JPH06228945A - Construction of wall - Google Patents

Construction of wall

Info

Publication number
JPH06228945A
JPH06228945A JP5048517A JP4851793A JPH06228945A JP H06228945 A JPH06228945 A JP H06228945A JP 5048517 A JP5048517 A JP 5048517A JP 4851793 A JP4851793 A JP 4851793A JP H06228945 A JPH06228945 A JP H06228945A
Authority
JP
Japan
Prior art keywords
steel sheet
press
wall
steel
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5048517A
Other languages
Japanese (ja)
Other versions
JP2618796B2 (en
Inventor
Morio Kitamura
北村  精男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Giken Seisakusho Co Ltd
Original Assignee
Giken Seisakusho Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Giken Seisakusho Co Ltd filed Critical Giken Seisakusho Co Ltd
Priority to JP5048517A priority Critical patent/JP2618796B2/en
Publication of JPH06228945A publication Critical patent/JPH06228945A/en
Application granted granted Critical
Publication of JP2618796B2 publication Critical patent/JP2618796B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To increase the strength, to shorten the time required for work completion and to reduce cost by a method wherein a retaining wall is constructed by putting steel sheet-piles serving as a form into the ground by pressure driving while putting with pressure H-steels into dented parts of the steel sheet-piles in specified numbers, and excavation is made thereafter to the ground inside the retaining wall. CONSTITUTION:A plurality of steel sheet-piles P for forming a retaining wall are put into the ground by pressure driving, and H-steels 10 are put with pressure into dented parts of the steel sheet-piles P in specified numbers, and thereby a continuous wall is provided. Then, the ground is excavated and reinforcements 41, 42 are arranged concrete 43 is placed with the steel sheet-piles P made serve as a form. Thereby, strength of the wall body can be heightened while the term of works is shortened and cost is reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、壁体の構築方法に関
し、特に地下構築物等におけるコンクリート壁体の構築
方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a wall body, and more particularly to a method for constructing a concrete wall body in an underground structure or the like.

【0002】[0002]

【従来の技術】従来、例えば地下構築物を築造する場
合、矢板やソイル杭等で土留壁を設けた後、地盤を掘削
して地下穴を形成する。この掘削を行うとき土留壁の倒
れを防止するため切梁および腹起こしを設ける。掘削が
終了すると、構築物を造るため鉄筋を所定位置に配置す
ると共に、型枠を設置し、この型枠にコンクリートを注
入して壁体を構築する。
2. Description of the Related Art Conventionally, for example, when constructing an underground structure, a soil retaining wall is provided with sheet piles or soil piles, and then the ground is excavated to form an underground hole. When this excavation is to be carried out, a girder and abdomen will be installed to prevent the retaining wall from falling. When the excavation is completed, a reinforcing bar is placed at a predetermined position for building a structure, a form is installed, and concrete is poured into the form to construct a wall.

【0003】[0003]

【発明が解決しようとする課題】このような従来の壁体
の構築方法では、土留壁が単なる平板からなるため、強
度的に弱く、土留壁が倒れる等の不都合が生じる。この
土留壁の倒れを防止するため切梁および腹起こしを設け
る必要がある。また、コンクリート打設を行う場合、そ
の型枠を土留壁とは別に設置する必要がある。この結
果、面倒な手間が掛かって、工期、工費の増大を来すと
いう問題があった。本発明は以上のような従来の実情に
鑑み、強度的に強く、工期、工費の短縮化を図ることの
できる壁体の構築方法を提供することを目的とする。
In such a conventional method of constructing a wall body, since the earth retaining wall is simply a flat plate, the strength is weak and the earth retaining wall falls over. To prevent this retaining wall from collapsing, it is necessary to provide a crossbeam and an upset. When placing concrete, it is necessary to install the formwork separately from the retaining wall. As a result, there has been a problem that it takes a lot of trouble to increase the construction period and the construction cost. The present invention has been made in view of the conventional circumstances as described above, and an object thereof is to provide a method for constructing a wall body that is strong in strength and can reduce the construction period and the construction cost.

【0004】[0004]

【課題を解決するための手段】本発明の壁体の構築方法
は、型枠となる鋼矢板を地盤に複数圧入して土留壁を作
成すると共に、前記圧入された鋼矢板のうち所定数の鋼
矢板の凹部にH型鋼を圧入した後、前記土留壁の内側地
盤を掘削し、その後前記型枠にコンクリートを打設する
ようにした。
According to the method for constructing a wall of the present invention, a plurality of steel sheet piles to be a formwork are press-fitted into the ground to form a retaining wall, and a predetermined number of the press-fitted steel sheet piles are used. After H-shaped steel was press-fitted into the recesses of the steel sheet pile, the inner ground of the earth retaining wall was excavated, and then concrete was placed in the formwork.

【0005】[0005]

【作用】上記の壁体の構築方法では、鋼矢板により土留
壁を構成した結果、鋼矢板が略コ字形に順次連なる壁と
なり通常の平板等からなる土留壁と比較して強度的に強
くなるため、切梁および腹起こしを設ける必要がなくな
り、しかも壁自体の厚みを薄くすることができる。ま
た、鋼矢板を型枠として使用するため、土留壁とは別に
型枠を設置する必要がない。さらに所定数の鋼矢板の凹
部の地盤にH型鋼を圧入した結果、H型鋼はコンクリー
ト壁体の補強材となりコンクリート壁体の強度の向上を
図ることができる。また、前記H型鋼は構造体用の支持
杭も兼ねるように使用でき、構造体用の支持抗としての
柱を別体に立設する必要がない。
In the above method of constructing the wall body, the steel retaining sheet is used to construct the retaining wall, and as a result, the steel retaining sheet becomes a substantially U-shaped continuous wall, which is stronger than the retaining wall made of a normal flat plate. Therefore, it is not necessary to provide a cross beam and an upset, and the thickness of the wall itself can be reduced. Further, since the steel sheet pile is used as the form, it is not necessary to install the form separately from the retaining wall. Further, as a result of press-fitting the H-section steel into the ground of the recesses of the predetermined number of steel sheet piles, the H-section steel serves as a reinforcing material for the concrete wall body and can improve the strength of the concrete wall body. Further, the H-section steel can be used so as to also serve as a support pile for a structure, and it is not necessary to stand a column as a support for the structure separately.

【0006】[0006]

【実施例】添付する図面に基づいて本発明の壁体の構築
方法の一実施例を説明する。本発明の壁体の構築方法
は、まず土留壁及び型枠となる鋼矢板を地盤に複数圧入
すると共に、H型鋼を所定数の鋼矢板の凹部の地盤に圧
入して連壁を設ける。前記H型鋼は壁体補強材及び構造
体用の支持杭のいずれか一方となり、あるいは両方とな
ることができる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the method for constructing a wall body of the present invention will be described with reference to the accompanying drawings. According to the method for constructing a wall of the present invention, first, a plurality of steel retaining sheets and steel sheet piles to be a formwork are press-fitted into the ground, and H-shaped steel is press-fitted into the ground of the recesses of a predetermined number of steel sheet piles to provide a connecting wall. The H-section steel can be either one of the wall reinforcement and the support pile for the structure, or both.

【0007】上記鋼矢板及びH型鋼を圧入する杭圧入引
抜機Aの構成を図1〜3に基づいて説明する。杭圧入引
抜機Aは、地盤に圧入した既設鋼矢板Pの複数本を挟持
するクランプ2を下部に備えたサドル4と、該サドル4
の前方に構成され、鋼矢板P及びH型鋼10を挟持して
圧入するチャック3を有する。前記サドル4上には、既
設鋼矢板Pの並列方向へ少なくとも1ピッチ分以上移動
可能なスライドベース5が搭載され、該スライドベース
5に立設されたマスト6の前方には、ガイドレール7に
沿って上下に摺動し、かつ圧入鋼矢板P若しくは圧入H
型鋼10を挟持するチャック3が昇降機構8を介して形
成されている。
The construction of the pile press-fitting / pulling-out machine A for press-fitting the steel sheet pile and the H-shaped steel will be described with reference to FIGS. The pile press-fitting / extracting machine A includes a saddle 4 having a clamp 2 at a lower portion for sandwiching a plurality of existing steel sheet piles P press-fitted into the ground, and the saddle 4
Of the steel sheet pile P and the H-shaped steel 10 are sandwiched and press-fitted. A slide base 5 is mounted on the saddle 4 so as to be movable in a direction parallel to the existing steel sheet piles P by at least one pitch, and a guide rail 7 is provided in front of a mast 6 standing on the slide base 5. Slide vertically along and press fit steel sheet pile P or press fit H
A chuck 3 for sandwiching the shaped steel 10 is formed via an elevating mechanism 8.

【0008】ここで、前記チャック3の構造を図3に基
づいて説明する。チャック3は、縦方向に鋼矢板PとH
型鋼10とのいずれかを選択的に挿通可能な中空体を有
するチャック本体31からなる。このチャック本体31
には、チャック本体31内面から相互に離間して突出す
る一対の固定爪32と、前記固定爪32と対向する位置
に、流体圧シリンダ装置34によって移動可能な可動爪
33とから構成される。上記チャック3は、図示のよう
に鋼矢板Pのウエブ11を固定爪32と可動爪33とで
挟持し、H型鋼10の場合は、一対の固定爪32の間に
連結板部13を配置せしめ、一方の側板部12を固定爪
32と可動爪33とで挟持する。
The structure of the chuck 3 will be described with reference to FIG. The chuck 3 has steel sheet piles P and H in the vertical direction.
The chuck body 31 has a hollow body that can selectively insert any one of the shape steel 10. This chuck body 31
The pair of fixed claws 32 protrude from the inner surface of the chuck body 31 so as to be spaced apart from each other, and the movable claw 33 movable to the position facing the fixed claw 32 by the fluid pressure cylinder device 34. The chuck 3 holds the web 11 of the steel sheet pile P between the fixed claw 32 and the movable claw 33 as shown in the figure. In the case of the H-shaped steel 10, the connecting plate portion 13 is arranged between the pair of fixed claws 32. The one side plate 12 is sandwiched between the fixed claw 32 and the movable claw 33.

【0009】上記杭圧入引抜機Aによる壁体の構築方法
について説明する。先ず、既設鋼矢板P列上に杭圧入引
抜機Aを固定する。そして圧入鋼矢板Pをチャック3で
挟持し既設鋼矢板P前端に連接して圧入して移動用杭と
する。次にスライドベース5を前進させてチャック3を
1ピッチ移動し、該チャック3に圧入鋼矢板Pを挟持
し、前端の鋼矢板Pに隣接させて適宜深さまで圧入す
る。その後、上記圧入鋼矢板Pの圧入を一旦停止し、ク
ランプ2の挟持状態を解除してサドル4を適宜高さ上昇
し杭1ピッチ分だけ前進させる。次いで、サドル4を下
降し既設鋼矢板Pをクランプ2で挟持する。その後チャ
ック3を再び下降せしめ、上記圧入鋼矢板Pを完全に圧
入する。この作業を繰り返すことにより、杭圧入引抜機
Aを既設鋼矢板P上を自走させながら順次杭を圧入して
いくことができる。
A method for constructing a wall body by the pile press-fitting / pulling machine A will be described. First, the pile press-fitting / pulling machine A is fixed on the existing steel sheet pile P row. Then, the press-fitted steel sheet pile P is sandwiched by the chuck 3 and connected to the front end of the existing steel sheet pile P by press fitting to form a moving pile. Next, the slide base 5 is moved forward to move the chuck 3 by one pitch, and the press-fitting steel sheet pile P is sandwiched between the chucks 3 and adjacent to the steel sheet pile P at the front end and press-fitted to a proper depth. After that, the press-fitting of the press-fitting steel sheet pile P is temporarily stopped, the clamped state of the clamp 2 is released, and the saddle 4 is appropriately raised in height and advanced by one pitch of the pile. Next, the saddle 4 is lowered and the existing steel sheet pile P is clamped by the clamp 2. After that, the chuck 3 is lowered again, and the press-fitting steel sheet pile P is completely press-fitted. By repeating this work, the pile press-in / pull-out machine A can be sequentially press-fitted while the pile press-fitting / extracting machine A is self-propelled on the existing steel sheet pile P.

【0010】そして、上記のように鋼矢板Pを圧入した
後、次いでチャック3にH型鋼10を挿入し鋼矢板Pの
凹部PaにH型鋼10を圧入する。この場合、H型鋼1
0は図3(B)に示したように、一対の固定爪32間に
H型鋼10の連結板部13を位置させ、一方の側板部1
2を該固定爪32と可動爪33とで挟持する。
After the steel sheet pile P is press-fitted as described above, the H-section steel 10 is then inserted into the chuck 3 and the H-section steel 10 is press-fitted into the recess Pa of the steel sheet pile P. In this case, H-shaped steel 1
As shown in FIG. 3 (B), 0 indicates that the connecting plate portion 13 of the H-shaped steel 10 is positioned between the pair of fixing claws 32, and one side plate portion 1
2 is sandwiched between the fixed claw 32 and the movable claw 33.

【0011】上記のように、鋼矢板Pを圧入しつつH型
鋼10を圧入する他に、鋼矢板Pの圧入を完了して土留
壁を作成した後にH型鋼10を圧入するようにしても良
い。また、図1の鋼矢板Pxの凹部PaにH型鋼10を
圧入した後、杭圧入引抜機Aのマスト6を旋回させて、
チャック3を180度旋回して反転し、圧入進行方向後
方の鋼矢板Pyの凹部PaにH型鋼10を圧入しても良
い。
As described above, in addition to press-fitting the H-shaped steel 10 while press-fitting the steel sheet pile P, the H-shaped steel 10 may be press-fitted after the press-fitting of the steel sheet pile P is completed and the earth retaining wall is created. . Further, after the H-shaped steel 10 is press-fitted into the recess Pa of the steel sheet pile Px in FIG. 1, the mast 6 of the pile press-fitting / extracting machine A is swung,
The H-shaped steel 10 may be press-fitted into the recess Pa of the steel sheet pile Py at the rear of the press-fitting advancing direction by turning the chuck 3 180 degrees and inverting it.

【0012】鋼矢板Pを圧入しつつH型鋼10を圧入す
る場合、圧入進行方向の前方の鋼矢板PにH型鋼10を
圧入していくと、あとからその錆矢板Pを挟持するとき
にH型鋼10が邪魔となる。そのため上記のように、圧
入進行方向後方の鋼失板Pyの凹部PaにH型鋼10を
圧入するようにすれば、この問題がなくなる。
When the H-section steel 10 is press-fitted while the steel sheet pile P is being press-fitted, when the H-section steel 10 is press-fitted into the steel sheet pile P in the forward direction of the press-fitting progress, when the rust sheet pile P is clamped later, H The shape steel 10 becomes an obstacle. Therefore, as described above, if the H-shaped steel 10 is press-fitted into the recessed portion Pa of the steel lost plate Py behind the press-fitting traveling direction, this problem will be eliminated.

【0013】以上のようにして鋼矢板P及びH型鋼10
を圧入して連壁を設けた後、地盤を掘削する。この掘削
が終了すると、次に、図4に示すように、鉄筋コンクリ
ート工事で縦筋41及び横筋42を所定位置に配置す
る、いわゆる配筋を行うと共に鋼矢板Pを型枠として使
用し、この型枠にコンクリート43の打設作業を行う。
この場合、H型鋼10はコンクリート壁体の補強材とな
り、必要に応じて構造体用の支持杭も兼ねられる。構造
体用の支持杭として使用する場合は、壁体補強材として
使用する場合よりもさらに深く圧入しておく。なお、H
型鋼10を配していない鋼矢板Pの内側に配筋を行うよ
うにしても良い。また、H型鋼10を配した鋼矢板Pの
内側に、H型鋼を囲むようにプープ筋等で配筋を行うよ
うにしても良い。
As described above, the steel sheet pile P and H type steel 10
After press-fitting and installing a connecting wall, the ground is excavated. When this excavation is completed, next, as shown in FIG. 4, the vertical reinforcement 41 and the horizontal reinforcement 42 are arranged at predetermined positions in the reinforced concrete construction, so-called reinforcement is performed, and the steel sheet pile P is used as a formwork. The concrete 43 is placed on the frame.
In this case, the H-shaped steel 10 serves as a reinforcing material for the concrete wall, and also serves as a support pile for the structure, if necessary. When using it as a support pile for a structure, press it deeper than when using it as a wall reinforcement. In addition, H
You may make it arrange | position a reinforcement inside the steel sheet pile P which does not arrange | position the shape steel 10. Moreover, you may make it arrange | position the inside of the steel sheet pile P which has arrange | positioned the H-section steel 10 with a poop reinforcement etc. so that H-section steel may be surrounded.

【0014】以上のような壁体の構築方法によると、次
のような利点がある。従来では、土留壁の倒れを防止す
るため、切梁および腹起こしを設ける必要があったが、
本実施例では鋼矢板Pにより土留壁を構成した結果、鋼
矢板Pが略コ字形に順次連なる壁となり、通常の平板等
からなる土留壁と比較して強度的に強くなるため切梁お
よび腹起こしを設ける必要がなくなる。しかも壁自体の
厚みを薄くすることができる。また、鋼矢板Pを型枠と
して使用した場合、土留壁とは別に型枠を設置する必要
がない。さらに、H型鋼10はコンクリート壁体の補強
材となりコンクリート壁体の強度の向上を図ることがで
きる。また、H型鋼10は構造体用の支持杭も兼ねるよ
うに使用でき、構造体用の支持杭としての柱を別に立設
する必要がない。
The method of constructing the wall as described above has the following advantages. Conventionally, it was necessary to provide a cutting beam and abdomen to prevent the retaining wall from falling.
In this embodiment, the steel retaining sheet P is used as the retaining wall, and as a result, the steel retaining sheet P becomes a substantially U-shaped wall in succession, which is stronger than the retaining retaining wall made of an ordinary flat plate or the like. There is no need to provide a wake up. Moreover, the thickness of the wall itself can be reduced. Further, when the steel sheet pile P is used as a form, it is not necessary to install the form separately from the retaining wall. Further, the H-shaped steel 10 serves as a reinforcing material for the concrete wall body and can improve the strength of the concrete wall body. Further, the H-shaped steel 10 can be used also as a support pile for a structural body, and it is not necessary to separately erect a column as a support pile for a structural body.

【0015】[0015]

【発明の効果】本発明の壁体の構築方法によれば、壁体
の強度の向上を図れると共に、面倒な手間が掛からず、
工期、工費の短縮化を図ることができる。
According to the method of constructing a wall body of the present invention, the strength of the wall body can be improved and no troublesome labor is required.
The construction period and construction cost can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例を示す概略平面図FIG. 1 is a schematic plan view showing an embodiment of the present invention.

【図2】本発明を実施する際に使用する杭圧入引抜機の
正面図
FIG. 2 is a front view of a pile press-fitting / pulling machine used when implementing the present invention.

【図3】同杭圧入引抜機のチャックの構成を示す断面図FIG. 3 is a cross-sectional view showing a configuration of a chuck of the pile press-fitting / pulling machine.

【図4】壁体の構造を示す概略平面図FIG. 4 is a schematic plan view showing a structure of a wall body.

【符号の説明】[Explanation of symbols]

A 杭圧入引抜機 P 鋼矢板 3 チャック 10 H型鋼 41 鉄筋 42 鉄筋 43 コンクリート A Pile press-in / pull-out machine P Steel sheet pile 3 Chuck 10 H-shaped steel 41 Reinforcing bar 42 Reinforcing bar 43 Concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 型枠となる鋼矢板を地盤に複数圧入して
土留壁を作成すると共に、前記圧入鋼矢板のうち所定数
の鋼矢板の凹部にH型鋼を圧入した後、前記土留壁の内
側地盤を掘削し、その後前記型枠にコンクリートを打設
する壁体の構築方法。
1. A plurality of steel sheet piles to be a formwork are press-fitted into the ground to form a retaining wall, and H-shaped steel is press-fitted into recesses of a predetermined number of the steel sheet piles of the press-fitting steel sheet piles. A method for constructing a wall body in which the inner ground is excavated, and then concrete is placed in the formwork.
JP5048517A 1993-01-28 1993-01-28 How to build a wall Expired - Fee Related JP2618796B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5048517A JP2618796B2 (en) 1993-01-28 1993-01-28 How to build a wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5048517A JP2618796B2 (en) 1993-01-28 1993-01-28 How to build a wall

Publications (2)

Publication Number Publication Date
JPH06228945A true JPH06228945A (en) 1994-08-16
JP2618796B2 JP2618796B2 (en) 1997-06-11

Family

ID=12805563

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5048517A Expired - Fee Related JP2618796B2 (en) 1993-01-28 1993-01-28 How to build a wall

Country Status (1)

Country Link
JP (1) JP2618796B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003055961A (en) * 2001-08-14 2003-02-26 Kawasaki Steel Corp Steel-concrete integrated underground wall and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4933405A (en) * 1972-07-28 1974-03-27
JPH0211838U (en) * 1988-07-07 1990-01-25

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4231418A (en) * 1979-05-07 1980-11-04 Hughes Aircraft Company Cryogenic regenerator

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4933405A (en) * 1972-07-28 1974-03-27
JPH0211838U (en) * 1988-07-07 1990-01-25

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003055961A (en) * 2001-08-14 2003-02-26 Kawasaki Steel Corp Steel-concrete integrated underground wall and construction method thereof

Also Published As

Publication number Publication date
JP2618796B2 (en) 1997-06-11

Similar Documents

Publication Publication Date Title
CN113958323B (en) Large-section tunnel construction method and supporting structure
KR101721579B1 (en) Excavation Propulsion Apparatus of Underground Concrete Structure on Segement Construction Base
KR101303448B1 (en) Leading pipe propulsion device and non-open cut pipe installation method of underground structures using the same
CN113513025A (en) A kind of foundation pit enclosure form LHCW construction method
KR101479267B1 (en) Method for constructing tunnel by using pipe
KR101840658B1 (en) The structure assembly for building a tunnel and building method thereof
JPH06228945A (en) Construction of wall
JP2553002B2 (en) Pile press-in / pull-out machine
KR20230136576A (en) Combined guide unit for sheet pile construction and construction method of sheet pile using it.
JP3135188B2 (en) Construction method of underground cavity
CN217150255U (en) Foundation pit support form LHCW tool
JP2000291031A (en) Construction method of seismic isolation structure
JPH10317374A (en) Method for constructing underground column made of reinforced concrete
JP3805342B2 (en) Yamadome wall structure
JP2757209B2 (en) Cut-and-joint underground construction method using synthetic steel beams
JPH11190024A (en) Earth retaining work
KR20210157071A (en) Wall forming method using U-type bending steel plate in the structure for underground tunnel formation
CN218541642U (en) Tie piece installation auxiliary device for masonry structure reinforcement
JP3677704B2 (en) Steel erection equipment
CN222183070U (en) A water trestle steel pipe pile positioning and beam installation platform
KR102276810B1 (en) Earth retaing structure, earth retaing plate and construction methd using the same
JP2000257069A (en) Earth retaining and earth retaining construction method
KR20240177474A (en) Retaining wall construction method using strip type steel plate inserting PHC Pile
JP2004190318A (en) Guide tube fixing structure
JPH093898A (en) Method and structure for earth retaining for excavation of rectangular hole

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19961203

LAPS Cancellation because of no payment of annual fees