- JPH06264623A JPH06264623A JP5050849A JP5084993A JPH06264623A JP H06264623 A JPH06264623 A JP H06264623A JP 5050849 A JP5050849 A JP 5050849A JP 5084993 A JP5084993 A JP 5084993A JP H06264623 A JPH06264623 A JP H06264623A
- Authority
- JP
- Japan
- Prior art keywords
- new
- building
- existing
- columns
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 6
- 229910000746 Structural steel Inorganic materials 0.000 abstract 1
- 230000001737 promoting effect Effects 0.000 abstract 1
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000010276 construction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、老朽化した工場建物等
において、その内部の設備を出来るだけ稼動させながら
解体撤去して、建物を大型のものに建替えする建替え工
法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a rebuilding method for decomposing and removing an aged factory building or the like while operating the equipment inside the factory building as much as possible to rebuild the building into a large one.
【0002】[0002]
【従来の技術】従来、工場等にあって大型化したい場合
には、既設建物を解体撤去して敷地を更地化し、この後
により大型の新設建物を建設している。あるいは、既設
建物を包み込む形体で新設建物の大スパンの柱−梁架構
を構築して、既設建物の設備の稼動を少しでも確保する
ことがなされることがある。2. Description of the Related Art Conventionally, when it is desired to increase the size of a factory or the like, an existing building is dismantled and the site is reclaimed, after which a larger new building is constructed. Alternatively, a large-span pillar-beam frame structure of a new building may be constructed in such a manner as to enclose the existing building, and the operation of the equipment of the existing building may be secured even a little.
【0003】[0003]
【発明が解決しようとする課題】従来の技術で述べたも
ののうち前者においては、既設建物を解体して、その後
新築するので、建物内の設備を使用して、生産を続行さ
せながら改築工事を行うことは不可能となる。また、既
設建物の敷地とは別の敷地に仮設工場を作り、設備等を
この仮設工場に移設して生産を継続させ、前記既設の建
物を解体撤去した後に建物を改築するやり方では、敷地
の確保の問題や設備の移設の手間がかかり、この設備の
移設の間は生産も停止せざるを得ないなど、生産増大を
図るための設備の規模拡大にとって重大な支障となると
言った問題がある。In the former one of those described in the prior art, the existing building is dismantled and then a new construction is carried out. Therefore, the renovation work is carried out while continuing the production by using the equipment in the building. It becomes impossible to do. In addition, a temporary factory is created on a site different from the site of the existing building, equipment is moved to this temporary factory to continue production, and the existing building is demolished and removed, and then the building is reconstructed. There is a problem that it will be a serious hindrance to the scale expansion of equipment to increase production, such as securing issues and the time and effort of moving equipment, and there is no choice but to stop production during this equipment transfer. .
【0004】また、後者においては、既設建物を跨いで
大スパン(60〜80m)の大梁を架設しなければなら
ずかかる大梁等に所定の強度をもたせるためには一般新
設建物に比べ鉄骨量が2〜3倍となりコスト高となって
しまうという問題がある。本発明は、従来の技術の有す
るこのような問題点に鑑みてなされたものであり、その
目的とするところは、鉄骨量が節約し得て低コストに仕
上り、かつ、建替えによる工場の生産ラインの停止日数
を少なくすることのできる建替え工法を提供しようとす
るものである。In the latter case, a large span (60 to 80 m) large beam must be erected over an existing building, and in order to give such a large beam a predetermined strength, the amount of steel frame is larger than that of a general new building. There is a problem that the cost becomes 2-3 times higher and the cost becomes higher. The present invention has been made in view of such problems of the conventional technology, and the purpose thereof is to save the amount of steel frames and finish at a low cost, and to produce a factory by rebuilding. The purpose is to provide a rebuilding method that can reduce the number of days the line is down.
【0005】[0005]
【課題を解決するための手段】上記目的を達成するため
に、本発明における建替え工法は、既設建物の外側に風
時・地震時の水平力を負担する新設柱を建て、当該新設
柱間に自重にのみ耐える設計になる新設大梁を上架し、
既設建物の既設柱頭と該大梁との間に屋根からの軸力を
負担するサポート柱をセットし、しかる後、新設建物を
建設し、該既設柱のみを残して順次既設建物を解体する
としたものである。[Means for Solving the Problems] In order to achieve the above-mentioned object, the rebuilding method in the present invention is to construct a new column outside the existing building to bear a horizontal force during wind and earthquake, and A new girder that is designed to withstand only its own weight
A support pillar that bears the axial force from the roof is set between the existing pillar of the existing building and the girder, and then a new building is constructed, and the existing building is dismantled sequentially leaving only the existing pillar. Is.
【0006】[0006]
【作用】既設建物の解体撤去を順次数回に分けて行なえ
ば、生産ラインの全面停止は回避され得ると共に、上架
される大梁は両端の新設柱のみのサポートで屋根荷重を
支持するものではなくして、途中何点かで既設の柱に由
るサポートを享受するものであるので、大梁や新設柱の
鉄骨量は大幅に節約される。[Operation] If the dismantling and removal of the existing building is carried out several times in sequence, the whole stop of the production line can be avoided, and the overhanging girder does not support the roof load with the support of only the new columns at both ends. At some point along the way, the support provided by the existing columns will be enjoyed, so the amount of steel frames for the girders and new columns will be greatly saved.
【0007】[0007]
【実施例】実施例について図を参照して説明する。図1
において、既設建物1の外側に新設柱2,2を建て、当
該柱2,2間に新設大梁3を上架する。当該大梁3は自
重にのみ耐えれば良しとする。その後、既設柱4の柱頭
と大梁3との間にサポート柱5をセットする。当該サポ
ート柱5は屋根からの軸力を負担する。また、風時・地
震時の水平力は、両側の新設柱2,2が負担する。該新
設柱2と大梁3をベースにして新設建物建設後、既設柱
4のみを残し順次既設建物1を解体する。EXAMPLES Examples will be described with reference to the drawings. Figure 1
In, the new columns 2 and 2 are built outside the existing building 1, and the new girders 3 are erected between the columns 2 and 2. It is good if the girder 3 can bear only its own weight. After that, the support pillar 5 is set between the capital of the existing pillar 4 and the girder 3. The support pillar 5 bears the axial force from the roof. In addition, horizontal force during wind and earthquake is borne by the new columns 2 and 2 on both sides. After constructing a new building based on the new pillar 2 and the girder 3, the existing building 1 is sequentially demolished while leaving only the existing pillar 4.
【0008】[0008]
【発明の効果】本発明は上述のとおり構成されているの
で、次に記載する効果を奏する。 (1)既設柱を利用する為、鉄骨量が大幅に少なくて済
み、低コストで建替えができる。 (2)既設建物解体撤去を順次数回に分けて行なえば、
生産ラインの全面停止は回避される。Since the present invention is configured as described above, it has the following effects. (1) Since existing columns are used, the amount of steel frames can be significantly reduced, and rebuilding can be done at low cost. (2) If the dismantling and removal of the existing building is done in several steps,
Full stoppage of the production line is avoided.
【図1】本発明工法の説明図である。FIG. 1 is an explanatory diagram of a method of the present invention.
1 既設建物 2 新設柱 3 新設大梁 4 既設柱 5 サポート柱 1 Existing building 2 New pillar 3 New girder 4 Existing pillar 5 Support pillar
Claims (1)
を負担する新設柱を建て、当該新設柱間に自重にのみ耐
える設計になる新設大梁を上架し、既設建物の既設柱頭
と該大梁との間に屋根からの軸力を負担するサポート柱
をセットし、しかる後、新設建物を建設し、該既設柱の
みを残して順次既設建物を解体するとしてなることを特
徴とする建替え工法。[Claim 1] A new pillar that bears a horizontal force during wind and earthquake is built outside the existing building, and a new large beam that is designed to withstand only its own weight is erected between the new pillars and the existing pillar of the existing building. A support pillar that bears the axial force from the roof is set between the large beam, and then a new building is constructed, and the existing building is dismantled sequentially leaving only the existing pillar. Replacement method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP05084993A JP3303218B2 (en) | 1993-03-11 | 1993-03-11 | Reconstruction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP05084993A JP3303218B2 (en) | 1993-03-11 | 1993-03-11 | Reconstruction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06264623A true JPH06264623A (en) | 1994-09-20 |
JP3303218B2 JP3303218B2 (en) | 2002-07-15 |
Family
ID=12870175
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP05084993A Expired - Fee Related JP3303218B2 (en) | 1993-03-11 | 1993-03-11 | Reconstruction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3303218B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0972099A (en) * | 1995-09-04 | 1997-03-18 | Takubo Kogyosho Kk | Repairing method for existing building |
US9027297B2 (en) | 2009-10-31 | 2015-05-12 | Rad Technology Medical Systems Llc | Relocatable radiation vault and methods of assembly and use |
-
1993
- 1993-03-11 JP JP05084993A patent/JP3303218B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0972099A (en) * | 1995-09-04 | 1997-03-18 | Takubo Kogyosho Kk | Repairing method for existing building |
US9027297B2 (en) | 2009-10-31 | 2015-05-12 | Rad Technology Medical Systems Llc | Relocatable radiation vault and methods of assembly and use |
Also Published As
Publication number | Publication date |
---|---|
JP3303218B2 (en) | 2002-07-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114809699A (en) | Construction method of assembly type outer facade enclosure system for reconstruction of upper part of super high-rise building | |
CN114263275A (en) | High-rise assembled steel structure-core tube same-layer construction method | |
JPH06264623A (en) | Replacement method | |
CN108978478A (en) | Bridge cast-in-situ box-beam deck-type bearing frame system and its construction method | |
CN110565941A (en) | PC aluminum formwork system for prefabricated building and construction method thereof | |
CN102116027A (en) | Frame type combined support-replacing system and construction method thereof | |
CN116181112A (en) | Method for dismantling and installing large-span roof and grid steel structure | |
JPS6367349A (en) | New construction on existing facilities | |
CN115162697B (en) | Special-shaped column construction work I-shaped steel cantilever platform and construction method | |
CN111764684B (en) | Construction method for protectively dismantling plant roof truss | |
CN111827678A (en) | A hoisting method of truss steel structure at the top of a silo | |
JP2527686B2 (en) | Tower-suspended building construction method | |
CN110805346A (en) | Shallow round bin assembly type bin top cover and construction process thereof | |
CN217232878U (en) | A plant column overhead support structure | |
CN116971538B (en) | Large-span arched beam structure and construction and installation method thereof | |
CN222685270U (en) | A high-altitude construction platform | |
JPH0932121A (en) | Construction method of structure and push-up system used therefor | |
JPH04228772A (en) | Method of building movable suspended scaffold for working at ceiling of large space structure | |
JP3122915B2 (en) | Single layer truss roof push-up method | |
CN114016648A (en) | ALC outer wall under curtain wall connected with steel column | |
JPH0339538A (en) | Construction work of wooden building | |
JP2000129785A (en) | Construction method of dome roof | |
JPH1046838A (en) | Demolition method of building | |
JPS6340034A (en) | Construction method for buildings with overhead traveling cranes | |
CN114319860A (en) | Movable beam-bottom tower support device and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090510 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100510 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110510 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120510 Year of fee payment: 10 |
|
LAPS | Cancellation because of no payment of annual fees |