JPH06321114A - Train operation control system - Google Patents
Train operation control systemInfo
- Publication number
- JPH06321114A JPH06321114A JP5114797A JP11479793A JPH06321114A JP H06321114 A JPH06321114 A JP H06321114A JP 5114797 A JP5114797 A JP 5114797A JP 11479793 A JP11479793 A JP 11479793A JP H06321114 A JPH06321114 A JP H06321114A
- Authority
- JP
- Japan
- Prior art keywords
- train
- substation
- power consumption
- total amount
- capacity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000005540 biological transmission Effects 0.000 abstract description 8
- 238000010586 diagram Methods 0.000 description 7
- 230000002159 abnormal effect Effects 0.000 description 2
- 230000003111 delayed effect Effects 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 230000001939 inductive effect Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Train Traffic Observation, Control, And Security (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、例えば事故等によっ
て発生する異常事態から正常列車ダイヤに復帰させるに
際し、変電所容量を越えることなく迅速に元の正常列車
ダイヤに戻すことができる列車運行管理システムに関す
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to train operation management capable of promptly returning to an original normal train schedule when the normal train schedule is restored from an abnormal situation caused by an accident or the like, without exceeding the substation capacity. It is about the system.
【0002】[0002]
【従来の技術】図7は例えば「三菱電機技報」(Vo
l.61・2・1987)に示されるこの種の従来の列
車運行管理システムの構成を示すものであり、図に示す
ように、継電連動装置1を介して得られた各列車の在線
情報に基づき、駅装置2によって各列車の追跡を行っ
て、その追跡結果は伝送路3を介して中央管理装置4に
伝送される。中央管理装置4はこのようにして伝送され
た追跡結果情報を基に、操作端末5に各列車の運行状況
を表示して指令員に状況を伝達する。指令員はこの伝達
情報に基づいて各き電区間に進入する列車の本数を把握
し、これら各列車の所要電力量の総量と変電所容量とを
比較することによって、支障はないか否かについて適時
判断を行っている。2. Description of the Related Art FIG. 7 shows, for example, "Mitsubishi Electric Technical Report" (Vo
l. 61.2 / 1987) shows the configuration of a conventional train operation management system of this type, and as shown in the figure, based on the in-rail information of each train obtained via the relay interlocking device 1. The station device 2 tracks each train, and the tracking result is transmitted to the central management device 4 via the transmission path 3. Based on the tracking result information transmitted in this way, the central management device 4 displays the operating status of each train on the operation terminal 5 and transmits the status to the commander. Based on this transmitted information, the orderer grasps the number of trains entering each feeder section and compares the total amount of power required for each train with the substation capacity to determine whether there is any problem. We make timely decisions.
【0003】[0003]
【発明が解決しようとする課題】従来の列車運行管理シ
ステムは以上のように構成されているので、絶えず指令
員が多数の列車の運行状況を見ながら判断しなければな
らず、事故で列車ダイヤが乱れた時等のように、緊急の
事態には追従することが困難で、各列車の所要電力量が
変電所容量をオーバーしてトリップし、停電等を引き起
こして列車ダイヤの混乱を招くという問題点があった。
又、現時点の運行状況から将来の運行を予測し、各き電
区間の列車の所要電力量を推測することは非常に困難で
あり、仮に出来たとしても極めて概算的なものであって
実質的には対応することができず、後追い的な処置しか
できないという問題点があった。Since the conventional train operation management system is constructed as described above, the dispatcher must constantly make judgments while watching the operation status of many trains. It is difficult to follow an emergency situation such as when the train is disturbed, and the required power amount of each train exceeds the substation capacity and trips, causing a power outage etc. There was a problem.
In addition, it is very difficult to predict future operation from the current operation status and to estimate the amount of electric power required for the train in each feeder section, and even if it can be done, it is extremely approximate and practical. However, there was a problem that it was not possible to deal with it and only follow-up measures could be taken.
【0004】この発明は上記のような問題点を解消する
ためになされたもので、事故等の異常事態から正常列車
ダイヤに復帰させるに際し、各き電区間ごとの各列車の
所要電力量の各総量を予測し、この各総量と各変電所容
量とを比較しながら列車ダイヤの修復を行うことによ
り、変電所容量を列車の所要電力量がオーバーして停電
等を引き起こすことなく、迅速に元の正常列車ダイヤに
戻すことが可能な列車運行管理システムを提供すること
を目的とするものである。The present invention has been made in order to solve the above problems, and when the normal train schedule is restored from an abnormal situation such as an accident, the required electric energy of each train for each feeder section is By predicting the total amount and repairing the train schedule while comparing each total amount with each substation capacity, the substation capacity can be quickly restored without causing power outages and the like due to excess train power requirements. It is an object of the present invention to provide a train operation management system capable of returning to the normal train schedule.
【0005】[0005]
【課題を解決するための手段】この発明に係る請求項1
の列車運行管理システムは、予め各き電区間における各
列車の所要電力量を算出するとともに、所要電力量の各
総量と各変電所容量との比較を行い、各総量が各変電所
容量を越える場合には先頭の列車から順に起動指令を与
え、又、越えない場合には全列車へ一斉に起動指令を与
えるようにしたものである。[Means for Solving the Problems] Claim 1 according to the present invention
Train operation management system calculates the required electric energy of each train in each feeding section in advance, compares each total amount of required electric power with each substation capacity, and each total amount exceeds each substation capacity. In this case, the start command is given in order from the first train, and if the trains are not exceeded, the start command is given to all trains at once.
