after the tunnel lining, tunnel digging by the next blasting becomes possible, from the digging of the tunnel part of a predetermined length to the start of the tunnel lining work by the formwork device. The work process of can be significantly shortened and the tunnel construction period can be greatly shortened by performing the work of discharging excavated skids during the work of forming blast holes on the outer peripheral face of the face. It is what it is.
【図1】装置全体の簡略側面図、FIG. 1 is a simplified side view of the entire apparatus,
【図2】その背面図、FIG. 2 is a rear view thereof,
【図3】切羽に発破孔を穿設した状態の簡略断面図、FIG. 3 is a simplified cross-sectional view showing a state in which a blast hole is formed in a face.
【図4】発破によって掘削されたトンネル部の断面図、FIG. 4 is a sectional view of a tunnel portion excavated by blasting,
【図5】切羽外周部に発破孔を穿設している状態の簡略
縦断側面図、FIG. 5 is a simplified vertical sectional side view showing a state in which a blast hole is formed in the outer peripheral portion of the face.
【図6】穿設された発破孔を有する切羽面の正面図、FIG. 6 is a front view of a face face having a blast hole formed therein.
【図7】ガイドレールを前進させた状態の側面図、FIG. 7 is a side view showing a state where the guide rail is advanced,
【図8】垂直ガイドレール部を連結させた状態の背面
図、FIG. 8 is a rear view showing a state in which the vertical guide rail portions are connected,
【図9】トンネル覆工開始時の背面図、FIG. 9 is a rear view when the tunnel lining starts,
【図10】トンネル覆工を施工している状態の斜視図、FIG. 10 is a perspective view showing a state in which a tunnel lining is being constructed,
【図11】その正面図、FIG. 11 is a front view thereof,
【図12】トンネル覆工と共に発破孔を穿設している状
態の簡略側面図、FIG. 12 is a simplified side view showing a state in which a blast hole is formed together with a tunnel lining,
【図13】その簡略正面図、FIG. 13 is a simplified front view of FIG.
【図14】トンネル天端近傍部にまで覆工した状態を示
す簡略正面図、FIG. 14 is a simplified front view showing a state in which lining has been performed up to the vicinity of the top of the tunnel.
【図15】トンネル天端部を覆工している状態を示す簡
略正面図。FIG. 15 is a simplified front view showing a state in which the top of the tunnel is lined.
1 移動台車 3 型枠装置 4 ガイドレール 5 発破孔穿設装置 6 支持桁部材 7a、7b ジャッキ 11 ノズル部 21 発破孔 22 急結剤混入コンクリート t トンネル壁面 1 Mobile bogie 3 Formwork device 4 Guide rail 5 Blast hole drilling device 6 Support girder members 7a, 7b Jack 11 Nozzle part 21 Blast hole 22 Concrete with admixture t Tunnel wall surface
───────────────────────────────────────────────────── フロントページの続き (72)発明者 木下 昭治 大阪市阿倍野区松崎町2丁目2番2号 株 式会社奥村組内 (72)発明者 児玉 敏行 大阪市阿倍野区松崎町2丁目2番2号 株 式会社奥村組内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Shoji Kinoshita 2-2-2 Matsuzaki-cho, Abeno-ku, Osaka City Okumura-gumi Co., Ltd. (72) Inventor Toshiyuki Kodama 2-2-2, Matsuzaki-cho, Abeno-ku, Osaka Stock company Okumura Gumi
Claims (2)
動台車上に該移動台車から前方に向かって突出移動可能
な支持桁部材を配設し、該支持桁部材上にトンネル壁面
に沿う形状を有する前後一対のガイドレールをジャッキ
を介して装架し、これらの前後ガイドレールの両側部に
該前後ガイドレール間に案内されてトンネル壁面の周方
向に移動する左右移動型枠装置を配設し、さらに、移動
型枠装置にノズル部を該移動型枠装置とトンネル壁面と
の間に臨ませている急結性コンクリート打設用配管を着
脱自在に装着してなることを特徴とするトンネル覆工装
置。1. A movable carriage is provided in a tunnel, a support girder member is provided on the movable carriage so as to project forward from the movable carriage, and the support girder member is provided along the tunnel wall surface. A pair of front and rear guide rails each having a shape are mounted via jacks, and a left and right moving formwork device which is guided between the front and rear guide rails and moves in the circumferential direction of the tunnel wall is arranged on both sides of the front and rear guide rails. In addition, a quick-setting concrete placing pipe having a nozzle portion facing the movable form device and the tunnel wall surface is detachably attached to the movable form device. Tunnel lining equipment.
方向に移動可能な発破孔穿設装置を備えていることを特
徴とする請求項1記載のトンネル覆工装置。2. The tunnel lining device according to claim 1, further comprising blast hole punching devices that are movable in the tunnel length direction at several locations on the movable carriage.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4245809A JP2623196B2 (en) | 1992-08-21 | 1992-08-21 | Tunnel lining equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4245809A JP2623196B2 (en) | 1992-08-21 | 1992-08-21 | Tunnel lining equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0666095A true JPH0666095A (en) | 1994-03-08 |
JP2623196B2 JP2623196B2 (en) | 1997-06-25 |
Family
ID=17139171
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4245809A Expired - Fee Related JP2623196B2 (en) | 1992-08-21 | 1992-08-21 | Tunnel lining equipment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2623196B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7397520B2 (en) | 2004-12-07 | 2008-07-08 | Seiko Epson Corporation | Electro-optical device and electronic apparatus |
JP2021031980A (en) * | 2019-08-26 | 2021-03-01 | 清水建設株式会社 | Tunnel lining construction system and tunnel lining construction method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106337686B (en) * | 2015-07-13 | 2019-10-15 | 中铁第六勘察设计院集团有限公司 | Three layers of subway station canopy structure of rocky stratum tunneling and construction method |
-
1992
- 1992-08-21 JP JP4245809A patent/JP2623196B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7397520B2 (en) | 2004-12-07 | 2008-07-08 | Seiko Epson Corporation | Electro-optical device and electronic apparatus |
JP2021031980A (en) * | 2019-08-26 | 2021-03-01 | 清水建設株式会社 | Tunnel lining construction system and tunnel lining construction method |
Also Published As
Publication number | Publication date |
---|---|
JP2623196B2 (en) | 1997-06-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4312540A (en) | Continuous mining apparatus and method | |
US4474287A (en) | Variable length conveyor assembly | |
CN214787374U (en) | Telescopic slagging-off device of inclined shaft construction | |
US3379024A (en) | Machine for constructing lined ducts through rock | |
US3604754A (en) | Apparatus for and method of driving a tunnel shaft | |
US1751147A (en) | Method of lining tunnels with concrete and apparatus therefor | |
JPH0666095A (en) | Tunnel covering device | |
JP2623197B2 (en) | Construction method of tunnel lining | |
JPH0666094A (en) | Tunnel covering method | |
US4390211A (en) | Continuous miner with cutter assembly attitude adjustment | |
JP3451531B2 (en) | Open tunnel excavator | |
JPH09250296A (en) | Suspension type form tunnel lining device | |
JP2709876B2 (en) | Tunnel wall construction equipment | |
JP2996096B2 (en) | Large section tunnel excavator | |
JPH05280274A (en) | Tunnel construction method | |
JP2573882B2 (en) | Tunnel rapid construction method and its drilling equipment | |
CN222513503U (en) | An open tunnel boring machine | |
JPH09125885A (en) | Tunnel lining device based on spray method and lining method | |
JP3760311B2 (en) | Tunnel excavator | |
JPH0288889A (en) | Constructing method of tunnel lining | |
JPH08338198A (en) | Tunnel excavating and lining device and tunnel internal surface concrete lining method | |
SU1114795A1 (en) | Unit for constructing tunnel calotte trench | |
JP3438208B2 (en) | Tunnel construction equipment | |
JP2022173962A (en) | VERTICAL CUTTING HOLE CONTINUOUS DRILLING DEVICE AND VERTICAL CUTTING HOLE CONTINUOUS DRILLING METHOD | |
JPH07113393A (en) | Gantry backhoe of concrete form loaded type |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |