JPH05330758A - Elevator guide rail installation assist device and guide rail installation method - Google Patents
Elevator guide rail installation assist device and guide rail installation methodInfo
- Publication number
- JPH05330758A JPH05330758A JP13900292A JP13900292A JPH05330758A JP H05330758 A JPH05330758 A JP H05330758A JP 13900292 A JP13900292 A JP 13900292A JP 13900292 A JP13900292 A JP 13900292A JP H05330758 A JPH05330758 A JP H05330758A
- Authority
- JP
- Japan
- Prior art keywords
- guide rail
- rail
- guide
- hoistway
- elevator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B19/00—Mining-hoist operation
- B66B19/002—Mining-hoist operation installing or exchanging guide rails
Landscapes
- Handcart (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、エレベータ昇降路内に
かご或いはつり合いおもりの案内用のガイドレールを付
設する作業に利用されるガイドレール付設作業支援装置
及びその装置を用いたガイドレール付設作業法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a guide rail installation work support device used for installing a guide rail for guiding a car or a counterweight in an elevator hoistway, and a guide rail installation work using the device. Concerning the law.
【0002】[0002]
【従来の技術】一般に、ビル等の建屋に対するエレベー
タ据付作業の一つとして、かご或いはつり合いおもりを
案内するガイドレールを昇降路内の最下部から最上部ま
での全長に亘り付設する必要がある。特に近年のように
建物が高層化すると、昇降路が長くなり、ガイドレール
を多数本継ぎ足して付設しなければならない。しかも、
その複数本のガイドレールは昇降路の外で連結して長大
な一本レールの剛体としてしまうと、狭い乗場出入口か
ら昇降路内に引き込むことができないので、ガイドレー
ル同士の連結は全て昇降路内の高所で行っている。2. Description of the Related Art Generally, as one of elevator installation work for buildings such as buildings, it is necessary to install a guide rail for guiding a car or a counterweight over the entire length from the bottom to the top of the hoistway. In particular, as buildings have become higher in height as in recent years, the hoistway becomes longer, and many guide rails must be added and attached. Moreover,
If the multiple guide rails are connected outside the hoistway to form a long one-rigid rigid body, the guide rails cannot be pulled into the hoistway from a narrow entrance / exit, so all guide rails must be connected inside the hoistway. Are going up in high places.
【0003】その従来のガイドレール付設作業として
は、まず、適当な単位長さ(通常4〜5m)の所要本数
のガイドレールを工場から現場の建屋の昇降路の最下部
の入口のフロア(乗場)に運ぶ。それらのガイドレール
を一本ずつ揚重機により昇降路内底部(下端ピット)に
引き込んで立て掛け状態に仮置きする。In the conventional work of installing guide rails, first, a required number of guide rails having an appropriate unit length (usually 4 to 5 m) are installed from the factory to the floor at the bottom entrance of the hoistway of the building (site ) To carry. Each of these guide rails is pulled into the bottom of the hoistway (lower end pit) by a lifting machine and temporarily placed in a leaning position.
【0004】次に、昇降路内に仮設足場を高く組み上
げ、この仮設足場上に作業員が乗って、前述の如く仮置
した一番目のガイドレールを昇降路上端の揚重機により
レール一本分の長さに相当する高さまで吊り上げさせ
る。そして、前記仮設足場に乗った作業員がその一番目
のガイドレールの下端に二番目のガイドレールの上端を
継ぎ足すように芯合わせしながら接合して、その相互を
継目板と複数のボルト・ナット等の締結具により連結す
る。この状態で再度前記揚重機を稼働させて一番目のガ
イドレールと二番目のガイドレールを一緒に吊り上げ、
この二番目のガイドレール一本分の長さに相当する高さ
まで吊り上げられたら、その下端に前記同様にして三番
目のガイドレールを連結する。Next, a temporary scaffold is built up in the hoistway to a high level, and a worker rides on the temporary scaffold, and the first guide rail temporarily placed as described above is used for one rail by a hoist at the top of the hoistway. Lift to a height equivalent to the length of. Then, an operator riding on the temporary scaffolding joins the lower end of the first guide rail with the upper end of the second guide rail while aligning the upper ends of the second guide rails, and joins them together with a joint plate and a plurality of bolts. Connect with fasteners such as nuts. In this state, operate the lifting machine again and lift the first guide rail and the second guide rail together,
After being lifted to a height corresponding to the length of one of the second guide rails, the third guide rail is connected to the lower end in the same manner as described above.
【0005】こうして吊り上げ連結作業を繰り返すこと
で、必要本数のガイドレールを連結しながら昇降路内壁
の所定のレール付設位置に沿って吊り上げ保持する。こ
の状態でその一連のガイドレールをゴンドラに乗った作
業員が昇降路内壁の所定のレール付設位置にレールブラ
ケットとレールクリップを介し締結しながら仮止めす
る。そして、最終的にはそれら一連のガイドレールを段
差なく鉛直状態に芯出し調整して本締め固定することで
付設作業を終了する。By repeating the lifting and connecting work in this manner, the required number of guide rails are connected and lifted and held along a predetermined rail attachment position on the inner wall of the hoistway. In this state, an operator who rides on the gondola temporarily fixes the series of guide rails to a predetermined rail-attached position on the inner wall of the hoistway while fastening the rail brackets and rail clips. Finally, the series of guide rails are centered and adjusted in a vertical state without steps, and finally fixed and fixed, whereby the installation work is completed.
【0006】[0006]
【発明が解決しようとする課題】ところで、前述した従
来のガイドレール付設作業では、昇降路内底部に搬入し
て立て掛け状態に仮置きしたガイドレールを揚重機によ
りレール一本分の長さに相当する高さまで吊り上げ、こ
の下端に次のガイドレールの上端を継目板と複数のボル
ト・ナット等の締結具により継ぎ足すように連結すると
行った具合に、ガイドレールを昇降路内の所定高さまで
吊り上げながら、その高所で次々とガイドレールの連結
作業を行う必要がある。By the way, in the above-described conventional work for attaching a guide rail, a guide rail that is carried into the bottom of the hoistway and temporarily placed in a leaning state is equivalent to the length of one rail by a lifting machine. The guide rail is lifted to a predetermined height in the hoistway by connecting the upper end of the next guide rail to this lower end by connecting the upper end of the next guide rail with a joint plate and multiple fasteners such as bolts and nuts. However, it is necessary to connect the guide rails one after another at the high places.
【0007】この昇降路内の高所でガイドレール連結作
業を行うには、作業者が乗るやぐらの如き高い仮設足場
が必要で、作業者が不安定で転落など危険度が高く、且
つ暗いなど、非常に作業環境が悪い。またガイドレール
の端部同士は精密加工仕上げされており、その仕上げ面
を注意深く慎重に扱いながら連結作業を行う必要がある
のと、ガイドレールがかなり重量物(30〜150Kg
/本)であるので、前述の如く暗く非常に作業環境が悪
い昇降路内高所では非常に連結作業がし難く非能率的で
あった。In order to perform the guide rail connecting work at a high place in the hoistway, a high temporary scaffold such as a yagura on which the worker rides is required, and the worker is unstable and is at a high risk of falling, and is dark. , The working environment is very bad. In addition, the ends of the guide rails are precision machined and it is necessary to carry out the connection work while carefully handling the finished surface, and the guide rails are very heavy (30 to 150 kg).
As described above, it was inefficient because it was very difficult to perform the connecting work at a high place in the hoistway, which was dark and had a very bad working environment.
【0008】また、吊り上げた一連のガイドレールを昇
降路内壁に固定するためのレールブラケットを、一々は
各所用高さに荷揚げするのは面倒であると共に、その各
所用高さでレールブラケットをレールクリップと締結具
でガイドレールにそれぞれ締結する作業も高所であるの
で手間の掛かる面倒な作業になっていた。[0008] Further, it is troublesome to unload the rail brackets for fixing a series of hoisted guide rails to the inner wall of the hoistway at each place height, and at the same time, the rail brackets are used to lift the rail brackets at each place height. Since the work of fastening each to the guide rail with the clip and the fastener is also at a high place, it was a troublesome work.
【0009】そこで、段取り作業の効率を上げるため
に、各ガイドレールの所用箇所に予めレールブラケット
をレールクリップと締結具で締結固定し、この状態で各
ガイドレールを昇降路内に搬入立て掛け、これらを一本
ずつ吊り上げながら順次連結して行くことが望ましい
が、こうした場合、レールブラケット付きガイドレール
を昇降路内に多数本立て掛け仮置きすると、そのガイド
レール相互のレールブラケット同志がが引っ掛かった
り、そのレールブラケットが昇降路内壁の各種ビームや
ファスナープレートなどに引っ掛かるなどして、取り扱
えが面倒で、一本ずつ吊り上げながら順次連結して昇降
路内壁の所定のレール付設位置に沿って吊り上げて行く
作業が非常に難しくなる。Therefore, in order to improve the efficiency of the setup work, the rail bracket is previously fastened and fixed to the required portion of each guide rail with a rail clip and a fastener, and in this state, each guide rail is carried in and hoisted in the hoistway. It is desirable to connect the rails one by one while sequentially connecting them, but in such a case, if a number of guide rails with rail brackets are erected in the hoistway and temporarily placed, the rail brackets of the guide rails may be caught or Since the rail bracket is caught on various beams and fastener plates on the inner wall of the hoistway, it is troublesome to handle, and the work of hoisting one by one and sequentially connecting them while hoisting along the predetermined rail attachment position on the inner wall of the hoistway is possible. Very difficult.
【0010】本発明は前記事情に鑑みなされ、その目的
とするところは、昇降路内へのガイドレールの搬入がエ
レベータ乗場出入口から簡便にできると共に、その昇降
路内に搬入したガイドレールを該乗場出入口近傍の手の
届くところで楽に且つ安全に順次吊り上げながら一本ず
つ継ぎ足すように連結して行くのを支援できて、面倒で
あった昇降路内の暗く高所での作業を大幅に軽減でき、
レール付設作業の高能率化を図るのに非常に有用なエレ
ベータ用ガイドレール付設作業支援装置を提供すること
にある。The present invention has been made in view of the above circumstances, and an object thereof is to easily carry a guide rail into a hoistway from an elevator hall entrance / exit, and to use the guide rail carried into the hoistway to the hall. It can easily and safely lift the doors near the doorway and connect them one after another while hoisting them one by one, which can greatly reduce the troublesome work in dark and high places in the hoistway. ,
An object of the present invention is to provide an elevator guide rail installation work support device that is extremely useful for increasing the efficiency of rail installation work.
【0011】また、昇降路外部で予めレールブラケット
を取り付けた状態のガイドレールを昇降路内に楽に搬入
して順次継ぎ足すように連結しながら吊り上げて行くの
を支援できて、段取り作業の効率アップを図るのに有効
となるエレベータ用ガイドレール付設作業支援装置を提
供することを目的とする。Further, it is possible to assist in easily carrying in the guide rails in which the rail brackets are previously attached outside the hoistway into the hoistway, and hoisting them while sequentially connecting them to increase the efficiency of setup work. It is an object of the present invention to provide an elevator guide rail installation work support device that is effective in achieving the above.
【0012】また、前記エレベータ用ガイドレール付設
作業支援装置を用いて、楽に且つ安全にしかも効率良く
ガイドレールの昇降路内への吊り上げ付設作業を行うこ
とができるエレベータ用ガイドレール付設作業法を提供
することを目的とする。Further, there is provided an elevator guide rail installation work method capable of performing lifting installation work of a guide rail in a hoistway easily, safely and efficiently by using the elevator guide rail installation work support device. The purpose is to do.
【0013】[0013]
【課題を解決するための手段と作用】本発明のエレベー
タ用ガイドレール付設作業支援装置は、前記目的を達成
するために、ガイドレールをエレベータ乗場出入口より
昇降路内方に送り込み可能に搭載するレール搬入台と、
このレール搬入台の先端部に設けられガイドレールを摺
動可能に案内し且つガイドレールを昇降路内方に送り込
むに従いそのガイドレールを昇降路内の乗場出入口近傍
に鉛直に落とし込み支持するレール案内支持機構と、こ
のレール案内支持機構により案内支持されるガイドレー
ルの落とし込み角度をコントロールする角度制御機構
と、ガイドレールの昇降路内への落とし込み高さをコン
トロールする高さ制御機構とを備えてなる。In order to achieve the above-mentioned object, the elevator guide rail installation work supporting device of the present invention is a rail for mounting the guide rail so that it can be fed into the hoistway from the elevator entrance / exit. With a loading platform,
Rail guide support that is provided at the tip of this rail loading table and guides the guide rail slidably and vertically drops the guide rail near the landing doorway in the hoistway as the guide rail is fed inside the hoistway. The mechanism includes a mechanism, an angle control mechanism that controls the drop angle of the guide rail guided and supported by the rail guide support mechanism, and a height control mechanism that controls the drop height of the guide rail into the hoistway.
【0014】こうしたエレベータ用ガイドレール付設作
業支援装置であれば、搬入台上に搭載したガイドレール
を一本ずつレール案内支持機構により案内して角度制御
機構と高さ制御機構でコントロールしながら、適当な乗
場出入口から昇降路内に楽に落とし込み搬入できて、そ
のガイドレールを昇降路内の乗場出入口近傍の手の届く
ところに鉛直に立てて支持できるようになる。これで、
その搬入したガイドレールを別の揚重機で吊り上げた
り、その下端に次に搬入したガイドレールを継ぎ足すよ
うに連結したりする作業を、該乗場出入口で楽に且つ安
全に行いえるように支援でき、昇降路内の暗く高所での
作業の大幅な軽減と作業能率の向上を図るのに大いに役
立つようになる。In the case of such an elevator guide rail installation work support device, the guide rails mounted on the carry-in table are guided one by one by the rail guide support mechanism and controlled appropriately by the angle control mechanism and the height control mechanism. It can be easily dropped into the hoistway from a landing entrance and can be carried in, and its guide rail can be vertically supported within a hoistway near the landing door and can be supported vertically. with this,
The guide rail that has been carried in can be lifted by another lifting machine, or the work of connecting the guide rail that has been carried in next to its lower end to be added can be assisted so that it can be done easily and safely at the entrance / exit of the hall, It will be very useful for drastically reducing work in dark and high places in the hoistway and improving work efficiency.
【0015】なお、前記レール搬入台は、下部に操舵可
能な車輪を有し、ガイドレールを搭載して建物内を移動
可能な走行台車であることが望ましい。この走行台車形
式のレール搬入台であれば、工場等から輸送したガイド
レールを建物内のエレベータ乗場出入口まで楽に輸送で
き、かつその乗場出入口でガイドレールの昇降路内への
搬入向き及び位置を適切に選定できるようになる。It is desirable that the rail carry-in pedestal is a traveling dolly having steerable wheels at its lower portion and having guide rails mounted therein so as to be movable in a building. With this traveling carriage type rail loading platform, the guide rails transported from factories etc. can be easily transported to the elevator landing doorway in the building, and the loading and unloading direction of the guide rails at the landing doorway is appropriate. Can be selected.
【0016】また、前記レール案内支持機構は、レール
搬入台の先端部に起倒方向に回動可能に装着された機構
本体と、この機構本体に各々装着されガイドレールの長
手方向に間隔を存した2箇所を摺動可能に抱持して案内
支持する二重の案内支持部を有し、且つその両案内支持
部が予めガイドレールに取り付けたブラケットを通過可
能に交互に待避する構成であることが望ましい。The rail guide support mechanism is mounted on the tip of the rail carry-in table so as to be rotatable in the up and down direction, and the rail guide support mechanism is mounted on each of the mechanism bodies and has a space in the longitudinal direction of the guide rail. It has a double guide support part that slidably holds and guides the above two places, and both of the guide support parts are alternately retracted so that they can pass through a bracket previously attached to the guide rail. Is desirable.
【0017】こうしたレール案内支持機構を備えること
で、昇降路外部で予めレールブラケットの取り付けなど
の段取り作業を行ったガイドレールであっても、そのレ
ールブラケットを二重の案内支持部が交互に待避しなが
ら通過させて、そのガイドレールを適確に案内支持し、
昇降路内の乗場出入口近傍に楽に落とし込み搬入して鉛
直状態に支持できるようになる。これでレールブラケッ
ト付きガイドレールでも別な揚重機による吊り上げ作業
及びその下端への次のガイドレールの連結作業並びに昇
降路内壁の所定のレール付設位置への固定作業を、楽に
効率良く行うのに有効となる。By providing such a rail guide support mechanism, even if the guide rail has been preliminarily set up outside the hoistway, such as mounting a rail bracket, the guide rails are alternately saved by the double guide support portions. While passing it, guide and support the guide rail accurately,
It is possible to easily drop it in the vicinity of the entrance and exit of the hoistway and carry it in vertically to support it. With this, even with a guide rail with a rail bracket, it is effective to easily and efficiently perform lifting work by another lifting machine, connecting the next guide rail to its lower end, and fixing work to the predetermined rail attachment position on the inner wall of the hoistway. Becomes
【0018】本発明のエレベータ用ガイドレール付設作
業法は、前記目的を達成するために、前述のエレベータ
用ガイドレール付設作業支援装置を用いて、一番目のガ
イドレールをエレベータ乗場出入口より昇降路内に案内
支持しながら落とし込んで、そのガイドレールを昇降路
内の乗場出入口近傍に鉛直に立てて支持し、このガイド
レールを昇降路上部に設置した揚重機によりガイドレー
ル一本分の長さだけ上方に吊り上げ、次に二番目のガイ
ドレールを前記同様ガイドレール付設作業支援装置を用
いて昇降路内の乗場出入口近傍に搬入して鉛直に立てて
支持し、この二番目のガイドレール上端を前記一番目の
ガイドレールの下端に乗場出入口近傍で連結し、この連
結状態の一番目と二番目とのガイドレールを再度揚重機
によりガイドレール一本分の長さだけ上方に吊り上げ、
こうしたガイドレールの搬入・連結・吊り上げ作業を規
定のガイドレール長さになるまで順次繰り返し、その一
連のガイドレールを昇降路内の乗場出入口近傍から該昇
降路内壁の所定のレール付設位置に吊り移して芯出しな
がら固定することを特徴とする。In order to achieve the above-mentioned object, the elevator guide rail installation work method of the present invention uses the above elevator guide rail installation work support device to move the first guide rail from the elevator hall entrance to the hoistway. The guide rail is vertically supported near the landing doorway in the hoistway and supported by a lifting machine installed above the hoistway, and the guide rail is lifted up by the length of one guide rail. Then, the second guide rail is carried to the vicinity of the landing doorway in the hoistway using the guide rail-equipped work support device in the same manner as above, and vertically supported to support the upper end of the second guide rail. Connect it to the lower end of the second guide rail near the entrance / exit of the landing, and again connect the first and second guide rails in this connected state with the lifting machine. Lifting upward by the length of one minute,
These guide rail loading, connection, and lifting operations are sequentially repeated until the specified guide rail length is reached, and the series of guide rails is suspended from the vicinity of the entrance / exit of the hoistway to the predetermined rail attachment position on the inner wall of the hoistway. It is characterized by fixing while centering.
【0019】こうしたエレベータ用ガイドレール付設作
業法であれば、ガイドレールの昇降路内への搬入吊り上
げ・連結と言った面倒な作業を、エレベータ乗場出入口
で楽に且つ安全にしかも効率良く行い得るようになっ
て、従来のような昇降路内の暗く高所での作業を大幅に
削減できるようになり、ガイドレールの昇降路内への付
設作業の能率向上が図れるようになる。According to such an elevator guide rail installation work method, it is possible to easily, safely, and efficiently perform troublesome works such as loading / lifting / connection of the guide rail into / from the hoistway at the elevator entrance / exit. Therefore, it is possible to significantly reduce the work in the dark and high places in the hoistway as in the conventional art, and improve the efficiency of the work of attaching the guide rails to the hoistway.
【0020】[0020]
【実施例の構成】以下、本発明の実施例を図面に基づい
て説明する。なお、説明の便宜上、図1乃至図10によ
り、エレベータ用ガイドレール付設作業支援装置から先
に説明する。Embodiments of the present invention will be described below with reference to the drawings. For convenience of description, the elevator guide rail installation work support device will be described first with reference to FIGS. 1 to 10.
【0021】まず、図1乃至図3に於いて、符号1は建
物のエレベータ昇降路2内に付設されるかご或いは吊り
合いおもり用のガイドレールを示している。このガイド
レール1のフランジ部背面側先端部には予め継目板3が
複数本のボルト・ナットにより締結されている。またこ
のガイドレール1のフランジ部背面側の長手方向途中複
数箇所にはアングル材の如きレールブラケット4がレー
ルクリップとボルト・ナット(図示省略)で仮締めして
取り付けられている。First, in FIG. 1 to FIG. 3, reference numeral 1 denotes a guide rail for a car or a hanging weight attached in an elevator hoistway 2 of a building. The seam plate 3 is previously fastened to the front end portion of the guide rail 1 on the rear surface side of the flange portion by a plurality of bolts and nuts. Further, rail brackets 4 such as angle members are temporarily tightened and attached by rail clips and bolts and nuts (not shown) at a plurality of positions in the longitudinal direction on the rear surface side of the flange portion of the guide rail 1.
【0022】こうしたガイドレール1を昇降路2内に搬
入して付設作業を支援する装置として、該ガイドレール
1を一本ずつ例えば地上一階フロア1Fのエレベータ乗
場出入口5より昇降路2内方に送り込み可能に搭載する
レール搬入台10が備えられている。このレール搬入台
10は乗場出入口5付近のフロア1Fに仮設される固定
式のものでも良いが、ガイドレール1を搭載して建物内
を移動可能な走行台車式が望ましい。As a device for carrying the guide rails 1 into the hoistway 2 to support the installation work, the guide rails 1 are guided one by one, for example, from the elevator landing doorway 5 on the first floor 1F above the hoistway 2. A rail carry-in table 10 that is mounted so as to be sent in is provided. The rail loading platform 10 may be a fixed type that is temporarily installed on the floor 1F near the entrance / exit 5 of the hall, but is preferably a traveling carriage type that can be moved in the building by mounting the guide rail 1.
【0023】したがって、このレール搬入台(台車)1
0は、前後に細長な台車台枠11の下側部に操舵(ステ
アリング)可能な左右一対ずつの前後車輪12を有し、
建物内の曲りのある通路を自在に向きを変えながら通行
できる構成とされている。なお、この前後車輪12はス
テアリング部にモータ等の走行駆動源を設けて、人力を
借りずにリモコン操縦等で自走式に操舵走行できる構成
でも良い。Therefore, this rail carrying table (cart) 1
0 has a pair of left and right front and rear wheels 12 that can be steered to the lower side of the elongated bogie frame 11 in the front and rear,
The structure is such that you can freely turn around the curved passageway inside the building. The front and rear wheels 12 may have a configuration in which a steering drive source such as a motor is provided in the steering portion so that the front and rear wheels 12 can be steered in a self-propelled manner by manipulating the remote controller or the like without borrowing human power.
【0024】この台車台枠11の上部中央線上には前後
方向に間隔を存し一列に配して複数個の溝付き支持ロー
ラ13が回転可能に軸着されて、これらの上にガイドレ
ール1をうつぶせに寝せた(図4に示す如くレール頂部
を下向きにフランジ部を上側にした)状態で水平に搭載
支持できると共に、そのガイドレール1をストッパ(図
示せず)を解除することで人手等により台車台枠11の
先端方にスムーズに送り出せるようになっている。A plurality of grooved support rollers 13 are rotatably mounted on the center line of the upper part of the bogie frame 11 in a row at intervals in the front-rear direction and rotatably mounted on the guide rails 1. It can be horizontally mounted and supported with the user lying down on its side (the rail top is facing downward and the flange is facing upward as shown in FIG. 4), and the guide rail 1 can be manually released by releasing a stopper (not shown). As a result, the bogie frame 11 can be smoothly sent to the front end.
【0025】こうしたレール搬入台10の台車台枠11
にガイドレール1を摺動可能に案内し且つガイドレール
1を昇降路2内方に送り込むに従いそのガイドレール1
を昇降路2内の乗場出入口5近傍に鉛直に落とし込み支
持するレール案内支持機構20が設けられていると共
に、このレール案内支持機構20により案内支持される
ガイドレール1の落とし込み角度θをコントロールする
角度制御機構30と、そのガイドレール1の昇降路2内
への落とし込み高さをコントロールする高さ制御機構4
0とが備えられている。A bogie frame 11 of such a rail carrying table 10
The guide rail 1 is slidably guided in the guide rail 1 and the guide rail 1 is fed into the hoistway 2 as the guide rail 1 is slid.
A rail guide support mechanism 20 for vertically dropping and supporting the rail is provided near the landing doorway 5 in the hoistway 2, and an angle for controlling the drop angle θ of the guide rail 1 guided and supported by the rail guide and support mechanism 20 is provided. A control mechanism 30 and a height control mechanism 4 for controlling the height of the guide rail 1 dropped into the hoistway 2.
0 and are provided.
【0026】前記レール案内支持機構20は、図1乃至
図3に示す如くレール搬入台10の台車台枠11の先端
部に軸21により起倒方向に回動自在に装着された長方
枠状の機構本体22と、この機構本体22に各々装着さ
れガイドレールの長手方向に間隔を存した2箇所を抱持
して案内支持する二重の案内支持部23A,23Bとを
有している。この両案内支持部23A,23Bでレール
搬入台10上に搭載されたガイドレール1の先端部を摺
動可能に案内し、そのガイドレール1を昇降路2内方に
送り込むに従い重量バランスにより機構本体22が軸2
1を中心に回動して該ガイドレール1を昇降路2内の乗
場出入口5近傍(乗場の作業員の手が楽に届く位置)に
鉛直に落とし込み支持する構成である。As shown in FIGS. 1 to 3, the rail guide support mechanism 20 has a rectangular frame shape which is attached to the tip of the bogie frame 11 of the rail loading table 10 by a shaft 21 so as to be rotatable in the up and down direction. The mechanism main body 22 and the double guide support portions 23A and 23B each of which is attached to the mechanism main body 22 and holds and guides two positions spaced apart in the longitudinal direction of the guide rail. The guide main body 1 mounted on the rail carry-in table 10 is slidably guided by the two guide supporting portions 23A and 23B, and the guide rail 1 is fed inwardly of the hoistway 2 by the weight balance as the mechanism main body is fed. 22 is axis 2
The guide rail 1 is pivoted around 1 to vertically drop and support the guide rail 1 in the vicinity of the entrance / exit 5 of the hoistway 2 (a position where a worker on the landing can easily reach).
【0027】更に詳述すると、その両案内支持部23
A,23Bは、図5及び図6に示す如く、ガイドレール
1の頂部に下側から転接して該ガイドレール1の重力を
支える下部支えローラ23aと、ガイドレール1の頂部
に左右から転接して挟む左右一対の案内ローラ23b
と、ガイドレール1のフランジ部背面に転接する抑えロ
ーラ23cとをそれぞれ回転自在に軸支し、これらロー
ラ23a,23b,23b,23cでガイドレール1を
抱持する状態で前後方向に摺動可能に案内支持する構成
である。More specifically, both guide supporting portions 23 thereof
As shown in FIGS. 5 and 6, A and 23B roll from the lower side to the top of the guide rail 1 to support the gravity of the guide rail 1 and a lower support roller 23a to the top of the guide rail 1 from the left and right sides. Left and right guide rollers 23b sandwiched between
And a pressing roller 23c rollingly contacting the rear surface of the flange portion of the guide rail 1 are rotatably supported, respectively, and the rollers 23a, 23b, 23b, and 23c can slide in the front-rear direction while holding the guide rail 1 The guide is supported by.
【0028】また、その両案内支持部23A,23Bの
抑えローラ23cは、各々ブラケット逃げ機構24によ
り交互に一側外方に待避可能に支持されている。つま
り、ブラケット逃げ機構24は、図6に示す如く、機構
本体22の一側張出し部内に装着した回転駆動部24a
と、この回転駆動部24aから上方に立ち上げた回転軸
24bと、この回転軸24b上端に基端部を嵌着して水
平方向に往復回動する回動アーム24cとを備え、この
回動アーム24cの先端に前記抑えローラ23cが装着
されている。このブラケット逃げ機構24により抑えロ
ーラ23c,23cが交互に一側外方に待避して、ガイ
ドレール1のフランジ部背面に予め取り付けた前記レー
ルブラケット4の通過を可能としている。The restraining rollers 23c of the two guide supporting portions 23A and 23B are alternately supported by the bracket escape mechanism 24 so as to be retracted outward on one side. That is, as shown in FIG. 6, the bracket escape mechanism 24 includes the rotary drive unit 24a mounted in the one side projecting portion of the mechanism main body 22.
A rotary shaft 24b that is raised upward from the rotary drive unit 24a; and a rotary arm 24c that fits a base end portion on the upper end of the rotary shaft 24b and is horizontally reciprocally rotated. The pressing roller 23c is attached to the tip of the arm 24c. By this bracket escape mechanism 24, the restraining rollers 23c, 23c are alternately retracted outward on one side, and the rail bracket 4 previously attached to the rear surface of the flange portion of the guide rail 1 can pass therethrough.
【0029】前記角度制御機構30は、図1及び図2に
示す如く、前記台車台枠11の後端部に設けた巻上機な
どの牽引機31と、この牽引機31から巻き取り・巻き
戻し可能に延出した牽引ロープ32と、この牽引ロープ
32の先端に取り付けた掛止金具33とを備えてなり、
この掛止金具33を前記ガイドレール1の後端部に後述
する如く掛止し、この状態で牽引機31により牽引ロー
プ32の長さを変えて行くことで、レール搬入台10上
からレール案内支持機構20で案内支持しながら昇降路
2内方に落とし込むガイドレール1の落とし込み角度θ
を徐々に大きくするようにコントロールする構成であ
る。As shown in FIGS. 1 and 2, the angle control mechanism 30 includes a towing machine 31 such as a hoisting machine provided at the rear end of the bogie underframe 11, and a winding / winding machine from the towing machine 31. It comprises a tow rope 32 extending so as to be able to return, and a hook metal fitting 33 attached to the tip of the tow rope 32,
This hooking metal 33 is hooked on the rear end of the guide rail 1 as will be described later, and in this state, the length of the tow rope 32 is changed by the towing machine 31 to guide the rail from the rail carrying table 10. Dropping angle θ of the guide rail 1 dropped inward of the hoistway 2 while being guided and supported by the support mechanism 20.
It is a configuration that controls to gradually increase.
【0030】この角度調整機構30の掛止金具33は、
図7に示す如く、ガイドレール1のフランジ部背面(上
面)に接合する平板部33aの左右両側にロープ止め部
33bを左右対称に突設し、これらに前記牽引ロープ3
2の先端がY字形なって連結されている。また、前記平
板部33aの下面に前後左右合計4本の掛止ピン33c
が突設され、これら掛止ピン33cを前記ガイドレール
1のフランジ部後端寄り部分に穿設されているレール締
結用穴(継目板締結用ボルト穴)に差し込めると共に、
これら掛止ピン33cの抜け止め部材33dを備えてい
る。なお、この抜け止め部材33dはコ字形プレート
で、左右片部にそれぞれ2個ずつのだるま状の掛止穴3
3eが形成され、これらの掛止穴33eを前記ガイドレ
ール1のフランジ部のレール締結用穴に貫通した4本の
掛止ピン33cに下側から嵌合して後方に引きずらすこ
とで、該各掛止ピン33cを一気に抜け止め状態にでき
るようになっている。The hook 33 of the angle adjusting mechanism 30 is
As shown in FIG. 7, rope stop portions 33b are symmetrically projected on both left and right sides of a flat plate portion 33a joined to the rear surface (upper surface) of the flange portion of the guide rail 1, and the pulling rope 3 is attached to them.
The tips of 2 are Y-shaped and connected. In addition, a total of four latching pins 33c are formed on the lower surface of the flat plate portion 33a.
Projectingly, and these hooking pins 33c can be inserted into the rail fastening holes (joint plate fastening bolt holes) bored in the portion of the guide rail 1 near the rear end of the flange portion,
A retaining member 33d for the retaining pins 33c is provided. The retaining members 33d are U-shaped plates, and each of the left and right side portions has two daruma-shaped retaining holes 3.
3e are formed, and these hooking holes 33e are fitted from below to the four hooking pins 33c penetrating the rail fastening holes of the flange portion of the guide rail 1 and are dragged rearward, Each of the latching pins 33c can be suddenly set in the retaining state.
【0031】前記高さ制御機構40は、図1及び図2に
示す如く、前記台車台枠11の先端部寄りに設けた巻上
機などの牽引機41と、この牽引機41から巻き取り・
巻き戻し可能に延出した牽引ロープ42と、前記レール
案内支持機構20の機構本体21上部に軸着され前記牽
引ロープ42の途中が巻き掛けられる滑車43と、この
牽引ロープ42の先端に取り付けた掛止金具44とを備
えてなり、この掛止金具44を前記ガイドレール1の先
端部に後述する如く掛止し、この状態で牽引機41によ
り牽引ロープ42の長さを変えて行くことで、レール搬
入台10上からレール案内支持機構20で案内支持しな
がら昇降路2内方に落とし込むガイドレール1の落とし
込み速度並びに落とし込み量をコントロールすると共
に、その昇降路2内に落とし込んだガイドレール1の鉛
直状態での高さを調整できるようになっている。なお、
その高さは鉛直に立ったガイドレール1の上端が当該一
階フロア1Fの乗場出入口5の開口範囲内略中間位置
(該乗場から作業員の手の届く高さ)に設定されてい
る。As shown in FIGS. 1 and 2, the height control mechanism 40 includes a towing machine 41 such as a hoisting machine provided near the front end of the bogie underframe 11, and a winding / winding machine from the towing machine 41.
The tow rope 42 extending so as to be able to be rewound, the pulley 43 pivotally attached to the upper part of the mechanism main body 21 of the rail guide support mechanism 20 and wound around the middle of the tow rope 42, and attached to the tip of the tow rope 42. A hooking metal fitting 44 is provided, and the hooking metal fitting 44 is hooked on the tip portion of the guide rail 1 as described later, and in this state, the length of the tow rope 42 is changed by the towing machine 41. While controlling and guiding the guide rail 1 which is dropped into the hoistway 2 from above the rail carry-in table 10 while being guided and supported by the rail guide support mechanism 20, the guide rail 1 dropped into the hoistway 2 is controlled. The height in the vertical state can be adjusted. In addition,
The height is set such that the upper end of the vertically standing guide rail 1 is located at a substantially middle position within the opening range of the hall entrance / exit 5 on the first floor 1F (a height that a worker can reach from the hall).
【0032】この高さ制御機構40の掛止金具44は、
前述の角度調整機構30の掛止金具33と略同様な構成
で、図8に示す如く、ガイドレール1の先端に予め締結
した継目板3の下面に接合する平板部44aと、この左
右両側に突設されて前記牽引ロープ42の先端Y字形部
が連結されたロープ止め部44bと、平板部44aの上
面に突設されて前記継目板3のレール締結用穴に差し込
める前後左右合計4本の掛止ピン44cと、これら掛止
ピン44cを抜け止めするだるま状の掛止穴を穿設した
抜け止め部材44dとを備えてなる。The hook metal fitting 44 of the height control mechanism 40 is
As shown in FIG. 8, a flat plate portion 44a joined to the lower surface of the joint plate 3 that is pre-fastened to the tip of the guide rail 1 and the left and right sides of the flat plate portion 44a have substantially the same structure as that of the hook 33 of the angle adjusting mechanism 30. A rope stopper 44b protrudingly connected to the tip Y-shaped portion of the tow rope 42, and a total of four front, rear, left and right that are protruded on the upper surface of the flat plate portion 44a and can be inserted into the rail fastening holes of the joint plate 3. Locking pins 44c, and a retaining member 44d provided with a daruma-shaped retaining hole for retaining the retaining pins 44c.
【0033】また、前記レール搬入台10には、図9に
矢印で示す如くレール案内支持機構20により昇降路2
内に鉛直状態に支持したガイドレール1の最終支持位置
を前後方向Xと左右方向Yと上下方向Zに微調整するレ
ール位置微調整機構が付加されている。このレール位置
微調整機構は図10に符号50で示す如く、互いに平行
配置するリニアガイド51aを備えた四辺形枠状の基枠
51と、この基枠51の中央に貫通した送りねじ52
と、この回転駆動ハンドル53と、前記送りねじ52に
この回転によりねじ送り作用を受けるべく螺合せしめら
れたナット53と、前記リニヤガイド51aに摺嵌した
各スライドガイド54に支持されてナット53と一体に
微動する被駆動部55とより構成されている。In addition, on the rail carrying-in table 10, a hoistway 2 is provided by a rail guide supporting mechanism 20 as shown by an arrow in FIG.
A rail position fine adjustment mechanism for finely adjusting the final support position of the vertically supported guide rail 1 in the front-rear direction X, the left-right direction Y, and the up-down direction Z is added. As shown by reference numeral 50 in FIG. 10, this rail position fine adjustment mechanism includes a quadrilateral frame-shaped base frame 51 having linear guides 51a arranged in parallel with each other, and a feed screw 52 penetrating the center of the base frame 51.
The rotation drive handle 53, the nut 53 screwed to the feed screw 52 to receive the screw feeding action by this rotation, and the nut 53 supported by the slide guides 54 slidably fitted to the linear guides 51a. And a driven part 55 which is finely moved integrally therewith.
【0034】こうしたレール位置微調整機構50が、2
個互いの軸線を前後方向Xと左右方向Yとに異にした状
態で、図9に示すレール搬入台10の建物床面に接する
車輪12の軸12aと台車台枠11とレール案内支持機
構20の軸21と機構本体22との間の結合部等のいず
れかの箇所に介在するように装着され、その各々の回転
駆動ハンドル53を回してねじ送りにより被駆動部55
を移動させることで、ガイドレール1を前後方向Xと左
右方向Yとに微調整できる。The rail position fine adjustment mechanism 50 has two
The axes 12a of the wheels 12, which are in contact with the building floor surface of the rail loading platform 10 shown in FIG. It is mounted so as to intervene at any place such as a coupling portion between the shaft 21 and the mechanism main body 22, and each of the rotary drive handles 53 is rotated to feed the driven portion 55 by screw feeding.
The guide rail 1 can be finely adjusted in the front-rear direction X and the left-right direction Y by moving.
【0035】また、前記同様のもう一つのレール位置微
調整機構が、軸線をレール案内支持機構20の機構本体
22の長手方向に向け、前記高さ制御機構40の滑車4
3の軸を微動させ得るように装着され、これで図9に示
す如く該滑車43を上下に移動させて牽引ロープ42を
引っ張ることにより、ガイドレール1の上下方向Zの高
さを微調整できるようになっている。Further, another rail position fine adjustment mechanism similar to that described above has its axis directed toward the longitudinal direction of the mechanism main body 22 of the rail guide support mechanism 20, and the pulley 4 of the height control mechanism 40.
It is mounted so that the shaft of No. 3 can be finely moved, and by moving the pulley 43 up and down to pull the tow rope 42 as shown in FIG. 9, the height of the guide rail 1 in the vertical direction Z can be finely adjusted. It is like this.
【0036】なお、前記高さ制御機構40の牽引機41
が牽引ロープ42を微動巻上可能な構成機能を持つもの
であれば、これで該ロープ42の長さを直接的に微妙に
変えてガイドレール1の上下方向Zの高さを微調整でき
るので、前述の滑車軸を微動させるレール位置微調整機
構は不要にできる。Incidentally, the traction machine 41 of the height control mechanism 40.
If the tow rope 42 has a configuration function capable of finely winding the tow rope 42, the length of the rope 42 can be directly and delicately changed to finely adjust the height of the guide rail 1 in the vertical direction Z. The rail position fine adjustment mechanism for finely moving the pulley shaft can be eliminated.
【0037】また、前記レール搬入台10には図示しな
いが安全機構が設けられている。つまり、台車台枠11
には車輪12のブレーキ機構が設けられていると共に、
エレベータ乗場出入口5の高さ(2メートル程度)相当
の伸長棒が上に向けて取り付けられ、更に台車台枠11
の先端側には左右に張出す伸長脚(アウトリガー)が取
り付けられ、これらでレール搬入台10の安定性を増し
て、昇降路2内方への転落等の危険を防止している。以
上のような構成のエレベータ用ガイドレール付設作業支
援装置の作用と共に、この装置を用いてのガイドレール
付設作業法を以下に述べる。Further, the rail carry-in table 10 is provided with a safety mechanism (not shown). That is, the bogie frame 11
Is equipped with a brake mechanism for the wheels 12, and
An extension bar corresponding to the height of the elevator hall entrance / exit 5 (about 2 meters) is attached upward, and the bogie frame 11 is further attached.
Extension legs (outriggers) that extend to the left and right are attached to the tip end side of the rails to increase the stability of the rail loading table 10 and prevent the risk of falling inward of the hoistway 2. The operation of the elevator guide rail installation work support device having the above-described configuration and the guide rail installation work method using this device will be described below.
【0038】まず、図1の想像線及び図3に示す様に、
ガイドレール1をレール搬入台10の台車台枠11の支
持ローラ13上に乗せる。この際、該ガイドレール1の
先端側部をレール案内支持機構20内にも貫通してお
く。この状態でレール搬入台10を車輪走行により建屋
内に移動させて、一階フロア1Fのエレベータ乗場出入
口5に搬送する。なお、そのガイドレール1には工場或
いは当該建屋内搬送途中箇所又はエレベータ乗場などの
適当箇所で継目板3及びレールブラケット4を所定箇所
に締結して取り付けておく。また、そのガイドレール1
の後端に角度制御機構30の牽引ロープ32先端の掛止
金具33を掛止すると共に、高さ制御機構40の牽引ロ
ープ42先端の掛止金具44をガイドレール1先端継目
板3に掛止するなどの段取り作業を行う。First, as shown in the imaginary line of FIG. 1 and FIG.
The guide rail 1 is placed on the support roller 13 of the bogie underframe 11 of the rail loading table 10. At this time, the tip side portion of the guide rail 1 is also penetrated into the rail guide support mechanism 20. In this state, the rail loading platform 10 is moved to the inside of the building by traveling on wheels, and is transported to the elevator landing doorway 5 on the first floor 1F. It should be noted that the guide rail 1 is fastened to the joint plate 3 and the rail bracket 4 by being fastened to a predetermined position at a suitable place such as a factory, a midway point of transportation in the building or an elevator hall. Also, the guide rail 1
The hooking metal fitting 33 at the tip of the tow rope 32 of the angle control mechanism 30 is hooked to the rear end, and the hooking metal fitting 44 at the tip of the tow rope 42 of the height control mechanism 40 is hooked to the guide rail 1 end joint plate 3. Perform setup work such as doing.
【0039】こうした状態で、レール搬入台10の台車
台枠11を移動調整して、この先端のレール案内支持機
構20がエレベータ乗場出入口5より昇降路2内に少し
突き出る状態で、該台車台枠11をブレーキ機構や伸長
棒や伸長脚(アウトリガー)により不動の状態に安定固
定する。こうしてから、作業員が台車台枠11上の搭載
されているガイドレール1を昇降路2内に送り出す。In such a state, the bogie frame 11 of the rail carry-in table 10 is moved and adjusted, and the rail guide support mechanism 20 at the tip of the bobbin frame is slightly projected from the elevator hall entrance / exit 5 into the hoistway 2. 11 is stably fixed in a stationary state by a brake mechanism, an extension rod, and an extension leg (outrigger). Then, the worker sends out the guide rail 1 mounted on the bogie underframe 11 into the hoistway 2.
【0040】このガイドレール1の昇降路2内方への送
り込みが進むにつれ、図1の実線に示す如く、ガイドレ
ール1の重心がレール案内支持機構20よりも前に出
て、このレール案内支持機構20の機構本体22が軸2
1を支点にガイドレール1を案内支持しながら前下がり
の方向に回転し始めて、そのガイドレール1を昇降路2
内方に落とし込む。As the guide rail 1 is fed into the hoistway 2, the center of gravity of the guide rail 1 comes out of the rail guide support mechanism 20 as shown by the solid line in FIG. The mechanism main body 22 of the mechanism 20 is the shaft 2
1 starts to rotate in the front downward direction while guiding and supporting the guide rail 1 with the fulcrum 1 as a fulcrum, and the guide rail 1 is moved to the hoistway 2
Drop inward.
【0041】この際、前記レール案内支持機構20は、
機構本体22の前後2箇所に配した案内支持部23A,
23Bが、図5及び図6に示す如く、下部支えローラ2
3aと左右の案内ローラ23b,23bと、抑えローラ
23cとにより、ガイドレール1を離さないように上下
左右から抱持して前進可能に案内支持すると共に、その
両案内支持部23A,23Bの抑えローラ23c,23
cは、ガイドレール1の背面に予め取り付けられたレー
ルブラケット4が通過するときの邪魔にならないよう
に、交互にブラケット逃げ機構24により一側外方に待
避し、そのいずれか必ず一方はレール背面を抑えながら
レールブラケット4を通過させる。これでガイドレール
1の離脱を防止しながら安全に案内支持して落とし込
む。At this time, the rail guide support mechanism 20 is
Guide support portions 23A arranged at two positions before and after the mechanism main body 22,
23B is a lower support roller 2 as shown in FIGS.
3a, the left and right guide rollers 23b and 23b, and the restraining roller 23c hold the guide rail 1 from above, below, left and right to guide and support it so that it can move forward, and to restrain both guide support portions 23A and 23B. Rollers 23c, 23
In order not to get in the way when the rail bracket 4 previously attached to the back surface of the guide rail 1 passes, c is alternately saved to the outside on one side by the bracket escape mechanism 24, and one of them is always on the back surface of the rail. Pass the rail bracket 4 while holding down. In this way, the guide rail 1 is prevented from coming off and safely guided and supported to be dropped.
【0042】また、その際、このガイドレール1の後端
を角度制御機構30の牽引ロープ32により牽引し、先
端を高さ制御機構40の牽引ロープ42により牽引され
て、急激に昇降路2内方に倒れ込んだり落ち込んだりす
ることを防止しながら、それら角度制御機構30と高さ
制御機構40の各牽引機31,41とを回転させて、そ
れぞれの牽引ロープ32,42を徐々に伸長し、そのガ
イドレール1の落とし込み角度θを徐々に大きくするよ
うにコントロールすると共に、その落とし込み速度並び
に落とし込み量をコントロールして、安全に該ガイドレ
ール1を昇降路2内に落とし込んで行く。At this time, the rear end of the guide rail 1 is pulled by the pulling rope 32 of the angle control mechanism 30, and the tip end is pulled by the pulling rope 42 of the height control mechanism 40, so that the inside of the hoistway 2 is suddenly pulled. Rotating the angle control mechanism 30 and each of the towing machines 31, 41 of the height control mechanism 40 while gradually preventing the vehicle from falling or falling, gradually extending the respective tow ropes 32, 42, The guide rail 1 is safely dropped into the hoistway 2 by controlling the dropping angle θ of the guide rail 1 to be gradually increased and controlling the dropping speed and the dropping amount.
【0043】こうして、ガイドレール1を昇降路2内に
落とし込み搬入して、図2に示す如くレール案内支持機
構20により該ガイドレール1を昇降路2内の乗場出入
口5近傍(乗場の作業員の手が楽に届く位置)に鉛直に
立った状態に支持すると共に、そのガイドレール1を高
さ制御機構40により高さ調整して、この上端が当該一
階フロア1Fの乗場出入口5の開口範囲内略中間位置
(該乗場から作業員の手の届く高さ)に保持する。ここ
で、そのガイドレール1の上端から前記角度制御機構3
0の掛止金具33を取り外す。In this way, the guide rail 1 is dropped into the hoistway 2 and carried in, and the guide rail 1 is moved by the rail guide support mechanism 20 as shown in FIG. The guide rail 1 is vertically supported at a position where the hand can easily reach), and the height of the guide rail 1 is adjusted by the height control mechanism 40 so that the upper end is within the opening range of the landing doorway 5 of the first floor 1F. It is held at a substantially intermediate position (a height that the worker can reach from the landing). Here, from the upper end of the guide rail 1, the angle control mechanism 3
Remove the hook metal fitting 33 of 0.
【0044】この状態で、図11に示すように、昇降路
2の上端に設置した揚重機60を稼働させ、この揚重機
ロープ61の下端掛止金具(図示せず)を前記最初に昇
降路2内に落とし込んだ一番目のガイドレール1の上端
に掛止して、レール一本分の長さだけ上方に吊り上げ
る。つまり、この一番目のガイドレール1をこの下端が
当該一階フロア1Fの乗場出入口5の開口範囲内略中間
位置にくるまで吊り上げる。ここでまた、このガイドレ
ール1の下端から前記高さ調整機構40の掛止金具44
を取り外す。In this state, as shown in FIG. 11, the hoist 60 installed at the upper end of the hoistway 2 is operated, and the lower end hooking metal (not shown) of the hoist rope 61 is first moved to the hoistway. Hang it on the upper end of the first guide rail 1 dropped in 2, and hang it up by the length of one rail. That is, the first guide rail 1 is suspended until the lower end of the guide rail 1 reaches a substantially middle position within the opening range of the hall entrance / exit 5 on the first floor 1F. Here, again, from the lower end of the guide rail 1 to the hook metal fitting 44 of the height adjusting mechanism 40.
Remove.
【0045】こうして、フリーとなった前記レール搬入
台10を走行移動させて、二番目のガイドレール1を前
述と同様にして一階フロア1Fの乗場出入口5から昇降
路2内に図11に示す如く落とし込み搬入し、レール案
内支持機構20により該ガイドレール1を昇降路2内の
乗場出入口5近傍の所定高さに鉛直に立った状態に支持
する。そして、この二番目のガイドレール1の上端から
角度制御機構30の掛止金具33を取り外す。In this way, the rail carrying table 10 that has become free is moved and moved, and the second guide rail 1 is shown in the hoistway 2 from the landing doorway 5 on the first floor 1F in the same manner as described above, as shown in FIG. As described above, the rail guide supporting mechanism 20 supports the guide rail 1 in a vertically standing state at a predetermined height near the landing doorway 5 in the hoistway 2. Then, the hook metal 33 of the angle control mechanism 30 is removed from the upper end of the second guide rail 1.
【0046】この状態で、当該一階フロア1Fの乗場出
入口5から作業員が直接目視しながら、その二番目のガ
イドレール1の上端が前記吊り上げた一番目のガイドレ
ール1の下端に接合するように、該二番目のガイドレー
ル1の水平方向の位置をレール搬入台10移動により調
整すると共に、この高さを高さ制御機構40で調整す
る。このとき、図9及び図10で示すようなレール位置
微調整機構50を操作することで、前後方向X及び左右
方向Yの位置と上下方向Zの高さを細かく調整する。In this state, the operator directly looks at the landing doorway 5 of the first floor 1F so that the upper end of the second guide rail 1 is joined to the lower end of the lifted first guide rail 1. First, the horizontal position of the second guide rail 1 is adjusted by moving the rail loading table 10, and this height is adjusted by the height control mechanism 40. At this time, by operating the rail position fine adjustment mechanism 50 as shown in FIGS. 9 and 10, the position in the front-rear direction X and the left-right direction Y and the height in the up-down direction Z are finely adjusted.
【0047】こうして、その一番目のガイドレール1の
下端と二番目のガイドレール1の上端とを接合したら、
更に作業員が図12に示すように、その両ガイドレール
1,1の側面に治具(スケール)63を当てがって万力
(図示せず)などにより矢印の如く挟み付けることで、
両ガイドレール1,1の横方向のズレを修正すると共
に、継目板3に接合して奥行方向のズレを修正するなど
して、該一番目のガイドレール1と二番目のガイドレー
ル1とを相互に芯合わせし、その相互を継目板3と複数
のボルト・ナット62などの締結具により連結する。In this way, when the lower end of the first guide rail 1 and the upper end of the second guide rail 1 are joined,
Further, as shown in FIG. 12, the worker applies a jig (scale) 63 to the side surfaces of both guide rails 1 and 1 and clamps them with a vise (not shown) as shown by the arrow.
The first guide rail 1 and the second guide rail 1 are joined together by correcting the lateral displacement of both guide rails 1 and 1 and joining the joint plate 3 to correct the displacement in the depth direction. The cores are aligned with each other, and the joints 3 are connected to each other by fasteners such as a plurality of bolts and nuts 62.
【0048】この連結作業の後、再度前記揚重機60を
稼働させて、該一番目のガイドレール1をこの下端に連
結した二番目のガイドレール1と一緒に吊り上げ、この
二番目のガイドレール1の下端が当該一階フロア1Fの
乗場出入口5から人の届く高さになるまで吊り上げる。
こうして次の三番目のガイドレール1を前述同様にして
昇降路2内に落とし込み搬入して前記二番目のガイドレ
ール1の下端に連結する。こうしてレール搬入・連結・
吊り上げ作業を繰り返すことで、図13に示す如く必要
本数のガイドレール1…を一連の状態に連結して昇降路
2内に上下方向に亘り鉛直状態に吊り上げる。After this connecting work, the lifting machine 60 is operated again, and the first guide rail 1 is lifted up together with the second guide rail 1 connected to the lower end, and the second guide rail 1 is lifted. The lower end of the floor is lifted from the landing doorway 5 on the first floor 1F to a height reachable by people.
In this way, the next third guide rail 1 is dropped into the hoistway 2 and carried in and connected to the lower end of the second guide rail 1 in the same manner as described above. In this way, rail loading / connection /
By repeating the hoisting work, the required number of guide rails 1 ... Are connected in a series as shown in FIG. 13 and hoisted vertically in the hoistway 2 in the vertical direction.
【0049】なお、前述の如く、建物の一階フロア1F
の乗場出入口5からガイドレール付設作業支援装置を用
いてガイドレール1の搬入・連結・吊り上げ作業を行っ
た場合、図13に示す如く、地上部分のガイドレール1
…と地下一階B1部分のガイドレール101の搬入・連
結ができるが、それより下側の最下階である例えば地下
二階B2の乗場出入口5から前記同様の搬入・連結・吊
り上げ作業を行えば、最下端ピット部のガイドレールを
残し、その他のB2階以上のガイドレールを全て連結し
て一挙に吊り上げ得るようになる。As mentioned above, the first floor of the building is on the first floor.
When carrying-in, connecting, and lifting work of the guide rail 1 from the hall entrance / exit 5 using the guide rail-attached work support device, as shown in FIG.
... and the guide rail 101 in the B1 portion of the first basement floor can be loaded and connected, but if the same loading, connection, and hoisting work is performed from the landing doorway 5 of the lowermost floor below that, for example, the second basement floor B2. , The guide rails at the bottom pit are left, and all the other guide rails on the B2 floor and above can be connected and lifted at once.
【0050】しかしながら、地下階では前述のレール搬
入台10が用いずらく、地上一階フロア1Fからしかガ
イドレール1を搬入できない場合には、図14及び図1
5に示すような方法により行う。However, when it is difficult to use the above-mentioned rail carry-in table 10 on the basement floor and the guide rail 1 can be carried in only from the ground floor 1F, FIG. 14 and FIG.
The method as shown in FIG.
【0051】つまり、まず図14に示す如く、前述同様
にレール搬入台10と揚重機60を用いて地上一階以上
のガイドレール1…の搬入・連結・吊り上げ作業を行
う。その後、前記同様にレール搬入台10を用いて地下
一階B1部分のガイドレール101を昇降路2内に落と
し込んで鉛直状態に搬入支持し、これを昇降路2上部の
別の揚重機60Aにより揚重機ロープ61Aを介してレ
ール一本分上方に吊り上げ、次に地下二階B2部分のガ
イドレール102を前記同様にして昇降路2内に落とし
込んで鉛直状態に搬入支持し、このガイドレール102
の上端を前後左右に位置調整すると共に高さ調整して前
記ガイドレール101の下端に接合し、その両者を前述
同様に芯合わせして連結する。こうした状態で前記別の
揚重機60Aを稼働して該ガイドレール101,102
をレール一本分下降すると共に、これら地下部分のガイ
ドレール101,102をレール搬入台10のレール案
内支持機構20と高さ制御機構40により支持する。そ
してそのガイドレール101上端から揚重機ロープ61
Aを外す。That is, first, as shown in FIG. 14, the rail loading table 10 and the hoisting machine 60 are used to carry in, connect, and lift the guide rails 1 ... Thereafter, similarly to the above, using the rail loading table 10, the guide rail 101 of the B1 part of the first basement floor is dropped into the hoistway 2 to be vertically loaded and supported, and this is lifted by another hoist 60A above the hoistway 2. The rail is lifted up by one rail via the heavy equipment rope 61A, and then the guide rail 102 of the second basement B2 portion is dropped into the hoistway 2 in the same manner as above to carry in and support the guide rail 102 vertically.
The upper end of the guide rail 101 is positionally adjusted to the front, rear, left and right, and the height is adjusted to join the lower end of the guide rail 101, and both of them are aligned and connected as described above. In this state, the other lifting machine 60A is operated to operate the guide rails 101, 102.
Is lowered by one rail, and the guide rails 101 and 102 of these underground portions are supported by the rail guide support mechanism 20 and the height control mechanism 40 of the rail loading table 10. Then, from the upper end of the guide rail 101, the lifting machine rope 61
Remove A.
【0052】こうして図15に示す状態として、地下部
分のガイドレール101の上端を前述同様に前後左右に
位置調整すると共に高さ調整して地上部分のガイドレー
ル1の下端に接合し、その両者を前述同様に芯合わせし
て連結する。これで昇降路最下端ピット部のガイドレー
ルを残して必要本数のガイドレール全てを上下に連結し
た状態で昇降路2内に一挙に吊り上げられるようにな
る。Thus, in the state shown in FIG. 15, the upper end of the guide rail 101 in the underground portion is adjusted to the front, rear, left and right in the same manner as described above, and the height is adjusted to join the lower end of the guide rail 1 in the ground portion. The cores are aligned and connected as described above. With this, the guide rails at the bottom pit of the hoistway can be left, and all the required number of guide rails can be lifted up and down in the hoistway 2 all at once.
【0053】また、前述の如く別の揚重機60Aを準備
できない場合は、前述同様にレール搬入台10と揚重機
60を用いて地上一階以上のガイドレール1…の搬入・
連結・吊り上げ作業を行った後、その揚重機60の揚重
機ロープ61を一旦昇降路2頂部梁等に仮固定して該揚
重機60から外し、その揚重機60に別なロープを巻き
取らせて、これを利用して前述同様に地下部分のガイド
レール101,102の搬入時の吊り上げを行うことも
できる。When another lifting machine 60A cannot be prepared as described above, the rail carrying table 10 and the lifting machine 60 are used to carry in the guide rails 1 ...
After connecting and hoisting work, the hoisting rope 61 of the hoisting machine 60 is temporarily temporarily fixed to the top beam of the hoistway 2 or the like and removed from the hoisting machine 60, and another rope is wound on the hoisting machine 60. Then, by utilizing this, the guide rails 101 and 102 in the underground portion can be lifted at the time of carrying in, as described above.
【0054】以上のようにして、昇降路最下端ピット部
のガイドレールを残してそれ以上の必要本数のガイドレ
ール全てを連結した状態で昇降路2内の乗り場出入口5
近傍寄りに鉛直に吊り上げた後は、これら一連のガイド
レール1〜102を図3で示した如く該昇降路2内壁の
所定のレール付設位置D(かご用の左右のガイドレール
付設位置並びにつり合いおもり用の左右のガイドレール
付設位置のいずれか)に吊り移す作業を行う。なお、そ
の昇降路2内壁の所定のレール付設位置Dにはガイドレ
ール1〜102に取付けたブラケット4を接合して固定
するファスナープレート64が上下方向に間隔を存して
予め固設している。As described above, the landing doorway 5 in the hoistway 2 with the guide rails at the lowermost pit of the hoistway being left and all the required number of guide rails being connected to each other.
After being vertically lifted near the vicinity, a series of these guide rails 1 to 102 are installed at predetermined rail mounting positions D on the inner wall of the hoistway 2 as shown in FIG. 3 (the left and right guide rail mounting positions for the car and the counterweight). (Either of the left and right guide rail installation positions) for the work. A fastener plate 64 for joining and fixing the brackets 4 attached to the guide rails 1 to 102 is fixed in advance at a predetermined rail attachment position D on the inner wall of the hoistway 2 with a space in the vertical direction. .
【0055】その所定のレール付設位置Dにガイドレー
ル1〜102を吊り移す作業は、図3に矢印イ,ロで示
す如く二段階的な横移動により行う。まず、その矢印イ
の横移動は、図16に示すように、昇降路2内のレール
付設位置D付近の上部に揚重機60Bを配置する。この
揚重機ロープ61Bを想像線で示す如く昇降路2内の乗
り場出入口近傍に前の揚重機60の揚重機ロープ61に
より吊り下げた一連のガイドレール1〜102の最上端
に連結する。そして、その揚重機60Bを稼働してこの
揚重機ロープ61Bを引き上げる。これでその揚重機ロ
ープ61Bの張力が増して前の揚重機ロープ61の張力
と均衡し、さらに揚重機ロープ61Bを引き上げると、
前の揚重機ロープ61は緩んで、図16に実線で示すよ
うに、一連のガイドレール1〜102が斜めに引き上げ
られながら横移動して所定のレール付設位置Dの正面近
傍に移動する。The operation of suspending the guide rails 1 to 102 at the predetermined rail attachment position D is performed by two-step lateral movement as shown by arrows a and b in FIG. First, for the lateral movement of the arrow a, as shown in FIG. 16, the lifting machine 60B is arranged in the upper part of the hoistway 2 near the rail attachment position D. This lifting machine rope 61B is connected to the uppermost ends of a series of guide rails 1 to 102 suspended by the lifting machine rope 61 of the preceding lifting machine 60 in the vicinity of the entrance and exit of the hoistway 2 as shown by an imaginary line. Then, the hoist 60B is operated to pull up the hoist rope 61B. With this, the tension of the lifter rope 61B is increased to balance with the tension of the previous lifter rope 61, and when the lifter rope 61B is further pulled up,
The front lifter rope 61 is loosened, and as shown by the solid line in FIG. 16, a series of guide rails 1 to 102 are laterally moved while being pulled up diagonally to the vicinity of the front of a predetermined rail attachment position D.
【0056】次に、その一連のガイドレール1〜102
を図3の矢印ロで示す横移動を行う。これは前記揚重機
60Bを図17に示すようにスライド台65に対し想像
線の位置から実線の位置にスライド移動させることで、
一連のガイドレール1〜102を水平に平行移動させ
て、これらのレールブラケット4が昇降路2内壁の各フ
ァスナプレート64の上面に重複するようになす。な
お、その各レールブラケット4は前記横移動時にファス
ナプレート64に干渉しないようにガイドレール1の規
定位置より若干高めに仮止めしておく。こうして一連の
ガイドレール1〜102を所定のレール付設位置Dの規
定高さに吊り下げ保持する。Next, the series of guide rails 1 to 102
Is horizontally moved as indicated by an arrow B in FIG. This is performed by sliding the lifting machine 60B from the position of the imaginary line to the position of the solid line with respect to the slide base 65 as shown in FIG.
A series of guide rails 1 to 102 are horizontally translated so that the rail brackets 4 overlap the upper surface of each fastener plate 64 on the inner wall of the hoistway 2. The rail brackets 4 are temporarily fixed to a position slightly higher than the specified position of the guide rail 1 so as not to interfere with the fastener plate 64 during the lateral movement. In this way, the series of guide rails 1 to 102 is suspended and held at the prescribed height of the predetermined rail attachment position D.
【0057】なお、前述の図16で示した矢印イの横移
動の際に、一連のガイドレール1〜102が振り子的な
動きをして、レールブラケット4が昇降路2内壁のファ
スナプレート64に当たるなどの障害が生じる場合は、
前の揚重機60と今度の揚重機60Bとの両方をゆっく
りコントロールしながら動作させて該振り子運動を小さ
くして行う。また、その両揚重機60,60Bのコント
ロール動作により、一連のガイドレール1〜102を上
下動させずに規定高さのままに略水平に横移動できれ
ば、前述までの一連のガイドレール全長をできるだけ長
くして、その下端に、最後に連結される最下端ピット部
のガイドレール103(図21参照)を短いものとする
ことができる。なおまた、図18乃至図20は前記ガイ
ドレール1〜102を昇降路2内の乗場出入口近傍から
所定のレール付設位置に吊り移す別の作業法を示してい
る。When the arrow A shown in FIG. 16 is moved laterally, the series of guide rails 1 to 102 move like a pendulum so that the rail bracket 4 contacts the fastener plate 64 on the inner wall of the hoistway 2. If a problem such as
Both the former lifting machine 60 and the next lifting machine 60B are operated while controlling them slowly to reduce the pendulum motion. Further, if the series of guide rails 1 to 102 can be moved horizontally substantially at the specified height without being vertically moved by the control operation of the both lifting machines 60 and 60B, the length of the series of guide rails up to the above can be achieved as much as possible. The guide rail 103 (see FIG. 21) at the lowermost pit portion that is finally connected to the lower end of the guide rail 103 can be made short and short. 18 to 20 show another work method for suspending the guide rails 1 to 102 from the vicinity of the entrance / exit of the hoistway 2 to a predetermined rail attachment position.
【0058】この場合は、まず図18に示すように、昇
降路2の上端機械室2aの床梁部等にフック71aを有
するジグ71を設置する。これは昇降路2内の所定のレ
ール付設位置付近の真上である。このジグ71のフック
71aに吊上げ金車72を引っ掛ける。一方、建物のて
も最上階フロアFnに巻上機等の揚重機60Cを設置
し、この揚重機ロープ61cを前記吊上げ金車72に巻
き掛けて垂らすと共に、そのロープ61cの垂下部途中
を最上階からチェインブロック73を用いた引寄せ金車
74により昇降路2内の乗場出入口近傍側に引き寄せ
る。この引き寄せた揚重機ロープ61c下端フックを、
前述したように昇降路2内に落とし込み搬入した最上段
のガイドレール1の上端に固定した吊上げ金具75に取
り付ける。こうして揚重機60Cを稼働させて揚重機ロ
ープ61cを巻き上げることにより、前述同様に多数本
連結したガイドレール1…を昇降路2内の乗場出入口近
傍に沿って吊り上げる。In this case, first, as shown in FIG. 18, a jig 71 having a hook 71a is installed on the floor beam or the like of the upper end machine room 2a of the hoistway 2. This is just above the predetermined rail attachment position in the hoistway 2. The hanging gold wheel 72 is hooked on the hook 71a of the jig 71. On the other hand, even in a building, a hoisting machine 60C such as a hoisting machine is installed on the uppermost floor Fn, the hoisting rope 61c is wound around the hoisting wagon 72 and hung down, and the midway of the hanging part of the rope 61c is the highest. From the floor, a pulling wagon 74 using a chain block 73 pulls the hoistway 2 toward the landing doorway side. This lower end hook of the hoist rope 61c
As described above, it is attached to the lifting metal fitting 75 fixed to the upper end of the uppermost guide rail 1 dropped into the hoistway 2 and carried in. In this way, the lifting machine 60C is operated to wind up the lifting machine rope 61c, so that a large number of connected guide rails 1 ... Are lifted along the vicinity of the landing entrance / exit in the hoistway 2.
【0059】なお、その一連のガイドレール1…を最後
に機械室2a天井等のフック76に吊持させるための吊
持ロープ78を予め該機械室2a内から最上階フロアに
渡しておく。そして、前記一連のガイドレール1…の上
端が最上階フロアFnの乗場出入口5近傍まで引き上げ
られた時に、この上端の吊上げ金具75に該吊持ロープ
76の下端フックを掛止する。前記天井フック76が準
備できないときには、二点鎖線で示すように機械室2a
内に架台79を介しフック76´を準備しておくように
する。Finally, a suspending rope 78 for suspending the series of guide rails 1 ... To the hook 76 such as the ceiling of the machine room 2a is passed from the machine room 2a to the top floor in advance. When the upper ends of the series of guide rails 1 ... Are pulled up to the vicinity of the landing entrance / exit 5 of the uppermost floor Fn, the lower end hooks of the hanging ropes 76 are hooked on the upper end lifting metal fittings 75. When the ceiling hook 76 cannot be prepared, as shown by the chain double-dashed line, the machine room 2a
The hook 76 'is prepared through the pedestal 79.
【0060】こうして、図19に示すように、揚重機6
0Cを稼働させて揚重機ロープ61cを巻き上げると共
に、チェインブロック73を緩めて、その両者相互の力
の均衡を保ちながら、一連のガイドレール1…を矢印ハ
で示す如く斜め上方に引上げるようにして横移動させ
て、ジグ71の直下である所定のレール付設位置付近に
吊り移す。Thus, as shown in FIG. 19, the lifting machine 6
0C is operated to wind up the hoisting machine rope 61c, loosen the chain block 73, and pull up the series of guide rails 1 ... And laterally move it, and suspend it near the predetermined rail attachment position immediately below the jig 71.
【0061】この際、ガイドレール1上端の吊上げ金具
75の左右に突出したアイボルト等に一対の姿勢操作用
ロープ80,81の先端フック部を掛止しておき、これ
ら両ロープ80,81を最上階フロアFnから作業員が
引っ張り操作して、該一連のガイドレール1…の揺れや
向きをコントロールして、レールブラケット4が昇降路
2内壁のファスナプレート64に干渉しないようにす
る。At this time, the end hooks of the pair of posture operating ropes 80, 81 are hooked on the eyebolts protruding to the left and right of the lifting metal fitting 75 at the upper end of the guide rail 1 so that both ropes 80, 81 are at the top. A worker pulls from the floor Fn to control the swing and direction of the series of the guide rails 1 ... so that the rail bracket 4 does not interfere with the fastener plate 64 on the inner wall of the hoistway 2.
【0062】こうしながら、図20に示すように、機械
室2aの天井等のフック76からチェインブロック82
を使い吊持ロープ78を引き上げて、一連のガイドレー
ル1…を規定高さに吊持する。これで該一連のがガイド
レール1…の重量はすべて近所ロープ78にかかり、ジ
グ71及び吊上げ金車72並びに揚重機ロープ61cは
自由になったら、そのジグ71と吊上げ金車72と揚重
機ロープ61cおよび吊上げ用金庫30は次の所定のレ
ール付設位置上方に移動して待機させると共に、、前記
左右の姿勢操作用ロープ80,81を作業員が引いて、
一連のガイドレール1…を回転させて、レールブラケッ
ト4が昇降路2内壁のファスナプレート64に取り付け
られる向きにする。In this way, as shown in FIG. 20, the chain block 82 is pulled from the hook 76 such as the ceiling of the machine room 2a.
Is used to pull up the suspension rope 78 to suspend the series of guide rails 1 ... Then, the weight of the series of guide rails 1 ... Is all applied to the neighborhood rope 78, and when the jig 71, the lifting wagon 72, and the lifting machine rope 61c are free, the jig 71, the lifting wagon 72, and the lifting machine rope are provided. 61c and the hoisting safe 30 are moved to a position above the next predetermined rail attachment position to be on standby, and at the same time, a worker pulls the left and right posture operation ropes 80 and 81,
A series of guide rails 1 ... Is rotated so that the rail bracket 4 is attached to the fastener plate 64 on the inner wall of the hoistway 2.
【0063】次に、図21により昇降路2の最下端ピッ
ト部のガイドレール103の搬入について述べる。この
最下段のガイドレール103は、前述した一連のガイド
レール1〜102の昇降路2内の乗場出入口近傍から所
定のレール付設位置に横移動させる際の振り子的な動き
や斜め上方に引き上げる動きの邪魔にならないように、
別途最後に搬入する。従ってこの最下段のガイドレール
103は標準のガイドレール(4〜5m)より短くても
良い。なお、前述の搬入作業で吊り上げた一連のガイド
レール1〜102の長さがすでに必要十分であるならば
該最下段のガイドレール103は不要としても良い。Next, the loading of the guide rail 103 at the lowermost pit of the hoistway 2 will be described with reference to FIG. The guide rail 103 at the lowermost stage has a pendulum-like movement and a diagonally upward pulling movement when the guide rails 1 to 102 are laterally moved from near the landing doorway in the hoistway 2 to a predetermined rail attachment position. Out of the way,
It will be delivered at the end separately. Therefore, the lowermost guide rail 103 may be shorter than the standard guide rail (4 to 5 m). The lowermost guide rail 103 may be omitted if the length of the series of guide rails 1 to 102 lifted in the above-mentioned loading operation is already sufficient.
【0064】この図21では、前述のガイドレール付設
作業支援装置を用いて最下段のガイドレール103の搬
入作業を行う例を示している。まず、図1及び図2で示
したと同様にレール搬入台10上に最下段のガイドレー
ル103を載せて一階フロアF1の乗場出入口5に搬送
し、ここで該最下段のガイドレール103をレール案内
支持機構20で案内すると共に、角度制御機構30と高
さ制御機構40の牽引ロープ32,42の長さを徐々に
変えることによりコントロールしながら昇降路2内に落
とし込み搬入して鉛直に立てる。そしてそのまま該牽引
ロープ32,42を長さを延ばしていくことで該最下段
のガイドレール103を最下端ピット部内に下ろす。な
お、この最下段のガイドレール103のピット部内への
搬入作業は従来同様に地下階から簡易揚重機を使って引
き込みしても可である。FIG. 21 shows an example of carrying in the lowermost guide rail 103 by using the above-mentioned guide rail attached work supporting device. First, similarly to the case shown in FIGS. 1 and 2, the lowermost guide rail 103 is placed on the rail loading table 10 and conveyed to the landing doorway 5 of the first floor F1 where the lowermost guide rail 103 is railed. While being guided by the guide support mechanism 20, the lengths of the pulling ropes 32 and 42 of the angle control mechanism 30 and the height control mechanism 40 are gradually changed to control them so that they can be dropped into the hoistway 2 and brought up vertically. Then, by extending the lengths of the tow ropes 32 and 42 as they are, the lowermost guide rail 103 is lowered into the lowermost pit portion. The loading operation of the lowermost guide rail 103 into the pit portion may be carried in from the basement floor using a simple lifting machine as in the conventional case.
【0065】ここで、そのピット部ないに搬入した最下
段のガイドレール103を作業員が手作業等により姿勢
制御しながら押上げて、この上端を先に吊り下げられて
いる一連のガイドレール1〜102の下端に芯合わせ接
合する。この芯合わせ接合の際、先に吊り下げられた一
連のガイドレール1〜102を動かすのは、かなりの自
重があるのと、レール間を連結している継目板3が折曲
したり座屈したりする可能性があるので難しい。そこ
で、最下段のガイドレール103を前述の角度制御機構
30と高さ制御機構40の牽引ロープ32,42で引き
上げるか、或いは別途用意したジャッキ(図示せず)を
使って押し上げる。そして、この最下段のガイドレール
103の上端をその上側のガイドレール102の下端に
連結する。この連結作業は従来同様にピット部内で人手
により行う。Here, a worker pushes up the lowermost guide rail 103 carried into the pit portion while controlling the posture by a manual work or the like, and the upper end of the guide rail 103 is suspended first. Align and join to the lower end of No. 102. At the time of this centering joining, moving the series of previously suspended guide rails 1 to 102 has a considerable weight, and the joint plate 3 connecting the rails is bent or buckled. It is difficult because it may happen. Therefore, the lowermost guide rail 103 is pulled up by the pulling ropes 32 and 42 of the angle control mechanism 30 and the height control mechanism 40, or pushed up by using a separately prepared jack (not shown). Then, the upper end of the lowermost guide rail 103 is connected to the lower end of the upper guide rail 102. This connection work is performed manually in the pit portion as in the conventional case.
【0066】最後に、図22に示す如く、前述のように
して昇降路2内壁の所定のレール付設位置に吊り下げた
一連のガイドレール1〜103を相互に段差なく鉛直状
態となるように芯出し調整して、複数のレールブラケッ
ト4を昇降路2内壁のファスナプレート64に本締め固
定する。この芯出し固定作業はゴンドラに乗った作業員
或いは昇降路内作業ロボット90により行う。なお、そ
のロボット90としては、例えば特開昭58−1938
76号公報に示されているようなもので、昇降路1内を
昇降しながら自動的にガイドレールの芯出し位置決め固
定作業を行う。Finally, as shown in FIG. 22, a series of guide rails 1 to 103 suspended at the predetermined rail attachment positions on the inner wall of the hoistway 2 as described above are aligned so that they are in a vertical state without any step. The rail brackets 4 are adjusted so that the rail brackets 4 are fixed to the fastener plates 64 on the inner wall of the hoistway 2 by full tightening. This centering and fixing work is performed by a worker on a gondola or a hoistway work robot 90. The robot 90 is, for example, Japanese Patent Laid-Open No. 58-1938.
As shown in Japanese Patent Laid-Open No. 76, the guide rail is automatically centered, positioned and fixed while moving up and down in the hoistway 1.
【0067】以上のような実施例のガイドレール付設作
業支援装置であれば、レール搬入台10でガイドレール
1を乗せてエレベータ乗場出入口5まで運搬できるの
で、搬入すべきガイドレール1…を建物のロビー等の別
の作業に邪魔にならない場所に仮置きして、そこから随
時運び込めて便利である。With the guide rail installation work support device of the above-described embodiment, the guide rail 1 can be placed on the rail loading table 10 and transported to the elevator hall entrance / exit 5. Therefore, the guide rails 1 ... It is convenient to temporarily put it in a place where it does not interfere with other work such as in the lobby, and carry it from there at any time.
【0068】また、ガイドレール付設作業支援装置のレ
ール搬入台(台車)10の走行並びに角度制御機構30
及び高さ制御機構40の牽引機31,41などを手動の
ものにすれば、基本的には無動力であり、電源などの準
備は不要である。Also, the traveling and angle control mechanism 30 of the rail loading table (carriage) 10 of the guide rail installation work support device.
If the towing machines 31, 41, etc. of the height control mechanism 40 are manually operated, they are basically unpowered, and preparation of a power source or the like is unnecessary.
【0069】さらには、ガイドレール付設作業支援装置
は最下段以外のガイドレール1〜102の昇降路2内へ
の搬入並びに連結作業を支援するだけではなく、最下段
のガイドレール103の下端ピット部内への搬入作業も
支援できる。Further, the work supporting device provided with guide rails not only supports the carrying-in and connecting work of the guide rails 1 to 102 other than the lowermost stage into the hoistway 2, but also the lower end pit portion of the lowermost guide rail 103. It can also support the work of bringing in.
【0070】更にまた、ガイドレール付設作業支援装置
は図9及び図10で示したようなレール位置微調整機構
50を備えていることで、昇降路2内に搬入して吊り上
げたn番目のガイドレールの下端に対し、n+1番目の
ガイドレールの上端を水平方向X,Yと上下方向Zに簡
単に微調整して確実に芯合わせしながら接合でき、台車
台枠11の停止位置の精度が多少ズレても、レール連結
作業が簡便且つ効率良く行い得るようになる。加えて、
その連結作業をエレベータ乗場出入口5近傍で行ない得
るので、そのレール連結作業そのものをロボットなどの
省力化手段を用いて行うことも可能となる。Furthermore, since the guide rail installation work supporting device is provided with the rail position fine adjustment mechanism 50 as shown in FIGS. 9 and 10, the n-th guide which is carried into the hoistway 2 and lifted up. With respect to the lower end of the rail, the upper end of the (n + 1) th guide rail can be easily finely adjusted in the horizontal directions X and Y and the vertical direction Z for reliable centering and joining, and the accuracy of the stop position of the bogie underframe 11 is somewhat. Even if there is a deviation, the rail connecting work can be performed easily and efficiently. in addition,
Since the connecting work can be performed in the vicinity of the elevator hall entrance / exit 5, the rail connecting work itself can be performed using a labor saving means such as a robot.
【0071】[0071]
【発明の効果】本発明のエレベータ用ガイドレール付設
作業支援装置は、前述の如く構成したので、昇降路内へ
のガイドレールの搬入がエレベータ乗場出入口から簡便
にできると共に、その昇降路内に搬入したガイドレール
を該乗場出入口近傍の明るい手の届くところで楽に且つ
安全に順次吊り上げながら一本ずつ継ぎ足すように連結
して行くのを支援できて、面倒であった昇降路内の暗く
高所での作業を大幅に軽減でき、レール付設作業の高能
率化を図るのに非常に有用な効果が得られる。Since the elevator guide rail installation work support device of the present invention is configured as described above, the guide rail can be easily carried into the hoistway from the elevator hall entrance and exit, and the hoistway can also be carried into the hoistway. The guide rails can be easily and safely lifted in a bright reach near the entrance of the hall, and they can be connected one after another while sequentially lifting them up. The work of can be greatly reduced, and a very useful effect can be obtained for improving the efficiency of the work for installing the rail.
【0072】また、エレベータ用ガイドレール付設作業
支援装置は、昇降路外部で予めレールブラケットを取り
付けた状態のガイドレールを昇降路内に楽に搬入して順
次継ぎ足すように連結しながら吊り上げて行くのを支援
できて、段取り作業の効率アップを図るのに有効となる
効果が得られる。In the elevator guide rail installation work support device, the guide rails with the rail brackets attached in advance outside the hoistway are easily carried into the hoistway, and the guide rails are sequentially lifted while being connected so as to be added. Can be supported, which is effective in increasing the efficiency of setup work.
【0073】本発明のエレベータ用ガイドレール付設作
業法は、前述した如く、前記エレベータ用ガイドレール
付設作業支援装置を用いて、楽に且つ安全にしかも効率
良くガイドレールの昇降路内への吊り上げ付設作業を行
うことができ、従来の如くやぐらの如き高い足場に作業
者が乗る必要は無く、作業者が転落するなどの危険度が
低く、且つ一階のエレベータ乗場などで作業ができるの
で、作業環境が大幅に改善される名どの効果が得られ
る。As described above, the elevator guide rail installation work method of the present invention uses the elevator guide rail installation work support device to easily, safely, and efficiently lift and install the guide rail into the hoistway. Since it is not necessary for the worker to ride on a high scaffold such as a tower like in the past, the risk of the worker falling is low and the work can be done in the elevator hall on the first floor. There are significant improvements that can be obtained.
【図1】本発明のガイドレール付設作業支援装置による
昇降路内へのガイドレールの搬入途中の状態の説明図。FIG. 1 is an explanatory view of a state where a guide rail is being carried into a hoistway by a guide rail attached work supporting device of the present invention.
【図2】同上ガイドレール搬入終了状態の説明図。FIG. 2 is an explanatory view of the same guide rail loading completion state.
【図3】同上ガイドレール搬入状態を上から見た説明
図。FIG. 3 is an explanatory view showing a state in which the guide rail is carried in as seen from above.
【図4】同上ガイドレール付設作業支援装置の台車台枠
上のガイドレール支持ローラの正面図。FIG. 4 is a front view of a guide rail supporting roller on a bogie underframe of the work support device with a guide rail.
【図5】同上ガイドレール付設作業支援装置のレール案
内支持機構の概略構成図。FIG. 5 is a schematic configuration diagram of a rail guide support mechanism of the work support device with the guide rail.
【図6】同レール案内支持機構の概略的正面図。FIG. 6 is a schematic front view of the rail guide support mechanism.
【図7】(a)は同上ガイドレール付設作業支援装置の
角度制御機構の掛止金具の正面図、(b)は同側面図、
(c)は同掛止金具の抜け止め部材の平面図。FIG. 7 (a) is a front view of a hook of an angle control mechanism of the work support device with a guide rail, and FIG. 7 (b) is a side view of the same.
(C) is a top view of the retaining member of the same metal fitting.
【図8】同上ガイドレール付設作業支援装置の高さ制御
機構の掛止金具の側面図。FIG. 8 is a side view of a hook metal of the height control mechanism of the work support device with the guide rail.
【図9】同上ガイドレール付設作業支援装置のレール位
置微調整の作用説明図。FIG. 9 is an operation explanatory diagram of the rail position fine adjustment of the work support device with the guide rail.
【図10】同上レール微動機構の概略構成図。FIG. 10 is a schematic configuration diagram of the same rail fine movement mechanism.
【図11】ガイドレール付設作業支援装置を利用したガ
イドレール付設作業法を示す最上段と二段目のガイドレ
ール搬入・吊り上げ・連結する状態の説明図。FIG. 11 is an explanatory diagram showing a state of carrying in, lifting, and connecting the guide rails of the uppermost stage and the second stage, which shows a guide rail attaching work method using the guide rail attaching work support device.
【図12】(a)(b)は同上ガイドレール付設作業法
におけるガイドレール相互の継目の芯合わせ連結状態を
示す正面図及び側面図。12 (a) and 12 (b) are a front view and a side view showing a centering connection state of joints of guide rails in the same guide rail installation work method as above.
【図13】同上ガイドレール付設作業法における最上段
から地下一階分までのガイドレールの搬入・吊り上げ・
連結する状態の説明図。[Fig. 13] Same as above, carrying in / lifting guide rails from the uppermost stage to the basement level in the work method with guide rails installed.
Explanatory drawing of the state connected.
【図14】同上ガイドレール付設作業法における最上段
から地上一階分までのガイドレールの連結・吊り上げ状
態と、地下一階及び地下二階分のガイドレールの搬入・
吊り上げ状態の説明図。[Fig. 14] Same as above, in the guide rail installation work method, the guide rails are connected / lifted from the uppermost stage to the first floor above ground, and the guide rails for the first basement floor and the second basement floor are carried in /
Explanatory drawing of a lifting state.
【図15】同上ガイドレール付設作業法における最上段
から地上一階分までのガイドレールの連結・吊り上げ状
態と、この下端に地下一階及び地下二階分のガイドレー
ルを連結する状態の説明図。FIG. 15 is an explanatory view of a state where the guide rails are connected and lifted from the uppermost stage to the ground floor and the guide rails for the first basement floor and the second basement floors are connected to the lower end of the guide rail installation work method.
【図16】同上ガイドレール付設作業法における昇降路
内に吊り上げた一連のガイドレールの所定のレール付設
位置近傍正面への横移動状態を示す説明図。FIG. 16 is an explanatory view showing a lateral movement state of a series of guide rails suspended in the hoistway to the front in the vicinity of a predetermined rail attachment position in the same guide rail attachment work method.
【図17】同上一連のガイドレールの揚重機のスライド
による所定のレール付設位置への水平な平行移動状態を
示す説明図。FIG. 17 is an explanatory view showing a state of horizontal parallel movement of a series of guide rails to a predetermined rail attachment position by sliding of a lifting machine in the same as above.
【図18】同上ガイドレール付設作業法におけるガイド
レールの別な吊り上げ手段を示す説明図。FIG. 18 is an explanatory view showing another lifting means of the guide rail in the above-mentioned work method of installing a guide rail.
【図19】同上吊り上げ手段を用いて一連のガイドレー
ルを所定のレール付設位置に横移動する状態の説明図。FIG. 19 is an explanatory view showing a state in which a series of guide rails are laterally moved to a predetermined rail attachment position by using the lifting means.
【図20】同上吊り上げ手段を用いて一連のガイドレー
ルを所定のレール付設位置によこい移動して近似した状
態の説明図。FIG. 20 is an explanatory view of a state in which a series of guide rails are moved to a predetermined rail attachment position and approximated by using the same lifting means.
【図21】同上ガイドレール付設作業法における昇降路
内壁の所定のレール付設位置に吊り上げた一連のガイド
レールと、最下段ピット部のガイドレールの搬入状態を
示す説明図。FIG. 21 is an explanatory view showing a series of guide rails that are hoisted to a predetermined rail installation position on the inner wall of the hoistway and a loading state of the guide rail of the lowermost pit portion in the same guide rail installation work method.
【図22】同上ガイドレール付設作業法における昇降路
内壁の所定のレール付設位置に吊り上げた一連のガイド
レールを芯出し固定する状態の説明図。FIG. 22 is an explanatory view showing a state in which a series of guide rails that have been lifted to a predetermined rail attachment position on the inner wall of the hoistway are centered and fixed in the above-described guide rail attachment work method.
1,101,102,103…ガイドレール、2…エレ
ベータ昇降路、3…継目板、4…レールブラケット、5
…エレベータ乗場出入口、10…ガイドレール付設作業
支援装置のレール搬入台(台車)、11…車台台枠、1
2…車輪、20…レール案内支持機構、22…機構本
体、23A,23B…案内支持部、23…抑えローラ、
24…ブラケット逃げ機構、30…角度制御機構、40
…高さ制御機構、60,60A,60B,60C…揚重
機、64…ファスナプレート。1, 101, 102, 103 ... Guide rail, 2 ... Elevator hoistway, 3 ... Seam plate, 4 ... Rail bracket, 5
… Elevator hall entrance / exit, 10… Rail loading platform (carriage) of the work support device with guide rails, 11… Car underframe, 1
2 ... Wheels, 20 ... Rail guide support mechanism, 22 ... Mechanism body, 23A, 23B ... Guide support part, 23 ... Suppression roller,
24 ... Bracket escape mechanism, 30 ... Angle control mechanism, 40
... Height control mechanism, 60, 60A, 60B, 60C ... Lifting machine, 64 ... Fastener plate.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 石川 佳延 東京都府中市東芝町1番地 株式会社東芝 府中工場内 (72)発明者 西田 善雄 東京都港区芝浦一丁目1番1号 株式会社 東芝本社事務所内 (72)発明者 仕入 英武 神奈川県横浜市鶴見区末広町2丁目4番地 株式会社東芝京浜事業所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Yoshinobu Ishikawa 1st Toshiba Town, Fuchu-shi, Tokyo Toshiba Corporation Fuchu factory (72) Inventor Yoshio Nishida 1-1-1, Shibaura, Minato-ku, Tokyo Toshiba Corporation In the head office (72) Purchased by the inventor Eibu 2-4 Suehiro-cho, Tsurumi-ku, Yokohama-shi, Kanagawa Prefecture Toshiba Keihin Office
Claims (4)
り昇降路内方に送り込み可能に搭載するレール搬入台
と、このレール搬入台の先端部に設けられガイドレール
を摺動可能に案内し且つガイドレールを昇降路内方に送
り込むに従いそのガイドレールを昇降路内の乗場出入口
近傍に鉛直に落とし込み支持するレール案内支持機構
と、このレール案内支持機構により案内支持されるガイ
ドレールの落とし込み角度をコントロールする角度制御
機構と、ガイドレールの昇降路内への落とし込み高さを
コントロールする高さ制御機構とを備えてなるエレベー
タ用ガイドレール付設作業支援装置。1. A rail loading table on which a guide rail is mounted so that it can be fed into the hoistway from an elevator entrance / exit, and a guide rail slidably guided and provided at the tip of the rail loading table. A rail guide support mechanism that vertically drops and supports the guide rail near the entrance of the hoistway as it is fed into the hoistway, and an angle control that controls the drop angle of the guide rail that is guided and supported by this rail guide support mechanism. An elevator guide rail installation work support device comprising a mechanism and a height control mechanism for controlling the height of the guide rail dropped into the hoistway.
を有し、ガイドレールを搭載して建物内を移動可能な走
行台車であることを特徴とする請求項1記載のエレベー
タ用ガイドレール付設作業支援装置。2. The elevator guide rail according to claim 1, wherein the rail carry-in table is a traveling carriage that has steerable wheels at a lower portion thereof and is equipped with a guide rail to be movable in a building. Attached work support device.
先端部に起倒方向に回動可能に装着された機構本体と、
この機構本体に各々装着されガイドレールの長手方向に
間隔を存した2箇所を摺動可能に抱持して案内支持する
二重の案内支持部を有し、且つその両案内支持部が予め
ガイドレールに取り付けたブラケットを通過可能に交互
に待避する構成であることを特徴とする請求項1記載の
エレベータ用ガイドレール付設作業支援装置。3. The rail guide support mechanism includes a mechanism main body mounted to a tip end portion of a rail carry-in table so as to be rotatable in a vertical direction.
Each of the guide bodies has a double guide support part which is attached to the mechanism body and slidably holds and guides two places spaced apart in the longitudinal direction of the guide rail, and both guide support parts are previously guided. 2. The elevator guide rail installation work support device according to claim 1, wherein the brackets attached to the rails are alternately retracted so that the brackets can pass through.
ル付設作業支援装置を用いて、一番目のガイドレールを
エレベータ乗場出入口より昇降路内に案内支持しながら
落とし込んで、そのガイドレールを昇降路内の乗場出入
口近傍に鉛直に立てて支持し、このガイドレールを昇降
路上部に設置した揚重機によりガイドレール一本分の長
さだけ上方に吊り上げ、次に二番目のガイドレールを前
記同様ガイドレール付設作業支援装置を用いて昇降路内
の乗場出入口近傍に搬入して鉛直に立てて支持し、この
二番目のガイドレール上端を前記一番目のガイドレール
の下端に乗場出入口近傍で連結し、この連結状態の一番
目と二番目とのガイドレールを再度揚重機によりガイド
レール一本分の長さだけ上方に吊り上げ、こうしたガイ
ドレールの搬入・連結・吊り上げ作業を規定のガイドレ
ール長さになるまで順次繰り返し、その一連のガイドレ
ールを昇降路内の乗場出入口近傍から該昇降路内壁の所
定のレール付設位置に吊り移して芯出しながら固定する
ことを特徴とするエレベータ用ガイドレール付設作業
法。4. The elevator guide rail installation work support device according to claim 1, wherein the first guide rail is dropped from the elevator landing doorway while being guided and supported in the hoistway, and the guide rail is dropped in the hoistway. It is supported vertically by standing near the entrance / exit of the landing, and this guide rail is lifted up by the length of one guide rail by a lifting machine installed in the upper part of the hoistway, and then the second guide rail is the same as above. Using the attached work support device, it is carried into the vicinity of the entrance / exit of the hoistway and vertically stands and supported, and the upper end of this second guide rail is connected to the lower end of the first guide rail near the entrance / exit, The first and second guide rails in the connected state are again lifted by the lifting machine by the length of one guide rail, and the guide rails are loaded and connected. The knotting and hoisting work is sequentially repeated until the length of the specified guide rail is reached, and the series of guide rails is suspended from the vicinity of the entrance / exit of the hoistway to the predetermined rail attachment position on the inner wall of the hoistway and fixed while centering. A method for installing an elevator guide rail, which is characterized in that
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13900292A JPH05330758A (en) | 1992-05-29 | 1992-05-29 | Elevator guide rail installation assist device and guide rail installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13900292A JPH05330758A (en) | 1992-05-29 | 1992-05-29 | Elevator guide rail installation assist device and guide rail installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05330758A true JPH05330758A (en) | 1993-12-14 |
Family
ID=15235185
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP13900292A Pending JPH05330758A (en) | 1992-05-29 | 1992-05-29 | Elevator guide rail installation assist device and guide rail installation method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05330758A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6357556B1 (en) * | 1997-03-07 | 2002-03-19 | Kone Corporation | Procedure and apparatus for the installation of an elevator |
JP2008285260A (en) * | 2007-05-16 | 2008-11-27 | Mitsubishi Electric Building Techno Service Co Ltd | Guide rail installation method for machine room-less elevator |
JP2017124889A (en) * | 2016-01-12 | 2017-07-20 | 三菱電機ビルテクノサービス株式会社 | Counterweight transport device and counterweight transport method |
CN114761347A (en) * | 2019-12-05 | 2022-07-15 | 因温特奥股份公司 | Method for constructing a carrying structure for escalators or moving walkways |
JP2023000369A (en) * | 2021-06-17 | 2023-01-04 | 東芝エレベータ株式会社 | Long article holding tool and method of taking guide rail into hoistway by using long article holding tool |
US20230049422A1 (en) * | 2020-01-17 | 2023-02-16 | Inventio Ag | Mobile transport device and method for introducing an installation frame into a shaft |
JP2023055288A (en) * | 2021-10-06 | 2023-04-18 | フジテック株式会社 | Jig and method for installing elevator guide rail |
-
1992
- 1992-05-29 JP JP13900292A patent/JPH05330758A/en active Pending
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6357556B1 (en) * | 1997-03-07 | 2002-03-19 | Kone Corporation | Procedure and apparatus for the installation of an elevator |
US7559409B2 (en) | 1997-03-07 | 2009-07-14 | Kone Corporation | Procedure and apparatus for the installation of an elevator |
JP2008285260A (en) * | 2007-05-16 | 2008-11-27 | Mitsubishi Electric Building Techno Service Co Ltd | Guide rail installation method for machine room-less elevator |
JP2017124889A (en) * | 2016-01-12 | 2017-07-20 | 三菱電機ビルテクノサービス株式会社 | Counterweight transport device and counterweight transport method |
CN114761347A (en) * | 2019-12-05 | 2022-07-15 | 因温特奥股份公司 | Method for constructing a carrying structure for escalators or moving walkways |
US20230049422A1 (en) * | 2020-01-17 | 2023-02-16 | Inventio Ag | Mobile transport device and method for introducing an installation frame into a shaft |
US12240514B2 (en) * | 2020-01-17 | 2025-03-04 | Inventio Ag | Mobile transport device and method for introducing an installation frame into a shaft |
JP2023000369A (en) * | 2021-06-17 | 2023-01-04 | 東芝エレベータ株式会社 | Long article holding tool and method of taking guide rail into hoistway by using long article holding tool |
JP2023055288A (en) * | 2021-10-06 | 2023-04-18 | フジテック株式会社 | Jig and method for installing elevator guide rail |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20080308362A1 (en) | Cable management assembly and method for construction elevator systems | |
JPH05330758A (en) | Elevator guide rail installation assist device and guide rail installation method | |
JP2008222382A (en) | Method for moving lifting device for installation | |
JP4353343B2 (en) | Large elevating stage, lifting method and reverse driving method using the same | |
JPH05178561A (en) | Installation method for guide rail for elevator | |
CN114945531A (en) | Mobile transfer device and method for introducing an assembly frame into a shaft | |
US12103819B2 (en) | Construction arrangement of an elevator and method | |
US20090097952A1 (en) | Method and device for transporting an elevator car drive machine | |
JPH06272389A (en) | Temporary unloading stage | |
JPH08245116A (en) | Installation engineering of elevator | |
CN111646376B (en) | Gun carriage hoisting device | |
JPH05319729A (en) | Attaching work device of guide rail of elevator and attaching work method of guide rail using that device | |
JPH08231161A (en) | Down type working elevator and method of extending elevator mast in downward direction | |
JP2000086113A (en) | Elevator, and installation method thereof | |
JP2001354374A (en) | Lifting device in elevator shaft | |
JPH0978842A (en) | Crane for scaffold | |
JP2001335255A (en) | Elevator installation construction method, and elevator installation unit | |
JP3037759B2 (en) | Method and apparatus for working in elevator shaft | |
JP7436126B1 (en) | Elevator gondola installation method and gondola device | |
JPS61257890A (en) | Panel hanging jig and panel hanger using said jig | |
JP3002221U (en) | Trolley with a gondola suspension arm | |
JPH06278967A (en) | Method and device for assembling guide rail | |
JP2000351553A (en) | Lifting equipment for elevator installation | |
CN115680248A (en) | Construction method for high-altitude installation of large bamboo formwork wallboard | |
JPS5934633B2 (en) | Construction elevator installation method |