【0006】又、この発明に係る請求項2の列車運行管
理システムは、予め記憶されている情報を基に各列車の
現時点以降の運行ダイヤを予測するとともに、運行ダイ
ヤにおける各列車の運転曲線をシミュレーションするこ
とにより各列車の消費電力量を求め、上記消費電力量か
ら各き電区間ごとの消費電力量の総量を時系列的に算出
して、各き電区間ごとの消費電力量の総量と各変電所容
量との比較を順次行い、各き電区間ごとの消費電力量の
総量が各変電所容量を越えるき電区間が有る場合には、
不足電力量に相当する一部の列車に起動遅延またはダ行
走行の指令を与え、又、越えるき電区間が無い場合に
は、全列車にカ行走行の指令を与えるようにしたもので
ある。Further, the train operation management system according to claim 2 of the present invention predicts an operation schedule of each train after the present time based on the information stored in advance, and calculates the operation curve of each train on the operation schedule. Obtain the power consumption of each train by simulation, calculate the total amount of power consumption for each feeding section in time series from the above power consumption, and calculate the total amount of power consumption for each feeding section. If there are feeder sections where the total amount of power consumption for each feeder section exceeds the capacity of each substation,
A command to delay the start or run to a certain train is given to some trains corresponding to the amount of power shortage, and if there is no crossing section, a command to run all trains is given. .
【0007】又、この発明に係る請求項3の列車運行管
理システムは、列車ダイヤを元の正常列車ダイヤに戻す
ための修復案を作成するとともに、修復案に基づく各き
電区間ごとの各列車の運転曲線をシミュレーションする
ことにより各列車の消費電力を求め、各列車の消費電力
量から各き電区間ごとの消費電力量の総量を算出して、
各き電区間ごとの消費電力量の総量と各変電所容量との
比較を行い、各き電区間ごとの消費電力量の総量が各変
電所容量を越えるき電区間が有る場合には、修復案を補
正して上記各動作を繰り返し、又、越えるき電区間が無
い場合には、修復案に沿って各列車に走行指令を与える
ようにしたものである。Further, the train operation management system according to claim 3 of the present invention creates a repair plan for returning the train schedule to the original normal train schedule, and each train for each feeder section based on the repair schedule. Power consumption of each train is obtained by simulating the operation curve of, and the total amount of power consumption for each feeding section is calculated from the power consumption of each train,
The total amount of power consumption for each feeder section is compared with the capacity of each substation, and if there is a feeder section where the total amount of power consumption for each feeder section exceeds the capacity of each substation, restoration is performed. The plan is corrected and the above-mentioned operations are repeated, and when there is no crossing section, a running command is given to each train according to the repair plan.
【0008】又、この発明に係る請求項4の列車運行管
理システムは、地上用送受信装置と車上用送受信装置と
の交信を、軌道回路に沿って配設される漏洩同軸ケーブ
ルと、車上に配設される車上用アンテナとを介して行う
ようにしたものである。In the train operation management system according to a fourth aspect of the present invention, the communication between the ground transceiver and the on-vehicle transceiver is performed by a leaky coaxial cable arranged along a track circuit and an on-board train. It is configured to be performed via an on-vehicle antenna provided in the.
【0009】[0009]
【作用】この発明の請求項1〜3における列車運行管理
システムは、各き電区間ごとの各列車の所要電力量の各
総量を予測し、この各総量と各変電所容量とを比較しな
がら列車ダイヤの修復を行うことにより、各列車の所要
電力量の各総量が各変電所容量をオーバーして停電等を
引き起こすこともなく、迅速に元の正常列車ダイヤに戻
す。The train operation management system according to claims 1 to 3 of the present invention predicts each total amount of electric power required for each train for each feeder section, and compares each total amount with each substation capacity. By repairing the train schedule, the total amount of electric power required for each train will not exceed the capacity of each substation and will not cause a power outage, etc., and will be quickly restored to the normal train schedule.
【0010】[0010]
実施例1.以下、この発明の実施例を図について説明す
る。図1はこの発明の実施例1における列車運行管理シ
ステムの構成を示すブロック図である。図において、継
電連動装置1、駅装置2、伝送路3、中央管理装置4お
よび操作端末5は図7に示す従来のものと同様である。
6は列車、7はその上を列車が走行するレールを含む軌
道回路、8は列車6の走行状況を検出するとともに、列
車6の運転制御を行う車上制御装置、9は地上との交換
情報の送受を行う車上用送受信装置、10はこの車上用
送受信装置9からの送信の発信、および地上から送信さ
れてくる情報の受信を行うアンテナである。Example 1. Embodiments of the present invention will be described below with reference to the drawings. 1 is a block diagram showing the configuration of a train operation management system in Embodiment 1 of the present invention. In the figure, the relay interlocking device 1, the station device 2, the transmission line 3, the central management device 4 and the operation terminal 5 are the same as those of the conventional device shown in FIG. 7.
6 is a train, 7 is a track circuit including rails on which the train runs, 8 is an on-board control device that detects the running condition of the train 6 and controls the operation of the train 6, and 9 is exchange information with the ground. An on-vehicle transmitting / receiving device 10 for transmitting / receiving the information is an antenna for transmitting a transmission from the on-vehicle transmitting / receiving device 9 and for receiving information transmitted from the ground.
【0011】11は地上に設置された地上用送受信装
置、12は軌道回路7に沿って設置され、アンテナ10
より発信される車上用送受信装置9からの情報を受信し
て、地上用送受信装置11に取り入れるとともに、地上
用送受信装置11からの情報をアンテナ10に対して発
信するLCX用ケーブル(漏洩同軸ケーブル)、13は
列車6に対して軌道回路7や先行列車等の条件から制限
速度情報を発信するATC地上装置、14は変電所で、
駅装置2に対して例えば停電等の動作モニタ情報14a
を送出している。15は中央管理装置4から送られる現
時点までの列車6の運行情報、ATC情報および変電所
情報等から、列車6の停車や走行状態およびき電状態等
を判断するとともに、現時点以降の各列車の運行状態を
予測し、各列車の運転曲線をシミュレートすることによ
って、各き電区間ごとの各所要電力量を求め、この各所
要電力量と各変電所14の容量とを比較するシミュレー
タ、16は列車6に変電所14よりの電力を供給するき
電回路である。11 is a ground transmitter / receiver installed on the ground, 12 is installed along the track circuit 7, and the antenna 10
The LCX cable (leakage coaxial cable) that receives the information from the on-vehicle transmitter / receiver 9 transmitted from the on-vehicle transmitter / receiver 9 and takes it into the ground transmitter / receiver 11 and transmits the information from the ground transmitter / receiver 11 to the antenna 10. ), 13 is an ATC ground device that transmits speed limit information to the train 6 from conditions such as the track circuit 7 and the preceding train, and 14 is a substation,
For the station device 2, for example, operation monitor information 14a such as a power failure
Is being sent. The reference numeral 15 determines stop and running states of the train 6 and the feeding state etc. from the operation information, ATC information and substation information etc. of the train 6 sent from the central control device 4 up to the present time, A simulator that calculates the required power amount for each feeder section by predicting the operating state and simulating the operation curve of each train, and compares the required power amount with the capacity of each substation 14, 16 Is a feeder circuit for supplying electric power from the substation 14 to the train 6.
【0012】次に、上記のように構成されるこの発明の
実施例1における列車運行管理システムの動作について
説明する。まず、列車が正常列車ダイヤで運行されてい
る間、車上用制御装置8、車上用送受信装置9、アンテ
ナ10およびLCX用ケーブル12経由による列車運行
情報、継電連動装置1からの各列車の在線情報、ATC
地上装置13からのATC情報および変電所14からの
変電所情報は、駅装置2にそれぞれ取り入れられた後、
伝送路3を介して中央管理装置4に伝送される。そし
て、中央管理装置4ではこれらの各情報を基にして、操
作端末5に各列車の運行状況を表示する。Next, the operation of the train operation management system according to the first embodiment of the present invention configured as described above will be described. First, while the train is operating on the normal train schedule, train operation information via the on-vehicle control device 8, on-vehicle transceiver device 9, antenna 10, and LCX cable 12, each train from the relay interlocking device 1 On-rail information, ATC
After the ATC information from the ground device 13 and the substation information from the substation 14 are respectively taken into the station device 2,
It is transmitted to the central management unit 4 via the transmission line 3. Then, the central management device 4 displays the operation status of each train on the operation terminal 5 based on these pieces of information.
【0013】一方、これらの各情報は中央管理装置4か
らシミュレータ15に対しても常時送り込まれており、
シミュレータ15ではこれらの各情報から列車6の停車
や走行状態およびき電状態等を常に把握している。そし
て、例えば事故等の発生により停電し、復旧後各き電区
間における列車6を一斉起動させる場合、シミュレータ
15は図2に示すように、まず常時把握されている各き
電区間における列車6の所要電力量の各総量を算出(ス
テップS1)する。On the other hand, each of these pieces of information is always sent from the central management unit 4 to the simulator 15,
The simulator 15 constantly grasps the stoppage, running state, feeding state, etc. of the train 6 based on these pieces of information. Then, for example, when the train 6 in each feeder section is simultaneously activated after a power outage due to occurrence of an accident or the like, the simulator 15, as shown in FIG. The total amount of required electric power is calculated (step S 1 ).
【0014】次に、ステップS1でそれぞれ算出された
列車6の所要電力量の各総量と、各き電区間を受けもつ
変電所14の容量との比較(ステップS2)を行う。そ
して、比較の結果、列車6の所要電力量の各総量が各変
電所14の容量を越えていない場合は、全列車6に中央
管理装置4、伝送路3、駅装置2、地上用送受信装置1
1、LCX用ケーブル12、アンテナ10、車上用送受
信装置9および車上制御装置8の経路を経由して一斉に
軌道指令(ステップS3)を与え、各列車6は一斉に起
動(ステップS4)される。Next, the total amount of electric power required for the train 6 calculated in step S 1 is compared with the capacity of the substation 14 that handles each feeding section (step S 2 ). Then, as a result of the comparison, when the total amount of electric power required for the train 6 does not exceed the capacity of each substation 14, the central management device 4, the transmission line 3, the station device 2, and the ground transceiver device are included in all the trains 6. 1
1, the LCX cable 12, the antenna 10, the on-vehicle transmission / reception device 9, and the on-vehicle control device 8 are simultaneously given a track command (step S 3 ), and each train 6 is simultaneously activated (step S 3 ). 4 ) be done.
【0015】一方、比較の結果、列車6の所要電力量の
各総量のうちいずれかが、対応する変電所14の容量を
越えている場合は、上記同様の経路を経由して各車上制
御装置8に、先頭列車から順次起動(ステップS5)を
行うよう指令を発し、各列車6はこの指令に基づき順次
起動(ステップS6)される。なおシミュレータ15か
ら車上制御装置8への指令は、車上制御装置8によって
表示画面等を使って運転手に指令されるか、列車6のカ
行回路にその条件が直接入力され、その条件を満足して
いれば運転手がマスコンを入れることにより起動は開始
される。On the other hand, as a result of the comparison, if any one of the total electric power required for the train 6 exceeds the capacity of the corresponding substation 14, the on-board control is performed via the same route as above. device 8, sequentially starting from the top train issues an instruction to perform (step S 5), each train 6 is sequentially activated on the basis of the command (step S 6). The command from the simulator 15 to the on-board control device 8 is given to the driver by the on-board control device 8 using a display screen or the like, or the condition is directly input to the train circuit of the train 6 and the condition is satisfied. If the above condition is satisfied, the driver starts the machine by inserting a mask.
【0016】上記実施例1によれば、各き電区間におけ
る列車の所要電力量の各総量を算出し、これら各総量と
それぞれ対応する各変電所14の各容量とを比較して、
各総量のいずれかが対応する変電所14の容量を越えて
いる場合は、先頭列車から順次起動指令を出し、各列車
6を順次起動させるようにしているので、オーバーロー
ドとなり再トリップして停電する等といった事態は防止
され、迅速に元の正常ダイヤに戻すことが可能になる。According to the first embodiment, the total amount of electric power required for the train in each feeder section is calculated, and each total amount is compared with the corresponding capacity of each substation 14,
If any one of the total amounts exceeds the capacity of the corresponding substation 14, the start trains are sequentially issued and the respective trains 6 are sequentially started up. It is possible to prevent the situation such as doing, and to quickly return to the original normal timetable.
【0017】実施例2.図3はこの発明の実施例2にお
ける列車運行管理システムの構成を示すブロック図であ
る。図において、図1に示す実施例1と同様な部分は同
一符号を付して説明を省略する。17は中央管理装置4
から送られる現時点までの列車6の運行情報、ATC情
報および変電所情報等から、列車6の停車や走行状態お
よびき電状態等を判断するとともに、現時点以降の各列
車の運行状態を予測し、各列車の運転曲線をシミュレー
トすることによって、各き電区間ごとの各所要電力量を
求め、この各所要電力量と各変電所14の容量とを比較
するシミュレータである。Example 2. FIG. 3 is a block diagram showing the configuration of the train operation management system in the second embodiment of the present invention. In the figure, the same parts as those in the first embodiment shown in FIG. 17 is a central management device 4
From the operation information of the train 6 up to the present time sent from, ATC information and substation information, etc., while judging the stop and running state of the train 6 and the feeding state, etc., predict the operation state of each train after the present time, This is a simulator for calculating each required electric energy for each feeding section by simulating an operation curve of each train and comparing each required electric energy with the capacity of each substation 14.
【0018】次に、上記のように構成されるこの発明の
実施例2における列車運行管理システムの動作について
説明する。まず、列車が正常列車ダイヤで運行されてい
る間の動作については、上記実施例1における場合と同
様であるので説明は省略するが、例えば何らかの事故等
により列車のダイヤに乱れが発生した場合、シミュレー
タ17は図4に示すように、まず、予め入力されている
各情報を基にして、各列車6の現時点以降の運行ダイヤ
を予測(ステップS1)する。Next, the operation of the train operation management system according to the second embodiment of the present invention configured as described above will be described. First, the operation while the train is operating on the normal train schedule is the same as in the case of the above-mentioned first embodiment, so the description thereof will be omitted. However, for example, when the train schedule is disturbed by some accident or the like, As shown in FIG. 4, the simulator 17 first predicts the operation schedule of each train 6 after the present time based on each information input in advance (step S 1 ).
【0019】次に、ステップS1によって予測された運
行ダイヤにおける各列車の運転曲線を、シミュレーショ
ンすることによって各列車の消費電力量を算出(ステッ
プS2)し、これら各消費電力量から各き電区間ごとの
消費電力量の総量を時系列的に算出(ステップS3)す
る。そして、ステップS3によって算出された消費電力
量の各総量と、各き電区間をそれぞれ受けもつ変電所1
4の容量との比較(ステップS4)を行う。Next, the electric power consumption of each train is calculated by simulating the operating curve of each train in the operating timetable predicted in step S 1 (step S 2 ), and each electric power consumption is calculated from these respective electric power consumption. time series calculated (step S 3) the total amount of power consumption of each electric period. Then, the total amount of power consumption calculated in step S 3 and the substation 1 that is in charge of each feeding section
Comparison with the capacity of 4 (step S 4 ).
【0020】比較の結果、各き電区間ごとの消費電力量
の総量が、それぞれ対応する変電所14の容量を越えて
いない場合は、上記実施例1の場合と同様の経路を経由
して各列車6へ、ステップS1によって予測された運行
ダイヤに沿ったカ行運転を指令(ステップS5)する。
一方、比較の結果、いずれかのき電区間内の所要電力量
の総量が、対応する変電所14の容量を越えている、す
なわちYESの場合は、不足電力量に相当する一部の列
車6に起動遅延またはダ行運転を指令(ステップS6)
し、再びステップS1に戻って運行ダイヤを新しく予測
し、以下、ステップS4での比較結果がNOと判断され
るまでステップS1〜S4、S6の動作を繰り返す。As a result of the comparison, when the total amount of power consumption for each feeding section does not exceed the capacity of the corresponding substation 14, the same route as in the case of the first embodiment is used. The train 6 is instructed to carry out a train operation according to the operation schedule predicted in step S 1 (step S 5 ).
On the other hand, as a result of the comparison, if the total amount of the required electric power in any of the feeding sections exceeds the capacity of the corresponding substation 14, that is, if YES, a part of the trains 6 corresponding to the insufficient electric power amount is supplied. start delay or da line command operation (step S 6)
And, again operation schedule new prediction returns to step S 1, are repeated the operations of steps S 1 ~S 4, S 6 until the comparison result in step S 4 is determined to be NO.
【0021】上記実施例2によれば、各き電区間ごとの
消費電力量の総量を時系列的に算出し、これら各総量と
各き電区間をそれぞれ受けもつ変電所14の容量とを比
較して、各総量のいずれかが対応する変電所14の容量
を越えている場合は、不足電力量に相当する一部の列車
6に起動遅延またはダ行運転を指令するようにしている
ので、事故等で列車ダイヤの乱れが発生しても、ある特
定のき電区間に列車6が集中し、そのき電区間に対応す
る変電所14がオーバーロードとなり再トリップして停
電する等といった事態は防止され、上記実施例1と同
様、迅速に元の正常ダイヤに戻すことが可能になる。According to the second embodiment, the total amount of power consumption for each feeding section is calculated in time series, and these total amounts are compared with the capacity of the substation 14 which handles each feeding section. Then, when any of the total amounts exceeds the capacity of the corresponding substation 14, the start delay or the double running operation is instructed to some of the trains 6 corresponding to the insufficient power amount. Even if the train schedule is disturbed due to an accident or the like, the train 6 is concentrated in a certain feeder section, the substation 14 corresponding to the feeder section is overloaded, re-trips, and a power failure occurs. As a result, it becomes possible to quickly return to the original normal timetable as in the case of the first embodiment.
【0022】実施例3.図5はこの発明の実施例3にお
ける列車運行管理システムの構成を示すブロック図であ
る。図において、図1に示す実施例1と同様な部分は同
一符号を付して説明を省略する。18は中央管理装置4
から送られる現時点までの列車6の運行情報、ATC情
報および変電所情報等から、列車6の停車や走行状態お
よびき電状態等を判断するとともに、現時点以降の各列
車の運行状態を予測し、各列車の運転曲線をシミュレー
トすることによって、各き電区間ごとの各所要電力量を
求め、この各所要電力量と各変電所14の容量とを比較
するシミュレータである。Example 3. FIG. 5 is a block diagram showing the configuration of the train operation management system in the third embodiment of the present invention. In the figure, the same parts as those in the first embodiment shown in FIG. 18 is a central management device 4
From the operation information of the train 6 up to the present time sent from, ATC information and substation information, etc., while judging the stop and running state of the train 6 and the feeding state, etc., predict the operation state of each train after the present time, This is a simulator for calculating each required electric energy for each feeding section by simulating an operation curve of each train and comparing each required electric energy with the capacity of each substation 14.
【0023】次に、上記のように構成されるこの発明の
実施例3における列車運行管理システムの動作について
説明する。まず、列車が正常列車ダイヤで運行されてい
る間の動作については、上記実施例1における場合と同
様であるので説明は省略するが、例えば何らかの事故等
により列車のダイヤに乱れが発生した場合、シミュレー
タ18は図6に示すように、まず、予め入力されている
各情報を基にして、列車ダイヤを元の正常ダイヤに早く
戻すための修復案を作成(ステップS1)する。Next, the operation of the train operation management system according to the third embodiment of the present invention configured as described above will be described. First, the operation while the train is operating on the normal train schedule is the same as in the case of the above-mentioned first embodiment, so the description thereof will be omitted. However, for example, when the train schedule is disturbed by some accident or the like, As shown in FIG. 6, the simulator 18 first creates a repair plan for quickly returning the train schedule to the original normal schedule based on the information input in advance (step S 1 ).
【0024】次に、ステップS1によって作成された修
復案に基づく各き電区間ごとの各列車の運転曲線を、シ
ミュレーションすることにより各列車の消費電力量を算
出(ステップS2)し、これら各消費電力量から各き電
区間ごとの消費電力量の総量を算出(ステップS3)す
る。そして、ステップS3によって算出された消費電力
量の各き電区間ごとの総量と、各き電区間をそれぞれ受
けもつ変電所14の各容量との比較(ステップS4)を
行う。Next, the power consumption of each train is calculated by simulating the operating curve of each train for each feeder section based on the repair plan created in step S 1 (step S 2 ). calculating a total power consumption of each feeding circuit sections from each power consumption (step S 3). Then, performed with the total amount of each feeding circuit section of the power consumption amount calculated in step S 3, compared with the capacity of the substation 14 having respectively receive the respective feeding circuit section (steps S 4).
【0025】比較の結果、各き電区間ごとの消費電力量
の総量が、それぞれ対応する変電所14の容量を越えて
いない場合は、上記実施例1の場合と同様の経路を経由
して各列車6へ、ステップS1によって作成された列車
ダイヤの修復案に基づく走行指令(ステップS5)を行
う。一方、比較の結果、いずれかのき電区間内の所要電
力量の総量が、対応する変電所14の容量を越えてい
る、すなわちYESの場合は、各き電区間内の所要電力
量の総量が対応する変電所14の容量を越えないよう、
新たな修復案の作成提案(ステップS6)を行い、再び
ステップS1に戻って新たな修復案の作成を行い、以
下、ステップS4での比較結果がNOと判断されるま
で、ステップS1〜S4、S6の動作を繰り返す。As a result of the comparison, if the total amount of power consumption for each feeding section does not exceed the capacity of the corresponding substation 14, the same route as in the case of the above-described first embodiment is used. A running command (step S 5 ) is issued to the train 6 based on the repair plan of the train schedule created in step S 1 . On the other hand, as a result of the comparison, if the total amount of required power in any feeding section exceeds the capacity of the corresponding substation 14, that is, if YES, then the total amount of required power in each feeding section. Does not exceed the capacity of the corresponding substation 14,
A proposal for creating a new repair plan is made (step S 6 ), the process returns to step S 1 again, and a new repair plan is created, and then step S 4 is repeated until the comparison result is judged to be NO. The operations of 1 to S 4 and S 6 are repeated.
【0026】上記実施例3によれば、乱れた列車ダイヤ
を元の正常ダイヤに迅速に戻すための修復案を作成し、
この修復案における各き電区間ごとの消費電力量の総量
を算出し、これら各総量と各き電区間をそれぞれ受けも
つ変電所14の容量とを比較して、各総量のいずれかが
対応する変電所14の容量を越えている場合、再度新た
な修復案の作成提案を行うようにしているので、事故等
で列車ダイヤの乱れが発生しても、ある特定のき電区間
に列車6が集中し、そのき電区間に対応する変電所14
がオーバーロードとなり再トリップして停電する等とい
った事態は防止され、上記各実施例と同様の効果を発揮
する。According to the third embodiment described above, a repair plan for quickly returning the disordered train schedule to the original normal schedule is prepared,
The total amount of power consumption for each feeder section in this restoration plan is calculated, and each of these total amounts is compared with the capacity of the substation 14 that handles each feeder section. When the capacity of the substation 14 is exceeded, a new restoration plan is proposed again, so even if the train schedule is disturbed due to an accident, etc. Substation 14 concentrated and corresponding to the feeder section
Is prevented from being overloaded and re-tripped to cause a power failure, and the same effects as those of the above-described respective embodiments are exhibited.
【0027】実施例4.尚、上記各実施例では、車上用
送受信装置9と地上用送受信装置11との交信は、軌道
回路7に沿って配設される漏洩同軸ケーブル12とアン
テナ10とを介して行うようにしているが、誘電無線や
空間波無線等で行うようにすることも可能である。Example 4. In each of the above embodiments, the communication between the on-vehicle transmitter / receiver 9 and the ground transmitter / receiver 11 is performed via the leaky coaxial cable 12 and the antenna 10 arranged along the track circuit 7. However, it is also possible to use an inductive radio or a space wave radio.
【0028】実施例5.又、上記各実施例では、分散式
の管理システムの場合について説明したが、列車集中制
御装置を使用した集中式の管理システムに適用できるこ
とは言うまでもない。Example 5. Further, in each of the above-described embodiments, the case of the distributed management system has been described, but it goes without saying that the present invention can be applied to a centralized management system using a train centralized control device.
【0029】[0029]
【発明の効果】以上のように、この発明の請求項1によ
れば、予め各き電区間における各列車の所要電力量を算
出するとともに、所要電力量の各総量と各変電所容量と
の比較を行い、各総量が各変電所容量を越える場合には
先頭の列車から順に起動指令を与え、又、越えない場合
には全列車へ一斉に起動指令を与えるようにし、As described above, according to claim 1 of the present invention, the required electric energy of each train in each feeding section is calculated in advance, and the total amount of the required electric energy and the substation capacity are calculated. If the total amount exceeds the capacity of each substation, a start command is given in order from the first train, and if the total amount does not exceed each substation capacity, a start command is given to all trains at once.
【0030】又、この発明の請求項2によれば、予め記
憶されている情報を基に各列車の現時点以降の運行ダイ
ヤを予測するとともに、運行ダイヤにおける各列車の運
転曲線をシミュレーションすることにより各列車の消費
電力量を求め、上記消費電力量から各き電区間ごとの消
費電力量の総量を時系列的に算出して、各き電区間ごと
の消費電力量の総量と各変電所容量との比較を順次行
い、各き電区間ごとの消費電力量の総量が各変電所容量
を越えるき電区間が有る場合には、不足電力量に相当す
る一部の列車に起動遅延またはダ行走行の指令を与え、
又、越えるき電区間が無い場合には、全列車にカ行走行
の指令を与えるようにし、Further, according to claim 2 of the present invention, the operation schedule of each train after the present time is predicted based on the information stored in advance, and the operating curve of each train on the operation schedule is simulated. Calculate the power consumption of each train, calculate the total power consumption for each feeder section in time series from the above power consumption, and then calculate the total power consumption for each feeder section and each substation capacity. If there is a feeder section where the total amount of power consumption for each feeder section exceeds the capacity of each substation, some trains corresponding to the shortage of electricity will be delayed or delayed. Give driving commands,
When there is no crossing section, all trains will be instructed to travel
【0031】又、この発明の請求項3によれば、列車ダ
イヤを元の正常列車ダイヤに戻すための修復案を作成す
るとともに、修復案に基づく各き電区間ごとの各列車の
運転曲線をシミュレーションすることにより各列車の消
費電力を求め、各列車の消費電力量から各き電区間ごと
の消費電力量の総量を算出して、各き電区間ごとの消費
電力量の総量と各変電所容量との比較を行い、各き電区
間ごとの消費電力量の総量が各変電所容量を越えるき電
区間が有る場合には、修復案を補正して上記各動作を繰
り返し、又、越えるき電区間が無い場合には、修復案に
沿って各列車に走行指令を与えるようにし、According to claim 3 of the present invention, a repair plan for returning the train schedule to the original normal train schedule is created, and the operation curve of each train for each feeder section based on the repair schedule is created. Calculate the power consumption of each train by simulating, calculate the total power consumption of each feeding section from the power consumption of each train, and calculate the total power consumption of each feeding section and each substation. If there is a feeding section where the total amount of power consumption for each feeding section exceeds the capacity of each substation, correct the repair plan and repeat the above operations. If there is no electricity section, give a travel command to each train according to the repair plan,
【0032】又、この発明の請求項4によれば、上記各
請求項1ないし3のいずれかにおいて、地上用送受信装
置と車上用送受信装置との交信を、軌道回路に沿って配
設される漏洩同軸ケーブルと、車上に配設される車上用
アンテナとを介して行うようにしたので、変電所容量を
列車の所要電力量がオーバーして停電等を引き起こすこ
となく、迅速に元の正常列車ダイヤに戻すことが可能な
列車運行管理システムを提供することができる。According to a fourth aspect of the present invention, in any one of the first to third aspects, the communication between the ground transceiver device and the on-vehicle transceiver device is arranged along the track circuit. Since it is done via the leaky coaxial cable and the on-board antenna that is installed on the car, the substation capacity can be quickly restored without causing power outages or the like due to excess train power requirements. It is possible to provide a train operation management system capable of returning to the normal train schedule.
【図1】この発明の実施例1における列車運行管理シス
テムの構成を示すブロック図である。FIG. 1 is a block diagram showing a configuration of a train operation management system according to a first embodiment of the present invention.
【図2】図1における列車運行管理システムの動作を示
すフロー図である。FIG. 2 is a flowchart showing the operation of the train operation management system in FIG.
【図3】この発明の実施例2における列車運行管理シス
テムの構成を示すブロック図である。FIG. 3 is a block diagram showing a configuration of a train operation management system according to a second embodiment of the present invention.
【図4】図3における列車運行管理システムの動作を示
すフロー図である。FIG. 4 is a flowchart showing the operation of the train operation management system in FIG.
【図5】この発明の実施例3における列車運行管理シス
テムの構成を示すブロック図である。FIG. 5 is a block diagram showing a configuration of a train operation management system in Embodiment 3 of the present invention.
【図6】図5における列車運行管理システムの動作を示
すフロー図である。6 is a flowchart showing the operation of the train operation management system in FIG.
【図7】従来の列車運行管理システムの構成を示すブロ
ック図である。FIG. 7 is a block diagram showing a configuration of a conventional train operation management system.
1 継電連動装置 2 駅装置 3 伝送路 4 中央管理装置 5 操作端末 6 列車 7 軌道回路 8 車上制御装置 9 車上用送受信装置 10 アンテナ 11 地上用送受信装置 12 LCX用ケーブル(漏洩同軸ケーブル) 13 ATC地上装置 14 変電所 15、17、18 シミュレータ 16 き電回路 S1〜S6 ステップ1 Relay interlocking device 2 Station device 3 Transmission line 4 Central management device 5 Operating terminal 6 Train 7 Track circuit 8 Onboard control device 9 Onboard transceiver 10 Antenna 11 Ground transceiver 12 LCX cable (leakage coaxial cable) 13 ATC ground equipment 14 Substation 15, 17, 18 Simulator 16 Feeding circuit S 1 to S 6 steps
Claims (4)
区間における各列車の所要電力量を算出するとともに、
上記所要電力量の各総量と各変電所容量との比較を行
い、上記各総量が上記変電所容量を越える場合には先頭
の列車から順に起動指令を与え、又、越えない場合には
全列車へ一斉に起動指令を与えるようにしたことを特徴
とする列車運行管理システム。1. When restarting after a power outage, the required electric energy of each train in each feeder section is calculated in advance, and
Compare the total amount of the required electric power with the substation capacity.If the total amount exceeds the substation capacity, give a start command in order from the first train. A train operation management system characterized in that it is designed to give a start command to all at once.
されている情報を基に上記各列車の現時点以降の運行ダ
イヤを予測するとともに、上記運行ダイヤにおける上記
各列車の運転曲線をシミュレーションすることにより上
記各列車の消費電力量を求め、上記消費電力量から各き
電区間ごとの消費電力量の総量を時系列的に算出して、
上記各き電区間ごとの消費電力量の総量と各変電所容量
との比較を順次行い、上記各き電区間ごとの消費電力量
の総量が上記各変電所容量を越えるき電区間が有る場合
には、不足電力量に相当する一部の列車に起動遅延また
はダ行走行の指令を与え、又、越えるき電区間が無い場
合には、全列車にカ行走行の指令を与えるようにしたこ
とを特徴とする列車運行管理システム。2. When the train schedule is disturbed, the train schedule of each train after the present time is predicted based on the information stored in advance, and the running curve of each train in the train schedule is simulated. Obtain the power consumption of each train, calculate the total amount of power consumption for each feeding section from the above power consumption in time series,
When the total amount of power consumption for each feeder section and the capacity of each substation are sequentially compared, and there is a feeder section where the total amount of power consumption for each feeder section exceeds the capacity of each substation. In addition, a command to delay the start or run to some trains is given to some trains that correspond to the amount of power shortage, and if there is no crossing section, a command to run all trains is given. A train operation management system characterized by that.
ダイヤを元の正常列車ダイヤに戻すための修復案を作成
するとともに、上記修復案に基づく各き電区間ごとの各
列車の運転曲線をシミュレーションすることにより上記
各列車の消費電力を求め、上記各列車の消費電力量から
各き電区間ごとの消費電力量の総量を算出して、上記各
き電区間ごとの消費電力量と各変電所容量との比較を行
い、上記各き電区間ごとの消費電力量が各変電所容量を
越えるき電区間が有る場合には、上記修復案を補正して
上記各動作を繰り返し、又、越えるき電区間が無い場合
には、上記修復案に沿って上記各列車に走行指令を与え
るようにしたことを特徴とする列車運行管理システム。3. When a train schedule is disturbed, a repair plan for returning the train schedule to the original normal train schedule is created, and a running curve of each train for each feeder section is simulated based on the repair plan. By calculating the power consumption of each train by calculating the total power consumption of each train section from the power consumption of each train, the power consumption of each train section and each substation If there is a feeder section where the power consumption for each feeder section exceeds the capacity of each substation, the above repair plan is corrected and the above operations are repeated, A train operation management system characterized in that when there is no electric section, a travel command is given to each of the trains according to the repair plan.
の交信は、軌道回路に沿って配設される漏洩同軸ケーブ
ルと、車上に配設される車上用アンテナとを介して行う
ようにしたことを特徴とする請求項1ないし3のいずれ
かに記載の列車運行管理システム。4. Communication between the terrestrial transmitter / receiver and the on-vehicle transmitter / receiver is performed via a leaky coaxial cable arranged along the track circuit and an on-vehicle antenna arranged on the car. The train operation management system according to any one of claims 1 to 3, characterized in that.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11479793A JP3161154B2 (en) | 1993-05-17 | 1993-05-17 | Train operation management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11479793A JP3161154B2 (en) | 1993-05-17 | 1993-05-17 | Train operation management system |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06321114A true JPH06321114A (en) | 1994-11-22 |
JP3161154B2 JP3161154B2 (en) | 2001-04-25 |
Family
ID=14646931
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11479793A Expired - Fee Related JP3161154B2 (en) | 1993-05-17 | 1993-05-17 | Train operation management system |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3161154B2 (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10322905A (en) * | 1997-05-22 | 1998-12-04 | Mitsubishi Electric Corp | Contract power excess prevention device for railway substation |
JP2002347623A (en) * | 2001-05-29 | 2002-12-04 | West Japan Railway Co | Transmission method and system for train operation related information |
JP2007015664A (en) * | 2005-07-11 | 2007-01-25 | Central Japan Railway Co | Crossing object detection device |
JP2010228576A (en) * | 2009-03-27 | 2010-10-14 | Daido Signal Co Ltd | CTC station device with relay interlocking device monitoring function |
JP2011031803A (en) * | 2009-08-04 | 2011-02-17 | Kawasaki Heavy Ind Ltd | Device and method for electric power simulation |
JP2013095398A (en) * | 2011-11-07 | 2013-05-20 | Hitachi Ltd | Monitoring and control system of electric railway |
WO2013099171A1 (en) * | 2011-12-26 | 2013-07-04 | 株式会社 東芝 | Transportation management device, transportation management system, and control program |
KR101355071B1 (en) * | 2012-05-21 | 2014-01-29 | 서울메트로 | Peak electricity dispersion technology based on the metering system of each railway vehicle |
JP2014069620A (en) * | 2012-09-28 | 2014-04-21 | Hitachi Ltd | Train operation management system, and train operation management method |
GB2507388A (en) * | 2012-09-28 | 2014-04-30 | Hitachi Ltd | Taking power consumption into account when rescheduling trains following a delay |
JP2014156227A (en) * | 2013-02-18 | 2014-08-28 | Toshiba Corp | Train diagram preparation device and method |
JP2015177695A (en) * | 2014-03-17 | 2015-10-05 | 三菱電機株式会社 | Train operation control system, on-train device, and train operation control method |
JP2017121835A (en) * | 2016-01-05 | 2017-07-13 | 株式会社東芝 | Train battery control device, method and program |
KR20210065407A (en) * | 2019-11-27 | 2021-06-04 | 한국철도기술연구원 | Substation infra design system and method for designing substation infra using the same |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111619623B (en) * | 2019-02-28 | 2022-02-08 | 比亚迪股份有限公司 | Operation control center, rail vehicle and sleeping method, device and system thereof |
-
1993
- 1993-05-17 JP JP11479793A patent/JP3161154B2/en not_active Expired - Fee Related
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10322905A (en) * | 1997-05-22 | 1998-12-04 | Mitsubishi Electric Corp | Contract power excess prevention device for railway substation |
JP2002347623A (en) * | 2001-05-29 | 2002-12-04 | West Japan Railway Co | Transmission method and system for train operation related information |
JP2007015664A (en) * | 2005-07-11 | 2007-01-25 | Central Japan Railway Co | Crossing object detection device |
JP2010228576A (en) * | 2009-03-27 | 2010-10-14 | Daido Signal Co Ltd | CTC station device with relay interlocking device monitoring function |
JP2011031803A (en) * | 2009-08-04 | 2011-02-17 | Kawasaki Heavy Ind Ltd | Device and method for electric power simulation |
JP2013095398A (en) * | 2011-11-07 | 2013-05-20 | Hitachi Ltd | Monitoring and control system of electric railway |
WO2013099171A1 (en) * | 2011-12-26 | 2013-07-04 | 株式会社 東芝 | Transportation management device, transportation management system, and control program |
KR101355071B1 (en) * | 2012-05-21 | 2014-01-29 | 서울메트로 | Peak electricity dispersion technology based on the metering system of each railway vehicle |
JP2014069620A (en) * | 2012-09-28 | 2014-04-21 | Hitachi Ltd | Train operation management system, and train operation management method |
GB2507388A (en) * | 2012-09-28 | 2014-04-30 | Hitachi Ltd | Taking power consumption into account when rescheduling trains following a delay |
GB2507388B (en) * | 2012-09-28 | 2015-06-03 | Hitachi Ltd | Train operation management system and train operation management method |
JP2014156227A (en) * | 2013-02-18 | 2014-08-28 | Toshiba Corp | Train diagram preparation device and method |
JP2015177695A (en) * | 2014-03-17 | 2015-10-05 | 三菱電機株式会社 | Train operation control system, on-train device, and train operation control method |
JP2017121835A (en) * | 2016-01-05 | 2017-07-13 | 株式会社東芝 | Train battery control device, method and program |
KR20210065407A (en) * | 2019-11-27 | 2021-06-04 | 한국철도기술연구원 | Substation infra design system and method for designing substation infra using the same |
Also Published As
Publication number | Publication date |
---|---|
JP3161154B2 (en) | 2001-04-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3161154B2 (en) | Train operation management system | |
CN101254791B (en) | Rail transit train automatic monitoring system based on communication | |
CN100551755C (en) | A kind of locomotive control method and locomotive control | |
CN111768074A (en) | A new intelligent adjustment method for train operation | |
EP2799307A1 (en) | Transportation management device, transportation management system, and control program | |
US20110144831A1 (en) | Power supply control system and power supply control method | |
JP7181048B2 (en) | Automated train driving system | |
CN106394617A (en) | Train head and end location redundancy system and train head and end location redundancy method | |
JPH0524539A (en) | Railway system | |
JP6047827B2 (en) | Operation control device, operation control method, and control program | |
AU2017202545B2 (en) | Method for initializing the FS mode for the movement of a train on a railway equipped with an ERTMS/ETCS signaling system | |
CN111123739A (en) | Network control system semi-physical simulation experiment platform used in full-automatic unmanned driving mode | |
JP2008024206A (en) | Control device for controlling power supply of mobile body | |
CN109677456A (en) | A kind of train route control method and system suitable for low-density railway | |
CN106672017A (en) | Rail transit turnout remote control system based on mobile terminal and method | |
JPH10322905A (en) | Contract power excess prevention device for railway substation | |
JP5826543B2 (en) | Train control device | |
JP7219047B2 (en) | Automated train driving system | |
JP2012040954A (en) | System for supplying electric power for electric railroad | |
EP3893350B1 (en) | Reconnection of electrically powered train units | |
CN109398425B (en) | Region blocking method and system based on object controller | |
JP2012040955A (en) | Power system for electric railway | |
CN114475707B (en) | Train control system that meets the requirements for C3 high-speed trains to run on conventional lines | |
RU2511742C1 (en) | Dispatch control over train motion at its approach to occupied track section and system to this end | |
Matsumoto et al. | High assurance technologies for autonomous decentralized train control system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |